![Page 1: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/1.jpg)
Ian Chester / Jan Talaśka2011-09-05
Offshore Wind Risks - Issues and Mitigations
Baltexpo 2011 - Offshore Wind presented by DNV
![Page 2: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/2.jpg)
DNV – An Independent Foundation
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
2
9,000employees, of which 76% have a university degree
300offices
100countries
![Page 3: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/3.jpg)
Services to the Wind Industry
Accredited Services
� Project Certification
� Type Certification
� Testing Services- Power Performance Testing- Loads Testing
Advisory Services
� Wind Resource Assessment
� Project Development Support
� Due Diligence
� Marine Advisory Services
� Asset Risk Management 30%
40%360
10 2030
4050310
320330
340 350
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
3
� Wind Turbine Technology
� Health, Safety and Environmental Risk Management
� Training and Educational Programs
0%
10%
20%
50
60
70
80
90
100
110
120
130140
150160170
180190200
210220
230
240
250
260
270
280
290
300
310
% of Time % of Energy
![Page 4: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/4.jpg)
Construction
Wind energyuncertainty
Turbine technology
Major Risks in Offshore Wind Farms
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
4
Marineconditions
Turbine foundations
Offshoreaccess
Subseacables
Regulatory regimeGrid
connection
![Page 5: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/5.jpg)
Offshore Wind - Combining DNV competences
=+
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
5
40+ years of offshore oil & gas experience
Global leader in project risk and certification of offshore
wind projects
25 years of hands-on experience with wind
turbines
40+ years of offshore oil & gas experience
![Page 6: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/6.jpg)
Wind Energy Uncertainty
� Issue- Reliability of kWh generated estimates- Real on-site data are scarce- Wind resource estimates have large
uncertainty- Loss factors are not well understood (e.g.
wakes and turbulence)- Potential large variation in wind resource
across a R3 site
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
6
� Mitigation- Offshore measurement (fixed tower, novel
solutions) over sufficient period of time(> 2 years)
- Layout optimisation and understanding the trade-offs
- Transparency of energy estimates
![Page 7: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/7.jpg)
Site Conditions – Marine Environment
� Issue- The weather and sea conditions- Varying water depths and sea bed conditions
across a site- Weather window for offshore work is small
� Mitigation- Solid, site-specific information
- Measurement campaigns
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
7
- Measurement campaigns- Data mining- Geotechnical investigation - Safety factors in design
- Relevant learning from oil and gas - Development / use of equipment / methods
suitable in adverse conditions
![Page 8: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/8.jpg)
Wind Turbine Technology
� Issue- Large MW turbines required 10 MW?- Component failures difficult to rectify
offshore
� Mitigation- Turbine selection- Strong warranty agreements- Condition monitoring
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
8
- Condition monitoring- Data monitoring, analysis and response- Proactive maintenance- Further research into design loadings- Turbine type certification- Engineered for reliability
![Page 9: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/9.jpg)
Wind Turbine Foundations
� Issue- Costly foundation designs due to:
- Harsher marine conditions- Deeper water- Larger turbines
- Shallow-water solutions may not work
� Mitigation- Standardisation
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
9
- Standardisation - Quality control during manufacture- Research programs (e.g. Carbon Trust OWA)- Information sharing between WTG
manufacturer and foundation designers for benefit
![Page 10: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/10.jpg)
Subsea Cables and Power Transmission
� Issue- Many problems during cable installation, e.g.
improper cable handling- Human introduced hazards (e.g. anchoring)- Natural hazards (seabed mobility)- Unplanned downtime not considered in
energy estimates
� Mitigation
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
10
Deep w
ater channel
� Mitigation- Cabling
- Understand site-specific conditions- Chose appropriate cabling design (e.g. armour, burial
depth, scour protection)- Work with experienced partners- Plan with contingencies
- Substation- Realistic expectations for annual maintenance time- Include unplanned outages- Diligent inspections and maintenance
![Page 11: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/11.jpg)
Grid Connection
� Issue- Load centres are far away from offshore wind
farms- Congestion in certain areas of the grid- Long distance / high power will require (less
proven) offshore HVDC solutions- Uncertainty about ownership / operation of
assets
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
11
� Mitigation- Early dialogue between developer and grid
operator- Careful evaluation of various options
![Page 12: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/12.jpg)
Construction
� Issue- Major project - Contract strategy selection- Managing the interfaces- Supply chain and facilities- Unexpected technical issues
� Mitigation- Previous project experience
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
12
- Previous project experience- Project lifecycle engineering supervision- Installation concept studies - Develop your own team- Plan A, B and C- Project Certification
![Page 13: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/13.jpg)
Construction Vessels
� Issue- Vessels are scarce and expensive
(e.g. +100 k£/day + mob/demob)- Capabilities (crane, deck space, propulsion)
limited- Vessel reliability
� Mitigation- Developers building own vessels
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
13
- Developers building own vessels- Long-term contracts (but uncertainties about
project schedules)
![Page 14: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/14.jpg)
Offshore Access
� Issue- Current access solution (boat fendering)
limited by sea state (e.g. < 1.5 m significant wave height)
- Access to turbines more frequent than expected
- Health and safety issues – reputational risk
� Mitigation
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
14
� Mitigation- Improvement of current solutions (e.g. to 3 m
significant wave height)- New access solutions (e.g. heave-
compensated gangway)- Additional access by helicopter-hoisting- Research programs (e.g. UK Carbon Trust
OWA)
![Page 15: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/15.jpg)
Operations & Maintenance
� Issue- Determining the optimum O&M approach- Lack of deep offshore wind O&M experience
in the market- Limited experienced personnel- Personnel health and safety issues
� Mitigation- Minimise need to access the turbines
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
15
- Minimise need to access the turbines- Turbines designed for easy O&M- O&M considered at the windfarm design
concept stage- Specialist vessels required
![Page 16: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/16.jpg)
Regulatory Regime
� Issue- Investors looking for long-term certainty- UK ROC scheme reasonably successful, but
also discussion about feed-in tariffs- Carbon tax
� Mitigation- Firm statement and action from Government- Long -term agreements
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
16
- Long -term agreements- Know the market
![Page 17: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/17.jpg)
An Opportunity
� The wind industry is moving further offshore
� Need to quantify offshore risk and become comfortab le with it
� Lever oil & gas experience
� Prime movers will have an advantage
� Reliable project outturns – cost, schedule and quali ty
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
17
![Page 18: Offshore Wind Risks - Issues and Mitigations...2011/09/07 · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave](https://reader033.vdocument.in/reader033/viewer/2022060810/608f18e84f3bdb1e4f2d2406/html5/thumbnails/18.jpg)
Safeguarding life, property and the environment
www.dnv.com
© Det Norske Veritas AS. All rights reserved.
Offshore Wind Risks - Issues and Mitigations
2011-09-05
18