1 The Narragansett Bay Commission Vincent J. Mesolella One Service Road Chairman Providence, RI 02905 Raymond J. Marshall, P.E. (401) 461-8848 Executive Director (401) 461-6540 FAX OFFICIAL MINUTES OF: Meeting of: Long Range Planning Committee Meeting Date: April 25, 2017 Time: 8:30 a.m. MEMBERS PRESENT: MEMBERS ABSENT: Dr. Richard Burroughs James S. Bennett Seth Handy, Esquire Mario Carlino, Committee Chairman Vincent Mesolella, NBC Chairman Ronald Leone Alan Nathan STAFF AND GUESTS PRESENT: Raymond J. Marshall, NBC Executive Director Laurie Horridge, Esq., NBC Thomas Uva, NBC Mark Thomas, NBC Karen Musumeci, NBC Karen Giebink, NBC Paul Nordstrom, NBC Jamie Samons, NBC Richard Bernier, NBC Deborah Samson, NBC Tom Brueckner, NBC Brandon Blanchard, Pare Corp. Kathryn Kelly, NBC George Palmisciano, Pare Corp. Matt Travers, Stantec Melissa Carter, Stantec Chris Feeney, Stantec Joanne Maceroni, NBC Meg Goulet, NBC Jennifer Harrington, NBC 1. Call to Order In the absence of the Long Range Planning Committee Chairman Mario Carlino, NBC Chairman Mesolella called the April 25, 2017 Long Range Planning Committee Meeting to order at 850 a.m.

Upload: tranlien

Post on 16-Mar-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

1

The Narragansett Bay Commission Vincent J. Mesolella One Service Road Chairman Providence, RI 02905 Raymond J. Marshall, P.E. (401) 461-8848 Executive Director (401) 461-6540 FAX

OFFICIAL MINUTES OF:

Meeting of: Long Range Planning Committee Meeting Date: April 25, 2017 Time: 8:30 a.m.

MEMBERS PRESENT: MEMBERS ABSENT: Dr. Richard Burroughs James S. Bennett Seth Handy, Esquire Mario Carlino, Committee Chairman Vincent Mesolella, NBC Chairman Ronald Leone Alan Nathan STAFF AND GUESTS PRESENT: Raymond J. Marshall, NBC Executive Director Laurie Horridge, Esq., NBC Thomas Uva, NBC Mark Thomas, NBC Karen Musumeci, NBC Karen Giebink, NBC Paul Nordstrom, NBC Jamie Samons, NBC Richard Bernier, NBC Deborah Samson, NBC Tom Brueckner, NBC Brandon Blanchard, Pare Corp. Kathryn Kelly, NBC George Palmisciano, Pare Corp. Matt Travers, Stantec Melissa Carter, Stantec Chris Feeney, Stantec Joanne Maceroni, NBC Meg Goulet, NBC Jennifer Harrington, NBC 1. Call to Order In the absence of the Long Range Planning Committee Chairman Mario Carlino, NBC Chairman Mesolella called the April 25, 2017 Long Range Planning Committee Meeting to order at 850 a.m.

A p r i l 2 5 , 2 0 1 7

N B C B O A R D M E E T I N G

Program Update

Phase III CSO Control Facilities Program

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

Agenda

2

1 Looking Back

3 Looking Ahead

4 Discussion

2 The “Optimized Plan”

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

Agenda

3

1 Looking Back

3 Looking Ahead

4 Discussion

2 The “Optimized Plan”

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G B A C K

Timeline

4

4.28.2015 NBC Board selects final alternative for Re-Evaluation Plan.

6.29.2015 Phase III Re-

Evaluation Plan (Draft) submitted to

RIDEM for regulatory review.

4.18.2016 Stantec/Pare receives NTP for Amendment 4.

4.28.2016 NBC responds to “specific comments”.

3.17.2016 RIDEM provides

comments on the Draft plan.

5.16.2016 NBC responses to “general comments”.

3.16.2017 NBC meets with RIDEM to discuss optimized plan, EA, and schedule for approval.

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G B A C K

Stantec/Pare Contract

5

Original contract to complete Phase III

Re-Evaluation

Plan

AMMENDMENT 1

AMMENDMENT 2

AMMENDMENT 3

AMMENDMENT 4

AMMENDMENT 5

AMMENDMENT 6

AMMENDMENT 7

No cost change. Updated SRF terms and conditions.

Additional hydraulic modelling work to complete re-evaluation.

Migrate hydraulic model to InfoWorks and obtain LIDAR mapping data.

Program start-up, temporary flow metering, optimization/validation.

Stress test at Bucklin Point and Environmental Assessment for Phase III.

Geophysical Investigation.

Conceptual Engineering Report Phase III (initial design phase).

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G B A C K

Phase III CSO Re-Evaluation

6

STANTEC/PARE SCOPE Pawtucket Tunnel Geological Study and

Geotechnical Investigation Plan

Upgrade/Expand Hydraulic Model

Implement Temporary Flow Metering Program

Validate/Optimize Selected Alternative

Identify GSI Alternatives and Complete 10% Design for Pilot Project

Package Projects and Estimate Costs

Analyze and Recommend Project Delivery Approaches

Sequence Packages and Develop Schedules

Rate Impact and Affordability Analysis

Develop Environmental Assessment for Phase III optimized plan

Program Start-up Activities and Development of Program Management Plan

SCHEDULE Re-Evaluation Phase – January 2, 2014 to

January 29, 2015

Program Start-up and Alternative Validation/Optimization April 18, 2016 to Present

BUDGET Total Contract Value - $7,165,335.76

(NTP through Amendment 5)

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

Agenda

7

1 Looking Back

3 Looking Ahead –

4 Discussion

2 The “Optimized Plan”

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Results - Total Program

8

Phase Re-Evaluation Plan Optimized Plan

Phase A $588.26M $476.51M

Phase B $54.79M $31.17M

Phase C $104.00M $164.45M

Phase D $68.56M $83.43M

Total $815.56M $755.56M

Optimization yielded

$60M reduction in program cost

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Results Phase IIIA Cash Flow

9

MIL

LIO

NS

$700

$600

$500

$400

$300

$200

$100

Phase IIIA – Cash Flow Analysis

Recommended Plan – Total Optimized Plan - Total

YEAR

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Results Phase IIIA Cash Flow

10

MIL

LIO

NS

YEAR

$700

$600

$500

$400

$300

$200

$100

$0 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

Phase IIIA – Cash Flow Analysis

Recommended Plan – Total Optimized Plan - Total

Design Phase (Recommended Plan)

Construction Phase (Recommended Plan)

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Results Phase IIIA Cash Flow

11

MIL

LIO

NS

$700

$600

$500

$400

$300

$200

$100

$0

Phase IIIA – Cash Flow Analysis

Recommended Plan – Total Optimized Plan - Total

Construction Phase

(Optimized Plan)

Pre

-Des

ign

Opt

imiz

atio

n (O

ptim

ized

Pla

n) Design Phase

(Optimized Plan)

YEAR

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Process

12

Stakeholder process identified opportunities to analyze/optimize the

selected alternative.

Hydraulic model expansion/enhancement to optimize conceptual

design project.

Analyzed Alternative Project

Delivery Approaches, Risk/Value

Management

Refined and optimized Phase III system conceptual

design.

Improved system operational

performance.

Reduced life-cycle cost of

system components.

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

T H E O P T I M I Z E D P L A N

Highlights

13

Key Cost Savings Changes

Elimination of northern CSO interceptors

Elimination of one drop shaft Reduction in tunnel length due to

east side alignment

Less Disruptive Plan

Avoiding impacts to schools, residential areas, and commercial businesses

Avoiding area with high levels of contamination

Still Conservative Estimate of Cost

Early in the planning process Opportunities for further cost

reduction through design process

Recommended Plan

(2015)

PHASE B High and Cross Street Interceptor

103, 104, and 105

PHASE B Middle Street Interceptor

201, 202, and 203

Recommended Plan

(2015)

PHASE B Upper BVI Relief Structure

PHASE B 15” Relief Sewer: 106

Optimized Plan (2017)

DROP 210

DROP 213

DROP 217

Recommended Plan

(2015)

DROP 213

Optimized Plan (2017)

PHASE A Pawtucket Tunnel on

West Alignment

Recommended Plan

(2015)

PHASE A Pawtucket Tunnel on

East Alignment

Optimized Plan (2017)

Optimized Plan (2017)

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

Agenda

22

1 Looking Back

3 Looking Ahead

4 Discussion

2 The “Optimized Plan”

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G A H E A D

Phase III Program Schedule

23

21 22 23 24 25

17 18 19 20 21

Phase IIIA Planning/Design/Pre-Construction: 6/2017 to 12/2021

Construction: 3/2021 to 10/2025 (Note: GSI Pilot Project 3/2018 to 12/2018 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

17 18 19 20 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

29 30 21 22 23 24 25

17 18 19 20 21 26 27 28

Phase IIIB Planning/Design/Pre-Construction: 1/2026 to 12/2028

Construction: 1/2029 to 6/2030

22 23 24 25 29 30 31 32 33 34 35 36 37 38 39 40 41

17 18 19 20 26 27 28 31 32 33 34 35 36 37 38 39 40 41

34 35 36 37

31 32 33 34

29 30

26 27 28

21 22 23 24 25

17 18 19 20 21

Phase IIIC Planning/Design/Pre-Construction: 1/2031 to 3/2034

Construction: 3/2034 to 12/2037

22 23 24 25 29 30 35 36 37 38 39 40 41

17 18 19 20 26 27 28 31 32 33 38 39 40 41

39 40 41

36 37 38 39

34 35 36 37

31 32 33 34

29 30

26 27 28

21 22 23 24 25

17 18 19 20 21

Phase IIID Planning/Design/Pre-Construction: 1/2036 to 9/2039

Construction: 9/2039 to 12/2041

22 23 24 25 29 30 35 40 41

17 18 19 20 26 27 28 31 32 33 38

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G A H E A D

Phase IIIA Program Schedule

24

PM/CM Program Implementation

Geotech/Prel. Design/CER

30% Design

Pawtucket Tunnel and Pump Station Cavern

Tunnel Pump Station Fit-Out

OF-205 Facilities

OF-210, OF-213, and OF-214 Facilities

Mid-BVI Relief Structure Facilities

OF-217 Facilities

OF-218 and Lower BVI Facilities

Regulator Modifications

GSI Pilot Projects

GSI Projects

2017 2018 2019 2020 2021 2022 2023 2024 2025

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

NPC Phase III-A Program Schedule

PM/CM Design Construction Bid Procurement

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G A H E A D

Next 14 Months

25

Conceptual Engineering Report (10% design) for Pawtucket Tunnel/Pump Station

IMPLEMENTATION OF PROGRAM MANAGEMENT PLAN Launch Preliminary Design for Phase IIIA Component Projects

Begin Geotechnical and Environmental Investigations

Develop Design Guidelines

Preliminary Design Tunnel/Drop Shafts/Pumping

Station/Site Civil

Design/Bid/Award GSI Pilot Project

Integration of SCADA and

Operational Controls

Develop a Regulatory Permitting Strategy

Update Program Costs and Schedule

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

L O O K I N G A H E A D

Regulatory Review/Approval

26

May 26, 2017 Submit revised “optimized” plan to RIDEM for review.

June 2017 Public Hearing for EA.

May 26, 2017 Submit Draft EA to RIDEM for review.

August/September 2017

RIDEM approve Phase III Re-evaluation plan.

September/October 2017 RIDEM issues FONSI for EA.

October 2017 NBC/RIDEM agree to terms on modifications to consent decree language.

STANTEC/PARE ● PHASE I I I CSO RE-EVALUATIO N

Agenda

27

1 Looking Back

3 Looking Ahead –

4 Discussion

2 The “Optimized Plan”

2

2. Approval of Minutes – May 24, 2016 – Long Range Planning Committee

NBC Chairman Mesolella asked for a motion to approve the May 24, 2016 Long Range Planning Committee meeting minutes as written. Commissioner Burroughs moved to approve the minutes of the May 24, 2016 Long Range Planning Committee as written. Commissioner Handy seconded the motion. The vote taken by the Long Range Planning Committee was unanimous. The motion carried. 3. Items for Action

A. CSO PHASE III UPDATE

Mr. Marshall advised the Committee that over the last year MWH (who has been acquired by Stantec) and Pare Engineering one of our local firms, have been working on optimizing our Phase III program to try to get the most “bang for the buck” and address as well as they can the affordability issues for the ratepayers. The Committee today will be hearing what they have achieved, where we have been, where we are now and where we are going. Also, at today’s CEO Committee meeting there is an action item for the additional funding for the next level of work for CSO Phase III and at today’s full Board meeting this presentation will be given again so the entire Board of Commissioners get to hear where we are and also act on the matter that will be before CEO for additional design funds. Mr. Marshall introduced Sean Searles of Stantec and advised that he would be making the CSO Phase III Update presentation before the Committee today. Attached is the Stantec’s presentation. After the presentation there was a lengthy discussion between the Committee members, NBC staff and Stantec staff regarding the optimization of the CSO Phase III project, the reduction in cost that could be achieved with the optimization of the project and the improvement in water quality vs. ratepayer affordability issues. 4. Other Business None. 5. Adjournment A motion to adjourn was made by Commissioner Nathan, seconded by Commissioner Burroughs and the Long Range Planning Committee meeting adjourned at 9:40 a.m. Respectfully submitted,

Raymond J. Marshall, P.E. Executive Director/Secretary