optix rtn 600 (idu 605) equipment commission-20080830-a.ppt
TRANSCRIPT
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
1/52
www.huawei.com
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.
Security Level:INTERNAL2014/7/21
OptiX RTN 600 IDU 605
Equipment Commissioning
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
2/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 1Page 1
Learning Guide
Before studying this course, you are supposed to complete the
study on
Basics of digital microwave communications or related
knowledge
OptiX RTN 600 Product Introduction. Refer to OptiX RTN 600
Radio Transmission System IDU 605 Hardware Description
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
3/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 2Page 2
References
Digital Microwave Communications Basics
OptiX RTN 600 Radio Transmission System Configuration Guide
OptiX RTN 600 Radio Transmission System Commissioning Guide
OptiX RTN 600 Radio Transmission System Maintenance Guide
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
4/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 3Page 3
Objectives
Upon completion of this course, you will be able to:
Finish proper preparations before the commissioning
Performing NE commissioning of the OptiX RTN 600
V100R002 IDU605
Performing hop commissioning of the OptiX RTN 600
V100R002 IDU605
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
5/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 4Page 4
Contents
1. Preparations for the OptiX RTN 600 Commissioning
2. NE Commissioning of the OptiX RTN 600
3. Hop Commissioning of the OptiX RTN 600
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
6/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 5Page 5
Contents
1. Preparations for the OptiX RTN 600 Commissioning
1.1 Determining Commissioning Items
1.2 Preparing Related Documents
1.3 Preparing Related Tools
1.4 Checking Commissioning Conditions
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
7/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 6Page 6
Determining Commissioning Items
1. NE Commissioning Items
Commissioning Item Optional/RequireRemarks
Powering on the
equipmentRequired
-
Connecting the Web LCT Required -
Configuring the data Required -
Testing indicators Required -
Testing E1 cables
connectionsOptional
It applies to the station where the E1 service
is accessed.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
8/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 7Page 7
Determining Commissioning Items (cont.)
2. Hop Commissioning Items
Commissioning Item Optional/ Required Remarks
Aligning the antenna Required -
Testing the ECC Required -
Testing the
orderwire phoneRequired
It is applicable when there is the order wire
phone available between stations.
Testing E1 services RequiredTest E1 service types turned up at the
station.
Testing the switching RequiredIt is applicable when the 1+1 HSB/FD/SD
protection is configured.
Testing the 24-Hour
BERRequired
-
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
9/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 8Page 8
Preparing Related Documents
The documents that are required include the engineering design
documents and commissioning guide documents.
Engineering design documents like
OptiX RTN 600 Radio Transmission System Network Planning
Document
OptiX RTN 600 Radio Transmission System Engineering Design
Document
Commissioning guide documents like:
OptiX RTN 600 Radio Transmission System IDU 605
Commissioning Guide
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
10/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 9Page 9
Preparing Tools
The tools that are required include the common tools, special tools andinstruments. The recommended list is as follows:
Type DescriptionCommon
tool
Adjustable wrench
Special toolAnti-static glove, ESD-preventive wrist strap,
telescope, and intercom
InstrumentMulti-meter, BER tester, and laptop computer
(installed with the Web LCT)
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
11/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 10Page 10
Checking Commissioning Conditions
The NE commissioning conditions to be checked include the status of the
equipment as well as that of the laptop computer used in the commissioning.
The NE commissioning conditions are listed as follows:
The hardware installation of the equipment must be complete, and it
should pass the installation check.
The power supply of the equipment must be available.
The service signal cables connected to other equipment must be routed
well.
The laptop computer must be installed with the Web LCT, andapplications should work normally.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
12/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 11Page 11
Checking Commissioning Conditions (cont.)
The hop commissioning items to be checked include the NE
commissioning status as well as the weather conditions. The hop
commissioning conditions are listed as follows:
The NE commissioning of the radio equipment at both ends of the
same radio link must be complete.
The weather should be suitable, and there should no rain or fog
between stations.
The on-site conditions and the personnel in charge of antennacommissioning must meet the requirement on the operation at a high
altitude.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
13/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 12Page 12
Summary
This chapter describes the following contents:
Documents and tools prepared before the commissioning
Commissioning conditions
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
14/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 13Page 13
Contents
1. Preparations for the OptiX RTN 600 Commissioning
2. NE Commissioning of the OptiX RTN 600
3. Hop Commissioning of the OptiX RTN 600
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
15/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 14Page 14
Contents
2. NE Commissioning of the OptiX RTN 600 2.1 Powering On the Equipment
2.2 Accessing the Web LCT
2.3 Configuring the Data
2.4 Testing the Connections of the E1 Cables
2.5 Testing Indicators
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
16/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 15Page 15
Powering On the Equipment
Prerequisites The hardware installation of the equipment must be complete, and it should
pass the installation check.
The input power must be available.
The power switch of the input power (such as the power box of the cabinet)
must be turned off.
Tools and Instruments
Multi-meter
Procedure
Set the POWER switch on the front panel of the IDU to O.
If the IDU 605 2B is used, you should set the ODU1 and ODU2 switches on
the front panel of the IDU to O"If the IDU 605 1A or 1B is usedyou
should set the ODU switches on the front panel of the IDU to O.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
17/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 16Page 16
Powering On the Equipment (cont.)
Turn on the power switch on the power box (or power cabinet).
testing the voltage and polarization of the input power at the access
point (such as the output terminal of the power box on the cabinet) by
multi-meter.
When the nominal voltage of the input power is48 V, the tested
voltage should be between38.4 V and57.6 V.
When the nominal voltage of the input power is60 V, the tested
voltage should be between48 V and72 V.
Set the POWER switch on the front panel of the IDU to I.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
18/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 17Page 17
Powering On the Equipment (cont.)
Observe the indicators on the front panel of the IDU 605. Front panelindicators should comply with the following statuses and sequences.
The PWR indicator on the front panel of the IDU 605 should be
green.
The IDU indicator on the front panel of the IDU 605 should be
green, flash green, and off. The process lasts about two minutes.
Then, the IDU indicator should be constantly on. If the green
indicator is constantly on, you can infer that no alarm is generated.
If the yellow indicator is constantly on, you can infer that a minor
alarm or a warning arises. If the red indicator is constantly on, you
can infer that a major alarm or a critical alarm arises.
If the IDU 605 2B is used, you should set the ODU1 and ODU2 switches on the
front panel of the IDU to "I".If the IDU605 1A or 1B is used you should set the
ODU switches on the front panel of the IDU to "I".
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
19/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 18Page 18
Accessing the Web LCT
Prerequisites
The equipment must be powered on.
Tools and Instruments
Laptop computer installed with the Web LCT.
Procedure Start the laptop computer, and log in to the operating system.
Set the IP address information of the computer . The IP address should
comply with the following conditions:
IP address:The IP address should be in the 129.9.0.0 network segment andshould be different from the IP address of the NE.
Subnet mask: 255.255.0.0
Gateway (default): null
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
20/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 19Page 19
Accessing the Web LCT (Cont.)
Use an Ethernet cable to connect the Ethernet port of the
laptop to the port marked "ETH" on the front panel of the IDU
605.The ETH interface supports the MDI/MDI-X autosensing.
Hence, you can use the straightthrough cable or crossover
cable to connect to it. In this case, the green indicators of theETH interface and network interface of the laptop computer are
lit on. Also, if you set the prompt for the local area connection in
the operating system of the laptop computer, a prompt is
displayed indicating that the network is connected.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
21/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 20Page 20
Accessing the Web LCT (Cont.)
On desktop, double-click the Start Web LCT icon.
The system displays the USER LOGIN window of the Web LCT.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
22/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 21Page 21
Accessing the Web LCTcont.
Enter User Name and Password, and then click Login. The user name of theWeb LCT is admin by default, and the corresponding password is T2000 by
default.
If the entered user name and the password are both correct, the NE List page is
displayed in the IE.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
23/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 22Page 22
Configuring the Data
Prerequisites
The documents that are required by data configuration must be available.
Tools and Instruments
Web LCT
Procedure Before configuring the NE data, create the NE, log in and modify the ID
settings of the NE according to the requirements in the Network Planning
Document.
The OptiX RTN 600 can be configured in two modes, General Mode andWizard Mode. Users can choose the proper configuration mode depending
on the specific configuration scenarios. For details, refer to the OptiX RTN
600 Radio Transmission System IDU 605 Configuration Guide.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
24/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 23Page 23
Testing the Connections of E1 Cables by
Using a BER Tester
Prerequisites
The E1 port must be transferred through the DDF.
The service data must be configured.
Tools and Instruments
Web LCT
BER tester
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
25/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 24Page 24
Testing the Connections of E1 Cables by
Using a BER TesterCont.
Procedure
Connect the BER tester to the first E1 port of the OptiX RTN 600 at the DDF.
Set the corresponding E1 port to outloop by using the Web LCT.
Select the PDH interface board in the Object Tree.
From the Function Tree, choose Configuration > PDH Interface.
Set Tributary Loopback of the E1 port to Outloop. Observe the BER tester. The AIS alarm should be cleared.
Release the outloop over the E1 port by using the Web LCT.
Select the PDH interface board in the Object Tree.
From the Function Tree, choose Configuration > PDH Interface.
Set Tributary Loopback of the E1 port to Non-Loopback.
Observe the BER tester. The BER tester should report the AIS alarm.
Repeat Step 1 to Step 5 to test other E1 ports.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
26/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 25Page 25
Testing the Connections of E1 Cables
Through PRBS
Prerequisite
The E1 port of the IDU 605 must travel through the DDF before being
connected to another device.
Data configuration must be complete.
The NE must be in normal communication with the Web LCT.
Tools and Instruments
Web LCT
Procedure
1. At the DDF, use an E1 cable to loop back the services over the first E1 port
towards the tributary board.
2. On the Web LCT, select the E1 interface board in the Object Tree.
3. In the function tree, choose Configuration > PRBS Test.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
27/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 26Page 26
Testing the Connections of E1 Cables
Through PRBSCont.
ProcedureCont.4. Select the first E1 port, and then set the PRBS-related parameters.
Direction: Tributary
Duration: 5
Measured in Time: s
5. Click Start to Test. The system displays a prompt dialog box.
6. Click OK.
7. When the Progress column is 100%, click Query to check the test result. The
Total PRBS column should be 0, and the curve diagram should be green.
8. Release the loopback set in Step 1.
9. Repeat Step 2 through Step 7 and check the test result. The curve diagram
should be yellow.
10. Repeat Step 1 through Step 9 to test all other E1 ports.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
28/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 27Page 27
Checking Alarms
Prerequisite The equipment must be connected to the Web LCT.
Data configuration must be complete.
The NE must be in normal communication with the Web LCT.
Tools and Instruments Web LCT
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
29/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 28Page 28
Checking Alarmscont.
Procedure
Select an NE from the Object Tree in the NE Explorer, and then click inthe toolbar.
Select Auto Refresh.
Check the displayed alarm information.
Check whether there are equipment alarms, particularly the following types of
alarms:
POWER_ALM
HARD_BAD
BD_STATUS
NESF_LOST
TEMP_ALARM
IF_CABLE_OPEN
For details on the previous alarms and about how to handle them, refer to the
OptiX RTN 600 Radio Transmission System IDU 605 Maintenance Guide.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
30/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 29Page 29
Summary
Introduce the prerequisite , Tools and Instruments, Procedure in each
Commissioning items of NE Commissioning
Powering On the Equipment
Accessing the Web LCT
Configuring Data
Testing the Connections of E1 Cables
Checking Alarms
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
31/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 30Page 30
Contents
1. Preparations for the OptiX RTN 600 Commissioning
2. NE Commissioning of the OptiX RTN 600
3. Hop Commissioning of the OptiX RTN 600
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
32/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 31Page 31
Contents
3. Hop Commissioning of the OptiX RTN 600
3.1 Aligning Antennas
3.2 Logging In to the Opposite NE
3.3
Testing the Orderwire Phone
3.4 Testing the E1 Service
3.5 Testing the IF 1+1 Switching
3.6 Testing the 24-Hour BER
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
33/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 32Page 32
Aligning Antennas
Prerequisite The NE commissioning of the radio equipment at both ends of the radio link
must be complete.
The weather should be suitable for outdoor work. There should be no rain,
snow, or fog between stations.
The on-site conditions must meet the requirements for the antenna to operate
at a high altitude and the personnel required to commission the antenna must
be trained to work at high altitudes.
The ATPC function must be disabled.
Tools and Instruments
Adjustable wrench
Multimeter
Intercom
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
34/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 33Page 33
Aligning Antennascont.
Precautions
If the radio link is configured in 1+1 protection mode and one antenna is used at each end,
power off the standby ODUs at both ends before aligning the antennas. After the antennas are
aligned, power on the standby ODUs at both ends.
If the radio link is configured in 1+1 SD mode, align the antennas as follows:
Power off the standby ODUs at both ends, and align the main antennas at both ends.
Power on the standby ODU at the local end. Maintain the position of the main antenna at
the remote end, and adjust the diversity antenna at the local end.
Power on the standby ODU at the remote end. Maintain the position of the main antenna at
the local end, and adjust the diversity antenna at the remote end.
If the radio link is configured in 1+1 FD mode and two antennas are used at each end, align the
antenna as follows:
At both ends, power on the main ODUs, power off the standby ODUs, and align the main
antennas.
At both ends, power off the main ODUs, power on the standby ODUs, and align the diversity
antennas.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
35/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 34Page 34
Aligning Antennascont.
Procedure
1. If the distance is long (more than 2 km), first position the antennas at both ends
in a horizontal manner. If the distance is short (less than 2 km), finely adjust the
elevation angle depending on the actual situation.
2. Connect a multimeter to the RSSI port on the ODU at the local end and test the
voltage value VBNC.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
36/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 35Page 35
Aligning Antennascont.
3. Adjust the azimuth angle of the antenna as follows:
Maintain the position of the remote antenna.
Use the multimeter to test the VBNC, and at the local end rotate the
antenna widely in a horizontal manner. Ensure that the three peak signals
of the VBNC are scanned and the central peak signal has the maximum
voltage.
4. Adjust the elevation angle of the antenna as follows:
At each VBNC voltage peak, adjust the elevation angle so that the VBNC
changes to the maximum value within the scanned range.
Adjust the antenna until the VBNC voltage reaches the maximum value.
Tighten the local antenna. When you tighten the antenna, ensure that the
VBNC voltage maintains the maximum value.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
37/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 36Page 36
Aligning Antennascont.
5. Repeat Step 2 to Step 4 to adjust the remote antenna.When the remotereceived signal level (RSL) reaches the maximum value,tighten the remote
antenna.
6. Repeat Step 2 to Step 5 for two to four times and ensure that the RSL at the
local end and the RSL at the remote end reach the maximum value. Tighten
the antennas at both ends.
7. Use the multimeter to test the VBNC voltage at both ends. Obtain the current
RSL by referring to the relation curve between the VBNC of ODUs and the
RSLs at both ends. The actual RSL should meet the design requirements. The
difference between the test value and the theoretical value should be within
the range from6 dB to +3 dB.
8. Tighten all the screws of the antennas.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
38/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 37Page 37
Logging In to the Opposite NE
Prerequisite
Aligning the antennas must be complete.
The equipment must be connected to the Web LCT.
Tools and Instruments
Web LCT
Precautions
You only need to test the ECC at one end of the radio link.
Procedure
In the NE List page, click Add NE.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
39/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 38Page 38
Logging In to the Opposite NEcont.
In the Add NE page, set the following attributes of the opposite NE: NE ID: ID of the opposite NE
Extended ID: extended ID of the opposite NE
Gateway Type: IP gateway
IP address: IP address of the local NE
User Name:root (default)
Password: password (default for the user root)
Click OK. In this case, a row of data for the newly added NE is added in the NE
List page.
Check Login Status of the newly added NE. The Login Status should be
Logged In.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
40/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 39Page 39
Testing the Orderwire Phone Prerequisite
The orderwire phone must be installed correctly at the station.
The orderwire data must be configured. Not be configrated, if use the orderwire group
calls.
Aligning the antenna must be complete.
Tools and Instruments
None.
Procedure
Check the status of the orderwire phones at both sides. The status should meet the
following requirements:
The ringing switch must be set to ON.
The dialing mode switch must be set to T, that is, the dual-tone dialing mode must
be selected.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
41/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 40Page 40
Testing the Orderwire Phonecont. Dial the orderwire phone of the opposite equipment
Pick up the orderwire phone, and press the TALK key on the front panel of thephone. In this case, the red indicator on the upper right of the front panel is on,
and is accompanied by the dialing prompt tone.
Dial the orderwire phone number of the opposite equipment. Normally, after the
opposite end answers, the talking quality is good and the voice is clear.
Answer the orderwire phone
The maintenance personnel at the opposite equipment side dials the orderwire
phone of the local equipment. Normally, the orderwire phone rings and at the
same time the red indicator at the back of the phone flashes.
Pick up the phone, and press the TALK key to talk. In this case, the red indicatoron the upper right of the front panel is on. Normally, the talking quality is good and
the voice is clear.
Testing the E1 Ser ices b Using a BER
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
42/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 41Page 41
Testing the E1 Services by Using a BER
Tester Prerequisite
The E1 service must be configured between stations.
Aligning the antennas must be complete.
Tools and Instruments
BER tester Web LCT
Procedure
Connect the BER tester to the first E1 port of the equipment on the local side.
On the equipment on the opposite side, use an E1 cable to loop back the services over
the first E1 port towards the tributary board, that is, hardware inloop over the E1 port. If
the hardware inloop fails, perform software inloop over the E1 port by using the Web
LCT.
Test the BER for 5 to 10 minutes by using the BER tester. There should be no bit errors.
Release the loopback.
Repeat Step 1 through Step 4 to test other E1 ports.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
43/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 42Page 42
Testing the E1 Service Through PRBS
Prerequisite
The E1 service must be available between stations.
Aligning the antenna must be complete.
Tools and Instruments
Web LCT
Procedure
Perform software inloop over the first E1 port of the opposite NE by using the
Web LCT.
On the Web LCT, select the E1 interface board of the local NE in the Object
Tree.
In the Function Tree, choose Configuration > PRBS Test.
Testing the E1 Service Through PRBS
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
44/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 43Page 43
Testing the E1 Service Through PRBS
cont.
Select the first E1 port, and then set the following PRBS-related parameters:
Direction: Cross
Duration:.5
Measured in Time:.s
Click Start to Test. The system displays a prompt dialog box.
Click OK.
When the Progress column is 100%, click Query to check the test result. The
Total PRBS column should be 0, and the curve diagram should be green.
Release the loopback set in Step 1.
Repeat Step 1 through Step 7 to test all other E1 ports.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
45/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 44Page 44
Testing the IF 1+1 Switching
Prerequisite
The equipment must be configured in IF 1+1 mode.
Aligning the antenna must be complete.
Tools and Instruments
BER tester Web LCT
Precautions
In the IDU 605 2B, the ODUs connect to the IF jumpers on the front panel of the
IDU 605 through IF cables. The main ODU connects to the IF jumper over the
ODU2 interface, and the standby ODU connects to the IF jumper over the ODU1
interface. On the front panel of the IDU,the power switch with a silkscreen of
"ODU2" controls the power supply of the main ODU, and the power switch with a
silkscreen of "ODU1" controls the power supply of the standby ODU.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
46/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 45Page 45
Testing the IF 1+1 Switching (cont.)
Procedure1. Connect one E1 port to the BER tester on the local equipment side.
2. At the opposite equipment side, perform hardware inloop over the E1
port. If the hardware inloop fails, perform software inloop over the E1
port by using the Web LCT.
3. Test the BER by using the BER tester. There should be no bit errors.
4. Check the working status of the board by using the Web LCT.
Select an NE from the Object Tree in the NE Explorer, and then choose
Configuration >Link Configuration.
Select IF 1+1 Protection, and then click Query. In Protection Group, the
Active Board of Device should be the active IF board .If 1+1 FD
protection or 1+1 SD protection is used, the Active Board of Channel
should also be the active IF board.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
47/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 46Page 46
Testing the IF 1+1 Switching (cont.)
5. Power off the ODU2 on the front panel of the IDU.
6. Check the BER test result. The service should recover immediately after a transient
interruption.
7. After the switching is complete, test the BER for 5 to 10 minutes. There should be no
bit error.
8. Power on the ODU2 on the front panel of the IDU.
9. When Revertive Mode of the IF 1+1 protection is set to Revertive, test the BER byusing the BER tester again. When the WTR time expires, the test result should
indicate that the service recovers after a transient interruption. WTR Time is set to
600s by default. Test the BER depending on the actual configuration.
10. Release the loopback set in Step 2.
11. At the opposite station, repeat Step 1 to Step 10 to test the IF 1+1 switching of theopposite equipment.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
48/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 47Page 47
Testing the 24-Hour BER
Prerequisite
Aligning the antenna must be complete.
Tools and Instruments
BER tester Web LCT
Precautions
If the 24-hour BER cannot be tested for each HOP of the link because of
restrictions of the actual situation, choose the E1 service of the first node and
the last node to perform the test. This operation ensures that the test path
covers all the radio links.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
49/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 48Page 48
Testing the 24-Hour BERcont. Procedure
At the opposite equipment side, extract several
typical E1 services, and perform hardware
inloopover the E1 ports. If the hardware inloop fails,
perform software inloop over the E1 port using the
Web LCT.
On the local equipment side, connect these E1
services serially at the DDF, and then access them
to the BER tester.
Perform the 24-hour BER test by using the BER
tester.
Record the test result. It should meet the design
requirements.
Release the loopback and serial connection.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
50/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 49Page 49
Testing the 24-Hour BERcont.
Postrequisite
If the first 24-hour BER test does not meet the specified requirement, find out
the cause and rectify the fault. Perform another 24-hour BER test until the test
is successful.
If the BER exceeds the nominal value in the test for a serial connection, locate
the fault by using the dichotomizing search or other methods until each
channel passes the 24-hour BER test independently.
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
51/52
Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 50Page 50
Summary
This chapter introduce Hop Commissioning , including
Aligning Antennas
Logging In to the Opposite NE
Testing the Orderwire Phone
Testing the E1 Service
Testing the IF 1+1 Switching
Testing the 24-Hour BER
-
8/12/2019 OptiX RTN 600 (IDU 605) Equipment Commission-20080830-A.ppt
52/52
Thank you
www.huawei.com