SPLOST UPDATE
Project update as of 6/30/2014
Review Referendum
Make recommendations for projects on deferred list
2
![Page 3: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/3.jpg)
Completed Projects as of 6/30/2014
Projects Total
HVAC Gymnasiums $ 10,575,366
Re Roofing 2,617,412
Land Purchases 3,260,255
Kinnett Stadium 2,070,696
Carver High School 43,909,424
Aaron Cohn Middle* 21,171,436
Northside Addition* 4,508,605
Richard Addition* 5,429,367
Lorenzo Road * 562,745
Total Projects $94,105,306
*Project near completion-final cost may vary up to $10,000 3
![Page 4: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/4.jpg)
In progress as of 6/30/2014
Projects
Estimated Budget Spent
Amount Remaining
Dorothy I. Height Elementary $20,034,788 $18,480,861 $1,553,927
4
![Page 5: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/5.jpg)
Design Stage
Projects Estimated
Budget Spent/
encumbered Amount
Remaining
Fine Arts Academy $ 28,300,000 0 $ 28,300,000
5
![Page 6: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/6.jpg)
On-going Projects as of 6/30/2014
Projects Estimated
Budget Spent Amount
Remaining
Technology $ 35,861,093 $25,444,234 $ 10,416,859
School Furniture and Equip 366,023 116,023 250,000
Security 565,000 251,204 313,796
Buses 2,000,000 1,984,965 15,035
Museum 1,000,000 490,752 509,248
Playgrounds 1,358,500 762,893 595,607
Other Facilities Needs 1,450,000 1,444,756 5,244
Total Projects $ 42,600,616 $30,494,827 $ 12,105,789
6
![Page 7: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/7.jpg)
Projects as of 6/30/2014
Projects Estimated
Budget Spent Amount
Remaining
Completed $ 94,105,306 $ 94,105,306 $ 0
In Progress 20,034,788 18,480,861 1,553,927
Design Stage 28,300,000 0 28,300,000
On-going 42,600,616 30,494,827 12,105,789
Debt Service/
Project Management 3,750,000 3,664,127 85,873
Total Projects 188,790,710 146,745,121 $42,045,589
7
![Page 8: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/8.jpg)
Referendum Review
On September 15, 2009, the citizens of the Muscogee County School District (the “School District”) voted and approved that a one percent sales and use tax (the “Sales and Use Tax”) be imposed in the School District to raise not more than $223,155,784 to pay or to be applied toward the cost of:
8
![Page 9: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/9.jpg)
SPLOST Revenue As of June 30, 2014
SPLOST Collections $159,829,732
Georgia State Financing and
Investment Commission 12,896,939
Transfers from General Fund 2,187,093
E Rate 1,266,646
Interest 134,720
Total Revenue $176,315,130
9
![Page 10: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/10.jpg)
SPLOST Revenue Estimated Additional Revenue
SPLOST Collections $16,509,398
Interest 10,000
Total Est Add’l Revenue $16,519,398
Total Estimated Revenue
As of June 30, 2014 $176,315,130
Add’l Estimated Revenue 16,519,398
Total Estimated Revenue $192,834,529 10
![Page 11: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/11.jpg)
(i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to
1. a new Carver High School, 2. a new middle school, 3. one and possibly two new elementary
schools, 4. a fine arts academy, 5. and other such projects,
Referendum Review
11
![Page 12: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/12.jpg)
12
![Page 13: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/13.jpg)
13
![Page 14: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/14.jpg)
14
![Page 15: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/15.jpg)
(i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to:
1. a new Carver High School
2. a new middle school,
3. one and possibly two new elementary schools,
4. a fine arts academy,
5. and other such projects,
Referendum Review
15
![Page 16: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/16.jpg)
16
![Page 17: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/17.jpg)
17
![Page 18: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/18.jpg)
18
![Page 19: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/19.jpg)
19
![Page 20: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/20.jpg)
Referendum Review (i) the acquisition, construction and equipping of
new school buildings and facilities, including but not limited to:
1. a new Carver High School
2. a new middle school,
3. one and possibly two new elementary schools,
4. a fine arts academy,
5. and other such projects,
20
![Page 21: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/21.jpg)
21
![Page 22: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/22.jpg)
22
![Page 23: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/23.jpg)
23
![Page 24: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/24.jpg)
24
![Page 25: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/25.jpg)
Referendum Review (i) the acquisition, construction and equipping of
new school buildings and facilities, including but not limited to:
1. a new Carver High School
2. a new middle school,
3. one and possibly two new elementary schools,
4. a fine arts academy,
5. and other such projects,
25
![Page 26: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/26.jpg)
Referendum Review (i) the acquisition, construction and equipping of
new school buildings and facilities, including but not limited to:
1. a new Carver High School
2. a new middle school,
3. one and possibly two new elementary schools,
4. a fine arts academy, (Design Stage)
5. and other such projects,
26
![Page 27: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/27.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
27
![Page 28: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/28.jpg)
28
![Page 29: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/29.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
29
![Page 30: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/30.jpg)
30
![Page 31: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/31.jpg)
31
![Page 32: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/32.jpg)
32
![Page 33: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/33.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
33
![Page 34: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/34.jpg)
34
![Page 35: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/35.jpg)
35
![Page 36: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/36.jpg)
36
![Page 37: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/37.jpg)
37
![Page 38: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/38.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
38
![Page 39: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/39.jpg)
39
![Page 40: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/40.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
40
![Page 41: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/41.jpg)
(iii) acquiring new school equipment and making certain technology improvements,
(iv) acquiring any property necessary or desirable therefore, both real and personal (the “Projects”)
(v)issuance of general obligation debt of Muscogee County School District in the principal amount not to exceed $70,000,000 (the “Debt”) for the above purposes.
Referendum Review
41
![Page 42: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/42.jpg)
2009 SPLOST Projects Deferred Deferred projects (projects listed lowest to highest cost estimates)
Security $ 935,000
Jordan Auditorium 1,000,000
Furniture and Equipment 2,633,977
System-Wide Athletic Facilities 3,000,000
Technology 5,000,000
System-Wide Gym 7,000,000
Total $ 19,568,977
42
![Page 43: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/43.jpg)
Estimated Unobligated Funds
Estimated Total Revenue $193,000,000
Amounts Obligated for current
projects 189,000,000
Estimated Unobligated Funds
$4,000,000
43
![Page 44: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/44.jpg)
Proposed Allocation for Deferred Projects
Projects Amount Deferred
Additional Allocation
Security $ 935,000 700,000
Jordan Auditorium 1,000,000 1,200,000
Furniture and Equipment 2,633,977 500,000
Athletic Facilities 3,000,000 1,600,000
Technology 5,000,000 0
System-Wide Gym 7,000,000 0
Total Projects $ 19,568,977 $4,000,000
44
![Page 45: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/45.jpg)
Security Upgrades Fire alarms
Intercoms
Smoke detectors
Burglar Alarms
School Security Notification System
45
![Page 46: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/46.jpg)
Jordan Auditorium Renovation Seating
Sound system
Lights
Other general renovation
46
![Page 47: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/47.jpg)
Furniture and Equipment Music Instruments and Equipment for Middle and
High Schools
Furniture for new computer labs
47
![Page 48: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/48.jpg)
Athletic Facilities Synthetic Turf and Expansion of Track Area for Kinnett
Stadium
Weight Room Equipment for High Schools
Other Athletic Projects and Improvements for High Schools
48
![Page 49: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/49.jpg)
Referendum Review (i) the acquisition, construction and equipping of
new school buildings and facilities, including but not limited to:
1. a new Carver High School
2. a new middle school,
3. one and possibly two new elementary schools,
4. a fine arts academy, (Design Stage)
5. and other such projects,
49
![Page 50: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/50.jpg)
(ii) adding to, renovating, improving and equipping existing school buildings and facilities, including but not limited to • Richards Middle School 12-Classroom Addition and Reno, • Northside High School 20-Classroom Addition, • Jordan High School Auditorium Upgrade, • Kinnett Stadium Upgrades, • System-Wide Athletic Facilities Upgrades, • air-conditioning gymnasiums, • security upgrades, • Alternative School and Adult Education Facility Upgrades, and other such projects,
Referendum Review
50
![Page 51: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/51.jpg)
(iii) acquiring new school equipment and making certain technology improvements,
(iv) acquiring any property necessary or desirable therefore, both real and personal (the “Projects”)
(v)issuance of general obligation debt of Muscogee County School District in the principal amount not to exceed $70,000,000 (the “Debt”) for the above purposes.
Referendum Review
51
![Page 52: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/52.jpg)
Projects Removed Second new elementary school
Alternative and Adult Education Facility Upgrades
52
![Page 53: October 2014 Work Session€¦ · Referendum Review (i) the acquisition, construction and equipping of new school buildings and facilities, including but not limited to: 1. a new](https://reader035.vdocument.in/reader035/viewer/2022070817/5f10ab317e708231d44a3d28/html5/thumbnails/53.jpg)
Recommendation Superintendent recommends approval of the
allocation of the estimated unobligated 2009 SPLOST funds as follows:
Projects
Additional Allocation
Security 700,000
Jordan Auditorium 1,200,000
Furniture and Equipment 500,000
Athletic Facilities 1,600,000
Total Projects $4,000,000
53