Introduction
• Richard Wheeler – Resident Engineer
• Client Monitoring Team member
• Contract meets Employer’s Requirements
10 Feb 2015 www.watermangroup.com 3
Construction • Concrete box for substructure • Watertight with vapour membrane to provide
Grade Two and above standard • Concrete core and shear walls providing
stability. • Steel frame providing office space from First
to 13th floor level • Concrete on profiled metal decking above
ground level • Intumescent paint for fire protection
10 Feb 2015 www.watermangroup.com 4
Accuracy
• Core verticality within 25mm
• Steel frame tolerances “half National Standard”
• Permitted deviations set out in Tolerances and Deflections Document
10 Feb 2015 www.watermangroup.com 5
Quality
• The Referral Culture – if we have a problem we ask the people we know
• Skanska, Severfield (UK) Ltd and Waterman
• ISO 9001 certification and auditing
• Regular on site and off site inspections
• Daily dialogue with suppliers and subcontractors
• Taking ownership as a project team
10 Feb 2015 www.watermangroup.com 6
Practice
• As-built records - EDM (Electronic Distance Measurement)
• Concrete material sampling and testing • Quality Control - Mill certificates • Quality Assurance - Welding procedures