Offtake Arrangements Document – An Overview
Paul Roberts
12th May 2005
![Page 2: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/2.jpg)
2
Scope of Offtake Arrangements Document
Sets Out Technical and Operational Details Relating to Gas Flows from NTS to LDZs from one LDZ to another LDZ
NTS
Distribution Network (DN)
NTS/LDZ Offtake
![Page 3: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/3.jpg)
3
Section A. Scope and Classification
Parties
(1) Transco NTS as NTS owner and operator
(2) Each DNO as DN owner and operator (including Transco)
System and Offtake Definitions
• Classification of Systems and Points on Systems
Recording of Specific Details in Supplemental Agreements
![Page 4: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/4.jpg)
4
Section B. Connection Facilities
Covers Land, Equipment and Buildings at each Offtake Site
• Measurement Equipment (detailed in Section D)
• Telemetry (detailed in Section E)
Rights Granted to Site Users
• Retention, installation, modification and replacement of its equipment
• Access rights
Compatibility of Both Parties Equipment
Decommissioning of an Offtake
Supplemental Agreement
• Schematic of Connection Facilities - Point of Offtake
• Land diagram
• Details Ownership, Equipment Specification of Connection Facilities
• Site Services for Site Users
![Page 5: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/5.jpg)
5
NTS Feeder
Distribution
NetworkMeters
Flow orpressurecontrol
Odorantinjection
Demarcation Point The Offtake
Section B. Connection Facilities
Typical NTS/LDZ Offtake Configuration
FiltersNTS
Block Valves
CVMeas.
SlamShut
valvesHeaters
Majority of equipment at Offtake Site owned and operated by DN
![Page 6: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/6.jpg)
6
Section C. Safety and Emergency
Gas Supply Emergencies
• Development and compliance with Emergency Procedures – E1, E2, E3
• Participation in procedure testing - planned by NTS
Safe Control of Operation (SCO) Interface Procedure
• Safe conduct of works or operations
Site Emergency Procedures
• Requirements to satisfy legal requirements (eg. COMAH, Pipeline Safety Regs)
Site Safety Rules
• Safe access and operation of personnel on a Offtake Site
Existing Gas Supply Emergency Procedures• E1 - Network Gas Supply Emergency Procedures • E2 - Local Gas Supply Emergency Procedures • E3 - Detailed Internal Procedures to ensure compliance with E1/E2
![Page 7: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/7.jpg)
7
Section D. Measurement
Responsibility• Downstream party responsible for measurement and data provisionMeasurement standards• Measurement data and accuracy - Annex D-1• Best practice recommendations and technical standards – Annex D-2Validation• Routine – every 12 months at downstream party’s cost• Exceptional – at upstream party’s requestFault management• Failure notification and rectification• Measurement correction/estimation• Access to records
Supplemental Agreement• Actual uncertainty limits and flow ranges for measured parameters
![Page 8: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/8.jpg)
8
Section E. Telemetry
Operational Data Flows• required by upstream party for safe and efficient operation of its System• Annexes specify standard telemetry signals, protocols, resilienceTelemetry Failure• process for resolutionDuring SOMSA• DN transmits signals to NTS via satellite Post SOMSA• Rights for NTS to install own telemetry on Offtake Site• DN obligation to provide signals to NTS telemetry equipment
Supplemental Agreement• Variations to “default” telemetry signals,
resilience and protocols
![Page 9: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/9.jpg)
9
Section F. Calorific Value
Responsibility
• DNO obligation under Gas (Calculation of Thermal Energy) Regulations to determine daily CV for each LDZ based on daily average CVs for LDZ input and offtake points
Daily CV determination• Basis on which Transco NTS will determine daily CVs for DNOs up to 31 March
2007
CV Shrinkage Costs• Cooperation to avoid or minimise CV Shrinkage
![Page 10: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/10.jpg)
10
Section G. Maintenance
Defines Relevant Maintenance to be planned and co-ordinated• Safety Relevant Maintenance
• can only be carried out safely if affected parties aware• Flow Relevant Maintenance
• NTS maintenance likely to impact upon ability to make gas available for offtake
• Measurement Equipment Maintenance• Urgent Maintenance Maintenance Planning• 2 year planning cycle - timescales in Annex G-2• Final programmes in March, updated in September• Revisions at 5 days notice, except for safety reasons subject to payment of
other parties works
![Page 11: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/11.jpg)
11
Section H. NTS Long Term Planning
• Exchange of demand information • facilitate production of system development statements by the
transporters in accordance with licence obligations
• Information to be exchanged• Historic and forecast demand for DM/NDM firm/interruptible loads• Detailed in Annex H-1
• Timescales for information provision
![Page 12: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/12.jpg)
12
Section I. NTS Operational Flows
Provision of Offtake Profile Notices (OPNs)
• Receipt of initial OPN and subsequent revisions requested by DN/NTS
• Offtake tolerances
Within day pressure
• Pressures which Transco NTS will make available between Applicable Offtake Pressures at 06:00 and 22:00 on reasonable endeavours basis
Interruption
• Process by which Transco NTS may require interruption of LDZ Interruptible Supply Points
• Exchange of information regarding LDZ Interruptible Supply Points
• DNO reimbursement to Transco NTS for relevant interruption payments it makes to Users
Demand forecasts
• Provision by DNO to Transco NTS of updated demand forecasts
![Page 13: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/13.jpg)
13
Section J. LDZ/LDZ Offtake – Planning and Operational Flows
Provision of Offtake Profile Notices (OPNs)
• Receipt of initial OPN and subsequent revisions requested by downstream DNO
System Planning
• Information provision and timescales
• Setting of Offtake Parameter Values • Maximum Daily Quantity• Maximum Offtake Rate• Minimum Offtake Pressure
• Preparation of Offtake Parameter Statement by upstream DNO• Offtake Parameter Values for LDZ/LDZ Offtakes for Gas Years 1-5• Indicative Offtake Parameter Values for Gas Years 6-10
• Establishment of rights to use Close offtakes
![Page 14: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/14.jpg)
14
Section K. LDZ System Entry Points
Applicability
• Existing LDZ System Entry Points
Capacity Allocation by Transco NTS
• Auction Obligated Incremental NTS Entry Capacity as per licence obligation
• Auction Incremental NTS Entry Capacity as per DNO instruction
Surrender and Curtailment
• DNO to accommodate nominated flows in accordance with capacity held by shippers
• If DNO unable to accommodate
• may instruct NTS to give interruptible curtailment notice or buy back
• Section I liabilities incurred by NTS reimbursed by DNO
![Page 15: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/15.jpg)
15
Section L. Cost Recovery and Invoicing
Covers arrangements for adhoc recoverable costs
• Invoicing and payment processes
![Page 16: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/16.jpg)
16
Section M. Information Flows
Offtake Communications Document
• Cover Transporter to Transporter information exchange
• for purposes of OAD and/or UNC
• Specifies • information to be exchanged (data,
reports, notices, ..)• requirement for information• Party responsible for information
provision• format of information• time/frequency of provision• means of provision
DNs
Transco NTS
Agency Systems
ShippersAgency Services
Agreement
Offtake
Communications Document
![Page 17: Offtake Arrangements Document – An Overview Paul Roberts 12 th May 2005](https://reader036.vdocument.in/reader036/viewer/2022082517/56649f145503460f94c28abb/html5/thumbnails/17.jpg)
17
Section N. General
• Admission, Withdrawal and Termination of Parties
• Supplemental Agreements Execution and Amendment
• upstream party responsible for drafting
• Information and Confidentiality
• Supplemental Agreements confidential
• Liabilities
• Each Party bears its own loss, except where otherwise stated
• Dispute Resolution
• Other Legal Boiler Plating