of “legacy” consistsweb2.utc.edu/~qvp171/2015 concrete canoe(kennesaw state...after a series of...
TRANSCRIPT
Executive Summary
Southern Polytechnic State University (SPSU) is located in the suburban setting of
Marietta, Ga. In the southeast ASCE student conference, the SPSU concrete canoe team
has placed 18th, 18
th, and 9
th in the last three years of competition. “Legacy” has a
maximum length of 19 feet 1 inches, a maximum width of 32 inches, and a weight of 330
pounds. The exterior design of the canoe is inspired by the hull of a battleship. The inside
of “Legacy” consists of a unique rendition of the American and the Gadsden flag. The
concrete mix used in the canoe is a high strength, yet lightweight design with a 1300 psi
compressive strength and a 210 psi tensile strength at a mere 57.4 lbs/ft3 dry and 60 lbs/ft
3
wet. The canoe is further supported with two layers of geo mesh reinforcement material.
Project Management
Team Captain JD Bowers spent the majority of the fall semester designing the
new mold and finding a few people to help in the process. After good help was found it
was then time to start construction of the mold. The mold was completed in early January
and the canoe poured soon after.
Additionally, the team faced a challenge of funding and was required to use
surplus materials from previous years in order to offset the cost required to build the
canoe. The main sources of funding for the project came initially from Southern
Polytechnic’s SGA, and later came from the Alumni Association. The initial batch of
funds were primarily used in the replenishing of exhausted materials and worn out
equipment critical to canoe construction. The remaining funds from the alumni
association, as well as post-fiscal SGA funds, were then used to cover transportation and
other costs associated with competition. After competition, any leftover money will be
used to preorder equipment and materials for next year’s competition.
Throughout the spring semester, faculty advisor Nancy Turner, P.E. periodically
evaluated the canoe’s progress providing suggestions for adjustments as needed. In terms
of safety measures, all team members participating have been required to wear close toed
shoes, secure hair, avoid jewelry, and exercise caution while lifting heavy objects.
Additionally, measures have been taken to ensure the canoe room remains well ventilated
during construction. Eyewear and masks have been provided and their use strongly
encouraged.
In terms of scheduling, ambitious deadlines for housekeeping matters, formwork
creation, concrete pouring, and preparation for competition were set in order to foster
efficient progression through the critical path of events (see project schedule on page 10).
Although many of these deadlines proved to be unrealistic, the canoe was still poured on
January 12nd
. This extra time has proved to be invaluable for several reasons. Firstly, the
canoe was given ample time to cure in order to reach its peak 28 day strength. Secondly,
unforeseen events such as two winter weather events has had minimal impact on progress
towards competition. The extra time has proved vital in preventing rushing through
finishing.
Organization Chart
Team Members
Team Captains
Faculty Advisor
Nancy Turner, P.E.
Nathan Boyd
Overseeing:
1. Technical Communication
2. Bookkeeping
Brian Demeza
-Canoe Finishing
-Mold Construction
Simone Belay
- Concrete Placement
Nate Echols
-Canoe Finishing
-Mold Construction
Tim Dow
-Canoe Finishing
-Mold Construction
Brandon Thrasher
-Concrete Placement
JD Bowers
Overseeing:
1. Construction
2. Paddling
Zach Strickland
-Canoe Finishing
-Mold Construction
-Concrete Placement
Elizabeth Cook
-Canoe Finishing
Valerie Croy
-Canoe Finishing
Ethan Grant
-Canoe Finishing
J.D. Bowers
-Transportation
-Canoe Finishing
Hull Design and Structural Analysis
The hull design of this year’s canoe incorporates several different allocations of
previous year’s canoes. The idea of Legacy came from 3 years’ experience of
competition. Since there have been so many different types of canoes over these past
years we chose a design that will try to incorporate many different small items so that it
will perform well. Legacy is 19’1” long and 31” wide. The reason for the massive size of
this canoe is so that the rowers are comfortable and feel stable in the water. The width of
Legacy should be more than enough displacement so the side to side motion will not be
an issue. The bottom of Legacy is flat. This idea came into play for water displacement.
The idea of a flat surface on the bottom of the canoe is something that is new to all of the
people that worked on building it, but after some test was run we determined that it was
not harmful, but not really helpful either. Having a flat bottom made construction easier
though. The nose and tail of Legacy was the next area that was looked at. After watching
races in the years before and the different shapes of the noses it was determined that a
wide slightly round nose is the way to go. This does not allow the canoe to “dig in” when
making sharp turns. Legacy is 14” deep this came into play solely from last year’s SPSU
canoe which was only 9” deep. After seeing it in the water last year it was determined
that this year’s canoe would be deeper so that it set out of the water higher.
Overall Legacy should be a canoe that performs very well against competition.
With the massive size of the canoe this year it will be a little bit harder to transport and
maneuver on land but in the water it should float and row very well.
Figure 1: Legacy after foam mold pulled out- Bowers, 2015
Structural Analysis
The structural Analysis of Legacy was based solely the research of Stephanie
Stache. In her write up she did analysis of the stresses with 2 people in the canoe as well
as 4 people. These images are displayed below. These images show the max stress points
in the canoe with the respective loads.
Figure 2: max stress 2 people- Stache, 2013
Figure 3: max stress 4 people- Stache, 2013
Development and Testing
The concrete mix design used in this year’s canoe is practically equivalent to the
mix design from last year. The reuse of this design is justified by its flexural strength,
durability, and low unit weight. The importance of using concrete with high flexural
strength cannot be overstated since the live load of the paddlers loads the concrete in
bending. In addition, the canoe needs to be able to withstand repeated cyclic loadings to
avoid cracking. The specific fiber incorporated, Nycon-PVA RECS7, has proven to
reduce the impact, shatter and abrasion resistance of concrete. This reputation has been
reinforced in lab tests. In compressive and tensile tests, test cylinders reinforced with
Nycon fibers showed considerable improvements in maximum strength after loaded near
failure as compared to cylinders without Nycon fibers. The fibers also aid in minimizing
permanent deformations in the canoe hull. Acryl 60 was used as the primary admixture in
the concrete, serving as a superplastisizer and to improve the flex properties of the canoe
mix. Although a drawback of using this admixture is strength loss, the added benefit of
increased flexibility justified the sacrifice. For sustainability reasons, Type C fly ash was
used to replace a marginal portion of cement paste.
Figure 4: 2 inch Concrete Cubes after 7 Day Curing, (Ginn, 2013)
Figure 1 displays concrete cubes possessing the final concrete mix proportions
used in the canoe design. The process for determining the mix proportions deviated from
standard methods and is detailed as follows: Three glass-based aggregates were used in
the concrete mix design: Scissor Poraver expanded glass and 3M glass bubbles. Most
notably, Poraver is an environmentally sustainable product made exclusively recycled
materials. This lightweight aggregate has a crush strength of 200 psi. This is significantly
stronger than most lightweight aggregates such as perlite and vermiculite Proportioning
of these aggregates was first determined by constructing a Microsoft Excel gradation
curve and forcing the fine aggregates used to fall within the minimum and maximum
limits determined by the gradation. The water to cement ratio was determined by setting a
target compressive strength of 1500 psi and tensile strength of 200 psi. The maximum
aggregate size was determined by limiting the size to ¾ of the minimum clear space
between the reinforcement materials and the edge of the canoe. According to this target,
the rough maximum aggregate size was determined to be roughly 1/8 of an inch. With the
general mix design parameters set, the finest aggregates used (3m products) and silica
fume were used to replace small portions of cement. The reasoning behind these tests was
to reduce the unit weight without significantly compromising strength. Several trials were
conducted on 2 inch concrete cubes until the unit weight was reduced by approximately
10 lb/ft3.
After a series of testing and fine tuning material proportions, a final mix was
designed weighing 57.4 lb/ft3. This was paired with a final compressive strength of 1300
psi, a splitting tensile strength of 210 psi, a flexural strength of 790 psi, and a maximum
bending moment of 1500 𝑙𝑏 𝑖𝑛⁄ . Photos of the compression, flexural and splitting tension
samples can be seen in figure 2 below:
Figure 5: (Left) Compressive Failure, (Right) Flexural and Bending (Ginn, 2013).
Construction
The formwork of the 2015 canoe Legacy went through many different prototypes
before a good design was chosen. The initial formwork was to be created from wood and
Plexiglas as seen in figure 6.
Figure 6: wood and Plexiglas mold- Bowers, 2014
After it was determined that the wood and Plexiglas mold would not work for us
we then decided to use 3 pound density foam for the mold. This mold was created by
using the plywood stations already cut for the mold we already tried, and a hotwire to cut
the foam as seen in figure 7. This male mold was placed on the table to be cut smoothly
and level. The attention to detail in this mold will make it useful for at least one more
year.
Figure 7: Cutting foam with hotwire and complete foam mold-Bowers, 2014
With all the stations cut and leveled on the table and the centerline marked on
each foam station the mold was ready to be taped together and covered with a thin plastic
to keep the concrete from adhering to the foam as seen in figure 8.
Figure 8: Taping stations together before pouring- Bowers, 2015
After the mold had been taped and covered with plastic it was ready for concrete.
In order to minimize concrete placement time, labor was divided between two teams: one
responsible for material proportioning and another responsible for concrete placement
within the mold. Materials were proportioned by mass using concrete test cylinders and
mixed in buckets. Each proportion of dry aggregates then were incorporated into a 5
gallon bucket followed immediately by admixture and water in order to minimize dust.
The concrete placement team then consolidated the aggregates, water, and admixture
with the cementations materials. During this consolidation, the materials were rapidly
mixed with a mortar paddle. The wet concrete was then ready to place inside the mold.
Roughly ½ inch of concrete was then applied via hands to the outside of the mold. The
precut geomesh reinforcing material was then placed on top of the initial layer before the
remaining layer of concrete was added. The reinforcement material was sealed inside the
concrete by pulling back the outer edges of reinforcement and filling the gap with wet
concrete. As the concrete was place it was troweled smooth to try and eliminate most of
the sanding process.
After a 21 day curing process via humidifier and controlled climate, the
canoe was prepared for finishing using primarily belt and rotary sanders. The canoe was
now ready for paint, sealer, and other finishing touches.
Environmental and economic sustainability incorporated in the canoe was
primarily incorporated in the formwork construction. The development of a reusable
mold for future competition years aids to limit the yearly waste of materials and money
that could be channeled into other aspects of the canoe design. It also keeps lumber,
foam, and other miscellaneous materials out of the landfill that are deemed useless at the
end of the competition year.
Proposed Project Schedule
August: Recruitment
Attend Student Government
Meeting (if applicable)
Advertise student
organization/recruitment
Update Orgsync roster and
pertinent Information
September: Buisness
Inventory and Reorder supplies
after rules released
Submit budget to alumni board
Visit sponsors if budget requires
October: Mold Creation
Design mold
o Design build process
o Design shape in
accordance with updated
rules
Actual Project Schedule
October
10/4/14: SGA Meeting
10/7/14: Submit Budget Requests
10/21/14: Alumni Presentation
10/24/14: Interest Meeting
10/31/14: Mold Build Completed
November
Mold Set Completed
December
12/11/14: Mold Preparation Began
12/31/14: Mold Preparation Ended
January
1/12/15: Concrete Placement
February
2/2/15: Canoe removed from mold
2/9/15: Canoe sanding finished
2/22/15: Started painting
Create Mold
November: Concrete Pouring
Preparation/concrete pouring
Curing Process
January: Canoe Finishing
Removal from mold
Sanding/Painting
February-March: Final Preparation
Complete report/notebook
Powerpoint
Tension cylinders
Compile products
Booth preparation: (displays, tables, stand, tent)
Order mold materials
Create canoe concrete mix design
References
Ginn, Casey (2013). “Canoe Report 2013” Southern Polytechnic State University (SPSU), Marietta, GA.
http://poraver.com/sites/default/files/download/Poraver_Weigths_Dimensions_capacities.pdf
Mixture ID: Design Proportions (Non
SSD)
Actual Batched Proportions
Yielded Proportions YD
Design Batch Size (ft
3):
0.25
Cementitious Materials SG Amount (lb/yd
3)
Volume (ft
3)
Amount (lb)
Volume (ft
3)
Amount (lb/yd
3)
Volume (ft
3)
CM1 Portland Cement 3.15 694.75 2.041 6.43 2.041 695 2.041
CM2 Fly Ash 2.30 121.58 0.491 1.13 0.491 121.5 0.491
Total Cementitious Materials: 816.33 2.532 7.56 2.532 816.50 2.532
Fibers
F1 Nycon PVA 1.12 15.00 0.200 0.12 0.200 14.02 0.200
Total Fibers: 15.00 0.20 0.12 0.20 14.02 0.20
Aggregates
A1 Poarver 0.1-0.3 mm Abs: 1.93
0.69 30.40 0.406 0.28 0.406 30.50 0.406
A2
Poarver 0.25-0.5 mm Abs: 10.2
0.59 60.79 0.949 0.56 0.949 60.75 0.949
A3 Poarver 1-2mm Abs: 8.68
0.39 75.99 1.795 0.70 1.795 76.00 1.795
A4 Poarver 2-4mm Abs: 8.68
0.34 121.58 3.324 1.13 3.324 121.50 3.324
A5 3M IM16K Abs: 5.65 0.46 21.71 0.435 0.20 0.435 21.75 0.435
A3 K20 Abs: 6.02 0.20 60.79 2.800 0.56 2.800 61.00 2.800
Total Aggregates: 371.26 9.709 3.96 9.709 371.50 9.709
Water
W1 Water for CM Hydration (W1a + W1b)
1.00
260.34 4.17 2.41 0.039 260.50 4.17
W1a. Water from Admixtures
24.19
0.22
24.25
W1b. Additional Water 236.15 2.19 236.00
W2 Water for Aggregates, SSD 1.00 69.67 0.65 69.75
Total Water (W1 + W2): 330.01 4.17 3.06 0.04 330.25 4.17
Solids Content of Latex, Dyes and Admixtures in Powder Form
S1 None Used
Total Solids of Admixtures:
Admixtures (including Pigments in Liquid Form)
% Solids
Dosage
(fl/ oz/cwt)
Water in
Admixture (lb/yd
3)
Amount (fl oz)
Water in
Admixture (lb)
Dosage (fl oz/cwt)
Water in
Admixture (lb/yd
3)
Ad1 Acrylic 60 lb/gal 0.00 2164.84 27.78 25.00 0.32 2155.60 27.66
Water from Admixtures (W1a): 27.78 0.32 27.66
Cement-Cementitious Materials Ratio 0.524 0.523 0.525
Water-Cementitious Materials Ratio 0.404 0.405 0.404
Slump, Slump Flow, in. 0 +/- 0.25 in 0 +/- 0.25 in 0 +/- 0.25 in
M Mass of Concrete. lbs 1517.60 1514.80 1511.44
V Absolute Volume of Concrete, ft
3
27.10 27.05 26.99
T
Theorectical Density, lb/ft3
= (M / V)
56.00 56.00 56.00
D Design Density, lb/ft
3 =
(M / 27) 56.21
D Measured Density, lb/ft3 56.93 57.40
A
Air Content, % = [(T - D) / T x 100%]
6.20 6.94 7.01
Y Yield, ft
3 =
(M/ D) 27 27 27
Ry Relative Yield = (Y / YD)
1.043
Appendix B- Mixture Proportions
Appendix C- Bill of Materials
Material Quantity Unit Cost
Total
Cost
Portland Cement, Type I/II 376 lbs $9.45/94 lb bag $37.80
Fly Ash, Class C 5 gal Donated N/A
Poraver Expanded Glass
Aggregate 231 lbs
$400/ 231 lbs
shipment $400
iM16K Glass Bubbles Aggregate 5 gal $50/gal $250
K1 Glass Bubbles Aggregate 40 lbs $655/40 lbs $655
Force 10,000 D Silica Fume
Powder 70 lbs Donated N/A
ACRYL 60 Admixture 5 gal $148/5 gal $148
Semi-Gloss Paint 2 gal $28/gal $56
Concrete Sealer
Foam Mold, Complete
Lump
Sum $935 $935
Total Production Cost $2,444