opportunities for managing vllw in the uk documents... · 2013. 12. 4. · •national strategy...
TRANSCRIPT
1 www.quintessa.org
Opportunities for Managing VLLW in the UK
DISPONET Workshop on Large Volumes of Radioactive Waste
November 2013
James Penfold
2
Presentation
• Background
• Historical perspective, up to the 2000
• Policy and other developments in the mid 2000s
• Developments in the last 5 years that are identifying opportunities for efficient management of large volumes of VLLW
• Policy and strategic information is from Government, NDA and UK sites. Views and interpretation are mine
3
Background
• Large and diverse nuclear industry, since 1940s • A very large amount of LLW will arise from
decommissioning, and aspects of the inventory are quite uncertain
• Wastes are very diverse, in terms of materials and radioactivity content, although construction waste and contaminated ground from decommissioning is a key component
• The volume of LLW is probably > 4 106 m3
• The costs are probably 10 Bn Euro • The timescale is probably 100 y
4
LLW Management Timeline
• 1947 – Nuclear industry born at Sellafield • 1959 – National LLW repository at Drigg • 1960, 1965 – First specific regulations (and “exemption
orders”) : • 1995 – Radioactive waste policy review : • 2005 – NDA established • 2007 – Updated LLW policy • 2008 – First NDA LLW strategic review • 2010 – Updated strategy
5
Historical Practice
Up to the 1990s…
• Most LLW was operational waste and redundant plant
• Almost all wastes consigned to LLWR (or Dounreay)
• The only scope for dealing with large volume VLLW separately was “Exemption Orders”
– Allowed specific types of waste (e.g. NORM) to be disposed without regulatory controls
– Up to about 10 Bq/g for natural radionuclides
– Quite widely used for “VLLW” although not always correctly
• From about 40 y of nuclear activities
– 800,000 m3 LLW in trenches at LLWR (Drigg) , 30,000 m3 of LLW in trenches at Dounreay
6
Key Developments in 1990s
• LLWR and Dounreay trenches closed, LLWR adopts Vault concept
• Deep geological repository planned to accept some LLW but Nirex fails to make the case for a rock laboratory near Sellafield
• Government review of radioactive waste management policy in 1995 – Existing concept of “Controlled Burial” at Landfills of LLW from non-
nuclear industry – Consulted on extending this to nuclear industry to reduce pressure on
LLWR – Concerns from public and stakeholders meant this was not adopted,
and LLW and VLLW from the nuclear industry had to be sent to LLWR (or stored)
• Some very lightly contaminated material could continue to be disposed of by the nuclear industry and others under “Exemption Orders”
7
Key Developments in 2000s
• Increased pace of decommissioning
• Dounreay commences a programme to establish new LLW and VLLW facilities
• Government establishes the Nuclear Decommissioning Authority in 2005 to manage nuclear cleanup
• Government and NDA review policy and strategy seeking to – Optimise – LLWR is limited (700,000m3 extra?)
– Reduce costs – of order 10 Bn Euro
8
Government Policy Review 2007
• Specifically for LLW, builds on 1995 Policy
• Definition of VLLW – High Volume VLLW: 4 Bq/g or 40 Bq/g H-3/C-14
• Emphasised the importance of: – “Optimisation”
– Proximity principle
– Early solutions
• Overturned previous policy on consignment of nuclear industry waste to landfills
• NDA/LLWR responsible for LLW Strategy
9
Strategic Review, 2008
• Key aim was to define the “Baseline” for LLW management
• This could then be used to identify improvements
• Inventory projections developed in detail
• Explored strategies
• Objective of 10% cost savings
• Mainly recommendations – Application of the Waste Management Hierarchy to site-
level strategies
– Encourage volume reduction (sorting, decontamination)
– Diversion of VLLW to landfills and exemption
10
Inventory Forecast, 2008
11
Key development: Waste Management Hierarchy (WMH)
12
Opportunities, 2008
13
Strategic Review 2011
• Development of Integrated Waste Strategy for each NDA site – But variable application of the WMH – Disposal at LLWR still the dominant option
• More detailed inventory data (volumes increased) • But 400,000 m3 recategorised as VLLW and LLW costs
reduced by about 10% • More waste management routes
– Metal treatment facility in Lillihall – Metals melting at Studsvik – 3 landfills have permits for VLLW – Several hazardous waste incinerators – LLWR will take ownership of wastes and arrange suitable
treatment through agreement with regulators
14
Inventory Forecast, 2011
15
Key development: Framework for Optimisation
16
Opportunities, 2011
• National strategy themes – Further improve application of WMH
– Best use of existing assets (LLWR)
– Make use of new waste management routes
• At a site level – Improve knowledge and waste tracking
– Share best practice
– Use of supply chain for metals melting, thermal treatment, etc.
– Improve scope for disposal to landfill
17
Future Opportunities Onsite recycling, reuse or disposal
• Decommissioning rubble remains a key element of the VLLW waste inventory
• Onsite disposal in designated facilities only under consideration at Sellafield and Dounreay
• Winfrith examining option of onsite disposal in existing basements (30,000 m3) – Options will be consulted on in December
– Key “pathfinder” for NDA
– Dialogue with local stakeholders
– Regulatory mechanisms need to be developed
18
Future Opportunities: Reuse in LLWR Capping
• Option currently being examined – Technical assessment of issues including effect on
safety performance
– Needs careful design e.g. to manage lightly contaminated leachate from cap
• Need a lot of material for cap profile, emplaced grdually
• Material is suitable
• Demand profile could fit arisings
• No complicated permitting issues
19
Future Opportunities Reduction, Recycling and Reuse
• Metals treatment
– Berkeley boilers shows scope for metal treatment
– Greater use of Studsvik facility
– Review “case” for facility in UK-based facility
• Recycling of concrete not really explored
– Scope is really only within nuclear industry
– Major construction nuclear projects are coming
– Timing and QA are the major issues
• What about soils?
20
Conclusions
• Up until mid-2000s the presumption was for all VLLW and LLW to go to LLWR (Drigg)
• Since then… – Government opened up possibilities for VLLW in 2007 and NDA
has sought to optimise waste management using the WMH – NDA has incentivised efficient solutions for VLLW – Sites have developed integrated strategies – Regulators have sought to facilitate where they can
• This has reduced costs by 10% and potentially diverted substantial volumes of VLLW from LLWR
• Challenge is now to explore alternative routes • There remain major opportunities for decommissioning
VLLW, in particular on-site disposal and recycling