On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
0405 Construction & Supply 34735Repair/Rehab. of Drainage Canal along Sorsogon-Bacon-
Manito Road, Bibincahan, Sorsogon City05/30/2017
Sorsogon 1st
DEO2.841 90 C 0.40 0.13 0.30 - - - 83.30 *83.3% Satisfactory
0405 Construction & Supply 34735
Construction of Flood Mitigation Structures (Baybay
Dagat Dike) Sitio Bacolod along Bito River, San
Fernando, Masbate
06/14/2016Masbate 3rd
DEO4.653 115 O 0.382 0.24 0.15 0.022 0.04 0.05 88.40% - On-going
0405 Construction & Supply 34735Construction / Repair / Rehabilitation of Multi-Purpose
Building (Municipal Hall), Monreal, Masbate08/19/2017
Masbate 3rd
DEO3.881 150 O 0.488 0.133 0.300 - - - 92.10 *92.10% Very Satisfactory
11-16 Construction 29646
Construction/ Maintenance of Flood Mitigation
Structures and Drainage Systems-Rehabilitation/
Improvement of Existing Dike along Marimla River, Left
Bank, Sta. 0+258 to Sta. 0+630; Sta. 0+033 to Sta.
0+089.90 and Sta. 0+033 to Sta. 0+129, Bamban, Tarlac
11/21/2017 DPWH 45.616 147 C 0.50 0.13 0.30 - - - 92.90 *92.9% Very Satisfactory
121 Construction Corporation
(Formerly: 121 Construction)21686
Improvement/Concreting with Drainage System along
Ballesteros Street11/29/2014 NCR 6.684 120 O 0.355 0.240 0.150 0.030 0.035 0.033 84.30% - On-going
128 Dragon Construction And
Supplies35408
Construction of Flood Control Structure, Brgy. Kanluran,
San Vicente, Camarines Norte, 2nd Legislative District03/14/2016
Camarines
Norte DEO0.949 30 C 0.40 0.20 0.30 - - - 89.60% *89.6% Very Satisfactory
2M Construction & EnterprisesImprovement/ Construction/ Concreting of Labasan -
Camanga Road05/29/2018
Zamboanga
Sibugay 2nd
DEO
28.649 133 O 0.39 0.24 0.15 0.03 0.07 0.05 92.10 - On-going
2M Construction & Enterprises 33331Slope Protection (Grouted Riprap) along Isabela-Maluso
Rd., Matarling Sect. at K15+190-K15+24903/13/2013 IX 4.842 75 O 0.328 0.240 0.150 0.030 0.040 0.050 83.80 - On-going
2M Construction & Enterprises 33331 Construction of Water System Level II 03/07/2016Zamboanga
City DEO1.945 75 C 0.43 0.15 0.30 - - - 87.50% *87.5% Satisfactory
2M Construction & Enterprises 33331Road Widening Including Drainage along Ipil-Magdaup
Wharf Road (S01143MN) (K2014+800 - K2015+297)03/13/2018
Zamboanga
Sibugay 2nd
DEO
16.187 177 C 0.49 0.20 0.28 - - - 96.60 92.92% Very Satisfactory
2-R Construction & Supply 15304Concreting of Barangay Camanggaan - Calapugan,
FMR, Brgy. Camanggaan-Calapugan03/19/2018
Pangasinan
3rd DEO3.977 119 C 0.46 0.13 0.30 - - - 89.40 *89.40% Very Satisfactory
2-R Construction & Supply 15304
Raising of Grade of Dike Agno River Basin Flood Control
Project (Phase III), Brgy. Cabalitian, Asingan,
Pangasinan
11/16/2015PANGASINA
N 3RD DEO9.167 120 O 0.391 0.24 0.15 0.03 0.05 0.05 91.10% - On-going
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 1 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
2-R Construction & Supply 15304Off Carriageway Improvement at Lingayen Capitol Loop,
K0364+(-219) to K0364+836, Lingayen, Pangasinan09/02/2016
Pangasinan
2nd DEO9.34 105 C 0.47 0.13 0.30 - - - 90.60% 87.36% Satisfactory
301 Engineers 38364
Indv. Project - Rehab./Reconst. of National Roads w/
Slips, Slope Collapse and Landslide along Iriga City-
Masoli Road
11/16/2017 DPWH 5.071 132 C 0.49 0.13 0.30 - - - 92.70 *92.7% Very Satisfactory
0405 Construction & SupplyJV-17-
1886
Development of Pocket Forest Park, Gardens and
Playground09/19/19 TIEZA 23.000 195 C 0.40 0.17 0.30 - - - 86.80 92.57% Very Satisfactory
3C'Sl Construction And Supply 36393
Construction of One Storey Two Classroom (Toilet
Attached) Tolosa CES, Cabadbaran City, Agusan del
Norte
03/14/2016 ADN DEO 1.927 90 C 0.44 0.13 0.30 - - - 87.40% *87.40% Satisfactory
3Diamonds Construction
Corporation35457
Rehabilitation of San Francisco River Control (San
Francisco-Maguiron Section)11/06/2017 DPWH 9.328 105 C 0.50 0.13 0.30 - - - 93.40 *93.40% Very Satisfactory
3G A Construction & Supply 35033Construction of Flood Control along Cabugao River,
Brgy. Turod - Patac03/16/2018
Ilocos Sur 1st
DEO9.304 140 C 0.48 0.13 0.30 - - - 91.20 *91.20% Very Satisfactory
3K Rock Engineering
Road Upgrading (Unpaved to Paved) based on Gravel
Roads Strategies, Traffic Benchmark for Uprading to
Paved Road Standards (HDM-4) Project Analysis)-
Tertiary Roads+ Apayao- Ilocos Norte Road
06/05/2018Apayao 1st
DEO, CAR96.499 417 O 0.363 0.255 0.112 0.03 0.055 0.033 84.80 - On-going
3K Rock Engineering 27908
Road Upgrading (Gravel to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standard (HDM-4 Project Analysis) Asin
(KM 8)-Nangalisan San Pascual, Tuba, Benguet-LU
Road, K0273+707 - K0273+728, K0273+790 -
K0274+127, K0275+351 - K0275+613, K0275+629 -
K0275+1014, K0275+1050 - K0275+1240, Tuba,
Benguet
11/17/2016Benguet 1st
DEO33.303 196 C 0.41 0.18 0.30 - - - 88.30 86.32% Satisfactory
3K Rock Engineering 27908
Rehabilitation/ Reconstruction/ Upgrading of Damaged
Paved National Roads including drainage based on
Pavement Management System/Highway-4 Kennon KO
238 + 880-KO 239 + 048, KO237 + 123- KO238 + 000,
KO228 + 791-KO229+000, KO228+080-KO228+440,
Tuba, Benguet
11/16/2016Regional
Office46.620 282 O 0.331 0.289 0.121 0.03 0.055 0.033 0.8590 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 2 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
3K Rock Engineering 27908
Road Upgrading (Gravel to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standard (HDM-4 Project Analysis) Asin
(Km 8) - Nangalisan San Pascual, Tuba, Benguet,
K0273+707 to K0273+728; K0273+790 to K0274+127;
K0275+531 to K0275+631; K0275+629 to K0275+1014;
K0275+1050 to K0275+1240, Tuba, Benguet
03/29/2017Benguet 1st
DEO33.303 195 C 0.44 0.13 0.30 - - - 86.90 *86.9% Satisfactory
3K Rock Engineering 27908
Road Upgrading (Unpaved to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standards (HDM-4 Project Analysis)
(Intermittent Sections) of Kabugao - Pudtol - Luna -
Cagayan Bdry. Road, K0611+917 to K0612+961,
K0612+973 to K0613+699, K0613+723 to K0614+500,
Apayao
08/27/2015 CAR 75.709 221 O 0.363 0.241 0 0.03 0.061 0.033 72.80% - On-going
3K Rock Engineering 27908
Road Upgrading (Gravel to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standard (HDM-4 Project Analysis) Asin
Km. 8 - Naglisan - San Pascual, Tuba, Benguet-La Union
Road, K0273+707 to K0273+728, K0273+790 to K0274+
08/23/2016BENGUET
1ST DEO33.303 195 O 0.339 0.24 0.15 0.02 0.051 0.05 0.8500 - On-going
3K Rock Engineering/Rvc
Construction (J.V.)27908
Road Upgrading (Gravel to Concrete) of Asin -
Nanganban - San Pascual Road K0270+594 -
K0272+220 ; K0275+5311 - K0275+7178
08/16/2014 CAR 91.358 237 O 0.379 0.240 0.150 0.024 0.060 0.050 90.30 - On-going
3-L Construction 16745Concreting of Barangay Road, Barangay Salvacion, Del
Gallego, Camarines Sur08/16/2017
Camarines
Sur 5th DEO1.410 40 O 0.496 0.133 0.300 - - - 92.90 - On-going
3-L Construction 16745Concreting of Mataoroc (Zone 3- Zone 5 FMR) Barangay
Mataoroc04/06/2018
Camarines
Sur 1st DEO4.723 90 C 0.49 0.15 0.30 - - - 94.50 *94.50% Very Satisfactory
3N Construction & Supply 37872
Cluster 5-Local Infrastructure Program-Repair/Rehab. of
Multi-Purpose Building, Barangay Sweetland,
Buenavista, Bohol
03/10/2016Bohol 2nd
DEO0.7682 75 C 0.47 0.13 0.30 - - - 90.00% *90.00% Very Satisfactory
3Rb Construction And Supply 19541
Cluster 6 - Network Development -
Improvement/Widening of National Roads - Secondary
Road along DM- Jct.-Legazpi-Sto. Domingo-Tabaco-
Cam. Sur Bdry. Roads, Malinao, Albay and along Ligao-
Tabaco Roads, Buang, Tabaco City, Albay 1st LD
06/08/2017Albay 1st
DEO92.711 190 O 0.387 0.232 0.150 0.03 0.061 0.033 89.30 - On-going
3Rb Construction And Supply 19541
Cluster 6- Network Development - Improvement/
Widening of National Roads - Secondary Roads along
DM- Junction - Legazpi - Sto. Domingo- Tabaco -
Camarines Sur Bdry Roads, Malinao, Albay and along
Ligao- Tabaco Roads, Buang , Tabaco City, Malinao and
Tabaco City
08/24/2017Albay 1st
DEO92.771 190 O 0.369 0.295 0.150 0.022 0.037 0.033 90.60 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 3 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
3Rb Construction And Supply 19541
Construction/ Maintenance of Flood Mitigation Structures
and Drainage Systems - Construction of Revetment
along Pooc Creek, Barangay Balibago and Barangay
Macabling, Sta. Rosa City, Laguna
03/19/2017 Laguna 2nd 19.002 140 C 0.34 0.20 0.30 - - - 84.40 *84.4% Satisfactory
3Rb Construction And Supply 19541Extension of River Control, Sta. 0+112.50 - Sta.
0+232.50, Bongabong, Tabaco City, Albay03/13/2017
Albay 1st
DEO16.705 128 C 0.49 0.14 0.30 - - - 92.60 *92.6% Very Satisfactory
3Rb Construction And Supply 19541
Widening of National Roads Outside N1 DM Jct-Legazpi-
Sto. Domingo-Tabaco-Camarines Sur Bdry. K0552+532-
K0553+660, K0554+600-K0555+400, Malilipot, Albay
and Tabaco City
03/07/2016Albay 1st
DEO43.1972 147 C 0.45 0.20 0.30 - - - 94.40% 94.40% Very Satisfactory
3Rb Construction And Supply 19541 Prieto Diaz Port Development Project 08/19/2015 DOTC 8.512 124 O 0.367 0.300 0.150 0.030 0.054 0.050 95.10 - On-going
3Rb Construction And Supply 19541Cluster 9-Construction/Rehabilitation/Improvement of
River Control Section, Estancia, Estancia, Malinao, Albay03/07/2016
Albay 1st
DEO3.9755 218 C 0.48 0.13 0.30 - - - 91.30% 91.30% Very Satisfactory
3R'S Builders And Resources 35922 Construction of Multi-Purpose Building 03/16/2016
MISAMIS
OCCIDENTA
L 2ND DEO
1.937 120 C 0.46 0.13 0.30 - - - 89.10% 89.10% Very Satisfactory
4 A'S Construction 9446Construction of 2STY 4CL School Building at Andabuen
National High School Benito Soliven, Isabela03/18/2017 Isabela 2nd 5.996 150 O 0.341 0.299 0.000 0.03 0.047 0.033 75.00 - On-going
4 A'S Construction 9446
Construction of Two (2) Storey Four (4) Classroom
School Building at Andabuen National High School
Benito Soliven, Isabela
11/19/2016 Isabela 2nd 5.996 150 O 0.389 0.2 0.15 0.02 0.052 0.05 0.8610 - On-going
4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 02/05/2015 BCDA 18.951 120 O 0.377 0.293 0.000 0.030 0.041 0.033 77.44 - On-going
4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 11/20/2014 BCDA 18.951 120 O 0.400 0.271 0.105 0.000 0.032 0.033 84.10 - On-going
4B Construction Corporation2014 heavy maintenance works along SCTEX lot 2 -
Bridge revetment, slope and drainage repair works10/31/2014 BCDA 12.430 90 O 0.298 0.288 0.135 0.000 0.035 0.050 80.53 - On-going
515 Life Construction, Corp.
CY 2017 Basic Educational Facilities Fund, Construction
of 2STY 6CL Bernardo Lirio Memorial National High
School
06/19/2018Batangas 3rd
DEO11.598 170 C 0.48 0.14 0.30 - - - 91.70 91.70% Very Satisfactory
525 Construction 28532Repair/ Maintenance of Flood Control Structure along
Balagtas River, San Juan Section, Balagtas, Bulacan05/31/2017
Bulacan 1st
DEO18.325 150 C 0.47 0.13 0.30 - - - 90.20 *90.2% Very Satisfactory
525 Construction 28532Construction of Flood Control Structure along Balagtas
at Dalig, Balagtas, Bulacan08/25/2017 Bulacan 1st 4.628 90 C 0.37 0.20 0.30 - - - 86.70 *86.7% Satisfactory
525 Construction 28532Rehabilitation of Roads Brgy. Igulot - Brgy. Binang -
Brgy. Turo09/19/2016
Bulacan 1st
DEO34.143 210 O 0.312 0.3 0.15 0.03 0.042 0.05 0.8840 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 4 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
525 Construction 28532
Valenzuela-Obando-Meycauayan Flood Control Project-
Meycauayan, Construction of River wall Protection,
Meycauayan-Valenzuela Boundary Phase I, RS , (Sta.
3+475.40-Sta. 3+567.00), Right Side, Meycauayan,
Bulacan
03/08/2016Bulacan
Second DEO24.1599 201 O 0.40 0.21 0.15 0.03 0.06 0.05 89.50% - On-going
525 Construction 28532
Valenzuela-Obando-Meycauayan Flood Control Project -
Meycauayan - Construction of Riverwall Protection,
Meycauayan-Valenzuela Boundary Phase I, RS (Sta.
3+475.40 - Sta. 3+567.00), Right Side
06/07/2016 Bulacan 2nd 24.159 201 C 0.49 0.10 0.30 - - - 89.30% 89.42% Very Satisfactory
525 Construction 28532Construction of Flood Control Structure along Angat
River, Pulilan, Bulacan11/17/2017 DPWH 10.880 150 C 0.47 0.13 0.30 - - - 90.50 *90.5% Very Satisfactory
5'S Construction & Supply 32404
Local Infrastructure Program - Improvement of Multi-
Purpose Building (Public Market) Iloilo 4th Legislative
District , Brgy. Poblacion, Banate Iloilo
03/09/2016Iloilo 2nd
DEO1.969 259 C 0.46 0.13 0.30 - - - 89.00% 89% Satisfactory
5'S Construction & Supply 32404Improvement of Multi-Purpose Building/ Barangay Hall,
Barangay Punong Lapuz, Iloilo City03/23/2018
Iloilo City
DEO1.914 118 C 0.49 0.13 0.30 - - - 92.50 *92.50% Very Satisfactory
6 Jewels Construction
CY 2017 Basic Educational Facilities Fund (Batch 4),
Construction of 2 units Unique Workshop (7 x 22.5) at
Gulod Senior High School
06/20/2018Batangas
2nd DEO5.314 115 C 0.49 0.13 0.30 - - - 92.60 92.60% Very Satisfactory
6 Jewels Construction 34737
MFO 1 - National Road Network Services, Network
Development Off-Carriageway Improvement including
Drainage, Secondary Roads Batangas Quezon Road,
K0134+(-664) - K0134+(-414), K0134+100 - K0134+407,
Batangas City, Batangas
08/25/2017Batangas
2nd DEO5.287 45 C 0.48 0.13 0.30 - - - 91.60 *91.6% Very Satisfactory
626 Construction & Trading, Inc. 34990Rehabilitation & Improvement of Bustos Dam and Picnic
Grounds09/27/2018 TIEZA 7.500 90 O 0.38 0.30 0.13 0.03 0.06 0.05 95.30 - On - Going
626 Construction & Trading, Inc. 34990 Improvement of Hot and Cold Spring Resort 10/09/2015 TIEZA 12.000 240 O 0.395 0.300 0.103 0.030 0.047 0.050 92.49 - On-going
626 Construction & Trading, Inc. 34990 Improvement of Balungao Hot and Cold Spring Resort 05/27/2015 TIEZA 11.800 180 O 0.397 0.299 0 0.030 0.045 0.017 78.74 Ongoing
722 Construction, Inc.(Formerly:
722 Construction)21923
Repair/Rehabilitation/Improvement along Baliuag-
Candaba Road K0054+000 to K0057+00011/24/2014 III 12.104 72 O 0.295 0.240 0.150 0.030 0.037 0.033 78.50% - On-going
739 Builders 31174
Barbar Small River Irrigation Project, Package 9 -
Construction of Main Canal Nagsupotan (Canalization,
Sta. 3+000 - 5+000)
10/26/2019 NIA 10.764 270 O 0.39 0.18 0.13 0.03 0.05 0.05 82.30 - On-going
739 Builders 31174Barbar Small River Irrigation Project, Package 11 -
Construction of Slope Protection Works at Diversion10/26/2019 NIA 15.134 270 O 0.31 0.24 0.13 0.03 0.05 0.05 81.00 - On-going
739 Builders 31174Provision of Techvoc Workshop Buildings/Laboratories
for Senior High School, Narvacan NCHS06/04/2017
Ilocos Sur
2nd District
Engineering
Office
2.307 85 C 0.48 0.20 0.24 - - - 92.30 *92.3% Very Satisfactory
739 Builders 31174Construction of Drainage Canal, Vigan-Sta. Catalina
Road, K0407+405-K0408+28808/17/2017
Ilocos Sur 1st
DEO11.177 120 C 0.49 0.17 0.23 - - - 88.80 *88.8% Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 5 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
739 Builders 31174
Provision of Techvoc Workshop Building/Laboratories for
Senior High School, Narvacan National High School,
Narvacan, Ilocos Sur
03/18/2017Ilocos Sur
2nd DEO2.306 115 O 0.225 0.300 0.051 0.03 0.052 0.033 69.10 - On-going
739 Builders / Arthit Corporation31174 /
40667
Upgrading and Improvement of Sta. Lucia - Nagrebcan -
Ronda Road10/09/2018
Provincial
Government
of Ilocos Sur
44.784 211 O 0.40 0.30 0.15 0.03 0.07 0.05 100.00 - On - Going
739 Builders / Arthit Corporation
(JV)
31174 /
40667 -
SN1-SN-
16780
Barbar Small River Irrigation Project, Package 10 -
Construction of Lateral D & Lateral E (Canalization Sta.
0+008.00 to Sta. 1+490.00) L=1,481.20 l.m.
10/26/2019 NIA 10.297 240 O 0.38 0.18 0.13 0.03 0.05 0.05 82.20 - On-going
739 Builders / Arthit Corporation
(JV)
31174 /
40667 -
SN1-SN-
16780
Barbar Small River Irrigation Project, Package 12 -
Construction of Re-Road Surfacing of Access Road at
Sta. 0+000 - 5+179.14
10/26/2019 NIA 10.791 240 O 0.38 0.18 0.12 0.03 0.06 0.05 81.20 - On-going
811 Trading & Construction 21215Construction of Two (2) Storey, Four Classroom Building
for Punong NHS, Sta. Cruz, Marinduque08/25/2017
Marinduque
DEO7.115 262 C 0.47 0.20 0.15 - - - 82.70 *82.7% Satisfactory
811 Trading & Construction 21215
Construction of 2 Storey/ 8 Classrooms at Doroteo S.
Mendoza SR Memorial National High School, Naujan,
Oriental Mindoro
08/17/2017Mindoro
Oriental DEO10.769 210 C 0.49 0.20 0.00 - - - 68.80 *68.8% Poor
811 Trading & Construction 21215
Construction of 2 Storey/8 Classrooms at Doroteo S.
Mendoza, Sr., Memorial National High School, Naujan,
Oriental Mindoro
11/17/2016Mindoro
Oriental DEO10.821 150 O 0.349 0.3 0.109 0.03 0.058 0.033 0.8790 - On-going
811 Trading & Construction/ Great
Lakes Enterprises, Joint Venture
JV-15-
1249
Construction of Wawa Seawall, Calapan City, Oriental
Mindoro08/26/2016
Mindoro
Oriental DEO18.576 181 O 0.382 0.2 0.3 0 0 0 0.8820 - On-going
876 Construction 24224Paving of Shoulder with Drainage and Slope Protection,
Calapan North Road (CNR)08/26/2016
Mindoro
Oriental DEO1.293 75 O 0.455 0.158 0.3 0 0 0 0.9130 - On-going
888 Acy Enterprises 32898
Cluster-Road Widening along Daang Maharlika
(S00223LT), K1024+443-K1024+699, K1024+721-
K1025+607
11/06/2017 DPWH 33.567 240 O 0.344 0.254 0.112 0.03 0.056 0.033 82.90 - On-going
888 Acy Enterprises 32898
Off-Carriageway Improvement Along Jct. Taft-Oras-San
Policarpio-Arteche Road (S00167SM) K0939+500-
K0940+744; K0942+280-K0943+344, K0943+432-
K0944+1087, Eastern Samar
08/15/2017Eastern
Samar DEO39.857 210 O 0.364 0.300 0.150 0.03 0.012 0.033 88.90 - On-going
888 Acy Enterprises 32898
Rehab./Major Repair of Permanent Bridges, Canlawis
Bridge along Lilo-an-San Ricardo Road (B00368LT),
Pintuyan, Southern Leyte
03/30/2017Southern
Leyte DEO19.585 247 C 0.41 0.13 0.30 - - - 84.50 *84.5% Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 6 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
888 Acy Enterprises 32898
Rehab./Major Repair of Permanent Dinahugan Bridge
along Bdry. So. Leyte-Maasin-Macrohon-Sogod-Daang
Maharlika (B003011LT)
06/26/2016Southern
Leyte DEO19.148 202 O 0.367 0.24 0.15 0.03 0.056 0.05 89.30% - On-going
888 Acy Enterprises 32898
Rehab/Major Repair of Permanent Bridges, Pandan
Bridge, Along Brdy, S. leyte-Maasin-Macrohon-Sogod-
Daang Maharlika
06/03/2015Southern
Leyte DEO8.812 150 O 0.4 0.24 0.15 0.03 0.052 0.033 90.50% - On-going
888 Acy Enterprises 32898
Off-Carriageway Improvement along Taft - Oras - San
Policarpio - Arteche Road, K0939+500 - K0940+744,
K0942+280 - K0943+344, K0943+432 - K0944+490,
K0944+672 - K0944+1087
04/10/2018Eastern
Samar DEO39.857 210 C 0.48 0.19 0.30 - - - 96.70 91.48% Very Satisfactory
888 Acy Enterprises 32898Road Widening along Daang Maharlika, K1024+443-
K1024+699.00; K1024+721-K1025+607.00004/09/2018
Southern
Leyte DEO33.567 240 C 0.48 0.13 0.30 - - - 91.50 *91.50% Very Satisfactory
8G Construction And General
Services35783
Rehabilitation/Improvement of Farm to Market Road at
Jandalamanon, Kilaban, Gomentoc and Candanaay,
Ayungon, Negros Oriental
03/11/2016
Negros
Oriental First
DEO
3.7437 50 C 0.44 0.13 0.30 0.00 0.00 0.00 86.80% 86.80% Satisfactory
8R'S Construction 22997
Rehabilitation/ Reconstruction/ Upgrading of Damaged
Paved National Rd. including Drainage (Marinduque
Circumferencial Road), K0004+000-K0004+600,
K0005+300-K0005+486, and K0005+670-K0005+832,
Boac-Mogpog, Marinduque
08/27/2016Marinduque
DEO26.202 257 O 0.347 0.259 0.15 0.03 0.025 0.033 0.8440 - On-going
969 Construction & Supplies 35818 Barangay San Roque, Delfin Albano, Isabela 06/02/2017Isabela 1st
DEO1.410 91 C 0.44 0.14 0.30 - - - 88.00 *88% Satisfactory
A B Aponesto Construction, Parts &
Supply22998
Repair/Rehab of Agusan River Flood Control, Osmena
Section, Compostela along Montevista – Compostela –
New Bataan – Maragusan – Mati Bdry. Road.
08/09/2014 XI 30.533 183 O 0.384 0.219 0.123 0.030 0.042 0.033 83.10 - On-going
A De Guia Construction 18228Construction of River Bank Protection, Siffu Flood
Control Project, Sittio Gabit Section, Roxas, Isabela08/28/2015
Isabela 2nd
DEO18.346 215 O 0.354 0.3 0.15 0.03 0.04 0.05 92.40% - On-going
A J Taylan Construction &
Development/Jlp Construction &
Supply Joint Venture
JV-14-518
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including Drainage Based on
Pavement Management System/Highway Development
and Management- 4(HDM-4), Pinili-Nueva Era Road,
K0453+(-224)-K0454+1013, K0455+884-K0456+433,
Pinili Road, Ilocos Norte
08/26/2015Ilocos Sur
2nd DEO37.519 219 O 0.355 0.209 0.15 0.03 0.051 0.05 84.50% - On-going
A. B. Taylan Construction &
Development / North Tech Builders
And Construction Supply Joint
Venture
JV-14-115
MFO-1 National Road Network Services: Network
Development: Widening of National Roads (Arterial)-
along N1, Bangag-Magapit Road, K0686+(-512) -
K0687+980, Bangag-Magapit, Allacapan, Cagayan
06/01/2017Regional
Office No. II74.138 294 C 0.45 0.13 0.30 - - - 88.60 *88.6% Satisfactory
A. C. Rivero Development
Corporation5122 Concreting of Brgy. San Miguel - Brgy. Cantandoy FMR 09/18/2019 DA 4.722 60 O 0.37 0.30 0.15 0.03 0.04 0.05 94.40 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 7 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A. C. Rivero Development
Corporation5122
Replacement/ Raising of PHHC Bridge (S00130NR)
along Bacolod Circumferential Road, Bacolod City11/16/2017 DPWH 19.600 255 O 0.391 0.240 0.150 0.03 0.04 0.05 90.10 - On-going
A. C. Soliven Construction *
General Merchandise19278
Rehabilitation/ Improvement of Existing Dike along
Lucung River, Upstream of Sta. Maria Section, Left Side,
Sta. (-)2+050 to Sta. (-)2+132 and Sta. (-)2+200 to Sta. (-
)2+619.60, Concepcion, Tarlac
08/20/2017Tarlac 2nd
DEO37.231 147 C 0.42 0.13 0.30 - - - 85.40 *85.4% Satisfactory
A. D. Pendon Construction &
Supply, Inc. (Formerly: A. D. P.
Construction & Supply)
3466
Asset Preservation of National Roads Preventive
Maintenance - Asset Preservation of National Roads -
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads Including Drainage, Odiong -
Sibalom - San Remigio - Leon Road, San Remigio, Antiq
06/09/2016ANTIQUE
DEO29.476 223 O 0.23 0.291 0.121 0.008 0.022 0 67.20% - On-going
A. D. Pendon Construction &
Supply, Inc. (Formerly: A. D. P.
Construction & Supply)
3466
Rehabilitation/ Reconstruction/ Upgrading of Damaged
Paved National Roads including Drainage, Iloilo-Capiz
Road (Pavia Diversion), K0010+449 to K0010+824.30,
Iloilo
11/16/2016ILOILO 4TH
DEO7.258 170 O 0.341 0.24 0.15 0.03 0.05 0.05 0.8610 - On-going
A. D. Pendon Construction &
Supply, Inc. (Formerly: A. D. P.
Construction & Supply)
3466Upgrading of Delgado St. K0001+(-402)-K0001+(-100),
K0001+(-100)-K0001+080, Iloilo City09/01/2016 ILOILO DEO 22.611 22.611 O 0.275 0.3 0.05 0.03 0.058 0 0.7130 - On-going
A. De Guia Construction 18228
Construction/ Rehabilitation of Flood Control Projects,
Nagassican Flood Control Projects, Sta. 0+000 to Sta.
0+224
08/12/2014 II 19.500 184 O 0.288 0.248 0.150 0.030 0.055 0.050 82.10 - On-going
A. De Guia Construction 18228
Construction of Drainage System / Protection Works
along Daang Maharlika, Isabela 4th LD K0311+590 -
K0314+350, San Luis - Caquilingan
10/27/2014 II 19.403 231 O 0.347 0.300 0.150 0.030 0.029 0.033 88.90% - On-going
A. De Guia Construction 18228Concreting of San Pablo-Salvacion Road, Barangay San
Pablo Alicia, Isabela11/11/2017 DPWH 6.930 122 C 0.47 0.13 0.30 - - - 90.30 *90.3% Very Satisfactory
A. De Guia Construction 18228
Network Development - Improvement/ Widening of
National Roads Primary Roads - Other Primary Roads
along National Roads along Santiago - Tuguegarao
Road, K0369+000 - K0371+000, K0373+000 -
K0374+000, K0374+947 - K0376+000, Aurora and San
Miguel, Isabela
08/19/2017Isabela 2nd
DEO91.157 251 O 0.381 0.240 0.150 0.03 0.07 0.033 90.40 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 8 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A. De Guia Construction 18228
MFO 1 - National Road Network Services: Network
Development: Improvement/Widening of National Roads,
Primary Roads along N1 Daang Maharlika (LZ) -
K0382+977-K0383+450 L/S, K0383+830-K0386+182
L/S, K0386+291-K0387+215 L/S, K0382+977-
K0383+450 R/S, K0383+83
06/15/2016Regional
Office79.349 248 O 0.393 0.24 0.15 0.03 0.047 0.05 91.00% - On-going
A. De Guia Construction 18228
Network Development-Improvement/Widening of
National Roads-Primary Roads-Other Primary Roads
along National Roads along Santiago-Tuguegarao Road,
K0369+000-K0371+000, K0373+000-K0374+000 &
K0374+947-K0376+000
04/09/2018Isabela 2nd
DEO91.157 281 C 0.36 0.20 0.30 - - - 86.30 91.40% Very Satisfactory
A. De Guia Construction 18228
Network Development, Improvement/Widening of
National Roads, Santiago-Tuguegarao Road, K0342+(-
039)-K0343+884, Oscar, Ramon
03/20/2018Isabela 3rd
DEO45.847 179 C 0.46 0.18 0.30 - - - 93.70 *93.70% Very Satisfactory
A. Dela Cruz Builders Inc. 38836Construction of Multi-Purpose Building at Dona Aurora
Elementary School, Brgy. Doña Aurora, Quezon City03/17/2018
Quezon City
2nd DEO14.724 250 C 0.49 0.13 0.30 - - - 92.20 *92.20% Very Satisfactory
A. J. Lava Builders Corp. (Formerly:
A. J. Lava Builders)22265
Flood Management Services Construction/Maintenance
of Flood Mitigation Structures and Drainage System
Improvement/Riprapping of Sitio Kapatagan River
(Downstream), Brgy. San Jose, Antipolo City, 2nd LD
11/11/2015RIZAL 1ST
DEO27.612 180 O 0.39 0.24 0.15 0.03 0.06 0.05 92.00% - On-going
A. J. Taylan Construction
Corporation2336
Laoag River Basin Flood and Sabo Project, Concrete
Revetment along Bongo River, Brgy. Sta Monica, Sitio 2,
San Nicolas, Ilocos Norte
03/09/2016
ILOCOS
NORTE 2ND
DEO
9.649 194 C 0.42 0.20 0.30 - - - 91.10% 91.10% Very Satisfactory
A. M. Oreta and Co., Incorporated 108 Region 2-PIDP-CBIMO 09/19/2015 NIA 80.788 690 O 0.370 0.300 0.130 0.030 0.060 0.050 94.00 - On-going
A. M. P. Construction 16574Construction of Flood Control Wall along Agbalili River,
Altavas, Aklan08/28/2016 AKLAN DEO 34.428 34.428 O 0.388 0.3 0.003 0.03 0.058 0 0.7790 - On-going
A. M. P. Construction 16574Construction of Flood Control Revetment Wall along
Agbalili River, Altavas, Aklan06/11/2016 AKLAN DEO 34.428 274 O 0.385 0.3 0.104 0.023 0.055 0.033 90.00% - On-going
A. M. P. Construction/ Forthright
Construction Joint Venture
JV-16-
1612
Construction/ Maintenance of Flood Mitigation Structures
and Drainage System, Rehabilitation/ Improvement of
Pampanga River Control, Brgy. Sapang Buho, Palayan
City, Nueva Ecija
08/23/2017Nueva Ecija
2nd DEO39.200 161 O 0.309 0.300 0.150 0.02 0.042 0.05 87.10 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 9 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A. P. B. Construction 17055
Network Development/ Widening of National Roads-
Secondary Road-Abra-Ilocos Norte Road K0409+000-
K0409+100, K0409+115-K409+178, K0409+307-
K0409+404, K0409+531-K0409+648, K0409+748-
K0410+139, K0410+159-K0410+360, K0410+369-
K0410+777, K0411+050-K0411+220, K0412+122-
K0412+499, K0413+000-K0414+354, K0414+764-
K0415+747, K0416+175-K0416+445, K041
11/20/2015Regional
Office81.971 286 O 0.318 0.29 0.15 0.022 0.045 0.033 85.80% - On-going
A. P. Consebido Construction And
Trading33616
Construction of Barangay Road, Barangay Dumarao,
Sta. 00+012.70-Sta. 0+149.00, Roxas, Palawan03/10/2016
Palawan First
DEO1.9478 100 C 0.43 0.20 0.27 - - - 89.90% 89.90% Very Satisfactory
A. P. D. Construction 17467
Retrofitting/Strengthening of Disiluad Br. (B01939LZ)
along Cordon-Aurora Boundary Road (Isabela Boundary -
Jct. Dumabato)
03/17/2016 Quirino 29.4724 180 C 0.49 0.13 0.30 - - - 91.90% 91.90% Very Satisfactory
A. R. Lustre Jr. Construction 7680
Construction of Multi-Purpose Building, Barangay Sta.
Monica, Inagawan Sub. And San Miguel, Puerto
Princesa City
03/11/2016Palawan 3rd
DEO1.9142 156 C 0.48 0.18 0.30 - - - 96.00% 96% Very Satisfactory
A. Y. U. Engineering And
Construction25632
Road Concreting, Bato to Likate Road, Brgy. Bato and
Kilate, Toril, Davao City09/02/2016
Davao City
2nd DEO9.800 105 C 0.48 0.13 0.30 - - - 0.9160 88.30% Satisfactory
A.B Taylan Construction &
Development 25273
Netwrork Development, Improvement of National Roads
along Manila North Road, K0508+050-K0508+125;
K0508+140-K0508+250; K0508+329; K0508+410-
K0509+755; K0509+760-K0510+501; K0519+000-
K0520+200; K0521+000-K0522+500; K0522+500-
K0523+060
11/08/2017 DPWH 144.750 255 C 0.47 0.13 0.30 - - - 90.60 *90.6% Very Satisfactory
A.B. Opena BuildersConcreting of Barangay Road, Purok 13,, Sanitarium
Compound, Brgy. San Pedro 06/02/2018
Camarines
Sur 5th DEO1.880 60 C 0.46 0.13 0.30 - - - 89.50 89.50% Very Satisfactory
A.B. Opeña Builders 33996Construction of Multi-Purpose Building at Colacling
National High School11/15/2017 DPWH 0.955 60 C 0.49 0.13 0.30 - - - 92.10 *92.1% Very Satisfactory
A.B. Opeña Builders 33996Concreting of Barangay Road at Brgy. Mabini, Del
Gallego, Camarines Sur 06/01/2017
Camarines
Sur 5th DEO1.410 40 C 0.44 0.13 0.30 - - - 87.70 *87.7% Satisfactory
A.B. Opeña Builders 33996Concreting of Barangay Road, Barangay Sta. Cruz,
Cabusao, Camarine Sur08/16/2017
Camarines
Sur 5th DEO1.881 45 O 0.489 0.134 0.300 - - - 92.30 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 10 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.B. Taylan Construction &
Development28233
Improvement/Widening of National Road along N1,
Manila North Roads, K0494+396-K0495+024;
K0496+164-K0496+423; K0496+775-K0497+444;
K0497+834-K0498+000; K0499+200-K0500+676;
K0500+676-K0500+698; K0500+676-K0500+756;
K0503+380-K0506+084; K0503+380-K0506+048,
Bacarra, Ilocos Norte
11/16/2016Regional
Office No. I146.250 325 O 0.49 0.133 0.3 0 0 0 0.9230 - On-going
A.B. Taylan Construction &
Development/ Badoc Builders &
Supply Joint Venture
JV-16-621Construction of Final Mitigation Structure along Badoc
River, U/S and D/S of Badoc Bridge08/16/2017
Ilocos Norte
2nd DEO44.100 225 C 0.46 0.20 0.30 - - - 95.70 *92.4% Very Satisfactory
A.B. Taylan Construction &
Development/ Badoc Builders &
Supply Joint Venture
JV-15-404
Road Upgrading (Unpaved to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standards (HDM-4) along Batac-Pinili via
Maipalig Road (S04765LZ)
08/17/2017Regional
Office No. I146.249 300 C 0.49 0.15 0.29 - - - 92.80 *92.8% Very Satisfactory
A.C Rivero Development
Corporation5122
Upgrading of Drainage System Along El Dorado Street,
Barangay Bosco, District II11/21/2017 DPWH 14.035 261 O 0.376 0.300 0.079 0.03 0.056 0.033 87.40 - On-going
A.C Rivero Development
Corporation5122
Rehabilitation/Reconstruction of Proposed Slope
Protection along Sta. Felomina-Bonbonon-Digkilaan-
Rogongon Road K1526+000-K1526+200 R/S
11/14/2017 DPWH 33.582 193 C 0.45 0.18 0.30 - - - 92.30 *92.3% Very Satisfactory
A.C Soliven Construction & General
Merchandise19278
Agno River Basin & Allied Rivers Flood Control Project -
Heightening of Villasis-Alacala Earth Dike Phase I, Agno
River Control
11/14/2017 DPWH 44.687 220 C 0.44 0.13 0.30 - - - 87.10 *87.1% Satisfactory
A.C Soliven Construction & General
Merchandise19278
Flood Management Services: Construction/ Maintenance
of Flood Mitigation Structures and Drainage System,
Construction of Flood Control Facilities at Paranum
Creek, Sta. 0+000 - Sta. 0+110 and Sta. 0+390 - Sta.
1+170, (L/S), Brgy. Camias, Magalang, Pampanga
06/08/2017Pampanga
3rd DEO17.784 150 O 0.370 0.242 0.150 0.03 0.065 0.033 89.00 - On-going
A.C Soliven Construction & General
Merchandise19278
Flood Management Services: Construction/ Maintenance
of Flood Mitigation Structures and Drainage System;
Construction of Flood Facilities at Paranum Creek,
Barangay Camias, Sta. 0+000 to Sta. 0+110, Magalang,
Pampanga
08/19/2017Pampanga
3rd DEO17.784 150 C 0.39 0.20 0.30 - - - 89.10 *89.04% Very Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 11 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.C Soliven Construction & General
Merchandise19278
Construction/Maintenance of Flood Mitigation Structure &
Drainage Systems - Agno River Basin Flood Control
Project-Extension/ Construction of Bank Protection of
River Course, Brgy. Mabanogbog, Namcamaliran
Pinmaludpod, Urdaneta City, Pangasinan
11/25/2016Pangasinan
3rd DEO34.299 250 O 0.4 0.3 0.15 0.03 0.035 0.025 0.9400 - On-going
A.C Soliven Construction & General
Merchandise19278
Construction/Maintenance of Flood Mitigation Structures
& Drainage Systems - Agno River Basin Flood Control
Project - Extension/Construction of Bank Protection of
River Course, Brgy. Mabanogbog, Nancamairan,
Pinmalupod, Urdaneta City, Pangasinan
03/23/2017Pangasinan
3rd DEO34.299 250 O 0.400 0.300 0.060 0.03 0.04 - 83.00 - On-going
A.C Soliven Construction & General
Merchandise19278
Construction of Bank Protection Works, Agnooo River
Basin Flood Control Project (Phase III) Brgy. Bantog,
Asingan, Pangasinan
11/16/2015PANGASINA
N 3RD DEO18.336 180 O 0.389 0.24 0.15 0.03 0.055 0.05 91.40% - On-going
A.C Soliven Construction & General
Merchandise19278
Construction of Bank Protection, Agno River Basin Flood
Control Project (Phase III), Barangay Bantog, Asingan,
Pangasinan
03/18/2016PANGASINA
N 3RD DEO18.335 180 C 0.41 0.20 0.30 - - - 91.28% 91.28% Very Satisfactory
A.C Soliven Construction & General
Merchandise19278
Construction/Rehabilitation of Drainage along National
Roads, Villasis-Malassiqui-San Carlos Road, K0190+785-
K0192+800 with Exception (B/S), Malasiqui, Pangasinan
03/15/2016PANGASINA
N 4TH DEO34.3 226 C 0.36 0.20 0.30 - - - 86.20% 86.20% Satisfactory
A.C. Mojares Construction, Inc. 1771Concreting and Sidewalk Improvement of Phase 2, Scout
Tobias St., Brgy. Laging Handa, Quezon City06/03/2014
Quezon City
2nd DEO10.018 207 O 0.394 0.24 0.15 0.015 0.028 0.05 87.70% - On-going
A.C. Rivero Development
Corporation
Construction of Drainage Structure along Road - Bdry.
So. Leyte - Maasin- Macrohon - Sogod - Jct. - Maharlika
(S00194LT) K1149+000 - K1152+000
05/29/2018Southern
Leyte DEO48.020 330 C 0.45 0.13 0.30 - - - 88.50 88.50% Satisfactory
A.C. Rivero Development
Corporation
Local Roads and Bridges - Local Roads - Local
Infrastructure Program / Concreting og Brgy. Road,
Batuan - San Isidro
05/29/2018Southern
Leyte DEO9.296 180 O 0.39 0.24 0.15 0.03 0.05 0.03 88.80 - On-going
A.C. Rivero Development
Corporation
Road Upgrading (Unpaved to Paved) of Quezon-
Aramaywan Road K)158+KO665-K158+749,
KO158+749-KO158+849 and KO172+635-KO175+005
06/02/2018Palawan 2nd
DEO74.758 225 O 0.35 0.22 0.15 0.02 0.05 0.05 84.10 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Rehabilitation/ Reconstruction of National Roads with
Slips, Slope Collapse and Landslide along Tomas Oppus
Street
06/03/2017Southern
Leyte DEO27.915 260 C 0.50 0.13 0.30 - - - 93.20 *93.2% Very Satisfactory
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
CY 2016 Basic Education Facilities Fund (BEFF),
Provision of Tech Voc. Laboratores, Batch 12, Merida
Vocation School, Merida, Leyte
04/01/2017Leyte 4th
Deo2.556 90 C 0.46 0.13 0.30 - - - 89.50 *89.5% Very Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 12 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Indv. Project - Concreting of Monte-Calvario-Igbac-
Barangay Road, Brgy. Monte-Calvario and Igbac11/16/2017 DPWH 9.860 83 C 0.48 0.13 0.30 - - - 91.60 *91.6% Very Satisfactory
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Off-Carriageway Improvement including Drainage along
Liloan-San Ricardo Road (S00218LT), K1070+685 to
K1072+000
11/06/2017 DPWH 45.307 270 O 0.368 0.239 0.150 0.03 0.065 0.05 90.20 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Replacement of PHHC Bridge along Bacolod
Circumferential Road06/06/2017 Bacolod City 34.299 330 O 0.373 0.200 0.029 0.03 0.058 0.033 72.33 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Replacement of PHHC Bridge along Bacolod
Circumferential Road, Bacolod City08/23/2017 Bacolod City 34.299 330 C 0.49 0.13 0.00 - - - 62.40 *68.34% Poor
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
MFO-1: National Road Network Services Off-
Carriageway Improvement including Drainage-
Secondary Roads Flaring of Intersection along Carrmen-
Patag-Bulua Road K1440+(-272) and K1441+370
03/16/2018
Cagayan de
Oro City 1st
DEO
9.221 195 C 0.48 0.20 0.12 - - - 79.70 *79.70% Unsatisfactory
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Road Upgrading (Unpaved to Paved) Based on Gravel
Road Strategies Traffic Benchmark for Upgrading to
Paved Road Standards (HDM-4 Project Analysis) along
Sta. Felomina-Bonbonon-Digkilaan-Rogongon Road
03/22/2018
Lanao del
Norte 2nd
DEO
33.269 202 C 0.49 0.13 0.30 - - - 92.50 *92.50% Very Satisfactory
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Construction and Maintenance of Bridges along National
Roads (Replacement of Weak Bridge) at Olingan Bridge03/15/2017
Zamboanga
del Norte 1st
DEO
21.622 355 C 0.46 0.20 0.15 - - - 81.00 *81% Unsatisfactory
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Upgrading/Conc. of San Juanico-Basey-Sohoton Rd.,
K0913+721.75-K0917+915.72, w/ exceptions08/07/2012 VIII 47.065 200 O 0.357 0.240 0.150 0.030 0.040 0.033 85.00 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Const./Completion of Subang Daku Bridge, Subang
Daku River, San Miguel08/17/2012 VIII 42.820 220 O 0.383 0.300 0.150 0.030 0.040 0.033 93.60 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Const./Impv't. of San Miguel-Jct. Buac Rd., Daang
Maharlika Rd (Km1207+000 - Km1209+454.40)08/19/2012 VIII 35.731 220 O 0.349 0.289 0.150 0.030 0.045 0.033 89.60 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Const./Completion of Maasin Flood Control along Tomas
Oppus Street (Road ID S00222LT)06/26/2016
Southern
Leyte DEO25.281 180 O 0.32 0.3 0.15 0.03 0.056 0.05 90.60% - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Widening of Permanent Bridges from 1 Lane to 2 Lanes
Malatgao Bridge (B00168PW) along Quezon, Punta,
Baja Rd., Quezon, Palawan
11/22/2016Palawan
Second DEO18.408 220 O 0.388 0.176 0.15 0.03 0.04 0.05 0.8340 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 13 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Completion of Dodiongan Bridge along Sta. Felomina-
Bonbonon-Digkilaan-Rogongon Road, Brgy. Bonbonon,
Iligan City K01526+058-K01526+118, K01526+910-
K01526+297
09/03/2015
Lanao del
Norte 2nd
DEO
37.105 236 O 0.384 0.285 0.15 0.02 0.045 0.05 93.40% - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122Off-Carriageway Improvement along Jct. Taft - Oras -
San Policarpio-Arteche Road, K0950+000 - K0955+00006/29/2015
Eastern
Samar DEO33.355 150 O 0.297 0.3 0.15 0.03 0.04 0.033 85.00% - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Replacement of Permanent Weak Bridge, Ramon
Magsaysay Bridge (B00469MN) Along Jct. Switch-Jct.
Monte Alegre Road
08/30/2016
Zamboanga
del Sur 1st
DEO
29.101 290 C 0.47 0.13 0.30 - - - 90% 88.07% Satisfactory
A.C. RIVERO DEVELOPMENT
CORPORATION (Formerly: A.C.
Rivero Construction)
5122
Replacement of Permanent Weak Bridge, Ramon
Magsaysay Bridge (B0469MN) along Jct. Switch-
Jct.Monte Alegre Road
08/29/2015Zamboanga
del Sur 1st29.101 230 O 0.288 0.299 0.15 0.03 0.051 0.05 86.79% - On-going
A.C. RIVERO DEVELOPMENT
CORPORATION (Formerly: A.C.
Rivero Construction)
5122
Construction and Maintenance of Bridges along National
Roads - (Widening of Permanent Bridges to more than 2
lanes), Miputak Bridge (BO1192MN) along Dipolog-
Oroquieta National Road
06/11/2016
Zamboanga
del Norte 1st
DEO
22.574 250 O 0.388 0.24 0.12 0.03 0.04 0.033 85.10% - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Construction and Maintenance of Bridges along National
Roads (Replacement of Permanent Weak Bridge),
Olingan Bridge (B01193MN)
08/25/2016
Zamboanga
del Norte 1st
DEO
21.559 340 O 0.38 0.24 0.105 0.03 0.045 0.017 0.8170 - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Construction and Maintenance of Bridges along National
Rd. (Replacement of Permanent Weak Bridge) at
Olingan Bridge along Dipolog-Oroquieta National Road,
Olingan, Dipolog City, Zamboanga del Norte
11/16/2015
Zamboanga
Del Norte 1st
DEO
21.218 220 O 0.371 0.22 0.15 0.022 0.042 0.05 85.50% - On-going
A.C. Rivero Development
Corporation (Formerly: A.C. Rivero
Construction)
5122
Construction/ Maintenance of Flood Control Mitigation
Structure and Drainage, Construction of Sibugay Flood
Control Brgy. Poblacion, Albuera, Leyte
08/22/2017Leyte 4th
DEO9.299 90 C 0.40 0.20 0.30 - - - 90.30 *90.3% Very Satisfactory
A.C. Rivero Development
Corporation / Jqd Construction And
General Services Joint Venture
JV-14-
1038
Rehabilitation/Major Repair of Permanent Weak Bridges,
Otikon Bridge Along Daang Maharlika (B00598LT),
Libagon, Southern Leyte
11/16/2015Southern
Leyte DEO31.056 195 O 0.249 0.3 0.15 0.03 0.06 0.05 83.90% - On-going
A.C. Rivero Development
Corporation / Jqd Construction And
General Services Joint Venture
0
Rehabilitation/Major Repair of Permanent Weak Bridge,
Otikon Bridge along Daang Maharlika, Libagon, Southern
Leyte
03/07/2016Southern
Leyte31.056 195 C 0.45 0.19 0.30 - - - 88.10% 88.10% Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 14 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Construction of Drainage along Mandurriao-Jaro
Road,K0006+100-K0007+082, K0007+082, Mandurriao,
Iloilo City
08/24/2017Iloilo City
DEO38.376 191 O 0.392 0.200 0.150 0.022 0.037 0.05 85.10 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466Const. of Slope Protection along Jct. Bancal-Leon-
Antique Boundary Rd., K0031+722-K0031+89103/22/2013 VI 13.802 188 O 0.388 0.241 0.150 0.030 0.055 0.050 91.40 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466 Construction of Multi-Purpose Building 10/28/2014 VI 4.227 120 O 0.362 0.214 0.121 0.030 0.049 0.050 82.60% - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466Construction/Rehab. Of Drainage System along Balasan-
Carles Road, Brgy. Barosbos10/29/2014 VI 43.954 274 O 0.373 0.218 0.150 0.030 0.054 0.050 87.50% - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Road Upgrading (Gravel to Paved) along Davao-
Sarangani Coastal Road km. 1671+600 to km.
1673+060, Biton-Lanao Section
08/07/2014 XI 40.082 208 O 0.014 0.300 0.000 0.030 0.014 0.000 35.80 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Rd. Upgrading (Gravel to Paved) along Davao-Sarangani
Coastal Rd., Km.1671+600-Km.1673+060, Biton-Lanao
Sect.
08/06/2013 XI 40.082 179 O 0.322 0.248 0.000 0.030 0.033 0.033 66.60 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Malag-it Box Culvert along Iloilo East Coast-Capiz Road
(Construction of Malag-it Bridge along Iloilo East Coast-
Capiz Road)
10/29/2014 VI 35.132 240 O 0.388 0.249 0.000 0.030 0.054 0.033 75.40% - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466Widening of Caradio-an Bridge alog Bacolod South
Road, Barangay Caradio-an10/23/2014 VI 24.804 273 O 0.378 0.221 0.034 0.030 0.045 0.033 74.10% - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466 Impvt./Conc. of Access Road, Tubalan Port, Tubalan 06/14/2010 XI 58.261 320 O 0.338 0.300 0.000 0.030 0.040 0.033 74.10 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Rehab./Reconst./Upgrading of Damaged Paved National
Road, Roxas City Boundary-Panitan Road-Jct. Bailan
Road, Capiz (KM.112+750-Km.122+705) with exception
08/31/2010 VI 53.673 225 O 0.364 0.240 0.150 0.030 0.051 0.050 88.50 - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466Construction of Drainage System along Iloilo East Coast
Capiz Road06/09/2015
Iloilo Third
DEO44.467 252 O 0.37 0.247 0.15 0.022 0.035 0.05 87.40% - On-going
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466 Widening of Sara-San Dionisio Road 06/09/2015Iloilo Third
DEO26.054 175 O 0.344 0.252 0.15 0.022 0.035 0.05 85.30% - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 15 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.D. Pendon Construction &
Supply, Inc. (Formerly: Adp
Construction & Supply
3466
Network Development, Widening of National Road,
Secondary Road along Roxas City, Cagay-Sibaguan
Balijuangan-Cudian-Ijisan Road
06/06/2015Capiz First
DEO10.341 121 O 0.368 0.251 0.105 0.03 0.035 0.033 82.20% - On-going
A.D.L. Constrak 26442
Concreting of Ipil-Sagana Bridge Approaches "A" and "B"
and Sta. Cruz Road, Brgy. Ipil and Sagan and Sta. Cruz,
Bongabong, Oriental Mindoro
08/24/2016Southern
Mindoro DEO3.290 35 O 0.424 0.164 0.3 0 0 0 0.8880 - On-going
A.D.L. Constrak 26442Rehabilitation/Reconstruction of Paclasan Seawall,
Roxas, Oriental Mindoro03/18/2017
Southern
Mindoro DEO3.627 67 O 0.438 0.200 0.300 - - - 93.80 - On-going
A.F.G Construction & Construction
Supply17161
Construction of Standard One (1) Unit - 2 Sty 10-CL
School Building, Eustacio Lopez NHS, Silay City,
Negros Occidental
03/22/2017
Negros
Occidental
1st DEO
17.397 235 C 0.48 0.13 0.30 - - - 90.80 *87.23% Satisfactory
A.F.G Construction & Construction
Supply17161
Repair/Imporvement of Multi Purpose Building, Barangay
Kasambagan 04/12/2018
Cebu City
DEO2.908 75 C 0.50 0.13 0.30 - - - 93.20 *93.20% Very Satisfactory
A.F.G Construction & Construction
Supply17161
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Road including Drainage Based on
Pavement Management System / Highway Development
and Management - 4 (HDM-4) (Intermittent Section)
along Hinigaran - Isabela Road, K0058+263 -
K0059+000
08/27/2015
Negros
Occidental
2nd
12.674 127 O 0.358 0.239 0.15 0.03 0.05 0.033 86.00% - On-going
A.F.G Construction & Construction
Supply17161
Concreting of Barangay Road, Brgy. Sta. Teresa,
Dumalag, Capiz11/10/2017 DPWH 9.407 97 C 0.42 0.14 0.30 - - - 85.50 *85.5% Satisfactory
A.F.G Construction & Construction
Supply17161 Const. of Tangalan-Ibajay Rd. 03/19/2013 VI 45.834 179 O 0.387 0.259 0.150 0.024 0.030 0.033 88.30 - On-going
A.F.G Construction & Construction
Supply17161
Odiong-Sibalom-San Remegio-Leon Rd. Upgrading
(Gravel to Paved), Km. 129+328-Km. 131+27508/15/2013 VI 40.453 179 O 0.336 0.240 0.150 0.030 0.037 0.033 82.60 - On-going
A.F.G Construction & Construction
Supply17161
Construction of Standard One (1) Unit - 2 Sty 10-CL
School Building at Brgy. Eustaquio Lopez NHS, Silay
City, Negros Occidental
06/16/2016
Negros
Occidental
First DEO
17.396 175 O 0.304 0.3 0.15 0.03 0.023 0.05 85.70% - On-going
A.F.G Construction & Construction
Supply17161
Const. of Two (2) Storey, Eight (8) Cl Sch. Bldg.,
Leonora Salapantan NHS08/22/2013 VI 8.949 150 O 0.347 0.200 0.108 0.030 0.032 0.033 75.00 - On-going
A.F.G Construction & Construction
Supply17161 Replacement/Const. of Tubog Bridge, Brgy. Tubog 08/15/2012 VI 7.587 180 O 0.372 0.230 0.150 0.010 0.035 0.033 83.00 - On-going
A.F.G Construction & Construction
Supply17161
Construction of 2-CL Alimanguan National High School
Brgy. Alimanguan06/05/2015
Palawan 1st
DEO1.721 120 O 0.36 0.24 0.15 0.03 0.047 0.033 86.00% - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 16 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.F.G Construction & Construction
Supply17161
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Road Including Drainage Based on
Pavement Management System/Highway Development
and Management-4 (HDM-4) (Intermittent Section) along
Hinigaran-Isabela Road, K0058+263 to
K0059+000Barangay
03/14/2016
Negros
Occidental
Second DEO
12.6742 157 C 0.45 0.13 0.30 - - - 88.40% 88.40% Satisfactory
A.F.G Construction & Construction
Supply17161
Preventive Maintenance Based on Pavement
Management System/Highway Development and
Management -4 (HDM-4) Jct Bagonawa-La Castellana-
Isabela Road, K0057+244 to K0072+800
03/14/2018
Negros
Occidental
2nd DEO
46.210 221 C 0.49 0.13 0.16 - - - 78.00 *78.00% Unsatisfactory
A.F.G. Construction And
Construction Supply/Yurich Builders
And Construction Supplu Joint
Venture
JV-15-
1239
Off-Carriageway Improvement including Drainage of
Puerto Princesa North Road, K0090+000-K0090+600,
K0091+100-K0091+350, K0095+200-K0096+246,
K0103+600-K0103+961, K0107+600-K0107+720,
Roxas, Palawan
03/13/2017Palawan 1st
DEO45.859 280 C 0.38 0.20 0.30 - - - 88.00 *89.38% Very Satisfactory
A.H. Raga Construction 36952
MFO1-National Road Network Services-Construction and
Maintenance of Bridge along National Roads-
Rehabilitation/Major Repair of Permanent Bridges-
Zapote Br. (BO2887LZ) Manila-Cavite (NCR Bdry-Jct
Cavite City Section), Bacoor City, Cavite
11/28/2017 DPWH 9.593 180 C 0.50 0.13 0.30 - - - 93.30 *93.3% Very Satisfactory
A.I.P Construction 32458
Construction/Improvement of Access Roads leading to
Declared Tourism Destinations; Guisset-Binga-Baloy-
Tinongdan Road leading to Binga Dam and Mt. Ugo, Site
for International Sky Running Event
11/08/2017 DPWH 96.500 386 O 0.376 0.240 0.150 0.03 0.056 0.05 90.20 - On-going
A.I.P Construction 32458
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including Drainage Based on
Pavement Management System/Highway Development
and Management-4 (HDM-4) (Intermittent Section), Lt.
Takay Road, K0308+(-599) to K0308+000 & K0308+616
to K0308+754, Baguio City
09/04/2015Baguio City
DEO13.442 104 O 0.36 0.228 0.15 0.03 0.056 0.05 87.40% - On-going
A.I.P. Construction
Construction/Improvement of Access Roads Leading to
Declared Tourism Destinations: Guisset-Binga-Baloy-
Tinongdan Road leading to Binga Dam and Mt. Ugo, Site
for the International Sky Running Event
05/29/2018Benguet 1st
DEO96.500 416 C 0.37 0.20 0.30 - - - 86.50 88.90% Satisfactory
A.J Taylan Construction
Corporation2336
Road Opening/Const. of Missing Links of National Road,
Solsona-Kabugao Road, Ilocos Norte Side09/09/2009 I 48.199 300 O 0.379 0.250 0.150 0.030 0.050 0.033 89.20 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 17 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.J Taylan Construction
Corporation2336
Laoag River Basin Flood and Sabo Project, Concrete
Revetment along Bongo River Brgy. Sta. Monica, Sitio 2,
San Nicolas, Ilocos Norte
11/13/2015
ILOCOS
NORTE 2ND
DEO
9.650 194 O 0.38 0.24 0.15 0.03 0.055 0.05 90.50% - On-going
A.J. Lava Builders Corp. (Formerly:
A.J. Lava Builders)22265
Repair & Maint. of Flood Control & Drainage Structures
along Rofriguez-San Jose-Quezon City Rd.11/19/2012 IVA 2.449 90 O 0.337 0.300 0.150 0.030 0.025 0.033 87.50 - On-going
A.J. Lava Builders Corp. (Formerly:
A.J. Lava Builders)22265
MFO2-Flood Management Services, Construction/
Maintenance of Flood Mitigation Structure and Drainage
Systems - Construction/ Maintenance of Flood Mitigation
Structures Drainage Systems - Construction of Flood
Control Structures along Montalban, Rizal
03/12/2018Rizal 2nd
DEO28.350 212 C 0.50 0.13 0.30 - - - 93.00 *93.00% Very Satisfactory
A.J. Lava Builders Corp. (Formerly:
A.J. Lava Builders)22265
MFO-1 National Road Network Services-Asset
Preservation of National Roads Preventive Maintenance
Based on Pavement Management System/Highway
Development and Management-4 (HDM-4) Cabrera -
Antipolo Road, K0026+(-554) to K0026+000, Taytay,
Rizal
11/21/2017 DPWH 14.260 60 C 0.41 0.20 0.30 - - - 90.60 *90.6% Very Satisfactory
A.J. Taylan Construction Corp/FR
Espiritu Jr. Builders (JV)JV-14-074 Additional Priority Flood Control Project 10/21/2014 I 41.179 163 O 0.299 0.276 0.150 0.030 0.056 0.050 86.10% - On-going
A.J. Taylan Construction
Corporation/ J.L.P Construction And
Supply Joint Venture
JV-16-
1092Improvement/Concreting of Sand Dunes Access Road 08/16/2017
Ilocos Norte
2nd DEO39.688 210 O 0.381 0.214 0.150 0.03 0.058 0.05 88.30 - On-going
A.J. Taylan Construction
Corporation/ J.Q.C. Summit
Construction And Development
Corporation
JV-15-
1238
Construction/Maintenance of Flood Control Mitigation
Structures and Drainage Systems, Damaged Flood
Control Facilities/Structures under the Laoag River Basin
and Flood Control and Sabo Project (LRBDCSP)-Batac
City Flood Control, Quiaoit River, Eroded Bank
Embankment
08/16/2017Ilocos Norte
2nd DEO14.700 396 C 0.47 0.13 0.30 - - - 89.90 *89.9% Very Satisfactory
A.J. Taylan Construction
Corporation/ J.Q.C. Summit
Construction And Development
Corporation
JV-15-
1238
Construction/Maintenance of Flood Mitigation Structures
and Drainage System, Damaged Flood Control
Facilities/Structures under the Laoag River Basin Flood
Control and Sabo Project (LRBDCSP) Batac City Flood
Control, Quiaoit River, Eroded Bank Embankment, Ilocos
Norte
03/15/2017Ilocos Norte
2nd DEO14.699 396 O 0.390 0.239 0.150 0.03 0.04 0.033 88.20 - On-going
A.J. Taylan Construction
Corporation/Zedik Builders (JV)JV-13-345
Road Upgrading (Gravel to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Standard (HDM-4 Project Analysis) of Piniti-
Banna (Espiritu) Road
08/08/2014 I 28.942 236 O 0.380 0.240 0.150 0.030 0.055 0.033 88.80 - On-going
A.J.Taylan Construction Corp./Jlp
Construction & Supply, Joint
Venture
JV-16-
1092Improvement/Concreting of Sand Dunes Access Road 03/15/2018
Ilocos Norte
2nd DEO39.688 236 C 0.46 0.12 0.30 - - - 88.00 89.00% Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 18 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.L Acharon Construction & Supply 33068
Off-Carriageway Improvement Paving
Shoulders/Construction along Makar-Kiamba Road
K1667+270 to K1667+720
11/15/2017 DPWH 13.150 150 C 0.47 0.15 0.30 - - - 91.80 *91.8% Very Satisfactory
A.L Acharon Construction & Supply 30872Construction of the Diversion Works and Canal System
of Libertad CIP - Phase 211/15-20/2010 NIA 16.060 202 O 0.373 0.264 0.150 0.023 0.038 0.050 89.69 - On-going
A.L Acharon Construction & Supply 30872 Benolho CIS 10/6-10/08 NIA 3.720 90 O 0.277 0.180 0.050 0.020 0.038 0.100 66.50 - On-going
A.L Acharon Construction & Supply 33068
Construction of Classroom in Areas Experiencing
Classroom Shortage - Construction of Two (2) Storey,
Two (2) Classroom School Building, Bawing Elementary
School Brgy. Bawing, General Santos City
03/18/2016South
Cotabato 2nd4.3497 120 C 0.47 0.12 0.30 0.00 0.00 0.00 88.90% 88.90% Satisfactory
A.L Acharon Construction & Supply 33068Off-Carriageway Improvement - Paving of Shoulders/
Construction Along Makar-Kiamba Road03/22/2018
South
Cotabato 2nd
DEO
11.019 120 C 0.48 0.13 0.30 - - - 90.90 *90.90% Very Satisfactory
A.L. Dare Construction
Construction/Maintenance of Flood Mitigation Structures
and Drainage Systems- Rehabilitation/Improvement of
Slope Protection along Pentor Balsik River (Balsik
Section-Phase III)
06/19/2018Bataan 1st
DEO22.904 192 C 0.48 0.13 0.30 - - - 91.70 91.70% Very Satisfactory
A.L. Dare Construction 11932
Rehabilitation/ Improvement of Sepung Ilog, Sta. Lucia,
Sta. Ana By Pass Road, Sta. 0+000 to Sta. 1+227, Sta.
Ana, Pampanga
11/27/2017 DPWH 25.187 135 C 0.49 0.13 0.30 - - - 92.60 *92.6% Very Satisfactory
A.L. Dare Construction 11932
Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.
(Int. Sect.) at Candaba-San Miguel Rd., K0070+290-
K0071+184
07/29/2013 III 11.909 139 O 0.319 0.240 0.136 0.030 0.055 0.033 81.30 Ongoing
A.L. Salazar Construction, Inc. 3899Drainage Improvement of Commonwealth Avenue Drive
to Zuzuaregui, Brgy. Batasan Hills, Quezon City08/25/2015 QC 1st DEO 17.562 270 O 0.38 0.24 0.15 0.023 0.045 0.05 88.80% - On-going
A.L. Salazar Construction, Inc. 3899Const./Widening/Upgrading/Rehab. of Access Rd. to
Taytay-Bantulan Port (Km.210+000-Km.214+211)03/12/2013 IVB 89.312 450 O 0.364 0.300 0.030 0.030 0.055 0.033 81.20 - On-going
A.L. Salazar Construction, Inc. 3899Const./Widening/Upgrading/Rehab. of Access Road
(Km.210+000-Km.214+211)08/03/2012 IVB 81.362 349 O 0.332 0.240 0.150 0.030 0.045 0.050 84.70 - On-going
A.L. Salazar Construction, Inc. 3899Drainage Improvement of Commonwealth Avenue Drive
to Zuzuaregui, Brgy. Batasan Hills, Quezon City04/12/2016
Quezon City
1st DEO17.5621 270 C 0.47 0.13 0.30 - - - 89.20% 89.20% Very Satisfactory
A.L. Salazar Construction, Inc. 3899Rehabiliation/Improvement of drainage System along C-
3 Road11/22/2014 NCR 17.425 209 O 0.380 0.240 0.150 0.030 0.045 0.033 87.80% - On-going
A.L.R. Construction Corporation 24110 Completion of 2-Storey 4-CL @ Landayan E/S 02/24/2010 IVA 5.030 225 O 0.354 0.300 0.150 0.015 0.018 0.033 87.00 - On-going
A.M Oreta & Co ., Inc / Ibc
International Builders Corporation
(Joint Venture)
JV-07096 Kalibo Airport Development Project 08/22/2017 DOTC 309.889 450 C 0.48 0.20 0.30 - - - 89.20% 95.00% Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 19 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.M Oreta & Co ., Inc / Ibc
International Builders Corporation
(Joint Venture)
JV-07096 Kalibo Airport Development Project 06/17/2015 DOTC 287.056 360 O 0.381 0.300 0.150 0.020 0.044 0.033 92.80 - On-going
A.M. Ayunan Construction 13983 Construction/Rehabilitation of Brgy Hall 11/11/2015Cotabato
First DEO0.924 75 O 0.363 0.16 0.052 0.03 0 0.016 62.10% - On-going
A.M. Ayunan Construction 13983Construction/Rehabilitation of Barangay Hall Barangay
Langkong, M'lang, Cotabato03/10/2016 Cotabato 1st 0.924 75 C 0.50 0.20 0.01 - - - 64.53% 64.53% Poor
A.M. Oreta & Co., Inc. / Camia
Const. Development Corporation
(Formerl
Construction and Maintenance of Bridges along National
Roads, Construction of New Permanent Bridges, along
Igawe Bridge, Apayao-Ilocos Norte Road
06/05/2018Apayao 1st
DEO57.890 527 O 0.36 0.30 0.05 0.03 0.06 0.03 82.40 - On-going
A.M. Oreta & Company Inc. / Labb
Construction (JV)
108 /
13524 -
SL2-SN-
03029
Small Reservoir Irrigation Project - Benliw SRIP -
Construction of Benliw Earthfill Dam & Appurtenant
Structures
07/09/2019 NIA 367.082 941 O 0.34 0.24 0.14 0.03 0.04 0.05 83.90 - On-going
A.M. Oreta / IBC (Joint Venture) JV-11-210Const. of Drainage System along Iloilo-Capiz Rd. (Old
Route) Nat'l Rd. CPU Sect., Iloilo City08/06/2012 VI 42.875 240 O 0.321 0.239 0.150 0.030 0.055 0.050 84.50 - On-going
A.M.P. ConstructionRehabilitation of Flood Control Structures along Talavera
River06/20/2018
Nueva Ecija
1st DEO27.925 210 O 0.36 0.30 0.15 0.03 0.055 0.05 94.10 - On-going
A.M.P. Construction 16574
Improvement of Canal Service Road - Concreting of
Canal Service / Access Road at SEE Lateral IA (Sta.
0+000 - 0+471)
09/28/2019 NIA 3.804 90 O 0.32 0.24 0.15 0.03 0.06 0.03 83.40 - On-going
A.M.P. Construction 16574Repair/Maintenance of Flood Control Talavera River
Control, Brgy. Sicsican Matanda, Talavera, Nueva Ecija06/02/2017
Nueva Ecija
1st DEO1.901 70 C 0.42 0.14 0.30 - - - 85.40 *85.4% Satisfactory
A.M.P. Construction 16574Construction of Flood Control Revetment Wall along
Agbalili River03/15/2016 Aklan DEO 34.428 244 O 0.328 0.3 0.101 0.03 0.045 0.033 83.70% - On-going
A.M.P. Construction/ Forthright
Construction Joint Venture
JV-16-
1612
Construction/ Maintenance of Flood Mitigation Structures
and Drainage Systems, Rehabilitation/ Improvement of
Pampanga River Control, Brgy. Sapang Buho, Palayan
City, Nueva Ecija
03/15/2018Nueva Ecija
2nd DEO39.200 161 C 0.47 0.13 0.30 - - - 90.50 88.46% Satisfactory
A.M.P. Construction/ Forthright
Construction Joint VentureJV-16-933
Improvement/ Rehabilitation of Revetment along
Talavera River Barangay Basang Hamog, Talavera,
Nueva Ecija
03/13/2018Nueva Ecija
1st DEO31.723 240 C 0.41 0.14 0.30 - - - 85.40 *85.40% Satisfactory
A.P Palacios Construction 29021 Rehab./Impvt. of Dikidit-Suguit FTMR 09/08/2009 III 4.723 150 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 - On-going
A.P. Consebido Construction And
Trading33616
Construction of Two (2) Units Technical-Vocational
Livelihood (TVL) Laboratories/Worshop Roxas National
Comprehensive High School, Roxas, Palawan
03/13/2017Palawan 1st
DEO5.347 140 O 0.451 0.200 0.300 - - - 95.10 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 20 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.P. Tagarino Engineering and
Construction Services32730
Mabolo Communal Irrigation System - Diversion Work
and Embankment Protection05/10/2019 NIA 28.040 300 O 0.33 0.28 0.15 0.02 0.04 0.05 87.00 - On-going
A.P.B. Construction 17055 Concreting of Ore West Capangdanan Road 11/09/2017 DPWH 24.500 175 C 0.41 0.13 0.30 - - - 84.00 *84% Satisfactory
A.P.B. Construction 17055
Improvement/Widening of National Roads along
Pangasinan-Nueva Ecija Roa, K0180+417-K0181+745;
K0183+129-K0184+062
08/21/2017Pangasinan
3rd DEO46.372 300 C 0.48 0.14 0.30 - - - 91.40 *91.4% Very Satisfactory
A.P.B. Construction 17055
Improvement/Upgrading of Naguilian-Bagulin Road
Leading to Tudingan Falls and Kedlap Burial Cave, Sta.
266+980-Sta. 271+279 with Exception, Naguilian-
Bagulin, La Union
03/14/2016LA UNION
2ND DEO41.295 179 C 0.26 0.20 0.30 - - - 83.36% 83.36% Satisfactory
A.P.B. Construction 17055
Rehabilitation/Reconstruction of National Roads with
Slips, Slope Collapse and Landslide: Magsaysay Ave.
(Trinidad Rd.), K0251+996 to K0251+1024; K0252+255
to K0252+270; K0252+350 to K0252+444, Baguio City
09/01/2016BAGUIO
CITY DEO19.805 177 O 0.387 0.3 0.118 0.03 0.04 0.017 0.8920 - On-going
A.P.B. Construction 17055
Off-Carriageway Improvement along Baguio-Bontoc
Road, K0253+(-586) to K0253+000, K0259+450 to
K0259+600, K0260+500 to K0262+000
06/02/2015Benguet 1st
DEO18.999 150 O 0.333 0.274 0.149 0.03 0.05 0.035 87.10% - On-going
A.P.B. Construction 17055
Improvement/Upgrading of Naguilian-Bagulin Road
Leading to Tudingan Falls and Kedlap Burial Cave Sta.
266+980 to Sta. 271+279, Naguilian, La Union
08/30/2015La Union 2nd
DEO41.295 179 O 0.335 0.287 0.15 0.023 0.037 0.05 88.20% - On-going
A.P.B. Construction 17055Rehab./Reconst./Upgrading of Damaged Paved National
Road, PMA cut-off Road 2 K0+000-K0+36008/18/2011 CAR 5.610 102 O 0.370 0.240 0.000 0.030 0.042 0.033 71.50 - On-going
A.P.O. General Construction 7010
MFO-1: National Road Network Services - Asset
Preservation of National Roads - Rehabilitation/
Reconstruction/ Upgrading Tertiary - Reconstruction from
Concrete to Concrete - Mt. Province - Ifugao Road (Kiling-
Paracelis Section), K0456+753-K0457+000, K0459+300-
K0460+000
11/11/2017 DPWH 28.581 250 O 0.351 0.240 0.150 0.03 0.061 0.05 88.20 - On-going
A.P.O. General Construction 7010Construction of 4 Storey 12 Classroom School Building
Senior High School in Aringay06/06/2017
La Union 2nd
District
Engineering
Office
21.893 255 O 0.397 0.239 0.138 0.03 0.065 0.033 90.20 - On-going
A.P.O. General Construction 7010
Road Upgrading (Unpaved to Paved) based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standard (HDM-4 Project Analysis) Junction-
Talubin-Barlig-Natonin-Paracelis-Calaccad Road,
K0443+054 - K0446+000
06/03/2017
Cordillera
Administrativ
e Region,
R.O.
97.500 455 C 0.43 0.13 0.30 - - - 86.10 *86.1% Satisfactory
A.P.O. General Construction 7010Construction of 4 Storey 12 Classroom School Building
Senior High School, Aringay, La Union03/18/2017
La Union 2nd
DEO21.481 195 O 0.285 0.300 0.112 0.03 0.041 0.033 80.10 - On-going
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 21 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.P.O. General Construction 7010
Road Upgrading (Gravel to Paved) along Acop-
Kapangan-Kibungan-Bakun Road, K0283+636 -
K0283+796, K0287+621 - K0287+685, K0289+214 -
K0289+473, K0289+549 - K0289+709, K0290+901 -
K0291+000, K0292+016 - K0292+114, K0298+781 -
K0299+514, K0299+531 - K0299+816
11/20/2014 CAR 72.026 267 O 0.362 0.240 0.150 0.030 0.061 0.050 89.30% - On-going
A.P.O. General Construction 7010
Rd. Upgrading (gravel to concrete) along Acop-
Kapangan-Kibungan-Bakun Rd., K0285+444-K0286+840
V.S. (K0285+423-K0286+836 as per RBIA) &
K0345+470-K0348+000 V.S. (K0345+500-K0348+000
as per RBIA)
11/21/2012 CAR 59.896 237 O 0.333 0.240 0.150 0.015 0.047 0.050 83.50 - On-going
A.P.O. General Construction 7010
Road Upgrading (Unpaved to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standards (HDM-4 Project
Analysis)(Intermittent Sections) along Mountain Province
- Ifugao Road (Kiling - Paracelis Section), K0460+508 to
K0460+868, K0467+904 to K0469+000, K0471+451 to
K0472+061, K0473+155 to K0473+582, K0474+350 to
K0474+368, K0477+312 to K0477+341, Paracelis,
Mountain Province
03/13/2016Regional
Office57.843 248 C 0.35 0.19 0.30 - - - 87.08% 87.08% Satisfactory
A.P.O. General Construction 7010
Road Upgrading (Unpaved to Paved) Based on Gravel
Road Strategies, Traffic Benchmark for Upgrading to
Paved Road Standards (HDM-4 Project Analysis)
(Intermittent Sections) along Mt. Province - Ifugao Road
(Kiling - Paracelis Section), K0460+508 to K0460+868,
K0467+904 to K0469+000, K0471+451 to K0472+061,
K0473+155 to K0473+582, K0474+350 to K0474+368,
K0477+312 to K0477+341, Paracelis, Mt. Province
08/29/2015 CAR 54.883 237 O 0.367 0.246 0.15 0.03 0.051 0.05 89.40% - On-going
A.P.O. General Construction 7010Rd. Upgrading (Gravel to Paved) Int. Sect., Acop-
Kapangan-Kibungan-Bakun Rd., K0348+000-K0349+00008/01/2013 CAR 23.654 207 O 0.356 0.239 0.150 0.023 0.048 0.050 86.60 - On-going
A.R. & Mark Builders 31673 Const. of Multi-Purpose Building, BUSECO Compound 10/21/2014 X 7.920 124 O 0.304 0.240 0.017 0.010 0.022 0.033 62.60% - On-going
A.R. & Mark Builders 31673Const. of 1-Storey, 1-CL & 1-Storey, 1-CL Kinder at
Maramag South PS, Pob.08/08/2013 X 1.448 187 O 0.393 0.235 0.120 0.030 0.023 0.033 83.40 - On-going
A.R. Lustre Jr. ConstructionRehabilitation/ of Paved Rd - Puerto Princesa Wharf Rd -
(S00031PW), Chainage 1180- Chainage 172205/31/2018
Palawan 3rd
DEO7.201 30 C 0.46 0.13 0.30 - - - 89.40 89.40% Very Satisfactory
A.R. Lustre, Jr. Construction 7680Asphalt Overlay of Puerto Princesa South Road,
K000+000 - K000+420, K001+420 - K002+30011/17/2017 DPWH 29.860 105 C 0.43 0.20 0.30 - - - 92.90 *92.9% Very Satisfactory
*1st/Final
* For DPWH, only the region and PMO office are listed 31st Release Page 22 of 688
-
On-going and Completed Projects
For the period July 1, 2017 to June 30, 2020
AMOUNTDUR (C.D.)
NAME OF CONSTRUCTORLICENSE
NO.PROJECT
DATE OF EVALUATION
*IMPL. AGENCY
CONTRACT
STATUS WMS FINAL RATINGQUALITATIVE DESCRIPTION
MTL TIME FAC ESH RDRCPES VISIT
RATING
A.R. Lustre, Jr. Construction 7680
Asphalt Overlay of Puerto Princesa South Road
K0000+000 to K000+420, K000+420 to K002+300,
Puerto Princesa City, Palawan
06/05/2017 Palwan 3rd 29.884 90 O 0.385 0.298 0.150 0.03 0.037 0.033 93.30 - On-going
A.R. Lustre, Jr. Construction 7680
Asphalt Overlay of Puerto Princesa South Road,
K0000+000 to K0000+420, K0000+420 to K0002+300,
Puerto Princesa City, Palawan
08/24/2017Palawan 3rd
DEO29.860 105 O 0.489 0.133 0.300 - - - 92.20 - On-going
A.R. Lustre, Jr. Construction 7680
Rehabilitation/Reconstruction of National Roads with
Slips, Slope Collapse and Landslide Puerto Princesa
South Road, K0139+214 to K0139+245, K0139+292 to
K0139+397, K0140+033 to K0140+111, K0141+807 to
K0141+880, K0142+000 to K0142+300, Espanola,
Palawan
03/14/2017Palawan 2nd
DEO47.859 266 C 0.40 0.20 0.30 - - - 90.20 *90.2% Very Satisfactory
A.R. Lustre, Jr. Construction 7680
Rehabilitation/Recons