Page 1: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Off-grid Dendro Power

Page 2: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Sri Lanka

About 1 - 1.5 million households in Sri Lanka will be left without grid-connected electricity.

Page 3: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Off-grid electricity generating technologies

The approximate cost comparisonInstallation costs per 1kW

Micro-hydro Rs 200,000 Dendro Rs 300,000 Bio-gas Rs 300,000 Wind Rs 600,000 Solar PV Rs 1,000,000

Page 4: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Step 1: Moneragala District participatory workshop for sensitising the district government officials, community based organisations and farmer groups - Nov 2001

Step 2: Pre-feasibility studies in four off-grid villages

Step 3: Cross checking with CEB grid extension plans

Step 4: Selection of a village for the feasibility study

Page 5: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Pilot Dendro Power Project in Wadakahakiula

Page 6: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Overall objective of the feasibility study

To examine whether necessary social conditions for setting up the proposed pilot plant exist in the village of Wadakahakiula.

An implementation plan should be developed with the active participation of intended beneficiaries and other stakeholders.

Wadagahakiula Project feasibility study: 2002 December

Page 7: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Necessary conditions

• Social acceptability of the community• Availability of the infrastructure for operation

and maintenance of the plant, • Affordability of majority of the population to

pay for electricity,• Enthusiasm of the community• To identify fuel-wood species• To assess the availability of fuel-wood in

required quantities for operation of the dendro power plant.

• To assess the potential for growing the fuel-wood if required

Page 8: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Necessary conditions

• To review and select the most appropriate energy conversion technology

• To develop preliminary design of the dendro powered electrification system

• To develop, the institutional mechanisms necessary for implementation and post implementation management

• To prepare cost estimates of the project• To establish a tariff structure for sustainable

operation and management of the power plant

Page 9: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Study Methodology

• Social assessment – 2day participatory workshop with 60 households

• Questionnaire based survey of all households – survey carried out by selected village members

• Fuelwood survey – based on field assessment.

• Distribution system design – based on field survey

• Siting of powerhouse – based on technical and social concerns

• Institutional and management system – developed through a participatory workshop

Page 10: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Profile of the Village• Suggested by CEB Uva office

• Situated in Badalkumbura DS area

• 3 km away from grid

• Permanent houses – 38%

• Semi-permanent houses – 36%

• Temporary houses – 26%

• Main source of income – Pepper cultivation (68% of households)

• Land ownership – 1 to 3 acres per household (74%)

• Average monthly income – Rs.6000 per household

• Current monthly expenditure on energy – approximately Rs.500 per household

Page 11: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project Profile

• No. of beneficiary households – 100

• Max. demand – 250W per house

• Period of electricity demand – 5 to 7am and 6 to 10pm

• Main uses of electricity – lighting, TV, Radio, iron

• Technology – Gasifier system

• Mode of operation – 100% gas

• Fuelwood type – Gliricidia (Nanchi)

• Fuelwood availability – widely grown in the village for fencing and pepper planting

Page 12: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Major Conclusions from the Feasibility Study

• Community participation is active however there are no well established CBOs exist in the village.

• Priority list 1- education 2- unemployment 3- electricity

• Willingness to obtain electricity – 94% of the households.

• Opportunities exist to initiate income-generating activities.

• Affordability of households to pay for electricity is high. At least 90% of the households are able become its direct beneficiaries.

• Availability of natural, human and financial resources is high.

• Fuelwood supply from existing plantations is more than enough for the plant.

• Dendro technology is mature for deployment in a village scheme.

Page 13: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Social Risks predicted

• Grid electricity may come to the village through political interventions.

• In the event of grid electricity is provided to the village, potential to access grid electricity is high because of the high affordability among people.

Page 14: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersBuildingsPower house (L x W x H) - 18m x 6m x 6m

Page 15: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersBuildingsFuel wood store - 12m x 6m x 4m

Page 16: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersBuildingsWell (Diameter x depth) - 5m x 6m

Page 17: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersDistribution linesConcrete Poles - 450 nos.Three phase length - 600 mTwo phase length - 400 mSingle phase length - 8100 mService cables (Insulated) - 4000 mArea targeted electrified - 2 km radiusDistribution losses @ 15% net - 4.5 kWPer h/h power allocation - 250 W

Cables 1,352,622.00

Poles 1,021,500.00

Labor 112,935.00

Other 51,926.00

Total 2,538,983.00

Page 18: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersPower plant capacity - 35 kWNet out put - 30 kWPrime Generator - 10 kVA

Machinery

System Installation

Electrical equipment and installation

Accessory Diesel Gen set

Page 19: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Summary - Project Expenses (SLRs)

A. Feasibility study 778,077.43

B. Building construction 1,480,939.40

C. Distribution lines 2,538,983.00

D. Machinery installation 3,416,400.00

E. Administrative expenses 1,222,078.30

Total 9,436,478.13

E. Community Contribution 393,950.00

Page 20: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Contributors SLRs

1. UNDP - GEF/SGP 4,226,284.81

2. Ministry of Science and Technology (Machinery) 2,660,000.00

3. RERED 1,800,000.00

Project Preparation 600,000.00

Co-financing 1,200,000.00

4. Uva PC (Cables) 500,000.00

5. EF 250,193.32

Total 9,436,478.13

Page 21: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Dendro Power plant

Page 22: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Project ParametersNo of householdsPlanned - 100 Currently connected - 58Total h/h requirements - 25 kWOperation hours per day - 6 hours (4.45 a.m. to 6.45 a.m. & 6.30 p.m. to10.30 p.m.) Fuel wood species - Gliricidia SepiumFuel wood requirement - 60kg/ hrFuel wood supplying area (Existing Plantations) - 2 km radius

Page 23: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Running Cost1. Month - 15th April to 14th May 2005 (58 families)Operating hours - 4 hours (6.30 pm to 10.30 pm)Fuel wood - Rs. 11,250Diesel (3Lts / hr) - Rs. 2,000Wages - Operator & Helper - Rs. 11,000Maintenance fund - Rs. 5,000Society - Rs. 1,000Total - Rs. 30,250Monthly Electricity bill per household - Rs. 356 (84 houses)Average income per household for supplying fuel wood - Rs. 70

2. Estimated cost for the month 15th May 2005 to 14th June 2005 Operating hours - 6 hoursFuel wood - Rs. 16,875Diesel (3Lts / hr) - Rs. 4,000Wages - Operator & Helper - Rs. 15,625Maintenance fund - Rs. 5,000Society - Rs. 1,000Total - Rs. 42,500

Page 24: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Fuel wood

Monthly Electricity bill per household - Rs. 500Price of fuel wood at Farm gate - Rs. 200/ m3; Rs. 1/ kgPrice of fuel wood at Power house gate - Rs. 375/m3; Rs 1.88/kgMonthly payment for fuel wood transportation - Rs. 7,875Average income per household for supplying fuel wood - Rs. 106

Page 25: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

•Rumor - politicians promises for grid electricity supply• Plant is not for the community but for the EF -being a fully funded project•The consumers concerns on high electricity bill•Resentment among some of the consumers regarding the operator and helper•The enthusiasm among the others in the dendro sector regarding the project

Issues•The confrontation between the fuel wood supplier and the farmers.

•President of the society did not get the electricity from the system

Page 26: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Affordability of the households to pay for electricityTotal monthly cost incurred by a rich family on three energy items (Kerosene, dry battery and car battery) is approximately Rs.563/- An average family, the monthly cost is around Rs.521/-. The poor families spend approximately Rs.293/- per month.

At least the rich and the average families who constitute the majority of the families in the three hamlets are able to afford to pay for their electricity consumption if the cost to be incurred by them is in the range of Rs.400-500 per month.

If other social benefits that a household would accrue from using electricity such as better lighting, reduced risks of accidents, use of other electric appliances, social status etc. are also added to this economic cost, household expenditure on electricity is very much compensated and justified.

Page 27: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Possible options

•Allow the community to explore the possibility of grid extension•Allow the community to explore the possibility of getting subsidy from any agency •Forget injustice and have a compromise with the supplier•Explore the possibility of introducing an income generating activity using day time power to lift the burden on the consumer

Please give us 3 more months to rectify the situation.

Page 28: Off-grid Dendro Power. Sri Lanka About 1 - 1.5 million households in Sri Lanka will be left without grid- connected electricity

Possible future options for off-grid dendro power

(We have a market of 20,000 villages)

• Try to establish a household level electrical appliance package to reduce the capacity• Try to integrate an income generating activity at the initial stage itself• Follow the grid connected dendro and approach the off-grid villages which provide fuel wood to grid dendro plant