OpenERP Project Methodology
SAMUEL MART INS
PROJECT AND SERV ICES D IRECTOR
S AM@OP EN ER P . C OM
OpenERP project STEPS
Pre-Sales Demo TrainingPre-analysis
offer
GAP-analysis POC GAP-analysis Estimation Planning
Detailed analysis
Functional analysis
Technical analysis
OpenERP Enterprise
DevelopmentsDevelopments & Unit tests
Integration tests
Client testing User trainingUser
Acceptance testing
DeploymentLive
environment release
Data migration
Go liveWarranty period support
Post Deployment support
L1 support L2 support
OpenERP Enterprise
Project – phase by phase
� The purpose of the Gap Analysis is to
� Evaluate the project scope
GAP-analysis POC GAP-analysis Estimation Planning
Evaluate the project scope
� Determine the customization level which will be required
� Assess the investments required
� Plan the project
� Organise the project governance
Project – phase by phase
HOW?Step 1: Company Mind Maps – Interviews:
GAP-analysis POC GAP-analysis Estimation Planning
Project – phase by phase
HOW?Step 2: Key Users Mind Maps – Interviews:
GAP-analysis POC GAP-analysis Estimation Planning
Project – phase by phase
HOW?Step 3: Define the GAPS and Estimates:
GAP-analysis POC GAP-analysis Estimation Planning
List the GAP’s
Weight the GAP’s :
• Complexity• Analysis• Development
Project – phase by phase
HOW?Step 3: Define the GAPS and Estimates:
GAP-analysis POC GAP-analysis Estimation Planning
Estimation based on:Estimation based on:
• Project Management• Analysis• Development• Testing•Migration• Deployment• Support
Project – phase by phase
HOW?Step 4: Plan the Project
GAP-analysis POC GAP-analysis Estimation Planning
Plan the project trying to phase development in small sprints:
• short analysis/development time => Quick in customer’s hand
=> Be AGILE
Project – phase by phase
� The deliverables of the Gap Analysis are :� Gap Analysis reporting (Needs, Scope, Risks, GAP’s)
GAP-analysis POC GAP-analysis Estimation Planning
� Gap Analysis reporting (Needs, Scope, Risks, GAP’s)
� Gap Analysis Matrix
� Project Road map
� Financial estimate
� Agreement on validation process and project
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� The Analysis purpose is to� Design the solution� Validate the solution� Validate the solution� Finalise the development estimationfrom both a functional and technical point of view
� The Development purpose is to� Implement the solution, � Test the solution � Validate the solution with Key Users
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� BE AGILE
Short Project Cycles:
• Increase Project visibility with client(demo’s, user tests,...)
• Keep control of requirements (quicktechnical and functional validation)
• Increase quality (early testing allowsyou to identify issues early and solvethem)
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� How to analyse:
� Use the Detailed analysis template to define:
� Process description and workflows� Process description and workflows
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� Views and wizards using mockups
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� Access rights
Objects User type 1 User type 2 User Type 3
Rights Rights Rights
“Rights” = access rights.“C” = create : user can create a new value for the object,”R” = read : user can read/access the object,“U” = update : user can modify an existing object,“D” = delete : user can delete an existing object,“No”: user has no access to the object.
Rights Rights Rights
Name CRUD C R
Address,… No D U
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� Change requests
Change Request Flow
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� The deliverables of the Analysis are :� Detailed description of
� Processes and Activities � Processes and Activities
� Views, Workflows and Wizards
� Access rights
� Reports and Data Model
� Detailed interface description
� Infrastructure setup
� High level Test Plan
� Review workload estimates and planning
Project – phase by phase
Detailed analysis
Functional analysis
Technical analysis
DevelopmentsDevelopments & Unit tests
Integration tests
� The deliverables of the Developments are :� Software configuration� Software configuration
� Custom modules
� Interfaces
� Data Import tools
� Test plan
Project – phase by phase
� The Client Testing purpose is to
� Train the client End Users
Client testing User trainingUser
Acceptance testing
� Train the client End Users� Handover the application to the client� Allow the client to perform end to end testing including:
� Application� Interfaces� Access rights� Outputs� Reports
� Put in Place the support tools (Bugs shared view, governance,...)
Project – phase by phase
� Bugs shared view
Client testing User trainingUser
Acceptance testing
Project – phase by phase
� The deliverables of the Client Testing (UAT) are :
Client testing User trainingUser
Acceptance testing
� Training material
� User guides
� Full test report
� Approval for production deployment
Project – phase by phase
� The (post) Deployment purpose is
�Deliver the solution into the production server
DeploymentLive
environment release
Data migration
Go liveWarranty period support
Post Deployment support
L1 support L2 support
�Deliver the solution into the production server
�Migrate the data if any
� Launch the production activities
� Support users (Question / bug fixing,...)