on-site lift station generators · b2 1 ls 723-510 bypass pumping lump sum b3 38 sy 814-510 cement...

250
On-Site Lift Station Generators LACEY CONTRACT NUMBER PW 2019-01

Upload: others

Post on 05-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

On-Site Lift Station Generators LACEY CONTRACT NUMBER PW 2019-01

Page 2: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 3: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

SPECIFICATIONS AND BID DOCUMENTS

DEPARTMENT OF PUBLIC WORKS

LACEY CONTRACT NUMBER PW 2019-01

CITY OF LACEY WASHINGTON

CITY OFFICIALS

MAYOR ANDY RYDER

DEPUTY MAYOR CYNTHIA PRATT

COUNCIL MEMBERS JASON HEARN

LENNY GREENSTEIN

MICHAEL STEADMAN

RACHEL YOUNG

CAROLYN COX

CITY MANAGER SCOTT H. SPENCE

CITY ATTORNEY DAVID S. SCHNEIDER

DIRECTOR OF PUBLIC WORKS SCOTT EGGER, P.E.

CITY ENGINEER ROGER SCHOESSEL, P.E.

Page 4: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 5: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey

BID PROPOSAL, CONTRACT DOCUMENTS, AND SPECIFICATIONS FOR:

On-Site Lift Station Generators

Lacey Contract No. PW 2019-01

RH2 Engineering, Inc., Project No. LAC 118.086

Spring 2019

THE CONTENT OF THIS DOCUMENT, AS A MEANS OF PROFESSIONAL SERVICE, IS PROTECTED BY 17 U.S.C. § 101, ET SEQ. AS SUCH, IT SHALL NOT BE USED, IN WHOLE OR IN PART, FOR ANY OTHER PROJECT OR PURPOSE WITHOUT WRITTEN AUTHORIZATION FROM RH2 ENGINEERING. © 2019 RH2 ENGINEERING, INC.

Signed: 04/17/19 Signed: 04/17/19

Signed: 04/17/19 Signed: 04/17/19

Page 6: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 7: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

TABLE OF CONTENTS

Advertisement for Bids ........................................................................................................ i

INSTRUCTIONS

Instructions to Bidders .................................................................................................... A-1

Bidder's Checklist ........................................................................................................... A-2

BID DOCUMENTS

Proposal & Bid Sheet ....................................................................................................... B-1

Bid Bond Form ................................................................................................................ B-5

Non-Collusion Certificate ................................................................................................ B-6

Certification of Compliance with Wage Payment Statutes .............................................. B-7

CONTRACT DOCUMENTS

Construction Contract ......................................................................................................C-1

Performance Bond Form ..................................................................................................C-4

Declaration of Option for Management of Statutory Retained Percentage......................C-6

AMENDMENTS AND SPECIAL PROVISIONS

Table of Contents ................................................................................................................ ii

Amendments ................................................................................................................... D-1

Special Provisions ......................................................................................................... D-38

TECHNICAL SPECIFICATIONS – PART E

Division 1 General ......................................................................................................... E1-1

Division 16 Electrical .................................................................................................. E16-1

Page 8: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

PREVAILING MINIMUM HOURLY RATES

State Wage Rates ............................................................................................................. F-1

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)

Short Form ...................................................................................................................... G-1

Page 10: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 11: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

A INSTRUCTIONS

Page 12: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 13: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

A-1

INSTRUCTIONS TO BIDDERS

Bidders shall examine contract and bid documents and the site and shall satisfy themselves as to conditions that exist.

Each Bidder shall submit to the City Clerk, Lacey, Washington a sealed bid endorsed upon the outside wrapper with On-Site Lift Station Generators at the time and place designated in the advertisement.

Bids may be delivered in person to Lacey City Hall, 420 College Street SE, or by mail to City of Lacey 420 College St SE Lacey, WA 98503.

The City of Lacey is committed to offering reasonable accommodations to persons with disabilities. We invite any person with special needs to contact the City Clerk at (360) 491-3212 at least seventy-two (72) hours before the meeting to discuss any special accommodations that may be necessary. Citizens with hearing impairment may call the TDD line at (800) 833-6388.

Each Bidder shall complete the proposal with prices in figures with the extension properly computed. The proposal must be properly signed by a duly authorized agent. Proposal must acknowledge addenda, if any, received.

If alternates are included in the proposal the Bidder shall complete the alternates. The City will award the contract to the lowest responsible Bidder as determined by the Special Provisions. The City reserves the right to delete alternates after award.

Each bid shall include properly executed bid surety as outlined in the Advertisement and the Proposal.

Each Proposal must be accompanied by a signed Affidavit of Non-Collusion.

The City does not pre-qualify Bidders. However, if the apparent low Bidder has not already been determined qualified, the City shall afford seven (7) days after notification for the low Bidder to provide evidence for evaluation, as to capability to perform the work. The evaluation will include consideration of experience, personnel, equipment, financial resources as well as performance record. The information must be sufficient to enable the Bidder to obtain the required qualification rating prior to the award of the contract.

No bidder may withdraw his bid after the hour set for the opening of bids or before award of the contract unless said award is delayed for a period of forty-five (45) days.

CONTRACT PARTS

The contract to be executed as a result of this bid consists of multiple parts, all of which pertain as if fully attached hereto and Bidder shall consider all parts as a complete document. In the event of discrepancies between the various parts, precedent shall be in the following order:

1. Contract Form, 2. Addenda (if any), 3. Proposal Form, 4. Special Provisions, 5. Technical Specifications, if included, 6. Contract Plans, 7. Amendments to the Standard Specifications, 8. WSDOT Standard Specifications for Road, Bridge, and Municipal Construction, 9. City of Lacey Development Guidelines and Public Works Standards, and 10. WSDOT Standard Plans for Road, Bridge and Municipal Construction

• The Bidder is directed to complete and return the forms in Section B as a bid proposal.

Page 14: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

A-2

BIDDER'S CHECKLIST

The bidder's attention is especially called to the following forms which must be executed in full as required, and submitted with the bid proposal:

1. Proposal: The unit prices bid must be shown in the space provided.

2. Proposal Signature Sheet: To be filled in and signed by the bidder. All addenda must be acknowledged.

3. Bid Deposit: Any bid shall be accompanied by a deposit of cash, certified check, cashier's check, or surety bond, in an amount equal to at least five percent (5%) of the total amount bid. Checks shall be payable to the City Clerk, City of Lacey, Washington.

If a surety bond is used, it shall be submitted on a form furnished by the Commission and signed by the bidder and his surety company. The sureties' "attorney-in-fact" must be registered with the Washington State Insurance Commissioner. The power of attorney must also be submitted with the bond. See Specification section 1-02.7 for more information.

4. Non-Collusion and Debarment Affidavit

5. Certification of Compliance with Wage Payment Statutes

The following must be submitted by 2:30 P.M. of the second business day following the bid submittal deadline:

6. Supplemental Criteria per Specification section 1-02.14

The following forms are to be executed after the contract is awarded:

7. Contract: This agreement to be executed by the successful bidder

8. Performance and Payment Bond

9. Insurance Certificate

Bidder’s Checklist

1. Proposal

2. Proposal Signature Sheet

Addenda Acknowledged

3. Bid Deposit

Power of Attorney included if applicable

4. Non-Collusion and Debarment Affidavit

5. Certification of Compliance with Wage Payment Statutes

6. Contractor has verified they can meet bidding qualifications/supplemental criteria

Page 15: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

B BID DOCUMENTS

Page 16: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 17: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

Contract Proposal

CITY OF LACEY

Federal Aid Project Number:

WSDOT Contract Number:

Lacey Contract Number: PW 2019-01

To: The Honorable Mayor and Council, Lacey, Washington

The undersigned, as bidder, has examined the bid documents, contract and bond forms, and the general and technical specifications, all as prepared by the Public Works Department, City of Lacey.

The undersigned, as bidder, proposes to furnish all material and perform all labor in accordance with specifications at the following prices.

Bidder must fill in unit prices in figures for each item and total.

Bidder shall sign this proposal form, furnish bid security and sign the enclosed affidavit.

DATE: _________________________________

On-Site Lift Station Generators

TIB Contract Number:

A General

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

25000 MC 104-010 Minor Change $1.00 $25,000.00A1

1 LS 109-010 Mobilization LUMP SUMA2

1 LS 110-010 Project Temporary Traffic Control LUMP SUMA3

1 LS 201-010 Clearing and Grubbing LUMP SUMA4

1 LS 202-510 Removal of Structures and Obstructions LUMP SUMA5

140 SY 212-030 Construction Geotextile for Soil StabilizationA6

60 TN 404-010 Crushed Surfacing Base CourseA7

4 TN 504-110 Commercial HMAA8

14 HR 708-810 Utility PotholingA9

1 LS 801-680 Erosion/Water Pollution Control LUMP SUMA10

1 LS 805-510 Lawn and Landscape Restoration LUMP SUMA11

4 EA 850-550 BollardA12

1 LS 850-792 Project Closeout $5,000.00 $5,000.00A13

Tax Rate (%) : 9.30 Tax:

Schedule A Subtotal:

Schedule A Total:

B - 1

Page 18: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

B Sewer - Lift Station 4

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMB1

1 LS 723-510 Bypass Pumping LUMP SUMB2

38 SY 814-510 Cement Conc. SidewalkB3

1 LS 850-802 Standby Generator LUMP SUMB4

Tax Rate (%) : 9.30 Tax:

Schedule B Subtotal:

Schedule B Total:

C Sewer - Lift Station 5

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMC1

1 LS 723-510 Bypass Pumping LUMP SUMC2

1 LS 850-802 Standby Generator LUMP SUMC3

Tax Rate (%) : 9.30 Tax:

Schedule C Subtotal:

Schedule C Total:

D Sewer - Lift Station 8

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

50 CY 203-720 Extra Excavation Incl. HaulD1

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMD2

1 LS 723-510 Bypass Pumping LUMP SUMD3

1 LS 850-802 Standby Generator LUMP SUMD4

Tax Rate (%) : 9.30 Tax:

Schedule D Subtotal:

Schedule D Total:

E Sewer - Lift Station 11

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUME1

1 LS 723-510 Bypass Pumping LUMP SUME2

1 LS 850-802 Standby Generator LUMP SUME3

Tax Rate (%) : 9.30 Tax:

Schedule E Subtotal:

Schedule E Total:

B - 2

Page 19: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

F Sewer - Lift Station 17

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

6 CY 505-010 Cement Conc. PavementF1

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMF2

1 LS 723-510 Bypass Pumping LUMP SUMF3

1 LS 850-802 Standby Generator LUMP SUMF4

Tax Rate (%) : 9.30 Tax:

Schedule F Subtotal:

Schedule F Total:

G Sewer - Lift Station 24

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMG1

1 LS 723-510 Bypass Pumping LUMP SUMG2

1 LS 850-802 Standby Generator LUMP SUMG3

Tax Rate (%) : 9.30 Tax:

Schedule G Subtotal:

Schedule G Total:

H Sewer - Lift Station 27

Quantity Unit Item ID Item Description Unit Price Extended PriceNo.

1 LS 722-540 Electrical, Controls & Telemetry LUMP SUMH1

1 LS 723-510 Bypass Pumping LUMP SUMH2

1 LS 850-805 Install City-Provided Standby Generator LUMP SUMH3

Tax Rate (%) : 9.30 Tax:

Schedule H Subtotal:

Schedule H Total:

Contract Total:(All Schedules)

B - 3

Page 20: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

The undersigned also agrees as follows:

1. Within 10 calendar days after the contract is awarded, to execute the contract and to furnish to the City of Lacey, Washington a satisfactory contract bond, guaranteeing the faithful performance of the work.

2. Enclosed with this proposal is a cashier’s check or certified check for $_____________ or a bid bond in the sum of $______________ which it is agreed shall be collected and retained by the City of Lacey as liquidated damages in the event this proposal is accepted by the City of Lacey with 45 calendar days after the receipt of bids and the undersigned fails to execute the contract and the required bond with the City of Lacey, under the conditions thereof, within 10 calendar days after the undersigned is notified that said proposal has been accepted, otherwise said check or bond shall be returned to the undersigned upon demand.

3. That this proposal cannot be withdrawn within 45 days after receipt of bids.

4. That it is the understanding that the City of Lacey may accept or reject any or all bids.

5. The undersigned hereby agrees to pay for labor not less than the prevailing rates of wages or less than the hourly minimum rates of wages set forth in the special provisions for the project.

Addenda Receipt Acknowledged

_______,_______,_______

Signature of Bidder Date

Firm Name Please Print Phone

Address of Bidder:

Name and Address of Firm Members:

Signature of Bidder (if a Corporation)

Title:

Firm Name: Phone:

Business Address:

Officers Address

Incorporated under the Laws of the State of

President:

Secretary:

Treasurer:

(If an Individual, Partnership, or Non-Incorporated organization)

B - 4

Page 21: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

B-5

BID BOND FORM

Herewith find deposit in the form of a certified check or bid bond in the amount of $____________________, which amount is not less than five percent (5%) of the total bid.

Signature

BID BOND

KNOW ALL MEN BY THESE PRESENTS:

That we, ,as Principal and ,as Surety

are held and firmly bound unto the City of Lacey, as Obligee, in the penal sum of

Dollars,

for the payment of which the Principal and the Surety bind themselves, their heirs, executors, successors and assigns, jointly and severally, by these presents.

The condition of this obligation is such that if the Obligee shall make any award to the Principal for:

according to the terms of the proposal or bid made by the Principal therefore, and the Principal shall duly make and enter into a contract with the Obligee in accordance with the terms of said proposal or bid and award and shall give bond for the faithful performance thereof, with Surety or Sureties approved by the Obligee; or if the Principal shall, in case of failure to so do, pay and forfeit to the Obligee the penal amount of the deposit specified in the call for bids, then this obligation shall be null and void; otherwise it shall be and remain in full force and effect and the Surety shall forthwith pay and forfeit to the Obligee, as penalty and liquidated damages, the amount of this bond.

SIGNED, SEALED AND DATED THIS day of ,20

Surety Principal

,20 Received return of deposit in the sum of $

Page 22: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

B-6

NON-COLLUSION AND DEBARMENT AFFIDAVIT State of ) )ss County of ) I, the undersigned, being duly sworn, deposes and says that the person, firm, association, copartnership or corporation herein named, has not either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in the preparation and submission of a proposal of the City of Lacey for consideration in the award of a contract on the improvement described as follows. I further certify that, except as noted below, the firm, association or corporation or any person in a controlling capacity associated therewith or any position involving the administration of State or federal funds; is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility by any federal or State agency; has not been suspended, debarred, voluntarily excluded or determined ineligible by any federal or State agency within the past three years; does not have a proposed debarment pending; and has not been indicted, convicted, or had a civil judgment rendered against said person, firm, association or corporation by a court of competent jurisdiction in any matter involving fraud or official misconduct within the past three years. I further acknowledge that by signing my signature, I am deemed to have signed and have agreed to the provisions of this affidavit.

Name of Project Name of Firm Signature of Authorized Member Sworn to before me this day of ,20 Notary Public (CORPORATE SEAL)

Page 23: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

B-7

CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES

The bidder hereby certifies that, within the three-year period immediately

preceding the bid solicitation date, the bidder is not a “willful” violator, as defined

in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as

determined by a final and binding citation and notice of assessment issued by the

Department of Labor and Industries or through a civil judgment entered by a court

of limited or general jurisdiction.

I certify under penalty of perjury under the laws of the State of Washington that

the foregoing is true and correct.

Bidder’s Business Name

Signature of Authorized Official*

Printed Name

Title

Date

City

State

Check One:

Sole Proprietorship ☐ Partnership ☐ Joint Venture ☐ Corporation ☐

State of Incorporation, or if not a corporation, State where business entity was

formed:

If a co-partnership, give firm name under which business is transacted:

* If a corporation, proposal must be executed in the corporate name by the president

or vice-president (or any other corporate officer accompanied by evidence of

authority to sign). If a co-partnership, proposal must be executed by a partner.

This form must be submitted with the Bid Proposal or as a Supplement to the Bid no later than 24 hours after the time for delivery of the Bid Proposal, as provided for in Section 1-02.9 of the Contract Provisions.

Page 24: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 25: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C CONTRACT

DOCUMENTS

Page 26: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 27: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-1

Contract Number PW 2019-01

CONSTRUCTION CONTRACT THIS AGREEMENT, made and entered into this _____ day of _______________, 20_______ , between the City of Lacey, hereinafter called Owner, under and by virtue of the charter, laws and ordinances of the said Owner and the laws of the State of Washington, and ___________________________________________________ hereinafter called Contractor, WITNESSETH: That in consideration of the payment, covenants and agreement hereinafter mentioned, attached and made a part of this Agreement, to be made and performed by the parties hereto, the parties covenant and agree as follows regarding:

1. The Contractor shall do all work and furnish all tools, materials and equipment in accordance with and as described in the attached Plans and Specifications, and in full compliance with the terms, conditions and stipulations herein set forth and attached, now referred to and by such reference incorporated herein and made a part hereof as fully for all purposes as if here set forth at length, and shall perform any alterations in or in addition to the work covered by this Contract and every part thereof and any force account work which may be ordered as provided in this Contract and every part thereof.

The Contractor shall provide and bear the expense of all materials, labor, equipment, tools, implements and conveniences and things of every description that may be requisite for the transfer of materials and for constructing and completing the work provided for in this Contract and every part thereof, except such as are mentioned in the Specifications to be furnished by the Owner.

2. The Owner hereby promises and agrees with the Contractor to employ, and does employ the Contractor to provide the materials and to do and cause to be done the above described work and to complete and finish the same according to the attached Plans and Specifications and the schedule of unit or itemized prices hereto attached, at the time and in the manner and upon the conditions provided for in this Contract and every part thereof.

3. Contractor, for himself and for his heirs, executors, administrators, successors, assigns, does hereby agree to the full performance of all the covenants herein contained upon the part of Contractor.

4. It is further provided that no liability shall attach to Owner or Agent thereof by reason of entering into this Contract, except as expressly provided herein.

5. Payments will be made under the Contract according to the schedule of rates and prices and the specification attached and made a part thereof. Partial payments under the Contract will be made at the request of the Contractor not more than once each month upon approval of the Owner, as hereinafter specified, provided they are in accordance with the provisions of RCW 60.28.010. There will be reserved and retained from monies

Page 28: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-2

earned by the Contractor, as determined by such monthly estimates, a sum equal to 5 percent of the Contract price.

Payment of the retained percentage shall be withheld for a period of forty-five (45) days following the final acceptance of the work and materials by the Owner, and shall be paid the Contractor at the expiration of said forty-five (45) days in event no claims, as provided by law, have been filed against such funds; and provided further, that releases have been obtained from all departments and agencies having jurisdiction over the activities of the Contractor. In the event such claims are filed, Contractor shall be paid such retained percentages less an amount sufficient to pay any such claims together with a sum sufficient to pay the cost of such action, and to cover attorney fees as determined by the Owner.

6. Requests for review of substitute items of material or equipment will not be accepted by the Owner or Agent from anyone other than the Contractor. If the Contractor wishes to furnish a substitute item, the Contractor shall make written application to the Owner's Agent for acceptance thereof, certifying that the proposed substitute will perform adequately the functions called for by the general design, be similar and of equal substance to that specified and be suited to the same use and capable of performing the same function as that specified. All variations of the proposed substitute from that specified shall be identified in the application and available maintenance, repair and replacement service will be indicated. The application will also contain an itemized estimate of all costs that will result directly or indirectly from acceptance of such substitute, which shall be considered by the Owner in evaluating the proposed substitute. The Owner may require the Contractor to furnish at the Contractor's expense, additional data about the proposed substitute. The Owner will be the sole judge of acceptability, and no substitute will be ordered without the Owner's prior written acceptance. The Owner may require the Contractor to furnish at the Contractor's expense, a special performance guarantee or other surety with respect to any other substitute.

The Owner or Agent will record the time and expenses in evaluating substitutions proposed by the Contractor. Whether or not the Owner accepts a proposed substitute, the Contractor shall reimburse the Owner for the costs of evaluating any proposed substitute.

7. The Owner reserves the right, after the final payment has been made, to claim and recover by process of law such sums as may be sufficient to make good any defects in the equipment or to recover any over-payment resulting from dishonest acts of the Contractor.

8. The contract time will commence to run, and the Contractor shall start to perform his obligation under the contract documents, on the day indicated in the Notice to Proceed given by Owner to Contractor; but in no event shall contract time commence to run later than the 30th calendar day after the date when both Owner and Contractor execute the Contract. A Notice to Proceed may be given at any time within thirty (30) calendar days after the date when both Owner and Contractor execute the Contract.

9. The Contractor shall guarantee the materials and workmanship for a period of one (1) year from and after the date of final acceptance by the Owner.

If, within said guarantee period, repairs are required which, in the opinion of the Owner, are rendered necessary as a result of work or materials which are inferior, defective or not in accordance with the terms of the Contract, the Contractor shall, promptly upon receipt

Page 29: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-3

of notice from the Owner, and without expense to the Owner, (a) correct all defects and place in satisfactory condition in every particular all of such guaranteed work and materials; (b) make good all damage which in the opinion of the Owner is caused by such defects; and (c) make good any other work or material or the equipment and contents of a building, structure or site disturbed in fulfilling any such guarantee.

If the Contractor, after notice, fails within ten (10) days to proceed to comply to the terms of this guarantee, the Owner may have the defects corrected, and the Contractor and his Surety shall be liable for all expense incurred, provided, however, that in case of an emergency where, in the opinion of the Owner, delay would cause serious loss or damage, repairs may be made without notice being given to the Contractor and the Contractor shall pay the cost thereof.

IN WITNESS WHEREOF, the said Contractor has executed this instrument and the City Manager, pursuant to resolution duly adopted, has caused this instrument to be executed in the name of the City of Lacey the day and year first above-written.

Contractor

Contractor’s Registration Number (UBI No.)

City of Lacey Business License Number City Manager ATTEST: By:

City Clerk APPROVED AS TO FORM: By :

City Attorney

Page 30: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-4

PERFORMANCE BOND FORM KNOW ALL MEN BY THESE PRESENTS: That _________________________________________________________________of _________________________________________________________, as Principal, and _________________________________________________________, as Surety, are jointly and severally held and bound unto the ______________________________in the penal sum of ______________________________Dollars ($ _______________ ) for the payment of which we jointly and severally bind ourselves, our heirs, executors, administrators, and assigns, firmly by these presents. The condition of this bond is such that, WHEREAS, on the _______ day of ___________________________, 20______, the said Principal made and entered into a certain contract with the CITY OF LACEY, Washington, by the terms, conditions and provisions of which contract the said Principal agreed to undertake and complete the work as per specifications made a part of said contract, which contract as so executed is incorporated herein and made a part hereof as fully for all purposes as if here set forth at length. NOW, THEREFORE, if the Principal shall well and truly perform and fulfill all the undertakings, covenants, terms and conditions, and agreements of said Contract during the original term of said Contract and any extensions thereof that may be granted by the City of Lacey, Washington, with or without notice to the Surety; and during the life of any guaranty required under the Contract; and shall also well and truly perform and fulfill all the undertakings, covenants, terms and conditions, and agreements of any and all duly authorized modifications of said Contract that may hereafter be made; notice of which modifications to the Surety being hereby waived; and furthermore, shall make prompt payment to all laborers, mechanics, subcontractors and materialmen and all persons who shall supply such contractor or subcontractor with provisions and supplies for performance of said Contract, then this obligation to be void, otherwise to remain in full force and effect. WITNESS our hand this day of , 20

Principal

Surety

Page 31: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-5

Address of local office and agent of Surety

APPROVED AS TO FORM: By: , 20

City Attorney

Page 32: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

C-6

DECLARATION OF OPTION FOR MANAGEMENT OF

STATUTORY RETAINED PERCENTAGE A. I hereby elect to have the retained percentage of this contract held in a fund by the City of

Lacey until forty-five (45) days following final acceptance of the work.

Contractor (please print)

Date Signature

B. I hereby elect to have the City of Lacey invest the retained percentage of this contract from time to time as such retained percentage accrues and in accordance with RCW Ch. 60.28.

I hereby designate _____________________________________________ as the repository for the escrow of said funds.

I hereby further agree to be fully responsible for payment of all costs or fees incurred as a result of placing said percentage in escrow and investing it as authorized by statue.

The City of Lacey shall not be liable in any way for any costs or fees in connection therewith.

Contractor (please print)

Date Signature

Page 33: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D AMENDMENTS AND

SPECIAL

PROVISIONS

Page 34: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 35: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

TABLE OF CONTENTS

WSDOT AMENDMENTS TO THE STANDARD SPECIFICATIONS ................................................................ 1

1-01 DEFINITIONS AND TERMS .......................................................................................................................... 1 1-02 BID PROCEDURES AND CONDITIONS ...................................................................................................... 1 1-03 AWARD AND EXECUTION OF CONTRACT .............................................................................................. 2 1-05 CONTROL OF WORK .................................................................................................................................... 2 1-06 CONTROL OF MATERIAL ............................................................................................................................ 3 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC............................................................ 5 1-08 PROSECUTION AND PROGRESS ................................................................................................................ 9 1-09 MEASUREMENT AND PAYMENT .............................................................................................................. 9 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS ............................................................................ 10 2-09 STRUCTURE EXCAVATION ...................................................................................................................... 10 3-01 PRODUCTION FROM QUARRY AND PIT SITES ..................................................................................... 10 4-04 BALLAST AND CRUSHED SURFACING .................................................................................................. 11 6-02 CONCRETE STRUCTURES ......................................................................................................................... 11 8-01 EROSION CONTROL AND WATER POLLUTION CONTROL ................................................................ 14 8-02 ROADSIDE RESTORATION ....................................................................................................................... 25 8-04 CURBS, GUTTERS, AND SPILLWAYS ...................................................................................................... 26 8-06 CEMENT CONCRETE DRIVEWAY ENTRANCES ................................................................................... 26 8-14 CEMENT CONCRETE SIDEWALKS .......................................................................................................... 26 8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION SYSTEMS,

AND ELECTRICAL ................................................................................................................................................... 26 9-02 BITUMINOUS MATERIALS ....................................................................................................................... 27 9-03 AGGREGATES ............................................................................................................................................. 28 9-04 JOINT AND CRACK SEALING MATERIALS ............................................................................................ 33 9-06 STRUCTURAL STEEL AND RELATED MATERIALS ............................................................................. 34 9-29 ILLUMINATION, SIGNAL, ELECTRICAL ................................................................................................ 34 9-34 PAVEMENT MARKING MATERIAL ......................................................................................................... 36

SPECIAL PROVISIONS .......................................................................................................................................... 38

INTRODUCTION TO THE SPECIAL PROVISIONS ............................................................................................... 38 DESCRIPTION OF WORK ........................................................................................................................................ 38 1-01 DEFINITIONS AND TERMS ........................................................................................................................ 39 1-02 BID PROCEDURES AND CONDITIONS .................................................................................................... 40 1-03 AWARD AND EXECUTION OF CONTRACT ............................................................................................ 48 1-04 SCOPE OF THE WORK ................................................................................................................................ 50 1-05 CONTROL OF WORK .................................................................................................................................. 51 1-06 CONTROL OF MATERIAL .......................................................................................................................... 55 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC.......................................................... 56 1-08 PROSECUTION AND PROGRESS .............................................................................................................. 62 1-09 MEASUREMENT AND PAYMENT ............................................................................................................ 67 1-10 TEMPORARY TRAFFIC CONTROL ........................................................................................................... 69 2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP ........................................................................... 70 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS ............................................................................ 71 2-05 TRENCH SAFETY SYSTEM ........................................................................................................................ 73 2-07 WATERING ................................................................................................................................................... 73 2-08 DUST CONTROL .......................................................................................................................................... 74 2-09 STRUCTURE EXCAVATION ...................................................................................................................... 75 5-04 HOT MIX ASPHALT..................................................................................................................................... 75 7-08 GENERAL PIPE INSTALLATION REQUIREMENTS ............................................................................... 92 7-22 LIFT STATION .............................................................................................................................................. 97 7-23 SANITARY SEWER BYPASS PUMPING ................................................................................................. 102

Page 36: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

8-01 EROSION CONTROL AND WATER POLLUTION CONTROL .............................................................. 105 8-05 LAWN AND LANDSCAPE RESTORATION ............................................................................................ 109 8-14 CEMENT CONCRETE SIDEWALKS ........................................................................................................ 110 8-50 MISCELLANEOUS ..................................................................................................................................... 111 9-03 AGGREGATES ........................................................................................................................................... 113 9-04 JOINT AND CRACK SEALING MATERIALS .......................................................................................... 113 9-14 EROSION CONTROL AND ROADSIDE PLANTING .............................................................................. 114

Page 37: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-1

WSDOT AMENDMENTS TO THE STANDARD SPECIFICATIONS

The following Amendments and Special Provisions shall be used in conjunction with the 2018 Standard Specifications for Road, Bridge, and Municipal Construction. The following Amendments to the Standard Specifications are made a part of this contract and supersede any conflicting provisions of the Standard Specifications. For informational purposes, the date following each Amendment title indicates the implementation date of the Amendment or the latest date of revision. Each Amendment contains all current revisions to the applicable section of the Standard Specifications and may include references which do not apply to this particular project.

1-01 DEFINITIONS AND TERMS (August 6, 2018 WSDOT 1-02.AP1)

1-01.3 Definitions

The following new term and definition is inserted before the definition for “Shoulder”: Sensitive Area – Natural features, which may be previously altered by human activity, that are present on or adjacent to the project location and protected, managed, or regulated by local, tribal, state, or federal agencies. The following new term and definition is inserted after the definition for “Working Drawings”: WSDOT Form – Forms developed and maintained by WSDOT that are required or available for use on a project. These forms can be downloaded from the forms catalogue at: http://wsdot.wa.gov/forms/pdfForms.html

1-02 BID PROCEDURES AND CONDITIONS (October 30, 2018 WSDOT 1-02.AP1)

1-02.4(1) General

This section is supplemented with the following: Prospective Bidders are advised that the Contracting Agency may include a partially completed Washington State Department of Ecology (Ecology) Transfer of Coverage (Ecology Form ECY 020-87a) for the Construction Stormwater General Permit (CSWGP) as part of the Bid Documents. When the Contracting Agency requires the transfer of coverage of the CSWGP to the Contractor, an informational copy of the Transfer of Coverage and the associated CSWGP will be included in the appendices. As a condition of Section 1-03.3, the Contractor is required to complete sections I, III, and VIII of the Transfer of Coverage and return the form to the Contracting Agency. The Contracting Agency is responsible for compliance with the CSWGP until the end of day that the Contract is executed. Beginning on the day after the Contract is executed, the Contractor shall assume complete legal responsibility for compliance with the CSWGP and full implementation of all conditions of the CSWGP as they apply to the Contract Work.

Page 38: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-2

1-02.5 Proposal Forms

The first sentence of the first paragraph is revised to read: At the request of a Bidder, the Contracting Agency will provide a physical Proposal Form for any project on which the Bidder is eligible to Bid.

1-02.6 Preparation of Proposal

Item number 1 of the second paragraph is revised to read: 1. A unit price for each item (omitting digits more than two places to the right of the decimal point), In the third sentence of the fourth paragraph, “WSDOT Form 422-031” is revised to read “WSDOT Form 422-031U”. The following new paragraph is inserted before the last paragraph: The Bidder shall submit with their Bid a completed Contractor Certification Wage Law Compliance form (WSDOT Form 272-009). Failure to return this certification as part of the Bid Proposal package will make this Bid Nonresponsive and ineligible for Award. A Contractor Certification of Wage Law Compliance form is included in the Proposal Forms.

1-03 AWARD AND EXECUTION OF CONTRACT (January 2, 2018 WSDOT 1-03.AP1)

1-03.3 Execution of Contract

The first paragraph is revised to read: Within 20 calendar days after the Award date, the successful Bidder shall return the signed Contracting Agency-prepared Contract, an insurance certification as required by Section 1-07.18, a satisfactory bond as required by law and Section 1-03.4, the Transfer of Coverage form for the Construction Stormwater General Permit with sections I, III, and VIII completed when provided, and shall be registered as a contractor in the state of Washington.

1-03.5 Failure to Execute Contract

The first sentence is revised to read: Failure to return the insurance certification and bond with the signed Contract as required in Section 1-03.3, or failure to provide Disadvantaged, Minority or Women’s Business Enterprise information if required in the Contract, or failure or refusal to sign the Contract, or failure to register as a contractor in the state of Washington, or failure to return the completed Transfer of Coverage for the Construction Stormwater General Permit to the Contracting Agency when provided shall result in forfeiture of the proposal bond or deposit of this Bidder.

1-05 CONTROL OF WORK (August 6, 2018 WSDOT 1-05.AP1)

1-05.5 Vacant

This section, including title, is revised to read:

Page 39: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-3

1-05.5 Tolerances

Geometrical tolerances shall be measured from the points, lines, and surfaces defined in Contract documents. A plus (+) tolerance increases the amount or dimension to which it applies, or raises a deviation from level. A minus (-) tolerance decreases the amount or dimension to which it applies, or lowers a deviation from level. Where only one signed tolerance is specified (+ or -), there is no specified tolerance in the opposing direction. Tolerances shall not be cumulative. The most restrictive tolerance shall control. Tolerances shall not extend the Work beyond the Right of Way or other legal boundaries identified in the Contract documents. If application of tolerances causes the extension of the Work beyond the Right of Way or legal boundaries, the tolerance shall be reduced for that specific instance. Tolerances shall not violate other Contract requirements. If application of tolerances causes the Work to violate other Contract requirements, the tolerance shall be reduced for that specific instance. If application of tolerances causes conflicts with other components or aspects of the Work, the tolerance shall be reduced for that specific instance.

1-05.9 Equipment

The following new paragraph is inserted before the first paragraph: Prior to mobilizing equipment on site, the Contractor shall thoroughly remove all loose dirt and vegetative debris from drive mechanisms, wheels, tires, tracks, buckets and undercarriage. The Engineer will reject equipment from the site until it returns clean. This section is supplemented with the following: Upon completion of the Work, the Contractor shall completely remove all loose dirt and vegetative debris from equipment before removing it from the job site.

1-06 CONTROL OF MATERIAL (January 7, 2019 WSDOT 1-06.AP1)

1-06.1(3) Aggregate Source Approval (ASA) Database

This section is supplemented with the following: Regardless of status of the source, whether listed or not listed in the ASA database the source owner may be asked to provide testing results for toxicity in accordance with Section 9-03.21(1).

1-06.2(2)D Quality Level Analysis

This section is supplemented with the following new subsection:

1-06.2(2)D5 Quality Level Calculation – HMA Compaction

The procedures for determining the quality level and pay factor for HMA compaction are as follows: 1. Determine the arithmetic mean, Xm, for compaction of the lot:

Page 40: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-4

n

xX m

=

Where: x = individual compaction test values for each sublot in the lot. ∑x = summation of individual compaction test values n = total number test values 2. Compute the sample standard deviation, “S”, for each constituent:

( )

( )

2

122

1

−=

nn

xxnS

Where: ∑x2 = summation of the squares of individual compaction test values (∑x)2 = summation of the individual compaction test values squared 3. Compute the lower quality index (QL):

S

LSLXQ m

L

−=

Where: LSL = 92 4. Determine PL (the percent within the lower Specification limit which corresponds to a given QL) from Table 1. For negative values of QL, PL is equal to 100 minus the table PL. If the value of QL does not correspond exactly to a figure in the table, use the next higher value. 5. Determine the quality level (the total percent within Specification limits): Quality Level = PL 6. Using the quality level from step 5, determine the composite pay factor (CPF) from Table 2. 7. If the CPF determined from step 6 is 1.00 or greater: use that CPF for the compaction lot; however, the maximum HMA compaction CPF using an LSL = 92 shall be 1.05. 8. If the CPF from step 6 is not 1.00 or greater: repeat steps 3 through 6 using an LSL = 91.5. The value thus determined shall be the HMA compaction CPF for that lot; however, the maximum HMA compaction CPF using an LSL = 91.5 shall be 1.00.

1-06.2(2)D1 Quality Level Analysis

The following new sentence is inserted after the first sentence: The quality level calculations for HMA compaction are completed using the formulas in Section 1-06.2(2)D5

Page 41: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-5

1-06.2(2)D4 Quality Level Calculation

The first paragraph (excluding the numbered list) is revised to read: The procedures for determining the quality level and pay factors for a material, other than HMA compaction, are as follows:

1-06.6 Recycled Materials

The first three sentences of the second paragraph are revised to read: The Contractor shall submit a Recycled Material Utilization Plan on WSDOT Form 350-075A within 30 calendar days after the Contract is executed. The plan shall provide the Contractor’s anticipated usage of recycled concrete aggregates for meeting the requirements of these Specifications. The quantity of recycled concrete aggregate will be provided in tons and as a percentage of the Plan quantity for eligible material listed in Section 9-03.21(1)E Table on Maximum Allowable percent (By Weight) of Recycled Material. The last paragraph is revised to read: Within 30 calendar days after Physical Completion, the Contractor shall report the quantity of recycled concrete aggregates that were utilized in the construction of the project for each eligible item listed in Section 9-03.21(1)E. The Contractor’s report shall be provided on WSDOT Form 350-075A, Recycled Materials Reporting.

1-06.6(1)A General

Item 1(a) in the second paragraph is revised to read: a. The estimated costs for the Work for each material with 25 percent recycled concrete aggregate. The cost estimate shall include for each material a documented price quote from the supplier with the lowest total cost for the Work.

1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC (August 6, 2018 WSDOT 1-07.AP1)

1-07.5 Environmental Regulations

This section is supplemented with the following new subsections:

1-07.5(5) U.S. Army Corps of Engineers

When temporary fills are permitted, the Contractor shall remove fills in their entirety and the affected areas returned to pre-construction elevations. If a U.S. Army Corps of Engineers permit is noted in Section 1-07.6 of the Special Provisions, the Contractor shall retain a copy of the permit or the verification letter (in the case of a Nationwide Permit) on the worksite for the life of the Contract. The Contractor shall provide copies of the permit or verification letter to all subcontractors involved with the authorized work prior to their commencement of any work in waters of the U.S.

1-07.5(6) U.S. Fish/Wildlife Services and National Marine Fisheries Service

The Contracting Agency will provide fish exclusion and handling services if the Work dictates. However, if the Contractor discovers any fish stranded by the project and a Contracting Agency biologist is not available, they shall immediately release the fish into a flowing stream or open water.

Page 42: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-6

1-07.5(1) General

The first sentence is deleted and replaced with the following: No Work shall occur within areas under the jurisdiction of resource agencies unless authorized in the Contract. The third paragraph is deleted.

1-07.5(2) State Department of Fish and Wildlife

This section is revised to read: In doing the Work, the Contractor shall: 1. Not degrade water in a way that would harm fish, wildlife, or their habitat. 2. Not place materials below or remove them from the ordinary high water line except as may be specified in the Contract. 3. Not allow equipment to enter waters of the State except as specified in  the  Contract. 4. Revegetate in accordance with the Plans, unless the Special Provisions permit otherwise. 5. Prevent any fish-threatening silt buildup on the bed or bottom of any body of  water. 6. Ensure continuous stream flow downstream of the Work area. 7. Dispose of any project debris by removal, burning, or placement above high-water flows. 8. Immediately notify the Engineer and stop all work causing impacts, if at any time, as a result of project activities, fish are observed in distress or a fish kill occurs. If the Work in (1) through (3) above differs little from what the Contract requires, the Contracting Agency will measure and pay for it at unit Contract prices. But if Contract items do not cover those areas, the Contracting Agency will pay pursuant to Section 1-09.4. Work in (4) through (8) above shall be incidental to Contract pay items.

1-07.5(3) State Department of Ecology

This section is revised to read: In doing the Work, the Contractor shall: 1. Comply with Washington State Water Quality Standards. 2. Perform Work in such a manner that all materials and substances not specifically identified in the Contract documents to be placed in the water do not enter waters of the State, including wetlands. These include, but are not limited to, petroleum products, hydraulic fluid, fresh concrete, concrete wastewater, process wastewater, slurry materials and waste from shaft drilling, sediments, sediment-laden water, chemicals, paint, solvents, or other toxic or deleterious materials. 3. Use equipment that is free of external petroleum-based products.

Page 43: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-7

4. Remove accumulations of soil and debris from drive mechanisms (wheels, tracks, tires) and undercarriage of equipment prior to using equipment below the ordinary high water line. 5. Clean loose dirt and debris from all materials placed below the ordinary high water line. No materials shall be placed below the ordinary high water line without the Engineer’s concurrence. 6. When a violation of the Construction Stormwater General Permit (CSWGP) occurs, immediately notify the Engineer and fill out WSDOT Form 422-011, Contractor ECAP Report, and submit the form to the Engineer within 48 hours of the violation. 7. Once Physical Completion has been given, prepare a Notice of Termination (Ecology Form ECY 020-87) and submit the Notice of Termination electronically to the Engineer in a PDF format a minimum of 7 calendar days prior to submitting the Notice of Termination to Ecology. 8. Transfer the CSWGP coverage to the Contracting Agency when Physical Completion has been given and the Engineer has determined that the project site is not stabilized from erosion. 9. Submit copies of all correspondence with Ecology electronically to the Engineer in a PDF format within four calendar days.

1-07.5(4) Air Quality

This section is revised to read: The Contractor shall comply with all regional clean air authority and/or State Department of Ecology rules and regulations. The air quality permit process may include additional State Environment Policy Act (SEPA) requirements. Contractors shall contact the appropriate regional air pollution control authority well in advance of beginning Work. When the Work includes demolition or renovation of any existing facility or structure that contains Asbestos Containing Material (ACM) and/or Presumed Asbestos-Containing Material (PACM), the Contractor shall comply with the National Emission Standards for Hazardous Air Pollutants (NESHAP). Any requirements included in Federal and State regulations regarding air quality that applies to the “owner or operator” shall be the responsibility of the Contractor.

1-07.7(1) General

The first sentence of the third paragraph is revised to read: When the Contractor moves equipment or materials on or over Structures, culverts or pipes, the Contractor may operate equipment with only the load-limit restrictions in Section 1-07.7(2). The first sentence of the last paragraph is revised to read: Unit prices shall cover all costs for operating over Structures, culverts and pipes.

1-07.9(1) General

The last sentence of the sixth paragraph is revised to read: Generally, the Contractor initiates the request by preparing standard form 1444 Request for Authorization of Additional Classification and Rate, available at

Page 44: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-8

https://www.dol.gov/whd/recovery/dbsurvey/conformance.htm, and submitting it to the Engineer for further action.

1-07.9(2) Posting Notices

The second sentence of the first paragraph (up until the colon) is revised to read: The Contractor shall ensure the most current edition of the following are posted: In items 1 through 10, the revision dates are deleted.

1-07.11(2) Contractual Requirements

In this section, “creed” is revised to read “religion”. Item numbers 1 through 9 are revised to read 2 through 10, respectively. After the preceding Amendment is applied, the following new item number 1 is inserted: 1. The Contractor shall maintain a Work site that is free of harassment, humiliation, fear, hostility and intimidation at all times. Behaviors that violate this requirement include but are not limited to: a. Persistent conduct that is offensive and unwelcome. b. Conduct that is considered to be hazing. c. Jokes about race, gender, or sexuality that are offensive. d. Unwelcome, unwanted, rude or offensive conduct or advances of a sexual nature which interferes with a person’s ability to perform their job or creates an intimidating, hostile, or offensive work environment. e. Language or conduct that is offensive, threatening, intimidating or hostile based on race, gender, or sexual orientation. f. Repeating rumors about individuals in the Work Site that are considered to be harassing or harmful to the individual’s reputation.

1-07.11(5) Sanctions

This section is supplemented with the following: Immediately upon the Engineer’s request, the Contractor shall remove from the Work site any employee engaging in behaviors that promote harassment, humiliation, fear or intimidation including but not limited to those described in these specifications.

1-07.11(6) Incorporation of Provisions

The first sentence is revised to read: The Contractor shall include the provisions of Section 1-07.11(2) Contractual Requirements (1) through (5) and the Section 1-07.11(5) Sanctions in every subcontract including procurement of materials and leases of equipment.

1-07.15(1) Spill Prevention, Control, and Countermeasures Plan

The last sentence of the first paragraph is revised to read:

Page 45: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-9

An SPCC Plan template and guidance information is available at http://www.wsdot.wa.gov/environment/technical/disciplines/hazardous-materials/spill-prevent-report.

1-07.18 Public Liability and Property Damage Insurance

Item number 1 is supplemented with the following new sentence: This policy shall be kept in force from the execution date of the Contract until the Physical Completion Date.

1-08 PROSECUTION AND PROGRESS (January 7, 2019 WSDOT 1-08.AP1)

1-08.1 Subcontracting

The first sentence of the seventh paragraph is revised to read: All Work that is not performed by the Contractor will be considered as subcontracting except: (1) purchase of sand, gravel, crushed stone, crushed slag, batched concrete aggregates, ready-mix concrete, off-site fabricated structural steel, other off-site fabricated items, and any other materials supplied by established and recognized commercial plants; or (2) delivery of these materials to the Work site in vehicles owned or operated by such plants or by recognized independent or commercial hauling companies hired by those commercial plants. The following new paragraph is inserted after the seventh paragraph: The Contractor shall not use businesses (material suppliers, vendors, subcontractors, etc.) with federal purchasing exclusions. Businesses with exclusions are identified using the System for Award Management web page at www.SAM.gov.

1-08.5 Time for Completion

Item number 2 of the sixth paragraph is supplemented with the following: f. A copy of the Notice of Termination sent to the Washington State Department of Ecology (Ecology); the elapse of 30 calendar days from the date of receipt of the Notice of Termination by Ecology; and no rejection of the Notice of Termination by Ecology. This requirement will not apply if the Construction Stormwater General Permit is transferred back to the Contracting Agency in accordance with Section 8-01.3(16).

1-08.7 Maintenance During Suspension

The fifth paragraph is revised to read: The Contractor shall protect and maintain all other Work in areas not used by traffic. All costs associated with protecting and maintaining such Work shall be the responsibility of the Contractor.

1-09 MEASUREMENT AND PAYMENT (August 6, 2018 WSDOT 1-09.AP1)

1-09.2(1) General Requirements for Weighing Equipment

The last paragraph is supplemented with the following:

Page 46: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-10

When requested by the Engineer, the Contractor’s representative shall collect the tickets throughout the day and provide them to the Engineer’s designated receiver, not later than the end of shift, for reconciliation. Tickets for loads not verified as delivered will receive no pay.

1-09.2(2) Specific Requirements for Batching Scales

The last sentence of the first paragraph is revised to read: Batching scales used for concrete or hot mix asphalt shall not be used for batching other materials.

1-09.10 Payment for Surplus Processed Materials

The following sentence is inserted after the first sentence of the second paragraph: For Hot Mix Asphalt, the Plan quantity and quantity used will be adjusted for the quantity of Asphalt and quantity of RAP or other materials incorporated into the mix..

2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (April 2, 2018 WSDOT 2-02.AP2)

2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters

In item number 3 of the first paragraph, the second sentence is revised to read: For concrete pavement removal, a second vertical full depth relief saw cut offset 12 to 18 inches from and parallel to the initial saw cut is also required, unless the Engineer allows otherwise.

2-09 STRUCTURE EXCAVATION (April 2, 2018 WSDOT 2-09.AP2)

2-09.2 Materials

In the first paragraph, the references to “Portland Cement” and “Aggregates for Portland Cement Concrete” are revised to read: Cement 9-01 Fine Aggregate for Concrete 9-03.1(2)

2-09.3(3)D Shoring and Cofferdams

The first sentence of the sixth paragraph is revised to read: Structural shoring and cofferdams shall be designed for conditions stated in this Section using methods shown in Division I Section 5 of the AASHTO Standard Specifications for Highway Bridges Seventeenth Edition – 2002 for allowable stress design, or the AASHTO LRFD Bridge Design Specifications for load and resistance factor design.

3-01 PRODUCTION FROM QUARRY AND PIT SITES (April 2, 2018 WSDOT 3-01.AP3)

3-01.1 Description

The first paragraph is revised to read:

Page 47: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-11

This Work shall consist of manufacturing and producing crushed and screened aggregates including pit run aggregates of the kind, quality, and grading specified for use in the construction of concrete, hot mix asphalt, crushed surfacing, maintenance rock, ballast, gravel base, gravel backfill, gravel borrow, riprap, and bituminous surface treatments of all descriptions.

4-04 BALLAST AND CRUSHED SURFACING (April 2, 2018 WSDOT 4-04.AP4)

4-04.3(5) Shaping and Compaction

This section is supplemented with the following new paragraph: When using 100% Recycled Concrete Aggregate, the Contractor may submit a written request to use a test point evaluation for compaction acceptance testing in lieu of compacting to 95% of the standard density as determined by the requirements of Section 2-03.3(14)D. The test point evaluation shall be performed in accordance with SOP 738.

6-02 CONCRETE STRUCTURES (April 2, 2018 WSDOT 6-02.AP6)

6-02.1 Description

The first sentence is revised to read: This Work consists of the construction of all Structures (and their parts) made of portland cement or blended hydraulic cement concrete with or without reinforcement, including bridge approach slabs.

6-02.2 Materials

In the first paragraph, the references to “Portland Cement” and “Aggregates for Portland Cement Concrete” are revised to read: Cement 9-01 Aggregates for Concrete 9-03.1

6-02.3(2) Proportioning Materials

The second paragraph is revised to read: Unless otherwise specified, the Contractor shall use Type I or II portland cement or blended hydraulic cement in all concrete as defined in Section 9-01.2(1).

6-02.3(2)A Contractor Mix Design

The last sentence of the last paragraph is revised to read: For all other concrete, air content shall be a minimum of 4.5 percent and a maximum of 7.5 percent for all concrete placed above the finished ground line unless noted otherwise.

6-02.3(2)A1 Contractor Mix Design for Concrete Class 4000D

Item number 5 of the first paragraph is deleted.

Page 48: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-12

Item number 6 of the first paragraph (after the preceding Amendment is applied) is renumbered to 5.

6-02.3(2)B Commercial Concrete

The second paragraph is revised to read: Where concrete Class 3000 is specified for items such as, culvert headwalls, plugging culverts, concrete pipe collars, pipe anchors, monument cases, Type PPB, PS, I, FB and RM signal standards, pedestals, cabinet bases, guardrail anchors, fence post footings, sidewalks, concrete curbs, curbs and gutters, and gutters, the Contractor may use commercial concrete. If commercial concrete is used for sidewalks, concrete curbs, curbs and gutters, and gutters, it shall have a minimum cementitious material content of 564 pounds per cubic yard of concrete, shall be air entrained, and the tolerances of Section 6-02.3(5)C shall apply.

6-02.3(4)D Temperature and Time For Placement

The following is inserted after the first sentence of the first paragraph: The upper temperature limit for placement for Class 4000D concrete may be increased to a maximum of 80°F if allowed by the Engineer.

6-02.3(5)C Conformance to Mix Design

Item number 1 of the second paragraph is revised to read: 1. Cement weight plus 5 percent or minus 1 percent of that specified in the mix design.

6-02.3(6)A1 Hot Weather Protection

The first paragraph is revised to read: The Contractor shall provide concrete within the specified temperature limits. Cooling of the coarse aggregate piles by sprinkling with water is permitted provided the moisture content is monitored, the mixing water is adjusted for the free water in the aggregate and the coarse aggregate is removed from at least 1 foot above the bottom of the pile. Sprinkling of fine aggregate piles with water is not allowed. Refrigerating mixing water or replacing all or part of the mixing water with crushed ice is permitted, provided the ice is completely melted by placing time. The second sentence of the second paragraph is revised to read: These surfaces include forms, reinforcing steel, steel beam flanges, and any others that touch the concrete.

6-02.3(13)A Strip Seal Expansion Joint System

In item number 3 of the third paragraph, “Federal Standard 595” is revised to read “SAE AMS Standard 595”.

6-02.3(24)C Placing and Fastening

The fourth sentence of the second paragraph is revised to read: All epoxy-coated bars in the top mat of the bridge deck shall be tied at all intersections, however they may be tied at alternate intersections when spacing is less than 1 foot in each direction and they are supported by continuous supports meeting all other requirements of supports for epoxy-coated bars.

Page 49: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-13

The sixth paragraph (excluding the numbered list) is revised to read: Precast concrete supports (or other accepted devices) shall be used to maintain the concrete coverage required by the Plans. The precast concrete supports shall: Item number 2 of the sixth paragraph is revised to read: 2. Have a compressive strength equal to or greater than that of the concrete in which they are embedded. The first sentence of the seventh paragraph is revised to read: In slabs, each precast concrete support shall have either: (1) a grooved top that will hold the reinforcing bar in place, or (2) an embedded wire that protrudes and is tied to the reinforcing steel. The eighth paragraph is revised to read: Precast concrete supports may be accepted based on a Manufacturer’s Certificate of Compliance. The ninth paragraph (excluding the numbered list) is revised to read: In lieu of precast concrete supports, the Contractor may use metal or all-plastic supports to hold uncoated bars. Any surface of a metal support that will not be covered by at least ½ inch of concrete shall be one of the following: The tenth paragraph is revised to read: In lieu of precast concrete supports, epoxy-coated reinforcing bars may be supported by one of the following: 1. Metal supports coated entirely with a dielectric material such as epoxy or plastic, 2. Other epoxy-coated reinforcing bars, or 3. All-plastic supports. The following new paragraph is inserted after the tenth paragraph: Damaged coatings on metal bar supports shall be repaired prior to placing concrete. The twelfth paragraph (after the preceding Amendment is applied) is revised to read: All-plastic supports shall be lightweight, non-porous, and chemically inert in concrete. All-plastic supports shall have rounded seatings, shall not deform under load during normal temperatures, and shall not shatter or crack under impact loading in cold weather. All-plastic supports shall be placed at spacings greater than 1 foot along the bar and shall have at least 25 percent of their gross place area perforated to compensate for the difference in the coefficient of thermal expansion between plastic and concrete. The shape and configuration of all-plastic supports shall permit complete concrete consolidation in and around the support. The thirteenth paragraph (after the preceding Amendment is applied) is revised to read:

Page 50: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-14

A “mat” is two adjacent and perpendicular layers of reinforcing steel. In bridge decks, top and bottom mats shall be supported adequately enough to hold both in their proper positions. If bar supports directly support, or are directly supported on No. 4 bars, they shall be spaced at not more than 3-foot intervals (or not more than 4-foot intervals for bars No. 5 and larger). Wire ties to girder stirrups shall not be considered as supports. To provide a rigid mat, the Contractor shall add other supports and tie wires to the top mat as needed.

6-02.3(27) Concrete for Precast Units

The last sentence of the first paragraph is revised to read: Type III portland cement or blended hydraulic cement is permitted to be used in precast concrete units.

6-02.3(28)B Casting

In the second paragraph, the reference to Section 6-02.3(25)B is revised to read Section 6-02.3(25)C.

6-02.3(28)D Contractors Control Strength

In the first paragraph, “WSDOT FOP for AASHTO T 23” is revised to read “FOP for AASHTO T 23”.

8-01 EROSION CONTROL AND WATER POLLUTION CONTROL (April 2, 2018 WSDOT 8-01.AP8)

8-01.1 Description

This section is revised to read: This Work consists of furnishing, installing, maintaining, removing and disposing of best management practices (BMPs), as defined in the Washington Administrative Code (WAC) 173-201A, to manage erosion and water quality in accordance with these Specifications and as shown in the Plans or as designated by the Engineer. The Contracting Agency may have a National Pollution Discharge Elimination System Construction Stormwater General Permit (CSWGP) as identified in the Contract Special Provisions. The Contracting Agency may or may not transfer coverage of the CSWGP to the Contractor when a CSWGP has been obtained. The Contracting Agency may not have a CSWGP for the project but may have another water quality related permit as identified in the Contract Special Provisions or the Contracting Agency may not have water quality related permits but the project is subject to applicable laws for the Work. Section 8-01 covers all of these conditions.

8-01.2 Materials

The first paragraph is revised to read: Materials shall meet the requirements of the following sections: Corrugated Polyethylene Drain Pipe 9-05.1(6) Quarry Spalls 9-13 Erosion Control and Roadside Planting 9-14 Construction Geotextile 9-33

Page 51: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-15

8-01.3(1) General

This section is revised to read: Adaptive management shall be employed throughout the duration of the project for the implementation of erosion and water pollution control permit requirements for the current condition of the project site. The adaptive management includes the selection and utilization of BMPs, scheduling of activities, prohibiting unacceptable practices, implementing maintenance procedures, and other managerial practices that when used singularly or in combination, prevent or reduce the release of pollutants to waters of the State. The adaptive management shall use the means and methods identified in this section and means and methods identified in the Washington State Department of Transportation’s Temporary Erosion and Sediment Control Manual or the Washington State Department of Ecology’s Stormwater Management Manuals for construction stormwater. The Contractor shall install a high visibility fence along the site preservation lines shown in the Plans or as instructed by the Engineer. Throughout the life of the project, the Contractor shall preserve and protect the delineated preservation area, acting immediately to repair or restore any fencing damaged or removed. All discharges to surface waters shall comply with surface water quality standards as defined in Washington Administrative Code (WAC) Chapter 173-201A. All discharges to the ground shall comply with groundwater quality standards WAC Chapter 173-200. The Contractor shall comply with the CSWGP when the project is covered by the CSWGP. Temporary Work, at a minimum, shall include the implementation of: 1. Sediment control measures prior to ground disturbing activities to ensure all discharges from construction areas receive treatment prior to discharging from the site. 2. Flow control measures to prevent erosive flows from developing. 3. Water management strategies and pollution prevention measures to prevent contamination of waters that will be discharged to surface waters or the ground. 4. Erosion control measures to stabilize erodible earth not being worked. 5. Maintenance of BMPs to ensure continued compliant performance. 6. Immediate corrective action if evidence suggests construction activity is not in compliance. Evidence includes sampling data, olfactory or visual evidence such as the presence of suspended sediment, turbidity, discoloration, or oil sheen in discharges. To the degree possible, the Contractor shall coordinate this temporary Work with permanent drainage and erosion control Work the Contract requires. Clearing, grubbing, excavation, borrow, or fill within the Right of Way shall never expose more erodible earth than as listed below:

Western Washington (West of the Cascade Mountain Crest)

Eastern Washington (East of the Cascade Mountain Crest)

Page 52: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-16

May 1 through September 30

17 Acres April 1 through

October 31 17 Acres

October 1 through April 30

5 Acres November 1

through March 31

5 Acres

The Engineer may increase or decrease the limits based on project conditions. Erodible earth is defined as any surface where soils, grindings, or other materials may be capable of being displaced and transported by rain, wind, or surface water runoff. Erodible earth not being worked, whether at final grade or not, shall be covered within the specified time period (see the table below), using BMPs for erosion control.

Western Washington (West of the Cascade Mountain Crest)

Eastern Washington (East of the Cascade Mountain Crest)

October 1 through April 30

2 days maximum

October 1 through June 30

5 days maximum

May 1 to September 30

7 days maximum

November 1 through March 31

10 days maximum

When applicable, the Contractor shall be responsible for all Work required for compliance with the CSWGP including annual permit fees. If the Engineer, under Section 1-08.6, orders the Work suspended, the Contractor shall continue to comply with this division during the suspension. Nothing in this Section shall relieve the Contractor from complying with other Contract requirements.

8-01.3(1)A Submittals

This section’s content is deleted. This section is supplemented with the following new subsection:

8-01.3(1)A1 Temporary Erosion and Sediment Control

A Temporary Erosion and Sediment Control (TESC) plan consists of a narrative section and plan sheets that meets the Washington State Department of Ecology’s Stormwater Pollution Prevention Plan (SWPPP) requirement in the CSWGP. Abbreviated TESC plans are not required to include plan sheets and are used on small projects that disturb soil and have the potential to discharge but are not covered by the CSWGP. The contract uses the term “TESC plan” to describe both TESC plans and abbreviated TESC plans. When the Contracting Agency has developed a TESC plan for a Contract, the narrative is included in the appendix to the Special Provisions and the TESC plan sheets, when required, are included in the Contract Plans. The Contracting Agency TESC plan will not include off-site areas used to directly support construction activity. The Contractor shall either adopt the TESC Plan in the Contract or develop a new TESC Plan. If the Contractor adopts the Contracting Agency TESC Plan, the Contractor shall modify the TESC Plan to meet the Contractor’s schedule, method of construction, and to include off-site areas that

Page 53: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-17

will be used to directly support construction activity such as equipment staging yards, material storage areas, or borrow areas. Contractor TESC Plans shall include all high visibility fence delineation shown on the Contracting Agency Contract Plans. All TESC Plans shall meet the requirements of the current edition of the WSDOT Temporary Erosion and Sediment Control Manual M 3109 and be adaptively managed as needed throughout construction based on site inspections and discharge samples to maintain compliance with the CSWGP. The Contractor shall develop a schedule for implementation of the TESC work and incorporate it into the Contractor’s progress schedule. The Contractor shall submit their TESC Plan (either the adopted plan or new plan) and implementation schedule as Type 2 Working Drawings. At the request of the Engineer, updated TESC Plans shall be submitted as Type 1 Working Drawings.

8-01.3(1)B Erosion and Sediment Control (ESC) Lead

This section is revised to read: The Contractor shall identify the ESC Lead at the preconstruction discussions and in the TESC Plan. The ESC Lead shall have, for the life of the Contract, a current Certificate of Training in Construction Site Erosion and Sediment Control from a course approved by the Washington State Department of Ecology. The ESC Lead must be onsite or on call at all times throughout construction. The ESC Lead shall be listed on the Emergency Contact List required under Section 1-05.13(1). The ESC Lead shall implement the TESC Plan. Implementation shall include, but is not limited to: 1. Installing, adaptively managing, and maintaining temporary erosion and sediment control BMPs to assure continued performance of their intended function. Damaged or inadequate BMPs shall be corrected immediately. 2. Updating the TESC Plan to reflect current field conditions. 3. Discharge sampling and submitting Discharge Monitoring Reports (DMRs) to the Washington State Department of Ecology in accordance with the CSWGP. 4. Develop and maintain the Site Log Book as defined in the CSWGP. When the Site Log Book or portion thereof is electronically developed, the electronic documentation must be accessible onsite. As a part of the Site Log Book, the Contractor shall develop and maintain a tracking table to show that identified TESC compliance issues are fully resolved within 10 calendar days. The table shall include the date an issue was identified, a description of how it was resolved, and the date the issue was fully resolved. The ESC Lead shall also inspect all areas disturbed by construction activities, all on-site erosion and sediment control BMPs, and all stormwater discharge points at least once every calendar week and within 24-hours of runoff events in which stormwater discharges from the site. Inspections of temporarily stabilized, inactive sites may be reduced to once every calendar month. The Washington State Department of Ecology’s Erosion and Sediment Control Site Inspection Form, located at https://ecology.wa.gov/Regulations-Permits/Permits-certifications/Stormwater-general-permits/Construction-stormwater-permit, shall be completed for each inspection and a copy shall be submitted to the Engineer no later than the end of the next working day following the inspection.

Page 54: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-18

8-01.3(1)C Water Management

This section is supplemented with the following new subsections:

8-01.3(1)C5 Water Management for In-Water Work Below Ordinary High Water Mark (OHWM)

Work over surface waters of the state (defined in WAC 173-201A-010) or below the OHWM (defined in RCW 90.58.030) must comply with water quality standards for surface waters of the state of Washington.

8-01.3(1)C6 Environmentally Acceptable Hydraulic Fluid

All equipment containing hydraulic fluid that extends from a bridge deck over surface waters of the state or below the OHWM, shall be equipped with an environmentally acceptable hydraulic fluid. The fluid shall meet specific requirements for biodegradability, aquatic toxicity, and bioaccumulation in accordance with the United States Environmental Protection Agency (EPA) publication EPA800-R-11-002. Acceptance shall be in accordance with Section 1-06.3, Manufacturer’s Certification of Compliance. The designation of environmentally acceptable hydraulic fluid does not mean fluid spills are acceptable. The Contractor shall respond to spills to land or water in accordance with the Contract.

8-01.3(1)C7 Turbidity Curtain

All Work for the turbidity curtain shall be in accordance with the manufacturer’s recommendations for the site conditions. Removal procedures shall be developed and used to minimize silt release and disturbance of silt. The Contractor shall submit a Type 2 Working Drawing, detailing product information, installation and removal procedures, equipment and workforce needs, maintenance plans, and emergency repair/replacement plans. Turbidity curtain materials, installation, and maintenance shall be sufficient to comply with water quality standards. The Contractor shall notify the Engineer 10 days in advance of removing the turbidity curtain. All components of the turbidity curtain shall be removed from the project.

8-01.3(1)C1 Disposal of Dewatering Water

This section is revised to read: When uncontaminated groundwater is encountered in an excavation on a project it may be infiltrated within vegetated areas of the right of way not designated as Sensitive Areas or incorporated into an existing stormwater conveyance system at a rate that will not cause erosion or flooding in any receiving surface water. Alternatively, the Contractor may pursue independent disposal and treatment alternatives that do not use the stormwater conveyance system provided it is in compliance with the applicable WACs and permits.

8-01.3(1)C2 Process Wastewater

This section is revised to read: Wastewater generated on-site as a byproduct of a construction process shall not be discharged to surface waters of the State. Some sources of process wastewater may be infiltrated in accordance with the CSWGP with concurrence from the Engineer. Some sources of process wastewater may

Page 55: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-19

be disposed via independent disposal and treatment alternatives in compliance with the applicable WACs and permits.

8-01.3(1)C4 Management of Off-Site Water

This section is revised to read: Prior to clearing and grubbing, the Contractor shall intercept all sources of off-site surface water and overland flow that will run-on to the project. Off-site surface water run-on shall be diverted through or around the project in a way that does not introduce construction related pollution. It shall be diverted to its preconstruction discharge location in a manner that does not increase preconstruction flow rate and velocity and protects contiguous properties and waterways from erosion. The Contractor shall submit a Type 2 Working Drawing consisting of the method for performing this Work.

8-01.3(1)E Detention/Retention Pond Construction

This section is revised to read: Whether permanent or temporary, ponds shall be constructed before beginning other grading and excavation Work in the area that drains into that pond. Detention/retention ponds may be constructed concurrently with grading and excavation when allowed by the Engineer. Temporary conveyances shall be installed concurrently with grading in accordance with the TESC Plan so that newly graded areas drain to the pond as they are exposed.

8-01.3(2)F Dates for Application of Final Seed, Fertilizer, and Mulch

In the table, the second column heading is revised to read: Eastern Washington1 (East of the Cascade Mountain Crest) Footnote 1 in the table is revised to read: Seeding may be allowed outside these dates when allowed or directed by the Engineer.

8-01.3(5) Plastic Covering

The first sentence of the first paragraph is revised to read: Erosion Control – Plastic coverings used to temporarily cover stockpiled materials, slopes or bare soils shall be installed and maintained in a way that prevents water from intruding under the plastic and prevents the plastic cover from being damaged by wind.

8-01.3(7) Stabilized Construction Entrance

The first paragraph is revised to read: Temporary stabilized construction entrance shall be constructed in accordance with the Standard Plans, prior to construction vehicles entering the roadway from locations that generate sediment track out on the roadway. Material used for stabilized construction entrance shall be free of extraneous materials that may cause or contribute to track out.

8-01.3(8) Street Cleaning

This section is revised to read:

Page 56: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-20

Self-propelled pickup street sweepers shall be used to remove and collect dirt and other debris from the Roadway. The street sweeper shall effectively collect these materials and prevent them from being washed or blown off the Roadway or into waters of the State. Street sweepers shall not generate fugitive dust and shall be designed and operated in compliance with applicable air quality standards. Material collected by the street sweeper shall be disposed of in accordance with Section 2-03.3(7)C. When allowed by the Engineer, power broom sweepers may be used in non-environmentally sensitive areas. The broom sweeper shall sweep dirt and other debris from the roadway into the work area. The swept material shall be prevented from entering or washing into waters of the State. Street washing with water will require the concurrence of the Engineer.

8-01.3(12) Compost Socks

The first two sentences of the first paragraph are revised to read: Compost socks are used to disperse flow and sediment. Compost socks shall be installed as soon as construction will allow but before flow conditions create erosive flows or discharges from the site. Compost socks shall be installed prior to any mulching or compost placement.

8-01.3(13) Temporary Curb

The second to last sentence of the second paragraph is revised to read: Temporary curbs shall be a minimum of 4 inches in height.

8-01.3(14) Temporary Pipe Slope Drain

The third and fourth paragraphs are revised to read: The pipe fittings shall be water tight and the pipe secured to the slope with metal posts, wood stakes, sand bags, or as allowed by the Engineer. The water shall be discharged to a stabilized conveyance, sediment trap, stormwater pond, rock splash pad, or vegetated strip, in a manner to prevent erosion and maintain water quality compliance. The last paragraph is deleted.

8-01.3(15) Maintenance

This section is revised to read: Erosion and sediment control BMPs shall be maintained or adaptively managed as required by the CSWGP until the Engineer determines they are no longer needed. When deficiencies in functional performance are identified, the deficiencies shall be rectified immediately. The BMPs shall be inspected on the schedule outlined in Section 8-01.3(1)B for damage and sediment deposits. Damage to or undercutting of BMPs shall be repaired immediately. In areas where the Contractor’s activities have compromised the erosion control functions of the existing grasses, the Contractor shall overseed at no additional cost to the Contracting Agency. The quarry spalls of construction entrances shall be refreshed, replaced, or screened to maintain voids between the spalls for collecting mud and dirt.

Page 57: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-21

Unless otherwise specified, when the depth of accumulated sediment and debris reaches approximately ⅓ the height of the BMP the deposits shall be removed. Debris or contaminated sediment shall be disposed of in accordance with Section 2-03.3(7)C. Clean sediments may be stabilized on-site using BMPs as allowed by the Engineer.

8-01.3(16) Removal

This section is revised to read: The Contractor shall remove all temporary BMPs, all associated hardware and associated accumulated sediment deposition from the project limits prior to Physical Completion unless otherwise allowed by the Engineer. When the temporary BMP materials are made of natural plant fibers unaltered by synthetic materials the Engineer may allow leaving the BMP in place. The Contractor shall remove BMPs and associated hardware in a way that minimizes soil disturbance. The Contractor shall permanently stabilize all bare and disturbed soil after removal of BMPs. If the installation and use of the erosion control BMPs have compacted or otherwise rendered the soil inhospitable to plant growth, such as construction entrances, the Contractor shall take measures to rehabilitate the soil to facilitate plant growth. This may include, but is not limited to, ripping the soil, incorporating soil amendments, or seeding with the specified seed. At the request of the Contractor and at the sole discretion of the Engineer the CSWGP may be transferred back to the Contracting Agency. Approval of the Transfer of Coverage request will require the following: 1. All other Work required for Contract Completion has been completed. 2. All Work required for compliance with the CSWGP has been completed to the maximum extent possible. This includes removal of BMPs that are no longer needed and the site has undergone all Stabilization identified for meeting the requirements of Final Stabilization in the CSWGP. 3. An Equitable Adjustment change order for the cost of Work that has not been completed by the Contractor. 4. Submittal of the Washington State Department of Ecology Transfer of Coverage form (Ecology form ECY 020-87a) to the Engineer. If the Engineer approves the transfer of coverage back to the Contracting Agency, the requirement in Section 1-07.5(3) for the Contractor’s submittal of the Notice of Termination form to the Washington State Department of Ecology will not apply.

8-01.4 Measurement

This section’s content is deleted and replaced with the following new subsections:

8-01.4(1) Lump Sum Bid for Project (No Unit Items)

When the Bid Proposal contains the item “Erosion Control and Water Pollution Prevention” there will be no measurement of unit or force account items for Work defined in Section 8-01 except as described in Sections 8-01.4(3) and 8-01.4(4). Also, except as described in Section 8-01.4(3), all of Sections 8-01.4(2) and 8-01.5(2) are deleted.

Page 58: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-22

8-01.4(2) Item Bids

When the Proposal does not contain the items “Erosion Control and Water Pollution Prevention”, Section 8-01.4(1) and 8-01.5(1) are deleted and the Bid Proposal will contain some or all of the following items measured as noted. ESC lead will be measured per day for each day that an inspection is made and a report is filed. Biodegradable erosion control blanket and plastic covering will be measured by the square yard along the ground slope line of surface area covered and accepted. Turbidity curtains will be measured by the linear foot along the ground line of the installed curtain. Check dams will be measured per linear foot one time only along the ground line of the completed check dam. No additional measurement will be made for check dams that are required to be rehabilitated or replaced due to wear. Stabilized construction entrances will be measured by the square yard by ground slope measurement for each entrance constructed. Tire wash facilities will be measured per each for each tire wash installed. Street cleaning will be measured by the hour for the actual time spent cleaning pavement, refilling with water, dumping and transport to and from cleaning locations within the project limits, as authorized by the Engineer. Time to mobilize the equipment to or from the project limits on which street cleaning is required will not be measured. Inlet protections will be measured per each for each initial installation at a drainage structure. Silt fence, gravel filter, compost berms, and wood chip berms will be measured by the linear foot along the ground line of the completed barrier. Wattles and compost socks will be measured by the linear foot. Temporary curbs will be measured by the linear foot along the ground line of the completed installation. Temporary pipe slope drains will be measured by the linear foot along the flow line of the pipe. Coir logs will be measured by the linear foot along the ground line of the completed installation. Outlet protections will be measured per each initial installation at an outlet location. Tackifiers will be measure by the acre by ground slope measurement.

8-01.4(3) Reinstating Unit Items with Lump Sum Erosion Control and Water Pollution Prevention

The Contract Provisions may establish the project as lump sum, in accordance with Section 8-01.4(1) and also include one or more of the items included above in Section 8-01.4(2). When that occurs, the corresponding measurement provision in Section 8-01.4(2) is not deleted and the Work under that item will be measured as specified.

Page 59: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-23

8-01.4(4) Items not included with Lump Sum Erosion Control and Water Pollution Prevention

Compost blanket will be measured by the square yard by ground slope surface area covered and accepted. Mulching will be measured by the acre by ground slope surface area covered and accepted. Seeding, fertilizing, liming, mulching, and mowing, will be measured by the acre by ground slope measurement. Seeding and fertilizing by hand will be measured by the square yard by ground slope measurement. No adjustment in area size will be made for the vegetation free zone around each plant. Fencing will be measured by the linear foot along the ground line of the completed fence.

8-01.5 Payment

This section’s content is deleted and replaced with the following new subsections:

8-01.5(1) Lump Sum Bid for Project (No Unit Items)

Payment will be made for the following Bid item when it is included in the Proposal: “Erosion Control and Water Pollution Prevention”, lump sum. The lump sum Contract price for “Erosion Control and Water Pollution Prevention” shall be full pay to perform the Work as described in Section 8-01 except for costs compensated by Bid Proposal items inserted through Contract Provisions as described in Section 8-01.4(2). Progress payments for the lump sum item “Erosion Control and Water Pollution Prevention” will be made as follows: 1. The Contracting Agency will pay 15 percent of the bid amount for the initial set up for the item. Initial set up includes the following: a. Acceptance of the TESC Plan provided by the Contracting Agency or submittal of a new TESC Plan, b. Submittal of a schedule for the installation of the BMPs, and c. Identifying water quality sampling locations. 2. 70 percent of the bid amount will be paid in accordance with Section 1-09.9. 3. Once the project is physically complete and copies of the all reports submitted to the Washington State Department of Ecology have been submitted to the Engineer, and, if applicable, transference of the CSWGP back to the Contracting Agency is complete, the remaining 15 percent of the bid amount shall be paid in accordance with Section 1-09.9.

8-01.5(2) Item Bids

“ESC Lead”, per day. “Turbidity Curtain”, per linear foot. “Biodegradable Erosion Control Blanket”, per square yard.

Page 60: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-24

“Plastic Covering”, per square yard. “Check Dam”, per linear foot. “Inlet Protection”, per each. “Gravel Filter Berm”, per linear foot. “Stabilized Construction Entrance”, per square yard. “Street Cleaning”, per hour. “Silt Fence”, per linear foot. “Wood Chip Berm”, per linear foot. “Compost Berm”, per linear foot. “Wattle”, per linear foot. “Compost Sock”, per linear foot. “Coir Log”, per linear foot. “Temporary Curb”, per linear foot. “Temporary Pipe Slope Drain”, per linear foot. “Temporary Seeding”, per acre. “Outlet Protection”, per each. “Tackifier”, per acre. “Erosion/Water Pollution Control”, by force account as provided in Section 1-09.6. Maintenance and removal of erosion and water pollution control devices including removal and disposal of sediment, stabilization and rehabilitation of soil disturbed by these activities, and any additional Work deemed necessary by the Engineer to control erosion and water pollution will be paid by force account in accordance with Section 1-09.6. To provide a common Proposal for all Bidders, the Contracting Agency has entered an amount in the Proposal to become a part of the Contractor’s total Bid.

8-01.5(3) Reinstating Unit Items with Lump Sum Erosion Control and Water Pollution Prevention

The Contract may establish the project as lump sum, in accordance with Section 8-01.4(1) and also reinstate the measurement of one or more of the items described in Section 8-01.4(2), except for Erosion/Water Pollution Control, by force account. When that occurs, the corresponding payment provision in Section 8-01.5(2) is not deleted and the Work under that item will be paid as specified.

Page 61: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-25

8-01.5(4) Items not included with Lump Sum Erosion Control and Water Pollution Prevention

Payment will be made for each of the following Bid items when they are included in the Proposal: “Compost Blanket”, per square yard. “Mulching”, per acre “Mulching with PAM”, per acre “Mulching with Short-Term Mulch”, per acre. “Mulching with Moderate-Term Mulch”, per acre. “Mulching with Long-Term Mulch”, per acre. “Seeding, Fertilizing and Mulching”, per acre. “Seeding and Fertilizing”, per acre. “Seeding and Fertilizing by Hand”, per square yard. “Second Application of Fertilizer”, per acre. “Liming”, per acre. “Mowing”, per acre. “Seeding and Mulching”, per acre. “High Visibility Fence”, per linear foot.

8-02 ROADSIDE RESTORATION (January 2, 2018 WSDOT 8-02.AP8)

8-02.2 Materials

The reference to the material “Soil” is revised to read “Topsoil”.

8-02.5 Payment

The following new paragraph is inserted following the Bid item “Plant Selection ___”, per each: The unit Contract price for “Plant Selection ___”, per each shall be full pay for all Work to perform the work as specified within the planting area prior to planting for weed control, planting area preparation and installation of plants with initial watering. The paragraph following the Bid item “PSIPE ___”, per each is revised to read: The unit Contract price for “PSIPE ___”, per each, shall be full pay for all Work to perform the work as specified within the planting area for weed control and planting area preparation, planting, cleanup, and water necessary to complete planting operations as specified to the end of first year plant establishment.

Page 62: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-26

8-04 CURBS, GUTTERS, AND SPILLWAYS (April 2, 2018 WSDOT 8-04.AP8)

8-04.2 Materials

In the first paragraph, the reference to “Portland Cement” is revised to read: Cement 9-01

8-04.3(1) Cement Concrete Curbs, Gutters, and Spillways

The first paragraph is supplemented with the following: Roundabout truck apron cement concrete curb and gutter shall be constructed with air entrained concrete Class 4000 conforming to the requirements of Section 6-02.

8-06 CEMENT CONCRETE DRIVEWAY ENTRANCES (April 2, 2018 WSDOT 8-06.AP8)

8-04.2 Materials

In the first paragraph, the reference to “Portland Cement” is revised to read: Cement 9-01

8-04.3 Construction Requirements

The first paragraph is revised to read: Cement concrete driveway approaches shall be constructed with air entrained concrete Class 4000 conforming to the requirements of Section 6-02 or Portland Cement or Blended Hydraulic Cement Concrete Pavement conforming to the requirements of Section 5-05.

8-14 CEMENT CONCRETE SIDEWALKS (April 2, 2018 WSDOT 8-14.AP8)

8-14.2 Materials

In the first paragraph, the reference to “Portland Cement” is revised to read: Cement 9-01 In the second paragraph, each reference to “Federal Standard 595” is revised to read “SAE AMS Standard 595”.

8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION SYSTEMS, AND ELECTRICAL (August 6, 2018 WSDOT 8-20.AP8)

8-20.1(1) Regulations and Code

The last paragraph is revised to read: Persons performing electrical Work shall be certified in accordance with and supervised as required by RCW 19.28.161. Proof of certification shall be worn at all times in accordance with

Page 63: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-27

WAC 296-46B-942. Persons failing to meet these certification requirements may not perform any electrical work, and shall stop any active electrical work, until their certification is provided and worn in accordance with this Section.

8-20.2(2) Equipment List and Drawings

This section is renumbered:

8-20.2(1) Equipment List and Drawings

8-20.3(4) Foundations

The second sentence of the first paragraph is revised to read: Concrete for Type II, III, IV, V, and CCTV signal standards and light standard foundations shall be Class 4000P and does not require air entrainment.

8-20.3(5)A General

The last two sentences of the last paragraph is deleted. This section is supplemented with the following: All conduits shall include a pull tape with the equipment grounding conductor. The pull tape shall be attached to the conduit near the end bell or grounded end bushing, or to duct plugs or caps if present, at both ends of the conduit.

8-20.3(8) Wiring

The seventeenth paragraph is supplemented with the following: Pulling tape shall meet the requirements of Section 9-29.1(10). Pull string may not be used.

8-20.3(14)C Induction Loop Vehicle Detectors

Item number 2 is deleted. Item numbers 3 through 12 are renumbered to 2 through 11, respectively.

9-02 BITUMINOUS MATERIALS (January 7, 2019 WSDOT 9-02.AP9)

9-02.1 Asphalt Material, General

The second paragraph is revised to read: The Asphalt Supplier of Performance Graded (PG) asphalt binder and emulsified asphalt shall have a Quality Control Plan (QCP) in accordance with WSDOT QC 2 “Standard Practice for Asphalt Suppliers That Certify Performance Graded and Emulsified Asphalts”. The Asphalt Supplier’s QCP shall be submitted and receive the acceptance of the WSDOT State Materials Laboratory. Once accepted, any change to the QCP will require a new QCP to be submitted for acceptance. The Asphalt Supplier of PG asphalt binder and emulsified asphalt shall certify through the Bill of Lading that the PG asphalt binder or emulsified asphalt meets the Specification requirements of the Contract.

9-02.1(4) Performance Graded Asphalt Binder (PGAB)

This section’s title is revised to read:

Page 64: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-28

Performance Graded (PG) Asphalt Binder The first paragraph is revised to read: PG asphalt binder meeting the requirements of AASHTO M 332 Table 1 of the grades specified in the Contract shall be used in the production of HMA. For HMA with greater than 20 percent RAP by total weight of HMA, or any amount of RAS, the new asphalt binder, recycling agent and recovered asphalt (RAP and/or RAS) when blended in the proportions of the mix design shall meet the PG asphalt binder requirements of AASHTO M 332 Table 1 for the grade of asphalt binder specified by the Contract. The second paragraph, including the table, is revised to read: In addition to AASHTO M 332 Table 1 specification requirements, PG asphalt binders shall meet the following requirements:

Additional Requirements by Performance Grade (PG) Asphalt Binders

Property Test Method

PG58S-22

PG58H-22

PG58V-22

PG64S-28

PG64H-28

PG64V-28

RTFO Residue: Average Percent Recovery @ 3.2 kPa

AASHTO T 3501

30% Min.

20% Min.

25% Min.

30% Min.

1Specimen conditioned in accordance with AASHTO T 240 – RTFO.

The third paragraph is revised to read: The RTFO Jnrdiff and the PAV direct tension specifications of AASHTO M 332 are not required.

9-02.1(6) Cationic Emulsified Asphalt

This section is revised to read: Cationic Emulsified Asphalt meeting the requirements of AASHTO M 208 Table 1 of the grades specified in the Contract shall be used.

9-02.5 Warm Mix Asphalt (WMA) Additive

This section, including title, is revised to read:

9-02.5 HMA Additive

Additives for HMA shall be accepted by the Engineer.

9-03 AGGREGATES (January 7, 2019 WSDOT 9-03.AP9)

9-03.1 Aggregates for Portland Cement Concrete

This section’s title is revised to read:

Page 65: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-29

Aggregates for Concrete

9-03.1(1) General Requirements

The first two sentences of the first paragraph are revised to read: Concrete aggregates shall be manufactured from ledge rock, talus, or sand and gravel in accordance with the provisions of Section 3-01. Reclaimed aggregate may be used if it complies with the specifications for concrete. The second paragraph (up until the colon) is revised to read: Aggregates for concrete shall meet the following test requirements: The second sentence of the second to last paragraph is revised to read: The Contractor shall submit test results according to ASTM C1567 through the Engineer to the State Materials Laboratory that demonstrate that the proposed fly ash when used with the proposed aggregates and cement will control the potential expansion to 0.20 percent or less before the fly ash and aggregate sources may be used in concrete.

9-03.1(2) Fine Aggregate for Portland Cement Concrete

This section’s title is revised to read: Fine Aggregate for Concrete

9-03.1(4) Coarse Aggregate for Portland Cement Concrete

This section’s title is revised to read: Coarse Aggregate for Concrete

9-03.1(4)C Grading

The first paragraph (up until the colon) is revised to read: Coarse aggregate for concrete when separated by means of laboratory sieves shall conform to one or more of the following gradings as called for elsewhere in these Specifications, Special Provisions, or in the Plans:

9-03.1(5) Combined Aggregate Gradation for Portland Cement Concrete

This section’s title is revised to read: Combined Aggregate Gradation for Concrete

9-03.1(5)B Grading

In the last paragraph, “WSDOT FOP for WAQTC/AASHTO T 27/T 11” is revised to read “FOP for WAQTC/AASHTO T 27/T 11”.

9-03.2 Aggregate for Job-Mixed Portland Cement Mortar

This section’s title is revised to read: Aggregate for Job-Mixed Portland Cement or Blended Hydraulic Cement Mortar

Page 66: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-30

The first sentence of the first paragraph is revised to read: Fine aggregate for portland cement or blended hydraulic cement mortar shall consist of sand or other inert materials, or combinations thereof, accepted by the Engineer, having hard, strong, durable particles free from adherent coating.

9-03.4(1) General Requirements

The first paragraph (up until the colon) is revised to read: Aggregate for bituminous surface treatment shall be manufactured from ledge rock, talus, or gravel, in accordance with Section 3-01. Aggregates for Bituminous Surface Treatment shall meet the following test requirements:

9-03.8(1) General Requirements

The first paragraph (up until the colon) is revised to read: Aggregates for Hot Mix Asphalt shall meet the following test requirements:

9-03.8(2) HMA Test Requirements

The two tables in the second paragraph are replaced with the following three tables:

Mix Criteria HMA Class 3∕8 inch ½ inch ¾ inch 1 inch Min. Max. Min. Max. Min. Max. Min. Max.

Voids in Mineral Aggregate (VMA), %

15.0 14.0 13.0 12.0

Voids Filled With Asphalt (VFA), % ESAL’s (millions) VFA < 0.3 70 80 70 80 70 80 67 80 0.3 to < 3 65 78 65 78 65 78 65 78 ≥ 3 73 76 65 75 65 75 65 75 Dust/Asphalt Ratio 0.6 1.6 0.6 1.6 0.6 1.6 0.6 1.6

Test Method ESAL’s (millions) Number of Passes Hamburg Wheel-Track Testing, FOP for AASHTO T 324 Minimum Number of Passes with no Stripping Inflection Point and Maximum Rut Depth of 10mm

< 0.3 10,000

0.3 to < 3 12,500

≥ 3 15,000

Indirect Tensile (IDT) Strength (psi) of Bituminous Materials FOP for ASTM D6931

175 Maximum

ESAL’s

(millions) N initial N design N maximum

% Gmm < 0.3 ≤ 91.5 96.0 ≤ 98.0 0.3 to < 3 ≤ 90.5 96.0 ≤ 98.0 ≥ 3 ≤ 89.0 96.0 ≤ 98.0

Gyratory Compaction (number of gyrations)

< 0.3 6 50 75 0.3 to < 3 7 75 115 > 3 8 100 160

Page 67: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-31

9-03.8(7) HMA Tolerances and Adjustments

In the table in item number 1, the fifth row is revised to read: Asphalt binder -0.4% to 0.5% 0.7%

In the table in item number 1, the following new row is inserted before the last row: Voids in Mineral Aggregate, VMA

-1.5%

9-03.9(1) Ballast

The second paragraph (up until the colon) is revised to read: Aggregates for ballast shall meet the following test requirements:

9-03.14(4) Gravel Borrow for Structural Earth Wall

The second sentence of the first paragraph is revised to read: The material shall be substantially free of shale or other soft, poor durability particles, and shall not contain recycled materials, such as glass, shredded tires, concrete rubble, or asphaltic concrete rubble.

9-03.21(1)B Recycled Concrete Aggregate Approval and Acceptance

The first sentence of the second paragraph is revised to read: Recycled concrete aggregate may be used as coarse aggregate or blended with coarse aggregate for Commercial Concrete, Class 3000 concrete, or Cement Concrete Pavement. Item number 4 of the second paragraph is revised to read: 4. For Cement Concrete Pavement mix designs using recycled concrete aggregates, the Contractor shall submit evidence that ASR mitigating measures control expansion in accordance with Section 9-03.1(1). This section is supplemented with the following new subsection:

9-03.21(1)B1 Recycled Concrete Aggregate Approval and Acceptance

Recycled concrete aggregate may be approved through a three tiered system that consists of the following:

Tier 1 Approval Requirements

Approval of the Reclamation Facility is not required.

Acceptance Requirements

Certification of toxicity characteristics in accordance with Section 9-03.21(1). Field acceptance testing in accordance with Section 3-04.

Approved to provide the following Aggregate Materials: 9-03.10 Aggregate for Gravel Base 9-03.12(1)B Gravel Backfill for Foundations Class B

Page 68: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-32

9-03.12(2) Gravel Backfill for Walls 9-03.12(3) Gravel Backfill for Pipe Zone Bedding 9-03.14(1) Gravel Borrow 9-03.14(2) Select Borrow 9-03.14(2) Select Borrow (greater than 3 feet below subgrade and side slope) 9-03.14(3) Common Borrow 9-03.14(3) Common Borrow (greater than 3 feet below subgrade and side slope) 9-03.17 Foundation Material Class A and Class B 9-03.18 Foundation Material Class C 9-03.19 Bank Run Gravel for Trench Backfill

Tier 2 Approval Requirements

The Reclamation Facility shall have a Quality Control Plan (QCP) in accordance with WSDOT QC 9 “Standard Practice for Approval of Reclamation Facilities of WSDOT Recycled Concrete and Returned Concrete”. The Reclamation Facility’s QCP shall be submitted and approved by the WSDOT State Materials Laboratory. Once accepted, any changes to the QCP will require a new QCP to be submitted for acceptance. Evaluation of aggregate source properties (LA Wear and Degradation) for the recycled concrete aggregate is not required.

Acceptance Requirements

Certification of toxicity characteristics in accordance with Section 9-03.21(1), required if requested. Field acceptance testing in accordance with Section 3-04 is required. Provide certification in accordance with WSDOT QC 9 for every lot. A lot shall be no larger than 10,000 tons.

Approved to provide the following Aggregate Materials: Tier 1 aggregate materials 9-03.1 Coarse Aggregate for Commercial Concrete or Concrete class 3000 9-03.9(1) Ballast 9-03.9(2) Permeable Ballast 9-03.9(3) Crushed Surfacing 9-03.12(1)A Gravel Backfill for Foundations Class A

Tier 3 Approval Requirements

The Reclamation Facility shall have a Quality Control Plan (QCP) in accordance with WSDOT QC 10 “Standard Practice for Approval of Reclamation Facilities of Recycled Concrete Aggregates from Stockpiles of Unknown Sources”. The Reclamation Facility’s QCP shall be submitted and approved by the WSDOT State Materials Laboratory. Once accepted, any changes to the QCP will require a new QCP to be submitted for acceptance. Evaluation of aggregate source properties (LA Wear and Degradation) for the recycled concrete aggregate is required.

Acceptance Requirements

Certification of toxicity characteristics in accordance with Section 9-03.21(1) is required. Field acceptance testing in accordance with Section 3-04 is required. Provide certification in accordance with WSDOT QC 10 for every lot. A lot shall be no larger than 10,000 tons

Approved to provide the following Aggregate Materials: Tier 1 aggregate materials 9-03.1 Coarse Aggregate for Commercial Concrete or Concrete class 3000 9-03.9(1) Ballast 9-03.9(2) Permeable Ballast

Page 69: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-33

9-03.9(3) Crushed Surfacing 9-03.12(1)A Gravel Backfill for Foundations Class A

For Reclamation Facilities that do not participate in Tier 2 and Tier 3, approval of recycled concrete aggregate will be in accordance with Section 9-03.21(1), and acceptance will be in accordance with Section 3-04.

9-03.21(1)E Table on Maximum Allowable percent (By Weight) of Recycled Material

“Portland Cement” is deleted from the first two rows in the table. The following new row is inserted after the second row:

Coarse Aggregate for Concrete Pavement 9-03.1(4) 0 100 0 0 The first column of the third row is revised to read: Coarse Aggregate for Commercial Concrete and Class 3000 Concrete.

9-04 JOINT AND CRACK SEALING MATERIALS (January 7, 2019 WSDOT 9-04.AP9)

This section’s title is revised to read: Joint Sealing Materials

9-04.1(2) Premolded Joint Filler for Expansion Joints

In this section, each reference to “AASHTO T 42” is revised to read “ASTM D 545”.

9-04.2(1)A1 Hot Poured Sealant for Cement Concrete Pavement

This section is supplemented with the following: Hot poured sealant for cement concrete pavement is acceptable for installations in joints where cement concrete pavement abuts a bituminous pavement.

9-04.2(1)A2 Hot Poured Sealant for Bituminous Pavement

This section is supplemented with the following: Hot poured sealant for bituminous pavement is acceptable for installations in joints where cement concrete pavement abuts a bituminous pavement.

9-04.2(1)B Sand Slurry for Bituminous Pavement

Item number 2 of the first paragraph is revised to read: 2. Two percent portland cement or blended hydraulic cement, and

9-04.3 Joint Mortar

The first paragraph is revised to read: Mortar for hand mortared joints shall conform to Section 9-20.4(3) and consist of one part portland cement or blended hydraulic cement, three parts fine sand, and sufficient water to allow proper workability.

Page 70: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-34

9-04.5 Flexible Plastic Gaskets

In the table, the Test Method value for Specific Gravity at 77°F is revised to read “ASTM D71”. In the table, the Test Method value for Flash Point COC, F is revised to read “ASTM D93 REV A”. In the table, the Test Method value for Volatile Matter is revised to read “ASTM D6”.

9-06 STRUCTURAL STEEL AND RELATED MATERIALS (January 2, 2018 WSDOT 9-06.AP9)

9-06.5 Bolts

This section’s title is revised to read:

Bolts and Rods

9-06.5(4) Anchor Bolts

This section, including title, is revised to read:

9-06.5(4) Anchor Bolts and Anchor Rods

Anchor bolts and anchor rods shall meet the requirements of ASTM F1554 and, unless otherwise specified, shall be Grade 105 and shall conform to Supplemental Requirements S2, S3, and S4. Nuts for ASTM F1554 Grade 105 black anchor bolts and anchor rods shall conform to ASTM A563, Grade D or DH. Nuts for ASTM F1554 Grade 105 galvanized anchor bolts and anchor rods shall conform to either ASTM A563, Grade DH, or AASHTO M292, Grade 2H, and shall conform to the overtapping, lubrication, and rotational testing requirements in Section 9-06.5(3). Nuts for ASTM F1554 Grade 36 or 55 black or galvanized anchor bolts and anchor rods shall conform to ASTM A563, Grade A or DH. Washers shall conform to ASTM F436. The bolts and rods shall be tested by the manufacturer in accordance with the requirements of the pertinent Specification and as specified in these Specifications. Anchor bolts, anchor rods, nuts, and washers shall be inspected prior to shipping to the project site. The Contractor shall submit to the Engineer for acceptance a Manufacturer’s Certificate of Compliance for the anchor bolts, anchor rods, nuts, and washers, as defined in Section 1-06.3. If the Engineer deems it appropriate, the Contractor shall provide a sample of the anchor bolt, anchor rod, nut, and washer for testing. All bolts, rods, nuts, and washers shall be marked and identified as required in the pertinent Specification.

9-29 ILLUMINATION, SIGNAL, ELECTRICAL (April 2, 2018 WSDOT 9-29.AP9)

9-29.1 Conduit, Innerduct, and Outerduct

This section is supplemented with the following new subsection:

Page 71: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-35

9-29.1(10) Pull Tape

Pull tape shall be pre-lubricated polyester pulling tape. The pull tape shall have a minimum width of ½-inch and a minimum tensile strength of 500 pounds. Pull tape may have measurement marks.

9-29.2(1) Junction Boxes

The first paragraph is revised to read: For the purposes of this Specification concrete is defined as portland cement or blended hydraulic cement concrete and non-concrete is all others.

9-29.2(1)A2 Non-Concrete Junction Boxes

The first paragraph is revised to read: Material for the non-concrete junction boxes shall be of a quality that will provide for a similar life expectancy as portland cement or blended hydraulic cement concrete in a direct burial application.

9-29.2(2)A Standard Duty Cable Vaults and Pull Boxes

In the table in the last paragraph, the fourth, fifth and sixth rows are revised to read:

Slip Resistant Lid ASTM A36 steel Frame ASTM A36 steel Slip Resistant Frame ASTM A36 steel

9-29.6(5) Foundation Hardware

In the last paragraph, “AASHTO M232” is revised to read “ASTM F 2329”.

9-29.12 Electrical Splice Materials

This section is supplemented with the following new subsections:

9-29.12(3) Splice Enclosures

9-29.12(3)A Heat Shrink Splice Enclosure

Heat shrink splice enclosures shall be medium or heavy wall cross-linked polyolefin, meeting the requirements of AMS-DTL-23053/15, with thermoplastic adhesive sealant. Heat shrink splices used for “wye” connections require rubber electrical mastic tape.

9-29.12(3)B Molded Splice Enclosure

Molded splice enclosures shall use epoxy resin in a clear rigid plastic mold. The material used shall be compatible with the insulation material of the insulated conductor or cable. The component materials of the resin insulation shall be packaged ready for convenient mixing without removing from the package.

9-29.12(4) Re-Enterable Splice Enclosure

Re-enterable splice enclosures shall use either dielectric grease or a flexible resin contained in a two-piece plastic mold. The mold shall either snap together or use stainless steel hose clamps.

9-29.12(5) Vinyl Electrical Tape for Splices

Vinyl electrical tape in splicing applications shall meet the requirements of MIL-I-24391C.

Page 72: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-36

9-29.12(1) Illumination Circuit Splices

This section is revised to read: Underground illumination circuit splices shall be solderless crimped connections capable of securely joining the wires, both mechanically and electrically, as defined in Section 8-20.3(8). Aerial illumination splices shall be solderless crimp connectors or split bolt vice-type connectors.

9-29.12(1)A Heat Shrink Splice Enclosure

This section is deleted in its entirety.

9-29.12(1)B Molded Splice Enclosure

This section is deleted in its entirety.

9-29.24 Service Cabinets

The third sentence of item number 6 is revised to read: The dead front cover shall have cutouts for the entire breaker array, with blank covers where no circuit breakers are installed. Item number 8 is revised to read: 8. Lighting contactors shall meet the requirements of Section 9-29.24(2). The last sentence of item number 10 is revised to read: Dead front panels shall prevent access to any exposed, live components, and shall cover all equipment except for circuit breakers (including blank covers), the photocell test/bypass switch, and the GFCI receptacle.

9-29.24(2) Electrical Circuit Breakers and Contactors

This section is revised to read: All circuit breakers shall be bolt-on type, with the RMS-symmetrical interrupting capacity described in this Section. Circuit breakers for 120/240/277 volt circuits shall be rated at 240 or 277 volts, as applicable, with an interrupting capacity of not less than 10,000 amperes. Circuit breakers for 480 volt circuits shall be rated at 480 volts, and shall have an interrupting capacity of not less than 14,000 amperes. Lighting contactors shall be rated for tungsten or ballasted (such as sodium vapor, mercury vapor, metal halide, and fluorescent) lamp loads. Contactors for 120/240/277 volt circuits shall be rated at 240 volts maximum line to line voltage, or 277 volts maximum line to neutral voltage, as applicable. Contactors for 480 volt circuits shall be rated at 480 volt maximum line to line voltage.

9-34 PAVEMENT MARKING MATERIAL (January 2, 2018 WSDOT 9-34.AP9)

9-34.2(2) Color

Each reference to “Federal Standard 595” is revised to read “SAE AMS Standard 595”.

Page 73: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-37

9-34.3 Plastic

In the first sentence of the last paragraph, “Federal Standard 595” is revised to read “SAE AMS Standard 595”.

9-34.3(2) Type B – Pre-Formed Fused Thermoplastic

In the last two paragraphs, each reference to “Federal Standard 595” is revised to read “SAE AMS Standard 595”.

9-34.7(1) Requirements

The first paragraph is revised to read: Field performance evaluation is required for low VOC solvent-based paint per Section 9-34.2(4), Type A – liquid hot applied thermoplastic per Section 9-34.3(1), Type B – preformed fused thermoplastic per Section 9-34.3(2), Type C – cold applied preformed tape per Section 9-34.3(3), and Type D – liquid applied methyl methacrylate per Section 9-34.3(4). The last paragraph is deleted.

9-34.7(1)C Auto No-Track Time

The first paragraph is revised to read: Auto No-Track Time will only be required for low VOC solvent-based paint in accordance with Section 9-34.2(4). The second and third sentences of the second paragraph are deleted.

Page 74: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-38

SPECIAL PROVISIONS

INTRODUCTION TO THE SPECIAL PROVISIONS (August 14, 2013 APWA GSP)

The work on this project shall be accomplished in accordance with the Standard Specifications for Road, Bridge and Municipal Construction, 2018 edition, as issued by the Washington State Department of Transportation (WSDOT) and the American Public Works Association (APWA), Washington State Chapter (hereafter “Standard Specifications”). The Standard Specifications, as modified or supplemented by the Amendments to the Standard Specifications and these Special Provisions, all of which are made a part of the Contract Documents, shall govern all of the Work. These Special Provisions are made up of both General Special Provisions (GSPs) from various sources, which may have project-specific fill-ins; and project-specific Special Provisions. Each Provision either supplements, modifies, or replaces the comparable Standard Specification, or is a new Provision. The deletion, amendment, alteration, or addition to any subsection or portion of the Standard Specifications is meant to pertain only to that particular portion of the section, and in no way should it be interpreted that the balance of the section does not apply. The project-specific Special Provisions are not labeled as such. The GSPs are labeled under the headers of each GSP, with the effective date of the GSP and its source. For example: (March 8, 2013 APWA GSP) (April 1, 2013 WSDOT GSP) (May 1, 2013 Lacey GSP) Also incorporated into the Contract Documents by reference are: Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted edition, with Washington State modifications, if any Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current edition City of Lacey Development Guidelines and Public Works Standards, current edition Contractor shall obtain copies of these publications, at Contractor’s own expense.

DESCRIPTION OF WORK This contract provides for construction of standby generator improvements at seven (7) lift stations including Lift Station 4, Lift Station 5, Lift Station 8, Lift Station 11, Lift Station 17, Lift Station 24, and Lift Station 27. Standby generator improvements at each lift station generally include provision and installation of a standby generator, automatic transfer switch, service entrance disconnect, and concrete generator pad. At Lift Station 27, standby generator shall be provided by the City for installation by the Contractor.

Page 75: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-39

1-01 DEFINITIONS AND TERMS

1-01.3 Definitions

(January 4, 2016 APWA GSP)

Delete the heading Completion Dates and the three paragraphs that follow it, and replace them with the following: Dates Bid Opening Date The date on which the Contracting Agency publicly opens and reads the Bids. Award Date The date of the formal decision of the Contracting Agency to accept the lowest responsible and responsive Bidder for the Work. Contract Execution Date The date the Contracting Agency officially binds the Agency to the Contract. Notice to Proceed Date The date stated in the Notice to Proceed on which the Contract time begins. Substantial Completion Date The day the Engineer determines the Contracting Agency has full and unrestricted use and benefit of the facilities, both from the operational and safety standpoint, any remaining traffic disruptions will be rare and brief, and only minor incidental work, replacement of temporary substitute facilities, plant establishment periods, or correction or repair remains for the Physical Completion of the total Contract. Physical Completion Date The day all of the Work is physically completed on the project. All documentation required by the Contract and required by law does not necessarily need to be furnished by the Contractor by this date. Completion Date The day all the Work specified in the Contract is completed and all the obligations of the Contractor under the contract are fulfilled by the Contractor. All documentation required by the Contract and required by law must be furnished by the Contractor before establishment of this date. Final Acceptance Date The date on which the Contracting Agency accepts the Work as complete. Supplement this Section with the following: All references in the Standard Specifications, Amendments, or WSDOT General Special Provisions, to the terms “Department of Transportation”, “Washington State Transportation Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, “Headquarters”, and “State Treasurer” shall be revised to read “Contracting Agency”.

Page 76: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-40

All references to the terms “State” or “state” shall be revised to read “Contracting Agency” unless the reference is to an administrative agency of the State of Washington, a State statute or regulation, or the context reasonably indicates otherwise. All references to “State Materials Laboratory” shall be revised to read “Contracting Agency designated location”. All references to “final contract voucher certification” shall be interpreted to mean the Contracting Agency form(s) by which final payment is authorized, and final completion and acceptance granted. Additive A supplemental unit of work or group of bid items, identified separately in the Bid Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition to the base bid. Alternate One of two or more units of work or groups of bid items, identified separately in the Bid Proposal, from which the Contracting Agency may make a choice between different methods or material of construction for performing the same work. Business Day A business day is any day from Monday through Friday except holidays as listed in Section 1-08.5. Contract Bond The definition in the Standard Specifications for “Contract Bond” applies to whatever bond form(s) are required by the Contract Documents, which may be a combination of a Payment Bond and a Performance Bond. Contract Documents See definition for “Contract”. Contract Time The period of time established by the terms and conditions of the Contract within which the Work must be physically completed. Notice of Award The written notice from the Contracting Agency to the successful Bidder signifying the Contracting Agency’s acceptance of the Bid Proposal. Notice to Proceed The written notice from the Contracting Agency or Engineer to the Contractor authorizing and directing the Contractor to proceed with the Work and establishing the date on which the Contract time begins. Traffic Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and equestrian traffic.

1-02 BID PROCEDURES AND CONDITIONS

1-02.1 Prequalification of Bidders

Delete this Section and replace it with the following:

Page 77: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-41

1-02.1 Qualifications of Bidder

(January 24, 2011 APWA GSP)

Before award of a public works contract, a bidder must meet at least the minimum qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified to be awarded a public works project.

1-02.1(1) Supplemental Qualifications Criteria

(July 31, 2017 APWA GSP)

In addition, the Contracting Agency has established Contracting Agency-specific and/or project-specific supplemental criteria, in accordance with RCW 39.04.350(3), for determining Bidder responsibility, including the basis for evaluation and the deadline for appealing a determination that a Bidder is not responsible. These criteria are contained in Section 1-02.14 Option C of these Special Provisions.

1-02.2 Plans and Specifications

(June 27, 2011 APWA GSP)

Delete this section and replace it with the following: Information as to where Bid Documents can be obtained or reviewed will be found in the Call for Bids (Advertisement for Bids) for the work. After award of the contract, plans and specifications will be issued to the Contractor at no cost as detailed below: To Prime Contractor No. of Sets Basis of Distribution

Reduced plans (11" x 17") 3 Furnished automatically upon award

Contract Provisions 3 Furnished automatically upon award

Large plans (22" x 34") 3 Furnished only upon request

Additional plans and Contract Provisions may be obtained by the Contractor from the source stated in the Call for Bids, at the Contractor’s own expense.

1-02.4 Examination of Plans, Specifications and Site of Work

1-02.4(1) General

(August 15, 2016 APWA GSP Option A)

The first sentence of the last paragraph is revised to read: Any prospective Bidder desiring an explanation or interpretation of the Bid Documents, must request the explanation or interpretation in writing soon enough to allow a written reply to reach all prospective Bidders before the submission of their Bids.

1-02.4(2) Subsurface Information

(March 8, 2013 APWA GSP)

Page 78: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-42

The second sentence in the first paragraph is revised to read: The Summary of Geotechnical Conditions and the boring logs, if and when included as an appendix to the Special Provisions, shall be considered as part of the Contract.

1-02.5 Proposal Forms

(July 31, 2017 APWA GSP)

Delete this section and replace it with the following: The Proposal Form will identify the project and its location and describe the work. It will also list estimated quantities, units of measurement, the items of work, and the materials to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal form that call for, but are not limited to, unit prices; extensions; summations; the total bid amount; signatures; date; and, where applicable, retail sales taxes and acknowledgment of addenda; the bidder’s name, address, telephone number, and signature; the bidder’s UDBE/DBE/M/WBE commitment, if applicable; a State of Washington Contractor’s Registration Number; and a Business License Number, if applicable. Bids shall be completed by typing or shall be printed in ink by hand, preferably in black ink. The required certifications are included as part of the Proposal Form. The Contracting Agency reserves the right to arrange the proposal forms with alternates and additives, if such be to the advantage of the Contracting Agency. The bidder shall bid on all alternates and additives set forth in the Proposal Form unless otherwise specified.

1-02.6 Preparation of Proposal

(June 20, 2017 APWA GSP)

Supplement the second paragraph with the following: 4. If a minimum bid amount has been established for any item, the unit or lump sum price must equal or exceed the minimum amount stated. 5. Any correction to a bid made by interlineation, alteration, or erasure, shall be initialed by the signer of the bid. Delete the fourth paragraph and replace it with the following: The Bidder shall submit with the Bid a completed Underutilized Disadvantaged Business Enterprise (UDBE) Utilization Certification, when required by the Special Provisions. For each and every UDBE firm listed on the Bidder’s completed Underutilized Disadvantaged Business Enterprise Utilization Certification, the Bidder shall submit written confirmation from that UDBE firm that the UDBE is in agreement with the UDBE participation commitment that the Bidder has made in the Bidder’s completed Underutilized Disadvantaged Business Enterprise Utilization Certification. WSDOT Form 422-031U (Underutilized Disadvantaged Business Enterprise Written Confirmation Document) is to be used for this purpose. Bidder must submit good faith effort documentation with the Underutilized Disadvantaged Business Enterprise Utilization Certification only in the event the bidder’s efforts to solicit sufficient UDBE participation have been unsuccessful. Directions for delivery of the Underutilized Disadvantaged Business Enterprise Written Confirmation Documents and Underutilized Disadvantaged Business Enterprise Good Faith Effort documentation are included in Sections 1-02.9 Delete the last paragraph, and replace it with the following: The Bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner.

Page 79: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-43

A bid by a corporation shall be executed in the corporate name, by the president or a vice president (or other corporate officer accompanied by evidence of authority to sign). A bid by a partnership shall be executed in the partnership name, and signed by a partner. A copy of the partnership agreement shall be submitted with the Bid Form if any UDBE requirements are to be satisfied through such an agreement. A bid by a joint venture shall be executed in the joint venture name and signed by a member of the joint venture. A copy of the joint venture agreement shall be submitted with the Bid Form if any UDBE requirements are to be satisfied through such an agreement.

1-02.6 Preparation of Proposal

(August 2, 2004 WSDOT 1-02.6OPT15.GR1)

The fifth and sixth paragraphs of Section 1-02.6 are deleted.

1-02.7 Bid Deposit

(March 8, 2013 APWA GSP)

Supplement this section with the following: Bid bonds shall contain the following:

1. Contracting Agency-assigned number for the project; 2. Name of the project; 3. The Contracting Agency named as obligee; 4. The amount of the bid bond stated either as a dollar figure or as a percentage which

represents five percent of the maximum bid amount that could be awarded; 5. Signature of the bidder’s officer empowered to sign official statements. The signature of

the person authorized to submit the bid should agree with the signature on the bond, and the title of the person must accompany the said signature;

6. The signature of the surety’s officer empowered to sign the bond and the power of attorney.

If so stated in the Contract Provisions, bidder must use the bond form included in the Contract Provisions. If so stated in the Contract Provisions, cash will not be accepted for a bid deposit.

1-02.9 Delivery of Proposal

(July 18, 2018 APWA GSP Option B)

Delete this section and replace it with the following: Each Proposal shall be submitted in a sealed envelope, with the Project Name and Project Number as stated in the Call for Bids clearly marked on the outside of the envelope, or as otherwise required in the Bid Documents, to ensure proper handling and delivery. To be considered responsive on a FHWA-funded project, the Bidder may be required to submit the following items, as required by Section 1-02.6:

Page 80: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-44

• UDBE Written Confirmation Document from each UDBE firm listed on the Bidder’s completed UDBE Utilization Certification (WSDOT 272-056U); • Good Faith Effort (GFE) Documentation These documents, if applicable, shall be received either with the Bid Proposal or as a Supplement to the Bid. The documents shall be received no later than 24 hours (not including Saturdays, Sundays and Holidays) after the time for delivery of the Bid Proposal. If submitted after the Bid Proposal is due, the document(s) shall be submitted as follows: 1. In a sealed envelope labeled the same as for the Proposal, with “Supplemental Information” added, or 2. By facsimile to the following FAX number: 360-412-3186, or 3. By e-mail to the following e-mail address: [email protected] All other information required to be submitted with the Bid Proposal must be submitted with the Bid Proposal itself, at the time stated in the Call for Bids. The Contracting Agency will not open or consider any Bid Proposal that is received after the time specified in the Call for Bids for receipt of Bid Proposals, or received in a location other than that specified in the Call for Bids. The Contracting Agency will not open or consider any “Supplemental Information” (UDBE confirmations or GFE documentation) that is received after the time specified above, or received in a location other than that specified in the Call for Bids.

1-02.10 Withdrawing, Revising, or Supplementing Proposal

(July 23, 2015 APWA GSP)

Delete this section in its entirety, and replace it with the following: After submitting a physical Bid Proposal to the Contracting Agency, the Bidder may withdraw, revise, or supplement it if: 1. The Bidder submits a written request signed by an authorized person and physically delivers it to the place designated for receipt of Bid Proposals, and 2. The Contracting Agency receives the request before the time set for receipt of Bid Proposals, and 3. The revised or supplemented Bid Proposal (if any) is received by the Contracting Agency before the time set for receipt of Bid Proposals. If the Bidder’s request to withdraw, revise, or supplement its Bid Proposal is received before the time set for receipt of Bid Proposals, the Contracting Agency will return the unopened Proposal package to the Bidder. The Bidder must then submit the revised or supplemented package in its entirety. If the Bidder does not submit a revised or supplemented package, then its bid shall be considered withdrawn. Late revised or supplemented Bid Proposals or late withdrawal requests will be date recorded by the Contracting Agency and returned unopened. Mailed, Emailed, or faxed requests to withdraw, revise, or supplement a Bid Proposal are not acceptable.

1-02.13 Irregular Proposals

(June 20, 2017 APWA GSP)

Delete this section and replace it with the following:

Page 81: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-45

1. A Proposal will be considered irregular and will be rejected if: a. The Bidder is not prequalified when so required; b. The authorized Proposal form furnished by the Contracting Agency is not used or is altered; c. The completed Proposal form contains any unauthorized additions, deletions, alternate Bids, or conditions; d. The Bidder adds provisions reserving the right to reject or accept the award, or enter into the Contract; e. A price per unit cannot be determined from the Bid Proposal; f. The Proposal form is not properly executed; g. The Bidder fails to submit or properly complete a Subcontractor list, if applicable, as required in Section 1-02.6; h. The Bidder fails to submit or properly complete an Underutilized Disadvantaged Business Enterprise Certification, if applicable, as required in Section 1-02.6; i. The Bidder fails to submit written confirmation from each UDBE firm listed on the Bidder’s completed UDBE Utilization Certification that they are in agreement with the bidder’s UDBE participation commitment, if applicable, as required in Section 1-02.6, or if the written confirmation that is submitted fails to meet the requirements of the Special Provisions; j The Bidder fails to submit UDBE Good Faith Effort documentation, if applicable, as required in Section 1-02.6, or if the documentation that is submitted fails to demonstrate that a Good Faith Effort to meet the Condition of Award was made; k. The Bid Proposal does not constitute a definite and unqualified offer to meet the material terms of the Bid invitation; or l. More than one Proposal is submitted for the same project from a Bidder under the same or different names. 2. A Proposal may be considered irregular and may be rejected if: a. The Proposal does not include a unit price for every Bid item; b. Any of the unit prices are excessively unbalanced (either above or below the amount of a reasonable Bid) to the potential detriment of the Contracting Agency; c. Receipt of Addenda is not acknowledged; d. A member of a joint venture or partnership and the joint venture or partnership submit Proposals for the same project (in such an instance, both Bids may be rejected); or e. If Proposal form entries are not made in ink.

1-02.14 Disqualification of Bidders

(******)

Delete this section and replace it with the following: A Bidder will be deemed not responsible if the Bidder does not meet the mandatory bidder responsibility criteria in RCW 39.04.350(1), as amended; or does not meet Supplemental Criteria in this Section: The Contracting Agency will verify that the Bidder meets the mandatory bidder responsibility criteria in RCW 39.04.350(1). Evidence that the Bidder meets Supplemental Criteria shall be provided by the Bidder as stated later in this Section. Relevant Experience & Reference Checks A. Criterion: The Bidder shall have successfully completed (1) one public work project within the last (5) five years, and the Bidder or Subcontractor shall have successfully completed (2) projects of a similar scope within the last (5) five years. In evaluating whether the projects were

Page 82: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-46

“successfully completed,” the Owner may check owner references for the previous projects and may evaluate the owner’s assessment of the Bidder performance. In conducting reference checks, the Owner may include itself as a reference if the bidder has performed work for the Owner, even if the bidder did not identify the Owner as a reference. The assessment may include but is not limited to the following areas: a. Administration / Management / Supervision i. Supervision and decision making ii. Coordination and communication with subcontractors and suppliers iii. Submission of documents, reports, material submittals iv. Timeliness of progress schedules v. Public safety and traffic control vi. Compliance with laws, ordinances and regulations vii. Maintenance of employee safety standards viii. Coordination and cooperation with department personnel on project matters ix. Relations with the general public, other agencies and/or adjacent contractors b. Quality of Work i. Adherence to plans and specifications ii. Standards of Workmanship iii. Completion of final (punch list) work c. Progress of Work i. Completion of project within allotted time ii. Scheduling and execution of schedule iii. Delivery of materials and supplies iv. Operation and use of equipment v. Use of personnel d. Equipment i. Condition ii. Maintenance iii. Proper/Suitable equipment used B. Documentation: The Bidder shall submit a list of projects to the Owner. Public work is as defined in RCW 39.04.010. For the purposes of meeting this criterion, the Owner has determined that “similar scope to this project” means projects that have the following characteristics: Installation of on-site generators for a public wastewater lift station. The information about each project shall include the following: • Contractor’s name (identify as bidder or subcontractor) • Owner’s name and contact information for the owner’s representative; • Contract amount; • Date of Completion; • A brief description of the scope of the project and how the project is similar to this project As evidence that the Bidder meets the mandatory and supplemental responsibility criteria stated above, the apparent low Bidder must submit to the Contracting Agency by 2:30 P.M. of the second business day following the bid submittal deadline, documentation verifying that the Bidder meets all of the supplemental criteria together with supporting documentation including but not limited to that detailed above (sufficient in the sole judgment of the Contracting Agency) demonstrating compliance with all supplemental responsibility criteria. The Contracting Agency reserves the right to request such documentation from other Bidders as well, and to request further documentation as needed to assess Bidder responsibility. The Contracting Agency also reserves the right to obtain information from third-parties and independent sources of information concerning a Bidder’s compliance with the mandatory and supplemental criteria, and to use that information in their evaluation. The Contracting Agency may (but is not required to)

Page 83: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-47

consider mitigating factors in determining whether the Bidder complies with the requirements of the supplemental criteria. The basis for evaluation of Bidder compliance with these mandatory and Supplemental Criteria shall include any documents or facts obtained by Contracting Agency (whether from the Bidder or third parties) including but not limited to: (i) financial, historical, or operational data from the Bidder; (ii) information obtained directly by the Contracting Agency from others for whom the Bidder has worked, or other public agencies or private enterprises; and (iii) any additional information obtained by the Contracting Agency which is believed to be relevant to the matter. If the Contracting Agency determines the Bidder does not meet the bidder responsibility criteria above and is therefore not a responsible Bidder, the Contracting Agency shall notify the Bidder in writing, with the reasons for its determination. If the Bidder disagrees with this determination, it may appeal the determination within two (2) business days of the Contracting Agency’s determination by presenting its appeal and any additional information to the Contracting Agency. The Contracting Agency will consider the appeal and any additional information before issuing its final determination. If the final determination affirms that the Bidder is not responsible, the Contracting Agency will not execute a contract with any other Bidder until at least two business days after the Bidder determined to be not responsible has received the Contracting Agency’s final determination. Request to Change Supplemental Bidder Responsibility Criteria Prior To Bid: Bidders with concerns about the relevancy or restrictiveness of the Supplemental Bidder Responsibility Criteria may make or submit requests to the Contracting Agency to modify the criteria. Such requests shall be in writing, describe the nature of the concerns, and propose specific modifications to the criteria. Bidders shall submit such requests to the Contracting Agency no later than five (5) business days prior to the bid submittal deadline and address the request to the Project Engineer or such other person designated by the Contracting Agency in the Bid Documents.

1-02.15 Pre-Award Information

(August 14, 2013 APWA GSP)

Revise this section to read: Before awarding any contract, the Contracting Agency may require one or more of these items or actions of the apparent lowest responsible bidder:

1. A complete statement of the origin, composition, and manufacture of any or all materials to be used,

2. Samples of these materials for quality and fitness tests, 3. A progress schedule (in a form the Contracting Agency requires) showing the order of

and time required for the various phases of the work, 4. A breakdown of costs assigned to any bid item, 5. Attendance at a conference with the Engineer or representatives of the Engineer, 6. Obtain, and furnish a copy of, a business license to do business in the city or county

where the work is located. 7. Any other information or action taken that is deemed necessary to ensure that the bidder

is the lowest responsible bidder.

Page 84: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-48

1-03 AWARD AND EXECUTION OF CONTRACT

1-03.1 Consideration of Bids

(January 23, 2006 APWA GSP)

Revise the first paragraph to read: After opening and reading proposals, the Contracting Agency will check them for correctness of extensions of the prices per unit and the total price. If a discrepancy exists between the price per unit and the extended amount of any bid item, the price per unit will control. If a minimum bid amount has been established for any item and the bidder’s unit or lump sum price is less than the minimum specified amount, the Contracting Agency will unilaterally revise the unit or lump sum price, to the minimum specified amount and recalculate the extension. The total of extensions, corrected where necessary, including sales taxes where applicable and such additives and/or alternates as selected by the Contracting Agency, will be used by the Contracting Agency for award purposes and to fix the Awarded Contract Price amount and the amount of the contract bond.

1-03.3 Execution of Contract

(October 1, 2005 APWA GSP)

Revise this section to read: Copies of the Contract Provisions, including the unsigned Form of Contract, will be available for signature by the successful bidder on the first business day following award. The number of copies to be executed by the Contractor will be determined by the Contracting Agency. Within 10 calendar days after the award date, the successful bidder shall return the signed Contracting Agency-prepared contract, an insurance certification as required by Section 1-07.18, and a satisfactory bond as required by law and Section 1-03.4. Before execution of the contract by the Contracting Agency, the successful bidder shall provide any pre-award information the Contracting Agency may require under Section 1-02.15. Until the Contracting Agency executes a contract, no proposal shall bind the Contracting Agency nor shall any work begin within the project limits or within Contracting Agency-furnished sites. The Contractor shall bear all risks for any work begun outside such areas and for any materials ordered before the contract is executed by the Contracting Agency. If the bidder experiences circumstances beyond their control that prevents return of the contract documents within the calendar days after the award date stated above, the Contracting Agency may grant up to a maximum of 10 additional calendar days for return of the documents, provided the Contracting Agency deems the circumstances warrant it.

1-03.4 Contract Bond

(July 23, 2015 APWA GSP)

Delete the first paragraph and replace it with the following: The successful bidder shall provide executed payment and performance bond(s) for the full contract amount. The bond may be a combined payment and performance bond; or be separate payment and performance bonds. In the case of separate payment and performance bonds, each shall be for the full contract amount. The bond(s) shall:

1. Be on Contracting Agency-furnished form(s);

Page 85: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-49

2. Be signed by an approved surety (or sureties) that: a) Is registered with the Washington State Insurance Commissioner, and b) Appears on the current Authorized Insurance List in the State of Washington

published by the Office of the Insurance Commissioner, 3. Guarantee that the Contractor will perform and comply with all obligations, duties, and

conditions under the Contract, including but not limited to the duty and obligation to indemnify, defend, and protect the Contracting Agency against all losses and claims related directly or indirectly from any failure: a) Of the Contractor (or any of the employees, subcontractors, or lower tier

subcontractors of the Contractor) to faithfully perform and comply with all contract obligations, conditions, and duties, or

b) Of the Contractor (or the subcontractors or lower tier subcontractors of the Contractor) to pay all laborers, mechanics, subcontractors, lower tier subcontractors, material person, or any other person who provides supplies or provisions for carrying out the work;

4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the project under titles 50, 51, and 82 RCW; and

5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign the bond; and

6. Be signed by an officer of the Contractor empowered to sign official statements (sole proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed by the president or vice president, unless accompanied by written proof of the authority of the individual signing the bond(s) to bind the corporation (i.e., corporate resolution, power of attorney, or a letter to such effect signed by the president or vice president).

1-03.4(1) Retainage in Lieu of Contract Bond

(April 2, 2018 Lacey GSP)

Add the following new section: For contracts of $35,000 or less, the Contractor may, at the Contractor’s option, authorize the Contracting Agency to retain fifty percent (50%) of the contract amount in lieu of furnishing a performance and/or payment bond. If the Contractor elects this option, the retainage shall be held for a period of thirty (30) days after the date of final acceptance, or until receipt of all necessary releases from the Departments of Revenue and of Labor and Industries and settlement of any liens filed under RCW 60.28, whichever is later. The Contractor must advise the Contracting Agency in writing of the Contractor's election to authorize retainage in lieu of a bond, at the time of execution of the Contract. In choosing this option, the Contractor agrees that if the Contractor, its heirs, executors, administrators, successors, or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract, and shall faithfully perform all the provisions of such contract and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of the Contract that may hereafter be made, at the time and in the manner therein specified, and shall pay all laborers, mechanics, subcontractors, and material sup pliers, and all persons who shall supply such person or persons, or subcontractors, with provisions and supplies for the carrying on of such work, on his or her part, and shall indemnify and save harmless the Contracting Agency, its officers and agents from any claim for such payment, then the funds retained in lieu of a performance bond shall be released at the time provided above; otherwise, the funds shall be retained until the Contractor fulfills the said obligations.

Page 86: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-50

1-03.7 Judicial Review

(November 30, 2018 APWA GSP)

Delete this section and replace it with the following: Any decision made by the Contracting Agency regarding the Award and execution of the Contract or Bid rejection shall be conclusive subject to the scope of judicial review permitted under Washington Law. Such review, if any, shall be timely filed in the Superior Court of the county where the Contracting Agency headquarters is located, provided that where an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction.

1-04 SCOPE OF THE WORK

1-04.2 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and Addenda

(April 30, 2015 Lacey GSP)

Revise the second paragraph to read: Any inconsistency in the parts of the contract shall be resolved by following this order of precedence (e.g., 1 presiding over 2, 2 presiding over 3, 3 over 4, and so forth):

1. Contract Form, 2. Addenda (if any), 3. Proposal Form, 4. Special Provisions, 5. Technical Specifications, if included, 6. Contract Plans, 7. Amendments to the Standard Specifications, 8. WSDOT Standard Specifications for Road, Bridge, and Municipal

Construction, 9. City of Lacey Development Guidelines and Public Works

Standards, and 10. WSDOT Standard Plans for Road, Bridge and Municipal

Construction

1-04.6 Variation in Estimated Quantities

(May 25, 2006 APWA GSP)

Supplement this Section with the following: The quantities for “Utility Potholing”, “Crushed Surfacing Base Course”, and “Construction Geotextile for Soil Stabilization” have been entered into the Proposal only to provide a common proposal for bidders. Actual quantities will be determined in the field as the work progresses, and will be paid at the original bid price, regardless of final quantity. These bid items shall not be subject to the provisions of 1-04.6 of the Standard Specifications.

1-04.6 Variations in Estimated Quantities

(July 23, 2015 APWA GSP Option B)

Revise the first paragraph to read:

Page 87: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-51

Payment to the Contractor will be made only for the actual quantities of Work performed and accepted in conformance with the Contract. When the accepted quantity of Work performed under a unit item varies from the original Proposal quantity, payment will be at the unit Contract price for all Work unless the total accepted quantity of any Contract item, adjusted to exclude added or deleted amounts included in change orders accepted by both parties, increases or decreases by more than 25 percent from the original Proposal quantity, and if the total extended bid price for that item at time of award is equal to or greater than 10 percent of the total contract price at time of award. In that case, payment for contract work may be adjusted as described herein:

1-05 CONTROL OF WORK

1-05.4 Conformity With and Deviations from Plans and Stakes

Supplement this section with the following:

Roadway and Utility Surveys

(July 23, 2015 APWA GSP, Option 1)

The Engineer shall furnish to the Contractor one time only all principal lines, grades, and measurements the Engineer deems necessary for completion of the work. These shall generally consist of one initial set of:

1. Slope stakes for establishing grading; 2. Curb grade stakes; 3. Centerline finish grade stakes for pavement sections wider than 25 feet; and 4. Offset points to establish line and grade for underground utilities such as water, sewers,

and storm drains. On alley construction projects with minor grade changes, the Engineer shall provide only offset hubs on one side of the alley to establish the alignment and grade.

1-05.4(2) Survey Control and Electronic Files

(August 10, 2010 Lacey GSP)

Add the following new section: The Contractor shall re-establish the survey control used in design by using existing survey monuments and other control points as provided by the City. When requested by the Contractor, the City will provide an electronic version of the construction plans (drawings), for use by the Contractor at the Contractor’s own risk. In all cases, the approved paper construction plans are the official contract documents. If the Contractor wishes to use the electronic version of the construction plans for the purposes of providing surveying of the proposed improvements, it shall be the Contractor’s responsibility to verify that any coordinates used from the electronic file match the station and offset location given in the contract construction plans. Construction plans are diagrammatic in nature. The coordinate locations of the various graphic elements within the electronic files may not necessarily be precisely shown with respect to their coordinate position. In all cases, the location callouts in the contract construction plans shall govern.

1-05.7 Removal of Defective and Unauthorized Work

(October 1, 2005 APWA GSP)

Page 88: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-52

Supplement this section with the following: If the Contractor fails to remedy defective or unauthorized work within the time specified in a written notice from the Engineer, or fails to perform any part of the work required by the Contract Documents, the Engineer may correct and remedy such work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary. If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public. Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized work. No adjustment in contract time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Contracting Agency’s rights provided by this Section. The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the work as required.

1-05.11 Final Inspections and Operational Testing

(October 1, 2005 APWA GSP)

Delete this section and replace it with the following:

1-05.11(1) Substantial Completion Date

When the Contractor considers the work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Contractor’s request shall list the specific items of work that remain to be completed in order to reach physical completion. The Engineer will schedule an inspection of the work with the Contractor to determine the status of completion. The Engineer may also establish the Substantial Completion Date unilaterally. If, after this inspection, the Engineer concurs with the Contractor that the work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefore. Upon receipt of written notice concurring in or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the work necessary to reach Substantial and Physical Completion. The Contractor

Page 89: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-53

shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the work. The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the work physically complete and ready for final inspection.

1-05.11(2) Final Inspection and Physical Completion Date

When the Contractor considers the work physically complete and ready for final inspection, the Contractor by written notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for final inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the final inspection reveals the work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected. If action to correct the listed deficiencies is not initiated within 7 days after receipt of the written notice listing the deficiencies, the Engineer may, upon written notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-05.7. The Contractor will not be allowed an extension of contract time because of a delay in the performance of the work attributable to the exercise of the Engineer’s right hereunder. Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the work was considered physically complete. That date shall constitute the Physical Completion Date of the contract, but shall not imply acceptance of the work or that all the obligations of the Contractor under the contract have been fulfilled.

1-05.11(3) Operational Testing

It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore when the work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation systems; buildings; or other similar work it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the physical completion date. Whenever items of work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer. The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal. Operational and test periods, when required by the Engineer, shall not affect a manufacturer’s guaranties or warranties furnished under the terms of the contract.

Page 90: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-54

1-05.12(1) One-Year Guarantee Period

(March 8, 2013 APWA GSP)

Add the following new section: The Contractor shall return to the project and repair or replace all defects in workmanship and material discovered within one year after Final Acceptance of the Work. The Contractor shall start work to remedy any such defects within 7 calendar days of receiving Contracting Agency’s written notice of a defect, and shall complete such work within the time stated in the Contracting Agency’s notice. In case of an emergency, where damage may result from delay or where loss of services may result, such corrections may be made by the Contracting Agency’s own forces or another contractor, in which case the cost of corrections shall be paid by the Contractor. In the event the Contractor does not accomplish corrections within the time specified, the work will be otherwise accomplished and the cost of same shall be paid by the Contractor. When corrections of defects are made, the Contractor shall then be responsible for correcting all defects in workmanship and materials in the corrected work for one year after acceptance of the corrections by Contracting Agency. This guarantee is supplemental to and does not limit or affect the requirements that the Contractor’s work comply with the requirements of the Contract or any other legal rights or remedies of the Contracting Agency.

1-05.14 Cooperation with Other Contractors

(August 3, 2015 Lacey GSP)

Supplement this section with the following: The Contractor shall coordinate residential refuse and recycling pick-up with Pacific Disposal (360) 923-0111. Construction activities shall be planned so that there is no interruption of services.

1-05.15 Method of Serving Notices

(March 25, 2009 APWA GSP)

Revise the second paragraph to read: All correspondence from the Contractor shall be directed to the Project Engineer. All correspondence from the Contractor constituting any notification, notice of protest, notice of dispute, or other correspondence constituting notification required to be furnished under the Contract, must be in paper format, hand delivered or sent via mail delivery service to the Project Engineer's office. Electronic copies such as e-mails or electronically delivered copies of correspondence will not constitute such notice and will not comply with the requirements of the Contract.

1-05.16 Water and Power

(October 1, 2005 APWA GSP)

Add the following new section: The Contractor shall make necessary arrangements, and shall bear the costs for power and water necessary for the performance of the work, unless the contract includes power and water as a pay item.

Page 91: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-55

1-05.18 Record Drawings

(January 3, 2011 Lacey GSP Option A)

Add the following new section: The Contractor shall furnish As-Built/Record Drawings of all changes to the original plans in accordance with the following conditions: One set of 22”x 34” plans showing the changes to the project as installed. Drawings shall be to scale with all notations neat in appearance. Turn the record drawings over to the Engineer for review and approval prior to final payment.

1-06 CONTROL OF MATERIAL

1-06.1 Approval of Materials Prior to Use

(January 4, 2016 Lacey GSP)

The second sentence of first paragraph is revised to read: The Contractor shall use the Qualified Product List (QPL), the Aggregate Source Approval (ASA) Database, or the City of Lacey Request for Approval of Material (COL RAM) form.

1-06.1(2) Request for Approval of Material (RAM)

The first paragraph is revised to read: The COL RAM shall be used with all submittals. The COL RAM shall be prepared by the Contractor in accordance with the instructions and submitted to the engineer for approval before the material is incorporated into the Work.. Supplement this section with the following: The Contractor shall submit sufficient information that describes the materials proposed as defined and described in these specifications and plans within 15 working days following the Notice to Proceed. The City of Lacey has identified the following items as long lead items. 1. Standby Generators 2. Automatic Transfer Switches Long lead items shall be submitted within 10 working days of Notice to Proceed. The list above may not include all long lead items. The contractor is responsible for identifying all items and shall notify the Engineer of any additional items. The Contractor shall submit one electronic of catalog cuts, shop drawings, and a material testing sample, as required for all items to be used in this contract for approval. The Contractor shall circle or highlight products and materials that are specific to this project, and cross out items that are not for this project. All items not in exact compliance with the specifications must be noted as a change. The Contractor shall include an explanation, product specifications, sample articles, and any other

Page 92: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-56

items that will aid the Engineer in approving an item not in exact accordance with the specifications. All submittals shall be submitted in Adobe Acrobat format and submittals that exceed 10 pages shall include a table of contents. Submittals that are not submitted in the format outlined may be rejected outright and the Contractor is required to resubmit in the correct format. The form and the submittal shall be sent in the same e-mail. Submittals that exceed 10 MB shall either be provided on a CD, a flash drive or via an internet link. The Engineer will review submittals within 10 working days. The Contractor may request additional working days if approval or disapproval is not received in 10 working days. The Contractor may not request additional working days for failure to submit sufficient information to approve an item, or for rejection of an item not in accordance with the specifications. Resubmittals shall be submitted within 5 working days from City’s transmittal, to the contractor, of the Engineer reviewed submittal. If the submittal is “Rejected”, the contractor shall resubmit the entire submittal. If the submittal is marked “Revise and Resubmit”, the contractor shall submit items that are identified in the Engineer’s comments. Any material purchased or labor performed prior to such approval shall be at the Contractor's risk. The Contractor must receive all material approvals before the materials will be allowed on the project.

1-06.6 Recycled Materials

(January 4, 2016 APWA GSP)

Delete this section, including its subsections, and replace it with the following: The Contractor shall make their best effort to utilize recycled materials in the construction of the project. Approval of such material use shall be as detailed elsewhere in the Standard Specifications. Prior to Physical Completion the Contractor shall report the quantity of recycled materials that were utilized in the construction of the project for each of the items listed in Section 9-03.21. The report shall include hot mix asphalt, recycled concrete aggregate, recycled glass, steel furnace slag and other recycled materials (e.g. utilization of on-site material and aggregates from concrete returned to the supplier). The Contractor’s report shall be provided on DOT form 350-075 Recycled Materials Reporting.

1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC

1-07.1 Laws to be Observed

(October 1, 2005 APWA GSP)

Supplement this section with the following: In cases of conflict between different safety regulations, the more stringent regulation shall apply. The Washington State Department of Labor and Industries shall be the sole and paramount administrative agency responsible for the administration of the provisions of the Washington Industrial Safety and Health Act of 1973 (WISHA).

Page 93: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-57

The Contractor shall maintain at the project site office, or other well-known place at the project site, all articles necessary for providing first aid to the injured. The Contractor shall establish, publish, and make known to all employees, procedures for ensuring immediate removal to a hospital, or doctor’s care, persons, including employees, who may have been injured on the project site. Employees should not be permitted to work on the project site before the Contractor has established and made known procedures for removal of injured persons to a hospital or a doctor’s care. The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of the Contractor’s plant, appliances, and methods, and for any damage or injury resulting from their failure, or improper maintenance, use, or operation. The Contractor shall be solely and completely responsible for the conditions of the project site, including safety for all persons and property in the performance of the work. This requirement shall apply continuously, and not be limited to normal working hours. The required or implied duty of the Engineer to conduct construction review of the Contractor’s performance does not, and shall not, be intended to include review and adequacy of the Contractor’s safety measures in, on, or near the project site.

1-07.2 State Sales Tax

(June 27, 2011 APWA GSP)

Delete this section, including its sub-sections, in its entirety and replace it with the following: The Washington State Department of Revenue has issued special rules on the State sales tax. Sections 1-07.2(1) through 1-07.2(3) are meant to clarify those rules. The Contractor should contact the Washington State Department of Revenue for answers to questions in this area. The Contracting Agency will not adjust its payment if the Contractor bases a bid on a misunderstood tax liability. The Contractor shall include all Contractor-paid taxes in the unit bid prices or other contract amounts. In some cases, however, state retail sales tax will not be included. Section 1-07.2(2) describes this exception. The Contracting Agency will pay the retained percentage (or release the Contract Bond if a FHWA-funded Project) only if the Contractor has obtained from the Washington State Department of Revenue a certificate showing that all contract-related taxes have been paid (RCW 60.28.051). The Contracting Agency may deduct from its payments to the Contractor any amount the Contractor may owe the Washington State Department of Revenue, whether the amount owed relates to this contract or not. Any amount so deducted will be paid into the proper State fund.

1-07.2(1) State Sales Tax — Rule 171

WAC 458-20-171, and its related rules, apply to building, repairing, or improving streets, roads, etc., which are owned by a municipal corporation, or political subdivision of the state, or by the United States, and which are used primarily for foot or vehicular traffic. This includes storm or combined sewer systems within and included as a part of the street or road drainage system and power lines when such are part of the roadway lighting system. For work performed in such cases, the Contractor shall include Washington State Retail Sales Taxes in the various unit bid item prices, or other contract amounts, including those that the Contractor pays on the purchase of the materials, equipment, or supplies used or consumed in doing the work.

Page 94: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-58

1-07.2(2) State Sales Tax — Rule 170

WAC 458-20-170, and its related rules, apply to the constructing and repairing of new or existing buildings, or other structures, upon real property. This includes, but is not limited to, the construction of streets, roads, highways, etc., owned by the state of Washington; water mains and their appurtenances; sanitary sewers and sewage disposal systems unless such sewers and disposal systems are within, and a part of, a street or road drainage system; telephone, telegraph, electrical power distribution lines, or other conduits or lines in or above streets or roads, unless such power lines become a part of a street or road lighting system; and installing or attaching of any article of tangible personal property in or to real property, whether or not such personal property becomes a part of the realty by virtue of installation. For work performed in such cases, the Contractor shall collect from the Contracting Agency, retail sales tax on the full contract price. The Contracting Agency will automatically add this sales tax to each payment to the Contractor. For this reason, the Contractor shall not include the retail sales tax in the unit bid item prices, or in any other contract amount subject to Rule 170, with the following exception. Exception: The Contracting Agency will not add in sales tax for a payment the Contractor or a subcontractor makes on the purchase or rental of tools, machinery, equipment, or consumable supplies not integrated into the project. Such sales taxes shall be included in the unit bid item prices or in any other contract amount.

1-07.2(3) Services

The Contractor shall not collect retail sales tax from the Contracting Agency on any contract wholly for professional or other services (as defined in Washington State Department of Revenue Rules 138 and 244).

1-07.18 Public Liability and Property Damage Insurance

Delete this section in its entirety, and replace it with the following:

1-07.18 Insurance

(January 4, 2016 APWA GSP)

1-07.18(1) General Requirements

A. The Contractor shall procure and maintain the insurance described in all subsections of section 1-07.18 of these Special Provisions, from insurers with a current A. M. Best rating of not less than A-: VII and licensed to do business in the State of Washington. The Contracting Agency reserves the right to approve or reject the insurance provided, based on the insurer’s financial condition. B. The Contractor shall keep this insurance in force without interruption from the commencement of the Contractor’s Work through the term of the Contract and for thirty (30) days after the Physical Completion date, unless otherwise indicated below. C. If any insurance policy is written on a claims made form, its retroactive date, and that of all subsequent renewals, shall be no later than the effective date of this Contract. The policy shall state that coverage is claims made, and state the retroactive date. Claims-made form coverage shall be maintained by the Contractor for a minimum of 36 months following the Completion Date or earlier termination of this Contract, and the Contractor shall annually provide the Contracting Agency with proof of renewal. If renewal of the claims made form of coverage

Page 95: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-59

becomes unavailable, or economically prohibitive, the Contractor shall purchase an extended reporting period (“tail”) or execute another form of guarantee acceptable to the Contracting Agency to assure financial responsibility for liability for services performed. D. The Contractor’s Automobile Liability, Commercial General Liability and Excess or Umbrella Liability insurance policies shall be primary and non-contributory insurance as respects the Contracting Agency’s insurance, self-insurance, or self-insured pool coverage. Any insurance, self-insurance, or self-insured pool coverage maintained by the Contracting Agency shall be excess of the Contractor’s insurance and shall not contribute with it. E. The Contractor shall provide the Contracting Agency and all additional insureds with written notice of any policy cancellation, within two business days of their receipt of such notice. F. The Contractor shall not begin work under the Contract until the required insurance has been obtained and approved by the Contracting Agency G. Failure on the part of the Contractor to maintain the insurance as required shall constitute a material breach of contract, upon which the Contracting Agency may, after giving five business days’ notice to the Contractor to correct the breach, immediately terminate the Contract or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to the Contracting Agency on demand, or at the sole discretion of the Contracting Agency, offset against funds due the Contractor from the Contracting Agency. H. All costs for insurance shall be incidental to and included in the unit or lump sum prices of the Contract and no additional payment will be made.

1-07.18(2) Additional Insured

All insurance policies, with the exception of Workers Compensation, and of Professional Liability and Builder’s Risk (if required by this Contract) shall name the following listed entities as additional insured(s) using the forms or endorsements required herein:

• The Contracting Agency and its officers, elected officials, employees, agents, and volunteers

The above-listed entities shall be additional insured(s) for the full available limits of liability maintained by the Contractor, irrespective of whether such limits maintained by the Contractor are greater than those required by this Contract, and irrespective of whether the Certificate of Insurance provided by the Contractor pursuant to 1-07.18(4) describes limits lower than those maintained by the Contractor. For Commercial General Liability insurance coverage, the required additional insured endorsements shall be at least as broad as ISO forms CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations.

1-07.18(3) Subcontractors

The Contractor shall cause each Subcontractor of every tier to provide insurance coverage that complies with all applicable requirements of the Contractor-provided insurance as set forth herein, except the Contractor shall have sole responsibility for determining the limits of coverage required to be obtained by Subcontractors. The Contractor shall ensure that all Subcontractors of every tier add all entities listed in 1 07.18(2) as additional insureds, and provide proof of such on the policies as required by that section as detailed in 1-07.18(2) using an endorsement as least as broad as ISO CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations.

Page 96: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-60

Upon request by the Contracting Agency, the Contractor shall forward to the Contracting Agency evidence of insurance and copies of the additional insured endorsements of each Subcontractor of every tier as required in 1-07.18(4) Verification of Coverage.

1-07.18(4) Verification of Coverage

The Contractor shall deliver to the Contracting Agency a Certificate(s) of Insurance and endorsements for each policy of insurance meeting the requirements set forth herein when the Contractor delivers the signed Contract for the work. Failure of Contracting Agency to demand such verification of coverage with these insurance requirements or failure of Contracting Agency to identify a deficiency from the insurance documentation provided shall not be construed as a waiver of Contractor’s obligation to maintain such insurance. Verification of coverage shall include: 1. An ACORD certificate or a form determined by the Contracting Agency to be equivalent. 2. Copies of all endorsements naming Contracting Agency and all other entities listed in 1 07.18(2) as additional insured(s), showing the policy number. The Contractor may submit a copy of any blanket additional insured clause from its policies instead of a separate endorsement. 3. Any other amendatory endorsements to show the coverage required herein. 4. A notation of coverage enhancements on the Certificate of Insurance shall not satisfy these requirements – actual endorsements must be submitted. Upon request by the Contracting Agency, the Contractor shall forward to the Contracting Agency a full and certified copy of the insurance policy(s). If Builders Risk insurance is required on this Project, a full and certified copy of that policy is required when the Contractor delivers the signed Contract for the work.

1-07.18(5) Coverages and Limits

The insurance shall provide the minimum coverages and limits set forth below. Contractor’s maintenance of insurance, its scope of coverage, and limits as required herein shall not be construed to limit the liability of the Contractor to the coverage provided by such insurance, or otherwise limit the Contracting Agency’s recourse to any remedy available at law or in equity. All deductibles and self-insured retentions must be disclosed and are subject to approval by the Contracting Agency. The cost of any claim payments falling within the deductible or self-insured retention shall be the responsibility of the Contractor. In the event an additional insured incurs a liability subject to any policy’s deductibles or self-insured retention, said deductibles or self-insured retention shall be the responsibility of the Contractor.

1-07.18(5)A Commercial General Liability

Commercial General Liability insurance shall be written on coverage forms at least as broad as ISO occurrence form CG 00 01, including but not limited to liability arising from premises, operations, stop gap liability, independent contractors, products-completed operations, personal and advertising injury, and liability assumed under an insured contract. There shall be no exclusion for liability arising from explosion, collapse or underground property damage. The Commercial General Liability insurance shall be endorsed to provide a per project general aggregate limit, using ISO form CG 25 03 05 09 or an equivalent endorsement. Contractor shall maintain Commercial General Liability Insurance arising out of the Contractor’s completed operations for at least three years following Substantial Completion of the Work. Such policy must provide the following minimum limits:

Page 97: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-61

$1,000,000 Each Occurrence $2,000,000 General Aggregate $2,000,000 Products & Completed Operations Aggregate $1,000,000 Personal & Advertising Injury each offence $1,000,000 Stop Gap / Employers’ Liability each accident

1-07.18(5)B Automobile Liability

Automobile Liability shall cover owned, non-owned, hired, and leased vehicles; and shall be written on a coverage form at least as broad as ISO form CA 00 01. If the work involves the transport of pollutants, the automobile liability policy shall include MCS 90 and CA 99 48 endorsements. Such policy must provide the following minimum limit: $1,000,000 Combined single limit each accident

1-07.18(5)C Workers’ Compensation

The Contractor shall comply with Workers’ Compensation coverage as required by the Industrial Insurance laws of the State of Washington.

1-07.23 Public Convenience and Safety

1-07.23(1) Construction Under Traffic

(May 2, 2017 APWA GSP)

Revise the third sentence of the second paragraph to read: Accessibility to existing or temporary pedestrian push buttons shall not be impaired; if approved by the Contracting Agency activating pedestrian recall timing or other accommodation may be allowed during construction.

1-07.23(1) Construction Under Traffic

(January 5, 2015 WSDOT 1-07.23(1).OPT5.FR1)

Section 1-07.23(1) is supplemented with the following Lane closures are subject to the following restrictions: If the Engineer determines the permitted closure hours adversely affect traffic, the Engineer may adjust the hours accordingly. The Engineer will notify the Contractor in writing of any change in the closure hours. Lane closures are not allowed on any of the following: 1. A holiday, 2. A holiday weekend; holidays that occur on Friday, Saturday, Sunday or Monday are considered a holiday weekend. A holiday weekend includes Saturday, Sunday, and the holiday.

1-07.24 Rights of Way

(July 23, 2015 APWA GSP)

Delete this section and replace it with the following:

Page 98: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-62

Street Right of Way lines, limits of easements, and limits of construction permits are indicated in the Plans. The Contractor’s construction activities shall be confined within these limits, unless arrangements for use of private property are made. Generally, the Contracting Agency will have obtained, prior to bid opening, all rights of way and easements, both permanent and temporary, necessary for carrying out the work. Exceptions to this are noted in the Bid Documents or will be brought to the Contractor’s attention by a duly issued Addendum. Whenever any of the work is accomplished on or through property other than public Right of Way, the Contractor shall meet and fulfill all covenants and stipulations of any easement agreement obtained by the Contracting Agency from the owner of the private property. Copies of the easement agreements may be included in the Contract Provisions or made available to the Contractor as soon as practical after they have been obtained by the Engineer. Whenever easements or rights of entry have not been acquired prior to advertising, these areas are so noted in the Plans. The Contractor shall not proceed with any portion of the work in areas where right of way, easements or rights of entry have not been acquired until the Engineer certifies to the Contractor that the right of way or easement is available or that the right of entry has been received. If the Contractor is delayed due to acts of omission on the part of the Contracting Agency in obtaining easements, rights of entry or right of way, the Contractor will be entitled to an extension of time. The Contractor agrees that such delay shall not be a breach of contract. Each property owner shall be given 48 hours notice prior to entry by the Contractor. This includes entry onto easements and private property where private improvements must be adjusted. The Contractor shall be responsible for providing, without expense or liability to the Contracting Agency, any additional land and access thereto that the Contractor may desire for temporary construction facilities, storage of materials, or other Contractor needs. However, before using any private property, whether adjoining the work or not, the Contractor shall file with the Engineer a written permission of the private property owner, and, upon vacating the premises, a written release from the property owner of each property disturbed or otherwise interfered with by reasons of construction pursued under this contract. The statement shall be signed by the private property owner, or proper authority acting for the owner of the private property affected, stating that permission has been granted to use the property and all necessary permits have been obtained or, in the case of a release, that the restoration of the property has been satisfactorily accomplished. The statement shall include the parcel number, address, and date of signature. Written releases must be filed with the Engineer before the Completion Date will be established.

1-08 PROSECUTION AND PROGRESS Add the following new section:

1-08.0 Preliminary Matters

(May 25, 2006 APWA GSP)

Add the following new section:

Page 99: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-63

1-08.0(1) Preconstruction Conference

(October 10, 2008 APWA GSP)

Prior to the Contractor beginning the work, a preconstruction conference will be held between the Contractor, the Engineer, and such other interested parties as may be invited. The purpose of the preconstruction conference will be: To review the initial progress schedule; To establish a working understanding among the various parties associated or affected by the work; To establish and review procedures for progress payment, notifications, approvals, submittals, etc.; To establish normal working hours for the work; To review safety standards and traffic control; and To discuss such other related items as may be pertinent to the work. The Contractor shall prepare and submit at the preconstruction conference the following: A breakdown of all lump sum items; A preliminary schedule of working drawing submittals; and A list of material sources for approval if applicable.

1-08.0(2) Hours of Work

(December 8, 2014 APWA GSP)

Except in the case of emergency or unless otherwise approved by the Engineer, the normal working hours for the Contract shall be any consecutive 8-hour period between 7:00 a.m. and 6:00 p.m. Monday through Friday, exclusive of a lunch break. If the Contractor desires different than the normal working hours stated above, the request must be submitted in writing prior to the preconstruction conference, subject to the provisions below. The working hours for the Contract shall be established at or prior to the preconstruction conference. All working hours and days are also subject to local permit and ordinance conditions (such as noise ordinances). If the Contractor wishes to deviate from the established working hours, the Contractor shall submit a written request to the Engineer for consideration. This request shall state what hours are being requested, and why. Requests shall be submitted for review no later than 5 prior to the day(s) the Contractor is requesting to change the hours. If the Contracting Agency approves such a deviation, such approval may be subject to certain other conditions, which will be detailed in writing. For example:

1. On non-Federal aid projects, requiring the Contractor to reimburse the Contracting Agency for the costs in excess of straight-time costs for Contracting Agency representatives who worked during such times. (The Engineer may require designated representatives to be present during the work. Representatives who may be deemed necessary by the Engineer include, but are not limited to: survey crews; personnel from the Contracting Agency’s material testing lab; inspectors; and other Contracting Agency employees or third party consultants when, in the opinion of the Engineer, such work necessitates their presence.)

2. Considering the work performed on Saturdays, Sundays, and holidays as working days with regard to the contract time.

Page 100: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-64

3. Considering multiple work shifts as multiple working days with respect to contract time even though the multiple shifts occur in a single 24-hour period.

4. If a 4-10 work schedule is requested and approved the non working day for the week will be charged as a working day.

5. If Davis Bacon wage rates apply to this Contract, all requirements must be met and recorded properly on certified payroll

1-08.0(2)A Lacey Hours of Work

(October 16, 2014 Lacey GSP Option A)

Add the following new section: Lacey Municipal Code (LMC) Chapter 14.38.010, prohibits outside construction activities between the hours of 9:00 p.m. and 7:00 a.m. in or adjacent to residential zones of the City. A waiver to this ordinance will not be allowed, except in case of emergency, or where operations are necessary during such hours in order to promote the safety of the traveling public as shown in theses specifications or as determined by the Engineer.

1-08.1 Subcontracting

(November 30, 2018 APWA GSP, Option B)

Delete the eighth paragraph.

1-08.3(2)A Type A Progress Schedule

(March 13, 2012 APWA GSP)

Revise this section to read: The Contractor shall submit five (5) copies of a Type A Progress Schedule no later than at the preconstruction conference, or some other mutually agreed upon submittal time. The schedule may be a critical path method (CPM) schedule, bar chart, or other standard schedule format. Regardless of which format used, the schedule shall identify the critical path. The Engineer will evaluate the Type A Progress Schedule and approve or return the schedule for corrections within 15 calendar days of receiving the submittal.

1-08.4 Prosecution of Work

(July 23, 2015 APWA GSP)

Delete this section in its entirety, and replace it with the following:

1-08.4 Notice to Proceed and Prosecution of Work

Notice to Proceed will be given after the contract has been executed and the contract bond and evidence of insurance have been approved and filed by the Contracting Agency. The Contractor shall not commence with the work until the Notice to Proceed has been given by the Engineer. The Contractor shall commence construction activities on the project site within ten days of the Notice to Proceed Date, unless otherwise approved in writing. The Contractor shall diligently pursue the work to the physical completion date within the time specified in the contract. Voluntary shutdown or slowing of operations by the Contractor shall not relieve the Contractor of the responsibility to complete the work within the time(s) specified in the contract.

Page 101: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-65

When shown in the Plans, the first order of work shall be the installation of high visibility fencing to delineate all areas for protection or restoration, as described in the Contract. Installation of high visibility fencing adjacent to the roadway shall occur after the placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). Upon construction of the fencing, the Contractor shall request the Engineer to inspect the fence. No other work shall be performed on the site until the Contracting Agency has accepted the installation of high visibility fencing, as described in the Contract.

1-08.4(1) Order Of Work

(****** Lacey)

Add the following new section: Prior to starting construction and issuance of notice to proceed by the City, the Contractor shall furnish the Contracting Agency with a schedule, sequence, and method of proceeding with the work. This schedule shall address all items herein and must be approved by the Contracting Agency prior to commencing any construction operations. The following specific requirements shall be included into the project schedule:

• The Contractor shall complete the work in the following order: 1.Lift Station 4 2.Lift Station 5 3.Lift Station 17 4.Lift Station 27 5.Lift Station 24 6.Lift Station 11 7.Lift Station 8 This work order is dependent on the generators being delivered at the same time. If the generators have a significant time lapse between deliveries, the Contractor may complete the work in a different order, upon approval by the Engineer. Once work has commenced at a site, the Contractor shall make daily progress and complete all work at the site, including Lawn and Landscape Restoration, before moving equipment and personnel to commence work at another site.

• There shall not be bypass pumping at more than two lift stations at a time.

1-08.5 Time for Completion

(****** Lacey)

This project shall be completed in accordance with the provisions of Section 1-08 of the Standard Specifications within 160 working days. All design and submittal work for this project shall be completed within the first 20 working days of the contract. The project working days may be suspended until the Contracting Agency is satisfied that the Contractor has procured the long lead items required for completion of the project and progress of work at the site can proceed to substantial completion without interruption.

Page 102: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-66

The Contractor, in order to receive a suspension of the contract time as specified herein; shall within 10 working days after approval of the equipment drawings by the Contracting Agency, provide the Contracting Agency with copies of the purchase order(s) for equipment items deemed critical by the Contracting Agency, including but not limited to, standby generators, automatic transfer switches and appurtenances required for completion of the contract. Such purchase order(s) shall disclose the estimated delivery dates for such critical equipment. If the Contracting Agency receives the purchase order(s) within the prescribed time frame, the contract time will be suspended upon completion of all design and submittal work except the heretofore mentioned critical items. If the Contracting agency does not receive the purchase order(s) within the prescribed time frame, the contract time for the entire project will continue without suspension for the critical items, and liquidated damages will be sought if the project is not complete within the specified number of working days.

1-08.5 Time for Completion

(November 30, 2018 APWA GSP Option A)

Revise the third and fourth paragraphs to read: Contract time shall begin on the first working day following the Notice to Proceed Date. Each working day shall be charged to the contract as it occurs, until the contract work is physically complete. If substantial completion has been granted and all the authorized working days have been used, charging of working days will cease. Each week the Engineer will provide the Contractor a statement that shows the number of working days: (1) charged to the contract the week before; (2) specified for the physical completion of the contract; and (3) remaining for the physical completion of the contract. The statement will also show the nonworking days and any partial or whole day the Engineer declares as unworkable. Within 10 calendar days after the date of each statement, the Contractor shall file a written protest of any alleged discrepancies in it. To be considered by the Engineer, the protest shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of time disputed. By not filing such detailed protest in that period, the Contractor shall be deemed as having accepted the statement as correct. If the Contractor is approved to work 10 hours a day and 4 days a week (a 4-10 schedule) and the fifth day of the week in which a 4-10 shift is worked would ordinarily be charged as a working day then the fifth day of that week will be charged as a working day whether or not the Contractor works on that day. Revise the sixth paragraph to read: The Engineer will give the Contractor written notice of the completion date of the contract after all the Contractor’s obligations under the contract have been performed by the Contractor. The following events must occur before the Completion Date can be established:

1. The physical work on the project must be complete; and 2. The Contractor must furnish all documentation required by the contract and required by law, to allow the Contracting Agency to process final acceptance of the contract. The following documents must be received by the Project Engineer prior to establishing a completion date:

a. Certified Payrolls (per Section 1-07.9(5)). b. Material Acceptance Certification Documents c. Monthly Reports of Amounts Credited as DBE Participation, as required by the Contract Provisions. d. Final Contract Voucher Certification e. Copies of the approved “Affidavit of Prevailing Wages Paid” for the Contractor and all Subcontractors

Page 103: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-67

f. A copy of the Notice of Termination sent to the Washington State Department of Ecology (Ecology); the elapse of 30 calendar days from the date of receipt of the Notice of Termination by Ecology; and no rejection of the Notice of Termination by Ecology. This requirement will not apply if the Construction Stormwater General Permit is transferred back to the Contracting Agency in accordance with Section 8-01.3(16). g. Property owner releases per Section 1-07.24

1-08.9 Liquidated Damages

(August 14, 2013 APWA GSP)

Revise the fourth paragraph to read: When the Contract Work has progressed to Substantial Completion as defined in the Contract, the Engineer may determine that the work is Substantially Complete. The Engineer will notify the Contractor in writing of the Substantial Completion Date. For overruns in Contract time occurring after the date so established, the formula for liquidated damages shown above will not apply. For overruns in Contract time occurring after the Substantial Completion Date, liquidated damages shall be assessed on the basis of direct engineering and related costs assignable to the project until the actual Physical Completion Date of all the Contract Work. The Contractor shall complete the remaining Work as promptly as possible. Upon request by the Project Engineer, the Contractor shall furnish a written schedule for completing the physical Work on the Contract.

1-09 MEASUREMENT AND PAYMENT

1-09.2(1) General Requirements for Weighing Equipment

(July 23, 2015 APWA GSP, Option 2)

Revise item 4 of the fifth paragraph to read: 4. Test results and scale weight records for each day’s hauling operations are provided to the Engineer daily. Reporting shall utilize WSDOT form 422-027, Scaleman’s Daily Report, unless the printed ticket contains the same information that is on the Scaleman’s Daily Report Form. The scale operator must provide an AM and PM tare weight for each truck on the printed ticket.

1-09.2(5) Measurement

(May 2, 2017 APWA GSP)

Revise the first paragraph to read: Scale Verification Checks – At the Engineer’s discretion, the Engineer may perform verification checks on the accuracy of each batch, hopper, or platform scale used in weighing contract items of Work.

1-09.6 Force Account

(October 10, 2008 APWA GSP)0

Supplement this section with the following: The Contracting Agency has estimated and included in the Proposal, dollar amounts for all items to be paid per force account, only to provide a common proposal for Bidders. All such dollar amounts are to become a part of Contractor's total bid. However, the Contracting Agency does not warrant expressly or by implication, that the actual amount of work will correspond with

Page 104: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-68

those estimates. Payment will be made on the basis of the amount of work actually authorized by Engineer.

1-09.9 Payments

(March 13, 2012 APWA GSP)

Supplement this section with the following: Lump sum item breakdowns are not required when the bid price for the lump sum item is less than $20,000. Delete the first four paragraphs and replace them with the following: The basis of payment will be the actual quantities of Work performed according to the Contract and as specified for payment. The Contractor shall submit a breakdown of the cost of lump sum bid items at the Preconstruction Conference, to enable the Project Engineer to determine the Work performed on a monthly basis. A breakdown is not required for lump sum items that include a basis for incremental payments as part of the respective Specification. Absent a lump sum breakdown, the Project Engineer will make a determination based on information available. The Project Engineer’s determination of the cost of work shall be final. Progress payments for completed work and material on hand will be based upon progress estimates prepared by the Engineer. A progress estimate cutoff date will be established at the preconstruction conference. The initial progress estimate will be made not later than 30 days after the Contractor commences the work, and successive progress estimates will be made every month thereafter until the Completion Date. Progress estimates made during progress of the work are tentative, and made only for the purpose of determining progress payment. The progress estimates are subject to change at any time prior to the calculation of the Final Payment. The value of the progress estimate will be the sum of the following: 1. Unit Price Items in the Bid Form — the approximate quantity of acceptable units of work

completed multiplied by the unit price. 2. Lump Sum Items in the Bid Form — based on the approved Contractor’s lump sum

breakdown for that item, or absent such a breakdown, based on the Engineer’s determination. 3. Materials on Hand — 100 percent of invoiced cost of material delivered to Job site or other

storage area approved by the Engineer. 4. Change Orders — entitlement for approved extra cost or completed extra work as determined

by the Engineer. Progress payments will be made in accordance with the progress estimate less: 1. Retainage per Section 1-09.9(1), on non FHWA-funded projects; 2. The amount of Progress Payments previously made; and 3. Funds withheld by the Contracting Agency for disbursement in accordance with the Contract

Documents.

Page 105: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-69

Progress payments for work performed shall not be evidence of acceptable performance or an admission by the Contracting Agency that any work has been satisfactorily completed. The determination of payments under the contract will be final in accordance with Section 1-05.1.

1-09.11(3) Time Limitation and Jurisdiction

(November 30, 2018 APWA GSP)

Delete this section and replace it with the following: For the convenience of the parties to the Contract it is mutually agreed by the parties that any claims or causes of action which the Contractor has against the Contracting Agency arising from the Contract shall be brought within 180 calendar days from the date of final acceptance (Section 1-05.12) of the Contract by the Contracting Agency; and it is further agreed that any such claims or causes of action shall be brought only in the Superior Court of the county where the Contracting Agency headquarters is located, provided that where an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction. The parties understand and agree that the Contractor’s failure to bring suit within the time period provided, shall be a complete bar to any such claims or causes of action. It is further mutually agreed by the parties that when any claims or causes of action which the Contractor asserts against the Contracting Agency arising from the Contract are filed with the Contracting Agency or initiated in court, the Contractor shall permit the Contracting Agency to have timely access to any records deemed necessary by the Contracting Agency to assist in evaluating the claims or action.

1-09.13(3) Claims $250,000 or Less

(October 1, 2005 APWA GSP)

Delete this Section and replace it with the following: The Contractor and the Contracting Agency mutually agree that those claims that total $250,000 or less, submitted in accordance with Section 1-09.11 and not resolved by nonbinding ADR processes, shall be resolved through litigation unless the parties mutually agree in writing to resolve the claim through binding arbitration.

1-09.13(3)A Administration of Arbitration

(November 30, 2018 APWA GSP)

Revise the third paragraph to read: The Contracting Agency and the Contractor mutually agree to be bound by the decision of the arbitrator, and judgment upon the award rendered by the arbitrator may be entered in the Superior Court of the county in which the Contracting Agency’s headquarters is located, provided that where claims subject to arbitration are asserted against a county, RCW 36.01.050 shall control venue and jurisdiction of the Superior Court. The decision of the arbitrator and the specific basis for the decision shall be in writing. The arbitrator shall use the Contract as a basis for decisions.

1-10 TEMPORARY TRAFFIC CONTROL

1-10.1 General

(January 3, 2017 Lacey GSP)

Supplement this section with the following:

Page 106: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-70

Delays to traffic shall be held to a minimum. There shall be no restrictions or interruptions to traffic on Saturdays, Sundays or Holidays. In addition, there shall be no restrictions or interruptions to traffic after 12:00 noon on the day prior to a holiday or holiday weekend. There shall be no delay to medical, fire, police, or other emergency vehicles with flashing lights or sirens. The Contractor shall alert all flaggers and personnel of this requirement. The Contractor shall be responsible for removing the permanent traffic signs, as deemed necessary by the Engineer, and shall install and maintain any temporary signs necessary for the safety of the public. The Contractor shall maintain pedestrian access at all times, without having pedestrians enter the travel lane. All lane restrictions shall be held to a minimum time and length. Lane closures shall comply with the traffic control plans and these specifications. If the Contractor wishes to deviate from the plans, the Contractor shall submit a traffic control plan to the Engineer, at no additional cost, that complies with the MUTCD, and the Traffic Control Plans, for approval by the Engineer within (5) five working days before the proposed lane closure. If the Engineer determines that lane restrictions are causing congestion, the Contractor will be required to open any lanes, as determined by the Engineer, until the congestion is eliminated. During non-working hours, Saturdays, Sundays, and Holidays, the Contractor shall keep all lanes open to traffic throughout the limits of the project with the lane and sidewalk area completely clear of all material, tools, personnel, and equipment as directed by the Engineer.

2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP

2-01.1 Description

(October 16, 2009 Lacey GSP)

Supplement this section with the following: The City of Lacey is a Tree City USA, and has deemed it necessary to protect all trees to the best of their ability. Only the trees that are evaluated by a certified Arborist as being diseased or detrimental to the project shall be removed as shown in the plans. The Contractor shall conduct a site review noting all trees within the construction zone prior to submitting a bid. Ease of construction, spoils, or stockpiling needs shall not justify tree removal. A high visibility fence shall be installed around all trees and vegetation as required by the Engineer prior to beginning work. The Contractor shall be responsible for installing, maintaining and removing the high visibility fence as required. Disposal of all organic waste shall be by Disposal Method No. 2. Disposal Method No. 1 and No. 3 will not be permitted in this contract. The City of Lacey encourages recycling of organic material at a certified organic recycling center. The Contractor shall take all precautions necessary to protect the public, property, trees, and natural vegetation from harm. Any damage to utilities or other structures on public right-of-way or private property shall be restored by the Contractor or authorized agent at the Contractor's expense.

Page 107: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-71

2-01.5 Payment

(October 16, 2009 Lacey GSP)

Modify this section with the following: The unit contract price per acre or lump sum for “Clearing and Grubbing” shall be full pay for all work described in this section including “Roadside Cleanup”. If no bid item for “Clearing and Grubbing” or “High Visibility Fence” is included in the proposal, any work described in this section shall be incidental to the project.

2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

2-02.1 Description

(****** Lacey)

Supplement this section with the following: The following items plus all materials resulting from incidental work including clearing; grubbing and roadside cleanup shall be removed from the job site, disposed of in a waste site or when noted on the plans, delivered to the City. This work consists of but shall not be limited to the following items: Asphalt Pavement Lane Markings (Buttons, Paint, Plastic, RPM) Cement Concrete Sidewalk Reinforced Cement Concrete Pad Unreinforced Cement Concrete Pad Fencing Refuse Abandoned Water Pipe Abandoned Water Valves and Fittings Silt Fence Roadside Cleanup Trees and Root Balls Rocks and Stumps Block Wall Crushed Rock Surfacing

2-02.2 Video

(July 17, 2012 Lacey GSP)

Add the following new section: The Contractor shall provide pre-construction video of the existing conditions for the construction area including all easements, streets, alleys, and driveways within the project area. Further, video shall include existing drainage, driveways, sidewalks, and other frontage improvements. The Contractor shall also provide pre-construction video of the existing conditions of each face of an existing structure (houses, garages, sheds, fences, etc.), within 30 feet of the construction area.

Page 108: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-72

The Contractor shall provide a copy of the video, in high definition DVD format, to the City prior to any construction. All costs for providing and furnishing the pre-construction video shall be considered incidental to the Project and no other payment will be allowed.

2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters

(October 16, 2016 Lacey)

Supplement this section with the following: In removing pavement, sidewalks, and curbs, the Contractor shall:

1. Mark all cut lines in the field and have the Engineer approve them prior to commencing cutting operations. The Engineer reserves the right to adjust removal to the nearest construction joint.

2. Make a vertical saw cut between any existing pavement, sidewalk, or curb that is to

remain and the portion to be removed.

3. All sawcuts shall be continuous and made with saws designed specifically for this purpose; no skip cutting, wheel cutting, or jack hammering will be allowed unless given prior approval by the Engineer.

4. Replace at no expense to the Contracting Agency any pavement designated to remain that

is damaged during the removal of other pavement. All damaged sidewalks and curbs shall be replaced to the nearest existing joint.

5. Haul all broken–up pieces of pavement, sidewalks, and curbs to an off-project disposal

site. All transitions to existing asphalt or cement concrete driveways, parking lots, curb and gutter and walkways shall be vertically sawcut full-depth with straight, uniform edges. Existing asphalt pavement roadway edge may be cut with a wheel, provided the wheel cut is full depth and no damage occurs to the pavement which is to remain. Neither impact tools nor pavement breakers may be used for trench crossing of existing pavement. Trench crossing of existing pavement shall be vertically sawcut. When sawcutting the existing roadway is needed to widen the road to perform excavation, the Contractor shall take extra precaution to make a neat, uniform cut, and shall sawcut pavement to full depth, regardless of number of passes necessary. Compaction of asphalt near the sawcut is critical and a vertical, neat line sawcut is required. If in the opinion of the Engineer, the cut is not satisfactory due to Contractor’s workmanship or equipment, or if the sawcut becomes damaged and irregular, the Contractor shall fix the problem to the satisfaction of the Engineer, at Contractor’s own expense.

2-02.5 Payment

(March 18, 2015 Lacey)

Delete this section and replace with the following:

Page 109: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-73

“Removal of Structures and Obstructions”, lump sum. The lump sum contract price for these bid items shall be full compensation for all labor, equipment and materials necessary to complete the requirements of this section.

2-05 TRENCH SAFETY SYSTEM (October 16, 2009 Lacey GSP)

Add the following new section:

2-05.1 Description

This work consists of furnishing, utilizing, moving, and maintaining a trench safety system.

2-05.3 Construction Requirements

The Contractor shall comply with all applicable state laws, OSHA, WISHA requirements, and Department of Labor and Industries regulations governing trench excavation and pipe laying. If extra excavation is used in lieu of, or in addition to shoring, cribbing, trench shields, or trench boxes, and select backfill material is required in the trench zone, then select backfill shall be used in the extra excavation zone.

2-05.4 Measurement

Trench safety system shall be paid for per lump sum regardless of the type, size and quantity used.

2-05.5 Payment

The lump sum contract price for “Trench Safety System” shall be full compensation for all labor, tools, equipment, and materials necessary to comply with the requirements stated above.

2-07 WATERING

2-07.3 Construction Requirements

(October 16, 2009 Lacey GSP)

Supplement this section with the following: If the Contractor anticipates the use of City water, the Contractor shall apply for a water meter through the City of Lacey. Any damage rendered to the meter shall be repaired or replaced by the Contracting Agency and those costs deducted from monies due to the Contractor. All water used shall be metered and used sparingly for the entire length of the project. The Contractor will not be charged for water used on the project. The Contractor shall use the water to keep the project site clean and to control dust during and after construction hours as determined by the Engineer.

Page 110: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-74

2-07.4 Measurement

(October 16, 2009 Lacey GSP)

Delete and replace this section with the following: The Contractor shall apply for a construction meter through the Contracting Agency. All water used shall be measured with the Contracting Agency supplied meter.

2-07.5 Payment

(October 16, 2014 Lacey GSP)

Delete and replace this section with the following: The Contractor will not be charged for water used on this project. A construction meter will also be provided free of charge. Any costs to repair meters damaged by the Contractor shall be recovered from monies due the Contractor. All costs to supply tank trucks, and apply water as directed by the Engineer shall be considered incidental to the project and no other payment will be allowed.

2-08 DUST CONTROL (October 16, 2009 Lacey)

Add the following new sections:

2-08.1 Description

This work consists of furnishing and applying Magnesium Chloride solution for dust control as the Engineer requires.

2-08.3 Construction Requirements

The Contractor shall apply magnesium chloride solution by means of tank trucks equipped with spray bars. Spray controls shall ensure that the solution flows evenly and in the amounts required by the manufacturer’s recommendation and directed by the Engineer.

2-08.4 Measurement

“Dust Control” per MGAL, shall be measured by tanks or tank trucks of known capacity or by meters approved by the Engineer. The Contractor shall supply and install any meters at no expense to the Contracting Agency.

2-08.5 Payment

“Dust Control”, per MGAL. The unit contract price per MGAL for “Dust Control” shall be full pay for all labor, materials, tools, and equipment necessary to furnish, haul, and apply the magnesium chloride solution.

Page 111: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-75

2-09 STRUCTURE EXCAVATION

2-09.3(1)E Backfilling

(October 16, 2009 Lacey GSP)

Modify this section with the following: Controlled Density Fill shall meet the following requirements: 1750# Sand, 1750# Pea Gravel, 230# Water, 141# Portland Cement, 6 ounces Water Reducing Agent per 100 lbs. cement. The Controlled Density Fill will require 24 hours of cure time, or as directed by the Engineer. Prior to backfill, all appurtenances shall be covered with 11 mill plastic as directed by the Engineer. The Contractor shall have a steel plate cover placed and anchored over the trench until the Engineer determines the mixture is sufficiently cured, so that a temporary or permanent patch can be placed. This process shall be coordinated so that there will be minimum inconvenience to the public.

2-09.5 Payment

(October 16, 2009 Lacey GSP)

Modify this section with the following: Structure Excavation Including Haul, and Shoring or Extra Excavation shall be incidental to the structure to be constructed unless a bid item is provided.

5-04 HOT MIX ASPHALT

5-04.1 Description

(July 18, 2018 APWA GSP)

Delete this entire section and replace it with the following: This Work shall consist of providing and placing one or more layers of plant-mixed hot mix asphalt (HMA) on a prepared foundation or base in accordance with these Specifications and the lines, grades, thicknesses, and typical cross-sections shown in the Plans. The manufacture of HMA may include warm mix asphalt (WMA) processes in accordance with these Specifications. WMA processes include organic additives, chemical additives, and foaming. HMA shall be composed of asphalt binder and mineral materials as may be required, mixed in the proportions specified to provide a homogeneous, stable, and workable mixture.

5-04.2 Materials

(July 18, 2018 APWA GSP)

Materials shall meet the requirements of the following sections: Asphalt Binder 9-02.1(4) Cationic Emulsified Asphalt 9-02.1(6) Anti-Stripping Additive 9-02.4

Page 112: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-76

HMA Additive 9-02.5 Aggregates 9-03.8 Recycled Asphalt Pavement 9-03.8(3)B Mineral Filler 9-03.8(5) Recycled Material 9-03.21 Portland Cement 9-01 Sand 9-03.1(2) (As noted in 5-04.3(5)C for crack sealing) Joint Sealant 9-04.2 Foam Backer Rod 9-04.2(3)A The Contract documents may establish that the various mineral materials required for the manufacture of HMA will be furnished in whole or in part by the Contracting Agency. If the documents do not establish the furnishing of any of these mineral materials by the Contracting Agency, the Contractor shall be required to furnish such materials in the amounts required for the designated mix. Mineral materials include coarse and fine aggregates, and mineral filler. The Contractor may choose to utilize recycled asphalt pavement (RAP) in the production of HMA. The RAP may be from pavements removed under the Contract, if any, or pavement material from an existing stockpile. The Contractor may use up to 20 percent RAP by total weight of HMA with no additional sampling or testing of the RAP. The RAP shall be sampled and tested at a frequency of one sample for every 1,000 tons produced and not less than ten samples per project. The asphalt content and gradation test data shall be reported to the Contracting Agency when submitting the mix design for approval on the QPL. The Contractor shall include the RAP as part of the mix design as defined in these Specifications. The grade of asphalt binder shall be as required by the Contract. Blending of asphalt binder from different sources is not permitted. The Contractor may only use warm mix asphalt (WMA) processes in the production of HMA with 20 percent or less RAP by total weight of HMA. The Contractor shall submit to the Engineer for approval the process that is proposed and how it will be used in the manufacture of HMA. Production of aggregates shall comply with the requirements of Section 3-01. Preparation of stockpile site, the stockpiling of aggregates, and the removal of aggregates from stockpiles shall comply with the requirements of Section 3-02.

5-04.2(2) Mix Design – Obtaining Project Approval

(July 18, 2018 APWA GSP)

No paving shall begin prior to the approval of the mix design by the Engineer. Nonstatistical evaluation will be used for all HMA not designated as Commercial HMA in the contract documents. Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, prelevel, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Project Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Project Engineer. The Proposal quantity of

Page 113: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-77

HMA that is accepted by commercial evaluation will be excluded from the quantities used in the determination of nonstatistical evaluation. Nonstatistical Mix Design. Fifteen days prior to the first day of paving the contractor shall provide one of the following mix design verification certifications for Contracting Agency review; • The WSDOT Mix Design Evaluation Report from the current WSDOT QPL, or one of the mix design verification certifications listed below. • The proposed HMA mix design on WSDOT Form 350-042 with the seal and certification (stamp & sig-nature) of a valid licensed Washington State Professional Engineer. • The Mix Design Report for the proposed HMA mix design developed by a qualified City or County laboratory that is within one year of the approval date.** The mix design shall be performed by a lab accredited by a national authority such as Laboratory Accredita-tion Bureau, L-A-B for Construction Materials Testing, The Construction Materials Engineering Council (CMEC’s) ISO 17025 or AASHTO Accreditation Program (AAP) and shall supply evidence of participation in the AASHTO: resource proficiency sample program. Mix designs for HMA accepted by Nonstatistical evaluation shall; • Have the aggregate structure and asphalt binder content determined in accordance with WSDOT Standard Operating Procedure 732 and meet the requirements of Sections 9-03.8(2), except that Hamburg testing for ruts and stripping are at the discretion of the Engineer, and 9-03.8(6). • Have anti-strip requirements, if any, for the proposed mix design determined in accordance with AASHTO T 283 or T 324, or based on historic anti-strip and aggregate source compatibility from previous WSDOT lab testing. At the discretion of the Engineer, agencies may accept verified mix designs older than 12 months from the original verification date with a certification from the Contractor that the materials and sources are the same as those shown on the original mix design. Commercial Evaluation Approval of a mix design for “Commercial Evaluation” will be based on a review of the Contractor’s submittal of WSDOT Form 350-042 (For commercial mixes, AASHTO T 324 evaluation is not required) or a Mix Design from the current WSDOT QPL or from one of the processes allowed by this section. Testing of the HMA by the Contracting Agency for mix design approval is not required. For the Bid Item Commercial HMA, the Contractor shall select a class of HMA and design level of Equivalent Single Axle Loads (ESAL’s) appropriate for the required use.

5-04.2(2) Mix Design – Obtaining Project Approval

(January 3, 2011 WSDOT GSP)

Section 5-04.2(2) is supplemented with the following ESAL's The number of ESAL's for the design and acceptance of the HMA shall be $1 million.

5-04.2(2)A Changes to the Job Mix Formula

Delete this section

Page 114: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-78

5-04.2(2)B Using Warm Mix Asphalt Processes

(July 18, 2018 APWA GSP)

The Contractor may elect to use additives that reduce the optimum mixing temperature or serve as a compaction aid for producing HMA. Additives include organic additives, chemical additives and foaming processes. The use of Additives is subject to the following: • Do not use additives that reduce the mixing temperature more than allowed in Section 5-04.3(6) in the production of mixtures. • Before using additives, obtain the Engineer’s approval using WSDOT Form 350-076 to describe the proposed additive and process.

5-04.3 Construction Requirements

5-04.3(2) Paving Under Traffic

(April 2, 2018 Lacey)

Delete this section and replace it with the following: When the Roadway being paved is open to traffic, the requirements of this Section shall apply. In hot weather, the Engineer may require the application of water to the pavement to accelerate the finish rolling of the pavement and to shorten the time required before reopening to traffic. During paving operations, temporary pavement markings shall be maintained throughout the project. Temporary pavement markings shall be installed on the Roadway prior to opening to traffic. Temporary pavement markings shall be in accordance with Section 8-23. The Contractor shall remove all pavement markings including paint, tape, thermoplastic and RPM’s. All costs in connection with performing the Work associated with these requirements shall be included in the unit Contract prices for the various Bid items involved in the Contract.

5-04.3(3)Equipment

5-04.3(3)A Mixing Plant

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: Plants used for the preparation of HMA shall conform to the following requirements: 1. Equipment for Preparation of Asphalt Binder – Tanks for the storage of asphalt binder shall be equipped to heat and hold the material at the required temperatures. The heating shall be accomplished by steam coils, electricity, or other approved means so that no flame shall be in contact with the storage tank. The circulating system for the asphalt binder shall be designed to ensure proper and continuous circulation during the operating period. A valve for the purpose of sampling the asphalt binder shall be placed in either the storage tank or in the supply line to the mixer. 2. Thermometric Equipment – An armored thermometer, capable of detecting temperature ranges expected in the HMA mix, shall be fixed in the asphalt binder feed line at a location near the charging valve at the mixer unit. The thermometer location shall be convenient and safe for

Page 115: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-79

access by Inspectors. The plant shall also be equipped with an approved dial-scale thermometer, a mercury actuated thermometer, an electric pyrometer, or another approved thermometric instrument placed at the discharge chute of the drier to automatically register or indicate the temperature of the heated aggregates. This device shall be in full view of the plant operator. 3. Heating of Asphalt Binder – The temperature of the asphalt binder shall not exceed the maximum recommended by the asphalt binder manufacturer nor shall it be below the minimum temperature required to maintain the asphalt binder in a homogeneous state. The asphalt binder shall be heated in a manner that will avoid local variations in heating. The heating method shall provide a continuous supply of asphalt binder to the mixer at a uniform average temperature with no individual variations exceeding 25°F. Also, when a WMA additive is included in the asphalt binder, the temperature of the asphalt binder shall not exceed the maximum recommended by the manufacturer of the WMA additive. 4. Sampling and Testing of Mineral Materials – The HMA plant shall be equipped with a mechanical sampler for the sampling of the mineral materials. The mechanical sampler shall meet the requirements of Section 1-05.6 for the crushing and screening operation. The Contractor shall provide for the setup and operation of the field testing facilities of the Contracting Agency as provided for in Section 3-01.2(2). 5. Sampling HMA – The HMA plant shall provide for sampling HMA by one of the following methods: a. A mechanical sampling device attached to the HMA plant. b. Platforms or devices to enable sampling from the hauling vehicle without entering the hauling vehicle.

5-04.3(3)C Pavers

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: HMA pavers shall be self-contained, power-propelled units, provided with an internally heated vibratory screed and shall be capable of spreading and finishing courses of HMA plant mix material in lane widths required by the paving section shown in the Plans. The HMA paver shall be in good condition and shall have the most current equipment available from the manufacturer for the prevention of segregation of the HMA mixture installed, in good condition, and in working order. The equipment certification shall list the make, model, and year of the paver and any equipment that has been retrofitted. The screed shall be operated in accordance with the manufacturer’s recommendations and shall effectively produce a finished surface of the required evenness and texture without tearing, shoving, segregating, or gouging the mixture. A copy of the manufacturer’s recommendations shall be provided upon request by the Contracting Agency. Extensions will be allowed provided they produce the same results, including ride, density, and surface texture as obtained by the primary screed. Extensions without augers and an internally heated vibratory screed shall not be used in the Traveled Way. When specified in the Contract, reference lines for vertical control will be required. Lines shall be placed on both outer edges of the Traveled Way of each Roadway. Horizontal control utilizing the reference line will be permitted. The grade and slope for intermediate lanes shall be controlled automatically from reference lines or by means of a mat referencing device and a slope control device. When the finish of the grade prepared for paving is superior to the

Page 116: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-80

established tolerances and when, in the opinion of the Engineer, further improvement to the line, grade, cross-section, and smoothness can best be achieved without the use of the reference line, a mat referencing device may be substituted for the reference line. Substitution of the device will be subject to the continued approval of the Engineer. A joint matcher may be used subject to the approval of the Engineer. The reference line may be removed after the completion of the first course of HMA when approved by the Engineer. Whenever the Engineer determines that any of these methods are failing to provide the necessary vertical control, the reference lines will be reinstalled by the Contractor. The Contractor shall furnish and install all pins, brackets, tensioning devices, wire, and accessories necessary for satisfactory operation of the automatic control equipment. If the paving machine in use is not providing the required finish, the Engineer may suspend Work as allowed by Section 1-08.6. Any cleaning or solvent type liquids spilled on the pavement shall be thoroughly removed before paving proceeds.

5-04.3(3)D Material Transfer Device or Material Transfer Vehicle

(April 2, 2018 Lacey, Option 1)

Delete this section and replace it with the following: A Material Transfer Device/Vehicle (MTD/V) is not required for this project.

5-04.3(3)E Rollers

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: Rollers shall be of the steel wheel, vibratory, oscilatory, or pneumatic tire type, in good condition and capable of reversing without backlash. Operation of the roller shall be in accordance with the manufacturer’s recommendations. When ordered by the Engineer for any roller planned for use on the project, the Contractor shall provide a copy of the manufacturer’s recommendation for the use of that roller for compaction of HMA. The number and weight of rollers shall be sufficient to compact the mixture in compliance with the requirements of Section 5-04.3(10). The use of equipment that results in crushing of the aggregate will not be permitted. Rollers producing pickup, washboard, uneven compaction of the surface, displacement of the mixture or other undesirable results shall not be used.

5-04.3(4) Preparation of Existing Paved Surfaces

(April 2, 2018 Lacey)

Delete this section and replace it with the following: When the surface of the existing pavement or old base is irregular, the Contractor shall bring it to a uniform grade and cross-section as shown on the Plans or approved by the Engineer. Preleveling of uneven or broken surfaces over which HMA is to be placed may be accomplished by using an asphalt paver, a motor patrol grader, or by hand raking, as approved by the Engineer. Compaction of preleveling HMA shall be to the satisfaction of the Engineer and may require the use of small steel wheel rollers, plate compactors, or pneumatic rollers to avoid bridging across preleveled areas by the compaction equipment. Equipment used for the compaction of preleveling HMA shall be approved by the Engineer.

Page 117: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-81

Before construction of HMA on an existing paved surface, the entire surface of the pavement shall be clean. All fatty asphalt patches, grease drippings, and other objectionable matter shall be entirely removed from the existing pavement. All pavements or bituminous surfaces shall be thoroughly cleaned of dust, soil, pavement grindings, and other foreign matter. All holes and small depressions shall be filled with an appropriate class of HMA. The surface of the patched area shall be leveled and compacted thoroughly. Prior to the application of tack coat, or paving, the condition of the surface shall be approved by the Engineer. A tack coat of asphalt shall be applied to all paved surfaces on which any course of HMA is to be placed or abutted. Tack coat shall be uniformly applied to cover the existing pavement with a thin film of residual asphalt free of streaks and bare spots at a rate between 0.02 and 0.10 gallons per square yard of retained asphalt. The rate of application shall be approved by the Engineer. A heavy application of tack coat shall be applied to all joints. For Roadways open to traffic, the application of tack coat shall be limited to surfaces that will be paved during the same working shift. The spreading equipment shall be equipped with a thermometer to indicate the temperature of the tack coat material. Equipment shall not operate on tacked surfaces until the tack has broken and cured. If the Contractor’s operation damages the tack coat it shall be repaired prior to placement of the HMA. The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1 and CSS-1h emulsified asphalt may be diluted once with water at a rate not to exceed one part water to one part emulsified asphalt. The tack coat shall have sufficient temperature such that it may be applied uniformly at the specified rate of application and shall not exceed the maximum temperature recommended by the emulsified asphalt manufacturer All vegetation including root structures and moss shall be removed in their entirety within the paved areas including adjoining curbs, gutters, and sidewalks. Further, all vegetation overgrowth shall be trimmed and removed 6 inches from back of proposed HMA edge limits as directed by the Engineer. Driveway preparation shall include saw cutting, filling, and grading the transitional area required to provide a HMA approach between the edge of pavement and driveway regardless of the existing surface treatment or width. Where a driveway or sidewalk interferes with the new roadway surface, the Engineer shall mark in the field where the asphalt or concrete shall be sawcut. All material that must be removed from the driveway shall be hauled and disposed off the project site. All imported material required to grade and compact driveway bases shall be paid for by the unit bid item “Crushed Surfacing Top Course.” All adjacent driveways shall require preparation. Temporary access shall be provided for all driveways prior to paving. There shall be no additional compensation for those driveways requiring more preparation than others. Shoulder preparation shall include cutting, filling, and grading the shoulder to ensure a uniform, longitudinal pavement edge. Maximum distance shall be 12 inches from proposed edge of pavement surface to a maximum depth of 6 inches from edge of roadway finish grade. Backfill requirements beyond these limits shall be repaired at the Contractor’s expense. All grading within drainage ditches or swales to establish or maintain existing flowlines shall also be included in shoulder preparation. All excess asphalt joint filler shall be completely removed and all premolded and rubberized joint filler shall be removed to a minimum 1/2 inch below the surface of the existing pavement.

Page 118: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-82

5-04.3(4)C Pavement Repair

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: The Contractor shall excavate pavement repair areas and shall backfill these with HMA in accordance with the details shown in the Plans and as marked in the field. The Contractor shall conduct the excavation operations in a manner that will protect the pavement that is to remain. Pavement not designated to be removed that is damaged as a result of the Contractor’s operations shall be repaired by the Contractor to the satisfaction of the Engineer at no cost to the Contracting Agency. The Contractor shall excavate only within one lane at a time unless approved otherwise by the Engineer. The Contractor shall not excavate more area than can be completely finished during the same shift, unless approved by the Engineer. Unless otherwise shown in the Plans or determined by the Engineer, excavate to a depth of 1.0 feet. The Engineer will make the final determination of the excavation depth required. The minimum width of any pavement repair area shall be 40 inches unless shown otherwise in the Plans. Before any excavation, the existing pavement shall be sawcut or shall be removed by a pavement grinder. Excavated materials will become the property of the Contractor and shall be disposed of in a Contractor-provided site off the Right of Way or used in accordance with Sections 2-02.3(3) or 9-03.21. Asphalt for tack coat shall be required as specified in Section 5-04.3(4). A heavy application of tack coat shall be applied to all surfaces of existing pavement in the pavement repair area. Placement of the HMA backfill shall be accomplished in lifts not to exceed 0.35-foot compacted depth. Lifts that exceed 0.35-foot of compacted depth may be accomplished with the approval of the Engineer. Each lift shall be thoroughly compacted by a mechanical tamper or a roller.

5-04.3(5) Producing/Stockpiling Aggregates, RAP, & RAS

Delete this section and replace it with the following:

5-04.3(5) Producing/Stockpiling Aggregates and RAP

(October 30, 2018 Lacey)

If Recycled asphalt pavement (RAP) is allowed per section 5-04.2, aggregates and RAP shall be stockpiled according to the requirements of Section 3-02. Sufficient storage space shall be provided for each size of aggregate and RAP. Materials shall be removed from stockpile(s) in a manner to ensure minimal segregation when being moved to the HMA plant for processing into the final mixture. Different aggregate sizes shall be kept separated until they have been delivered to the HMA plant.

5-04.3(5)A Stockpiling RAP or RAS for High RAP/Any RAS Mixes

Delete this section

5-04.3(6) Mixing

(October 30, 2018 Lacey)

Delete this section and replace it with the following: After the required amount of mineral materials, asphalt binder, recycling agent and anti-stripping additives have been introduced into the mixer the HMA shall be mixed until complete and

Page 119: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-83

uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials is ensured. When discharged, the temperature of the HMA shall not exceed the optimum mixing temperature by more than 25°F as shown on the reference mix design report or as approved by the Engineer. Also, when a WMA additive is included in the manufacture of HMA, the discharge temperature of the HMA shall not exceed the maximum recommended by the manufacturer of the WMA additive. A maximum water content of 2 percent in the mix, at discharge, will be allowed providing the water causes no problems with handling, stripping, or flushing. If the water in the HMA causes any of these problems, the moisture content shall be reduced as directed by the Engineer. Storing or holding of the HMA in approved storage facilities will be permitted with approval of the Engineer, but in no event shall the HMA be held for more than 24 hours. HMA held for more than 24 hours after mixing shall be rejected. Rejected HMA shall be disposed of by the Contractor at no expense to the Contracting Agency. The storage facility shall have an accessible device located at the top of the cone or about the third point. The device shall indicate the amount of material in storage. No HMA shall be accepted from the storage facility when the HMA in storage is below the top of the cone of the storage facility, except as the storage facility is being emptied at the end of the working shift. If Recycled asphalt pavement (RAP) is allowed per section 5-04.2, RAP utilized in the production of HMA shall be sized prior to entering the mixer so that a uniform and thoroughly mixed HMA is produced. If there is evidence of the recycled asphalt pavement not breaking down during the heating and mixing of the HMA, the Contractor shall immediately suspend the use of the RAP until changes have been approved by the Engineer. After the required amount of mineral materials, RAP, new asphalt binder and asphalt rejuvenator have been introduced into the mixer the HMA shall be mixed until complete and uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials, and RAP is ensured..

5-04.3(7) Spreading and Finishing

(April 2, 2018 Lacey)

Delete this section and replace it with the following: The mixture shall be laid upon an approved surface, spread, and struck off to the grade and elevation established. HMA pavers complying with Section 5-04.3(3) shall be used to distribute the mixture. Unless otherwise directed by the Engineer, the nominal compacted depth of any layer of any course shall not exceed the following: HMA Class 1” 0.35 feet HMA Class ¾” and HMA Class ½” wearing course 0.208 feet other courses 0.25 feet HMA Class ⅜” 0.17 feet On areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impractical, the paving may be done with other equipment or by hand. When more than one JMF is being utilized to produce HMA, the material produced for each JMF shall be placed by separate spreading and compacting equipment. The intermingling of HMA produced from more than one JMF is prohibited. Each strip of HMA placed during a work shift

Page 120: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-84

shall conform to a single JMF established for the class of HMA specified unless there is a need to make an adjustment in the JMF. The Contractor shall complete the first lift over the entire length of the project, before the final lift will be allowed to be installed. If traffic signal loops are required, these loops shall be installed prior to the final lift.

5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: For HMA accepted by nonstatistical evaluation the aggregate properties of sand equivalent, uncompacted void content and fracture will be evaluated in accordance with Section 3-04. Sampling and testing of aggregates for HMA accepted by commercial evaluation will be at the option of the Engineer.

5-04.3(9) HMA Mixture Acceptance

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: Acceptance of HMA shall be as provided under nonstatistical, or commercial evaluation. Nonstatistical evaluation will be used for the acceptance of HMA unless Commercial Evaluation is specified. Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, prelevel, temporary pavement, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Engineer. The mix design will be the initial JMF for the class of HMA. The Contractor may request a change in the JMF. Any adjustments to the JMF will require the approval of the Engineer and may be made in accordance with this section. HMA Tolerances and Adjustments 1. Job Mix Formula Tolerances – The constituents of the mixture at the time of acceptance shall be within tolerance. The tolerance limits will be established as follows: For Asphalt Binder and Air Voids (Va), the acceptance limits are determined by adding the tolerances below to the approved JMF values. These values will also be the Upper Specification Limit (USL) and Lower Specification Limit (LSL) required in Section 1-06.2(2)D2

Property Non-Statistical Evaluation Commercial Evaluation Asphalt Binder +/- 0.5% +/- 0.7% Air Voids, Va 2.5% min. and 5.5% max N/A

For Aggregates in the mixture: a. First, determine preliminary upper and lower acceptance limits by applying the following tolerances to the approved JMF.

Page 121: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-85

Aggregate Percent Passing Non-Statistical Evaluation Commercial Evaluation 1”, ¾”, ½”,and 3/8” sieves +/- 6% +/- 8% No. 4 sieve +/- 6% +/- 8% No. 8 Sieve +/- 6% +/- 8% No. 200 sieve +/- 2.0% +/- 3.0%

b. Second, adjust the preliminary upper and lower acceptance limits determined from step (a) the minimum amount necessary so that none of the aggregate properties are outside the control points in Section 9-03.8(6). The resulting values will be the upper and lower acceptance limits for aggregates, as well as the USL and LSL required in Section 1-06.2(2)D2. 2. Job Mix Formula Adjustments – An adjustment to the aggregate gradation or asphalt binder content of the JMF requires approval of the Engineer. Adjustments to the JMF will only be considered if the change produces material of equal or better quality and may require the development of a new mix design if the adjustment exceeds the amounts listed below. a. Aggregates –2 percent for the aggregate passing the 1½″, 1″, ¾″, ½″, ⅜″, and the No. 4 sieves, 1 percent for aggregate passing the No. 8 sieve, and 0.5 percent for the aggregate passing the No. 200 sieve. The adjusted JMF shall be within the range of the control points in Section 9-03.8(6). b. Asphalt Binder Content – The Engineer may order or approve changes to asphalt binder content. The maximum adjustment from the approved mix design for the asphalt binder content shall be 0.3 percent

5-04.3 (9)D Mixture Acceptance – Commercial Evaluation

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: If sampled and tested, HMA produced under Commercial Evaluation and having all constituents falling within the tolerance limits of the job mix formula shall be accepted at the unit Contract price with no further evaluation. When one or more constituents fall outside the commercial tolerance limits in the Job Mix Formula shown in 5-04.3(9), the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The commercial tolerance limits will be used in the calculation of the CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the existing sublots or samples from the street shall be tested to provide a minimum of three sets of results for evaluation. For each lot of HMA mix produced and tested under Commercial Evaluation when the calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The Job Mix Compliance Price Adjustment will be calculated as the product of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. If a constituent is not measured in accordance with these Specifications, its individual pay factor will be considered 1.00 in calculating the Composite Pay Factor (CPF).

5-04.3(10) HMA Compaction Acceptance

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following:

Page 122: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-86

HMA mixture accepted by nonstatistical evaluation that is used in traffic lanes, including lanes for intersections, ramps, truck climbing, weaving, and speed change, and having a specified compacted course thickness greater than 0.10-foot, shall be compacted to a specified level of relative density. The specified level of relative density shall be a Composite Pay Factor (CPF) of not less than 0.75 when evaluated in accordance with Section 1-06.2, using a LSL of 92.0 (minimum of 92 percent of the maximum density). The maximum density shall be determined by WSDOT FOP for AASHTO T 729. The specified level of density attained will be determined by the evaluation of the density of the pavement. The density of the pavement shall be determined in accordance with WSDOT FOP for WAQTC TM 8, except that gauge correlation will be at the discretion of the Engineer, when using the nuclear density gauge and WSDOT SOP 736 when using cores to determine density. Tests for the determination of the pavement density will be taken in accordance with the required procedures for measurement by a nuclear density gauge or roadway cores after completion of the finish rolling. If the Contracting Agency uses a nuclear density gauge to determine density the test procedures FOP for WAQTC TM 8 and WSDOT SOP T 729 will be used on the day the mix is placed and prior to opening to traffic. Roadway cores for density may be obtained by either the Contracting Agency or the Contractor in accordance with WSDOT SOP 734. The core diameter shall be 4-inches minimum, unless otherwise approved by the Engineer. Roadway cores will be tested by the Contracting Agency in accordance with WSDOT FOP for AASHTO T 166. If the Contract includes the Bid item “Roadway Core” the cores shall be obtained by the Contractor in the presence of the Engineer on the same day the mix is placed and at locations designated by the Engineer. If the Contract does not include the Bid item “Roadway Core” the Contracting Agency will obtain the cores. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the Engineer is satisfied that material conforming to the Specifications can be produced. HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used for preleveling wheel rutting shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer. Test Results For a sublot that has been tested with a nuclear density gauge that did not meet the minimum of 92 percent of the reference maximum density in a compaction lot with a CPF below 1.00 and thus subject to a price reduction or rejection, the Contractor may request that a core be used for determination of the relative density of the sublot. The relative density of the core will replace the relative density determined by the nuclear density gauge for the sublot and will be used for calculation of the CPF and acceptance of HMA compaction lot. When cores are taken by the Contracting Agency at the request of the Contractor, they shall be requested by noon of the next workday after the test results for the sublot have been provided or made available to the Contractor. Core locations shall be outside of wheel paths and as

Page 123: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-87

determined by the Engineer. Traffic control shall be provided by the Contractor as requested by the Engineer. Failure by the Contractor to provide the requested traffic control will result in forfeiture of the request for cores. When the CPF for the lot based on the results of the HMA cores is less than 1.00, the cost for the coring will be deducted from any monies due or that may become due the Contractor under the Contract at the rate of $200 per core and the Contractor shall pay for the cost of the traffic control.

5-04.3(10)D HMA Compaction-Visual Evaluation

Delete this section and replace it with the following:

5-04.3(10)D HMA Nonstatistical Compaction

5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots

(July 18, 2018 APWA GSP)

Add the following new section: HMA compaction which is accepted by nonstatistical evaluation will be based on acceptance testing performed by the Contracting Agency dividing the project into compaction lots. A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance. A lot is defined as the total quantity of material or work produced for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to one day’s production or 400 tons, whichever is less except that the final sublot will be a minimum of 200 tons and may be increased to 800 tons. Testing for compaction will be at the rate of 5 tests per sublot per WSDOT T 738. The sublot locations within each density lot will be determined by the Engineer. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the Engineer is satisfied that material conforming to the Specifications can be produced. HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used to prelevel wheel ruts shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer.

5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance Testing

(July 18, 2018 APWA GSP)

Add the following new section: The location of the HMA compaction acceptance tests will be randomly selected by the Engineer from within each sublot, with one test per sublot.

5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments

(July 18, 2018 APWA GSP)

Add the following new section:

Page 124: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-88

For each compaction lot with one or two sublots, having all sublots attain a relative density that is 92 percent of the reference maximum density the HMA shall be accepted at the unit Contract price with no further evaluation. When a sublot does not attain a relative density that is 92 percent of the reference maximum density, the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The maximum CPF shall be 1.00, however, lots with a calculated CPF in excess of 1.00 will be used to offset lots with CPF values below 1.00 but greater than 0.90. Lots with CPF lower than 0.90 will be evaluated for compliance per 5-04.3(11). Additional testing by either a nuclear moisture-density gauge or cores will be completed as required to provide a minimum of three tests for evaluation. For compaction below the required 92% a Non-Conforming Compaction Factor (NCCF) will be determined. The NCCF equals the algebraic difference of CPF minus 1.00 multiplied by 40 percent. The Compaction Price Adjustment will be calculated as the product of CPF, the quantity of HMA in the compaction control lot in tons, and the unit Contract price per ton of mix.

5-04.3(11)C Rejection Without Testing (Mixture or Compaction)

(July 18, 2018 APWA GSP)

Delete this section and replace it with the following: The Engineer may, without sampling, reject any batch, load, or section of Roadway that appears defective. Material rejected before placement shall not be incorporated into the pavement. Any rejected section of Roadway shall be removed. No payment will be made for the rejected materials or the removal of the materials unless the Contractor requests that the rejected material be tested. If the Contractor elects to have the rejected material tested, a minimum of three representative samples will be obtained and tested. Acceptance of rejected material will be based on conformance with the nonstatistical acceptance Specification. If the CPF for the rejected material is less than 0.75, no payment will be made for the rejected material; in addition, the cost of sampling and testing shall be borne by the Contractor. If the CPF is greater than or equal to 0.75, the cost of sampling and testing will be borne by the Contracting Agency. If the material is rejected before placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at a CPF of 0.75. If rejection occurs after placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at the calculated CPF with an addition of 25 percent of the unit Contract price added for the cost of removal and disposal.

5-04.3(12)A1 Transverse Joints

(April 2, 2018 Lacey)

Delete this section and replace it with the following: The Contractor shall conduct operations such that the placing of the top or wearing course is a continuous operation or as close to continuous as possible. Unscheduled transverse joints will be allowed and the roller may pass over the unprotected end of the freshly laid mixture only when the placement of the course must be discontinued for such a length of time that the mixture will cool below compaction temperature. When the Work is resumed, the previously compacted mixture shall be cut back to produce a slightly beveled edge for the full thickness of the course. All joints must be flush and provide a smooth transition across the meet line. A temporary wedge of HMA constructed on a 24H:1V shall be constructed where a transverse joint as a result of paving or planing is open to traffic. The wedge shall be maintained until the

Page 125: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-89

paving is resumed. The HMA in the temporary wedge shall be separated from the permanent HMA by strips of heavy wrapping paper or other methods approved by the Engineer. The wrapping paper shall be removed and the joint trimmed to a slightly beveled edge for the full thickness of the course prior to resumption of paving. The material that is cut away shall be wasted and new mix shall be laid against the cut. Rollers or tamping irons shall be used to seal the joint.

5-04.3(12)A2 Longitudinal Joints

(April 2, 2018 Lacey)

Supplement this section with the following: Cold joints shall be allowed only at locations approved by the Engineer. Upon Completion of paving operations, all joints shall be sealed with PG 58H-22 asphalt binder.

5-04.3(19) Submittals - Paving Plan

(October 30, 2018 Lacey)

Add the following new section: The Contractor must submit a paving plan to the Engineer at least 5 Working Days in advance of the start date. These plans must show how the moving operation and traffic control are coordinated, as they will be discussed at the pre-paving briefing. When requested by the Engineer, the Contractor must provide the traffic control plan with a scale showing both the area of operation and sufficient detail of traffic beyond the area of operation where detour traffic may be required. The traffic control plan must show where flaggers are proposed. At a minimum, the plan must include: 1. A copy of the accepted traffic control plan, see Section 1-10.2(2), detailing each day’s traffic control as it relates to the specific requirements of that day’s work. Briefly describe the sequencing of traffic control consistent with the proposed work sequence, and scheduling of placement of temporary pavement markings and channelizing devices after each day’s work. 2. Names and locations of HMA Supplier facilities to be used, and locations of temporary parking and staging areas. 3. List of all equipment to be used for paving. 4. Description (geometric or narrative) of the scheduled sequence of work, and intended area for each day’s work, must include the directions of proposed paving, sequence of adjacent lane paving, sequence of skipped lane paving, intersection scheduling and sequencing. 5. Approximate times and days for starting and ending daily operations.

5-04.3(20) Pre-Paving Briefing

(October 30, 2018 Lacey)

Add the following new section:

Page 126: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-90

At least 2 Working Days before the first paving operation and the first planing operation, or as scheduled by the Engineer for future paving and planing operations to ensure the Contractor has adequately prepared for notifying and coordinating as required in the Contract, the Contractor must be prepared to discuss that day’s operations as they relate to other entities and to public safety and convenience, including driveway and business access, garbage truck operations, Metro transit operations and working around energized overhead wires, school and nursing home and hospital and other accesses, other contractors who may be operating in the area, pedestrian and bicycle traffic, and emergency services. The Contractor, and Subcontractors that may be part of that day’s operations, must meet with the Engineer and discuss the proposed operation as it relates to the submitted paving plan, approved traffic control plan, and public convenience and safety. Such discussion includes, but is not limited to: 1. The actual times of starting and ending daily operations. 2. The sequencing and scheduling of paving operations and of planing operations, as applicable, as it relates to traffic control, to public convenience and safety, and to other con-tractors who may operate in the Project Site. 3. Notifications required of Contractor activities, and coordinating with other entities and the public as necessary. 4. Description of the sequencing of installation and types of temporary pavement markings as it relates to planning and to paving. 5. Description of the sequencing of installation of, and the removal of, temporary pavement patch material around exposed castings and as may be needed 6. Description of procedures and equipment to identify hidden metal in the pavement, such as survey monuments, monitoring wells, street car rail, and castings, before planning, see Section 5-04.3(14)B2. 7. Description of how flaggers will be coordinated with the planing, paving, and related operations. 8. When to start applying tack and coordinating with paving. 9. Description of contingency plans for that day’s operations such as equipment breakdown, rain out, and Supplier shutdown of operations. 10. Number of sublots to be placed, sequencing of density testing, and other sampling and testing.

5-04.3(21) Paving Operations Supervisor

(April 2, 2018 Lacey GSP)

Add the following new section: The Contractor shall identify a Paving Operations Supervisor (POS) at the Preconstruction Conference. The POS shall be employed by the Paving Contractor, shall have direct and immediate control of the paving operations on the Project at all times, and shall perform no other duties on the project. No part of the paving operations shall commence or continue without the physical presence of the POS on-site. The POS shall act as the main point of contact in the field to the Engineer and shall execute all requests by the Engineer promptly and immediately.

Page 127: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-91

Specific duties include, but are not limited to the following: Ensures all paving operations meet the requirements of Section 5-04. Ensures all iron is marked and properly lowered prior to pavement planing operations. Ensures paving schedule is communicated to the Engineer 72 hours in advance of paving operations commencing. The Engineer shall be responsible for delivering paving notices to affected business owners and residents. Any changes to the paving schedule must also be communicated to the Engineer 72 hours in advance of the change. Ensures existing surfaces to be paved are prepared in accordance with Sec. 5-04.3(4) a minimum of two (2) hours prior to paving. Specific attention shall be given to surface cleanliness, match lines to adjoining pavement are vertical and smooth, and matching to existing driveways and rolled gutters are prepared. In the event that preparation of existing surfaces are behind schedule, paving operations may be halted and rescheduled at the Engineer’s request if, in his judgment, the delay of paving shall result in a less than satisfactory end product or inconvenience to the public. All costs resulting from paving rescheduling shall be borne by the Contractor. Ensures all tack coating is completed in accordance with Sec. 5-04.3(4).

5-04.3(22) Temporary Patching

(April 2, 2018 Lacey GSP)

Add the following new section: All excavations within or across streets, driveways, or failure of existing pavement that will be exposed to traffic shall be temporarily patched by the end of the working day or as directed by the Engineer. The patch shall be constructed of a minimum of 0.17 feet of either Commercial HMA or as directed by the Engineer. The Contractor shall maintain all temporary patches until such time as the permanent pavement is in place.

5-04.3(24) Roadway Shoulder Final Grading

(April 2, 2018 Lacey GSP)

Add the following new section: The Contractor shall backfill and grade a 5 foot wide or a 5:1 transition (whichever is less) flush from the new edge of pavement down to the existing shoulder grade with Crushed Rock or Topsoil Type A to match existing shoulder material and condition. The Crushed Rock shall match gradation, shape, and color to of the existing rock shoulder. Upon placing and grading either material, the Contractor shall roll and compact the transition as directed by the Engineer. The Contractor shall then hydroseed all shoulder transitions backfilled with topsoil.

5-04.3(25) HMA Wedge Curb

(April 2, 2018 Lacey GSP)

Add the following new section: The Contractor shall construct a HMA wedge curb where shown on the plans and shall be integral to the mainline paving operation respective to being placed and compacted. HMA used for wedge curb shall be compensated with the HMA bid item per ton and no other compensation shall be allowed.

5-04.4 Measurement

(******)

Page 128: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-92

Supplement this section with the following: Commercial HMA shall be measured per ton of material required to complete asphalt patch restoration and repair.

5-04.5 Payment

(April 2, 2018 Lacey GSP)

Supplement this section with the following: The unit Contract price per ton for all HMA bid items shall also include Paving Operations Supervisor (POS) and the removal of excess tack coat of asphalt from existing surfaces, including, but not limited to existing pavement markings. Pavement markings shall be restored to a pre-construction condition or better. No additional compensation shall be given to the Contractor for installing new pavement markings if existing pavement markings cannot be restored to a pre-construction condition or better as directed by the Engineer. If no bid item for “HMA for Pre-leveling Cl. __ PG __ ” is included, all materials, equipment, and labor necessary to pre-level the existing pavement prior to paving shall be fully compensated by the bid item “HMA Cl. __ PG __ ” and “Fiber Reinforced HMA Cl. PG ” and no other pay shall be allowed. The unit Contract price per ton for “HMA for Pavement Repair Cl PG “ shall also include all costs for constructing speed humps as shown in the plans, including pavement markings if no bid item for this is included in the proposal. “Roadway Core”, per each. The Contractor’s costs for all other Work associated with the coring (e.g., traffic control) shall be incidental and included within the unit Bid price per each and no additional payments will be made. “Preparation of Existing Surfaces,” lump sum. The lump sum contract price for “Preparation of Existing Surfaces” shall be full pay for all labor, materials, and equipment to remove all vegetation from proposed paved surfaces or that vegetation that will interfere with paving operations prior to paving. “Driveway and Shoulder Preparation”, lump sum. The lump sum contract price for “Driveway and Shoulder Preparation” shall be full pay for all labor, materials, and equipment to cut, fill, and grade all driveways and shoulders prior to paving. “Crushed Rock for Shoulder Grading,” per ton. “Topsoil Type A for Shoulder Grading,” per cubic yard. The unit contract price for the above bid items shall be full compensation for all labor, material and equipment, including seeding of topsoil, to provide a smooth transition between the new edge of pavement and existing roadway.

7-08 GENERAL PIPE INSTALLATION REQUIREMENTS

7-08.1 Description

(December 31, 2014 Lacey GSP)

Page 129: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-93

This section is revised to read: This work includes installing culverts, storm sewers, sanitary sewers, and water mains. The contractor shall also follow Section 7-02, 7-04, 7-09 or 7-17 as it applies to the specific kind of Work.

7-08.2 Materials

(October 16, 2009 Lacey GSP)

Supplement this section with the following: Bank Run Gravel for Trench Backfill shall be in accordance with Section 9-03.19. Controlled Density Fill shall be in accordance with Section 2-09.3(1)E. Imported Pipe Bedding shall be in accordance with Section 9-03.16.

7-08.3 Construction Requirements

7-08.3(1) Excavation and Preparation of Trench

(October 30, 2018 Lacey GSP)

Supplement this section with the following: The contractor shall locate and preserve all existing utilities per RCW 19.122. Utility locations shown on the plans depict the physical features that were visible at the time of the survey. The City of Lacey is not responsible for the location of underground utilities that are marked or not marked in the field by other utility providers. Utility service laterals are not typically shown on plans or locatable and the contractor shall anticipate such services. The City will locate the meters and the mains. For service laterals, pursuant to RCW 19.122.030, the City will indicate a presence of an un-locatable service lateral and if requested can meet with the contractor or provide copies of available records. The Contractor shall have a crimping tool available during excavation to crimp any broken water services. Before commencing work, the contractor shall coordinate with One-Call services to determine the location of all utilities. The Contractor shall pothole all apparent conflicts between existing utilities and proposed construction as approved by the Engineer. The Contractor shall notify Engineer of location and approximate time to complete prior to potholing. The Contractor shall notify the Engineer of any conflicts with the existing utilities and proposed work at least 3 days prior to proceeding with work. Potholing of the utilities shall be completed a minimum distance of 300 feet in front of pipe laying operations. No adjustment to the contract price or time will be made if the contractor fails to follow this specification. Potholing for Utility Crossings and Connections shall be performed by the Contractor using vacuum excavation truck or other device approved by the Engineer. If the Contractor potholes prior to approval no compensation shall be made for the potholing. The Contractor shall deflect pressurized pipe at the joints no greater than the maximum allowable deflection as determined by the pipe or fitting manufacturer to avoid conflicts with crossing utilities. Vertical bends and vertical thrust blocking shall be avoided by deflecting pipe either upwards or downwards prior to the utility crossing.

7-08.3(1)A Trenches

(December 31, 2014 Lacey GSP)

Section 7-08.3(1)A is supplemented with the following to the fourth paragraph:

Page 130: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-94

All material excavated from trenches shall not be piled on the roadway.

7-08.3(1)C Bedding the Pipe

(February 25, 2015 Lacey GSP)

Section 7-08.3(1)C is supplemented with the following If native material meets the requirements of 7-08.2 the Contractor shall use all suitable native material prior to using imported pipe bedding or bank run gravel. All material shall be approved by the Engineer prior to placement. If the Contractor places imported material prior to approval, no compensation shall be made for the imported material.

7-08.3(3) Backfilling

(October 30, 2018 Lacey GSP)

Supplement this section with the following: For backfilling trenches for longitudinal runs of pipe, the Contractor shall use all suitable native material prior to using bank run gravel and/or controlled density fill. All native backfill material shall be approved by the Engineer prior to placement. If the Contractor places imported material prior to approval, no compensation shall be made for the imported material. All backfill material shall be compacted and tested according to Section 2-03.3(14)D. For transverse runs of pipe including the service lines within the roadway prism, the Contractor shall use controlled density fill unless approved otherwise by the Engineer. All native material shall be excavated, hauled and disposed of offsite. All exceptions shall be approved by the Engineer. At the end of each workday, the Contractor shall install a lift of temporary asphalt cold mix on top of the trench backfill, flush with the existing pavement. No trench excavation shall be exposed to traffic without a temporary asphalt cold mix sealing the existing pavement surface. If approved by the Engineer, the Contractor may choose to use HMA for Pavement Repair Cl. ½” PG 64-22 for permanent pavement repair if a bid item for this work has been included in the Proposal. All costs associated with providing and removal of temporary asphalt cold mix shall be incidental to the bid item for the pipe being installed and no other compensation will be allowed.

7-08.3(3)A Controlled Density Fill

(December 31, 2014 Lacey GSP)

Section 7-08.3(3)A is added with the following: The Contractor shall use controlled density fill (CDF) as shown in the Plans or directed by the Engineer. Controlled Density Fill shall meet the following requirements: 1750# Sand, 1750# Pea Gravel, 230# Water, 141# Portland Cement, 6 ounces Water Reducing Agent per 100 lbs. cement.

Page 131: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-95

The Controlled Density Fill will require 24 hours of cure time, or as directed by the Engineer. Prior to backfill, all appurtenances shall be covered with 11 mill plastic as directed by the Engineer.

7-08.3(3)B Steel Plating for Pipe Trench

(February 25, 2015 Lacey GSP)

Section 7-08.3(3)B is added with the following: The Contractor shall install steel plating over the trench per the plans to allow for CDF to fully cure and allow vehicle traffic to pass during non-working hours. The steel plating shall remain complete over the trench until the pavement repair is complete. This process shall be coordinated so that there will be minimum inconvenience to the public. All costs for all labor, materials, and equipment to furnish, place, assemble, install, maintain and remove the steel plates and associated materials shall be included in the unit contract price per foot of pipe installed and no additional compensation shall be allowed.

7-08.3(5) Pipe Abandonment

(April 30, 2015 Lacey)

Add the following new section: The Contractor shall abandon pipes where shown on the Plans or directed by the Engineer. For abandonment, removal, handling and disposal of asbestos cement piping, refer to Section 7-09.3(19)D of these Special Provisions. All abandonments shall be done after all new utility mains and service connections are installed unless authorized by the Engineer. Abandonments shall include all excavation, pipe cutting and removal, fittings, concrete plugging, and backfilling. Some abandonments require specific fittings as indicated on the Plans. All fittings required to complete the abandonment shall be included in the cost for the abandonment. Potholing per 7-08.3(1) to verify required fittings shall be done as directed by the Engineer. Pipe abandonments shall be completed in cooperation with the engineer in order to minimize disruption of utility service to the residents. If water services will be interrupted follow the requirements of 7-09.3(19)B. All pipes to be abandoned shall have the first 2 linear feet of abandoned pipe filled/plugged with a watertight concrete grout. The inspector shall inspect the abandonment prior to backfilling. In the case of an abandonment associated with a connection to an existing main, no payment shall be made for the bid item “Pipe Abandonment”. The Contractor shall include all costs with these associated abandonments under the “Connect to Existing Water Main”, “Connect to Existing Reclaimed Water Main”, “Connect to Existing Gravity Sewer Main”, or “Connect to Existing Sanitary Sewer Main” pay item. In addition, payment for “Pipe Abandonment” will only be paid for the locations and quantities called out on the plans or as directed by the Engineer.

7-08.3(8) Detectable Marking Tape

(January 4, 2016 Lacey)

Add the following new section: All pipeline installed under this contract will be identified by a continuous color coded tracer marker. For pressure lines it shall be buried 12 inches to 18 inches below finished grade, and for

Page 132: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-96

sewer lines it shall be buried 24 inches to 30 inches below finished grade. The marker shall be imprinted every 30 to 40 inches in permanent black ink indicating the type of line buried below and shall also have the word “Caution” prominently shown. The tracer marker shall be plastic non-biodegradable and have a metallic core or backing which can be detected by a standard metal detector. In addition to the , detectable marking tape a U.S.E coated 12 gauge tracer wire shall be taped to all mains and service lines. The wire shall be brought up and tied to all valves and meter boxes. The tracer wire shall be looped up into all valve boxes per the plans. A low voltage grease-type splice kits, or better shall be used on all tracer wire connection points. After the wire nut is used to connect the wire together an overhand knot shall be tied just outside the connection to prevent it from coming apart. All service and mainline tracer wires shall be properly connected. A tracer wire magnesium anode shall be installed at all dead ends of the tracer / locate system. On long stretches of pipe anodes may be required at a minimum spacing of 1000’. The anode type shall be Copperhead Anode Part# ANO-14, 1.5# x 1.315”Dx18.5”L or approved equal. When connecting a new main or a new service to an existing main, the new tracer wire shall be connected to the existing tracer wire if available. Special high strength locate wire may be required for directional drilling where the wire is allowed to be pulled in with the pipe or conduit. High strength wire shall be Neptco Trace-Safe 1800 lb. strength or approved equal and shall be connected with the wire manufacturer’s connections. Continuity or locate testing of the wire will be done by the City. The contractor shall give 72 hours notice for continuity testing by the City. The testing shall be conducted prior to paving or final restoration of landscape areas. The locating device will be connected to the tracer wire at any or all Gate Valves and Services and tracer wire shall transmit an acceptable signal strength as determined by the City for a minimum of 300 feet. Contractor will locate and repair any failed connections. The wire shall be furnished and installed by the Contractor. Color coding of tape and wire shall be as follows:

a) Water – Blue b) Sewer – Green c) Reclaimed – Purple d) Electrical conduits – Red e) Communication Conduits - Orange

Installation of the pipeline tracer marker and 12 gauge coated copper wire is considered incidental to the construction of the pipe and conduits and no other compensation will be allowed.

7-08.4 Measurement

(October 30, 2018 Lacey)

Supplement this section with the following: “Imported Pipe Bedding” will be measured per ton. “Bank Run Gravel for Trench Backfill” will be measured per ton. “Utility Potholing”, will be measured per hour. “Pipe Abandonment” will be measured per each, for each section called out on the Plans. “Controlled Density Fill” will be measured by the cubic yard for the quantity of material placed.

Page 133: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-97

7-08.5 Payment

(October 30, 2018 Lacey)

Supplement this section with the following: “Bank Run Gravel for Trench Backfill” per ton and “Imported Pipe Bedding” per ton. The unit contract price per ton for "Bank Run Gravel for Trench Backfill" and “Imported Pipe Bedding” shall be full compensation for all labor, material and equipment to furnish, place and compact the backfill. Native material used for backfill shall be considered incidental to the pipe installation and no additional compensation shall be allowed. Payment shall be based on actual amount of imported bedding or bank run gravel for trench backfill used. The Engineer reserves the right to adjust the bid proposal quantity as required. There will be no additional compensation made for the removal and wasting of trench excavation that is unsuitable for backfill. If no bid item for “Bank Run Gravel for Trench Backfill” or “Imported Pipe Bedding” is included, any work described in these sections shall be included in the unit contract price per foot of pipe installed and no additional compensation shall be allowed. “Utility Potholing”, per hour shall be full compensation for all labor, material and equipment necessary to excavate, backfill, and restore the utility location(s) required by the Engineer and determine its vertical and horizontal location. Utility potholing will only be paid for work approved by the Engineer in advance. If no bid item for “Utility Potholing” is included, any work described in this section shall be incidental to the project. “Pipe Abandonment”, per each. The unit contract price per each for “Pipe Abandonment” shall be full pay for providing all labor, tools, equipment and materials necessary to abandon the specified piping including the plug material. If no bid item for “Pipe Abandonment” is included, any work described in this section shall be incidental to the project. “Controlled Density Fill”, per cubic yard. If no bid item for “Controlled Density Fill” is included, any work described in this section shall be incidental to the project.

7-22 LIFT STATION (October 29, 2010 Lacey)

Add the following new section:

7-22.1 Description

(******)

Page 134: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-98

The Contractor shall modify the existing Lift Stations, provide site restoration, standby power generation systems, electrical and control systems, electric power and control wiring raceways, wiring, reinforced concrete pads, and all lift station appurtenances as shown in the Plans, and described in these Special Provisions, Standard Specifications, and the Technical Specifications. This work consists of furnishing, installing, testing and placing in satisfactory and successful operation all equipment, materials, devices and necessary appurtenances to provide a complete sanitary sewer pump station at each location, together with such other miscellaneous installations and equipment hereinafter specified and/or shown in the Plans. This work shall include all materials, appliances and appurtenances not specifically mentioned herein or shown in the Plans, but which are necessary to make a complete working installation of all systems shown in the Plans or described herein or in the Technical Specifications. This work shall include standby power generator system design, manufacturing, testing, and having a local supplier responsible for service, parts, and warranty for the total system.

7-22.2(1) Electrical System

(October 29, 2010 Lacey)

General See the Technical Specifications and Plans for detailed information. Permits & Fees The Contractor shall obtain and pay for all licenses, permits and inspections required by laws, ordinances and rules governing work specified herein. The Contractor shall arrange for inspection of work by the inspectors and shall give the inspectors all necessary assistance in their work of inspection. The Contractor shall consult with and follow the requirements of the local fire, power, telephone, and television utilities serving the area and shall coordinate his work with them. As-Built Drawings The Contractor shall maintain, in addition to any reference drawings, an as-built set of prints, on which all deviations from the original design shall be drafted in a neat, legible manner with red colored pen or pencil. The red-lined plans shall identify all revisions including addenda items, change orders, and Contractor revisions. The Contractor is responsible to revise panel schedules and load calculations as required. Upon completion of the lift station electrical work, the Contractor shall deliver the red-lined plans to the City. Instruction Periods Upon completion of the work and after all tests and final inspection of the work by the City, the Contractor shall demonstrate and instruct the City’s designated operation and maintenance personnel in the operation and maintenance of the various electrical systems. The Contractor shall arrange scheduled instruction periods with the City. The Contractor's representatives shall be superintendents or foremen knowledgeable in each system and suppliers representatives when so specified. Scheduled instruction periods shall be: 1. Generator and Automatic Transfer Switch 1 day

Page 135: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-99

Shop Drawing Submittals The Contractor shall submit to the Engineer, detailed shop drawings, to include: 1. Manufacturer's Catalog Data. 2. Complete Physical and Technical Data. 3. Wiring Diagrams where applicable. 4. Detailed Reference (written or highlighted) noting compliance with the appropriate specification section and applicable item numbers within that section. 5. Other Descriptive Data as required by the Engineer. Shop drawings shall be submitted individually, attached to an e-mail noting the specification and section being submitted and shall be, but not limited to the items of equipment listed below: 1. Disconnect Switches 2. Arc Flash Protection Study 3. Electrical System Protective Device Study 4. Wiring Devices 5. Device Boxes 6. Coverplates 7. Raceways and Connectors 8. Copper Wire 9. Automatic Transfer Switches 10. Generator System 11. All Specialty Systems not listed above. 12. Any other items requested by Engineer. All submittals shall have a completed City provided submittal form attached to the transmittal. Submittals deemed too large to be transmitted via e-mail shall be transmitted to the Engineer via compact disc or digital video disc. A printed copy of the digital submittal form shall be included with any physical media transmitted. The submittal form will be completed and returned to the Contractor indicating the submittal status.

7-22.3(1) Lift Station Modification

(******)

The existing lift stations shall be modified as shown in the Plans and described in the Project Technical Specifications. The Contractor shall remove existing conduit, structures, foundation, trees, stumps, and paving as shown on the plans and as necessary for construction of the new facilities. Items not being salvaged shall be properly disposed of. The disposal cost shall be included in the lump sum bid price for “Removal of Structures and Obstructions”. Electrical systems shall be modified at each Lift Station Site per plans and follows: Lift Station 4 - Reuse existing 208V utility feeders, conduit, and utility meter. Install new disconnect, A.T.S., and associated wiring. Install new generator 208V circuit, block heater, battery charger, run, fail and start circuits. Lift Station 5 - Reuse existing 208V utility feeders, conduit, and utility meter. Install new disconnect, A.T.S., and associated wiring. Install new generator 208V circuit, block heater, battery charger, run, fail and start circuits.

Page 136: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-100

Lift Station 8 - Reuse existing 208V utility feeders. Install new conduit, utility meter, disconnect, A.T.S., and associated wiring. Install new generator 208V circuit, block heater, battery charger, run, fail and start circuits. Lift Station 11 - Reuse existing 208V utility feeders. Install new conduit, utility meter, disconnect, A.T.S., and associated wiring. Install new generator 208V circuit, block heater, battery charger, run, fail and start circuits. Lift Station 17 - Reuse existing 480V utility feeders and conduit. Install new utility meter, disconnect, A.T.S., and associated wiring. Install new generator 480V circuit, block heater, battery charger, run, fail and start circuits. Lift Station 24 - Reuse existing 240V utility feeders, conduit, and utility meter. Install new conduit to disconnect, disconnect, A.T.S., and associated wiring. Install new generator 240V circuit, block heater, battery charger, run, fail and start circuits. Lift Station 27 - Reuse existing 240V utility feeders and conduit. Install new utility meter, disconnect, A.T.S., and associated wiring. Install City-provided generator 240V circuit, block heater, battery charger, run, fail and start circuits.

7-22.3(3)B Operation, Maintenance And Service Manuals, And Parts Books

(October 29, 2010 Lacey)

The systems manufacturer or their authorized local dealer shall furnish three hard copies and one electronic PDF copy of the manuals and books listed below for each unit provided under this contract. Each lift station site shall receive a customized copy of the manuals and books listed below. Operating Instructions Manual shall include description and illustration of all switchgear controls and indicators, engine and generator controls and indicators, and control and power subsystems. Parts Books Manual shall illustrate and list all assemblies, subassemblies and components, except standard fastening hardware (nuts, bolts, washers, etc.). Preventative Maintenance Instructions Manual shall include instructions on the complete system that cover daily, weekly, monthly, biannual, and annual maintenance requirements and include a complete lubrication chart. Routine Test Procedures Manual shall include test procedures for all electronic and electrical circuits and for the main AC generator. Troubleshooting Chart Manual shall cover the complete lift station system showing description of trouble, probable cause, and suggested remedy. Recommended Spare Parts List Manual shall list all consumables anticipated to be required during routine maintenance and testing, and all spare non-consumable items recommended by the subsystem manufacturer.

Page 137: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-101

Wiring Diagrams and Schematics Manual shall include wiring diagrams, schematics, and the function of all electrical components. Electrical System Instructions and Manuals A preliminary copy of manuals, complete except for the bound cover, shall be submitted 20 days prior to completion of the project for checking and review. One electronic and three (3) bound, corrected copies shall be delivered to the City 20 days prior to scheduled instruction periods after review of the preliminary copy. Submit a receipt for the manuals to the Engineer with the completed form. Manuals shall contain shop drawings, final wiring diagrams, operating and maintenance (O&M) instructions, replacement parts lists, and equipment nameplate data for all equipment and systems installed. Control systems equipment submittals shall contain step-by-step circuit description information designed to acquaint maintenance personnel with equipment operation in each mode of operation. Manuals shall contain original brochures supplied by manufacturers indicating the exact equipment installed. Photo Xerox copies of originals will not be accepted. Each type of device provided shall be identified in the O & M Manual using the same identification as shown in the plans and specifications. The information included must be the exact equipment installed not the complete “line” of the Manufacturer. Where sheets show the equipment installed and other equipment, the installed equipment shall be neatly and clearly identified on such sheets. Parts lists shall give full ordering information assigned by the original parts manufacturer. Relabeled and/or renumbered parts information as reassigned by contractor or equipment supplier is not acceptable. The following information shall be provided for each device: 1. Manufacturer's name, address and phone number. 2. Local supplier's name, address and phone number. 3. Complete parts lists including quantities and manufacturer's part numbers. 4. Installation instructions. 5. Recommended maintenance items including maintenance procedure and recommended interval of maintenance listed in hours of operation, calendar unit or other similar time unit. The hard copies of the O & M Manual shall be assembled in a loose leaf, 3-ring, hard cover binder. The information contained in the manuals shall be grouped in an orderly arrangement by specification index. The manuals shall have a typewritten index and divider sheets between categories with identifying tabs. The covers shall be imprinted with the name of the project, City, Electrical Engineer, Contractor, and year of completion. The back edge shall be imprinted with the name of the project, City, and year of completion. The electronic copy of the O&M Manual shall be assembled in the same order as the hard copy, with each section as an individual pdf file. As a minimum, the following selection shall be broken out: 1. Generator and ATS Wiring diagrams for each system shall be complete for the specific system installed. “Typical” line diagrams will not be acceptable unless properly marked to indicate the exact field installation.

7-22.4 Measurement

(October 29, 2010 Lacey)

No unit of measure shall apply to the lump sum price for “Electrical, Controls, and Telemetry”.

Page 138: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-102

No unit of measure shall apply to the lump sum price for “Standby Generator”. No unit of measure shall apply to the lump sum price for “Install City-Provided Standby Generator”. The Contractor shall provide the required schedule of values indicating critical progress points of each bid item to facilitate submission and processing of partial payment request(s) of lump sum bid items.

7-22.5 Payment

(******)

Payment will be made in accordance with Section 1-04.1, for each of the following bid items that are included in the proposal. “Electrical, Controls, and Telemetry”, Per lump sum The unit contract price per lump sum for “Electrical, Controls, and Telemetry” shall be full compensation for all labor, materials and equipment required to provide and install the automatic transfer switch, conduits and fittings including excavation and backfill, conduit supports including concrete foundation and pad, service entrance disconnect, utility meter base, power and signal lines, and all other equipment, assemblies, subassemblies and work appurtenant and peripheral to the standby generator electrical, controls, and telemetry as shown on the Plans and described in the Project Technical Specifications, and these Special Provisions. The unit contract price per lump sum for “Electrical, Controls, and Telemetry” shall also be full compensation for all labor, materials and equipment required to remove the existing generator receptacle on the main control panel, automatic transfer switch, conduits and fitting, conduit supports, service entrance disconnect, utility meter base, power and signal lines, and all other equipment, assemblies, subassemblies and work appurtenant and peripheral to the site electrical, controls, and telemetry, including the covering of penetrations as shown on the Plans and described in the Project Technical Specifications, and these Special Provisions. “Standby Generator”, per lump sum The unit contract price per lump sum for “Standby Generator” shall be full compensation for all labor, materials, and equipment required to provide and install the standby generator, including the excavation, reinforced concrete foundation, and backfill as shown on the Plans and described in the Project Technical Specifications, and these Special Provisions. “Install City-Provided Standby Generator”, per lump sum The unit contract price per lump sum for “Install City-Provided Standby Generator” shall be full compensation for all labor, materials, and equipment to install the City-provided standby generator, and to provide and install the reinforced concrete foundation, including the excavation and backfill as shown on the Plans and described in the Project Technical Specifications, and these Special Provisions.

7-23 SANITARY SEWER BYPASS PUMPING

7-23.1 General

(October 29, 2010 Lacey)

The Contractor is required to furnish all materials, labor, equipment, power, and maintenance, etc. to implement a temporary pumping system for the purpose of diverting the existing sanitary

Page 139: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-103

sewer flow around the work area as needed for the duration of the project. The bypass system as supplied by the contractor shall meet the requirements of all codes and regulatory agencies having jurisdiction, these General Specifications and the Technical Specifications. The Contractor shall submit a bypassing plan to the Engineer in accordance with the Project Technical Specifications. The design, installation, and operation of the temporary pumping system shall be the Contractor’s responsibility. The Contractor shall employ the services of a subcontractor who can demonstrate to the engineer that he specializes in the design and operation of temporary bypass pumping systems. The subcontractor shall provide at least five (5) references of projects of a similar size and complexity as this project performed by his firm within the past three years.

7-23.1(1) Bypass Pumping Plan

(******)

The Contractor shall submit a detailed description of the proposed pumping system and the bypass pumping contractor’s references in conformance with the Project Technical Specifications for review and approval at the pre-construction conference. A separate pre-bypass pumping meeting will be conducted within 4 weeks of submittal of the bypass pumping plan and at minimum 2 weeks prior to the bypass pumping, at which time the Contracting Agency will notify the Contractor of any deficiencies or corrections that are required. Re-submittal of the corrected bypass pumping plan is required. Provided the corrected bypass pumping plan is satisfactory, an additional pre-bypass pumping meeting will not be required.

7-23.3 System Requirements

7-23.3(1) Design Requirements

(******)

Temporary sewer bypass systems shall be designed by a registered Professional Engineer in the State of Washington. Engineer shall have demonstrated experience in the design of pumping systems of comparable size and complexity. The Contractor shall make all arrangements for bypass pumping during the time when the gravity sewer main is shut down for any reason. System shall overcome any existing force main pressure on discharge.

7-23.3(2) Performance Requirements

(******)

It is essential to the operation of the existing system being bypassed that no interruptions in the flow occur throughout the duration of the project. To this end, the Contractor shall provide, maintain, and operate all temporary facilities such as dams, plugs, pumping equipment (both primary and back-up units as required), conduits, all necessary power, and all other labor and equipment necessary to intercept the incoming flow before it reaches the point where it would interfere with his work, carry it past the work area and return it to the existing wastewater collection system downstream of his work. The design, installation and operation of the temporary pumping system shall be the Contractor’s responsibility. The bypass system shall meet the requirements of all codes and regulatory agencies having jurisdiction. It shall be the responsibility of the Contractor to schedule and

Page 140: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-104

perform the work in a manner that does not cause or contribute to incidents of overflows, releases or spills of sewage from the sanitary sewer system or the bypass pumping operation. The Contractor shall provide all necessary means to safely convey the sewage past the work area. The Contractor will not be permitted to stop or impede the main flows under any circumstances. The Contractor shall divert the flow around the work area in a manner that will not cause damage to, or surcharging of Contracting Agency’s system and will protect public and private property from damage and flooding. The Contractor shall protect water resources, wetlands, and other natural resources.

7-23.3(4) Spills

(******)

In the event of a spill, the Contractor will contact the LOTT Spill Reporting Group at (360) 528-5700 and notify the City and Engineer immediately. Spills or leaks of sewage to surface waters or drainage courses is prohibited. In the event of sewage spills, the Contractor shall immediately take whatever actions are deemed necessary to stop and remedy the results of the spill. Should the Contractor not take immediate action, the Owner will be entitled to take whatever actions are deemed necessary to stop, contain, and decontaminate a spill, at the Contractor’s expense. Costs incurred by the Contractor or Owner, including penalties imposed on the Owner as a result of any sewage spill caused by the Contractor, its employees, or subcontractors, shall be borne in full by the Contractor, including legal fees and other expenses to the Contractor or Owner resulting directly or indirectly from the spill.

7-23.4 Measurement

(October 29, 2010 Lacey)

No unit of measurement shall apply to the lump sum price for “Bypass Pumping”.

7-23.5 Payment

(October 29, 2010 Lacey)

Payment will be made in accordance with Section 1-04.1, for the following bid item that is included in the proposal. “Bypass Pumping”, lump sum. The unit contract price per lump sum for “Bypass Pumping” shall be full pay for all labor, materials, and equipment to furnish, place, assemble, install and operate the bypass pumping system complete in place, including pumps, piping, valves, control systems, generators, permits, testing, wyes, tees, special fittings, joint materials, operators and all other work to provide and operate a complete and operating bypass pumping system. Further, all labor, equipment, and materials required for decommissioning, disassembly and removal from the site shall be included.

Page 141: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-105

8-01 EROSION CONTROL AND WATER POLLUTION CONTROL

8-01.3 Construction Requirements

8-01.3(1) General

(January 5, 2015 WSDOT)

The first through eighth paragraphs of Section 8-01.3(1) are deleted and replaced with the following: The Contractor shall install a high visibility fence along the site preservation lines shown in the Plans or as instructed by the Engineer. Throughout the life of the project, the Contractor shall preserve and protect the delineated area, acting immediately to repair or restore any fencing damaged or removed. Controlling pollution, erosion, runoff, and related damage requires the Contractor to perform temporary Work items including but not limited to: 1. Providing ditches, berms, culverts, and other measures to control surface water. 2. Building dams, settling basins, energy dissipaters, and other measures, to control downstream flows. 3. Controlling underground water found during construction. 4. Covering or otherwise protecting slopes until permanent erosion-control measures are working. To the degree possible, the Contractor shall coordinate this temporary Work with permanent drainage and erosion control Work the Contract requires. All sediment control devices including, but not limited to, sediment ponds, perimeter silt fencing, or other sediment trapping BMPs shall be installed prior to any ground disturbing activity. Clearing, grubbing, excavation, borrow, or fill within the Right of Way shall never expose more erodible earth than as listed below:

Western Washington (West of the Cascade Mountain Crest)

Eastern Washington (East of the Cascade Mountain Crest)

May 1 through September 30

17 Acres April 1 through October 31

17 Acres

October 1 through April 30

5 Acres November 1 through March 31

5 Acres

8-01.3(1)A Submittals

(August 3, 2015 WSDOT)

Section 8-01.3(1)A is revised to read: A Temporary Erosion and Sediment Control (TESC) Plan consists of a narrative section and plan sheets that meets Ecology’s Stormwater Pollution Prevention Plan (SWPPP) requirement in the CSWGP. When the Contracting Agency has developed a TESC Plan for a Contract the narrative

Page 142: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-106

is included in the appendix to the Special Provisions and the TESC plan sheets are included in the Contract Plans. The Contracting Agency TESC plan will not include off-site areas used to directly support construction activity. The Contractor shall either adopt the TESC Plan in the Contract or develop a new TESC Plan. If the Contractor adopts the Contracting Agency TESC Plan the Contractor shall modify the TESC Plan to meet the Contractor’s schedule, method of construction, and to include off-site areas that will be used to directly support construction activity such as equipment staging yards, material storage areas, or borrow areas. Contractor TESC Plans shall include all high visibility fence delineation shown on the Contracting Agency Contract Plans. All TESC Plans shall meet the requirements of the current edition of the WSDOT Temporary Erosion and Sediment Control Manual M 3109 and be adapted as needed throughout construction based on site inspections and discharge samples to maintain compliance with the CSWGP. The Contractor shall develop a schedule for implementation of the TESC work and incorporate it into the Contractor’s progress schedule. The Contractor shall submit their TESC Plan (either the adopted plan or new plan) and implementation schedule as Type 2 Working Drawings. At the request of the Engineer updated TESC Plans shall be submitted as Type 1 Working Drawings.

8-01.3(1)B Erosion and Sediment Control (ESC) Lead

(January 5, 2015 WSDOT)

Supplement this section with the following: The ESC Lead shall implement the TESC Plan. Implementation shall include, but is not limited to: 1. Installing and maintaining all temporary erosion and sediment control Best Management Practices (BMPs) included in the TESC Plan to assure continued performance of their intended function. Damaged or inadequate TESC BMP’s shall be corrected immediately. 2. Updating the TESC Plan to reflect current field conditions. 3. Discharge sampling and submitting Discharge Monitoring Reports (DMRs) to Ecology in accordance with the CSWGP. 4. Develop and maintain the Site Log Book as defined in the CSWGP. As a part of the Site Log Book, the Contractor shall develop and maintain a BMP tracking table to show that identified TESC compliance issues are fully resolved within 10 calendar days. The table shall include the date an issue was identified, a description of how it was resolved, and the date the issue was fully resolved. The ESC Lead shall also inspect all areas disturbed by construction activities, all on-site erosion and sediment control BMP’s, and all stormwater discharge points at least once every calendar week and within 24-hours of runoff events in which stormwater discharges from the site. Inspections of temporarily stabilized, inactive sites may be reduced to once every calendar month. The Erosion and Sediment Control Inspection Form (WSDOT Form 220-030) shall be completed for each inspection and a copy shall be submitted to the Engineer no later than the end of the next working day following the inspection.

8-01.3(2) Seeding, Fertilizing and Mulching

(July 17, 2012 Lacey GSP)

Page 143: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-107

Supplement this section with the following: The Contractor shall provide water or irrigation to all seeded areas as often as conditions dictate depending on weather and soil conditions. Water will be provided as described in Section 2-07.

8-01.3(2)A Preparation For Application

(October 16, 2009 Lacey GSP)

Supplement this section with the following: All landscaped areas in the Plans shall be cultivated to the requirements in this section.

8-01.3(2)B Seeding And Fertilizing

(December 31, 2014 Lacey GSP)

Supplement this section with the following: Seed and fertilizer shall only be sown by Method 1 as approved by the Engineer. Seed shall be broadcast with approved hydraulic seeding equipment, in combination with wood cellulose fiber mulch, soil stabilizer and fertilizer distributed uniformly over designated areas. Half of seed shall be sown with sower moving in one direction, the other half with sower moving at right angles to first sowing. Hydroseeding operator shall remove all seed mulch in its entirety from adjoining paving, structures and plants.

8-01.3(2)D Mulching

(October 16, 2009 Lacey GSP)

Supplement this section with the following: Wood cellulose fiber mulch shall be applied at a rate of 2000 pounds per acre. Straw Mulch will not be permitted.

8-01.3(2)F Dates For Application Of Final Seed, Fertilizer, And Mulch

(December 31, 2014 Lacey GSP)

Delete the second paragraph of this section and replace with the following: Hydroseeding shall occur on all areas shown in the plans. Hydroseeding shall occur between August 15 and September 30 or between March 15 and May 15. In areas receiving automatic irrigation, hydroseeding may occur between May 15 and August 15. Actual planting shall be performed only when weather and soil conditions are suitable and in accordance with locally accepted practice and/or approved by the Engineer. Hydroseeding shall not be attempted when wind velocities would prevent uniform application or when winds would drift the material outside the areas to be seeded. Supplement this section with the following: The Contractor shall provide proposed mix proportions, submittals, seed certification, and certification of compliance of all materials used a minimum of 5 working days before seeding is to begin, for the Engineer’s written approval.

Page 144: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-108

8-01.3(9)A2 Silt Fence

(October 16, 2014 Lacey GSP)

Supplement this section with the following: If the Engineer determines that site conditions dictate additional silt fence throughout the duration of the project, the Contractor shall immediately install additional silt fence as directed by the Engineer.

8-01.3(9)D Inlet Protection

(July 17, 2012 Lacey GSP)

Delete the first paragraph and replace with the following: All catch basins and inlets within the project limits, downstream or affected by construction activities shall have inlet protection and as required by the Engineer. Inlet protection devices shall be installed prior to beginning clearing, grubbing, or earthwork activities.

8-01.3(15) Maintenance

(January 5, 2015 WSDOT)

The fifth paragraph of Section 8-01.3(15) is deleted.

8-01.3(16) Removal

(January 5, 2015 WSDOT)

The Contractor shall remove all temporary BMP’s and all associated hardware from the project limits prior to Physical Completion unless otherwise approved by the Engineer. At the request of the Contractor and at the sole discretion of the Engineer the CSWGP may be transferred back to the Contracting Agency. Approval of the Transfer of Coverage request will require the following: 1. All other Work required for Contract Completion has been completed. 2. All Work required for compliance with the CSWGP has been completed to the maximum extent possible. This includes removal of BMPs that are no longer needed and the site has undergone all Stabilization identified for meeting the requirements of Final Stabilization in the CSWGP. 3. An Equitable Adjustment change order for the cost of Work that has not been completed by the Contractor. 4. Submittal of the Washington State Department of Ecology Transfer of Coverage form (Ecology form ECY 020-87a) to the Engineer. If the Engineer approves the Transfer of Coverage back to the Contracting Agency the requirement in Section 1-07.5(3) for the Contractor’s submittal of the Notice of Termination form to Ecology will not apply.

8-01.4 Measurement

(April 30, 2015 Lacey GSP)

Page 145: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-109

Supplement this section with the following: All items required for erosion control shall be included in the lump sum bid item “Erosion/Water Pollution Control” unless a specific bid item is included in the proposal. Modify this section with the following: No specific unit of measure shall apply to the lump sum item “ESC Lead”

8-01.5 Payment

(******)

Modify this section with the following: The Contractor shall receive payment of 60 percent of the unit contract price, per acre, upon the completion of the initial hydroseeding. Payment shall be increased to 100 percent of the unit contract price, per acre, upon the point where the first mowing is required, as determined by the Engineer. All partial payments shall be limited to the actual area of weed free healthy vigorous growth. Partial payments shall not constitute acceptance of the area, nor shall the ownership or title transfer to the Contracting Agency. Areas found not acceptable at any stage shall be rejected and replaced at the Contractor’s expense. Previous partial payments made for areas rejected will be deducted from future payments due the Contractor. Delete “Erosion/Water Pollution Control”, by force account and add the following bid item: “Erosion/Water Pollution Control”, lump sum. The lump sum contract price for “Erosion/Water Pollution Control” shall be full compensation for all labor, material, and equipment necessary to implement, install, maintain and remove all erosion and water pollution control items including removal and disposal of sediment, stabilization and rehabilitation of soil disturbed by these activities, and any additional Work deemed necessary by the Engineer to control erosion and water pollution. The requirements for the ESC Lead shall also be included in this lump sum bid item if no bid item is included in the proposal. The Contractor shall bear full responsibility for erosion/water pollution control in all sources of material, disposal sites, and haul roads. “Erosion/Water Pollution Control” material consists of but shall not be limited to the following items: Silt Fencing High Visibility Silt Fencing Wattles Sand Bags Catch Basin Inserts Straw Bales Hydroseeding

8-05 LAWN AND LANDSCAPE RESTORATION (October 16, 2014 Lacey GSP)

Add the following new section:

Page 146: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-110

8-05.1 Description

The Contractor shall take every precaution to preserve and protect existing lawn and landscape areas. Only those landscaped areas necessary for construction shall be disturbed. All lawn areas and landscaping damaged or removed shall be repaired as directed by the Engineer. Lawn areas damaged or removed shall be restored with sod as directed by the Engineer.

8-05.3 Construction Requirements

The Contractor shall repair any vegetation, fencing, culverts, ditch sections, or any other objects or structures that are not covered by a specific bid item. Restoration shall return anything damaged by construction to their original condition or to a condition superior to the original condition. The Contractor shall be responsible to evaluate the site prior to bidding this project to determine the areas to be affected by the particular construction method or machinery proposed to be used.

8-05.4 Measurement

No unit of measure shall apply to the lump sum price for Lawn and Landscape Restoration.

8-05.5 Payment

“Lawn and Landscape Restoration”, lump sum. The lump sum contract price for “Lawn and Landscape Restoration” shall be full pay for all labor, materials, and equipment to restore the project site to condition equal to, or superior to the original condition. If no bid item for “Lawn and Landscape Restoration” is included, any work described in this section shall be incidental to the project.

8-14 CEMENT CONCRETE SIDEWALKS

8-14.1 Description

(March 31, 2015 Lacey)

Supplement this section with the following: Where applicable in this section “concrete sidewalks” shall read “concrete sidewalks and driveways” unless a bid item is provided. Depth shall be as shown in the Plans. The minimum driveway depth shall be 6 inches. The Contractor shall match color, texture, and material of existing sidewalks and driveways. All ADA requirements will be strictly enforced including ramps and slopes as shown in the plans. Sidewalk and Bus Pads shall not exceed 2% cross slope.

8-14.4 Measurement

(April 2, 2018 Lacey)

Supplement this section with the following: Cement concrete sidewalks shall be measured by the square yard of finished surface outside of the ramp pay limits and will not include the surface area of the curb ramps (i.e. the sidewalk

Page 147: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-111

quantities indicated on the Plans are for informational purposes only and include the ramp area). Cement Concrete sidewalks shall include cement concrete bike ramps, and bus pads.

8-14.5 Payment

(April 2, 2018 Lacey)

Supplement this section with the following: The unit contract price for “Cement Conc. Sidewalk” per square yard shall be full pay for furnishing all materials, equipment, and labor to construct the sidewalk, and bus pads complete in-place, to include forms, and concrete. Further, the Contractor shall make all excavations including haul and disposal, regardless of depth required, for constructing the sidewalk to the lines and grades shown, and shall include all costs associated with maintaining pedestrian access through the construction area with crushed surfacing top course or other material as approved by the Engineer.

8-50 MISCELLANEOUS Add the following new sections:

8-50.1 BOLLARDS

(******)

Description

This work shall consist of furnishing and installing steel bollards in accordance with the Plans, Standard Plans, and these Specifications, at the locations shown in the Plans or as staked by the Engineer.

Materials

Posts and Hardware Bollard posts shall be ASTM A 53, NPS 6 (6” Nom.) schedule 80 steel pipe. Steel plate shall be per ASTM A 36. All steel parts shall be hot-dip galvanized after fabrication in accordance with AASHTO M 111. Reflective Tape Reflective tape shall be one of the following or an approved equal: Scotchlite High Intensity Grade Series 2870 Reflexite AP-1000 Scotchlite Diamond Grade LDP Series 3970 T-6500 High Intensity (Type IV) Concrete Footings shall be constructed using concrete. Min. 4000 PSI.

Construction Requirements

Page 148: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-112

Bollards shall be constructed in accordance with the Standard Plans. Bollard footing surfaces shall slope away from the bollard to meet pavement grade. The footing shall follow the dimensions and details of the square footing and the surface shall have a smooth trowel finish. Bollards shall not vary more than 1/2 inch in 30 inches from a vertical plane. Bollard posts and the exposed parts of the base assembly shall be painted in accordance with Section 6-07.3(11) for galvanized surfaces. The top coat shall match Federal Standard 595, Color No. 33538 Traffic Signal Yellow.

Measurement

Measurement for bollards will be by the unit for each type of bollard furnished and installed.

Payment

Payment will be made in accordance with Section 1-04.1, for the following bid items: The unit contract price per each for “Bollard” shall be full pay for all labor, materials, and equipment required to install a bollard including foundation excavation, concrete footing, finishing, rebar, steel pipe and plate, paint, and other items required to install a bollard complete in-place.

8-50.2 PROJECT CLOSEOUT

(April 2, 2018 Lacey)

Description

This work shall consist of completing all miscellaneous items of work in accordance with the Plans and these Specifications that are required to achieve Completion and Final Acceptance, as identified by the Engineer and the Contracting Agency. This work may include but is not limited to punch list items, record drawings, O&M Manuals, training, material acceptance documents, copies of the approved “Affidavit of Prevailing Wages Paid” for the Contractor and all Subcontractors, and any other work required in these Plans and Specifications that has not been completed.

Measurement

No unit of measurement shall apply to the lump sum price for “Project Closeout”.

Payment

“Project Closeout”, lump sum. The unit contract price per lump sum for “Project Closeout” includes all compensation for all costs of completing the miscellaneous items of work identified by the Contracting Agency prior to final acceptance of the Project. A fixed lump sum price has been included in the Proposal for this work. Any additional costs anticipated or incurred by the Contractor for the work shall be included in the various lump sum and unit price bid items as found in the Proposal. Neither partial payment, nor additional compensation shall be allowed.

Page 149: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-113

9-03 AGGREGATES Add the following new Section:

9-03.16 Imported Pipe Bedding

(April 30, 2015 Lacey)

Bedding material for pressure mains and services shall be clean sand/gravel mixture free from organic matter and conforming to the following gradation:

Sieve Size Percent Passing 3/4” square 100 3/8” square 70-100 U.S. No. 4 55-100 U.S. No. 10 35-95 U.S. No. 20 20-80 U.S. No. 40 10-55 U.S. No. 100 0-10 U.S. No. 200 0-3

Bedding material for gravity mains and stubs/or laterals shall be clean sand/gravel mixture free from organic matter and conforming to the following gradation:

Sieve Size Percent Passing 3/8” square 85-100 U.S. No. 4 10-30 U.S. No. 8 0-10 U.S. No. 16 0-5

All percentages are by weight

9-03.21 Recycled Materials

(April 30, 2015 Lacey)

Section 9-03.21 is supplemented with the following: Recycled materials will not be used unless approved by the Engineer.

9-04 JOINT AND CRACK SEALING MATERIALS (January 7, 2019 WSDOT 9-04.AP9)

This section’s title is revised to read: Joint Sealing Materials

9-04.1(2) Premolded Joint Filler for Expansion Joints

In this section, each reference to “AASHTO T 42” is revised to read “ASTM D 545”.

Page 150: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-114

9-14 EROSION CONTROL AND ROADSIDE PLANTING

9-14.1(1) Topsoil Type A

(October 16, 2009 Lacey)

Supplement this section with the following: Topsoil Type A shall be composed of a three way winter mix consisting of 2 parts soil, 2 parts compost, 3 parts sand. Soil shall be classified as gravelly sand, well-graded sand, poorly graded sand, or silty sand. Compost shall be a weed free well decomposed, humus-like material derived from the decomposition of grass clippings, leaves, branches, wood, and other organic materials. Compost shall be produced at a permitted solid waste composting facility. Composts containing shavings, cedar sawdust, or straw will not be permitted. Sand shall consist of 100 percent passing the 3/8 inch sieve, minimum 95 percent passing the #4 sieve, and maximum of 5 percent passing the #100 sieve. Topsoil shall meet the following requirements: Screen Size (approximate particle size) 5/8” maximum Maturity measure (C:N ratio) 30:1 Total Nitrogen 0.5% minimum PH range 5.5-8.0 Foreign matter by dry weight 1% maximum The Contractor shall provide a sample of the topsoil and a laboratory analysis with recommendations from the laboratory for desired additives for the Engineers approval. The Contractor shall incorporate any additives recommended by the laboratory.

9-14.2 Seed

(October 16, 2016 Lacey)

Supplement this section with the following: There shall be several types of mixes used on this project. The list of approved seed varieties are specifically identified in the table. If multiple varieties are permitted, the approved seed type is list below. They shall be applied at the given rates. Source identified seed shall be fourth generation or earlier. Non-Source Identified seed shall meet or exceed Washington State Department of Agriculture Certified Seed Standards. Seeds shall be certified “Weed Free”, indicating there are no noxious or nuisance weeds in the seed. Lawn Mix - shall be applied at 200 pounds per acre and the maximum weed seed shall be no more than 0.5%. Grass seed of the following composition, proportion, and quality shall be applied as follows:

Kind and Variety of Seed Percent By Weight

Minimum Pure Seed

Minimum Germination

Equal Mix 3-Perennial Ryegrasses 60% 98% 90%

One Chewing Fine Fescue 20% 98% 90%

Page 151: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

D-115

One Creeping Red Fescue 20% 98% 90%

Woody Mix - shall be applied at 100 lbs per acre. Seed of the following percentage by weight shall be applied:

Botanical Name Common Name Percent By Weight

Arctostaphylos uva-ursi Bearberry 20% Eschscholzia californica California Poppy 5% Gaultheria shallon Salal 15% Mahonia aquifolium Oregon Grape 20% Trifolium fragiferum Strawberry Clover 15% Trifolium Repens White Clover 15% Trifolium incarnatum Crimson Clover 10%

Approved Seed Type: Perennial Ryegrasses Hawkeye Catalina II Gator 3 Kokomo Admire All Star 2 Applaud Mach 1 SR 4420 Amazing Repell III SR 4220 Brightstar SLT Pentium Grand Slam Pennant II Manhattan 4 Brightstar II Cathedral II Charger II Elfkin Inspire Line Drive Pinnacle II Pizzazz Promise Seville II Terradyne

Creeping Red Salsa Cindy Jasper Salem Flyer

Chewing Tiffany Shadow II Treazure E Longfellow Weekend Tamara Enjoy Victory Bridgeport Shadow W/Endo Proformer Southport Bargreen Jamestown II

Tall Fescue Shenandoah Guardian Trailblazer Olympic Apache Jaguar Adventure Avanti Bonanza Finelawn Arid Rebel

Page 152: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 153: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

E TECHNICAL

SPECIFICATIONS

Page 154: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 155: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

Table of Contents

i

Division 1 General ...........................................................................................................................1-1

1.10 General ........................................................................................................................................... 1-1

1.50 Construction Support ..................................................................................................................... 1-1

1.51 Temporary Bypass Pumping Systems ........................................................................................ 1-1

1.70 Execution and Closeout ................................................................................................................. 1-6

1.75 Testing, Startup, and Operation ................................................................................................. 1-6

1.75.01 Schedule ................................................................................................................................ 1-6

1.75.02 Testing ................................................................................................................................... 1-6

1.75.03 Scheduling of Owner Review for Testing .............................................................................. 1-7

1.75.06 Electrical and Control Systems Testing ................................................................................. 1-8

1.75.30 Startup .................................................................................................................................. 1-8

1.79 Training and Documentation ..................................................................................................... 1-8

1.79.1 Training ................................................................................................................................... 1-8

1.79.2 Operation and Maintenance Manuals .................................................................................... 1-9

1.79.3 Construction Record Drawings ............................................................................................. 1-10

Division 16 Electrical ..................................................................................................................... 16-1

16.00 General ....................................................................................................................................... 16-1

16.05 Common Work for Electrical .................................................................................................. 16-1

16.10 Electrical Site Work .................................................................................................................... 16-6

16.10.1 Common Work for Electrical Site Work .............................................................................. 16-6

16.10.2 Underground Marking Tape (Detectable Type) .................................................................. 16-7

16.15 Electrical Grounding ................................................................................................................... 16-8

16.15.1 Common Work for Electrical Grounding ............................................................................. 16-8

16.20 Utility Service ............................................................................................................................. 16-9

16.21.2 Electrical Utility Meter Enclosure ....................................................................................... 16-9

16.21.4 Circuit Breaker Service Disconnect Switch ........................................................................ 16-10

16.55 Switches and Protective Devices ............................................................................................. 16-10

16.55.1 Common Work for Switches and Protective Devices ....................................................... 16-10

16.55.16 Molded Case Circuit Breakers ......................................................................................... 16-11

16.60 Conductors ............................................................................................................................... 16-11

16.61 Low Voltage Wire and Cable ................................................................................................ 16-11

16.70 Raceways, Boxes and Fittings .................................................................................................. 16-13

Page 156: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

Table of Contents

ii

16.71 Raceways .............................................................................................................................. 16-13

16.90 Power Generation .................................................................................................................... 16-15

16.91 Engine Generator ................................................................................................................. 16-15

16.91.2 Diesel Engine Generator Set ............................................................................................. 16-15

16.92 Transfer Switches ................................................................................................................. 16-29

16.92.2 Automatic Transfer Switch ................................................................................................ 16-29

16.95 Testing ...................................................................................................................................... 16-31

16.95.1 Common Work for Testing ................................................................................................ 16-31

16.95.3 Conductor Test Report ...................................................................................................... 16-33

16.95.4 Ground Electrode Resistance Test Report ........................................................................ 16-34

Page 157: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

E 1-1

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

Division 1 General

1.10 GENERAL

Sections in these specifications titled “Common Work for . . .” shall apply to all following subsections whether directly referenced or not.

Sections in these specifications titled “Related Sections” shall be read as integral to the specification as if they were fully detailed within. All work and materials described in such sections shall be provided and performed by the Contractor.

1.50 CONSTRUCTION SUPPORT

1.51 Temporary Bypass Pumping Systems

Part 1 - General

Scope

Under this item the Contractor is required to furnish all materials, labor, equipment, power, maintenance, etc. to implement a temporary pumping system at each lift station for the purpose of diverting the existing wastewater flows around the work area for the required duration of the temporary shutdown.

The design, installation and operation of the temporary pumping system shall be the Contractor's responsibility. Employ the services of a vendor who can demonstrate to the Engineer that he specializes in the design and operation of temporary bypass pumping systems. The vendor shall provide at least five (5) references of projects of a similar size and complexity as this project performed by his firm within the past three years. The bypass system shall meet the requirements of all codes and regulatory agencies having legal jurisdiction.

Site Summary

The following supplemental information is provided to assist the Contractor but does not remove responsibility from the Contractor to review each site and reach a determination for how to size and implement bypass pumping to satisfy the requirements of this specification.

Lift Station 4

There is an existing 4-inch bypass discharge port available on site. The bypass pumps will need to be sized to pump approximately 100 GPM at 40-feet TDH. This site is critical as the wetwell cannot backup into the main without flooding basements in the area.

Lift Station 5

There is an existing 4-inch bypass discharge port available on site. The bypass pumps will need to be sized to pump approximately 100 GPM at 45-feet TDH.

Lift Station 8

There are no existing bypass ports available on site. It is approximated that the bypass pumps will need to be sized to pump 7,000 GPD. If the Contractor chooses to pump into a truck, they must coordinate with the Engineer on where to dispose the wastewater back into the collection system.

Page 158: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-2

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

Lift Station 11

There are no existing bypass ports available on site. The bypass pumps will need to be sized to pump approximately 3,500 GPD. If the Contractor chooses to pump into a truck, they must coordinate with the Engineer on where to dispose the wastewater back into the collection system.

Lift Station 17

There are existing bypass suction and discharge ports available on site. The Contractor shall provide the appropriate fittings to utilize the ports. The bypass pumps will need to be sized to pump approximately 100 GPM at 125-feet TDH.

Lift Station 24

There are no existing bypass ports available on site. The bypass pumps will need to be sized to pump approximately 5,500 GPD. The contractor may suction out liquids from the wetwell and coordinate with the Engineer on where to dispose the wastewater back into the collection system. The contractor may not suction out solids without first coordinating with LOTT Engineer.

Lift Station 27

There are no existing bypass ports available on site. The bypass pumps will need to be sized to pump approximately 2,500 GPD. The contractor may suction out liquids from the wetwell and coordinate with the Engineer on where to dispose the wastewater back into the collection system. The contractor may not suction out solids without first coordinating with LOTT Engineer.

Submittal

Prepare with the vendor a specific, detailed description of the proposed pumping system and submit it and the vendor's references for the Engineer’s review. The submittal should include detailed plans and descriptions outlining all provisions and precautions to be taken by the Contractor regarding the handling of existing wastewater flows. This plan must be specific and complete, including such items as schedules, locations, elevations, capacities of equipment, materials and all other incidental items necessary and/or required to insure proper protection of the facilities, including protection of the access, traffic control and bypass pumping locations. No construction shall begin until all provisions and requirements have been approved by the Owner.

The plan shall include but not be limited to details of the following: 1. Staging area for pumps. 2. Sewer plugging method and types of plugs. 3. Number, size, material, location and method of installation of suction piping. 4. Number, size, material, method of installation and location of installation

of discharge piping. 5. Bypass pump sizes, capacity, number of each size to be on site and power

requirements. 6. Bypass pumping to have full redundancy.

Page 159: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-3

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

7. Calculations of static lift, friction losses, and flow velocity (pump curves showing pump operating range shall be submitted).

8. Standby power generator size, location. 9. Downstream discharge plan. Indicate connection type and discharge location

in existing valve vault. 10. Method of protecting structures from erosion and damage. 11. Thrust and restraint block sizes and locations. 12. Sections showing suction and discharge pipe depth, embedment, select fill and

special backfill. 13. Method of noise control for each pump and/or generator. 14. Any temporary pipe supports and anchoring required. 15. Design plans and computation for access to bypass pumping locations

indicated on the drawings. 16. Calculations for selection of bypass pumping pipe size. 17. Schedule for installation of and maintenance of bypass pumping lines. 18. Plan indicating selection location of bypass pumping line locations. 19. Plan indicating power supply from the local power company if required. All

costs shall be included within the bid item. 20. Traffic Control Plan during bypass pumping. 21. List of spare parts and support equipment to be maintained on site. 22. Secondary containment type and size, and plan for deployment. 23. Methods for monitoring and assuring equipment is operating per plan. 24. Alarm response plan which shall include contacting City of Lacey. 25. Contingency plan for spill, leak or other discharge.

Part 2 - Products

Equipment

All pumps used shall be fully automatic self-priming units that do not require the use of foot-valves or vacuum pumps in the priming system. The pumps may be electric or diesel powered. All pumps used must be constructed to allow dry running for long periods of time to accommodate the cyclical nature of effluent flows. All pumps must be constructed with acoustical enclosures that shall reduce pump and engine noise to 69 dBa or less at a distance of 30 FT. The pumps shall be contained inside a temporary portable secondary containment structure(s) to contain any fuel or sewage that may spill during the normal course of operation. Pumps shall be capable of pumping solids with a nominal spherical dimensions of three (3) inches without clogging.

Provide the necessary stop/start controls for each pump.

Noise levels of equipment shall meet Washington State noise level requirements. Make the necessary provisions to control the noise of the temporary pumping equipment such that the noise generated by the equipment is limited to 55dBA during the day (7 a.m. to 10 p.m.) and 45 dBA at night (10 p.m. to 7 a.m.) at property lines. Sound attenuating enclosures may be required to meet provisions and measures.

Include an autodialer with a list of minimum three (3) names and numbers in case of an emergency during the bypass pumping phase.

Page 160: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-4

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

Include one stand-by pump of each size to be maintained on site. Back-up pumps shall be on-line, isolated from the primary system by an automatic valve. Also man the bypass pumping equipment 24 hours a day, during construction procedures.

Discharge Piping - In order to prevent the accidental spillage of flows, all discharge systems shall be temporarily constructed of rigid pipe with positive, restrained joints. Under no circumstances will aluminum "irrigation" type piping or glued PVC pipe be allowed. Discharge hose will only be allowed in short sections and by specific permission from the Engineer.

General Description

Design Requirements:

1. Verify the flow conditions with the City. Provide all pipeline plugs, pumps of adequate size to handle flows, and temporary discharge piping to ensure that the total flow can be safely diverted around the section to be repaired or constructed.

2. Have adequate standby pumping equipment online and ready for immediate operation and use in the event of an emergency or breakdown. One standby pump for each size pump utilized shall be installed at each bypass location, ready for seamless backup in the event of primary pump failure. Standby equipment shall provide full redundancy for the pumping system.

3. Bypass pumping system shall be capable of bypassing the flow around the work area as necessary for satisfactory performances of work.

4. Bypass pumping shall continue 24 hours per day until the installation of the new

generators is complete and all appurtenances have been installed per contract plans, and the facility is tested and ready to be put back online.

Part 3 - Execution

Scheduled power outages requiring bypass pumping shall only occur Monday through Thursday unless otherwise approved by the Engineer.

Field Quality Control and Maintenance

Test:

1. Perform leakage and pressure tests of the bypass pumping discharge and suction piping using clean water prior to actual operation. The Engineer will be given 3 working days notice prior to testing.

Inspection:

1. Inspect bypass pumping system on a continuous basis to ensure that the system is working correctly. Contractor shall monitor pump power source fuel levels and make arrangements for timely refueling as needed.

Maintenance Service:

1. Insure that the temporary pumping system is properly maintained, and a responsible operator shall be on hand at all times when pumps are operating.

Extra Materials:

Page 161: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-5

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

1. Spare parts for pumps and piping shall be kept on site as required. 2. Adequate hoisting equipment for each pump and accessories shall be maintained on

the site.

Preparation

Precautions:

1. Contractor is responsible for locating any existing utilities in the area the Contractor selects to locate the bypass pipelines. Locate his bypass pipelines to minimize any disturbance to existing utilities and shall obtain approval of the pipeline locations from the City and the Engineer. All costs associated with relocating utilities and obtaining all approvals shall be paid by the Contractor.

2. During all bypass pumping operations, protect the facility structures and all wastewater lines from damage inflicted by any equipment. Be responsible for all physical damage caused by bypass operations that are caused by human or mechanical failure. Contractor to have personnel to monitor bypass pumping on a continuous basis.

Spills

Spills:

1. The contractor is fully responsible for any damage that may result from an inadequate or improper installation, maintenance or operation, or failure of any kind of the sewer bypass pumping system.

2. In the event of a spill the Contractor will contact the LOTT Spill Reporting Group at (360) 528-5700 and notify the City and Engineer immediately.

Installation and Removal

1. Plugging or blocking of wastewater flows shall incorporate primary and secondary plugging device. When plugging or blocking is no longer needed for performance and acceptance or work, it is to be removed in a manner that permits the wastewater flow to slowly return to normal without surge, to prevent surcharging or causing other major disturbances downstream.

2. When working inside manhole or force main, exercise caution and comply with OSHA requirements when working in the presence of sewer gases, combustible oxygen-deficient atmospheres, and confined spaces. Employ Contractor’s own safety program.

3. The bypass pipelines must be located out of roadways. Upon completion of the bypass pumping operations, and after the receipt of written permission from the Engineer, remove all the piping, restore all property to pre-construction condition and restore all pavement and facilities.

Page 162: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-6

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

1.70 EXECUTION AND CLOSEOUT

1.75 Testing, Startup, and Operation

1.75.01 Schedule

The placing of all improvements in service shall consist of three parts: “testing”, “startup”, and “operation”. Not less than 30 calendar days before the anticipated time for beginning testing, the Contractor shall notify and submit to the Owner for approval, a complete plan for the following:

1. Schedules for tests:

A. Emergency power system

2. Detail schedule of procedures for startup.

3. Complete schedule of events to be accomplished during testing.

4. An outline of work remaining under the contract that will be carried out concurrently with the operation phases.

Failure to provide proper notification to the Owner may lead to liquidated damages if schedule cannot be maintained. If rescheduling is required because components are not ready for testing the notification requirements are reset and shall provide for 21 calendar days advance notice in order to reserve Engineer’s and/or Owner Representatives’ time.

1.75.02 Testing

The Contractor may periodically request preliminary testing for items that must be covered or tested before other work can proceed. In these cases, the work shall not be tested or covered up without timely notice to the Owner of its readiness for testing. Should any work be covered up without notice, approval, or consent, it must, if required by the Owner, be uncovered for examination at the Contractor’s expense. Where work is to be tested, all necessary equipment shall be set up and the work given a preliminary test so that any and all defects may be discovered and repaired prior to calling out the Owner for the test.

Final testing shall consist of individual tests and checks made on equipment intended to provide proof of performance of unit and proper operation of unit control together with necessary tests to show system operation in the presence of the Owner. Assure proper alignment, size, condition, capability, strength, proper adjustment, lubrication, pressure, hydraulic test, leakage test, and all other tests deemed necessary by the Owner to determine that all materials and equipment are of specified quality, properly situated, anchored, and in all respects, ready for use. Any certificates required by these specifications by the manufacturer’s representatives shall be supplied to the Owner prior to startup.

All piping shall be tested as required by specifications and applicable codes. Tests on individual items of equipment, such as pipelines, structures, controls, and other items shall be as necessary to show proper system operation. During testing, the Contractor shall correct any defective work discovered. Startup shall not begin until all tests required by these specifications have been completed and approved by the Owner.

Page 163: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-7

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

Not less than five working days before the anticipated time for beginning the testing, the Contractor shall provide a list of representatives that will be attending the testing. The Owner may request additional representatives at no additional cost if said representatives are identified in these specifications.

Qualified product representatives to be on site for the following equipment, at a minimum:

• Standby Generators

• Automatic Transfer Switches

Additional representatives required may be identified elsewhere in these specifications.

The Contractor shall conduct all testing and startup. Testing and startup shall not be a cause for claims for delay by the Contractor and all expenses for testing and startup shall be incidental to this contract. The Contractor shall make arrangements for all materials, supplies, and labor necessary to efficiently complete the testing, startup, and operation. At a minimum, the Contractor shall provide:

• Voltmeter

• Amp meter.

• Load Bank (generator testing)

• Sound Level (dB) measuring device (generator testing)

1.75.03 Scheduling of Owner Review for Testing

See Division 1.75.01 Schedule for scheduling and notification requirements.

In addition, the Contractor shall provide further notification two working days and two working hours (to confirm schedule) of the scheduled test to the Owner confirming that the Contractor has successfully completed all preliminary testing and that all equipment, tools, materials, labor, subcontractors, manufacturer’s representatives, and all other items required for witnessed testing are available and fully functional. Failure to provide advance notification and confirmation, or meet any of the testing requirements shall constitute a failed test in accordance with the section Inspection and Tests of the General Conditions.

A detailed testing schedule shall be provided by the Contractor and updated as needed to be at least 48 hours ahead of actual testing at the project site. If testing requires downtime in order to perform repairs due to failed test, the Contractor shall pay the Owner in the amount of $200 per hour per Owner Representative on site (minimum of $400 per scheduled visit) for downtime lasting longer than 1 hour required to complete repairs to verify the complete construction is ready for startup and operation. This amount will be deducted from the appropriate bid item that relates to the finished construction and documented by the Owner at their discretion. The Contractor is required to have all systems pre-tested to their satisfaction prior to calling the Owner for formal testing.

Page 164: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-8

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

1.75.06 Electrical and Control Systems Testing

See Division 16.95 for electrical system testing.

The following is a list of components that shall be tested prior to project completion. This list is intended as a general guide and is not necessarily complete:

• Standby generator operations, status, and alarms

• Automatic transfer switch operations, status, and alarms

• Local control

• Automatic control

1.75.30 Startup

Startup shall consist of a simulated operation of all equipment and controls. The purpose of startup shall be to check that all equipment will function under operating conditions, that all interlocking controls and sequences are properly set, and that the facility will function as an operating unit.

Technically qualified factory representatives shall be present for the startup phase. All Representatives shall be trained, qualified, and have experience in troubleshooting and fixing field issues. The startup shall continue until it is demonstrated that all functions, controls, and machinery are functioning correctly.

Authorized factory representatives shall be provided for the following items:

• Standby generators

• Automatic transfer switches

1.79 Training and Documentation

Failure to provide acceptable final documentation including O&M manuals and as-built drawings will result in non-payment of the appropriate bid item in the schedule of prices.

The Contractor shall remove all tags and instructions that come packaged with or attached to equipment used on the project. Deliver all such documents to the Owner bound in a three-ring binder or with the Operation and Maintenance Manual. Insert documents in sleeves if they cannot be punched. Scan all such documents to Adobe PDF format and provide with the Operation and Maintenance Manual.

1.79.1 Training

At the time that the facility is ready to be put into operation, the Contractor is to conduct an operation and maintenance training meeting with the owner to explain in detail the operation and maintenance requirements of each of the facility’s components. The training meeting shall not occur on the same date(s) as a startup.

Operation of the facility shall commence immediately after completion of testing, startup, and owner training and after satisfactory repairs and adjustments have been made.

Page 165: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-9

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

1.79.2 Operation and Maintenance Manuals

Detailed requirements for specific equipment and systems may also be included in their respective specification sections.

Prior to the receipt of payment for more than 90 percent of the work, the Contractor shall deliver to the Owner acceptable manufacturer’s operating and maintenance instructions covering equipment and systems installed on the Project requiring operational and/or maintenance procedures and for any additional items indicated by the Owner, including coatings furnished under this contract.

At a minimum, provide O&M information for the following:

• Generators

• Transfer switch

• Electrical systems

The operating and maintenance instructions shall include, as a minimum, the following data for each coating and item of mechanical and electrical equipment:

Products

A. Equipment Identification including brand name, model number and serial numbers.

B. Date of manufacture and date of installation on job site.

C. Complete as-built elementary wiring and one-line diagrams.

D. Complete parts list, by generic title and identification number, complete with exploded views of each assembly.

Maintenance

A. Recommended spare parts.

B. Lubrication schedule including the applicable lubricant designation available from the Standard Oil Company of California.

C. Recommended preventive maintenance procedures and schedules. Schedule shall be provided for daily, weekly, monthly, quarterly, semi-annually and annually maintenance.

D. Disassembly and re-assembly instructions including parts identification and a complete parts breakdown for all equipment.

E. Weights of individual components of each item of equipment weighing over 50 pounds.

F. Name, location, and telephone number of the nearest suppliers and spare parts warehouses.

G. All manufacturers’ warranties. Include name, address, and telephone number of the manufacturer’s representative to be contacted for warranty, parts, or service information.

Page 166: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-10

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

H. Cleaning, repair, and maintenance instructions for each coating system.

I. Provide videotapes, video CDs or DVDs utilized in the manufacturer’s instruction program for the owner.

Operation

A. Recommended trouble-shooting and startup procedures.

B. Recommended step-by-step operating procedures.

C. Emergency operation modes, if applicable.

D. Normal shutdown procedures.

E. Long term shutdown (mothballing) procedures.

F. Equipment specifications and guaranteed performance data.

G. General manuals which describe several items not in the contract will not be accepted unless all references to irrelevant equipment are neatly eradicated or blocked out.

Provide 3 hard copies of O&M manuals for each site. The O&M manuals shall be customized for each lift station site, with each site being a separate binder. A duplicate CD copy of the binder must be provided but shall not substitute a hard copy unless approved by the Owner.

Each set of instructions shall be bound into multiple volumes; each volume to be complete with an index and bound in a suitable, hard-covered binder. Binders shall be of hardback construction with full-length metal hinge. Capacity shall be 3-inch to 5-inch as appropriate for the quantity of O&M documentation. More than one binder may be required for large projects. Binders shall be equal to Wilson-Jones WLJ344 series or WLJ369 series or Specialty Loose Leaf models 87784, 98085, 98086, or 98984.

Manuals shall be assembled and indexed so that information on each coating and piece of equipment can be readily found.

Progress payments for the total contract work in excess of 90 percent completion may not be made until the operation and maintenance manual has been delivered and approved by the Owner, at their discretion.

The Contractor shall secure and deliver to the Owner all equipment warranties and other warranties and guarantees required for all equipment and processes. Delivery shall be done at one time covering all major and minor equipment warranties. Copies of the warranties shall be included in each O & M Manual.

1.79.3 Construction Record Drawings

Prior to receiving final payment for the work, the Contractor shall deliver a complete set of acceptable “As-Constructed” records to the Engineer. Plans shall be made on clean, unmarked prints for this project in accordance with the following standards:

• Yellow markings or highlights = deleted items

• Red markings = new or modified items

Page 167: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 1 – General

E 1-11

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\1 General.docx 4/16/2019 4:55 PM © 2019 RH2 Engineering, Inc.

The Contractor shall provide “as-built” information on all items and work shown on the plans showing details of the finished product including dimensions, locations, outlines, changes, manufacturers, etc. The information must be in sufficient detail to allow the Owner’s personnel to locate, maintain, and operate the finished product and its various components.

See also electrical plan requirements in Division 16.05.

Page 168: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 169: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

E 16-1

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Division 16 Electrical

16.00 GENERAL

The Contractor shall provide all labor, material, tools, equipment and services required to complete the furnishing, installation, wiring, connection, calibration, adjustment, testing and operation of all electrical equipment, devices and components as indicated and implied by the plans and specifications.

Sections in these specifications titled “Common Work for . . .” shall apply to all following sections whether directly referenced or not.

16.05 Common Work for Electrical

Part 1 - General

Summary

Plans are diagrammatic and indicate general arrangements of systems and equipment, except when specifically, dimensioned or detailed. The intention of the plans is to show size, capacity, approximated location, direction and general relationship of one work phase to another, but not exact detail or arrangement.

Permits and Fees

The Contractor shall coordinate and provide all permits, licenses, approvals, inspections by the authority having jurisdiction and other arrangements for work on this project and all fees shall be paid for by the Contractor. The Contractor shall include these fees in the bid price.

Codes and Standards

Provide all electrical work in accordance with latest edition of National Electrical Code, National Electrical Safety Code, Washington State Electrical Code, and local ordinances. If any conflict occurs between government adopted code rules and these specifications, the codes are to govern. All electrical products shall bear a label from a certified testing laboratory recognized by the State of Washington. Recognized labels in the State of Washington are UL, ETL, and CSA-US.

Definitions

Dry Locations: All those indoor areas which do not fall within the definitions below for wet, damp, or corrosive locations and which are not otherwise designated on the Plans.

Wet Locations: All locations exposed to the weather, whether under a roof or not, unless otherwise designated on the Plans.

Damp Locations: All spaces wholly or partially underground, or having a wall or ceiling forming part of a channel or tank unless otherwise designated on the Plans.

The words “plans” and “drawings” are used interchangeably in this specification and in all cases shall be interpreted to mean “Plans”.

The word “provide” shall be interpreted to mean furnish and install.

Page 170: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-2

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Submittals

Provide submittals of each item specified in this division to engineer for approval in accordance with the submittals’ sections of these specifications. Submittals for motor control centers, motor control panels, control panels, instrumentation panels, and pump control panels shall include as a minimum a wiring diagram or connection schematic and an interconnection diagram.

Wiring Diagram or Connection Schematic

1. This plan or plans shall include all of the devices in a system and show their physical relationship to each other including terminals and interconnecting wiring in assembly. This diagram shall be in a form showing interconnecting wiring only by terminal designations (wireless diagram).

Interconnection Diagram

1. This diagram shall show all external connections between terminals of equipment and outside points, such as motors and auxiliary devices. References shall be shown to all connection diagrams which interface to the interconnection diagrams. Interconnection diagrams shall be of the continuous line type. Bundled wires shall be shown on a single line with the direction of entry/exit of the individual wires clearly shown. All devices and equipment shall be identified. Terminal blocks shall be shown as actually installed and identified in the equipment complete with individual terminal identification. All jumpers, shielding and grounding termination details not shown on the equipment connection diagrams shall be shown on the interconnection diagrams. Spare wires and cables shall be shown.

Submittal information shall be provided to the Owner for the following items:

1. Utility Meter Enclosure

2. Service Disconnect

3. Circuit Breakers

4. Conduit and Fittings

5. Electrical Handholes and Vaults

6. Wire and Cables

7. Automatic Transfer Switches

8. Engine Generator Sets

9. Other Electrical Components listed in this division and/or required by the Engineer.

Project Conditions

Contractor shall keep all power shutdown periods to a minimum. Carry out shutdowns only after a shutdown schedule has been submitted and approved by both the Owner and the Engineer.

Page 171: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-3

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Part 2 - Products

Source Quality Control

Provide adequate space and fit for the electrical installation, including, but not limited to, determination of access-ways and doorways, shipping sections, wall and floor space, and space occupied by mechanical equipment. Provide electrical equipment that fits in the areas shown on the plans. All equipment shall be readily accessible for maintenance, shall have electrical clearances in accordance with NEC and shall be installed in locations which will provide adequate cooling.

Do not use equipment exceeding dimensions indicated or equipment or arrangements that reduce required clearances or exceed specified maximum dimensions unless approved by the Engineer.

Identification of Listed Products

Electrical equipment and materials shall be listed for the purpose for which they are to be used, by an independent testing laboratory. When a product is not available with a testing laboratory listing for the purpose for which it is to serve, the inspection authority may require the product to undergo a special inspection at the manufacturer’s place of assembly. All costs and expenses incurred for such inspections shall be included in the original contract price.

Materials

Use equipment, materials and wiring methods suitable for the types of locations in which they will be located, as defined in Definitions above.

All materials and equipment specified herein shall, within the scope of UL Examination Services, be approved by the Underwriter’s Laboratories for the purpose for which they are used and shall bear the UL label.

Components

Fasteners for securing equipment to walls, floors and the like shall be either hot-dip galvanized after fabrication or stainless steel. Provide stainless steel fasteners in Corrosive locations. When fastening to existing walls, floors, and the like, provide capsule anchors, not expansion shields. Size capsule anchors to meet load requirements. Minimum size capsule anchor bolt is 3/8-inch.

NEMA Rating

Unless otherwise noted, provide enclosures as follows:

1. Class 1, Division 1 & 2 Locations: NEMA Type 7

2. Indoors unclassified Locations: NEMA Type 12

3. Corrosive Locations: NEMA Type 4X

4. Outdoors and/or Wet Locations: NEMA Type 4X

Accessories

Wire Identification

Page 172: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-4

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

1. Identify each wire or cable at each termination and in each pull box using numbered and lettered wire markers. All electrically common conductors shall have the same number. Each electrically different conductor shall be uniquely numbered. Identify panelboard circuits using the panelboard identification and circuit number. Identify motor control circuits using the equipment identification number assigned to the control unit by the motor control center manufacturer and the motor control unit terminal number. Identify other circuits as approved by the Engineer. Identify each wire or cable in each pull box with plastic sleeves having permanent markings. Conductors between terminals of different numbers shall have both terminal numbers shown at each conductor end. The terminal number closest to the end of the wire shall be the same as the terminal number.

Finishes

Refer to each electrical equipment section of these Specifications for painting requirements of equipment enclosures.

Part 3 - Execution

Installation

General

1. Complete the wiring, connection, adjustment, calibration, testing and operation of mechanical equipment having electrical motors and/or built-in or furnished electrical components in accordance with electrical code, UL listing requirements and manufacturer’s instructions. Install electrical components that are furnished with mechanical equipment.

2. Provide the size, type and rating of motor control devices, equipment and wiring necessary to match the ratings of motors furnished with mechanical equipment.

3. Complete the procurement, installation, wiring, connection, calibration, adjustment, testing and operation of all electrical devices, components accessories and equipment which is not shown or specified but which is nonetheless required to make the systems shown and specified properly functional.

Workmanship

1. Assign a qualified representative who shall supervise the electrical construction work from beginning to completion and final acceptance.

2. Provide all labor using qualified craftsmen, who have had experience on similar

projects.

3. Ensure that all equipment and materials fit properly in their installations.

Field Services

1. Provide field services of qualified technicians to supervise and check out the installation of the equipment, to supervise and check out interconnecting wiring, to conduct start-up and operation of the equipment, and to correct any problems which occur during testing and start-up.

Page 173: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-5

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Installing Equipment

1. Provide the required inserts, bolts and anchors, and securely attach all equipment and materials to their supports.

2. Install all equipment and junction boxes to permit easy access for normal maintenance.

Cutting, Drilling and Welding

1. Provide any cutting, drilling, and welding that is required for the electrical construction work.

2. Structural members shall not be cut or drilled, except when approved by the Engineer. Use a core drill wherever it is necessary to drill through concrete or masonry. Perform patch work with the same materials as the surrounding area and finish to match.

Metal Panels

1. Mount all metal panels, which are mounted on, or abutting concrete walls in damp locations or any outside walls ¼-inch from the wall, and paint the back side of the panels with a high build epoxy primer with the exception of stainless steel panels. Film thickness shall be 10 Mils minimum.

Field Quality Control

Minor Deviations

1. The electrical plans are diagrammatic in nature and the location of devices, fixtures and equipment is approximate unless dimensioned. On the basis of this, the right is reserved by the owner to provide for minor adjustments and deviations from the locations shown on the Plans without any extra cost. Deviations from the Plans and/or specifications required by code shall also be done, subsequent to Owner’s approval, without extra cost.

2. Plans indicate the general location and number of the electrical equipment items. When raceway, boxes, and ground connections are shown, they are shown diagrammatically only and indicate the general character and approximate location. Layout does not necessarily show the total number of raceways or boxes for the circuits required. Furnish, install, and place in satisfactory condition all raceways, boxes, conductors and connections, and all of the materials required for the electrical systems shown or noted in the contract documents complete, fully operational, and fully tested upon the completion of the project.

Project Record Plans

1. A set of Plans shall be maintained at the job site showing any deviations in the electrical systems from the original design. A set of electrical Plans, marked in red to indicate the routing of concealed conduit runs and any deviations from the original design, shall be submitted to the Engineer for review at the completion of the project prior to final acceptance.

2. After testing and acceptance of the project the Contractor shall furnish in the O&M manuals an accurate connection schematic and interconnection diagram for every

Page 174: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-6

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

service entrance panel, pump control panel, motor control center, and instrumentation panel provided this project.

Cleanup and Equipment Protection

Equipment Protection

1. Exercise care at all times after installation of equipment, motor control centers, control panels, etc., to keep out foreign matter, dust debris, and moisture. Use protective sheet metal covers, canvas, heat lamps, etc., as needed to ensure equipment protection.

Cleaning Equipment

1. Thoroughly clean all soiled surfaces of installed equipment and materials upon completion of the project. Clean out and vacuum all construction debris from the bottom of all equipment enclosures.

Painting

1. Repaint any electrical equipment or materials scratched or marred in shipment or installation, using paint furnished by the equipment manufacturer.

Final Cleanup

1. Upon completion of the electrical work, remove all surplus materials, rubbish, and debris that accumulated during the construction work. Leave the entire area neat, clean and acceptable to the Owner.

2. Lamps and fluorescent tubes shall be cleaned and defective units replaced at the time

of final acceptance.

16.10 ELECTRICAL SITE WORK

16.10.1 Common Work for Electrical Site Work

Part 1 – General

Description of Work

The work included in this section consists of furnishing and installing conduit, fittings, handholes, pull vaults, warning tape, cables, wires, and related items, complete as specified herein and as indicated on the plans for a complete and functional underground electrical system. Special vaults, grounding, trench backfill requirements may be specified with the particular equipment or electrical system involved.

Part 2 – Products

General

Materials and equipment shall conform to the respective specifications and standards; and to be the specifications herein. Electrical rating shall be as indicated on plans.

Raceways and conduit shall be provided per Section 16.70.

Wire and cable shall be provided per Section 16.60.

Page 175: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-7

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Part 3 – Execution

Construction

Provide all excavation, trenching, backfill and surface restoration required for the electrical work.

Trenching shall be to depths as required by Code, particular installation, or as shown on the Plans. Trench width and length as required by the installation or as shown. Trench bottom shall be free of debris and graded smooth. Where trench bottom is rock or rocky, or contains debris larger than 1 inch or material with sharp edges, over excavate 3 inches and fill with 3 inches of sand. Separation between new electrical utilities and other utilities shall be 12 inches minimum, except gas line separation shall be 12 inches both vertical and horizontal. Perform crossing of concrete or asphalt only after surface material has been saw cut to required width and removed.

Backfill around raceways shall be 3-inches of pea gravel or sand for systems of 600 volt or less. Provide red marker tape over raceways below grade. Place backfill material to obtain a minimum degree of compaction of 95 percent of maximum density at optimum moisture content. Moisten backfill material as required to obtain proper compaction. Do not use broken pavement, concrete, sod, roots or debris for backfill.

16.10.2 Underground Marking Tape (Detectable Type)

Part 2 – Products

Manufacturers

Tape shall be Brady “Detectable Identoline – Buried Underground Tape”, or equal.

Materials

Underground marking tape shall be for location and early warning protection of buried power and communication lines. Tape shall be detectable by a pipe/cable locator or metal detector from above the undisturbed ground. Tape shall be nominally 2 inches wide with a type B721 aluminum foil core laminated between two layers of 5 Mil thickness polyester plastic. The plastic color shall be red for electrical lines and orange for telephone lines.

Part 3 – Execution

Installation

Approved underground marking tape shall be installed in the trench directly over the conduit or raceway, vertical distance from the conduit or raceway as noted on the Plans.

Page 176: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-8

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.15 ELECTRICAL GROUNDING

16.15.1 Common Work for Electrical Grounding

Part 1 - General

References

Service and equipment grounding shall be per Article 250 of the National Electrical Code (NEC).

Performance Requirements

Verify that a low-resistance ground path is provided for all circuits so an accidental contact to ground of any live conductor will instantly trip the circuit.

Part 2 - Products

Components

The grounding systems shall consist of the ground rods, grounding conductors, ground bus, ground fittings and clamps, and bonding conductors to water piping and structural steel as shown on the Plans.

System components shall be as allowed in the N.E.C. unless specified otherwise below.

1. Ground Rods: Ground rods shall be cone pointed copper clad Grade 40 HS steel rods conforming to ASTM B228. The welded copper encased steel rod shall have a conductivity of not less than 27% of pure copper.

2. Ground Conductors: Buried conductors shall be medium-hard drawn bare copper; other conductors shall be soft drawn copper. Sizes over No. 6 AWG shall be stranded. Coat all ground connections except the exothermic welds with electrical joint compound, non-petroleum type, UL listed for copper and aluminum applications.

3. Ground Rod Boxes: Boxes shall be a 9-inch diameter precast concrete unit with hot-dip galvanized traffic cover. Boxes shall be 12-inches deep minimum. Covers shall be embossed with the wording “Ground Rod”.

Part 3 - Execution

General Grounding Installation

When available a UFER ground per latest edition of NEC shall be provided as the primary means to ground the electrical system.

Ground electrical service neutral at service entrance equipment to supplementary grounding electrodes.

Ground each separately derived system neutral to nearest effectively grounded building structural steel member or separate grounding electrode.

Provide a ground rod box for each ground rod so as to permit ready access to facilitate testing.

Provide a ground wire in every conduit carrying a circuit of over 110 volts to ground.

Page 177: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-9

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Make embedded or buried ground connections, taps and splices with exothermic welds. Coat ground connections.

Bond metallic water piping at its entrance into each building.

Vault and Handhole Grounding

Exposed noncurrent-carrying metal parts of equipment, conductor supports or racks, conduits and other metal appurtenances, including any metal cover and its supporting ring, shall be bonded together and connected to a common ground. The size of the grounding means shall be as prescribed in the National Electric Code. Where the grounding means is exposed, the grounding conductor shall be not smaller than #8 AWG copper.

Ground Connections

Above grade ground connections shall be exothermic weld, mechanical, or compression-type connectors; or brazing.

Below grade ground connections shall be exothermic weld.

Install all ground connections is strict accordance with connector manufacturer’s recommendations and methods.

Testing

Following completion of the grounding electrode system, if installed, measure ground resistance at each ground rod using the three rod method. Submit results to engineer prior to final acceptance by the Owner.

Perform testing per NETA Standard ATS paragraph 7.13. Testing methods shall conform to NETA Standard ATS using the three electrode method for large systems. Conduct tests only after a period of not less than 48 hours of dry weather.

Furnish to the Engineer a test report with recorded data of each ground rod location. See Division 16.95.4.

16.20 UTILITY SERVICE

16.21.2 Electrical Utility Meter Enclosure

Manufacturers

Meter enclosure shall be a Circle AW or equal and as required to meet the requirement of the serving utility. Installation shall be in vandal proof NEMA 4X stainless steel enclosure with a lockable hinged door. Meter shall include a metal vandal screen that can be purchased from serving utility. Meter shall be safety switch type to meet Puget Sound Energy requirements.

Materials

Contractor shall coordinate with Puget Sound Energy on the type of metering required and shall provide all labor and material necessary to meet Puget Sound Energy requirements. Meter enclosure to be mounted no more than 6 feet to the center of the glass dome.

Page 178: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-10

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.21.4 Circuit Breaker Service Disconnect Switch

Design

The switch shall be heavy duty type, shall be quick-make, quick break, and shall be horsepower rated. The switch shall have blades as required to open all ungrounded conductors. The disconnect shall have a minimum available fault current withstand rating of 42,000 amperes unless noted otherwise on the plans.

Service equipment shall meet the requirements of the serving utility and shall be suitable for use as service equipment. Service entrance disconnect shall be furnished with a UL service entrance label.

Manufacturers

Materials, equipment and accessories specified in this section for the service disconnect switch shall be as noted on the Plans, no substitutions.

Materials

The switch shall be pad-lockable in both the OFF or ON position.

The enclosure shall be NEMA 4X Stainless Steel rated unless noted otherwise on the plans. The enclosure shall have interlocking cover to prevent opening door when switch is closed. The interlock shall include a defeating scheme. The enclosure shall be padlockable.

Circuit breakers shall be molded case thermal-magnetic type and meet molded case circuit breaker specifications covered in Division 16.55.16.

16.55 SWITCHES AND PROTECTIVE DEVICES

16.55.1 Common Work for Switches and Protective Devices

Part 1 - General

Design Requirements

Overcurrent devices shall be NEMA rated.

Extra Materials

Provide one fuse for each ungrounded conductor and a minimum of one spare fuse per phase of each ampacity and voltage used on the project. Deliver fuses to Owner at the completion of the project.

Part 3 – Execution

Installation

Overcurrent protection devices and safety switches shall be centered 60 inches above the finished floor unless noted otherwise on the Plans.

Page 179: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-11

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.55.16 Molded Case Circuit Breakers

Part 1 - General

Design Requirements

Breakers shall have the interrupting rating and trip rating indicated on the Plans. All breakers shall be calibrated for operation in an ambient temperature of 40 degrees Celsius.

Part 2 - Products

Manufactured Units

Molded case circuit breakers shall be quick-make and quick-break type with wiping type contacts. Each breaker shall be provided with arc chutes and individual trip mechanisms on each pole consisting of both thermal and magnetic trip elements. Two and three pole breakers shall be common trip. Molded case circuit breakers shall be trip-free. Each breaker shall have trip indication independent of the “ON” or “OFF” positions.

16.60 CONDUCTORS

16.61 Low Voltage Wire and Cable

Part 1 - General

Design Requirements

This section is for power and control conductors for 600 volts or less.

All conductors shall be copper. Wire or cable not shown on the Plans or specified, but required, shall be of the type and size required for the application and in conformance with the applicable code.

Part 2 - Products

Materials

Conductors

1. Stranded copper wire shall be 600 volt Type THW, THWN, or THHW, Class B stranding, sizes #14 AWG, #12 AWG, and #10 AWG only. Use of THHN insulation shall be for field wiring only. Aluminum conductors shall not be allowed.

2. Stranded copper wire shall be 600 volt Type XHHW, Class B stranding, sizes #8 AWG and larger. Aluminum conductors shall not be allowed.

Splices

1. Splicing of conductors shall not be allowed.

Terminations

1. Crimp type terminals shall be self-insulating sleeve type, with ring or rectangular type tongue, suitable for the size and material of the wire to be terminated, and for use with either solid or stranded conductors.

Page 180: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-12

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

2. Terminal lugs shall be split bolt or bolted split sleeve type in which the bolt or set screw does not bear directly on the conductor.

3. Wire Markers shall be plastic sleeve type. Wire numbers shall be permanently imprinted on the markers. Wire markers shall be shrunk onto the wires.

Finishes

Color Coding: Provide color coding for all circuit conductors as shown on the Plans.

Part 3 – Execution

Location (Installment) Schedule

Provide the following conductors for the following applications

1. Use stranded copper conductors for all power and control circuits unless noted otherwise on plans or below. Size as noted on the plans.

2. Size #14 AWG wire or smaller shall not be allowed on power circuits.

Installation

Conductor Identification

1. Except for interior lighting and receptacle circuits, identify each wire or cable at each termination and in each pullbox, junction box, handhole, and manhole using numbered and lettered wire markers. All electrically common conductors shall have the same number. Each electrically different conductor shall be uniquely numbered. Identify panelboard circuits using the panelboard identification and circuit number. Identify motor control circuits using the equipment identification number assigned to the control unit by the motor control center manufacturer and the motor control unit terminal number. Identify other circuits as shown in the circuit schedule as favorably by the Engineer.

2. Conductors between terminals of different numbers shall have both terminal numbers shown at each conductor end. The terminal number closest to the end of the wire shall be the same as the terminal number.

Testing

Insulation Resistance Tests: For all circuits 150 volts to ground or more and for all motors circuits over ½ horsepower, test cables per NETA Paragraph 7.3.1. The insulation resistance shall be 20 megohms or more. Submit results to Engineer for review.

Part 3 - Execution

Installation

Cable Installation

1. Cables shall be continuous from initiation to termination without splices.

2. Cable shielding shall be grounded at one end of the cable only. Bonding shall be to a single ground point only. Bonding from cable to cable in multiple run installations shall not be permitted.

Page 181: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-13

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

3. Install instrumentation cables in separate raceway systems with voltages not to exceed 30 volts DC.

Conductor Identification

1. Except for interior lighting and receptacle circuits, identify each wire or cable at each termination and in each pullbox, junction box, handhole, and manhole using numbered and lettered wire markers. All electrically common conductors shall have the same number. Each electrically different conductor shall be uniquely numbered. Identify panelboard circuits using the panelboard identification and circuit number. Identify motor control circuits using the equipment identification number assigned to the control unit by the motor control center manufacturer and the motor control unit terminal number. Identify other circuits as shown in the circuit schedule as determined by the Engineer.

2. Conductors between terminals of different numbers shall have both terminal numbers shown at each conductor end. The terminal number closest to the end of the wire shall be the same as the terminal number.

Testing

Insulation Resistance Tests: Perform insulation resistance on all circuits. Make these tests before any equipment has been connected. Test the insulation with a 500 Vdc insulation resistance tester with a scale reading 100 mega ohms. The insulation resistance shall be 20 mega ohms or more. Submit results to Engineer for review.

16.70 RACEWAYS, BOXES AND FITTINGS

16.71 Raceways

Part 1 – General

Design Requirements

Conduit sizes not noted on Plans shall be in accordance with NEC requirements for the quantities and sizes of wire installed therein.

Part 2 – Products

Components

Conduit and Fittings

1. PVC Coated Rigid Steel Conduit(PVC-GRS): Rigid conduit shall be steel, hot dipped galvanized inside and out with a 40 Mil PVC factory applied PVC coating. The GRS must meet USA Standards Institute C80-1 Underwriters Laboratories Standard UL6 and carry a UL label. Use cast threaded hub fittings and junction boxes for all rigid conduit except in locations not permitted by the NEC.

Conduit, Cable Supports, and Unistrut

1. Conduit Supports: Type 316 stainless steel framing channel SST profile shall be used to support groups of conduit. Supports shall meet ASTM A240 requirements for Type 316.

Page 182: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-14

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Conduit Sealants

1. Moisture Barrier Types: Sealant shall be a non-toxic, non-shrink, non-hardening, putty type hand applied material providing an effective barrier under submerged conditions.

2. Fire Retardant Types: Fire stop material shall be a reusable, non-toxic, asbestos-free, expanding, putty type material with a 3-hour rating in accordance with UL 1479. Provide products indicated by the manufacturer to be suitable for the type and size of penetration.

3. Conduit penetrations shall be Myers Hub type.

Part 3 - Installation

Raceway Applications

PVC Coated Galvanized Rigid Steel (GRS) conduit shall be used in all locations.

Installation

Size of Raceways:

1. Raceway sizes as shown on the Plans, if not shown on the Plans, then size in accordance with NFPA 70.

2. Unless specifically indicated otherwise, the minimum raceway size shall be: a) Conduit: 1-inch

All raceways shall contain a separate grounding conductor.

Spare conduits shall contain one 3/16-inch diameter nylon pull rope.

Conduit routing is shown diagrammatic on the Plans. Contractor is responsible for routing the conduits in a neat manner, parallel and perpendicular to walls and ceilings.

Location of conduit ends are shown approximately. Contractor is responsible for ending conduits in location that will not conflict with electrical equipment. Route conduit ends to facilitate ease of equipment maintenance. Conduits extending from the floor to a device shall be located as close as possible to avoid creating a hazard.

Conduit shall not be routed on exterior of structures except as specifically indicated on the plans.

Where water cannot drain to openings, provide drain fittings in the low spots of the conduit run.

Securely fasten raceways at intervals and locations required by NEC, or the type of raceway employed.

Provide all required openings in walls, floors and ceilings for conduit penetration.

1. Do not install one (1) inch and larger raceways in or through structural members (beams, slabs, etc.) unless approved by Engineer.

2. New Construction: Avoid cutting openings, where possible, by setting sleeves or frames in masonry and concrete, and by requesting openings in advance.

Page 183: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-15

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

3. Existing Construction: Core drill openings in masonry and concrete. Avoid structural members and rebar.

Conduit Encasement or Embedment in the earth shall be separated from the earth by at least 3-inches of concrete unless otherwise shown on the Plans. Plastic conduit spacers shall be located five feet on centers. The spacers shall be secured to the conduits by wire ties. The conduits shall be watertight.

Install explosion-proof seal-offs in hazardous areas shown on the Plans and as required by the N.E.C.

All conduit openings not encased in a panel shall be sealed with duct seal.

16.90 POWER GENERATION

16.91 Engine Generator

16.91.2 Diesel Engine Generator Set

Part 1 - General

Scope

This section covers the work necessary to furnish diesel engine power generating systems complete and ready for operation.

The work consists of furnishing Standby Power Systems with features and accessories as specified herein and shown on the drawings. The Standby Power System shall consist of a diesel engine-driven alternator; digital (micro-processor based) electronic generator set and control system (with all required appurtenances); battery charger; sound- attenuating, weather-proof, outdoor enclosure; sub-base fuel tank and fuel transfer pump (if required). Minimum rating of the generating set will be as shown on the drawings.

Generator sets will be furnished for Lift Station No. 4, Lift Station No. 5, Lift Station No. 8, Lift Station No. 11, Lift Station No. 17, and Lift Station No. 24.

The Standby Power System shall be furnished by a single manufacturer who is regularly engaged in the production of engine-generator sets and associated control products. The responsibility for performance of this Specification in its entirety must be assumed solely by the manufacturer of the system.

See electrical plan drawings for sizing, stepping, and additional generator requirements.

Codes and Standards

A. THE GENERATOR SET INSTALLATIONS AND ON-SITE TESTING SHALL CONFORM TO THE REQUIREMENTS OF THE FOLLOWING CODES AND STANDARDS, AS APPLICABLE. THE GENERATOR SET SHALL INCLUDE NECESSARY FEATURES TO MEET THE REQUIREMENTS OF THESE STANDARDS.

1. ANSI S1.13-1971—Measurement of Sound Pressure Levels in Air.

2. CSA 282, 1989 Emergency Electrical Power Supply for Buildings.

Page 184: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-16

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

3. IEEE446 – Recommended Practice for Emergency and Standby Power Systems for

Commercial and Industrial Applications.

4. NFPA 30 – Flammable and Combustible Liquids.

5. NFPA 37 – Standard For the Installation and Use of Stationary Combustion Engines

and Gas Turbines.

6. NFPA 70 – National Electrical Code. Equipment shall be suitable for use in systems

in compliance to Article 700, 701, and 702.

7. NFPA 99 – Essential Electrical Systems for Health Care Facilities.

8. NFPA 110 – Emergency and Standby Power Systems. The generator set shall meet

all requirements for Level 1 systems. Level 1 prototype tests required by this standard

shall have been performed on a complete and functional unit, component level type

tests will not substitute for this requirement.

B. THE GENERATOR SETS AND SUPPLIED ACCESSORIES SHALL MEET THE REQUIREMENTS OF THE FOLLOWING STANDARDS:

1. NEMA MG1-1998 part 32. Alternator shall comply with the requirements of this

standard.

2. UL142 – Sub-base Tanks.

3. UL1236 – Battery Chargers.

4. UL2200. The generator set shall be listed to UL2200 or submit to an independent third

party certification process to verify compliance as installed.

C. THE CONTROL SYSTEM FOR THE GENERATOR SETS SHALL COMPLY WITH

THE FOLLOWING REQUIREMENTS.

1. EN50082-2, Electromagnetic Compatibility – Generic Immunity Requirements, Part

2: Industrial.

2. EN55011, Limits and Methods of Measurement of Radio Interference Characteristics

of Industrial, Scientific and Medical Equipment.

3. FCC Part 15, Subpart B.

4. IEC8528 part 4. Control Systems for Generator Sets.

D. THE GENERATOR SET MANUFACTURER SHALL BE CERTIFIED TO ISO 9001

INTERNATIONAL QUALITY STANDARD AND SHALL HAVE THIRD PARTY

CERTIFICATION VERIFYING QUALITY ASSURANCE IN

DESIGN/DEVELOPMENT, PRODUCTION, INSTALLATION, AND SERVICE,

IN ACCORDANCE WITH ISO 9001.

Acceptable Manufacturers

Approved accepted manufacturers are Kohler, MTU, and Caterpillar.

Page 185: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-17

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Warranty

The manufacturer shall provide base warranty coverage on the material and workmanship of the generator set for a minimum of sixty (60) months or 3,000 hours of runtime for Standby product from registered commissioning and start-up.

Submittals

The following specific information shall be provided for each generator:

A. An outline drawing showing the proposed engine-generator set, drive system, fuel tank,

and enclosure. The outline drawing shall indicate the required clearances for door

and access panel opening, maintenance, refueling and cooling.

B. Submit sound ratings at 23 feet when the unit is enclosed in the manufacturer’s sound

absorbing housing.

C. Catalog cuts and technical description of the proposed engine-generator set; the technical

description shall include materials and dimensions of cylinders, pistons, crankshaft,

and other major parts, and a complete list of all accessories that are to be provided.

D. Curves showing the engine fuel consumption and kW output.

E. Generator descriptive information, output ratings, and transient response

characteristics. Provide printouts of generator sizing based on the motors to be started and

run, and their sequence of starting.

F. Description of parts and service availability.

G. Rated horsepower of generator.

Part 2 – Products

Components

A. Diesel Engine

1. The general design of the engine furnished shall be the standards of the

manufacturer, except where these differ from the requirements of these

Specifications. The design shall be such as to provide adequate strength of all parts

for the specified duty. The complete engine-generator unit shall be mounted

on a common steel fuel tank sub-base.

2. The engine shall be a four-cycle diesel type suitable for a continuous output as specified

herein when driving a synchronous generator at a speed not exceeding 1,800 rpm.

Horsepower ratings shall be adequate for 1,000 foot elevation operation.

3. The engine shall be equipped with automatic starting by a 12-volt or a 24-volt battery

driven starter acting in response to the automatic transfer switch, shown on the

drawings. Batteries shall be 200 amp-hour minimum capacity and the 24-volt system

may be either one 24-volt or two 12-volt batteries in series. The batteries shall be

housed in an acid-resistant frame, or box, which shall be mounted adjacent to

Page 186: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-18

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

the engine within the enclosure. The battery shall be protected against the cold

down to -10 degrees Fahrenheit. Location of the battery container shall not

interfere with maintenance and inspection of the engine.

4. A fuel oil transfer pump driven off the engine shall be provided to pump the fuel from

the integral tank to the engine. This pump shall be suitable for operation with a 12-foot

suction lift. A spin-on fuel filter with water separator shall be provided. Fuel

connections to engine shall be with flexible hose suitable for the purpose at least 18

inches long.

5. The governor shall be electronic and shall provide speed drop externally

adjustable from isochronous to 5 percent. The governor shall be set to

isochronous. An overspeed trip shall be provided.

6. The jacket water cooling system shall consist of an engine mounted radiator with jacket

water pump, fan, assembly, fan guard, and valved coolant drain. The drain shall have a

drain valve installed with a flexible rubber drain line (1/2 inch min., inside diameter).

The hose shall be long enough to reach outside of the generator enclosure for the

purpose of servicing and draining the liquid.

7. Provide an engine thermostat to regulate engine coolant temperature as

recommended by the manufacturer. Provide a high-coolant temperature device to shut

down the engine through the engine control panel when the engine temperature

exceeds 200 degrees F. Jacket water heaters suitable for operation on 120-volt, 60-

Hz current shall be provided to maintain engine water temperature at 120

degrees F with an ambient temperature of 50 degrees F. Heaters shall be

thermostatically controlled. The engine cooling system shall be filled with a mixture

of water and permanent type antifreeze to protect the system to a temperature of -

10 degrees F.

8. The engine lubricating system shall be the full-pressure type with a device to shut

down the engine through the engine control panel on low oil pressure. Provide a

spin-on type oil filter, canister style not acceptable, and a bayonet type oil level stick.

Provide a valved oil drain extension. The drain shall have a drain valve installed with a

flexible rubber drain line (1/2 inch min., inside diameter). The hose shall be long enough

to reach outside of the generator enclosure for the purpose of servicing and draining the

liquid.

9. Lubrication oil shall be cooled by a water-cooled heat exchanger utilizing jacket water.

10. The engine air intake shall be equipped with a dry type air cleaner with filter service

indicator.

11. Instrumentation to be provided shall include an oil pressure gauge, coolant

temperature gauge, tachometer, fuel pressure gauge, and running time meter. These

Page 187: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-19

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

gauges shall be installed on the engine starting panel as described under STARTING

CONTROL PANEL. All of these gauges shall be included as part of an electronic

display rather than mechanical gauges.

B. Generators

1. The generators shall be single-bearing, synchronous type, suitable for direct

connection to the engine. The generator shall be rated as shown on the

drawings, at 60 Hz, standby.

2. A permanent magnet generator (PMG) shall provide excitation power to the

automatic voltage regulator for immunity from voltage distortion caused by non-

linear SCR controlled loads from the generator. The PMG shall sustain main field

excitation power for optimum motor starting and to sustain short circuit current

for selective operation and coordination of system overcurrent devices.

3. The engine generator unit shall have a steady state voltage regulation not

exceeding plus or minus 1 percent. Frequency regulation shall be isochronous.

Transient voltage dip shall not exceed 20 percent of rated voltage with a sudden

application of rated load, and recovery to rated steady state conditions shall occur

within 2 seconds following the load change.

4. The generator shall be supplied with a voltage level control to provide an

adjustable output voltage of plus or minus 5 percent. The voltage control device shall

be mounted on the engine starting panel.

C. Sub-Base and Vibration Isolators

1. The engine and generator shall be mounted on a fuel tank base sufficiently rigid to

prevent deflection between vibration isolators. The engine-generator shall be mounted

on Korfund Series L vibration isolators. Vibration isolators shall be sized by the

isolator manufacturer and shall be such to limit the maximum vibration

transmissibility to 10 percent.

D. Torsional Vibration

1. The complete engine-generator set shall be so designed, constructed, and installed

as to be free from objectionable vibration in any mode. Freedom from torsional

vibration shall be demonstrated by torsiograph records taken during the factory test of

this or a similar unit.

E. Factory Paint

1. The complete engine-generator set, including the instrument panel, shall be given

a factory-applied primer and two finish coats of the manufacturer's standard

heat-resistant engine paint. All areas damaged during shipment shall be touched up after

installation.

F. Starting Control Panel

Page 188: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-20

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

1. Provide an NFPA-110 Level 1 control panel. The engine will automatically start from

a signal from the automatic transfer switch. When the engine fires, starting control shall

automatically disconnect the cranking control and prevent re-cranking for a

definite period of time after engine stops. The starting control panel shall be vibration

isolated with hooded panel lights, in a sound attenuated weatherproof enclosure.

2. Four cranking cycles of 10 seconds ON and 10 seconds OFF shall be provided prior to

lockout on overcranking.

3. Fault indicating lamps on the panel shall be push to test type and shall indicate low oil

pressure, high water temperature, overspeed, and overcrank. The engine shall shut

down under any of these conditions and may not be restarted until the system is

manually reset. Provide low fuel level and fuel leak indicating lamps. All indicators shall

also show on the electronic display of the instrument panel.

4. A three-position selector switch shall be provided in the panel for AUTO, OFF,

MANUAL.

5. A fully automatic float/equalize, constant voltage, current limiting type battery

charger, suitable for operation on 120-volt power shall be furnished within the

enclosure. The charger shall be equipped with a DC voltmeter, a DC ammeter, loss of

power light, low battery voltage light, high battery voltage light and power on light

which shall be mounted on the face of the cranking panel and match the generator

instrumentation.

6. The starting control panel shall include a panel type 3-1/2-inch ammeter, a panel

type 3-1/2-inch voltmeter with selector switch and frequency meter (vibrating reed type)

mounted on the engine starting panel. All necessary instrument transformers shall be

included.

7. The starting control panel shall have sufficient space to permit mounting of the engine

and generator instrumentation specified under DIESEL ENGINE and under

GENERATOR on the face. All instruments shall be identified either on the

instrument face or by engraved, black, laminated plastic nameplates with white 1/4

-inch high letters. Control panel shall be mounted so that panel is less than 6’ AFG.

8. Provide two generator mounted circuit breakers, molded case, 3 pole, NEMA

1/IP22. One which will disconnect the generator from the supply circuit and the other

for a load bank connection. Circuit breakers to be sized as shown on the plan drawings.

The Main Circuit breaker connected for system load shall utilize a solid-state trip unit

and shall have the electrical characteristics, rating, and modifications as shown. The

Load Bank breaker shall be a standard thermal mag sized for full load of the generator.

The breakers shall be UL/CSA Listed and connected to engine/generator safety

shutdowns. Breakers shall be housed in an extension terminal box which is isolated

from vibrations induced by the generator set and shall have a metal nameplate that

Page 189: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-21

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

contains a permanent record of the circuit breaker catalog number and maximum

ratings. Mechanical type lugs, sized for the circuit breaker feeders shown on drawing,

shall be supplied on the load side of breaker.

a. Main circuit breaker trip system shall be a microprocessor-based true rms

sensing designed with sensing accuracy through the thirteenth (13th)

harmonic. Sensor ampere ratings shall be as indicated on the associated

drawing. The solid-state trip circuit breaker shall include the following

adjustments; each adjustment shall have discrete settings (fully adjustable)

and shall be independent of all other adjustments:

i. An ampere trip setting (long time pickup) that is adjustable from

0.5 times (minimum) to 1.0 times the plug ampere rating, in

0.1 increments.

ii. An adjustable long time pickup delay.

iii. A short time pickup trip setting that is adjustable from 2 times

(minimum) to 9 times (minimum) the long-time ampere trip setting.

iv. An adjustable short time delay ramp function.

v. An instantaneous pickup that is adjustable from 1.5 times (minimum)

to 15 times the long-time ampere trip setting.

b. Main circuit breaker shall have a quick-make, quick break, over-center toggle

type, trip-free mechanism to prevent holding contacts closed against a

position between "ON" and "OFF" when tripped automatically.

Breaker shall be common trip such that an overload or short circuit on

any one pole will result in all poles opening simultaneously.

c. The interrupting capacity of the Main Circuit Breaker shall be 22 kAIC,

minimum.

9. Form C dry contacts shall be prewired to terminal blocks in the control panel for

remote indication of the following status and alarm conditions, at a minimum.

a. Generator Running

b. Generator Fail

G. Sound Attenuated Weather Protective Housing

1. The engine generator sets shall be enclosed in weather protective sound

attenuating metal housing. The enclosure shall be of a pre-painted sheet metal

construction with sound insulation that reduces the engine generator noise to

maximum of 78 dBA at 23 feet from the generator in all directions. There shall be a

minimum of two (2) doors per side on the generator for access and maintenance.

Page 190: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-22

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

The doors shall be hinged and lockable with stainless steel hardware; bolted on

doors will not be accepted. The weather protective housing shall be designed to

permit sufficient flow of air for efficient cooling and combustion in an ambient

temperature of 50°C (122°F).

2. A single junction box shall be provided in the enclosure for power to jacket water

heaters and battery charger. A dedicated outlet shall be installed for each the battery

charger and the water jacket heater. The outlets shall be installed on the outside of the

engine control panel and be accessible to engine side of panel. Junction box shall be

rated NEMA 12 or better.

3. Housing shall be manufactured by the generator manufacturer.

H. Mounted Exhaust System

1. An exhaust silencer shall be provided. The silencer shall be of chambered

construction and shall be of the critical silencing type and shall provide a

maximum dBA level of 78 at a distance of 23 feet in a free field environment. Silencer

shall be sized to assure proper operation without excessive back pressure when

installed in the exhaust system.

2. Provide support system (seismic zone 4) for exhaust system and piping in

accordance with applicable codes. The exhaust silencer shall be supplied with a

condensation trap and rain cap.

3. Provide flexible connections of the exhaust system at the engine. Flexible bellow

exhaust pipe shall be seamless stainless steel exhaust pipe with a minimum

length of 12 inches.

I. Fuel Tank

1. The system shall include a double walled diesel fuel sub-base storage tank as an integral

part of the generator enclosure. The tank shall be equipped with a high fuel sensor and

alarm at 90% full. The tank shall be equipped with a low fuel level sensor. The tank

shall be equipped with a leak detection system between the inner and outer tank

walls. Fuel leaks, high fuel level and low fuel level shall be annunciated on the

generator control panel. The tank shall include fuel level gauge, fuel tank filler cap

and necessary tank vents to comply with applicable codes and regulations. Tank

shall be constructed in a manner to support the weight of the generator set and

enclosure. Fuel tank shall be sized to provide 48 hours of operation fully loaded.

J. Coolant Heater

1. Provide a thermostatically controlled coolant heater sized appropriately by the

generator manufacturer. Heater shall be rated 120V, 1-phase, 60Hz. A dedicated outlet

for the coolant heater shall be provided as mentioned in Section G, above.

Page 191: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-23

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

K. Spare Parts

1. The following spare parts shall be furnished for each generator:

a. 3 sets of fuel oil filter elements and gaskets.

b. 3 spin-on type lubricating oil filters, canister style is not acceptable.

c. 1 air cleaner filter element.

d. 2 sets of V-belts for fan and pump drives.

L. Automatic Transfer Switch

1. Shall be as shown on the Electrical Drawings.

Part 3 - Execution

Installation

A. Installation shall comply with applicable state and local codes as required by the

authority having jurisdiction. Install equipment in accordance with manufacturer's

instructions and instructions included in the listing or labeling of UL listed products.

B. Provide and install emergency system conductors in a raceway system completely

separate from other wiring. Control interconnection wiring shall be properly sized and run

in a raceway separate from power cables.

Testing

A. To provide proven reliability of the system, three series of tests shall be performed:

Prototype Model Tests, Production Model Tests, and Field Tests. The manufacturer

shall provide documentation demonstrating satisfactory prototype and production

test results. Generator sets that have not been prototype tested, and factory tested

at 0.8 PF will not be acceptable.

B. Generator Set Factory Prototype Tests and Evaluation:

a. These tests and evaluations must have been performed on a prototype generator

set representative of the Model specified. A summary of the generator set testing

results shall be submitted for review. The manufacturer's standard series

of component development tests on the generator system, engine, and other

major components shall also be performed and available for review but shall

not be acceptable as a substitute for prototype testing on the complete

representative generator set prototype.

b. Torsiograph Analysis and Test: The manufacturer of the generator set shall verify

that the engine-generator set, as configured, is free from harmful torsional

stresses. The analysis shall include correlation of empirical data from tests on

a representative prototype. The empirical data must include spectrum analysis

Page 192: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-24

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

of the torsional transducer output within the operating speed range of

the engine-generator set. Calculations based on engine and generator

separately are not acceptable.

c. Temperature Rise Test: Complete thermal evaluation of a prototype generator

rotor and stator must include actual measurement of internal generator and

exciter temperatures by embedded detector method, and measurement of

average temperature rise by resistance method. No position measured any

place in the windings may exceed the temperature rise limits of NEMA

for the particular type of insulation system used. Resistance method

temperature rise data shall be confirmed by a full load test on the generator

set prototype to include conducted and radiated heat from the engine.

d. Short Circuit Test: A test on a prototype generator set shall have

demonstrated that the generator set is designed to withstand the mechanical

forces associated with a short circuit condition. With the generator set operating

at rated load and speed, the generator terminals must be short circuited on all three

phases for a duration of 20 seconds. At the conclusion of this test, the generator

set must be capable of full load operation.

e. Endurance Run Test: A minimum of five hundred (500) continuous hours of

endurance testing with a representative generator set prototype operating as

defined by the manufacturer's standby rating shall have been performed.

Endurance testing shall be used to verify structural soundness and durability.

f. Maximum Power Test: With the prototype generator set at normal operating

temperature and with all power consuming auxiliaries in place, the maximum

power available at rated speed shall be determined with the governor set at its fuel

stop. The generator set shall maintain this power for a minimum of two minutes.

g. Linear Vibration Test: A test for in-line motion of components occurring

along a repeatable path shall meet the manufacturer's acceptance criteria.

h. Cooling System Test: A cooling system test shall demonstrate the ability of

the generator set cooling system to maintain normal operating temperature while

operating at full rated load and power factor at the highest ambient

temperature of the system rating. Cooling air requirements, radiator

airflow and maximum allowable restriction at radiator discharge, shall be verified

by this test.

i. Maximum Motor Starting kVA: Motor starting kVA shall be determined

by test, based on a sustained RMS recovery voltage of at least 95% of no load

voltage with the specified load kVA at near zero power factor applied to the

generator set. Voltage dip shall be measured by a light beam oscillograph.

Page 193: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-25

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

j. Transient Response, Steady-state Speed Control, and Voltage Regulation:

Prototype generator set tests shall demonstrate consistent performance as

follows; stable voltage and frequency at all loads from no load to full rated load,

consistent frequency bandwidth with steady-state load, maximum voltage and

frequency dip on load acceptance and rejection, and restoration to steady state

after sudden load changes. Transient response is a complete generator set

(engine, generator, exciter, and regulator) performance criteria and cannot be

established based on generator data alone.

C. Factory Tests:

a. Generator set factory production tests: on the equipment to be shipped, shall be

performed at rated load and 0.8 PF. These tests shall include; 1 hour run at full

load, maximum power, voltage regulation, transient and steady-state

governing, single step load pickup, and safety shutdowns.

b. Provide a factory certified test record of the production testing.

D. On-Site Acceptance Test:

a. The complete installation shall be tested for compliance with the specification

following completion of all site work. Testing shall be conducted by

representatives of the manufacturer, with required fuel supplied by Contractor.

The Engineer shall be notified two weeks in advance and shall witness the

tests.

b. The Installation acceptance tests to be conducted on-site shall include:

i. “Cold Start" test per NFPA 110 (1988), 5-13.2.3 with the unit

connected to the required load bank.

ii. A four- h o u r full load test per NFPA 110, 5-13.2.5. Contractor shall

provide a portable resistive load bank and make temporary connections.

Data which is specified to be recorded in the “cold start” test shall be

recorded at the start of the full load test and every 15 minutes thereafter.

The unit shall be connected to the required load bank during this test.

iii. One step rated load increase and decrease test in accordance with

NFPA 110, 5-13.2.6. The unit shall be connected to the required load bank

during this test. Use recording oscilloscope to measure voltage and

frequency transients. This test can be performed by an independent testing

agency or a consultant on completion of the manufacturer’s on-site

acceptance test.

iv. A four-hour functional test of all pump station operations under loss of

normal power. The unit shall be connected to automatic transfer switch

during this test. This test shall include automatic start-up by means of

Page 194: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-26

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

simulated power outage to test automatic starting, transfer of the load, and

automatic shutdown. Prior to this test, all transfer switch timers shall be

adjusted by the generator set commissioning agent for proper system

coordination. Engine coolant temperature, oil pressure, and battery charge

level along with generator voltage, amperes, and frequency shall be

monitored throughout the test.

E. Generator/Transfer Switch Pre-Startup Checklist (Required To Be Filled Out By

Contractor)

Page 195: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-27

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Page 196: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-28

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Page 197: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-29

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

F. Preparation of Operating and Maintenance manuals

a. Provide Operating and Maintenance manuals in accordance with specification

Section D Amendments and Special Provisions paragraph 7-22.3(3)B.

G. Training

a. Provide one day of operator training on proper operation and maintenance of

engine generator sets. Training shall be conducted concurrent to the on-site

acceptance test specified herein.

16.92 Transfer Switches

16.92.2 Automatic Transfer Switch

Part 1 - General

Design Criteria

The transfer switches shall be NEMA 1 rated for indoor installations and NEMA 3R Secure rated for outdoor installations; refer to Plans for transfer switch locations. The transfer switch shall be equipped with two or three poles for normal and emergency service, depending on the site.

The transfer switches shall be mechanically and electrically held and rated to the site voltage for all classes of load and continuous inductive duty. Refer to plans for site voltages. The transfer switches shall be open transition.

The transfer switches shall conform to UL 1008 provisions for Withstand Current Ratings and Closing Ratings.

The switch shall be double throw inherently interlocked mechanically and electrically to prevent supplying the load from both sources simultaneously. The operating current shall be obtained from the source to which the load is to be transferred.

All contacts, coils, etc. shall be readily accessible for replacement from front of panel without major disassembly of associated parts.

A transfer switch shall be provided for each site; Lift Station No. 4, Lift Station No. 5, Lift Station No. 8, Lift Station No. 11, Lift Station No. 17, Lift Station No. 24, Lift Station No. 27.

Part 2 – Products

Manufactured Units

The automatic transfer switches shall be as noted on the Plans, no substitutions.

Components

The transfer switch shall include the following accessories:

A. Undervoltage Sensor: Adjustable solid state low voltage sensing relays (pick up 85 to 98 percent of normal voltage set at 98 percent; drop out 75 to 100 percent set of

Page 198: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-30

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

90 percent of pickup setting). Provide for each phase on both utility and backup power sources.

B. Time Delay Start and Stop on Drop Out: Solid state adjustable time delay on start (0 to 15 seconds). Set start delay for 15 seconds. Timer will send start signal to gen set CP, where louver timer will allow 15 second delay for louvers to open prior to starting gen set.

C. Time Delay Stop: Solid state adjustable time delay (0 to 10 minutes) to allow generator cooldown after normal power is restored and retransfer occurs. Set at five minutes.

D. Time Delay Transfer and Retransfer: Solid state time delay relay adjustable 2 to 120 seconds for transfer to emergency and 0 to 30 minutes for retransfer to normal. Set at five minutes for retransfer to normal. Set at three seconds for transfer to emergency.

E. With or Without Load Selector Switch: Switch to select exercise with or without station load.

F. Normal-Test Switch: Switch such that in the “Normal” mode the transfer switch will operate automatically and in the “Test” mode the generator will start for test purposes. This switch shall work in conjunction with the “With” or “Without” load switch.

G. Exerciser Clock: Provide solid state exerciser clock to set the day, time, and duration of generator set exercise/test period. Provide with/without load selector switch for the exercise period.

H. Position lights for normal and emergency potions indication and for normal and emergency power available.

I. Switch position indication limit switches for normal and generator positions.

J. Provide dry contacts wired to terminal strip for 1) ATS in emergency position, 2) ATS common trouble alarm, 3) Normal Position.

K. Power Meters: Provide an AC Voltmeter, an Ammeter, and a Frequency meter; 2.5 inch, analog, 2-percent accuracy. Provide a phase selector switch to read L-L voltage and current of both power sources.

L. Operator Interface Display: Provide operator interface display that allows operators to adjust all settings and see all values.

A. Control Board: Provide current generation hardware and firmware for the control board.

B. Provide manual override switch to bypass the control system and transfer load from source to source when control is disabled.

Page 199: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-31

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.95 TESTING

16.95.1 Common Work for Testing

Part 1 - General

Submittals

Test reports shall be submitted to the Engineer prior to final acceptance.

Scheduling and Coordination

The Contractor shall inform the Engineer in advance of testing.

Prior to scheduling the testing, the Contractor shall have satisfied himself that the project area is properly cleaned up; all patching and painting deemed necessary properly completed; and all systems, equipment and controls are functioning as intended.

Part 2 - Products

Source Quality Control

Submit reports of factory tests and adjustments performed by equipment manufacturers to the Engineer prior to field testing and adjustment of equipment. These reports shall identify the equipment and show dates, results of test, measured values and final adjustment settings. Provide factory tests and adjustments for equipment where factory tests are specified in the equipment specifications. The Engineer may inspect the fabricated equipment at the factory before shipment to job site. Provide the Engineer with sufficient prior notice so that an inspection can be arranged at the factory.

Part 3 – Execution

Site Testing

Test all circuits for continuity, freedom from ground, and proper operation during progress of the work.

Insulation Resistance, Continuity, and Rotation: Perform routine insulation resistance, continuity and rotation tests for all distribution and utilization equipment prior and in addition to tests performed by the testing laboratory specified herein.

Conduct special test as required for service and/or system ground.

Arc Flash Study, Protection Device Coordination and Short Circuit Analysis

Provide the services of a recognized independent testing laboratory or coordination analysis consultant for the proper system coordination of the protective devices furnished on this project. Submit the name and the qualifications of the laboratory or consultant for review by the Engineer; qualifications must include professional registration of proposed personnel as electrical engineers.

The protective device on the line side closest to the fault or abnormal conditions shall isolate the problem portion of the system and minimize damage in that portion. The rest of the system shall be maintained in normal service. The coordination shall be in conformance with the recommendations of latest IEEE Standard 242.

Page 200: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-32

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

Provide an Arc Flash Hazard Study for the electrical distribution system shown on the Plans. The intent of the Arc Flash Hazard Study is to determine hazards that exist at each major piece of electrical equipment shown on the one line diagrams. This includes switchgear, switchboards, panelboards, motor control centers, generators, transfer switches, and transformers. The study will include creation of Arc Flash Hazard Warning Labels listing all items as required in NFPA 70E-2018. These labels serve as a guide to assist technicians and others in the selection of proper Personal Protective Equipment when working around exposed and energized conductors. The electrical contractor will install the labels. The arc flash hazard study shall consider all operating scenarios during normal conditions alternate operations, emergency power conditions, and any other operations, which could result in maximum arc flash hazard. The label shall list the maximum incidental energy calculated and the Scenario number and description on the label.

Submit the analysis that shall include arc flash, impedance, and short circuit calculations, list of any assumptions made and the analysis, the recommended settings of the protective devices, and the system time/current characteristic curves. The submittal shall be completed and submitted in conjunction with the circuit breaker submittal to allow time for review and re-submittal, if necessary, before the implementation of final settings and adjustments by the testing laboratory.

Field Quality Control

General: Conduct final test in the presence of Owner and/or their authorized representative. Contractor shall provide all testing instrumentation and labor required to demonstrate satisfactory operation of systems, equipment and controls.

Operational Tests: Operational test all circuits to demonstrate that the circuits and equipment have been properly installed, adjusted and are ready for full-time service. Demonstrate the proper functioning of circuits in all modes of operation, and including alarm conditions, and demonstrate satisfactory interfacing with the data acquisition and alarm systems.

Page 201: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-33

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.95.3 Conductor Test Report

Conductor Test Report Page 1 of 1

PROJECT: OWNER:

Contractor Co. Name:

Tested by:

Phone Number:

Test Date:

Race-way

V C Operating Load Voltage Insulation Resistance - OHMS

Label

(1)

(2)

(3)

VAB

VCB

VCA

VAN

VBN

VCN

A-B

B-C

C-A

A-G

B-G

C-G

A

B

C

D

E

F

G

1. Refer to raceway and wire schedule and one-line diagram for description of feeder identified by label shown on this report

2. Visual Inspection – Check when completed

3. Continuity Test – Check when completed

Page 202: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

City of Lacey Spring 2019 On-Site Lift Station Generators Division 16 - Electrical

E 16-34

Z:\Bothell\Data\LAC\118-086\4-Design\Specifications\16 Electrical.docx 4/16/2019 4:52 PM © 2019 RH2 Engineering, Inc.

16.95.4 Ground Electrode Resistance Test Report

Ground Electrode Resistance Test Report

PROJECT: OWNER:

Contractor Co. Name:

Tested by:

Phone Number:

Test Date:

Test Meter Type:

Test Distance-D:

Soil Conditions:

Measured Resistance:

DESCRIPTION OF TEST PROCEDURE, CONDITIONS, RESULTS:

Page 203: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

F PREVAILING

WAGES

Page 204: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 205: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

PREVAILING WAGE RATES The following wage rates are in effect for this project. State of Washington Department of Labor and Industries Washington State Prevailing Wage Rates For Public Works Contracts Thurston County Rates For All Trades Effective: May 10, 2019, including any correction notices issued by Labor and Industries prior to bid. Wage Rates and the Benefit Code Key may be found at: https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx Supplemental to State Wage Rates may be found at: http://www.wsdot.wa.gov/Design/ProjectDev/WageRates/default.htm A copy is also available for viewing at the City of Lacey Public Works Engineering office located at 420 College St SE, Lacey, WA 98503. If requested, a hard copy will be mailed to you.

Page 206: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 207: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

G CONSTRUCTION

STORMWATER

POLLUTION

PREVENTION PLAN

(SWPPP)

Page 208: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

THIS PAGE INTENTIONALLY LEFT BLANK

Page 209: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators5900 25th Ave SE, Lacey, WA (Lift Station 4)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

In public right of way.

approximately 1,000approximately 2,500

NANA

NA

In City of Lacey right of way.In City of Lacey right of way.

Jessica Wilson

TBD at Preconstruction Conference420 College Street SE (360) 491-5600

approximately 750

approximately 315

approximately 1,100

approximately 665

2/5/2019

Page 210: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station in City ofLacey right of way.

50

Drainage flow path would be towards the existing street catch basin west of the site, eventually leading east to Hicks Lake.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

Page 211: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 212: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

X

X

Page 213: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

X

X

XX

X

XX

X

Page 214: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X

Page 215: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators3607 Ryan St SE, Lacey, WA (Lift Station 5)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

In public right of way.

approximately 1,000approximately 1,000

NANA

NA

In City of Lacey right of way.In City of Lacey right of way.

Jessica Wilson

420 College Street SE (360) 491-5600

approximately 1,000

approximately 250

approximately 1,000

approximately 250

2/5/2019

TBD at Preconstruction Conference

Page 216: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station in City ofLacey right of way.

Drainage flow path would be along the street towards the northeast. Flow would likely end in forested low area, southwest of Hicks Lake.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

Page 217: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 218: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

Page 219: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

XX

X

X

X

X

Page 220: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

Page 221: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators590 College St SE, Lacey, WA (Lift Station 8)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

10.81 acres (470,884 sq ft)

approximately 650approximately 1,000

48,700NA

NA

11816320200City of Lacey

Jessica Wilson

420 College Street SE (360) 491-5600

approximately 314,000

NA

approximately 314,100

approximately 100

2/5/2019

TBD at Preconstruction Conference

Page 222: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station on Cityof Lacey property.

Would flow off site towards Abbey Way SE to the south, which leads to existing storm ponds to the east of this property.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

50

Page 223: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 224: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

X

X

X

Page 225: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

XX

X

XX

X

Page 226: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X

X

Page 227: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators

6480 Glen Ct SE, Lacey, WA (Lift Station 11)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

2.58 acres (112,385 sq ft)

approximately 250approximately 3,600

NANA

NA

31170200000

City of Lacey

Jessica Wilson

420 College Street SE (360) 491-5600

approximately 7,800

approximately 100

approximately 7,950

approximately 250

2/5/2019

TBD at Preconstruction Conference

Page 228: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station on Cityof Lacey property.

85

This site is the low point in the area. Drainage should not flow off theproperty.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

75

Page 229: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 230: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

X

Page 231: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

XX

X

XX

X

Page 232: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X

Page 233: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators480 College Street NE, Lacey, WA (Lift Station 17)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

31.12 acres and 20.18 acres

approximately 350approximately 7,100

approximately 21,700 and 0NA

NA

Easements on 11816210100 and 11816210000St. Placid Priory owns both parcels.

Jessica Wilson

500 College Street NE NA

approximately 95,800 and 400

approximately 0 and 30

approximately 95,800 and 570

approx. 0 and 200

2/5/2019

TBD at Preconstruction Conference

Page 234: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station in City ofLacey easements.

90 and 99

Drainage flow path would be towards College Creek which is east of the project site.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

1 and 1

Page 235: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 236: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

X

X

Page 237: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

X

XX

X

XX

X

Page 238: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X

Page 239: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators2201 Mayes Road SE, Lacey, WA (Lift Station 24)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

2.31 acres (100,624 sf)

approximately 500approximately 2,500

NANA

NA

Easement on 38510000010BMCH Washington LLC

Jessica Wilson

NA

approximately 10,500

approximately 500

approximately 10,500

approximately 500

2/5/2019

San Jose, CA

TBD at Preconstruction Conference

Page 240: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

X

X

X

X

X

X

XWork will be performed at existing lift station in City ofLacey easement.

85

Drainage flow path would be towards Long Lake east of the parcel.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

5

95

next to parcel

Page 241: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 242: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

XX

X

X

X

X

X

Page 243: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

X

XX

X

XX

X

Page 244: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X

Page 245: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-1

Appendix 3A – Construction Stormwater Pollution Prevention Plan (SWPPP) “Short Form”

All projects must comply with Core Requirement #2 to address erosion and sediment control, starting prior to initial land disturbance and continuing until final stabilization of the entire project site. This “Short Form” is for small projects that are not required to complete a full Construction Stormwater Pollution Prevention Plan (SWPPP)*.

Please submit a completed Short Form to the City of Lacey along with a basic site illustration showing existing and proposed site features including SWPPP BMPs. Refer to the City of Lacey 2016 Stormwater Design Manual for further information. Please type or print clearly.

Background Information

Project Name:

Project Address or Location:

Parcel Number:

Parcel Owner:

Address (if different from above): Phone:

Erosion Control Supervisor:

Company: Mobile Phone:

Form Completed By:

(printed name) (signature) (date)

Project Description:

Total Parcel Area: square feet (sq. ft.)

Total Project Area: square feet (sq. ft.)

Total Area of Land Disturbance: sq. ft. (must be <7,000 sq. ft.)*

Hard Surface Areas (e.g., roofs, driveways, sidewalks, pavement, etc.):

Existing Hard Surface = sq. ft. (total, before project)

Proposed Hard Surface = sq. ft. (total, after project)

Hard Surface to be Replaced = sq. ft. (total, after project)

Roof Area of Structures:

Existing Roof Area = sq. ft. (total, before project)

Proposed New Roof = sq. ft. (total, after project)

Roof to be Replaced = sq. ft. (total, after project)

Total of New + Replaced Hard Surfaces = sq. ft. (must be <2,000 sq. ft.)*

* Note: If project exceeds the size thresholds, you cannot use this Short Form and must complete a full SWPPP.

On-Site Lift Station Generators951 College Lane NE, Lacey, WA (Lift Station 27)

Install a backup generator and appurtenant electrical work to runthe lift station during power outages.

In public right of way and 6,534

approximately 1,000approximately 1,500

NANA

NA

In City of Lacey right of way and on easement of Parcel 11808440109.City of Lacey and 15th Avenue Duplex Homeowners Assoc

Jessica Wilson

420 College Street SE (360) 491-5600

right of way and approx. 1,500

right of way and approx. 60

approx. 600 and 1,500

approx. 600 and 60

2/5/2019

TBD at Preconstruction Conference

Page 246: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-2 Chapter 3 – Stormwater Submittals July 2016

What types of vegetation are present at the project site before the project begins?

Trees/Forest No Yes, covering approx. % of project site

Pasture/Brush No Yes, covering approx. % of project site

Lawn/Landscaping No Yes, covering approx. % of project site

Which of these conditions or features are present at the project site?

Slopes >20% No Yes, covering approx. % of project site

Creek or Stream No Yes, covering approx. % of project site

Wetlands No Yes, covering approx. % of project site

Buffer Zones No Yes, covering approx. % of project site

Lakes and Ponds No Yes, covering approx. % of project site

Springs and Seeps No Yes If yes, along frontage only? No Yes

Ditches or Swales No Yes If yes, along frontage only? No Yes

Storm Drain Grates No Yes If yes, along frontage only? No Yes

Existing Utilities No Yes If yes, along frontage only? No Yes

Easements No Yes If yes, along frontage only? No Yes

Describe locations of features:

Describe the drainage flow path downstream from the site to the nearest surface water:

Describe the estimated schedule of start dates and end dates for site construction activities:

Construction Activity Estimated Start Date Estimated End Date

Mark Clearing Limits

Establish Construction Access

Install Erosion and Sediment Controls

Demolition/Clearing/Grading

Utility Construction

Asphalt/Concrete Paving

House/Building/Structure Construction

Landscaping and Final Site Stabilization

Completion of Project Site Work (Removal of Sediment Controls)

X

X

X

X

X

X

XX

X

X

X

X

XWork will be performed at existing lift station in City ofLacey right of way and easement.

Drainage flow path would be generally east along 15th Ave NE towardsWoodland Creek.

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

May 2019 December 2019

November 2019 December 2019

December 2019 December 2019

ROW and 50

Page 247: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-3

Common Elements Applicable to Small Sites – Construction Stormwater Pollution Prevention Plan

All land-disturbing projects are required to consider all 13 elements identified in the City of Lacey 2016 Stormwater Design Manual (SDM), Chapter 5. However, small sites that use this Short Form should pay particular attention to the following five Minimum Erosion and Sediment Control Objectives:

1. Protection of Adjacent Properties, Drainage Systems, Surface Waters, and Buffers (Elements #1–#9 below) Protect adjacent off-site areas from surface water flows and sediment deposition by appropriate use of Best Management Practices (BMPs) such as silt fencing, straw wattles, mulching, inlet protection, etc. Apply BMPs prior to initial land-disturbance, and maintain until site work is finished and site is stabilized.

2. Prevent Soil Track-out Onto Streets (Element #2 below) Stabilize access route with quarry spalls or crushed rock (or pavement) to minimize the tracking of soils and debris onto public roads. Limit vehicle access to work site to one route.

3. Stabilization of Cleared Areas (Elements #5, #6, and #8 below) Stabilize all exposed soils through application of BMPs to prevent erosion and movement of sediments. At all times, contractor should have sufficient labor, materials, and equipment on-site to apply BMPs and stabilize all exposed soils within 12 hours as site and weather conditions dictate. Seasonal restrictions under Element #5 below apply to all sites. Permanently stabilize site at project completion.

4. Apply and Maintain BMPs (Elements #11 and #12 below) Control any adverse effects due to site work with appropriate erosion and sediment control BMPs, and regularly inspect and maintain all erosion and sediment control BMPs to ensure continued performance of their intended functions. Remove temporary BMPs at project completion.

5. Protect Low Impact Development BMPs (Element #13 below) Protect LID BMPS from soil compaction and sedimentation through careful site planning, equipment operation, erosion and sediment control, and site restoration.

Page 248: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-4 Chapter 3 – Stormwater Submittals July 2016

Checklist: 13 Elements of Construction Site Erosion and Sediment Control

Note: Each of the 13 Elements must be considered for applicability to your project. Review each element and identify all BMPs that are likely to be implemented on your site. Note the City of Lacey 2016 Stormwater Design Manual (SDM) Chapter 5 includes supplemental information for each element that must also be considered for your site. See Chapter 5 for more information on these and other construction-phase BMPs. The 2016 SDM is available online at <www.ci.lacey.wa.us/city-government/reports-plans/library>.

Required Elements

General Requirements

Best Management Practices (BMPs) (check all that are likely to be implemented)

Element #1:

Clearing Limits

Prior to beginning land-disturbing activities, mark clearing limits and delineate sensitive areas and their buffers with high-visibility fencing.

BMP C101: Preserve Natural Vegetation

BMP C102: Buffer Zones

BMP C103: High-Visibility Plastic or Metal Fence

BMP C233: Silt Fence

Element #2:

Construction Access

Establish stabilized access to project site (quarry spalls, etc.). Clean the public road if sediment is tracked off site.

BMP C105: Stabilized Construction Entrance

BMP C106: Wheel Wash

BMP C107: Construction Road/ Parking Area Stabilization

Element #3:

Control Flow Rates

Prevent erosion and protect off-site and downstream areas by controlling the volume, velocity and peak flow rate of site runoff.

BMP C203: Water Bars

BMP C207: Check Dams

BMP C209: Outlet Protection

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

Element #4:

Sediment Controls

Install sediment controls to prevent sediment movement and to keep sediment from leaving site.

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

BMP C235: Wattles

BMP C240: Sediment Trap

BMP C241: Temp. Sediment Pond

BMP C250: Construction Stormwater Chemical Treatment

BMP C251: Construction Stormwater Filtration

Element #5:

Stabilize Soils

All unworked and exposed soils shall be stabilized to prevent erosion. During the “wet season” (October 1 through April 30) no soils shall remain exposed and unworked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and unworked for more than 7 days.

BMP C120: Temporary and Permanent Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C123: Plastic Covering

BMP C124: Sodding

BMP C125: Topsoiling/ Composting

BMP C126: Polyacrylamide (PAM) for Soil Erosion Protection

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C140: Dust Control

X

X

X

X

Page 249: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

July 2016 Chapter 3 – Stormwater Submittals 3A-5

Element #6:

Protect Slopes

Design and construct cut and

fill slopes to minimize erosion.

BMP C120: Temporary and Permanent

Seeding

BMP C121: Mulching

BMP C122: Nets and Blankets

BMP C130: Surface Roughening

BMP C131: Gradient Terraces

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C203: Water Bars

BMP C204: Pipe Slope Drains

BMP C205: Subsurface Drains

BMP C206: Level Spreader

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-encased Check Dam)

Element #7:

Protect Drain

Inlets

Protect conveyance system

from sediment by filtering or

treating stormwater prior to

flow entering inlets.

BMP C220: Storm Drain Inlet Protection Note:

Never put anything other than

stormwater into a storm drain.

“Only rain down the drain.”

Element #8:

Stabilize

Channels and

Outlets

All conveyance channels and

outlets shall be constructed

and stabilized to prevent

erosion.

BMP C202: Channel Lining

BMP C122: Nets and Blankets

BMP C207: Check Dams

BMP C209: Outlet Protection

Element #9:

Control

Pollutants

Handle, store and dispose of

concrete washout and

construction debris in closed

container or by removal from

site so it does not contaminate

stormwater. Apply spill

prevention and cleanup to

vehicle and equipment

activities.

BMP C151: Concrete Handling

BMP C152: Sawcutting and Surfacing Pollution

Prevention

BMP C153: Material Delivery, Storage and

Containment

BMP C154: Concrete Washout Area

BMP C250: Construction Stormwater Chemical

Treatment

BMP C251: Construction Stormwater Filtration

Element #10:

Control

De-Watering

Manage dewatering water to

prevent sediment discharge

from site. Manage turbid water

separately from stormwater.

BMP C203: Water Bars

BMP C206: Level Spreaders

BMP C236: Vegetative Filtration

Element #11:

Maintain BMPs

Inspect, maintain and repair

BMPs as needed to keep them

in fully functional condition.

BMP C150: Materials On Hand

Element #12:

Manage the

Project

Phase project to prevent soil

erosion and transport. Avoid

soil disturbance from October 1

through April 30. CESCL to

inspect and monitor BMPs on

sites over 1 acre in area.

BMP C150: Materials On Hand

BMP C162: Scheduling

X

X

X

XX

X

XX

X

Page 250: On-Site Lift Station Generators · B2 1 LS 723-510 Bypass Pumping LUMP SUM B3 38 SY 814-510 Cement Conc. Sidewalk B4 1 LS 850-802 Standby Generator LUMP SUM Tax Rate (%) : 9.30Tax:

CITY OF LACEY 2016 STORMWATER DESIGN MANUAL

3A-6 Chapter 3 – Stormwater Submittals July 2016

Element #13:

Protect Low

Impact

Development

(LID) BMPs

Protect all LID BMPs from

sedimentation and compaction

through preventative

measures, as well as

installation and maintenance of

construction SWPPP BMPs on

portions of the site that drain to

the LID BMPs.

BMP C102: Buffer Zone

BMP C103: High Visibility Fence

BMP C200: Interceptor Dike and Swale

BMP C201: Grass-Lined Channels

BMP C207: Check Dams

BMP C208: Triangular Silt Dike (TSD)

(Geotextile-Encased Check Dam)

BMP C231: Brush Barrier

BMP C233: Silt Fence

BMP C234: Vegetated Strip

►Submit completed form to the City of Lacey with a basic site illustration showing existing and proposed site features including SWPPP BMPs, property boundaries, north arrow, and adjacent streets.

Notes:

See Lacey Contract No. PW 2019-01, Lacey Drawing No. D-19-01 for existing andfuture site features, including SWPPP BMPs, property boundaries, north arrow, andadjacent streets.

X