Optimising Movements and Runway Capacity Glynn Turner Lockheed Martin

Upload: others

Post on 21-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Optimising Movementsand Runway Capacity

Glynn TurnerLockheed Martin

Page 2: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Thought Process

• Identify Problem

• Determine what needs to be done

• Develop Solution

• Determine Success Parameters

• Implement Solution

• Assess Results

• Did it work or not

Page 3: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

1-What are we trying to fix

Statement of Problem:

• Need to maintain runway capacity at all times

Why?

• Too much separation reduces landing rate

• Wastes available capacity

• Too close then breaks minimum separation

• Infringes safety requirements

• Increased number of Go Rounds

Page 4: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

1-What do we need to happen

Need a Solution that helps users:

• Maintain mandated minimum separation

• Maintain planned arrival rates

• Reduces associated delays

• Remove Min Separation busts

• Reduce go rounds

Page 5: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

1-Proposed solution

Page 6: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

1-What outcomes do we want

We want maximized runway throughput that:

• Delivers the declared landing capacity

• Removes losses of minimum separation

• Delivers a safe, efficient service

• Reduces the number of Go Rounds

• Minimises delay

Page 7: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Intelligent Approach 1.0

Page 8: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

What are we trying to fix -2

Statement of Problem:

• Need to maximise runway capacity at all times

Why?

Weather:

• Causes loss of landing slots

• Introduces airborne delays/holding

• Causes flight cancellations

• Impacts passenger/airline customers

Snow LVPs Winds T/Storm Capacity Other

Winds 44%

Page 9: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

What do we need to happen -2

Need a Solution that helps users:

In all Wind Conditions:

• Maintain planned arrival rates

• Maintain mandated minimum separation

• Reduce associated delays

Page 10: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Time Based Separation, is it feasible?

150,000 Flights Measured…

…Proving Wake Dissipates

as Headwinds Increase

Page 11: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Wind Effects

Page 12: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Wind Effects

Page 13: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Results With TBS

Page 14: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Intelligent Approach 2.0

Page 15: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Time Based Separation Results

Pre and Post TBS 0-20 Knots Wind

Page 16: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Time Based Separation Results

Pre and Post TBS >20 Knots Wind

Page 17: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

TBS performance in Nov 2015

• Estimate over 25,000 minutes of delay saved versus distance based separation

15 days of strong headwinds

November 15, 2015 Storm Barney:

EUROCONTROL: Strong winds generated 65% of the total daily ATFM delay

LHR at the runway 21kts, gusting to 32kts, 80kts at 4000ft and 60kts straight down the runway at 3000ft35-40 Movements / Hour

Page 18: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

TBS Delivering Results

5nm becomes 3.7nm in 60 knot headwind

Page 19: Optimising Movements and Runway Capacity Movements_Gly… · Pre and Post TBS 0-20 Knots Wind. Time Based Separation Results Pre and Post TBS >20 Knots Wind. TBS performance in Nov

Intelligent Approach 2.0

Reduced cancellations

No Increase in Go Arounds or Wake Turbulence Encounters

+2.9 movementsper hour in strong wind conditions

62%reduction in ATFM

wind delay

178NMof spacing saved per day

in strong wind conditions (>20kts)

83% of aircraft experienced smaller

Arrival-Arrival separations

78NMof spacing on approach saved per

day, on average

+1.2 movementsper hour across all wind conditions

No pilot inquires or comments