oetc 2016-2020 projects
TRANSCRIPT
-
7/26/2019 OETC 2016-2020 Projects
1/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 12
Table1: Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
1 Al Ayjah132/33kV grid station Q3 2015 Energized
35 km 132kV OHL from Sur grid
station
2x125MVA transformers
6 no. 132kV GIS
To cater for the new load growth at Ras Al Had area
Solve the issue of voltage drop of 33kV lines. Currently
this area is fed by 33kV feeders from Sur grid station
Load transfer from existing Sur grid
2Madinat Nizwa132/33kV grid
stationQ3 2015 Energized
2 x 125 MVA transformers
6 no. 132kV GIS
12 km 132kV double circuit OHLfrom Nizwa grid station
Load transfer from Nizwa grid station
To meet load growth requirements in the area
3Rusail Industrial132/33kV
grid stationQ3 2015 Energized
12 no. 132kV GIS
4 x 125MVA transformers
Replacement of old 132kV and 33kV switch gears due to
132kV and 33kV short circuit effects
Replacement of old 75MVA transformers with 125MVA
To cater for the new load growth at Rusail area
4 Amerat132/33kV grid station(TX1 & TX2)
Q3 2015 Energized
2 x 125 MVA transformers
8 no. 132kV GIS
5km LILO of 132kV OHL between
MSQ and Jahloot
Load transfer from Jahloot and Wadi Adai grid stations
To meet the high load growth at Amrat area
To resolve 33kV voltage issues
-
7/26/2019 OETC 2016-2020 Projects
2/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 13
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
5A'salam132/33kV grid station
(TX1 & TX2)Q3 2015 Energized
2x 125MVA transformers
8.4km 132kV 2500mm2 UGC from
Mobella to A'salam
7.4km132kV 2500mm2 UGC from
Seeb Main to A'salam
10 no. 132kV GIS
To cater for the load growth at Mobella
Load transfer from grids in this area (Mawalleh , Seeb
Main , Barka Main and Mobella)
6Ghala132/33kV grid station
(TX1 & TX2)Q3 2015 Energized
2 x 125 MVA transformers
12 no. 132kV GIS
4km UGC 2500mm from Airport
Heights grid station
To cater for the expected load growth in Ghala area
Load transfer from Bousher and Airport Heights grid
stations
To supply the new Al Arfan area load
7 Khadhra132/33kV grid station(TX1 & TX2)
Q4 2015 Energized
2 x 125MVA transformers
10. no. 132kV GIS
0.135 km LILO of 132kV between
MISKhabourah
To cater for the new demand within the area
Load transfer from Khaborah & MIS grid stations
-
7/26/2019 OETC 2016-2020 Projects
3/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 14
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
8
New 400kV OHL between Sur
Power Plantand Qalat Al
Awamer400 kV grid stations
Q4 2015 Completed
223 km 400kV lines route length
between SurQalat Al Awamer
To evacuate the power from Sur Generation
To support the voltage and power flow to Al Dakhliah
area
To comply with Transmission Security Standards
requirements
9 Madinat Barka132/33kV gridstation (TX1 & TX2)
Q4 2015 UnderConstruction
2x 125MVA transformers
10 no. 132kV GIS
0.13 km LILO of 132kV OHL from
Filaj to Mualdah
To cater for the load growth at Barka area
To meet Transmission Security Standard
Load transfer from Barka Main
10Al Hamriyah220/132kV grid
stationQ1 2016
Energized
(Grid
Station)
Under
Construction(220kV
OHL)
2 x 500MVA transformers 220/132kV
8 no. 220kV GIS
14 no. 132kV GIS
33.8 km 220kV OHL from Jahloot to
Al Hamriyah
LILO the 132kV Wadi Adai- WadiKabir lines grids station
LILO the 132kV Qurum-Muttrah lines
to Al Hamriyah grids station
To supply the load of the area
To support the voltage at Muscat area Grids
( Wadi Adai, Wadi Kabir, Muttrah , Qurum and AlFalaj)
To evacuate the power coming from Sur via Jahloot grid
station
To increase the system reliability within Muscat area gridstations
To increase and maintain the system security of 132kV
lines within the area
-
7/26/2019 OETC 2016-2020 Projects
4/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 15
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
11 Ibra 132/33kV grid station Q1 2016Under
Construction
6 no. 132kV GIS
28 km OHL 132kV route length
between Mudhairib and Ibra gridstations
2x 125MVA transformers
To meet load growth requirements
To meet Transmission Security Standard
Load transfer from Mudhairib
12New 132kV Line Ashoor -
Awqad(Part-1)Q1 2016
Under
Construction
8.5 km 132kV OHL
1.2 km 132kV UGC
To complete the ring of 132kV system
To meet Transmission Security Standard
13New 132kV Line Ashoor -
Awqad(Part-2)Q1 2016
Under
Construction 48.3 km 132kV OHL
To complete the ring of 132kV system
To meet Transmission Security Standard
14
Sur IPP400/220kV Grid Station
& Jahloot 400/220kV Grid
Station
Q2 2016Under
Construction
At Jahloot:
4 x500MVA, 400/220kV transformers
10 no. 400kV GIS
2 no. 220kV GIS
At Sur Power Plant:
5 x 750MVA 400/220kV
transformers
13 no. 400kV
1 no. 220kV GIS
To evacuate the power from Sur Generation
-
7/26/2019 OETC 2016-2020 Projects
5/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 16
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
15JBB Hassan132/33kV grid
stationQ2 2016
Under
Construction
2 x 125 MVA transformers
8 no. 132kV GIS
2x16 km LILO Al kamil-Sur 132kV
OHL
6x132kV AIS at JBB Ali grid station
Load transfer from existing JBB Ali grid station
To meet load growth requirements in the area
To meet Transmission Security Standard
16Qalat Al Awamer132/33kV
grid stationQ2 2016
Under
Construction
2 x 125 MVA transformers
8 no. 132kV GIS
2x0.62 km LILO of Izki Mudhaibi
132kV UGC
To cater for the new demand in the area
Load Transfer from Izki grid station
17Qalat Al Awamer220kV grid
stationQ2 2016
Under
Construction
2x 500 MVA transformers(220/132kV)
7 no. 220kV GIS
To evacuate the power from Sur Generation
To support the voltage and power flow to Al Dakhliah
area
To comply with Transmission Security Standards
requirements
-
7/26/2019 OETC 2016-2020 Projects
6/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 17
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2016
18Qalat Al Awamer400/220 kV
grid stationQ2 2016
Under
Construction
2x 500 MVA transformers
(400/220kV)
10 no. 400kV GIS
To evacuate the power from Sur Generation
To support the voltage and power flow to Al Dakhliah
area
To comply with Transmission Security Standards
requirements
Peak 2017
19 Dreez132/33kV grid station Q4 2016Under
Construction
2 x 125 MVA
30 km 132kV OHL from Ibri
8 no. 132kV GIS
To cater for the new demand within the area
Load transfer from Ibri and Al Hayl grid stations
20Sohar Free Zone220/132/33kV
grid stationQ4 2016
Under
Construction
2x 0.17 km LILO Wadi Al JizziLiwa 132kV OHL
2x 500 MVA transformers
8 no. 220kV GIS
2x 0.48 km UGC as LILO of 220kV
OHL Sohar 2 PS -SIS 2x125MVA transformers
16 no.132kV GIS
To cope with the load growth.
To meet Transmission Security Standard
To supply the free zone area industrial loads
-
7/26/2019 OETC 2016-2020 Projects
7/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 18
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2017
21Replacement of Mahadha
132kV AIS to GISQ4 2016
UnderConstruction
14 no. 132kV GIS
To replace the existing AIS to GIS due to:
Lightening
Maintenance Issus
Old Assets
System reliability
System security
22 Upgrading Misfahgrid stationto 400kV
Q4 2016 UnderConstruction
3 x 500MVA transformers
(400/220kV)
11 no. 400kV GIS
3 no. 220kV GIS
To support the evacuation of Sur power plant
To maintain the security requirement
23Adding third & fourth
transformers 132/33kV at
Muladahgrid station
Q1 2017Under
Construction
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet load growth requirements
To meet Transmission Security Standard
24Adding third & fourth
transformers 132/33kV at Liwa
grid station
Q1 2017Under
Construction
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To cater for the new demand in the area
To meet Transmission Security Standard
-
7/26/2019 OETC 2016-2020 Projects
8/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 19
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2017
25400 kV OHL between Qalat Al
Awamerand MisfahQ2 2017
Under
Construction 100 km OHL 400kV
To support the evacuation of Sur power plant
To meet Transmission Security Standard
2633kV busbars Interlinking atBousher & Mawalleh South
grid stationsQ2 2017 Design
8 no. of 33kV at Bousher & MawallehSouth
To meet Transmission Security Standard
27 Saadah132/33kV grid station Q2 2017Under
Construction
4x125MVA Transformers
10 no. of 132kV GIS.
4 no. 33kV Interlink
13km LILO from Ashoor-
Awqad132kV UGC
To meet load growth requirements To meet Transmission Security Standard
Load Transfer from Al Qarm, Ittin and Awqad grid
stations
28Daghmar132/11kV grid
stationQ2 2017
UnderConstruction
3x 50 MVA (shifted from the
Mawalleh North grid station)
4km OHL from Quriyat grid stat ion
2 no. 132kV GIS at existing Quriyatgrid station
7 no. 132kV GIS at Daghmar
To supply the new IWP at Quriyat
-
7/26/2019 OETC 2016-2020 Projects
9/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 20
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2017
29
Connection of Salalah-2 IPP&Adding third & fourth
transformers to Salalah Free
Zonegrid station
Q2 2017Under
Construction
16 no. of 132kV GIS
2x125MVA transformers
To connected the new Salalah-2 IPP Power Plant
To meet load growth requirements
To meet Transmission Security Standard
30
132kV Linking System between
Al Falaj, Muttrahand Wadi
KabirGrid stations & Adding
Fourth 125MVA transformer at
Wadi Kabirgrid station
Q2 2017 UnderConstruction
3km 132kV 2500mm2 cables between
Muttrah-Al Falaj grid stations
One circuit Twin YEW 1.5 km OHL and 2
km UGC 132kV between Muttrah-Wadi
Kabair grid stations
10 no. 132kV GIS at Wadi Kabair grid
station
8 no. 132 GIS at Al Falaj
1 x 125MVA transformer at Wadi Kabir
To secure the loads and meet Transmission
Security Standard.
Safety clearance and environment issues
To cater for the new demand in the area
Peak 2018
31 Adding 400kV reactors Q3 2017 Design
2x35 MVAr reactors at end of 400kV line
between Sur-Jahloot
4x40 MVAr reactors at end of 400kV line
between Sur-Qalat Al Awamer
2x30 MVAr reactors at end of 400kV line
between Qalat Al Awamer-Misfah
To maintain the voltage within the range during
the winter time
-
7/26/2019 OETC 2016-2020 Projects
10/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 21
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
32Dil Abdusalam132/33kV grid
stationQ3 2017 Design
2 x 125 MVA transformers
2x8 km LILO of Saham-
Khaborah132kV OHL
8 no. 132kV GIS
To cater for the new demand in the area
Load Transfer from Saham & Khaborah grid stations
To meet Transmission Security Standard
33
Adding third & fourth
transformers 132/33kV at
Khadhragrid station
Q3 2017 Design 2 x 125 MVA transformers
4 no. 33kV Interlink
To meet Transmission Security Standard
To cater for the load growth in the area
34
Adding third & fourth
transformers 132/33kV at
Madinat Barkagrid station
Q3 2017 Design 2 x 125 MVA transformers
4 no. 33kV Interlink
To meet Transmission Security Standard
To cater for the load growth in the area
35Madinat Shinas132/33kV
grid stationQ3 2017 Design
2 x 125 MVA transformers
24.06 km 132kV OHL from Shinas to
Madinat Shinas
2 no. 132kV GIS at Shinas
6 no. 132kV GIS at Madinat Shinas
To cater for the new demand in the area
Load Transfer from Shinas grid station
To meet Transmission Security Standard
-
7/26/2019 OETC 2016-2020 Projects
11/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 22
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
36 Suwaiq 132/33kV grid station Q3 2017 Design
2 x 125 MVA transformers
2x0.2 km LILO of MIS-Khadhra
132kV OHL
8 no. 132kV GIS
To cater for the new demand in the area
To meet Transmission Security Standard
Load Transfer from MIS grid station
37 Sinaw132/33kV grid station Q3 2017 Design
2 x 125 MVA transformers
2x15 km LILO of Qalat Al Awamer -
Mudhaibi 132kV OHL
8 no. 132kV GIS
To cater for the new demand in the area
Load transfer from Mudhaibi Solve the issue of voltage drop of 33kV lines
To meet Transmission Security Standard
38
Upgrading of Mawalleh North
grid station from 3x50MVA
(132/11kV) to 2 x 125 MVA
(132/33kV) transformers
Q3 2017 Design 2 x 125 MVA transformers
To cater for the new demand in the area
To support the 33kV network in the Seeb area and
enable to transfer more load from neighbouring grid
stations (Seeb & Mawalleh)
39 Jebreen132/33kV grid station Q3 2017 Design
2 x 125 MVA transformers
2x0.5 km LILO of Nizwa - Ibri
132kV OHL
8 no. 132kV GIS
To cater for the new demand in the area
Load Transfer from Bahla grid station
To meet Transmission Security Standard
-
7/26/2019 OETC 2016-2020 Projects
12/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 23
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
40 Ibri 400kVgrid station Q3 2017Under
Construction
3 x 500 MVA transformers (400/220kV)
19 No. 400kV GIS at Ibri IPP
10 No. 220kV GIS at Ibri IPP
2x4.3 km LILO of 220kV OHL IbriMahadha
To evacuate power coming from Ibri IPP
Power Plant and supply Ibri area
To maintain Transmission Security
Standard
41
Adding 2x125MVA
transformers 220/33kV at
Barka-3 PSgrid station
Q4 2017 Design 2 x 125 MVA transformers
2 no. 220kV GIS
To Supply the Barka IWP
Load Transfer from Barka Main grid station
42
Construction of a new 132 kV
OHL from Sohar Free Zoonto
Shinas
Q4 2017 Design
2 no. 132kV GIS at Shinas
2 no. 132kV GIS at Sohar Free Zone
20km 132kV OHL from Sohar Free Zone to Shinas
To meet Transmission Security Standard
43
Upgrading of Adamgrid
station from 2x40MVA to
2x125MVA transformers
Q2 2018 Design 2 x 125 MVA transformers
6 no. 132kV GIS
To maintain Transmission Security
Standard
To cater for the new demand in the area
44 Security of SIAgrid station Q2 2018 Design
1 no 132kV GIS
2 no. of 220kV GIS
1x500MVA transformer
3.2 km UGC of 220kV SPS 1 SIA
To meet Transmission Security Standard at
SIA during maintenance period
-
7/26/2019 OETC 2016-2020 Projects
13/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 24
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
45
New 132kV double circuits
lines from Rustaq-Wadi bani
Auwf-Nakhalwith a new
Wadi bani Auwf132/33 kV
grid station
Q2 2018 Design
2 no 132kV GIS at Nakhal
2 no 132kV AIS at Rustaq
88km 132kV OHL
2x125 MVA at Wadi bani Auwf
8 no. of 132kV GIS at Wadi bani Auwf
To meet Transmission Security Standard at Rustaq
during maintenance period
Load Transfer from Rustaq grid station
46
Upgrading of SeebMaingrid
station from 2 x 63 MVA to 2 x
125 MVA transformers and
installing 33kV busbars
Interlinking
Q2 2018 Design 2 x 125 MVA transformers
4 no. 33kV Interlink
To maintain Transmission Security Standard
To cater for the new demand in the area
47Uwaynat132/33kV grid
stationQ2 2018 Design
4 x 125 MVA transformers
2x5 km LILO of Sohar-SIS 132kV OHL
10 no. 132kV GIS
4 no. 33kV Interlink
To cater for the new demand in the area
Load Transfer from the existing Saham and Sohar grid
stations
48400kV connection line to Ibri
IPP Power PlantQ2 2018 Design
250 km 400kV OHL between Ibri to
Qalat Al Awamer
Adding 8 x 50 MVAr reactors at 400kV
line ends
To evacuate power coming from Ibri IPP Power Plant
and supply Ibri area
To maintain Transmission Security Standard
-
7/26/2019 OETC 2016-2020 Projects
14/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 25
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
49400kV line connection between
Sohar Free Zone &SISQ2 2018 Design
42 km 400kV OHL between Sohar Free
Zone to SIS
3 x 500 MVA transformers (400/220kV)
at SIS
9 no. 400kV GIS at SIS
3 no. 220kV GIS at SIS
Adding 2 x 50 MVAr reactor at Sohar
Free Zone
To develop 400kV network
To evacuate full power from Sohar III IPP
To maintain Transmission Security Standard
50400kV line connection between
Sohar Free Zone &MahadhaQ2 2018 Design
63 km 400kV OHL between Sohar Free
Zone to Mahadhah
2 no. 400kV GIS at Mahadhah
Adding 4 x 50 MVAr reactor at 400kV
line
To develop 400kV network
To evacuate full power from Sohar III IPP
To maintain Transmission Security Standard
51
Installing 220kV GIS and
adding fourth 125MVA
transformer at MSQgrid
station
Q2 2018Under
Construction
1 x 125MVA transformer
6 no. of 220kV GIS
8 no. of 132kV GIS
4 no. 33kV Interlink
To meet load growth requirements To meet Transmission Security Standard
To cater for the new demand in the area
-
7/26/2019 OETC 2016-2020 Projects
15/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 26
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2018
52Sohar Free Zone 400kVgrid
stationQ2 2018 Design
6 km OHL from Terminal Tower to Sohar FreeZone
3.3 km 400kV cable from Sohar III IPP to
Terminal Tower
0.9 km 400kV cable from Terminal Tower toSohar Free Zone
3 x 500 MVA transformers (400/220kV) at
Sohar Free Zone
20 no. 400kV GIS at Sohar III IPP
17 no. 400kV GIS at Sohar Free Zone
3 no. 220kV GIS at Sohar Free Zone
To evacuate power coming from Sohar III IPP
Power Plant and to supply area
To maintain Transmission Security Standard
53Upgrading Mobellagrid station
to 220kVQ2 2018
Under
Construction
2 x 500MVA transformers
2x0.5 km LILO of Al Filaj-Airport Heights220kV OHL
8 no. 220kV GIS
2 no 132kV GIS
Supporting Mobella demand
Securing of the supply within the area
Peak 2019
54Ghala Heights132/33kV grid
stationQ3 2018 Design
4 x 125 MVA transformers
14 no. of 132kV GIS
New 132kV cable of 7km from Ghala to Ghala
Heights and 7km from Ghala Heights to Bousher
4 no. 33kV Interlink
To cater for the new demand in the area
Load transfer from Bousher
To meet Transmission Security Standard
-
7/26/2019 OETC 2016-2020 Projects
16/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 27
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2019
55 Samad 132/33kV grid station Q2 2019 Design
2 x 63 MVA transformers (shifted from
Mudhaibi grid station)
38.5 km 132kV OHL from Mudhaibi
6 no. 132kV GIS
To cater for the new demand in the area
Load transfer from Mudhaibi grid station
56
Adding third & fourth
transformers 132/33kV at
Ghalagrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
57
Reactive Power
Compensation Requirements
(SVC)
Q2 2019 Planning SVC at Hamriyah
SVC at Airport Heights
To maintain the voltage within the range during the
transient at the winter time
58
Adding third & fourth
transformers 132/33kV at
Ameratgrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
59
Adding third & fourth
transformers 132/33kV at
Airport Heightsgrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
-
7/26/2019 OETC 2016-2020 Projects
17/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 28
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2019
60
Adding third & fourth
transformers 132/33kV at
A'salamgrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
61 Halban132/33kV grid station Q2 2019 Design
4x 125 MVA transformers
10 no. 132kV GIS
4 no. 33kV Interlink
2x0.4 km LILO 132kV UGC Barka
MainMobella
To cater for the new demand in the area
Load transfer from Mobella & Barka Main grid
stations
62Sumail Industrial132/33kV
grid stationQ2 2019 Design
2 x 125 MVA transformers
12km LILO of Rusail-Sumail 132kV
OHL
8 no. 132kV GIS
To cater for the new demand in the area
Load transfer from Sumail grid station
63 Bedyah132/33kV grid station Q2 2019 Design
2 x 125 MVA transformers
0.6 km LILO of Mudhairib
Al Kamil132 kV OHL
8 no. 132kV GIS
To cater for the new demand in the area Load transfer from Mudhairib
-
7/26/2019 OETC 2016-2020 Projects
18/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 29
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2019
64
Adding third & fourth
transformers 132/33kV at
Sohar Free Zonegrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
65 Qabel 400/132kV grid station Q2 2019 Design
2 x 500 MVA transformers (400/132kV)
2x0.2 km LILO of 400kV OHL Sur
Qalat Al Awamer
2x0.2 km LILO of 132kV OHLMudhairibIbra
8 no. of 400kV GIS at Qabel grid station
8 no. 132kV GIS at Qabel grid station
2 no. 132kV AIS at Mudhairib 132 kV
grid station
To increase the system reliability within Sharqia area
when Al Kamil IPP is retired
To increase and maintain the system security of 132kV
lines within the area
To evacuate power coming from Sur Power Plant
66Upgrading Bureimi Industrial
grid station to 220kVQ2 2019 Design
2 x 500 MVA transformers
8 no. of 220kV GIS
2x6 km LILO of 220kV OHL Mahdhah
UAE
2 no 132kV GIS
To maintain Transmission Security Standard
requirements
To meet load growth requirements
To increase the system reliability within Al Bureimi
area
-
7/26/2019 OETC 2016-2020 Projects
19/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 30
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2019
67Birkat Al Mouz132/33kV grid
stationQ2 2019 Design
2 x 125 MVA transformers
8 no. 132kV GIS
2x0.35 km LILO of Izki- Nizwa 132 kV OHL
To cater for the new demand in the area
Load transfer from Nizwa & Madinat Nizwa
grid stations
68Upgrading Khaborahgrid
station to 220kVQ2 2019 Design
2 x 500 MVA transformers
8 no. of 220kV GIS
2x16km LILO of 220kV OHL SISMIS
2 no 132kV GIS
To cater for the new demand in the area
To increase the system reliability within AlBatinah South North
69Construction of a new 132 kV
OHL from JahloottoQuriyatQ2 2019 Planning
132 kV OHL from Jahloot to Quriyat (50km).
2 no. 132kV GIS at Quriyat
2 no. 132kV AIS at Jahloot
To meet Transmission Security Standard
70Adding third & fourth
transformers 132/33kV at
Bureimi Industrialgrid station
Q2 2019 Design
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
Load transfer from Bureimi grid station
-
7/26/2019 OETC 2016-2020 Projects
20/20
Five-Year Annual Transmission Capability Statement (2016 - 2020)
Page | 31
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N Project
Expected
Completion
Date
Status Main Equipment Purpose
Peak 2020
71 Yanqul 132/33kV grid station Q2 2020 Design
2 x 125 MVA transformers
8 no. 132kV GIS
2x4 km LILO 132kV OHL Dank - Al Hayl
To cater for the new demand in the area
Load transfer from Al Hayl grid station
To maintain the 33kV OHL losses
72
Adding third & fourth
transformers 132/33kV at
Ghubrahgrid station
Q2 2020 Planning
2 x 125 MVA transformers
2 no. 132kV GIS
4 no. 33kV Interlink
To meet Transmission Security Standard
To meet load growth in the area
73 Khoudh132/33kV grid station Q2 2020 Planning
4 x 125 MVA transformers
10 no. 132kV GIS
LILO 132kV Mawalleh South Rusail
Industrial
4 no. 33kV Interlink
To cater for the new demand in the area
Load transfer from Mawalleh South grid station
74 Khuwair132/33kV grid station Q2 2020 Planning
2 x 125 MVA transformers
10 no. 132kV GIS
LILO 132kV MSQ
Ghubrah
To cater for the new demand in the area
Load transfer from MSQ grid station