ootagawa bridge 1. overview - jsce · 2015-12-24 · ootagawa bridge 1. overview the ootagawa...
TRANSCRIPT
- 1 -
Ootagawa Bridge
1. Overview
The Ootagawa Bridge is a six-span continuous steel and concrete composite arch bridge
that is located in the lowest reaches of the Ootagawa discharge channel running through
the west area of Hiroshima city. The bridge started operations as part of the city’s
Hiroshima-minami Road on March 26, 2014 (Photo 1).
The basic design of the bridge was selected as the best in the international competition
hosted by the Hiroshima Municipal Government (13 entries from Japan, 2 from
overseas). Viewing the bridge from upstream, the design creates a harmonious blend of
the two low-rising steel arches and the landscape around the Seto Inland Sea, including
Itsukushima Island (Photo 2). The sidewalk is completely separated from the dedicated
roadway and is linear with varying sections, each of which has supporting structures
according to their positional relationships with the roadway.
The superstructure of the bridge was constructed by extending the girders in sequence,
making use of the arches’ main structures. The main girders were extended while being
suspended by using vertical members from the arches’ main structures, which were
constructed simultaneously in the middle of the extension construction. This resulted in a
low girder height-to-span ratio.
Photo 1. Ootagawa Bridge after completion
- 2 -
Photo 2. Double arches with Itsukushima Island in the background
Structural overview
Structural system: Six-span continuous steel and concrete composite bridge
Foundation system: Steel-pipe sheet pile foundation, steel-pipe piles, and
cast-in-place piles
Bridge length: 412 m; maximum span 116 m
Span: 40.0 m + 46.5 m + 47.0 m + 2 x 116.0 m + 46.5 m
Main girder system: One-segment and two-segment PC box girder; girder
height 2.7 m
Total width: Inbound lane: 9.75-16.235 m
Outbound lane: 9.75-12.585 m
Client: Hiroshima Municipal Government (Streetscape Section
of Road Department of Road Traffic Bureau)
Designer: Eight-Japan Engineering Consultants Inc.
Contractor: Shimizu Corporation
Work period: September 28, 2011, to December 27, 2013
2. Characteristics of the bridge
(1) Special structure of steel arch PC composite bridge
Generally, a bridge with a continuous arch structure and traffic lanes under the arch is
not easy to design. The continuous arch structure of this bridge was achieved by
balancing the horizontal reaction generated in each arch’s main structure with the tensile
force of the external cables installed in the PC (prestressed concrete) box girders.
Moreover, the rigidity of the main girders at the fulcrums was increased by means of a
finback structure with internal cables installed at the attachment areas in the arches’
main structures, which mitigated the negative moment generated at the rigidly
connected fulcrums.
- 3 -
The PC continuous-moment-frame box-girder bridge is reinforced by the arches’ steel
main structures. The loads are sustained by both the main girders and the arches’ main
structures, which creates a slender girder shape (girder height-to-span ratio: 1/43) with a
limited girder height. The arches’ main structures are located in the median strip area
between the inbound and outbound lanes. The arches’ main structures were constructed
simultaneously in the middle stage of the extension construction of the main girders.
Then, while the suspension cables from the main structures supported the main girders,
the main girders were extended in sequence and constructed. The suspension cables
were tensioned and fixed to the vertical suspension cross girders that connected the
inbound and outbound lanes (Figures 1 and 2).
11600047000 11600046500
8800
18200
15000
12324H.W.L TP+3.101
40000
空域制限M
17800
28000
29500
29000
26500
10800
10000 7500
46500
6径間連続鋼・コンクリート複合アーチ橋 L=412000
5400
32500
P6
場所打ち杭φ1200,n=20本鋼管矢板基礎
φ1200,n=53本鋼管矢板基礎φ1200,n=51本
鋼管矢板基礎φ1200,n=48本
鋼管矢板基礎
n=45本
鋼管杭基礎
n=24本
13000
32000
添架歩道橋
固定支保工部 L=92500 張出施工部 L=319500
φ1000 φ1200
E
P5
E
P4
R
P3
R
P2
R
P1
E
A1
添架歩道 桁下区間 添架歩道 移行区間 添架歩道 並行区間
観音井口線
Profile
Plan
Figure 1. General view of the bridge
31462500 5650 1350 1350 5650 2500
2700
下 り 線 上 り 線22646
615 8520 6153146
615 8520 615
2500
500
500
1100
2600
1600
充填コンクリート
角型鋼管
1S28.6床版横締めケーブル1S28.6
横桁横締めケーブル
内ケーブル12S15.2外ケーブル19S15.2
4000
□300x300
吊ケーブル
桁下区間
• @ • @
σck=80N/mm2
鋼製ブラケット
移行区間
並行区間
添架歩道
アーチ主構
SPWCφ7x109
Arch’s main structureSquare steel pipe
Concrete infill
Suspension cable
Attached sidewalkOutbound lane Inbound lane
Parallel section
Transfer section
Transversely-tensioned cable onto floor slab
Transversely-tensioned cable onto cross girder
Internal cable 12S15.2
External cable 19S15.2
Steel bracket
Section under girder
Figure 2. Typical section
(2) Sidewalk designed for user convenience and to provide a view of the Seto Inland Sea
116000
46500 47000
46500
11600040000
6径間連続鋼・
PU68687
20269
8687
26060
20744
7500
10135
20269
10000
10000
10000
10000
30800
5400
11582
20270
P2
P1A1
P3P4
P5
PD6
L=412000
コンクリート複合アーチ橋
桁下区間 移行区間
並行区間
添架歩道橋
添架歩道 添架歩道
添架歩道 右
岸
左
岸上流
下流
Six-span continuous steel and concrete composite arch bridge L=412000
Fixed shoring section L=92500 Extending construction section L=319500
Attached sidewalk Section under girder Attached sidewalk Transfer section Attached sidewalk Parallel section
Kanon-inokuchi line
Attached pedestrian bridge
Steel-pipe pile foundation ø1000 n=24
Steel-pipe sheet pile foundation ø1200 n=45
Steel-pipe sheet pile foundation ø1200 n=51
Steel-pipe sheet pile foundation ø1200 n=48
Steel-pipe sheet pile foundation ø1200 n=53
Cast-in-place piles ø1200 n=20
Airspace limit
a
Attached sidewalk Parallel section
Six-span continuous steel and concrete composite arch bridge L=412000
Attached sidewalk Transfer section Attached sidewalk Section under girder
Right bank
Downstream
Upstream
Attached pedestrian bridge Left bank
- 4 -
Completely separated from the roadway dedicated to vehicle traffic, the sidewalk is
connected to the bank road on both banks to provide easier accessibility and a view of
the Seto Inland Sea. The sidewalk has a planar linear shape that allows pedestrians to
travel from the connection point on the right bank (upstream side of the girder adjacent
to the residential area), walk through the space under the girder in the roadway section,
and exit on the downstream side and view a splendid panorama of the sea. The
longitudinal gradient is a gentle 2.5% or less. Moreover, the sidewalk’s supporting
structures are designed to correspond to its varying sections: Steel brackets support the
parallel section with the roadway, while suspension brackets support the transfer
section. The section under the girder is supported by suspension (Photo 3).
Photo 3. Layout of the sidewalk and sequence of sidewalk sections from the right bank to
the left bank
(3) Construction of brackish water area
The non-flooding period of the Ootagawa discharge channel falls between October 26
and June 10. The work generally was carried out within this period, with temporary
facilities installed on the river banks. All six substructures A1 to P5 were constructed on
the river banks. The bridge construction site was 200 m from the estuary, and the work
proceeded by taking into consideration the maximum tidal difference of 3 m in the Seto
Island Sea, which is noted for its great tidal variations.
(4) Simultaneous construction of the arch’s two main structures on a barge
The water at the construction point was up to 5 m deep, which made it difficult to use
large crane ships to construct the main structures of the two arches. Instead, both
structures were constructed simultaneously on barges equipped with lifting jacks to
accommodate the ebb and flow of the tide. The work schedule for the main girder
extension construction was coordinated with the work schedules for the arches’ main
structures, main girders, and construction equipment. The sea tide conditions restricted
Section under girder Transfer section Parallel section
- 5 -
the days and times of work, which necessitated an elaborately developed construction
plans (Photo 4).
(5) Concrete infill for arch’s main structure
The main structure of each arch is a truss frame (braced rib arch main structure)
composed of upper and lower cord members with a steel box section and square
steel-pipe diagonal members arranged in a V shape. The interior of the box section (cell)
needed to be filled with self-compacting high-strength and high-durability concrete (80
N/mm2) to improve the buckling resistance and fatigue characteristics; however, due to
constraints on the on-site operations and the site conditions, the filling operation
required the concrete to be transported pneumatically over a distance of 300 m. Because
of this, before the work started, a test using a life-size mockup was conducted to find a
concrete composition that could be pneumatically transported and could provide the
necessary infilling performance.
Photo 4. Simultaneous construction of the arch’s main structures using a barge
(6) Super-short work schedule
The 412 m bridge was constructed in a very short period of 27 months, including the
superstructure and substructure and the inbound and outbound lanes. In addition to the
constraints imposed by the river and the special structure of the main girders, the project
involved many special construction methods, such as installing bracket materials in the
attached sidewalk, using barges to simultaneously construct the two arches, filling the
arches’ main structures with concrete, connecting the inbound and outbound lanes, and
supporting the main girders from the arches’ main structures. Thus, the schedule was
very challenging.
3. Conclusion
The project, including additional bridge surfacing work, was completed in March 2014
and the bridge started operations on March 23. We hope that the bridge will contribute to
- 6 -
further economic growth in the Hiroshima costal area and mitigate traffic congestion in
the surrounding area. We also hope that the bridge will be loved by the local residents and
visitors for a long time.
Lastly, we would like to express our deep gratitude to those concerned in the local area
and inside and outside the companies for their cooperation and assistance.
Photo 5. Ootagawa Bridge after completion