  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    1/29

    OptiX OSN 3500&7500&7500 IIV200R013C10SPC100

    TMPLS to MPLS-TP UpgradeGuide

    Issue 01

    Date 2014-04-11

    HUAWEI TECHNOLOGIES CO., LTD.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    2/29

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    i

    Copyright Huawei Technologies Co., Ltd. 2014. All rights reserved.

    No part of this document may be reproduced or transmitted in any form or by any means without prior

    written consent of Huawei Technologies Co., Ltd.

    Trademarks and Permissions

    and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.

    All other trademarks and trade names mentioned in this document are the property of their respect ive

    holders.

    Notice

    The purchased products, services and features are stipulated by the contract made between Huawei and

    the customer. All or part of the products, services and features described in this document may not be

    within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,

    information, and recommendations in this document are provided "AS IS" without warranties, guarantees orrepresentations o f any k ind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in the

    preparation of this document to ensure accuracy of the contents, but all statements, information, and

    recommendations in this document do not constitute a warranty of any kind, express or implied.

    Huawei Technologies Co., Ltd.

    Address: Huawei Industrial Base

    Bantian, Longgang

    Shenzhen 518129

    People's Republic of China

    Website: http://www.huawei.com

    Email: [email protected]

    http://www.huawei.com/mailto:[email protected]:[email protected]://www.huawei.com/
  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    3/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide Change History

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    ii

    Change History

    Issue Date Description

    01 2014-04-11 This issue is the first official release.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    4/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide Contents

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    iii

    Contents

    Change History ................................................................................................................................ ii1 Before You Start............................................................................................................................. 1

    1.1 Upgrade Object ive .............................................................................................................................................................1 1.2 Preparing for the Upgrade ................................................................................................................................................1 1.3 Method Introduction..........................................................................................................................................................21.4 Impact of the Upgrade.......................................................................................................................................................3

    1.4.1 Impact on the Sys tem Dur ing the Upgrade .........................................................................................................31.4.2 Impact on the Sys tem After the Upgrade ............................................................................................................3

    1.5 Precautions ..........................................................................................................................................................................32 Upgrade Process Overview ......................................................................................................... 5

    2.1 Upgrade Flowchart ............................................................................................................................................................5 2.2 Running Inspection Scripts ..............................................................................................................................................62.3 Checking the Software Version .......................................................................................................................................9

    2.3.1 Checking the NE Software Version ......................................................................................................................92.3.2 Checking the U2000 Version ...............................................................................................................................102.3.3 Upgrading the NE Software .................................................................................................................................102.3.4 Upgrading the U2000............................................................................................................................................10

    2.4 Checking Feature Coupling............................................................................................................................................102.5 Migrating Serv ices ...........................................................................................................................................................12 2.6 Replacing the Cross-Connect Board on OptiX OSN 3500.......................................................................................15 2.7 OptiX OSN Replacing the Cross-Connect Board on OptiX OSN 7500.................................................................172.8 Switching to Dual-Stack OAM Mode ..........................................................................................................................182.9 Switching to MPLS-TP OAM .......................................................................................................................................21

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    5/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    1

    1 Before You Start1.1 Upgrade Objective

    This document guides you to upgrade the feature TMPLS OAM of the OptiX OSN3500/7500/7500 II to MPLS-TP OAM. After the upgrade, the OptiX OSN 3500/7500/7500 IIcan perform OAM operations with the peers that support MPLS-TP OAM.

    1.2 Preparing for the Upgrade

    The table below lists the preparations you need to complete before an upgrade.

    Table 1-1Preparations for an upgrade

    Item Description

    Versions of the U2000 and NEsoftware

    Upgrade the U2000 and NE software to the versionsthat support MPLS-TP.

    Upgrade the NE software to V200R013C10SPC100.

    Upgrade the U2000 to V200R001C00.

    Hardware Ensure that the boards on the equipment meet thefollowing requirements:

    The cross-connect board on the OptiX OSN 3500is SSN3PSXCSA.

    The cross-connect board on the OptiX OSN 7500is SST2PSXCSA.

    Ensure that the subrack type of the OptiX OSN3500/7500 meets the requirements described insection2.2 "Running Inspection Scripts."

    Personnel Ensure that the upgrade personnel have the basic

    network skills, master the common operations on theU2000, know basics about the transport equipment,and understand the concepts of MPLS-TP.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    6/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    2

    Item Description

    Feature Before switching Y.1711 to Y.1731, ensure thefollowing conditions are met.

    The OptiX OSN 3500 does not support two-slotboards.

    Slots 26 to 31 on the OptiX OSN 7500 do notsupport packet boards.

    The services that run the IGMP protocol do notsupport complex traffic c lassification.

    The PWs configured with the interworkingfunction (IWF) do not support MPLS-TP OAM.

    Switching to the dual-stack mode is notsupported if the number of enabled TMPLSOAM features exceeds 1024.

    1.3 Method Introduction

    An upgrade from TMPLS OAM to MPLS-TP OAM includes four procedures.

    1. (Optional) Migrate services on the OptiX OSN 7500. Because slots 26 to 31 on theOptiX OSN 7500 do not support packet boards after the upgrade, the services that areoriginally carried by the boards in slots 26 to 31 need to be migrated beforehand.

    2. (Optional) Replace cross-connect boards. If the cross-connect boards on the OptiX OSN3500/7500 do not support MPLS-TP OAM, replace them with proper ones.

    3. (Mandatory) Switch the single-stack OAM mode (TMPLS) to the dual-stack OAM mode(TMPLS+MPLS-TP). The OptiX OSN 3500/7500/7500 II uses the single-stack OAMmode by default. Therefore, you need to switch the single-stack OAM mode to thedual-stack OAM mode. The switching is irreversible. That is, you can only switch thesingle-stack OAM mode to the dual-stack OAM mode.

    4. (Mandatory) Select and switch services to MPLS-TP OAM. You select the desiredservices and switch them to MPLS-TP OAM. The switching is reversible.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    7/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    3

    1.4 Impact of the Upgrade

    1.4.1 Impact on the System During the Upgrade

    Impact on Services

    During the switching to dual-stack OAM mode on the OptiX OSN 3500, services areinterrupted for less than 12 seconds.

    During the switching from SST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, servicesare interrupted for less than 2.5 seconds.

    During the service migration on the OptiX OSN 7500, services are interrupted until themigration f inishes.

    Impact on Network Communications

    If the equipment communicates with the U2000 through DCC channels, the communication

    will be interrupted for less than 12 seconds during the switching to dual-stack OAM mode onthe OptiX OSN 3500 or for less than 2.5 seconds during the switching from SST1PSXCSA toSST2PSXCSA on the OptiX OSN 7500.

    1.4.2 Impact on the System After the Upgrade

    After the switching to dual-stack OAM mode on the OptiX OSN 3500, the services that runthe IGMP protocol do not support complex traffic classification. After the switching fromSST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, slots 26 to 31 do not supportpacket boards.

    1.5 Precautions

    The switching to dual-stack OAM mode is irreversible. You can return to thepre-switching condition only by restoring the databases that are automatically backed upbefore the switching. If you return to the pre-switching condition through databaserestoration, cold reset the cross-connect board to recover services.

    Ensure power supply to the equipment where the switching to dual-stack OAM mode isbeing performed. If the equipment is powered off before the switching finishes, theequipment may enter an unexpected state and you can return to the pre-switching

    condition only by restoring the databases that are automatically backed up before theswitching.In V200R013C10SPC100, the algorithm PBKDF is added, and three digestalgorithms are supported: MD5, SHA256, and PBKDF. Users can configure a digestalgorithm on the U2000. The security of the three digest algorithms from low to high isas follows: MD5, SHA256, and PBKDF2. If a stronger digest algorithm is configuredafter an upgrade, the digest information of an account added before the upgrade is stillstored in the database. You need to manually delete this account and create another one,or change the password of the account added before the upgrade.

    For example, before an upgrade, digest information is generated using MD5. Supposethat an administrator account szhw exists, and the digest information of the accountpassword generated using MD5 is stored in the database. After an upgrade is performedand the digest algorithm is changed to PBKDF2, the digest information of the szhw

    account password generated using MD5 is still stored in the database. You can delete this

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    8/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    4

    szhw account and create a new szhw account. Then, the new szhw account's digestinformation generated using PBKDF2 is stored in the database, and the digest

    information generated using MD5 is deleted.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    9/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    5

    2 Upgrade Process Overview2.1 Upgrade Flowchart

    Figure 2-1Upgrade flowchart

    Running inspection

    scripts

    (Mandatory) Switching to

    dual-stack OAM mode

    (Mandatory) Switching to

    MPLS-TP OAM

    End

    (Mandatory) Checkingthe software version

    (Optional) Migrating

    services

    (Optional) Replacing

    cross-connect boards

    (Mandatory) Checking

    feature coupling

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    10/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    6

    2.2 Running Inspection Scripts

    Description

    Run inspection scripts to check whether the upgrade conditions are met.

    Precautions

    Inspection scripts can be used to check:

    Whether the cross-connect board on the OptiX OSN 3500 is SSN3PSXCSA

    Whether any two-slot packet board is installed on the OptiX OSN 3500

    Whether the subrack type of the OptiX OSN 3500 is high-power backplane subrack(VER.E)

    Whether the cross-connect board on the OptiX OSN 7500 is SSST2PSXCSA

    Whether slots 26 to 31 on the OptiX OSN 7500 house any packet board

    Whether the subrack type of the OptiX OSN 7500 is high-power backplane subrack(VER.D)

    Whether one E-LAN service is configured with complex traffic classification and IGMP

    Whether all specifications of TMPLS can be switched to MPLS-TP

    Procedure

    Step 1 Start the Inspector and add the NEs to be upgraded.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    11/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    7

    Step 2 Choose Configure > Configure Inspector Template from the Main Menu. In the ConfigureInspection Templatewindow, select Checking whether the NE can be upgraded from thedistributed mode to centralized mode and Checking OAM specifications from theupgrade from 1711 to 1731, and click Finish.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    12/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    8

    Step 3 Click in the Inspectorwindow. The inspection starts and endures three to five minutes.After the inspection finishes, view the results in the Check Resultpane.

    ----End

    Verification

    Prepare for the upgrade according to the inspection results.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    13/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    9

    2.3 Checking the Software Version

    2.3.1 Checking the NE Software Version

    Step 1 In NE Explorer, choose Configuration > NE Attribute from the Function Tree.

    ----End

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    14/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    10

    2.3.2 Checking the U2000 Version

    Step 1 On the U2000, choose Help > About from the Main Menu.

    ----End

    2.3.3 Upgrading the NE SoftwareFor details on how to upgrade the NE software, see the OptiX OSN 1500&3500&7500&7500

    II Intelligent Optical Transmission&Switching System V200R013C10SPC100 UpgradeGuide-Simulation Package Diffusionand OptiX OSN 1500&3500&7500&7500 II IntelligentOptical Transmission&Switching System V200R013C10SPC100 Upgrade Guide-SimulationPackage Loading.

    2.3.4 Upgrading the U2000

    For details on how to upgrade the U2000, see the related upgrade guide.

    2.4 Checking Feature Coupling

    Description

    After the switching to dual-stack OAM mode, the services that run the IGMP protocol doesnot support complex traffic classification. Therefore, you need to check whether IGMPSnooping and complex traffic classification are configured for the same services before theswitching.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    15/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    11

    Procedure

    Step 1 In NE Explorer, choose Configuration > Packet Configuration > Ethernet ProtocolConfiguration > IGMP Snooping Configurationfrom the Function Tree. Check whetherIGMP Snooping is enabled for any service.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    16/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    12

    Step 2 In NE Explorer, choose Configuration > Packet Configuration > Ethernet ServiceManagement > E-LAN Service from the Function Tree. In the right pane, click QoSandcheck whether the service with enabled IGMP Snooping has any QoS policy.

    Step 3 Delete the QoS policy or disable IGMP Snooping according to the actual requirements.

    ----End

    Verification

    No service is configured with IGMP Snooping and complex traffic classification.

    2.5 Migrating Services

    After the switching from SST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, slots 26to 31 do not support packet boards.

    If there is any packet board in slots 26 to 31 and the board is configured with services, youneed to migrate the services to the boards in slots 1 to 8 and slots 11 to 18 before theswitching.

    After the services are migrated, remove the packet boards in slots 26 to 31 and delete thecorresponding logical boards on the U2000. Service migration can be performed withHuawei's circuit cutover tool (TCAT).

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    17/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    13

    To migrate the services that TCAT does not support, you can delete these services and restorethem on the target boards. Considering the complexity of service migration, ask R&Dengineers to assess the feasibility of service migration beforehand.

    SLOT1

    SST1P

    SXCSA

    SLOT2

    SLOT3

    SLOT4

    SLOT5

    SLOT6

    SLOT7

    SLOT8

    SST1P

    SXCSA

    SLOT11

    SLOT12

    SLOT13

    SLOT14

    SLOT15

    SLOT16

    SLOT1

    SST1P

    SXCSA

    SLOT2

    SLOT3

    SLOT4

    SLOT5

    SLOT6

    SLOT7

    SLOT8

    SST1P

    SXCSA

    SLOT11

    SLOT12

    SLOT13

    SLOT14

    SLOT15

    SLOT16

    SLOT17

    SLOT18

    SLOT17

    SLOT18

    SSN1PEG8

    S

    LOT27

    S

    LOT28

    S

    LOT29

    S

    LOT30

    S

    LOT31

    SLOT19

    SLOT20

    SLOT21

    SLOT22

    SLOT23

    PIUA---

    -PIUB

    SLOT34

    SLOT35

    SLOT36

    SLOT37

    SLOT38

    G

    SCC

    G

    SCC

    SSN1PEG8

    S

    LOT27

    S

    LOT28

    S

    LOT29

    S

    LOT30

    S

    LOT31

    SLOT19

    SLOT20

    SLOT21

    SLOT22

    SLOT23

    PIUA---

    -PIUB

    SLOT34

    SLOT35

    SLOT36

    SLOT37

    SLOT38

    G

    SCC

    G

    SCC

    SSN1PE

    G8

    SST1PSX

    CSA

    SLOT2

    SLOT3

    SLOT4

    SLOT5

    SLOT6

    SLOT7

    SLOT8

    SST1PSX

    CSA

    SLOT11

    SLOT12

    SLOT13

    SLOT14

    SLOT15

    SLOT16

    SSN1PE

    G8

    SST1PSX

    CSA

    SLOT2

    SLOT3

    SLOT4

    SLOT5

    SLOT6

    SLOT7

    SLOT8

    SST1PSX

    CSA

    SLOT11

    SLOT12

    SLOT13

    SLOT14

    SLOT15

    SLOT16

    SLOT17

    SLOT18

    SLOT17

    SLOT18

    SLO

    T26

    SLO

    T27

    SLO

    T28

    SLO

    T29

    SLO

    T30

    SLO

    T31

    SLOT19

    SLOT20

    SLOT21

    SLOT22

    SLOT23

    PI

    UA---

    -PIUB

    SLOT34

    SLOT35

    SLOT36

    SLOT37

    SLOT38

    GSC

    C

    GSC

    C

    SLO

    T26

    SLO

    T27

    SLO

    T28

    SLO

    T29

    SLO

    T30

    SLO

    T31

    SLOT19

    SLOT20

    SLOT21

    SLOT22

    SLOT23

    PI

    UA---

    -PIUB

    SLOT34

    SLOT35

    SLOT36

    SLOT37

    SLOT38

    GSC

    C

    GSC

    C

    Before migration, some services are configured on

    the boards in slots 26 to 31.

    The services are migrated to boards in slots

    1 to 8 and slots 11 to 18.

    LSP

    Description

    Migrate the services on the packet boards in slots 26 to 31 to the boards in slots 1 to 8 andslots 11 to 18.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    18/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    14

    Precautions

    Services may be interrupted during inner-NE migration. To minimize the interruption time ofthe services under migration, make the target ports ready and synchronize the DCN and clockconfiguration of the source ports to the target ports before you perform service migration. To

    prepare for a rollback in case of migration failure, back up the databases.

    Procedure

    Step 1 Synchronize the Layer 2 and Layer 3 attributes of the source ports to the target ports.

    Step 2 Migrate services with the TCAT. (For details, see the help manual related to the TCAT.)

    Step 3 Remove the source boards.

    Step 4 Delete the logical boards of the source boards.

    ----End

    Verification

    For NNI ports, test the connectivity of MPLS tunnels using LSP Ping.

    In NE Explorer, choose Configuration > Packet Configuration > MPLS Management >

    Unicast Tunnel Managementfrom the Function Tree. In the right pane, click OAM

    Parameters. Right-click the migrated tunnels and choose Ping Testfrom the shortcut menu.If the number of transmitted packets equals the number of received packets in a ping test, themigration is successful.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    19/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    15

    Check the test results.

    2.6 Replacing the Cross-Connect Board on OptiX OSN3500

    Description

    Replace the SSN2PSXCSA board on the OptiX OSN 3500 with the SSN3PSXCSA board.

    S

    L

    O

    T

    1

    S

    S

    N

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    N

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    G

    S

    C

    C

    G

    S

    C

    C

    S

    L

    O

    T

    1

    S

    S

    N

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    N

    3

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    G

    S

    C

    C

    G

    S

    C

    C

    S

    L

    O

    T

    1

    S

    S

    N

    3

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    N

    3

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    G

    S

    C

    C

    G

    S

    C

    C

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    20/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    16

    Precautions

    Ensure that services are available during the replacement.

    To help you understand the procedure, slot 9 is specified as active slot and slot 10 is specified

    as standby slot. The board in slot 9 is the working board and the boards in slots 9 and 10 arenormal.

    The board software version of the new cross-connect board should be V200R013C10SPC100.If the board software version of the new cross-connect board is not V200R013C10SPC100,update the board software version immediately after the board goes online.

    Procedure

    Step 1 Remove the SSN2PSXCSA board in slot 10.

    Step 2 Delete the logical board SSN2PSXCSA in slot 10.

    Step 3 Add a logical board SSN3PSXCSA in slot 10.Step 4 Install an SSN3PSXCSA board in slot 10 and wait until the board goes online.

    Step 5 Issue the active/standby switching command to the cross-connect boards.

    Step 6 Remove the SSN2PSXCSA board in slot 9.

    Step 7 Delete the logical board SSN2PSXCSA in slot 9.

    Step 8 Add a logical board SSN3PSXCSA in slot 9.

    Step 9 Install an SSN3PSXCSA board in slot 9 and wait until the board goes online.

    ----End

    Verification

    The active and standby cross-connect boards are online and in the normal state. There is noalarm related to incorrect board types. Services are normal.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    21/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    17

    2.7 OptiX OSN Replacing the Cross-Connect Board onOptiX OSN 7500

    Description

    Replace the SST1PSXCSA board on the OptiX OSN 7500 with the SST2PSXCSA board.

    S

    L

    O

    T

    1

    S

    S

    T

    1

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    T

    1

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    S

    L

    O

    T

    1

    7

    S

    L

    O

    T

    1

    8

    S

    L

    O

    T

    1

    S

    S

    T

    1

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    T

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    S

    L

    O

    T

    1

    7

    S

    L

    O

    T

    1

    8

    S

    L

    O

    T

    1

    S

    S

    T

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    2

    S

    L

    O

    T

    3

    S

    L

    O

    T

    4

    S

    L

    O

    T

    5

    S

    L

    O

    T

    6

    S

    L

    O

    T

    7

    S

    L

    O

    T

    8

    S

    S

    T

    2

    P

    S

    X

    C

    S

    A

    S

    L

    O

    T

    1

    1

    S

    L

    O

    T

    1

    2

    S

    L

    O

    T

    1

    3

    S

    L

    O

    T

    1

    4

    S

    L

    O

    T

    1

    5

    S

    L

    O

    T

    1

    6

    S

    L

    O

    T

    1

    7

    S

    L

    O

    T

    1

    8

    S

    L

    O

    T

    2

    6

    S

    L

    O

    T

    2

    7

    S

    L

    O

    T

    2

    8

    S

    L

    O

    T

    2

    9

    S

    L

    O

    T

    3

    0

    S

    L

    O

    T

    3

    1

    S

    L

    O

    T

    1

    9

    S

    L

    O

    T

    2

    0

    S

    L

    O

    T

    2

    1

    S

    L

    O

    T

    2

    2

    S

    L

    O

    T

    2

    3

    P

    I

    U

    A

    ----

    P

    I

    U

    B

    S

    L

    O

    T

    3

    4

    S

    L

    O

    T

    3

    5

    S

    L

    O

    T

    3

    6

    S

    L

    O

    T

    3

    7

    S

    L

    O

    T

    3

    8

    G

    S

    C

    C

    G

    S

    C

    C

    S

    L

    O

    T

    2

    6

    S

    L

    O

    T

    2

    7

    S

    L

    O

    T

    2

    8

    S

    L

    O

    T

    2

    9

    S

    L

    O

    T

    3

    0

    S

    L

    O

    T

    3

    1

    S

    L

    O

    T

    1

    9

    S

    L

    O

    T

    2

    0

    S

    L

    O

    T

    2

    1

    S

    L

    O

    T

    2

    2

    S

    L

    O

    T

    2

    3

    P

    I

    U

    A

    ----

    P

    I

    U

    B

    S

    L

    O

    T

    3

    4

    S

    L

    O

    T

    3

    5

    S

    L

    O

    T

    3

    6

    S

    L

    O

    T

    3

    7

    S

    L

    O

    T

    3

    8

    G

    S

    C

    C

    G

    S

    C

    C

    S

    L

    O

    T

    2

    6

    S

    L

    O

    T

    2

    7

    S

    L

    O

    T

    2

    8

    S

    L

    O

    T

    2

    9

    S

    L

    O

    T

    3

    0

    S

    L

    O

    T

    3

    1

    S

    L

    O

    T

    1

    9

    S

    L

    O

    T

    2

    0

    S

    L

    O

    T

    2

    1

    S

    L

    O

    T

    2

    2

    S

    L

    O

    T

    2

    3

    P

    I

    U

    A

    ----

    P

    I

    U

    B

    S

    L

    O

    T

    3

    4

    S

    L

    O

    T

    3

    5

    S

    L

    O

    T

    3

    6

    S

    L

    O

    T

    3

    7

    S

    L

    O

    T

    3

    8

    G

    S

    C

    C

    G

    S

    C

    C

    Precautions

    During the replacement, services are interrupted for 2.5 seconds. To help you understand theprocedure, slot 9 is specified as active slot and slot 10 is specified as standby slot. The boardin slot 9 is the working board and the boards in slots 9 and 10 are normal. The board softwareversion of the new cross-connect board should be V200R013C10SPC100. If the board

    software version of the new cross-connect board is not V200R013C10SPC100, update theboard software version immediately after the board goes online.

    Procedure

    Step 1 Remove the SST1PSXCSA board in slot 10.

    Step 2 Delete the logical board SST1PSXCSA in slot 10.

    Step 3 Add a logical board SST2PSXCSA in slot 10.

    Step 4 Install an SST2PSXCSA board in slot 10 and wait until the board goes online.

    Step 5 Issue the active/standby switching command to the cross-connect boards. (Services areinterrupted for 2.5 seconds during the switching.)

    Step 6 Remove the SST1PSXCSA board in slot 9.

    Step 7 Delete the logical board SST1PSXCSA in slot 9.

    Step 8 Add a logical board SST2PSXCSA in slot 9.

    Step 9 Install an SST2PSXCSA board in slot 9 and wait until the board goes online.

    ----End

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    22/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    18

    Verification

    The active and standby cross-connect boards are online and in the normal state. There is noalarm related to incorrect board types. Services are normal.

    2.8 Switching to Dual-Stack OAM Mode

    The switching to dual-stack OAM mode can be performed after the operations on software,hardware, and services are completed. The switching duration varies depending on thenumber of services and the maximum duration is ten minutes. The switching causes serviceinterruption of 12 seconds on the OptiX OSN 3500 and the OAM and APS alarms on the peerNE of the OptiX OSN 7500/7500 II. The switching only enables the equipment to supportMPLS-TP and does not affect services.

    Description

    Switch the single-stack OAM mode to the dual-stack OAM mode on the OptiX OSN3500/7500/7500 II.

    Precautions

    During the switching, do not make any configuration and ensure the power supply to the

    equipment. If the equipment is powered off during the switching, you can return to thepre-switching condition only by restoring the databases automatically backed up before theswitching.

    The U2000 interface is locked during the switching. Do not configure the equipment using

    other tools.If the LSP/PW APS is configured, ensure that the involved services are running on theworking trails. Otherwise, these services may be interrupted for over 12 seconds.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    23/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    19

    Procedure

    Step 1 Check whether the services involved in LSP/PW APS are running on the working trails. InNE Explorer, choose Configuration > Packet Configuration > APS ProtectionManagementfrom the Function Tree. Check whether the services involved in LSP/PW APS

    are running on the working trails.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    24/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    20

    Step 2 Choose Configuration> NE Batch Configuration> MPLS OAM Configurationfrom theMain Menu.

    Step 3 Select the desired NE and click Switch to Dual-Stack Mode (TMPLS+MPLS-TP). Theswitching endures a maximum of ten minutes.

    ----End

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    25/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    21

    Verification

    The U2000 displays a successful switching message and no unexpected OAM alarm isreported.

    2.9 Switching to MPLS-TP OAM

    To ensure that the OAM can work properly after the switching to MPLS-TP OAM, you needto perform the switching on each node of the OAM-enabled line. Therefore, the switchingshould be performed with the U2000 in end-to-end mode.

    Description

    Switch the TMPLS OAM to the MPLS-TP OAM.

    Precautions

    The OAM detection intervals supported by Y.1711 are not consistent with those supported byY.1731. When the system encounters the detection interval inconsistencies, related alarms arereported and persist until the switching finishes. You can query the updates in detection

    intervals on the U2000.

    DetectionIntervalSupported by

    Y.1711

    DetectionIntervalSupported by

    Y.1731

    DetectionIntervalSupported by

    Y.1731

    DetectionIntervalSupported by

    Y.1711

    FFD 3.3 ms 3.33 ms 3.33 ms FFD 3.3 ms

    FFD 10 ms 10 ms 10 ms FFD 10 ms

    FFD 20 ms 10 ms 100 ms FFD 100 ms

    FFD 50 ms 100 ms 1 s CV 1s

    FFD 100 ms 100 ms 10 s CV 1s

    FFD 200 ms 100 ms 1 min CV 1s

    FFD 500 ms 1 s 10 min CV 1s

    CV 1s 1 s

    For the OptiX OSN 3500/7500/7500II in dual-stack mode, the number of supportedTMPLS-TP OAM specifications is different from the number of supported MPLS-TP OAMspecifications. To be specific, the OptiX OSN 3500/7500 supports 2k MPLS-TP OAMspecifications; the OptiX OSN 7500II supports 4k MPLS-OAM specifications, with slots 1 to8 supporting a maximum of 2.5k and slots 11 to 18 supporting a maximum of 2.5k. Therefore,the switching from TMPLS OAM to MPLS-TP OAM will fail if the number of supportedTMPLS-TP OAM specifications is larger than the number of supported MPLS-TP OAMspecifications.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    26/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    22

    Procedure

    Step 1 In NE Explorer, choose Configuration> Packet Configuration> MPLS Management>Unicast Tunnel Managementfrom the Function Tree. Click Static Tunnelin the right pane.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    27/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    23

    Step 2 Select the desired tunnel, right-click, and choose Switch to Y.1731from the shortcut menu.

    ----End

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    28/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Issue 01 (2014-04-11) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    24

    Verification

    There is no alarm related to MPLS-TP tunnel OAM or MPLS-TP PW OAM. An LB testinitiated on the MEP is successful. In NE Explorer, choose Configuration > PacketConfiguration > MPLS Management > Unicast Tunnel Managementfrom the Function

    Tree. In the right pane, click MPLS-TP OAM. In the MEP tab page, select the desired tunnel,right-click, and choose Start LB from the shortcut menu. If the LB response packets arereceived correctly, the switching is successful.

  • 7/22/2019 Optix Osn 3500&7500&7500 II v200r013c10spc100 Tmpls to Mpls-tp Upgrade Guide

    29/29

    OptiX OSN 3500&7500&7500 II

    TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

    Check the test results.