Operational Excellence in Effort ReportingConference Call: March 14, 2012
Vision Statement:Implement a compliant, streamlined, electronic effort reporting process by June 2012 that reduces administrative burden.
Agenda
Topic
Project Update Donna Kiley, Anne Connolly
Campus Feedback: Phase 1 System Testing Anne Connolly
IFR/Cost Sharing Department Anne Connolly
Campus feedback Campus team
System Testing Timeline Anne Connolly
2
Project Update
3
Committed Effort Annual Operations Managers/Vice Presidents for Research
Meeting: Thursday, March 29 Paul Parker providing project update
Phase 1 System Testing objectives: Learning ecrt core functionality Validating first iteration of data Assuring core system is accurate Identifying campus effort coordinators and proxies
Feedback Review of issues sent by campus team Feedback from campus team
Campus Feedback: Phase 1 System Testing
4
Issues Performance
Timeliness of work list loading in the effort coordinator role Payroll report loading slowly or not at all
Internet Explorer compatibility Training Data
Campus-specific Global
Campus Feedback: Phase 1 System Testing
5
Issue Cause SolutionEffort coordinator work list takes too long to load if it loads at all
Primary effort coordinator was associated to every effort statement in the TEST environment. The large number of statements slowed down or prevented the work list from loading. This list refreshes each time a user accesses ecrt.
In some cases Huron had to add a right to the campus set up.
TEST environment was updated so that the Effort Tasks tab populates first.
A new right will also be added to restrict the number of statements that will appear on that tab.
Payroll Report A software upgrade to the TEST environment causes the Payroll Report to load slowly or not at all.
Payroll Report previously worked. Huron is working on the issue.
Effort Tasks tab not loading
This is an issue with the Attachment functionality. It does not create a processing task for the effort coordinator when it should.
Huron is fixing this issue.
Performance Issues
Campus Feedback: Phase 1 System Testing
6
Issue Cause SolutionPop-up calendars not populating start and end dates
The version of Java used by ecrt causes compatibility issues with Internet Explorer.
Huron recommends using the Mozilla Firefox browser. Campus users should have this installed on their computers.
If Internet Explorer must be used it is best to run it in Compatibility View:
•Click the Compatibility View icon on the address bar located at the top of your browser window
•If this icon is not visible go to Tools > Compatibility View and check the box next to Display all websites in Compatibility View
Tasks not displaying on the Effort Tasks tab
Items not displaying correctly on the page until the tester rolled over the item with his or her mouse
Internet Explorer Compatibility
Campus Feedback: Phase 1 System Testing
7
The following will be included in the training plan Definition of Base: Will be included in a glossary of terms Searching for a specific person’s effort statement without using the
Department Dashboard Primary effort coordinator role and tasks
Training
Issue Cause SolutionNo data message would appear after entering the first three letters of an individual’s last name (campus-specific issue)
A right was missing from the campus set up.
Huron added the missing right.
Global Issues
Cannot toggle from $ View to % View in the Cost Share Report
The cost sharing data is uploaded from Oracle to ecrt in dollar amounts so we cannot display percentages in the Cost Share Report.
Cost sharing percentages may be viewed on the effort statement.
Huron will update our set up to remove the option to toggle to percentages.
SPES Report percentages do not match Oracle
This results when pay periods cross periods of performance.
We need to continue our “Dates Matter” discussion to determine if we should update our effort reporting periods.
IFR/Cost sharing department This is the current department for SUNY monthly employees because it is required by Oracle for SUNY payroll processing
Discussion topic
RF payroll suspense items The TEST environment is set up to display these items even if the charges were removed from the suspense account
This will be excluded from the ecrt production environment if these charges net to zero.
Campus Feedback: Phase 1 System Testing
8
Data
IFR/Cost Sharing Department
9
SUNY-monthly employees are included in this department during the academic year when their salary charges are reimbursed to SUNY via the income fund reimbursable process Required Oracle set up for SUNY payroll processing
SUNY-monthly employees that are paid by the RF during the summer will show up in their regular department for that period
IFR/Cost Sharing Department
10
Discussion topic: Use the existing flexfield from the Oracle assignment record Central office would populate this data initially Campuses would need to maintain this information going forward A SUNY employee’s actual department would display in ecrt and on
the effort statement Potential use in other business applications
System Testing Timeline
11
Phase 1 March 5 – 19 Continue working on the test scripts Retry the Payroll Report test scripts Provide effort coordinator names and
e-mail addresses Phase 2
Anticipated to start March 22 Campus testers will receive new
testing package
March 2012
Sun Mon Tues Wed Thur Fri Sat
1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31
Summary
Minutes from this meeting will be posted on the
Operational Excellence in Effort Reporting Web page
Direct questions to:Anne ConnollyProject [email protected](518) 434-7240
12