ootagawa bridge 1. overview - jsce · 2015-12-24 · ootagawa bridge 1. overview the ootagawa...

6
- 1 - Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located in the lowest reaches of the Ootagawa discharge channel running through the west area of Hiroshima city. The bridge started operations as part of the city’s Hiroshima-minami Road on March 26, 2014 (Photo 1). The basic design of the bridge was selected as the best in the international competition hosted by the Hiroshima Municipal Government (13 entries from Japan, 2 from overseas). Viewing the bridge from upstream, the design creates a harmonious blend of the two low-rising steel arches and the landscape around the Seto Inland Sea, including Itsukushima Island (Photo 2). The sidewalk is completely separated from the dedicated roadway and is linear with varying sections, each of which has supporting structures according to their positional relationships with the roadway. The superstructure of the bridge was constructed by extending the girders in sequence, making use of the arches’ main structures. The main girders were extended while being suspended by using vertical members from the arches’ main structures, which were constructed simultaneously in the middle of the extension construction. This resulted in a low girder height-to-span ratio. Photo 1. Ootagawa Bridge after completion

Upload: others

Post on 20-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 1 -

Ootagawa Bridge

1. Overview

The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge

that is located in the lowest reaches of the Ootagawa discharge channel running through

the west area of Hiroshima city. The bridge started operations as part of the city’s

Hiroshima-minami Road on March 26, 2014 (Photo 1).

The basic design of the bridge was selected as the best in the international competition

hosted by the Hiroshima Municipal Government (13 entries from Japan, 2 from

overseas). Viewing the bridge from upstream, the design creates a harmonious blend of

the two low-rising steel arches and the landscape around the Seto Inland Sea, including

Itsukushima Island (Photo 2). The sidewalk is completely separated from the dedicated

roadway and is linear with varying sections, each of which has supporting structures

according to their positional relationships with the roadway.

The superstructure of the bridge was constructed by extending the girders in sequence,

making use of the arches’ main structures. The main girders were extended while being

suspended by using vertical members from the arches’ main structures, which were

constructed simultaneously in the middle of the extension construction. This resulted in a

low girder height-to-span ratio.

Photo 1. Ootagawa Bridge after completion

Page 2: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 2 -

Photo 2. Double arches with Itsukushima Island in the background

Structural overview

Structural system: Six-span continuous steel and concrete composite bridge

Foundation system: Steel-pipe sheet pile foundation, steel-pipe piles, and

cast-in-place piles

Bridge length: 412 m; maximum span 116 m

Span: 40.0 m + 46.5 m + 47.0 m + 2 x 116.0 m + 46.5 m

Main girder system: One-segment and two-segment PC box girder; girder

height 2.7 m

Total width: Inbound lane: 9.75-16.235 m

Outbound lane: 9.75-12.585 m

Client: Hiroshima Municipal Government (Streetscape Section

of Road Department of Road Traffic Bureau)

Designer: Eight-Japan Engineering Consultants Inc.

Contractor: Shimizu Corporation

Work period: September 28, 2011, to December 27, 2013

2. Characteristics of the bridge

(1) Special structure of steel arch PC composite bridge

Generally, a bridge with a continuous arch structure and traffic lanes under the arch is

not easy to design. The continuous arch structure of this bridge was achieved by

balancing the horizontal reaction generated in each arch’s main structure with the tensile

force of the external cables installed in the PC (prestressed concrete) box girders.

Moreover, the rigidity of the main girders at the fulcrums was increased by means of a

finback structure with internal cables installed at the attachment areas in the arches’

main structures, which mitigated the negative moment generated at the rigidly

connected fulcrums.

Page 3: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 3 -

The PC continuous-moment-frame box-girder bridge is reinforced by the arches’ steel

main structures. The loads are sustained by both the main girders and the arches’ main

structures, which creates a slender girder shape (girder height-to-span ratio: 1/43) with a

limited girder height. The arches’ main structures are located in the median strip area

between the inbound and outbound lanes. The arches’ main structures were constructed

simultaneously in the middle stage of the extension construction of the main girders.

Then, while the suspension cables from the main structures supported the main girders,

the main girders were extended in sequence and constructed. The suspension cables

were tensioned and fixed to the vertical suspension cross girders that connected the

inbound and outbound lanes (Figures 1 and 2).

11600047000 11600046500

8800

18200

15000

12324H.W.L TP+3.101

40000

空域制限M

17800

28000

29500

29000

26500

10800

10000 7500

46500

6径間連続鋼・コンクリート複合アーチ橋 L=412000

5400

32500

P6

場所打ち杭φ1200,n=20本鋼管矢板基礎

φ1200,n=53本鋼管矢板基礎φ1200,n=51本

鋼管矢板基礎φ1200,n=48本

鋼管矢板基礎

n=45本

鋼管杭基礎

n=24本

13000

32000

添架歩道橋

固定支保工部 L=92500 張出施工部 L=319500

φ1000 φ1200

E

P5

E

P4

R

P3

R

P2

R

P1

E

A1

添架歩道 桁下区間 添架歩道 移行区間 添架歩道 並行区間

観音井口線

Profile

Plan

Figure 1. General view of the bridge

31462500 5650 1350 1350 5650 2500

2700

下 り 線 上 り 線22646

615 8520 6153146

615 8520 615

2500

500

500

1100

2600

1600

充填コンクリート

角型鋼管

1S28.6床版横締めケーブル1S28.6

横桁横締めケーブル

内ケーブル12S15.2外ケーブル19S15.2

4000

□300x300

吊ケーブル

桁下区間

• @ • @

σck=80N/mm2

鋼製ブラケット

移行区間

並行区間

添架歩道

アーチ主構

SPWCφ7x109

Arch’s main structureSquare steel pipe

Concrete infill

Suspension cable

Attached sidewalkOutbound lane Inbound lane

Parallel section

Transfer section

Transversely-tensioned cable onto floor slab

Transversely-tensioned cable onto cross girder

Internal cable 12S15.2

External cable 19S15.2

Steel bracket

Section under girder

Figure 2. Typical section

(2) Sidewalk designed for user convenience and to provide a view of the Seto Inland Sea

116000

46500 47000

46500

11600040000

6径間連続鋼・

PU68687

20269

8687

26060

20744

7500

10135

20269

10000

10000

10000

10000

30800

5400

11582

20270

P2

P1A1

P3P4

P5

PD6

L=412000

コンクリート複合アーチ橋

桁下区間 移行区間

並行区間

添架歩道橋

添架歩道 添架歩道

添架歩道 右

岸上流

下流

Six-span continuous steel and concrete composite arch bridge L=412000

Fixed shoring section L=92500 Extending construction section L=319500

Attached sidewalk Section under girder Attached sidewalk Transfer section Attached sidewalk Parallel section

Kanon-inokuchi line

Attached pedestrian bridge

Steel-pipe pile foundation ø1000 n=24

Steel-pipe sheet pile foundation ø1200 n=45

Steel-pipe sheet pile foundation ø1200 n=51

Steel-pipe sheet pile foundation ø1200 n=48

Steel-pipe sheet pile foundation ø1200 n=53

Cast-in-place piles ø1200 n=20

Airspace limit

a

Attached sidewalk Parallel section

Six-span continuous steel and concrete composite arch bridge L=412000

Attached sidewalk Transfer section Attached sidewalk Section under girder

Right bank

Downstream

Upstream

Attached pedestrian bridge Left bank

Page 4: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 4 -

Completely separated from the roadway dedicated to vehicle traffic, the sidewalk is

connected to the bank road on both banks to provide easier accessibility and a view of

the Seto Inland Sea. The sidewalk has a planar linear shape that allows pedestrians to

travel from the connection point on the right bank (upstream side of the girder adjacent

to the residential area), walk through the space under the girder in the roadway section,

and exit on the downstream side and view a splendid panorama of the sea. The

longitudinal gradient is a gentle 2.5% or less. Moreover, the sidewalk’s supporting

structures are designed to correspond to its varying sections: Steel brackets support the

parallel section with the roadway, while suspension brackets support the transfer

section. The section under the girder is supported by suspension (Photo 3).

Photo 3. Layout of the sidewalk and sequence of sidewalk sections from the right bank to

the left bank

(3) Construction of brackish water area

The non-flooding period of the Ootagawa discharge channel falls between October 26

and June 10. The work generally was carried out within this period, with temporary

facilities installed on the river banks. All six substructures A1 to P5 were constructed on

the river banks. The bridge construction site was 200 m from the estuary, and the work

proceeded by taking into consideration the maximum tidal difference of 3 m in the Seto

Island Sea, which is noted for its great tidal variations.

(4) Simultaneous construction of the arch’s two main structures on a barge

The water at the construction point was up to 5 m deep, which made it difficult to use

large crane ships to construct the main structures of the two arches. Instead, both

structures were constructed simultaneously on barges equipped with lifting jacks to

accommodate the ebb and flow of the tide. The work schedule for the main girder

extension construction was coordinated with the work schedules for the arches’ main

structures, main girders, and construction equipment. The sea tide conditions restricted

Section under girder Transfer section Parallel section

Page 5: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 5 -

the days and times of work, which necessitated an elaborately developed construction

plans (Photo 4).

(5) Concrete infill for arch’s main structure

The main structure of each arch is a truss frame (braced rib arch main structure)

composed of upper and lower cord members with a steel box section and square

steel-pipe diagonal members arranged in a V shape. The interior of the box section (cell)

needed to be filled with self-compacting high-strength and high-durability concrete (80

N/mm2) to improve the buckling resistance and fatigue characteristics; however, due to

constraints on the on-site operations and the site conditions, the filling operation

required the concrete to be transported pneumatically over a distance of 300 m. Because

of this, before the work started, a test using a life-size mockup was conducted to find a

concrete composition that could be pneumatically transported and could provide the

necessary infilling performance.

Photo 4. Simultaneous construction of the arch’s main structures using a barge

(6) Super-short work schedule

The 412 m bridge was constructed in a very short period of 27 months, including the

superstructure and substructure and the inbound and outbound lanes. In addition to the

constraints imposed by the river and the special structure of the main girders, the project

involved many special construction methods, such as installing bracket materials in the

attached sidewalk, using barges to simultaneously construct the two arches, filling the

arches’ main structures with concrete, connecting the inbound and outbound lanes, and

supporting the main girders from the arches’ main structures. Thus, the schedule was

very challenging.

3. Conclusion

The project, including additional bridge surfacing work, was completed in March 2014

and the bridge started operations on March 23. We hope that the bridge will contribute to

Page 6: Ootagawa Bridge 1. Overview - JSCE · 2015-12-24 · Ootagawa Bridge 1. Overview The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge that is located

- 6 -

further economic growth in the Hiroshima costal area and mitigate traffic congestion in

the surrounding area. We also hope that the bridge will be loved by the local residents and

visitors for a long time.

Lastly, we would like to express our deep gratitude to those concerned in the local area

and inside and outside the companies for their cooperation and assistance.

Photo 5. Ootagawa Bridge after completion