BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON October 22, 2010 National Commission on Energy Policy Workshop on Power Sector Environmental Regulations Sue Tierney Managing Principal Upcoming Power Sector Environmental Regulations: Framing the issues about potential reliability/cost impacts

Upload: sook

Post on 07-Feb-2016

31 views

Category:

Documents


0 download

DESCRIPTION

Upcoming Power Sector Environmental Regulations: Framing the issues about potential reliability/cost impacts. October 22, 2010 National Commission on Energy Policy Workshop on Power Sector Environmental Regulations. Sue Tierney Managing Principal. Point of view. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: October 22, 2010 National Commission on Energy Policy

BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON

October 22, 2010National Commission on Energy PolicyWorkshop on Power Sector Environmental Regulations

Sue Tierney

Managing Principal

Upcoming Power Sector Environmental Regulations:Framing the issues about potential reliability/cost impacts

Page 2: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 2- October 22, 2010

Point of view

Today’s remarks are my own perspective.

My starting point is my understanding that:

public health and electric reliability objectives both are “givens”;

the national and regional health benefits of implementing updated clean air rules warrant action – and the geographic distribution of benefits resembles that of the costs.

Page 3: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 3- October 22, 2010

Point of view

I recently co-authored report for Clean Energy Group: Ensuring a Clean, Modern Electric Generating Fleet while Maintaining Electric System Reliability

Co-authors: Paul Hibbard of Analysis Group; and Michael J Bradley, Chris Van Atten and others at MJB Associates;

CEG participating companies are some of the nation’s largest generators of electricity, with over 170,000 MW of electric generating capacity (including 110,000 MW of fossil generating capacity) in the U.S., and serve nearly a fifth of all U.S. electric customers.

Calpine Corporation Constellation EnergyEntergy Corporation Exelon CorporationNextEra Energy National GridPG&E Corporation Public Service Enterprise Group

Our report focused on air rules (CATR, MACT rules).

http://www.mjbradley.com/documents/MJBAandAnalysisGroupReliabilityReportAugust2010.pdf; http://www.analysisgroup.com/article.aspx?id=10786

Page 4: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 4- October 22, 2010

Some key questions:

What can we tell now about the impact on electric industry reliability of EPA’s rules on plant retirements, retrofits?

What tools are available to manage through the transition in a reliable way?

What may be the biggest challenge to assuring reliability during a compliance period?

Page 5: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 5- October 22, 2010

What can we tell about the impacts on reliability? (1)

The overall amount of affected capacity is smaller than it might first appear.

Of the 310 MW of coal capacity in the U.S.:

Many of the affected plants are likely to retire due to market economics .

– This is particularly true since many of the least-economically viable units are small, uncontrolled, old, relatively inefficient – and will face economic closure decisions from the air (and water) rules.

Many of the plants are already controlled or have proposed retrofits.

– 65% (over 200 GW) has already installed or planned scrubbers.

– ~50% is already or soon to be retrofitted with advanced NOx controls.

An estimated 25-75 GW is in a genuinely uncertain state.

Page 6: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 6- October 22, 2010

What can we tell about the impacts on reliability? (2)

EPA projects that the new CATR regulations would require:

14 GW of additional capacity (beyond previously announced units) would need to be retrofitted with scrubbers.

Less than 1 GW retrofitted with advanced NOx controls by 2014.

This amount is significantly less than what the industry has added in the recent past:

Between 2008-2010, approximately 60 GW of coal capacity was installed with scrubbers, with the industry completing 50+ scrubber retrofits each year.

Page 7: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 7- October 22, 2010

What can we tell about the impacts on reliability? (3)

At an aggregate level, the U.S. bulk power system has adequate spare generating capacity to absorb potential coal plant retirements.

Across all NERC regions, more than 100 GW of surplus generating capacity is available relative to target reserve margins in 2013

–This is significantly higher than the 25-75 GW of retirements projected by industry analysts.

Page 8: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 8- October 22, 2010

All NERC reliability regions have excess capacity, totaling over 100 GW of excess capacity nationwide

NERC Electric Reliability Region

Projected Reserve Margin(1) in 2013Cushion Above NERC

Target Reserve Margin (2) In 2013

TRE 23.9% 7.8 GW

FRCC 28.6% 6.1 GW

MRO 22.1% 3.2 GW

NPCC 24.4% 5.9 GW

RFC 24.3% 17.1 GW

SERC 26.3% 23.9 GW

SPP 30.3% 7.7 GW

WECC 42.6% 35.6 GW

Total 107.3 GW

Estimated Reserve Margins in NERC Regions

1. Includes capacity defined by NERC as Adjusted Potential Reserve Margin, which is the sum of deliverable capacity resources, existing resources, confidence factor adjusted future resources and conceptual resources, and net provisional transactions minus all derates and net internal demand expressed as a percent of net internal demand. 2. Capacity in excess of what is required to maintain NERC Reference Margin or the regional target reserve levels.

Source: NERC, 2009 Long-Term Reliability Assessment: 2009-2018, October 2009.

Page 9: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 9- October 22, 2010

What can we tell about the impacts on reliability? (4)

The reliability impact of these proposed rules will depend on:

– actions to address these issues in a timely manner – to replace capacity as needed.

The electric industry has a proven track record of adding additional generating capacity, transmission solutions and demand-side measures when and where needed, and of coordinating effectively to address reliability concerns.

–In the three years between 2001 and 2003, the electric industry built over 160 GW of new generation—about four times what analysts project will retire over the next five years.

–There are good examples of situations where the industry moved quickly and appropriately to address reliability issues when the need presented itself.

Page 10: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 10- October 22, 2010

Industry track record of adding new generating capacity when and where needed

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005

RenewableHydroNuclearOtherOilGasCoal

Nameplate Capacity (MW)

Source: Ceres, et al., Benchmarking Air Emissions of the 100 Largest Electric Power Producers in the United States, June 2010.

Between 2001 and 2003, over 160 GW of NGCC

generating capacity was brought online.

U.S. Power Plant Capacity Added By In-service Year

Page 11: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 11- October 22, 2010

What can we tell about the impacts on reliability? (5)

The reliability issues associated with these proposed rules will vary by region:

Potential retirements (driven by the air rules first, and then potentially by the water rules over time) may occur particularly in the following areas between 2015 and 2018:

–Midwest (Midwest ISO region and PJM)

– the Southeast

– the Southwest Power Pool

– parts of the Northeast

More analysis needs to be done in these regions to identify the localities where issues could arise – and where market and planning responses could help mitigate reliability concerns.

Page 12: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 12- October 22, 2010

Location of controlled and uncontrolled generating units(Not necessarily where the retirements will occur)

Credit Suisse, “A Thought: CATR is First Step in Changing the Coal Fleet,” July 7, 2010

Page 13: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 13- October 22, 2010

Small coal plant (by vintage and controls) (<300 MW)(Not necessarily where the retirements will occur)

Credit Suisse, “A Thought: CATR is First Step in Changing the Coal Fleet,” July 7, 2010

Page 14: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 14- October 22, 2010

The electric industry is well-positioned to respond:

Manage Retirements

Schedule Outages

Many tools available to:

Page 15: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 15- October 22, 2010

The electric industry is well-positioned to respond

Managing Retirements: Adequate capacity and under-utilized existing capacity.

Market and/or IRP responses: new capacity will be added as a result of market and planning signals.

States’ supervision of utilities’ efforts in the face of uncertainty (e.g., retirements, equipment additions, off-system purchases, reserve sharing).

States can introduce more aggressive energy efficiency, demand response, load-management tools – including ratemaking incentives to accompany them. Consider demand-side opportunities exist in affected regions.

RTO markets: forward capacity markets, demand-response markets, planning and load-flow studies with “what if” analyses; Reliability-Must-Run agreements if needed.

All regions: rapid-response planning initiatives to address any apparent reliability issues.

Page 16: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 16- October 22, 2010

The electric industry is well-positioned to respond

Scheduling Outages: NOx, SO2, mercury, acid gas control technologies are commercially available.

Existing under-utilized capacity at gas-fired combined cycle plants can facilitate the scheduling of outages.

RTOs can help coordinate outages and provide for sharing reserves.

EPA can grant time extensions to complete pollution control installations on a case-by-case basis.

DOE can override compliance requirements in limited emergency circumstances.

EPA and the President can extend deadlines for utility MACT rules where necessary for electric system reliability.

Page 17: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 17- October 22, 2010

What may be the biggest challenge to assuring reliability during compliance?

Creating incentives for action in the face of regulatory uncertainty:

Deciding to proceed under the assumption that EPA will adopt, implement and enforce regulations – rather than deciding to fight the notion that EPA will do so.

Managing the transition using all available tools (including energy efficiency, demand response, maintenance/outage planning, reserve sharing, planning studies, market information) including coordinated responses in emergency circumstances.

Creating incentives for compliance strategies that simultaneously support early analyses and provision of various signals to the market, as well as prudent decision-making under conditions of uncertainty.

Page 18: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 18- October 22, 2010

Conclusions: This is do-able (3)1. Industry practice and pertinent system data indicate

that the electric sector is well-positioned to respond to EPA’s mission to “help millions of Americans breathe easier and live healthier” without threatening electric reliability. With economic costs, there will also be economic benefits – related to health as well as investment/construction stimulus.

2. Industry studies that raise the spotlight on reliability issues do not typically incorporate assumptions about how the market will respond and therefore are not necessarily sound pictures of what will occur; they are positive for inducing market responses.

Page 19: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 19- October 22, 2010

Conclusions: This is do-able (2)3. Existing substantial excess capacity, the electric

industry’s proven track record to timely construct new generation and to efficiently coordinate the scheduling of planned outages, together with transmission enhancements, “smart grid” investments, fuel conversions, relatively low gas prices, demand-side actions, should mitigate reliability (and cost) concerns.

4. As a final backstop, existing statutory, market and regulatory safeguards will facilitate the retirement of inefficient units, and an orderly transition to cleaner, more efficient generation.

Page 20: October 22, 2010 National Commission on Energy Policy

NCEP Workshop – Power Sector Environmental Regulations

Page 20