  • 14th October 2020

    Will LamondMott MacDonald

    Offshore Wind TurbinesAn Overview and Future Trends

  • Mott MacDonald Limited

    Senior Wind Energy Consultant for Mott MacDonald based in Glasgow, Scotland. Nine years experience as a Project Manager for a variety of offshore wind assignments for lenders, owners and acquirers in the UK, Europe, USA, and the East Asia region.

    Key LTA projects as Project Manager include the first financed US offshore wind farm (Block Island - 2015) and the first financed French offshore wind farm (St Nazaire - 2019).Will Lamond

    Senior Wind Energy Consultant

  • We are a global engineering,

    management and development

    consultancy focused on guiding

    our clients through many

    of the planet’s most

    intricate challenges.

    Introducing Mott MacDonald

    Opening opportunities with

    connected thinking

    • EUR1.6 billion turnover

    • Multidisciplinary

    • Multisector

    • Over 17,000 staff

    • Global presence

    • Employee owned

    Who we are

  • Cape Town

    Tokyo

    Bangkok

    Brighton

    New Delhi

    Melbourne

    Taipei

    Glasgow

    Paris

    Bogota

    Madrid

    Mott MacDonald’s wind offices

    Houston

    Boston

    Singapore

    Genova

    Brisbane

    Denver

  • Offshore wind global businessKey highlights

    1/2of global installed offshore

    wind capacity advised

    90GW of wind globally

    250staff working in offshore

    wind

    2004Establishment of wind

    services

  • Offshore wind business in AsiaKey highlights

    2010Year of setting up in Japan

    20Involved in over 20 offshore

    wind projects in East Asia

    1993Year of setting up in Taiwan

    35staff working on offshore

    wind based in Asia

  • • 1st Project Financed Deal in the world – Princess Amalia – Q7 project

    • 1st Project Financed deal in Taiwan – Swancor Formosa 1 – Phase 1

    • 1st Project Financed Deal in Belgium – Thornton Bank

    • 1st Project Financed deal in the USA – Block Island wind farm

    • 1st Project Financed Deal in France – Saint-Nazaire wind farm

    • Owner’s Engineer for 143 MW project – Akita Offshore Wind, Japan

    • TA / OE for 187 MW project – Kashima Offshore Wind , Japan

    • OE for a demonstrator project in the US – Fishermen’s Energy NJ, USA

    7

    90GWEngineering and

    technical advisory

    services for over

    90GW of wind

    energy projects

    worldwide

    Mott MacDonald Offshore Wind

    History highlights

  • Environmental & Social Impact Studies

    Key services

    Energy Yield Analysis Metocean Studies

    Tendering & Procurement Advice

    Agreements & Contract Review

    Package, Project & Program Management

    Detailed Design

    Feasibility & Technical

    StudiesTechnology Assessment

    Electrical Engineering

    WTG & OSP Foundations Optioneering

    Seismic Studies and FEED Design

    Geophysical and Geotechnical Studies

    Subsea Cable Routing Design

    Construction & Operation Monitoring

  • 1Offshore Wind

    Turbine

    Technologies

    2Installation

    Considerations

    3Asset Life

    Extension

    In this presentation

    Offshore Wind Turbines – An Overview and Future Trends

  • 10Mott MacDonald | Presentation

    Wind Turbine Technologies – Hybrid Arrangement

    Hybrid concept where gearbox is used to increase

    rotation to a moderate speed (circa 600 rpm) which can

    then drive a smaller Permanent Magnet Generator

    (PMG) than in the direct drive concept

    Advantages

    • Lower ratio gearbox than DFIG/SCIG

    potentially increasing reliability

    • Greater part-load efficiency than

    DFIG/SCIG due to permanent magnets

    • More compact than a full direct PMSG

    Disadvantages

    • More mechanically complex than direct

    drive due to gearbox

    • High cost of generator compared to

    DFIG/SCIG

    Source: MHI Vestas

  • 11Mott MacDonald | Presentation

    Wind Turbine Technologies – Direct Drive

    Advantages

    • No gearbox which reduces the number of

    mechanical moving parts historically

    prone to failure

    • Better grid support/fault ride-through due

    to use of full scale converters (power

    electronics)

    Disadvantages

    • Cost, volatility and supply chain

    constraints of Permanent Magnet (PM)

    material supply

    • PM may demagnetise due to extreme

    temperatures or short-circuit loadingSource: Siemens Gamesa

  • 12Mott MacDonald | Presentation

    Wind Turbine Technologies – Key Global Players

    MHI Vestas

    • V164-10.0MW

    • V174-9.5MW

    • Rumours of new, higher rated platform with

    larger rotor diameter. No official statements.

    SGRE –

    • SG 8.0-167

    • SG 11-200

    • SG 14-220

    GE Renewable Energy –

    • Haliade X 12.0-220

    • Not officially confirmed but 13MW variant

    expected

  • 13Mott MacDonald | Presentation

    Wind Turbine Technologies – Capacity Evolution

    V164/V174 – originally as

    6.0MW, now offered at

    9.5MW/10MW

    SWT-154 – originally 6.0MW,

    now as 8.0MW with 167m

    rotor

    Reasonable to assume

    latest WTG platforms (i.e.

    SGRE 14-220) will evolve to

    higher rated capacity

    Source: IRENA Future of Wind 2019

  • 14Mott MacDonald | Presentation

    Installation Considerations – current vessel capability

    Current vessel statistics

    • 900 to 1,400 ton lifting capacity

    • 5,000 to 8,500 ton load capacity

    • Suitable for current commercial

    9.0/10.0MW WTGs

    Standard installation methodology:

    • Tower erected onshore, installed offshore

    in one lift

    • Nacelle in one lift, blades in separate lifts

    Source: Van Oord

  • 15Mott MacDonald | Presentation

    Installation Considerations – future vessels

    Source: Jan de Nul

    Expected future vessel requirements

    • 2,500 to 3,000 ton lifting capacity

    • Up to 16,000 ton load capacity

    • Designed for 15MW+ WTGs

    Publicly announced vessels

    • Jan de Nul “Valiant” – 3,000 ton lifting

    capacity. Expected in 2022.

    • CSBC and DEME “Green Jade” for Taiwan

    – 4,000 ton lifting capacity. Expected in

    2022.

    • NYK and Van Ord announce Japanese

    JUV. Expected in 2022/3

    • Shimizu announced Japanese JUV.

    Expected 2022.

  • 16Mott MacDonald | Presentation

    Asset Life Extension

    Certified WTG design life currently 25 years

    Recent EU transactions see push for 30-35 years

    operational life

    Key considerations:

    • Fatigue life of WTG structural elements:

    • Tower

    • Nacelle bedframe

    • Yaw interface

    • Rotor hub

    • Long term monitoring campaign coupled with

    structural load modelling

    • Increased O&M cost profile

    • Replaceable components

    • Increased inspections and monitoring

    • Run to fail in later years – impact on revenue

  • Thank you

  • We are excited about the potential for

    offshore wind in Taiwan and look forward

    to talking with you.