    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 12

    Table1: Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    1 Al Ayjah132/33kV grid station Q3 2015 Energized

    35 km 132kV OHL from Sur grid

    station

    2x125MVA transformers

    6 no. 132kV GIS

    To cater for the new load growth at Ras Al Had area

    Solve the issue of voltage drop of 33kV lines. Currently

    this area is fed by 33kV feeders from Sur grid station

    Load transfer from existing Sur grid

    2Madinat Nizwa132/33kV grid

    stationQ3 2015 Energized

    2 x 125 MVA transformers

    6 no. 132kV GIS

    12 km 132kV double circuit OHLfrom Nizwa grid station

    Load transfer from Nizwa grid station

    To meet load growth requirements in the area

    3Rusail Industrial132/33kV

    grid stationQ3 2015 Energized

    12 no. 132kV GIS

    4 x 125MVA transformers

    Replacement of old 132kV and 33kV switch gears due to

    132kV and 33kV short circuit effects

    Replacement of old 75MVA transformers with 125MVA

    To cater for the new load growth at Rusail area

    4 Amerat132/33kV grid station(TX1 & TX2)

    Q3 2015 Energized

    2 x 125 MVA transformers

    8 no. 132kV GIS

    5km LILO of 132kV OHL between

    MSQ and Jahloot

    Load transfer from Jahloot and Wadi Adai grid stations

    To meet the high load growth at Amrat area

    To resolve 33kV voltage issues

  • 7/26/2019 OETC 2016-2020 Projects

    2/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 13

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    5A'salam132/33kV grid station

    (TX1 & TX2)Q3 2015 Energized

    2x 125MVA transformers

    8.4km 132kV 2500mm2 UGC from

    Mobella to A'salam

    7.4km132kV 2500mm2 UGC from

    Seeb Main to A'salam

    10 no. 132kV GIS

    To cater for the load growth at Mobella

    Load transfer from grids in this area (Mawalleh , Seeb

    Main , Barka Main and Mobella)

    6Ghala132/33kV grid station

    (TX1 & TX2)Q3 2015 Energized

    2 x 125 MVA transformers

    12 no. 132kV GIS

    4km UGC 2500mm from Airport

    Heights grid station

    To cater for the expected load growth in Ghala area

    Load transfer from Bousher and Airport Heights grid

    stations

    To supply the new Al Arfan area load

    7 Khadhra132/33kV grid station(TX1 & TX2)

    Q4 2015 Energized

    2 x 125MVA transformers

    10. no. 132kV GIS

    0.135 km LILO of 132kV between

    MISKhabourah

    To cater for the new demand within the area

    Load transfer from Khaborah & MIS grid stations

  • 7/26/2019 OETC 2016-2020 Projects

    3/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 14

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    8

    New 400kV OHL between Sur

    Power Plantand Qalat Al

    Awamer400 kV grid stations

    Q4 2015 Completed

    223 km 400kV lines route length

    between SurQalat Al Awamer

    To evacuate the power from Sur Generation

    To support the voltage and power flow to Al Dakhliah

    area

    To comply with Transmission Security Standards

    requirements

    9 Madinat Barka132/33kV gridstation (TX1 & TX2)

    Q4 2015 UnderConstruction

    2x 125MVA transformers

    10 no. 132kV GIS

    0.13 km LILO of 132kV OHL from

    Filaj to Mualdah

    To cater for the load growth at Barka area

    To meet Transmission Security Standard

    Load transfer from Barka Main

    10Al Hamriyah220/132kV grid

    stationQ1 2016

    Energized

    (Grid

    Station)

    Under

    Construction(220kV

    OHL)

    2 x 500MVA transformers 220/132kV

    8 no. 220kV GIS

    14 no. 132kV GIS

    33.8 km 220kV OHL from Jahloot to

    Al Hamriyah

    LILO the 132kV Wadi Adai- WadiKabir lines grids station

    LILO the 132kV Qurum-Muttrah lines

    to Al Hamriyah grids station

    To supply the load of the area

    To support the voltage at Muscat area Grids

    ( Wadi Adai, Wadi Kabir, Muttrah , Qurum and AlFalaj)

    To evacuate the power coming from Sur via Jahloot grid

    station

    To increase the system reliability within Muscat area gridstations

    To increase and maintain the system security of 132kV

    lines within the area

  • 7/26/2019 OETC 2016-2020 Projects

    4/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 15

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    11 Ibra 132/33kV grid station Q1 2016Under

    Construction

    6 no. 132kV GIS

    28 km OHL 132kV route length

    between Mudhairib and Ibra gridstations

    2x 125MVA transformers

    To meet load growth requirements

    To meet Transmission Security Standard

    Load transfer from Mudhairib

    12New 132kV Line Ashoor -

    Awqad(Part-1)Q1 2016

    Under

    Construction

    8.5 km 132kV OHL

    1.2 km 132kV UGC

    To complete the ring of 132kV system

    To meet Transmission Security Standard

    13New 132kV Line Ashoor -

    Awqad(Part-2)Q1 2016

    Under

    Construction 48.3 km 132kV OHL

    To complete the ring of 132kV system

    To meet Transmission Security Standard

    14

    Sur IPP400/220kV Grid Station

    & Jahloot 400/220kV Grid

    Station

    Q2 2016Under

    Construction

    At Jahloot:

    4 x500MVA, 400/220kV transformers

    10 no. 400kV GIS

    2 no. 220kV GIS

    At Sur Power Plant:

    5 x 750MVA 400/220kV

    transformers

    13 no. 400kV

    1 no. 220kV GIS

    To evacuate the power from Sur Generation

  • 7/26/2019 OETC 2016-2020 Projects

    5/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 16

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    15JBB Hassan132/33kV grid

    stationQ2 2016

    Under

    Construction

    2 x 125 MVA transformers

    8 no. 132kV GIS

    2x16 km LILO Al kamil-Sur 132kV

    OHL

    6x132kV AIS at JBB Ali grid station

    Load transfer from existing JBB Ali grid station

    To meet load growth requirements in the area

    To meet Transmission Security Standard

    16Qalat Al Awamer132/33kV

    grid stationQ2 2016

    Under

    Construction

    2 x 125 MVA transformers

    8 no. 132kV GIS

    2x0.62 km LILO of Izki Mudhaibi

    132kV UGC

    To cater for the new demand in the area

    Load Transfer from Izki grid station

    17Qalat Al Awamer220kV grid

    stationQ2 2016

    Under

    Construction

    2x 500 MVA transformers(220/132kV)

    7 no. 220kV GIS

    To evacuate the power from Sur Generation

    To support the voltage and power flow to Al Dakhliah

    area

    To comply with Transmission Security Standards

    requirements

  • 7/26/2019 OETC 2016-2020 Projects

    6/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 17

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2016

    18Qalat Al Awamer400/220 kV

    grid stationQ2 2016

    Under

    Construction

    2x 500 MVA transformers

    (400/220kV)

    10 no. 400kV GIS

    To evacuate the power from Sur Generation

    To support the voltage and power flow to Al Dakhliah

    area

    To comply with Transmission Security Standards

    requirements

    Peak 2017

    19 Dreez132/33kV grid station Q4 2016Under

    Construction

    2 x 125 MVA

    30 km 132kV OHL from Ibri

    8 no. 132kV GIS

    To cater for the new demand within the area

    Load transfer from Ibri and Al Hayl grid stations

    20Sohar Free Zone220/132/33kV

    grid stationQ4 2016

    Under

    Construction

    2x 0.17 km LILO Wadi Al JizziLiwa 132kV OHL

    2x 500 MVA transformers

    8 no. 220kV GIS

    2x 0.48 km UGC as LILO of 220kV

    OHL Sohar 2 PS -SIS 2x125MVA transformers

    16 no.132kV GIS

    To cope with the load growth.

    To meet Transmission Security Standard

    To supply the free zone area industrial loads

  • 7/26/2019 OETC 2016-2020 Projects

    7/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 18

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2017

    21Replacement of Mahadha

    132kV AIS to GISQ4 2016

    UnderConstruction

    14 no. 132kV GIS

    To replace the existing AIS to GIS due to:

    Lightening

    Maintenance Issus

    Old Assets

    System reliability

    System security

    22 Upgrading Misfahgrid stationto 400kV

    Q4 2016 UnderConstruction

    3 x 500MVA transformers

    (400/220kV)

    11 no. 400kV GIS

    3 no. 220kV GIS

    To support the evacuation of Sur power plant

    To maintain the security requirement

    23Adding third & fourth

    transformers 132/33kV at

    Muladahgrid station

    Q1 2017Under

    Construction

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet load growth requirements

    To meet Transmission Security Standard

    24Adding third & fourth

    transformers 132/33kV at Liwa

    grid station

    Q1 2017Under

    Construction

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To cater for the new demand in the area

    To meet Transmission Security Standard

  • 7/26/2019 OETC 2016-2020 Projects

    8/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 19

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2017

    25400 kV OHL between Qalat Al

    Awamerand MisfahQ2 2017

    Under

    Construction 100 km OHL 400kV

    To support the evacuation of Sur power plant

    To meet Transmission Security Standard

    2633kV busbars Interlinking atBousher & Mawalleh South

    grid stationsQ2 2017 Design

    8 no. of 33kV at Bousher & MawallehSouth

    To meet Transmission Security Standard

    27 Saadah132/33kV grid station Q2 2017Under

    Construction

    4x125MVA Transformers

    10 no. of 132kV GIS.

    4 no. 33kV Interlink

    13km LILO from Ashoor-

    Awqad132kV UGC

    To meet load growth requirements To meet Transmission Security Standard

    Load Transfer from Al Qarm, Ittin and Awqad grid

    stations

    28Daghmar132/11kV grid

    stationQ2 2017

    UnderConstruction

    3x 50 MVA (shifted from the

    Mawalleh North grid station)

    4km OHL from Quriyat grid stat ion

    2 no. 132kV GIS at existing Quriyatgrid station

    7 no. 132kV GIS at Daghmar

    To supply the new IWP at Quriyat

  • 7/26/2019 OETC 2016-2020 Projects

    9/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 20

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2017

    29

    Connection of Salalah-2 IPP&Adding third & fourth

    transformers to Salalah Free

    Zonegrid station

    Q2 2017Under

    Construction

    16 no. of 132kV GIS

    2x125MVA transformers

    To connected the new Salalah-2 IPP Power Plant

    To meet load growth requirements

    To meet Transmission Security Standard

    30

    132kV Linking System between

    Al Falaj, Muttrahand Wadi

    KabirGrid stations & Adding

    Fourth 125MVA transformer at

    Wadi Kabirgrid station

    Q2 2017 UnderConstruction

    3km 132kV 2500mm2 cables between

    Muttrah-Al Falaj grid stations

    One circuit Twin YEW 1.5 km OHL and 2

    km UGC 132kV between Muttrah-Wadi

    Kabair grid stations

    10 no. 132kV GIS at Wadi Kabair grid

    station

    8 no. 132 GIS at Al Falaj

    1 x 125MVA transformer at Wadi Kabir

    To secure the loads and meet Transmission

    Security Standard.

    Safety clearance and environment issues

    To cater for the new demand in the area

    Peak 2018

    31 Adding 400kV reactors Q3 2017 Design

    2x35 MVAr reactors at end of 400kV line

    between Sur-Jahloot

    4x40 MVAr reactors at end of 400kV line

    between Sur-Qalat Al Awamer

    2x30 MVAr reactors at end of 400kV line

    between Qalat Al Awamer-Misfah

    To maintain the voltage within the range during

    the winter time

  • 7/26/2019 OETC 2016-2020 Projects

    10/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 21

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    32Dil Abdusalam132/33kV grid

    stationQ3 2017 Design

    2 x 125 MVA transformers

    2x8 km LILO of Saham-

    Khaborah132kV OHL

    8 no. 132kV GIS

    To cater for the new demand in the area

    Load Transfer from Saham & Khaborah grid stations

    To meet Transmission Security Standard

    33

    Adding third & fourth

    transformers 132/33kV at

    Khadhragrid station

    Q3 2017 Design 2 x 125 MVA transformers

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To cater for the load growth in the area

    34

    Adding third & fourth

    transformers 132/33kV at

    Madinat Barkagrid station

    Q3 2017 Design 2 x 125 MVA transformers

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To cater for the load growth in the area

    35Madinat Shinas132/33kV

    grid stationQ3 2017 Design

    2 x 125 MVA transformers

    24.06 km 132kV OHL from Shinas to

    Madinat Shinas

    2 no. 132kV GIS at Shinas

    6 no. 132kV GIS at Madinat Shinas

    To cater for the new demand in the area

    Load Transfer from Shinas grid station

    To meet Transmission Security Standard

  • 7/26/2019 OETC 2016-2020 Projects

    11/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 22

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    36 Suwaiq 132/33kV grid station Q3 2017 Design

    2 x 125 MVA transformers

    2x0.2 km LILO of MIS-Khadhra

    132kV OHL

    8 no. 132kV GIS

    To cater for the new demand in the area

    To meet Transmission Security Standard

    Load Transfer from MIS grid station

    37 Sinaw132/33kV grid station Q3 2017 Design

    2 x 125 MVA transformers

    2x15 km LILO of Qalat Al Awamer -

    Mudhaibi 132kV OHL

    8 no. 132kV GIS

    To cater for the new demand in the area

    Load transfer from Mudhaibi Solve the issue of voltage drop of 33kV lines

    To meet Transmission Security Standard

    38

    Upgrading of Mawalleh North

    grid station from 3x50MVA

    (132/11kV) to 2 x 125 MVA

    (132/33kV) transformers

    Q3 2017 Design 2 x 125 MVA transformers

    To cater for the new demand in the area

    To support the 33kV network in the Seeb area and

    enable to transfer more load from neighbouring grid

    stations (Seeb & Mawalleh)

    39 Jebreen132/33kV grid station Q3 2017 Design

    2 x 125 MVA transformers

    2x0.5 km LILO of Nizwa - Ibri

    132kV OHL

    8 no. 132kV GIS

    To cater for the new demand in the area

    Load Transfer from Bahla grid station

    To meet Transmission Security Standard

  • 7/26/2019 OETC 2016-2020 Projects

    12/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 23

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    40 Ibri 400kVgrid station Q3 2017Under

    Construction

    3 x 500 MVA transformers (400/220kV)

    19 No. 400kV GIS at Ibri IPP

    10 No. 220kV GIS at Ibri IPP

    2x4.3 km LILO of 220kV OHL IbriMahadha

    To evacuate power coming from Ibri IPP

    Power Plant and supply Ibri area

    To maintain Transmission Security

    Standard

    41

    Adding 2x125MVA

    transformers 220/33kV at

    Barka-3 PSgrid station

    Q4 2017 Design 2 x 125 MVA transformers

    2 no. 220kV GIS

    To Supply the Barka IWP

    Load Transfer from Barka Main grid station

    42

    Construction of a new 132 kV

    OHL from Sohar Free Zoonto

    Shinas

    Q4 2017 Design

    2 no. 132kV GIS at Shinas

    2 no. 132kV GIS at Sohar Free Zone

    20km 132kV OHL from Sohar Free Zone to Shinas

    To meet Transmission Security Standard

    43

    Upgrading of Adamgrid

    station from 2x40MVA to

    2x125MVA transformers

    Q2 2018 Design 2 x 125 MVA transformers

    6 no. 132kV GIS

    To maintain Transmission Security

    Standard

    To cater for the new demand in the area

    44 Security of SIAgrid station Q2 2018 Design

    1 no 132kV GIS

    2 no. of 220kV GIS

    1x500MVA transformer

    3.2 km UGC of 220kV SPS 1 SIA

    To meet Transmission Security Standard at

    SIA during maintenance period

  • 7/26/2019 OETC 2016-2020 Projects

    13/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 24

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    45

    New 132kV double circuits

    lines from Rustaq-Wadi bani

    Auwf-Nakhalwith a new

    Wadi bani Auwf132/33 kV

    grid station

    Q2 2018 Design

    2 no 132kV GIS at Nakhal

    2 no 132kV AIS at Rustaq

    88km 132kV OHL

    2x125 MVA at Wadi bani Auwf

    8 no. of 132kV GIS at Wadi bani Auwf

    To meet Transmission Security Standard at Rustaq

    during maintenance period

    Load Transfer from Rustaq grid station

    46

    Upgrading of SeebMaingrid

    station from 2 x 63 MVA to 2 x

    125 MVA transformers and

    installing 33kV busbars

    Interlinking

    Q2 2018 Design 2 x 125 MVA transformers

    4 no. 33kV Interlink

    To maintain Transmission Security Standard

    To cater for the new demand in the area

    47Uwaynat132/33kV grid

    stationQ2 2018 Design

    4 x 125 MVA transformers

    2x5 km LILO of Sohar-SIS 132kV OHL

    10 no. 132kV GIS

    4 no. 33kV Interlink

    To cater for the new demand in the area

    Load Transfer from the existing Saham and Sohar grid

    stations

    48400kV connection line to Ibri

    IPP Power PlantQ2 2018 Design

    250 km 400kV OHL between Ibri to

    Qalat Al Awamer

    Adding 8 x 50 MVAr reactors at 400kV

    line ends

    To evacuate power coming from Ibri IPP Power Plant

    and supply Ibri area

    To maintain Transmission Security Standard

  • 7/26/2019 OETC 2016-2020 Projects

    14/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 25

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    49400kV line connection between

    Sohar Free Zone &SISQ2 2018 Design

    42 km 400kV OHL between Sohar Free

    Zone to SIS

    3 x 500 MVA transformers (400/220kV)

    at SIS

    9 no. 400kV GIS at SIS

    3 no. 220kV GIS at SIS

    Adding 2 x 50 MVAr reactor at Sohar

    Free Zone

    To develop 400kV network

    To evacuate full power from Sohar III IPP

    To maintain Transmission Security Standard

    50400kV line connection between

    Sohar Free Zone &MahadhaQ2 2018 Design

    63 km 400kV OHL between Sohar Free

    Zone to Mahadhah

    2 no. 400kV GIS at Mahadhah

    Adding 4 x 50 MVAr reactor at 400kV

    line

    To develop 400kV network

    To evacuate full power from Sohar III IPP

    To maintain Transmission Security Standard

    51

    Installing 220kV GIS and

    adding fourth 125MVA

    transformer at MSQgrid

    station

    Q2 2018Under

    Construction

    1 x 125MVA transformer

    6 no. of 220kV GIS

    8 no. of 132kV GIS

    4 no. 33kV Interlink

    To meet load growth requirements To meet Transmission Security Standard

    To cater for the new demand in the area

  • 7/26/2019 OETC 2016-2020 Projects

    15/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 26

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2018

    52Sohar Free Zone 400kVgrid

    stationQ2 2018 Design

    6 km OHL from Terminal Tower to Sohar FreeZone

    3.3 km 400kV cable from Sohar III IPP to

    Terminal Tower

    0.9 km 400kV cable from Terminal Tower toSohar Free Zone

    3 x 500 MVA transformers (400/220kV) at

    Sohar Free Zone

    20 no. 400kV GIS at Sohar III IPP

    17 no. 400kV GIS at Sohar Free Zone

    3 no. 220kV GIS at Sohar Free Zone

    To evacuate power coming from Sohar III IPP

    Power Plant and to supply area

    To maintain Transmission Security Standard

    53Upgrading Mobellagrid station

    to 220kVQ2 2018

    Under

    Construction

    2 x 500MVA transformers

    2x0.5 km LILO of Al Filaj-Airport Heights220kV OHL

    8 no. 220kV GIS

    2 no 132kV GIS

    Supporting Mobella demand

    Securing of the supply within the area

    Peak 2019

    54Ghala Heights132/33kV grid

    stationQ3 2018 Design

    4 x 125 MVA transformers

    14 no. of 132kV GIS

    New 132kV cable of 7km from Ghala to Ghala

    Heights and 7km from Ghala Heights to Bousher

    4 no. 33kV Interlink

    To cater for the new demand in the area

    Load transfer from Bousher

    To meet Transmission Security Standard

  • 7/26/2019 OETC 2016-2020 Projects

    16/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 27

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2019

    55 Samad 132/33kV grid station Q2 2019 Design

    2 x 63 MVA transformers (shifted from

    Mudhaibi grid station)

    38.5 km 132kV OHL from Mudhaibi

    6 no. 132kV GIS

    To cater for the new demand in the area

    Load transfer from Mudhaibi grid station

    56

    Adding third & fourth

    transformers 132/33kV at

    Ghalagrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    57

    Reactive Power

    Compensation Requirements

    (SVC)

    Q2 2019 Planning SVC at Hamriyah

    SVC at Airport Heights

    To maintain the voltage within the range during the

    transient at the winter time

    58

    Adding third & fourth

    transformers 132/33kV at

    Ameratgrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    59

    Adding third & fourth

    transformers 132/33kV at

    Airport Heightsgrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

  • 7/26/2019 OETC 2016-2020 Projects

    17/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 28

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2019

    60

    Adding third & fourth

    transformers 132/33kV at

    A'salamgrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    61 Halban132/33kV grid station Q2 2019 Design

    4x 125 MVA transformers

    10 no. 132kV GIS

    4 no. 33kV Interlink

    2x0.4 km LILO 132kV UGC Barka

    MainMobella

    To cater for the new demand in the area

    Load transfer from Mobella & Barka Main grid

    stations

    62Sumail Industrial132/33kV

    grid stationQ2 2019 Design

    2 x 125 MVA transformers

    12km LILO of Rusail-Sumail 132kV

    OHL

    8 no. 132kV GIS

    To cater for the new demand in the area

    Load transfer from Sumail grid station

    63 Bedyah132/33kV grid station Q2 2019 Design

    2 x 125 MVA transformers

    0.6 km LILO of Mudhairib

    Al Kamil132 kV OHL

    8 no. 132kV GIS

    To cater for the new demand in the area Load transfer from Mudhairib

  • 7/26/2019 OETC 2016-2020 Projects

    18/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 29

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2019

    64

    Adding third & fourth

    transformers 132/33kV at

    Sohar Free Zonegrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    65 Qabel 400/132kV grid station Q2 2019 Design

    2 x 500 MVA transformers (400/132kV)

    2x0.2 km LILO of 400kV OHL Sur

    Qalat Al Awamer

    2x0.2 km LILO of 132kV OHLMudhairibIbra

    8 no. of 400kV GIS at Qabel grid station

    8 no. 132kV GIS at Qabel grid station

    2 no. 132kV AIS at Mudhairib 132 kV

    grid station

    To increase the system reliability within Sharqia area

    when Al Kamil IPP is retired

    To increase and maintain the system security of 132kV

    lines within the area

    To evacuate power coming from Sur Power Plant

    66Upgrading Bureimi Industrial

    grid station to 220kVQ2 2019 Design

    2 x 500 MVA transformers

    8 no. of 220kV GIS

    2x6 km LILO of 220kV OHL Mahdhah

    UAE

    2 no 132kV GIS

    To maintain Transmission Security Standard

    requirements

    To meet load growth requirements

    To increase the system reliability within Al Bureimi

    area

  • 7/26/2019 OETC 2016-2020 Projects

    19/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 30

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2019

    67Birkat Al Mouz132/33kV grid

    stationQ2 2019 Design

    2 x 125 MVA transformers

    8 no. 132kV GIS

    2x0.35 km LILO of Izki- Nizwa 132 kV OHL

    To cater for the new demand in the area

    Load transfer from Nizwa & Madinat Nizwa

    grid stations

    68Upgrading Khaborahgrid

    station to 220kVQ2 2019 Design

    2 x 500 MVA transformers

    8 no. of 220kV GIS

    2x16km LILO of 220kV OHL SISMIS

    2 no 132kV GIS

    To cater for the new demand in the area

    To increase the system reliability within AlBatinah South North

    69Construction of a new 132 kV

    OHL from JahloottoQuriyatQ2 2019 Planning

    132 kV OHL from Jahloot to Quriyat (50km).

    2 no. 132kV GIS at Quriyat

    2 no. 132kV AIS at Jahloot

    To meet Transmission Security Standard

    70Adding third & fourth

    transformers 132/33kV at

    Bureimi Industrialgrid station

    Q2 2019 Design

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    Load transfer from Bureimi grid station

  • 7/26/2019 OETC 2016-2020 Projects

    20/20

    Five-Year Annual Transmission Capability Statement (2016 - 2020)

    Page | 31

    Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

    S.N Project

    Expected

    Completion

    Date

    Status Main Equipment Purpose

    Peak 2020

    71 Yanqul 132/33kV grid station Q2 2020 Design

    2 x 125 MVA transformers

    8 no. 132kV GIS

    2x4 km LILO 132kV OHL Dank - Al Hayl

    To cater for the new demand in the area

    Load transfer from Al Hayl grid station

    To maintain the 33kV OHL losses

    72

    Adding third & fourth

    transformers 132/33kV at

    Ghubrahgrid station

    Q2 2020 Planning

    2 x 125 MVA transformers

    2 no. 132kV GIS

    4 no. 33kV Interlink

    To meet Transmission Security Standard

    To meet load growth in the area

    73 Khoudh132/33kV grid station Q2 2020 Planning

    4 x 125 MVA transformers

    10 no. 132kV GIS

    LILO 132kV Mawalleh South Rusail

    Industrial

    4 no. 33kV Interlink

    To cater for the new demand in the area

    Load transfer from Mawalleh South grid station

    74 Khuwair132/33kV grid station Q2 2020 Planning

    2 x 125 MVA transformers

    10 no. 132kV GIS

    LILO 132kV MSQ

    Ghubrah

    To cater for the new demand in the area

    Load transfer from MSQ grid station