o&m training for sugar mills professionals session ... · pdf filehhv/gcv usa 9178 2192 88...
TRANSCRIPT
Services to sugar millsO&M training for sugar mills professionals
Session : Boilers
Trainer: Frans Baltussen
Date: July 2017
O&M of bagasse based High Pressure Boiler
O&MO&M of bagasse based High Pressure Boilerof bagasse based High Pressure BoilerThe course will help to understand:
1. The fuel consumption/efficiency of boiler and power output of power plant
1.1 Boiler efficiency
1.2 The power output
2. Reliability
2.1 Boiler
2.2 Fuel /firing System
2.3 The fly ash arrestor and ash removing systems
2.4 The fans and dampers
2.5 The controls
2.6 The sootblowing system
2.7 The feed water system
2.8 The water and steam side conditioning/ chemistry
2.9 The piping systems and valves
2.10 The refractory and insulation systems
2.11 Preservation during standstill
3. Safeties in system for protection persons and equipment
What are main objectives:
• Ensure a high Reliability of the plant
• Ensure a high Efficiency of the plant in order to minimize the fuel consumption and to maximize the power output
• Ensure the safety of the plant at highest level so that persons can work safely and equipment will be not damaged in case of upsets.
You need to understand the basics of the plant.
Bagasse needs to be fired efficiently
The power and steam needs to be generated during season and off season in the most efficient way.
1.1: Boiler efficiency
Boiler efficiency is : heat absorbed by the water steam system/heat input
Heat absorbed by water steam system is in KW : (mst * hst – mw * hw)
mst = mass of steam at outlet in kg/shst= enthalpy of steam at outlet in KJ/kgmw= mass of water at economizer inlet in kg/shw= enthalpy of water at economizer inlet in kJ/kg
1. The fuel consumption/ efficiency of boiler and power output of power plant
Heat input is: mf * heating value of fuel + m air * (Tair –Treference air).
mf = mass of fuel supplied into boiler
Question is how to measure the fuel amount.
Is possible with fuel cells in conveyor
However a very complicated system which requires maintenance and spares and is costly
Therefore the efficiency is mostly determined in an indirect way
Into silo chutes boiler
Conveyor with fuel cells
Conveyor with fuel cells
Surplus bagasse to storage yard
heating value of fuel is in KJ/kg
2 types of heating value are considered:
* on higher heating value (HHV) also called gross heating value (GCV)
* on lower heating value (LHV) also called nett heating value (NCV)
The difference between the 2 is the latent heat
Tube with cold
water
Flue gasses with water vapourand dewpoint of 50 C
Flue gasses with no water vapour at 50 C
Water heated up from 10 to 30 C by condensation of water vapour on tube
Heat for condensing and evaporating the vapour is called latent heat
Basis is bagasse with 52% moisture
Common used in
Heating value based on 52% moisture
efficiency Moisture content in Flue gasses
In KJ/kg In kcal/kg % % weight % volume
HHV/GCV USA 9178 2192 8817.5 26.7
LHV/NCV Europe 7295 1742 70
Comparison between the 2 heating values
Both can be used.
Condensation of flue gasses we will avoid in bagasse fired boilers as we have some Sulphur in it and a lot of ash.
Causing: corrosion and fouling.
Therefore mostly efficiency on basis of lower heating value is used. The latent heat is not seen as a loss.
Heating value bagasse versus moisture content
It is , however, not said that water content is not important.
How less water in bagasse how more we save in fuel consumption
This is related to the bagasse with lower moisture content at inlet boiler
This is related to the bagasse with 52% moisture content from mill
Efficiency calculation in indirect way/ as per indirect method
Boiler
Q fuel
Q stack
Q rad and conv
Q Blow down
Q nett
Q air
Q ash including unburned
M fuel * LHV
M fuel * m (air stoich) * 1,35 * cpm * T air
M steam* ( hst – hw)
.%/100 *Q nett
0,1/100 * mst * h’2/100 * Q fuel
M fuel * (m flue gas * cpm * T flue gas + LHV of CO * m flue gas * CO vol%/100)
Only unknown is M fuel
10
Heat balance boiler
Is very smallAmount.
Efficiency = 100% - losses%Losses can be determined on basis of each kg of fuel supplied. Fuel flow is not needed
What information is required to calculate the losses
Data required unit Measuring device
Oxygen content Vol % wet or dry portable
CO content Vol% wet or dry portable
Stack temperature C portable
Air temperature at outlet steam air preheater
C portable
Water content in bagasse Wt% Lab of sugar mill
Ultimate analysis and heating values bagasse
Wt% and KJ/kg Lab outside
Ash content from boiler and its heating value
Kg and KJ/kg Lab outside
Ash content from cyclones and its heating value
Kg and KJ/kg Lab outside
What is needed to measure the performance of boiler
The ash collection should be done properly. Take several samples over a longer period and mix those very well and then take the sample for the lab.
The stack losses
The measuring of oxygen content and temperature should be taken at the right spot in order to have average value.
The best location for the oxygen measurement is in case of one ID fan at 2 m from outlet of ID fan. In case of 2 ID fans the average of 2 outlets
For the stack temperature we need to measure the flue gas temperature at outlet of last heating surfaces of boiler.
The ID fan will increase the flue gasses with 2 to 5 C and the long ducting and i.e. electrostatic filter will cool down the flue gasses.
Flue gasses do not mix easilyEspecially over the width of boiler
At outlet of cyclone more proper mixedHowever still not over the width.Require a temperature measurement over the complete width to determine the average temperature.
In case of no cyclone we need a grid measurment
Flue tubes of flue gas air preheater heavy corrodedAnd many tubes with leakages
Take care for tube leakages in flue gas air preheater
Cold air
Flue gas outlet
Condensation of vapour in flue gasses on tubes what result in corrosion
To ID fan
Install at boiler outlet a proper oxygen analyzer suitable:• for high humidity in flue gasses• For dusty flue gasses ( puffing system)
Important is regular calibration of analyzer
Also check each shift the flue gas emissions with portable analyzer.• At boiler outlet • And at ID fan outlet
O2 vol% dry
CO2 vol% dry
CO vol% dry
Portable Analyzer
Take always a longer probe of approx 1 m length of InconelDeep into flue gas flowSuitable for also furnace measurement at different spots
Excess air
percentage
Note: By measuring also the CO2 content it is possible to check if the analyzer is working properly
Bagasse in sugar mills
Water content wt% 46 till 52 ( some times 54)
Fibre content wt% 43 -52
Soluble solids wt% 2-6
Average density Kg/m3 150 loose
400 bailed
Proximate Analysis On Dry Basis(% of Dry Basis)
Ash wt% 2,5
Volatile wt% 85,5
Fixed carbon wt% 12
Higher heating value (HHV or GCV)Is including the latent heat
KJ/kg 9178 on basis of 52% water
Lower heating value (LHV or NCV)
KJ/kg 7295 on basis of 52% water
Ultimate Analysis On Dry Basis(% of Dry Basis)
C wt% 47,82
H wt% 5,85
N wt% 0,14
S wt% 0,3
Ash wt% 3,23
O (by diff) wt% 42,66
Cl wt% 0
For accurate data the fuel should be analyzed in the laboratory.
By combustion calculation the following can be calculated for bagasse:• heating values,• Air requirement ,• flue gas flow, • Compositions• Heat content• Adiabatic flame temperature
Bagasse composition
Bagasse in sugar mills
At stoichiometric combustion with air of 72% relative humidity the values are as follows:• Air quantity: 2,11 Nm3/kg / 2,70 kg/kg• Flue gas flow: 3,05 Nm3/kg / 3,68 kg/kg• O2 : 0 vol% • CO2 : 13,63 vol% • SO2 : 0,03 vol%• N2 : 52,74 vol%• Ar : 0,62 vol%• H2O : 32,98 vol%• Adiabatic firing temperature: 1465 C
The bagasse can be fired with an excess air of 1,35.Means 35% more air is supplied then required for stoichiometric combustion.
What are the O2 and CO2 contents?
• Air quantity: 1,35 * 2,11 =2,85 Nm3/kg
• Flue gas flow: 3,05 + 0,35*2,11 = 3,79 Nm3/kg
• O2 : (0,35*2,11*0,2047/3,79 ) * 100% = 3,99 vol%
• CO2 : {(0,35*2,11*0,0003) + (0,1363*3,05)}/3,79 *100%= 10,98 vol%
• H2O : {(0,35*2,11*0,0223) + (0,3298*3,05)}/3,79 *100%= 26,98 vol%
• Adiabatic firing temperature is 1264 C
• The CO content will be approx. 350 mg/Nm3• The efficiency losses due to CO is approx. 0,175 %
For combustion air of 72% relative humidity the composition is as follows:• O2 : 20,47 vol% • CO2 : 0,03 vol% • N2 : 76,37 vol%• Ar : 0,9 vol%• H2O : 2,23 vol%
Air and flue gas flows from bagasse firingBasis 52% water in bagasse
Flue gas composition versus bagasse moistureFlue gas composition versus bagasse moisture
At lower water content in bagassethe cpm value will drop.At 45% water approx 0.6% less
CO content during capacity test and the impact on efficiency:Based on operating data running at 141 tph HP steam
Oxygen content in flue gas: vol% wet
Measured CO content in flue gas: ppm
Eff. LossDue to CO%
Improved eff due to less excess air (ref from 5 vol% oxygen) %
Overall improved eff. Due to less excess air.%
Additional power consumptionfansKW
T stack
3,5 (n=1,3) Estimate 600
0,3 (estimate)
1,4 1,1 -190 156
4(n=1,35)
Approx 350 0,175 0,9 0,725 -141 158
5(n=1,45)
Approx 152 0,075Reference point
164
6 (n=1,59) Approx 50 0,025 -1,4 -1,375 +140 171
Impact excess air and CO on boiler efficiency
Max allowable CO = 800 ppmv
The Higher CO content indicate mostly higher unburned content in fly ash
In existing boilers seen ash samples of fly ash with 22% carbon in ash with LHV value of 1861 KJ/kg. This is seen with CO contents of approx. 300 till 1000 ppmv.
However also seen 59% carbon and LHV value of 4800 kcal/kg. The CO contents are then 6000 to far above 10000 ppmv
When ash is 2.5 % on dry basis then the losses due to unburned ash are:
• 1.6% on basis of 22% carbon• 6.9 % on basis of 59% carbon
The water content in bagasse should be maximum 52%. At higher content the firing get more poor what increases the unburned.
Unburned in ash
Convection and radiation losses
Difficult to measure.
Measure the casing temperature in C and surfaces in m2 and ambient temperature.
Temperatures are for each surface different . Calculate average.
Determine the heat transfer coef. In w/m2 C.Mostly there is some wind . Also due to natural draft. Take 14 W/m2C
Losses in KW= (14/1000 * surface area) * (temperature difference casing and ambient)
Calculate the total convection and radiation heat and total fuel input.
Can be taken also from the ABMA standard radiation loss chart (PTC 4.1) which is based on the average wall temperature measured by the staff
Or from DIN 1942 standard
Graphic as per DIN 1942Also ASME has a graphic
24
Important for measuring the performance
Not important are steam pressure and steam temperature
Important is the steam capacity. At lower capacity the efficiency will slightly increase .
100% MCR: 87 % 70% MCR: 87.9%60% MCR: 86.9%
The feed water temperature is important. How lower how lower the flue gas temperature when eco installed at boiler outlet.In case of flue gas air preheater at boiler outlet then air temperature is important.
Before testing first 4 hr stabilization period on constant load
Then test run at constant load for 4 hrsNo sootblowing during test.Blow down is closed. Cleaning of fuel bed during test is permittedReadings at 15 min intervalsFlows at each 5 minute intervalsAll instruments should be calibrated , certificates to be present
There have been hardly any studies available on bagasse based biomass decomposition.
There is some know how available which makes it possible to make some assumption.
Bagasse is one of the easiest decomposable lingo cellulose species.
Anarobic digestion is the bacterial fermentation of organice material like bagasse in oxygen free condition.
It produces a gas composed of methane (CH4) and carbon dioxide (CO2). Called biogas Optimum temperature for this process is 38 C.
Biomass decomposition
Bagasse decomposition
Approx. 4,6 % reduction in LCV value per month
The heating value can drop fast during storage. See below graph
Be aware that during off season much more fuel will be required.
Other Biomass available in Pakistan
1. Bagasse2. Sugar cane Trash3. Corncobs4. Rice husks5. Cotton Stalks6. Wheat straw7. Wheat rice
All those fuels have common:•High Volatile content•Nett Heating value on basis of ash and water free all approx the same (17,8 till 19 MJ/kg)
NOTE:• The composition can vary per season and per area.• It is necessary to send fuel to lab for analysis• The fuels can be fired on different stoker types and in fluidized bed system.
Fuels are different in:• moisture content•Ash content• Alkali content in ash• Sulfur• Chloride• density
28
The ash characteristics of fuels are important.
Specially important are:• the alkali metals (Ca, Na, K) are important.• silica
Further the sulfur and Chlorine content in the fuel is an important factor
Those contents needs to be verified in the lab before deciding the best combustion and boiler system.
Later in the session concerning boiler fouling we will discuss this in more detail
Chlorine, sulfur and ash characteristics
29
Characteristics of biomass
30
8.4
30
811
52
15 15
5.710
1511
1513
7
13 12
2529
4.4
11.7
2
18
2.5
8
18.516
7.0
0.0
10.0
20.0
30.0
40.0
50.0
60.0
Moisture Content % LHV(MJ/Kg) Ash
Effect on fuel handlingfor solid fuels
31
2,3091,302
2,5991,526
2,9541,615 2,098
20,336
23,780
0
5,000
10,000
15,000
20,000
25,000
LHV(MJ/M³)
Elements in biomass & coal potentially
leading to corrosion and deposits.
32
0.600.2
0.02 0.1 0.030.3 0.2
7.1
0.80.50 0.4
0.2 0.1 0.01
0.70.5
1.47 1.47
0.730.32 0.18
2.442.22
0.12 0.09
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
Sulphur (S)%
Chlorine (Cl)%
K+Na%
Dewpoint of flue gasses with biomass firing
Dewpoint of water vapour in flue gasses:
Water content in flue gas is based on 52% moisture in bagasse and excess air of 35%: 29 vol%Means partial pressure of H2O is approx. 0,29 bara which result in dewpoint of approx. 66 C
Dewpoint of SO2/SO3 vapour in flue gasses:
Sulfur content in bagasse is approx. 0,3% on dry weight basis
There will be a certain conversion of SO2 into SO3 (approx. 2%) which will condense at certain temperature as H2SO4 on the tubes.
The dewpoint as per formula of Ganapathy is as follows:• For 0,14% S in bagasse on wt%: 139 C• For 0,07% S in bagasse on wt%: 133 C• For 0,04% S in bagasse on wt%: 129 C• For 0,01% S in bagasse on wt%: 116 C
The flue gas temperature should not drop to low due to condensation of vapour on heating surfaces
DEWPOINT
This means there is a potential of corrosion of tubes at cold end due to condensation of sulfuric gasses.
This is also observed in the flue gas air preheaters of the 25 bara boilers.
The dewpoint for bagasse firing is normally approx 90 C.
Means metal temperature should not drop below 90 C
a. When economizer at boiler outlet metal temperature is approx same as water temperature
b. When flue gas air preheater metal temperature is higher then air inlet temperature
Air 13 m/sAt 27 C
Flue gas 8,7 m/sAt 152 C
ao = 65 W/m2K
ai = 44 W/m2K
Metal temperature is 110 C
Heat transfer coef at innerside
Heat transfer coef at outerside
A perfect expansion process as in a steam turbine is with a constant entropy. See line A – B in
This is a isentropic process (ideal)However this is not possible as all kind of losses will occur like leakages between wheels and friction losses.
h1= friction losses in diffusor, heat into steamh2= friction losses in wheels, heat into steamh3= friction losses at outlet, heat into steamH4= losses through seals of wheels
The isotropic efficiency is the hT = 100 * (hA – hF) / (hA – hB) %
The power supplied to the shaft is m * (hA – hF) KWm= mass of steam per kg
The power at generator terminal is minus the losses in gearbox and generator. This approx. 5%
h1h2h3h4
A
B
CD
EF
H in KJ /kg
S in KJ /kgK
The Entropy:
35
The isotropic efficiency of steam turbine
enthalpy
entropy
1.2 the power output:
Extraction point in sugar mill at 2,5 baraSteam temperature should be slightly superheated 5 C. Other wise the heating surface in evaporators are not working properly.
110 bara 540 C 64 bara ,
480 C
25 bara , 350 C
Isotropic efficiencies different pressure levels:
At 110 bara:Isotropic eff= (3464 – 2350)/(3464 – 2090) * 100%= 80,2%Power per kg/s of steam: 1114 KW
At 62 bara:Isotropic eff= (3370 – 2360)/(3370 – 2150) * 100%= 82,7%Power per kg/s of steam: 1020 KW
36
550 C
500 C
50 C
400 C
350 C
300 C
250 C
200 C
150 C
100 C
450 C
103 bara 535 C: h=3461 KJ/kg82 bara 515 C: h=3434 KJ/kg62 bara 480 C: h=3370 KJ/kg
2.6 bara 129 C; h= 2720
65
0 K
J/kg
64 KJ/kg9.8 % more
27 KJ/kg3.8 % more
Dry steam towards the 1st effect at
62
bar
a 4
80
C8
2 b
ara
51
5 C
10
3 b
ara
53
5 C
Mollier diagram
Difference in heat available for power generation
Steam condition at inlet existing steam turbines
22
bar
a 3
50
C
entropy
enthalpy
110 bara 540 C 64 bara ,
480 C
25 bara , 350 C
Isotropic Efficiency existing steam turbine with 66% is lower then the 80 to 83% for the HP steam turbine.Means high losses
Why the existing steam turbine in sugar mill for driving the shredder and crushing rollers are
replaced by electric drives??
The flows of 15 to 30% are too high for extracting from High pressure steam turbine. Will reduce the isotropic efficiency.
The steam temperature is too high at extraction point which requires de-superheating. This results in less steam over HP steam turbine.
38
System with one boiler and one
condensing /extraction steam turbine
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 CDemi water
E
Advantage Disadvantage
It is a simple Condensing wheel has low efficiency during season
Having low investment
When one main equipment trip then sugar mill will
shut down
39
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 C
Demi water
E
E
System with two parallel systems each 50% capacity and consisting each of one
boiler and one condensing/extraction steam turbine
Advantage Disadvantage
High redundancy in case same quality will be taken
for equipment as of ‘option. a’Condensing wheel has low efficiency during season
When one unit trips then other unit can run at 50%
load
High investment costs because of additional boiler
and steam turbine.
40
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 CDemi water
E
E
Advantage Disadvantage
In case back pressure trips then
condensing/extraction steam turbine can run and
plant has an output of 70% load
2nd steam turbine which result in higher investment
cost
High efficiency during season and off season High storage of bagasse
The size of boiler and steam turbine can be 10%
smaller
System with one boiler and one back pressure steam turbine for
season operation and one condensing steam turbine for season
and off season
41
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 CDemi water
E
E E
System with two parallel systems each 50% capacity and consisting each of one
boiler and one back pressure steam turbine for operation during season, and one
condensing/extraction steam turbine for off season
Advantage Disadvantage
In case back pressure steam turbine trips the plant
can run still at 100% capacity.
3rd steam turbine and 2nd boiler which result in
higher investment cost.
High efficiency during season and off season High storage of bagasse
In case one boiler trips the plant can run still at 50%
capacity
42
More process steam required in relation to electric power result in higher plant efficiency
seasonOff-season
Minimum steam flow over condensing wheel into condensor
High losses in condensor
What is efficiency during season and off season
43
Boiler
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 C
Demi water
E
FG
eco stack
Steam air preheater
air
To water storage
For additional steam air pre heaters
System with one boiler and one condensing
/extraction steam turbine and air steam
preheater
Prevents corrosion in flue gas air preheater and generate more power over full season for fixed bagasse amount
Approx. 5 % more power
44
The HP co-generation plant with steam air preheaters 66 bara
More steam over steam turbine and extracted to heat up the air.
No increased losses in condenser while more energy generated
2,5 barg
9 barg
Extraction pressure control
45
The HP co-generation plant with steam air preheaters 86 and 110 bara
Flue gas air preheater eliminated
46
Extraction pressure control
Extraction pressure control
The HP co-generation plant with BFW preheaters for 66 and 110 bara
More steam over steam turbine and extracted to heat up the air.No increased losses in condenser while more energy generated
Boiler
Process steam2,2 bara, 135 C
E
Condensate return85% at 98 C
Demi water
E
FG
eco stack
air
BFW preheaters
Take care for corrosion at cold end
47
Take care during operation for following parameter;
parameter target consequences
Water content in bagasse Keep as low as possible High water content more unburnedLower efficiency and higher fuel consumption
Oxygen content Keep it at 3.5 vol % wet More oxygen lower eff and lower fuel consumptionMore oxygen less CO and less unburnedToo high then check flue tubes. Leakages. Tune the air control
CO content Keep it below 800. Prefer 300 ppmv Too high CO means high unburned and high fuel consumptionCheck the firing.
Flue gas temperature Keep as low as possible Higher eff and lower fuel consumptionToo high then sootblowing.
Air inlet temperature Keep it sufficient high to avoid to low metal temperature
Too low then fouling and corrosion. Metal temp measurement.Increase air inlet temperature by feeding more steam to steam air preheater
Carbon in ash Keep low. Max 20% High energy losses. High fuel consumption.Check the firing
High surface temperature casing and cladding
Keep surface temperature approx 20 to 25 C maximum ablve ambient temperature
High energy losses. High fuel consumptionImprove the insulation
parameter target consequences
Too low flue gas pressure Approx same as in clean condition In case to high then high fouling. Steam temperature too low, stack temperature too high . High power consumption. ID fan could be running at max speed. No control anymore.
Overpressure in furnace Should be 5 to 10 mbar underpressure
ID fan could be at max speed due to leakages and/or high pressure drop due to fouling.
Steam temperature too low
Should be at setpoint In case too low then steam turbine performance too low and possible trip. Put control on manual and try to increase it.Also perform additional sootblowing
Steam temperature too high
Should be at setpoint In case too high then overheating in superheater tubes, piping and steam turbine. Put control on manual and bring it down.
2. Reliability
The operator should understand the basics of design
The equipment should be kept in good and optimal condition
The operator should check during operation the proper working of the equipment
The operator should understand the controls and be able to fine tune if necessary.
Do avoid any manual control
During outage the equipment should be thoroughly checked and cleaned, greased, etc.
Make check lists of each equipment
Make record sheets of inspections including findings
Make directly clear objective reporting of incidents and collect all data and damaged material parts.
9621247 1345 1451
18381531 1406 1255
328 613 690 759
25 BARA, 350 C 66 BARA, 490 C 86 BARA, 520 C 110 BARA, 540 C
HEAT LOAD HEATING SURFACES AT DIFFERENT PRESSURES
eco evap sup
51
2 types of boilers:
• Self supporting• suspended
Both with single or bi-drum possible
2.1 Boiler
HP bagasse fired boiler 140 tph 65,7 barg 485 C, single drum and self supporting
Economiser 3
evaporator
HP superheatersingle-drum
Flue gas Air preheater plus steam air preheater
cyclones
Economiser 1
Economiser 2
In HP cogeneration system are nowadays 2 designs used in sugar mills:• suspended• self supporting
To ID fan and stack 150 till 160 C
Desuperheating station
furnace
Dumping grate
Bagasse spreader
Over firing air
22
50
0
Boiler type
52
For 86 and 110 bara
Alternatives in self supporting boilers
Bi drum supported on downcommer
Bi drum supported on downcommer
Boiler type - suspended
HP bagasse fired boiler 140 tph 65,7 barg 485 C, bi-drum drum and suspended
Bi-drumHP superheaters
Economiser
Flue gas Air preheater
cyclones
furnace
Dumping grate
54
In case of 110 bara moduleAnd single drum
Also for 86 bara
Expansions
Top suspendedExpansion from top downwards
Bottom supportedExpansion from bottom upwards
Boiler should not be restricted in expansions
Put indicator on the different point of expansions and check regularly.
100 mm downwards
Steam drum suspension
Al weight taken by hangers. Inspect those regularly for cracks, malfunctioning, deformation
Distance needed for flexibility hanger to take the expansion differences
The hanger in the top of steelstructure
Rotation should be made possible
Example of expansions in bottom supported boiler
Linear expansion coefficient of CS steel: 1,2 mm/m per 100 C.
Saturation temperature:• 70 bara = 286 C• 80 bara = 295 C• 90 bara = 303 C• 100 bara = 311 C• 110 bara = 318 C• 115 bara = 321 C
Expansions for 150 tph , 110 bara and 540 C
10 m
12
m
25
m
1,2 * 321/100 * 25= 96 mm
1,2 * 321/100 * 10= 39 mm
46 mm60 mm
39 mm
The sliding forces from bottom supported parts
High sliding forces
W
F l
F f
F f = F l = m * W
Friction factors: m• Steel to steel and dry clean surface: 0,5 till 0,8• Steel to steel and grease lubricated: 0,16• Steel to stainless steel: 0,5• steel to Teflon: 0,05 to 0,2• Teflon to Teflon: 0,04
Galling in case for carbon steel on carbon steel .Is adhesion of 2 sliding materials.Take at least stainless steel plus carbon steel of lubricate the surfaces
Support on concrete structure
Support in concrete structure
Concrete floor
Keep height lowApprox 200 mmTo avoid cracking of concrete
Hole for installing beam piece under plate in concrete
Beam piece for transferring the sliding force deeper into concrete structure
Anchors to take keep the support into position and taking the moments
High sliding forces
Wrong !!!!
The guidance for sliding
guidance
2 mm free gap
Height 2 mm more then plate
Take sufficient space for expansions
Install 2 mm plate under the support plate and weld to plate
Prepare hole and weld SS sheet to base plate
Buckstays
cold hot
Wall expand
Take care for high expansion differences. Check if those are free expanding
buckstay
Heating surfaces
Check the fouling.
Check if sootblower reaches all areas
Slagging on superheater tubesSuperheaters needs sootblowing with retractable sootblowers to have more penetration
Suspended to headers
Check the supports
Check the seals of tubes through walls
Check supports
Ensure that superheater coils have sufficient space for expansions
Check expansions headers of superheaters
Is refractory or insulation still in position
Check supports
66
Check the sootblower supports
Check foulingImpulse of sootblowing steam can be too less
Check if sootblower steam is not damaging tubes.
Could be due to condensate formation in sootblower lines
Flue tubes of flue gas air preheater heavy corrodedAnd many tubes with leakages
Check the tubes of flue gas air preheaterFor corrosion
seal
ex
tube
Tube sheet
Check the seals near tube sheet
Measurement furnace pressure Tube in Top with this shape of opening
Ensure that it is always open.
No blockage of ash
Clean also during operation
Steam drum with vertical cyclone separator
Steam drum outlet
scrubbers
cyclone
baffles
cyclone
Downcommerinlet
Feed water pipes
scrubbers
NOTE:Minimum size of steam drum with cyclone is 1450 mm ID diameter when installed at both sides
The number of cyclone required is depending on its design. Normally cyclone capacity is for each:• 66 bara :approx. 5,6 tph• 110 bara :approx. 7,7 tph
Vortex breaker
69
Check the steam drum internals Clean the chevron plates
Check if baffles are in place. undamaged
Check the fouling in steam
Check the small nozzles of level instruments and clean
Check cyclones on wear and tear
For high steam purity
100
100
55% of radius
LLTrip
Recheck water levels
demister
Baffles and demister
demister
D
Vst hor
Clean and check demister
Close all gaps.No bypass of steam
Demister
Spreader stokers
• Fuels to be uniform thrown / spread over then grate area
• Fines ignite and burn in suspension
• The coarser particles fall on the grate and burn on a thin fast burning bed.
• The fuel and air needs to be uniformly distributed over the bed
• A part of the air (overfiring air) is injected above the grate into the furnace to mix the unburned gasses and particle with air
• The furnace is made large enough to ensure complete combustion before entering the convection part.
2.2 Fuel/ firing system
Bagasse feeder should guarantee:
• Continuous flow of bagasse.
means chutes should be with angles and no sharp corners, smooth surfaces internally.
the bagasse should not get be compressed and then fall out of feeder
• No lumps at outlet. The bagasse get in silo and in feeder compressed. The lumps at outlet of feeder need to be broken by a lump breaker
high amount of fines supply into spreaders
Large lumps fall on grate
Bridge forming Above feeder
Feeders should run at same speeds to guarantee same feed over full area
Spreading of bagasse should be uniform over depth
Same speed and equalized spreading
Different speed
Equalized spreading in depth
Continuous pulsating damper in each air line to spreader for equalizing the spreading of bagasse over the fuel grade
E ETo bagasse spreaders
Pulsating damper
Existing air distribution improved air distribution
500 1000
80
0
Air ductAt hopper inlet
Take 8 mm thick plate of CS
80
0Weld at both sides to existing air duct
Duct approx. 920 * 650 mm
Approx 920
Cut hole 30 mm in plate and weld to duct
800Air distribution in hopper
Air distribution over grate in hopper should be equalized.
Dumping grate
Cast iron grate bars with venture openings for air supply installed on a horizontal bar which is supported in bearing at both side in frame
All horizontal bars connected with lever for dumping
Pneumatic or hand lever
Split in 2 sections
multiple dumping grate sections
More sections besides each other
Ash removal not continuously
Ash removal by stopping feed of fuel and air.
Disturb firing
Pressure drop in boiler during dumping.
Effect on steam temperature
Dumping grate example 1
The dumping grate has a lot of moving parts and requires a high maintenance activity
Support structure can be damaged due to fire in hopper
Air distribution is poor due to large opening and low pressure drop
Dumping grate example 2
The dumping grate has a lot of moving parts and requires a high maintenance activity
Support structure can be damaged due to fire in hopper
Air distribution is poor due to large opening and low pressure drop
Water cooled pinhole grate
The grate is water cooled so that the supported structure underneath will be protected against overheating.
The ash removal is by discontinuous by blowing steam through nozzles installed in the grate as a pin.
This system is worldwide applied for bagasse firing and used up to 220 tph steam capacity
The grate tiles supported on water cooled tubes
Example of cast iron grate section of pinhole grate as per Joh Thompson design
The cast iron grate sections protected with stainless steel plates
Cast iron parts
Example watercooled pinhole grate as per design of TES from USAinstalled in Jamaica for 113 tph steam capacity
Cast iron grate sections
Steam cleaning systemPinhole grate
Example of cleaning pinhole grate
before
after
Travelling grate
Rotation directionVery slow speed
Continuous ash removal
Re-firing of unburned particlesCashed separated from flue gasses possible
Air supply
Large travelling grate sections
Section maximum5, m width and 6,5 m depthLarger ones split in 2 sections with at each side a drive.The drive is normally hydraulic
Hydraulic drive
Need of special parts for smooth operationand to resist the wear and tear
High alloy steel shafts and sleeve bearings
Forced steel chain links, case steel hardened pins and rollers. Supports and rails also hardened
High strength steel hardened ductile iron sprockets
Special shaped Grate castings in alloy
The grate and furnace heat release
The loading of the grate and furnace are important factors for firing the biomass.
When there is high moisture we will need more time for drying the fuel before it ignites. How more fine it is how easier to dry. So the grate loading should be lower
When there is a high moisture content it is important to supply the primary under the grate as high possible.
The air distribution over the grate should be as equal as possible in order to lower the excess air as far as possible
The upwards flue gas velocity should not be too high to ensure that particles will not be blown out to fast from furnace.
The slagging and clinkering should be avoided
There are many figures mentioned as heat release for grates by supplierwhich are confusing
Recommended heat release for grates with spreader stokersbased on GCV value of fuel
Excess air in relation to moisture content of fuel
Furnace heat release
Velocity is lower and need more time for complete combustion
Velocity is approx. same as flue gas and need less time for complete combustion
Total volume of furnace should be such that residence time is minimum 3 seconds
Experience shows good burn out of 1 to 3% with a furnace heat release of 186 to 230 KW /m3 on GCV value. However, the overfiring system should then also made proper.
Overfiring system
The distribution of air and fuel including sizing is never equal.There will be CO strains and areas where to less air is available for further combustion.Further the biomass has lighter particles which will be blown out easy from furnace.
Therefore biomass firing requires always high over firing air required up to 50%
Mixingof all flue gasses
and particles with air
Overfiring system in bagasse fired boilers
Overfiring system in furnace of bagasse fired boiler
Openings in furnace walls of approx. 13 * 50 mm
Overfiring systemwith small jets at multilevel
Originally from stoker fired coal boilersPorts on front and rear wall
The small jets have not much penetration by which the mixing is not optimum.Channeling occurs
Some flow modelling of small air jets
No deep penetration
Test done by creating a cyclone effect in furnace
• installed above fuel distributors• Intended to create swirl• Could be made of larger capacity• The larger jets had higher momentum• However. Poor coverage still• Also channeling• Poor mixing• Higher excess air was required• Imbalance in gasses leaving furnace
Studied Alternative type of air jets in a cyclonic effect
Studied effect with large jets from front and rear wallResults are:
• Installed above fuel distributors • Large pipes of approx. 100 m in one layer• Outlet velocity approx. 40 to 50 m/s• Could be made of higher capacity and momentum• Interlaced or opposed jet arrangements• Good coverage is possible with interlaced• However in arrangement interference with fuel
distributors, ah re injection and furnace openings
Large jets from front and rear wall
Studied effect with large jets from side walls
The effect was also positive
However when furnace is more then 10,5 m width and 6 m deep then it is not possible to get a deep injection of air
High capacity cyclone 400 to 500 mg/Nm3
Approx. 70% fly ash captured.Not high efficient but high capacity one
2.3. The fly ash arrestor and ash removing systems
Mostly used in pakistan
Multi cyclone
Use the right swirler
Check erosion of cyclone body and swirlers
High efficiency cyclone to 200 /250 mg/Nm3
High efficiency cyclone
Alternative for low emissions of 50 mg/Nm3
High pressure drop of 15 to 20 mbar and high power consumption due to air compressor for pulse jet cleaning
Very important is to control the air pressure for cleaning the bags.
Need sufficient pressure
50 to 100 mg/Nm3
Electric static precipitator ( ESP)50 to 100 mg/Nm3.
High voltage between plates and gridsParticles are charged by the grids and migrate to the plates.Plates gets cleaned by rapper system.
Needs large areaHow lower the emission how larger the ESP
Ash removal from hoppers of grate
Manual:
• takes time to remove • air supply to grate get disturbed• Effect on steam pressure
With wet ash conveyor
• Preferred.• No disturbance of air supply to grate• Ensure always that seals are sufficient under the water level
100 mm
High wear and tear
In case of pinhole and travelling grate always wet ash conveyor required
Ash removal from hoppers heating surfaces and fly ash arrestor
From hoppers of heating surfaces only a small ash quantity. Remove manuallyRequired an ash rotary valve for continuous removal and sealing of air leakage.
Take care that the openings in valve are very small to minimize air leakage.
From hoppers of fly ash arrestor the ash discharge should be continuously.Normally wet ash system is applied. Same as from grate.Water seal is more difficult as pressure difference is 200 mWG.The ash is very light and difficult to discharge from hopper.Mostly no water seal used.
Each hopper provided with ash rotary valve and discharge in wet ash conveyor
Dry fly ash removal is also possible. The ash should be collected in bottle and blown into the silo.This system is however expensive and is costly in maintenance.
108
QH curve fan with speed control
Curve of system pressure dropagainst capacity
100% MCR
design
70 KW
Besides power savings speed control gives a more smooth control of the flow than with dampers.
When 2 * 50% are installed then dampers are installed at the inlet side of ID fans and at outlet side of FD fans.The dampers can be provided with drives for air control in case of problems with VFD.
The dampers require positioning transmitters and limit switches.Those instruments need to be checked regularly to ensure they will work correctly when needed.
Check during operation regularly the bearing temperatures and vibrations
The ID and FD fans are provided with variable speed electric drives
2.4. The fans and dampers
Take care for pressure drop and distribution in ducting
Pressure drop:Bend R=D factor 0,3Round bend with 3 sections
Factor 2 till 2,5 Factor 3
Install in bends with short radius a guide vaneFactor 0,5
Install in inlet sections vertical plates for improved distribution of flue gassesFactor 1
At stack inlet a 45 degree uplift is required . Factor 0,5
Install baffle in middle of duct to minimize turbulence between flows Dampers with 2 or more blades
Factor 0,5
1/3 Ri=500
Check the damper blades for cracks
Check the guide vanes for cracks
Keep screen at inlet venture clean during operation
venturi
To keep excess air low as possible it is measured in an air venture.Also any deviation in air flows can be easily noticed during operation
Damper installed at inlet ID fan to avoid dust collection in fan during a fan stop/trip
ducting
Stiffening required
Round duct only small stiffening inside to keep round shape
Check internal of ducting for cracks
Check if ducting can expand freely in right direction.
Expansion joints
For air ducting fabric material can be used
Take care that there is always an internal baffle at inner side installed to minimize the pressure losses
In flue gas ducting use SS bellows. Collected dust will not harm the material in case of fire
Flow direction
Weld joint to duct . No bolting
Check during outage the expansion bellows for cracks and leakagesCheck during operation the expansions
Expansion of hot ducting
The SS bellows needed mostly at each side of duct
Check during operation the expansions
114
PID’s bagasse firing system
E
E
E
E
Plate slide Plate slide
E
VSD
VSD
Fixed speed
VSD
Fixed speed
Signal load control4- 20 mA-
E
E
PI
PS
Spreader air fans
MCCAutomatic
start standby
Sight glassSight glass
Sight glassSight glass
peepholes
2 inch connections
3inch
inch
inchinch
Rotary air damper
Rotary air damper
Spreader fans
3 more
Bagasse feeding and spreading system2.5. The controls
Air system
FGAP2grate
FGAP2 overf
FGAP1grate
GFAP1overf
Right side wall
left side wall
Overfiring nozzles
2 * 5 dumping grates
5 air dampersPut air on and it will closeNormally open by spring
Raw water 1 inch
overflow
Push button for operation at each grate
E
VSD
E
VSD
StapOFA
Stapgrate
FT
FT
TT
TT
TT
TT
PT
E
VSD
o/c
o/c
E
VSDo/c
o/c
Load controlAir fuel ratio
E
Damper fan close directly
automatic when fan stops.
PT
116
PID’s Flue gas system
Dumping grate
PT
TP
TP
TP
TP
TP
TP= testpoint of 1 inch
Fly ash arrestor
PI
TT
Pressure control
PS
PS
H L
Flue gas system
E
FGAP2grate
FGAP2 overf
FGAP1grate
GFAP1overf
sup2
sup1B
sup1A
evap
2 *
eco
E 2 * E 2 *
XT
O2E
VSD
E
VSD
o/c
o/c
pT
TP
TP
TP
TP
TP
TP
TP
TP
TT
drain
Damper fan close directly
automatic when fan stops.
Trip boiler
Sootblowing system
Fly ash arrestor
FGAP2grate
FGAP2 overf
FGAP1grate
GFAP1overf
sup2
sup1B
sup1A
eco
2 *
E
E
E
E
E
eco
E
E
E
E
E
E
2 *
2 *
2 *
3 *
evap
evap
E
2 *3 *
3 *
3 *
3 * 3 *
3 *
3 *
2 inch
PT
PI
From de-superheating line at inlet superheater 2
1,5 inch
1,5 inch
1,5 inch
Blow down vessel
TT
TT
2 inch
Design pressure 25 bargDesign temp. 400 C
Design pressure 124 bargDesign temp. 450 C
Pressure control
Automatic sequence control
Signal to start/stop sootblowers
Signals from sootblowers
temperature control
118
Sup 1 BDeaerator
LT
LIC
PT
PI
LS
LG
LIC
To sample cooler ¼ inch
Dosing hydrazine½ inch
Dosing ammonia½ inch
Design pressure deaerator at 2 barg, saturated and 100% vacuum
2 inch drain
Condensate And demi water return
??inch
From LP header? inch
Into demi water tank1 inch
? inch
1/2 inch
Steam air preheater
1 inch drain
To pressure/temperature reducing station
?? inch
BFW pumps
Boiler feed water system
Capacity?
To BFW pumpsL
HTo cond pumps
E
? inch
PI
PI
?? inch? inch
Second pump
2nd
2nd
To boiler
2nd
PT
Start 2nd
pump
L
condensate
Condensate vesselDiam 1000 and 1500 mm highOn 4 m level
2 inch balancing line
?? tph LP steam from outlet steam turbine at 1,2 barg
To condensate clean tank
LT
LG
12 inch
? inch? inch
? inch
? inch
? inch
3 inch
System Steam air preheater
8 inch
? inch globe
Condensate vessel
Installed near vessel
Water level control valve
TIC
At 8 m level
Design 3 barg 150 C
Steam air preheater system for higher air temperatures like 105 C
Water system boiler
2 inch
2 inch
LS
LG
LL
LT
1 in
ch
1 in
ch
2 inch
2 inch
LS
LG
LL
LT
1 in
ch
1 in
ch
Steam drum
eco
1 in
ch
Tri phosphate dosing
??inch
FT
1 inch
From BFW pumps
FIC
LIC
1 in
ch 1 in
ch
To de-superheater
Parabolic valve for manual control
1 i
nch
1,5 inch
1,5 inch
1,5 inch
1,5 inch
Sample cooler
Trip boiler ( stop feeder and air supply)After stop air fans then stop ID fan
The ash characteristics of fuels are important.
Specially important are:• the alkali metals (Ca, Na, K) are important.• silica
Further the sulfur and Chlorine content in the fuel is an important factor
Those contents needs to be verified in the lab before deciding the best combustion and boiler system.
121
2.6. The sootblowing system
Elements in biomass potentially leading to corrosion and deposits.
122
0.600.2
0.02 0.1 0.030.3 0.2
7.1
0.80.50 0.4
0.2 0.1 0.01
0.70.5
1.47 1.47
0.730.32 0.18
2.442.22
0.12 0.09
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
Sulphur (S)%
Chlorine (Cl)%
K+Na%
Those elements determine the clinkering, slagging and fouling and also the erosion and corrosion potentials of the fuels.
Ash fusion temperatures
Initial deformation temperature C 1380
Sintering temperature C 1400
Hemispherical temperature C 1400
Fluid temperature C 1400
The ash starts to get sticky
First sign of softening. Change of outer surface
The form is changing too its half of heightIt did shrunk till one third of height
Ash Behaviour
123
Mechanisms of deposit build up in biomass boilers
124
Rotable sootblower
125
Check if nozzles are installed inbetween tubes
Rotable sootblower installed
126
The poppet valve
127
Set pressure in lanceInstall pressure gauge for checking the pressure in lance
The nozzle and support
128
Check the nozzles for cracks and fouling
Long retractable sootblower
129
The travelling of long retractable sootblowers
130Check the travel path of sootblower.
The long retractable sootblower installed
131
Grease theTeeth bars andKeep those clean from dust
Check limit switches of sootblower
The semi retractable sootblower installed
132
Grease theTeeth bars andKeep those clean from dust
Check limit switches of sootblower
Guidance at both sides
Especially for finned tubes required
The sootblower system
From primairysuperheater
To secondairysuperheaterPTPI
E E E
E E E
E
TT
Keep temperature 20 C above saturation temperatureOpen this valve shortly when sootblower stop and other starts
Small orifice for keeping line warm
Ensure slope of 1 degree
Always connection from below
Take care for expansion differences between line and sootblowerconnections
Valve should be fast reactingEspecially when sootblower stop
Take steam from far end of de-superheateroutlet
To blow down vessel, Install diffusor in blow down vessel at inlet to reduce wear and tear and noise
133
Sootblowing direction
Execute sootblowing at hot side in direction of flue gas flow
134
2.7. The Feed water system
Deaerator:
Deaerator has to remove the oxygen.
Check during operation its working. High oxygen content will result in corrosion.
Minimum pressure in deaerator is 0.2 barg. Ensure no lower pressure.
Check during operation if the vibrations are not too high. If so then problem have to be solved asap.
Keep the level always as high as possible to have always sufficient water buffer.
Also check the expansions
During outage check the fouling at inlet sprayer. Larger parts can block it.
Check also the trays during outage for fouling and for cracks. Also check bolts
Same for steam distribution pipe.
Clean nozzles for water level measurement during outage.
BFW pumps:
During operation check regularly for vibrations and bearing temperature
Also record the discharge pressure of BFW pump in order to have an indication of the wear and tear of internals
The minimum flow valve can leak and will lower the capacity and/or increase the power consumption.
At higher loads check by closing the minimum flow valve if the pressure at outlet pump is increasing and read from QH curve how much it is leaking
Change each week the pump in operation. Also standby pump should run
Boiler
Process steam
Condensate return85% at 98 C
Demi water
E
FG
eco stack
Air100 C
E
E115 C
155 C
200 C
115 C
150 C
Water storage
E
Washing steam
deaerator
Extraction condensing steam turbine
condensor
Chemical transport in steam cycle
Injection BFW for steam temp controlImpurities in BFW will lower purity of steam which could harm superheater and steam turbine
Mechanical carry over
Blow down
Malfunction deaeratorresults in high concentration of oxygen in system. pitting
Ingress of O2 and CO2
Silica deposits in condensing wheelsalt deposits in wheels
pH of BFW should be high enough to avoid flow accelerated corrosion in BFW line, eco, pumps and BFW heaters
Any contaminated condensate with sugar will harm the system
Preciparations of Ca and Mg saltsIn natural circulation system boiler
2.8. The conditioning of water and steam side/chemistry
Steam purity requirements
Boiler Water requirements
Boiler drum water requirements BOILER PRESSURE
66 bara 80 bar 110 bar
Boiler water Conductivity After cation Exchanger @25 °C pH 25 °C Silica Phosphate Hydrazine
SiO2 PO4 N2H4
MicrS/cm
mg/kg mg/kg mg/kg
150 9.5-10.5
<6 <6
Traces
150 9.5-10.5
<4 <6
Traces
150 9.5-10.5
<1,8 <6
Traces
max. max. max. max.
For controlling the oxygen level in the feed water hydrazine will be injected into the deaerator storage vessel.
The pH of the boiler feed water to the boiler will be controlled by injection of ammonia into the feed water line at the inlet of the deaerator,The pH value of the boiler water in the evaporator system will be controlled by injecting Natrium Tri-phosphate into the feed water line downstream the economizer.
Boiler Feed Water requirements Non-solids-containing water
Boiler Feed Water
De-Superheater spray water
Conductivity After cation Exchange @ 25 °C pH @ 25 °C Hardness Total CO2 Silica Total iron Total copper Oxygen Permangate Oil
CaCO3 CO2 SiO2 Fe Cu O2 KMnO4
Micro S/cm mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg
0.2 9
N.d. N.d. 0.02 0.02
0.003 0.02
5 0.5
0.2 9
N.d. N.d. 0.02 0.02 0.003 0.02
5 0.3
max. min. max. max. max. max. max. max.
Boiler Feed water requirements
To meet the steam purity requirements high purity water shall be fed into the system.Further the return condensate from sugar mill should also meet those requirements.
This water quality can be generated by a demineralized water treatment plant extended with a mixed bed ionization exchange.
Conditioning the water and sampling during operation
Boiler
Process steam
Condensate return
Demi water
E
FG
eco stack
Air
E
E
115 C
150 C
Water storage
E
Washing steam
deaerator
Extraction condensing steam turbine
condensor
Ammonia for pH controlFor water system min PH is 8,5For BFW pumps min pH is 9,2 when CS materials are used. Quantity based on measured conductivity upstream and at outlet deaerator and corrected on BFW flow.
Note: take always as minimum Cr impellers in BFW pumps
HydrazineIn case oxygen in outlet is too highAnd for conservation during standstill
Dosing phosphate to keep pH in natural circulation system at 9,8 and reduce the hardness, catch the salts
Continuous blow down toControl the conductivity after cation exchange at 50 micro S. Take out the deposits
Intermittent blow down lower headers to remove sludge during each shift
Sample: Continuous check on contaminations
SampleConductivitybefore cation of pH continuously
SampleConductivity after cationfilter continuously
Steam sample
sample
Sample: at outlet demi water plant is a continuous sampling
Blow off O2 and CO2
Sampling of water and steam during operation
Dosing rate of ammonia
Supplied as liquid and can be reduced to concentration of 10% in dosing vessel before dosing it into boiler.The dosing needs to be continuously and quantity depends on PH of boiler feed water and BFW flow
Morpholine is a good alternative
Hydrazine is not recommended as it can cause cancer. Only used for oxygen scavenging in case deaerator does not work properly. Then dose approx. 0,1 mg/lAnd for conservation. 25 till 100 mg/l depending on standstill period. Alternative is eliminox.
Dosing rate of phosphate
Normally 3 is taken
Max 6 ppm PO4 in boiler water
Band of pH control
Phosphate is supplied as powder and needs to be mixed with water in vessel to concentration of 5%.The dosing is discontinuously with the pH band.
Care shall be taken for proper mixing.
Put dosing pump at floor level, not on top of vessel otherwise it could block the lines.
Doing system of phosphate
M
M
FE
silencer
Steam blow off for start up of boiler
Steam from future boilers
To steam turbine 1
To steam turbine 2
To steam turbine 3To steam turbine bypass station
Steam header with condensate drip and steam trap
PT
PT
Note :The boiler needs a steam blow off facility to be able to start up the boiler and to bring the steam temperature till acceptable levels before feeding into the steam turbine
When the first boiler will be started up the steam of boiler should go as fast as possible in steam air preheater and deaerator for warming up.
Normal practice for connecting high pressure systems
2.9. The piping systems and valves
FT
Block and bleed
Understand how piping will expand.
Check the piping for its expansions. Is it as per expectations?If not then high stresses
Check the hangers of piping. Is the loading as per expectations
Desuperheater.Check the desuperheater for cracks and check the springs. and also check internally the surface of pipe for cracks
Expansions
Expansions in Headers and connecting piping in superheaters
Header is 540 C
wall is 320 C
Difference in expansion for 10 m wide wall:(1,4 * 540/100 – 1,2 * 320/100 ) * 10 = 37 mm
18,5 mm
Need enough distance to create flexibility for 18,5 mm deflection.If not enough then split header in 2 parts
Ensure header can expand in both directions
The de-superheater loop and connecting piping
10 D
20 D
Condensate trap
Heavy header cannot supported by small flexible tubes
Take care that de-superheater has enough length upstream and downstream
De-superheater type
Ensure sufficient length upstream and downstream the orifice
Orifice or venturi
30 d 7 d
D= internal diameter
HP steam flow measurement
Safety valve testing
• Steam blow off over the steam blow off valve• Increase pressure slowly to 85% of set pressure• Install the gags to not tested safety valves• Raise pressure to set pressure by closing start-up valve
slowly • Maintain in all circumstances some flow over the
steam blow off valve for superheater cooling• Record set pressure opening• Record maximum pressure raise• Open slowly steam blow off valve to lower pressure• Record the seating pressure• Lower the pressure to 85%.• Check the set pressure and closing pressure as per
design.• If not then adjust the set or blowdown pressure and
retest• Also do same for the other 2• Record the test. With pictures
Insulation Functions:• Reduce energy losses to ambient• Avoid corrosion of boiler parts due to rain water
Insulation is mostly a under estimated part of the boiler
We take in our design a low loss of heat in order to lower bagasse consumption
In existing boilers is insulation system very poor:• To thin• Several hot parts are uninsulated• Not weatherproof ( rain water)• Poor material
The losses are in existing boilers approx. 5 to 6%
While we need to meet approx 0,8 %. The surface temperature should be max 25 C above ambient
Therefore insulation needs high attention during design and installation.
Also the installation of roof at steam drum guarantees the condition
2.10 . The refractory and insulation systems
Poor insulation
What to insulate
surfaces above 50 C accessible from grade or platform during operational inspections
-personal protection.
All surfaces above 50 C and having effect on the efficiency of the system should be
provided with a proper heat insulation system.
Systems like flue gas ducting at boiler outlet or piping systems like drain or blow down
piping need only personal protection from downstream first block valves . No heat
insulation as it has no effect on the efficiency of the system
All parts in which flue gasses could condense during the normal operation should be
also insulated. Like hoppers of cyclone
Insulation wool available in Pakistan
wired mat with galvanized hexagonal wire netting
The available thickness of ceramic wool blanket in Pakistan market is 25 mm
Require for all those materials that they are free from Chlorides
Selection of type and thickness of insulation wool
• Always use the 50 and 75 mm thickness blankets.
• The 100 mm thick blanket should not be used as overlapping is preferred above 75
mm thickness .
• When more thickness required use 2 layers .
• The layers should be min 50 mm overlapped.
• The density of the insulation mat depends on the application.
Normally use 80 kg/m3 density
Above 500 C install always first a layer of ceramic wool with density of min. 120 kg
/ m3 till the surface temperature of rockwool is lowered below 500 C.
What are economic insulation thicknesses
economic insulation thickness tableRockwool isolation hard board 850
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
0 50 100
150
200
250
300
350
400
450
500
550
600
650
700
750
800
850
900
950
1000
diameter outside (mm)
ins
ula
tio
n t
hic
kn
es
s
50
100
150
200
250
300
350
400
450
500
550
note rockwool 850:density kg/m3 110 to 125temperature C 50 100 150 200 250 300thermal conductivity: w/mk 0,039 0,045 0,051 0,059 0,067 0,078
Piping cladding supporting
Each 1 m
Insulation thickness for walls
Operating pressure in boilerBarg
Operating temperature in boiler C
Required Insulation thickness and to be usedmm
Cladding temperature above ambient temperature C
Till 1 60 to 120 40 (50) 17
1,1 to 4 120 to 152 50 (50) 20
5 to 10 159 to 184 75 (75) 20
11 to 15 188 to 201 90 (2*50) 19
16 to 20 204 to 215 100 (2*50) 20
21 to 25 217 to 226 104 (2*50) 20.4
26 to 30 228 to 236 110 (2*50) 21,6
31 to 35 237 to 244 120 (75 +50) 19
36 to 40 246 to 252 125 (75 +50) 20
41 to 60 253 to 276 150 (75 +75) 20
61 to 80 278 to 296 175 (2* 75 +50) 20
81 to 120 297 to 325 200 (4*50) 20
Density : 80 kg/m3
Cladding systems for walls
Cladding systems for walls
Cladding systems for ducting
refractory
There is limited amount of refractory inside the boiler:
• Around the grate• for peephole • For inspection doors• for burner openings• For sealing areas
The castable needs to be suitable for 1600 C and needs to have a pH value of min 8 to protect the materials
Normally applied with manual pouring
Castable have a hydraulic binder, which hardened in the presence of moisture.Once in place castable should not dry to exposure of heat.Curing start immediately after the castable is placed.Moist condition can be mainatained by covering the castables with wet sack or by frequent sprinkling.Curing takes at least 24 hrs, preferred 72 hrsAfter the curing period, natural air drying of 2 to 3 days.
Dry out of refractory
Dry out is needed to :• Remove mechanical water added during the mixing process• Chemical water added during manufacturing
For dry out a slow ramp rate of the heat is requiredRecommended 30 to55 C.First hold point is between 100 and 200 C.This hold point is most critical for removing the mechanical waterThe next hold points is to remove the chemical water and to form the final bondWithin the refractory for maximum strength2nd hold point is at 300 till 370 C3rd hold point is at 500 till 600 CHold up time is 1 hr for each inch of castable thickness
2.11. Preservation boiler during standstill
During off season the plant will run some further in single cycle mode to burn all bagasse and to supply power into grid.
Thereafter some months a stop.
After stoppage of boiler record the fouling of all boiler parts at inner and outer side.Also record the damages noticed. Including pictures.
Thereafter clean the heating surfaces fully and remove all dirt. Avoid any pockets of dirt.Keep the boiler fully open and ensure the boiler will be vented properly so that all water can be evaporated.
The steam drum and lower headers of boiler should be all fully cleaned.Flush the boiler after cleaning several times till you are sure that it is clean.
Then let the innerside also be dried by the natural draft.
Check the boiler entirely for corrosion, erosion and damages
Check the insulation of boiler and remove wet mats and dry out the areas. Check the corrosion of parts. Repair where needed. Then reinstall when quality is oke.Ensure all cladding of insulation is rain water tight.
Check all equipment on corrosion, erosion and damages. Repair where needed.
Check the refractory for damages and replace where required.
Ensure the boiler and equipment are all clean and dry so that in months before start of season the boiler parts cannot corrode
3. Safeties in system for protection persons and equipment
Thank You for Your Kind Attention