originaloriginal the united states environmental protection agency-region iii in re: : avtex fibers...

42
ORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990 .*,.•,: Front Royal, Virginia The above-entitled matter came on for a public hearing beginning at approximately 7:05 p.m., at the Front Royal Youth Center, 201 East 8th Street, Front (j , Royal, Virginia.. -..;•;• REPRESENTATIVES FROM THE EPA: WILLIAM W. TOFFEL Community Relations Coordinator BONNIE GUY GROSS Remedial Project Manager BOB CARON On-Scene Coordinator AR5000I6 STABNER COURT REPORTING CO. 13 So. Loudoun Street Rt.1, Box 2535 Winchester, VA 22601 Front Royal, VA 22630 (703) 667-3704 (703) 635-9425

Upload: others

Post on 29-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ORIGINALTHE UNITED STATES

ENVIRONMENTAL PROTECTION AGENCY-REGION III

IN RE: :

AVTEX FIBERS SUPERFUND SITE :

PUBLIC MEETING :

August 22, 1990

.*,.• , : Front Royal, Virginia

The above-entitled matter came on for a public

hearing beginning at approximately 7:05 p.m., at the

Front Royal Youth Center, 201 East 8th Street, Front

( j , Royal, Virginia.. - . . ; • ; •

REPRESENTATIVES FROM THE EPA:

WILLIAM W. TOFFELCommunity Relations Coordinator

BONNIE GUY GROSSRemedial Project Manager

BOB CARONOn-Scene Coordinator

AR5000I6STABNER COURT REPORTING CO.

13 So. Loudoun Street Rt. 1, Box 2535Winchester, VA 22601 Front Royal, VA 22630

(703) 667-3704 (703) 635-9425

Page 2: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

U12

13

14

15

16

17

18

19

20

21

r i 22j _ I

2

<.

MR. TOFFEL: I would like to say good evening

and welcome you for a discussion on the proposed plan

for the Avtex Fibers, Front Royal. We are going to have

a little discussion as to what is taking place.

But first I would like to introduce the folks

that are here this evening. Bonnie Guy Gross is our

Remedial Project Manager. Next to me is Bob Caron. He

is the On-Scene Coordinator.

I am Bill Toff el. I am the Community

Relations Coordinator. And we have some representatives

also from EPA. Bill Hagel is here. He is the Sections v

Chief in Waste Management Division for Virginia and West

Virginia.

From the State of Virginia, we have a number

of people here. Jamie Walters is my counterpart in

community relations. I am sure a number of you will

want to talk to Jamie.

Bob Wynn, the Project Officer from the State

of Virginia for this particular site, and John Horin,

the Remedial Project Manager is here. I see Mr. George

of the County, and I am sure some other city and town

and county officials will be here. jtocnnn i

J

j

;

Page 3: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1 We welcome everyone.

2 I would like to tell you that this is a formal

3 meeting. It is recorded by a court reporter and all of

4 this will go in the record.

5 I would like you to know that this plan and

6 all the materials related to this site can be reviewed

7 at the repository that is located over at the Samuels

8 Public Library. That's at 538 Villa Avenue, here in

9 Front Royal.

10 You are invited to review this material, make

[ , 11 comment on this proposed plan and we will accept

12 comments until September 14, 1990.

13 It was formally published. It was in the

14 Northern Virginia Daily on the 14th of this month, so

15 there is a 30 day period in which it is open. Your

16 comments should be sent to me, Bill Toffel, or to Bonnie

17 Guy Gross, at 841 Chestnut Street in Philadelphia. The

18 zip is 19107.

19 There are some .cards on the table, and there

20 is that address in the proposed plan. So if you have

21 comments and wish to send them, you can either refer to

22 that or come up and we will give you the address «flf 5000 I 8

Page 4: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

n 4 01 I did mention the court reporter. This

2 meeting does become a part of the public record. That

3 is why the reporter is here this evening.

4 I would ask that your questions, and we will

5 have an opportunity for questions pertaining to the

6 formal presentation about the proposed plan.

7 We understand there are concerns about the

8 odor that emanates from the site. There are other

9 questions and concerns, and we will address those, but

10 we would like to do that after the formal portion of the

i_I 11 meeting. We will stay around as long as we have to, to \

12 talk about those questions.

13 There will be a responsiveness summary. We

14 will answer all the pertinent questions that we receive,

15 those questions that come in by the 14th of September,

16 and they will also be placed in the repository.

17 Superfund, a situation such as Love Canal, led

18 to the enactment of the very formal title called the

19 Comprehensive Environmental Response Compensation

20 Liability Act, CERCLA. It all boils down to the common

21 term, Superfund. About ten years ago, in 1980, it was

r -n 22 enacted.

AR5000I9

Page 5: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1 Now, his law provided a broad federal

2 authority and resources to respond directly to releases

3 or threatened releases of hazardous substances that

4 could endanger human health or the environment, and that

5 law, well, as I say, was enacted ten years ago.

6 We had amendments to that law known as SARA,

7 in 1986, the Superfund Amendments and Reauthorization

8 Act was enacted. This reauthorized the program for five

9 years. It increased the fund to $8.5 billion, and it

10 put some teeth into the enforcement actions that we have

11 available to us today. n

12 The U.S. Environmental Protection Agency has

13 the primary responsibility for the managing the clean up

14 and enforcement activities under Superfund.

15 The comprehensive regulation known as the

16 National Contingency Plan describes the guidelines and

17 procedures for implementing this law. Every Superfund

18 site is unique. Clean-ups have to be tailored to

19 specific needs of each site, because the releases of

20 hazardous substances is different at each site.

21 EPA makes a .concerted efforts to encourage

22 those responsible to pay ffor the clean up. Howfivntn^fn O n

Page 6: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10ii 11

12

13

14

15

16

17

18

19

20

21

r-i 221 _ 1

6

^

an immediate problem threatens human health, the welfare

or the environment, EPA will take actions.

Now, if efforts to ensure responsible party

response do not seem to prompt action, and EPA's

determination is that actions are necessary, then EPA

can initiate what is called a removal action.

That is a good bit of what has been happening

here at the Avtex site. We have been under a removal

action for almost a year.

These are short-term or so-called short-term

actions to clean up the hazardous site that poses a

threat to human health or the environment. This could

be just the removal of tanks or drums or in some cases a

train derailment or an overturned tractor-trailer, a

removal team would go out.

The situation at Avtex is slightly different.

It is extremely involved, yet we were still under what

is called a removal process.

The second portion of that is called the

remedial action. This is the study , the design, the

construction, the long term, and usually much more

expensive action aimed at a permanent remedy. And tlQu? . .

J

J

J

Page 7: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1 is the phase we are starting to go into now.

2 Bonnie is going to explain the proposed plans

3 for one of the steps of this remedial action.

4 The states have always been encouraged to

5 participate in the Superfund process and states are more

6 formally involved today than ever before in the

7 selection, the initiation, the development of the

8 remedial responses.

9 EPA must develop state participation

10 regulations that will provide for a number of

[ i 11 opportunities to participate, including review, comment

12 on planned documents, involvement in long-term planning

13 activities and participation in negotiations.

14 You should know that we are working very closely

15 with the State of Virginia on this particular site.

16 Based on the principal that the polluter

17 should pay, Superfund contains authorities which allow

18 EPA to ensure that those responsible for hazardous waste

19 problems pay for the clean up.

20 Superfund enforcement authorities enable EPA

21 to encourage responsible parties to undertake clff fffityQ Q 9 9

22 activities and recover fund monies spent for clean up

JR500022

Page 8: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

n O1 from those responsible parties.

2 The clean up actions, in case of imminent

3 hazard to human health or the environment, Superfund

4 authorizes EPA to order the responsible party to

5 undertake necessary actions to control that threat.

6 To accomplish this, the agency can either

7 issue an administrative order or bring a civil action

8 against the responsible party. The new Superfund

9 provides specific procedures for negotiating

10 settlements.

I_1 11 Because the people in the community with the N-X

12 Superfund site personally face the hazardous waste

13 problems associated with that site, EPA encourages

14 community residents to participate in the process of

15 determining the best way to clean it up.

16 To ensure effective and substantive two-way

17 communication from the outset. At each remedial

18 response site, a community relations program is tailored

19 to local circumstances, and often EPA or state staff

20 will interview residents, local officials, civic

21 leaders, learning all they can about the site in jj o ut

r -i 22 the community concerns.

Page 9: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

r

1 In this case, we had a community relations

2 plan that was started quiet a few years ago. And,

3 frankly, it's outdated, so we are in the process of

4 doing a new community relations plan.

5 This is not necessary under a removal action.

6 In this case, Avtex is unique. We are moving into the

7 remedial stage so we are doing a community relations

8 plan.

9 Many of you will probably be interviewed by

10 myself in association with someone from Booz, Alien,

[) 11 learning just how you feel about the situation, what has

12 been happening in the past what, may happen in the

13 future.

14 EPA is also required to publish a notice and

15 brief analysis of the proposed remedial action plan.

16 There are copies over here—that is what we are trying

17 to do tonight—provide an opportunity for the public to

18 comment on that plan, provide an opportunity for a :

19 public meeting to allow for two-way communication on the

20 remedial action of this plan.

21 We must make a copy of the transcript fj^QQQPtl

r 22 public meeting available to the public, and prepare a

Page 10: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10iI 11

12

13

14

15

16

17

18

19

20

21

r -i 221 __ 1

10v^

response to each significant comment made on the

proposed remedial action plan. That is what is taking

place this evening. This will all be available at the

repository in the library.

Community relations activities are somewhat

different during a removal action, where human health

and environment must be protected from an immediate

threat.

During the initial phase of these response

actions, the agency's primary responsibility is to finform the community about actions being taken and the ^

possible effect on the community.

Back around Thanksgiving, it wasn't quite as

formal as we are doing it now, with a community

relations plan. We set up a headquarters in this

building. We went around door to door. We worked

through WFTR and worked the Northern Virginia Daily. We

worked through the newspapers. We walked and talked

with everyone to let you know what was going on here

when we had a situation that was less than optimum. But

now we are going into a very formal process to keeo jfou

informed.v.

J

j

j

Page 11: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

u12

3

4

5

6

7

8

9

10

L 1112

13

14

15

16

17

18

19

20

21

, 22

11

There is another item I should inform you

about. We have a grant program to make funding for

technical assistance available to those who may be

affected by a release, and the purpose of this grant is

to help concerned citizens understand and interpret

technical information.

Some of the materials you will see over in

that repository, it would take you — well, I am not a

technical person. It takes a technical person to go

through and understand and interpret all of the data

that is in there. It's all there, all the testing that

has been done at this site.

But there is money available through what ist ' ,

called a TAG grant. There are certain prerequisites in

order to get this TAG grant. It can be up to $50,000.

The grant recipient must contribute at least 20 percent

of the total cost of that grant, but I should let you

know that that is available.• • £' • ' - .

I am being a lot more formal than I normally

would at a public meeting, but I know that we have to

get these things across in a very specific manner to you

this evening. AR500026

Page 12: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

312

13

14

15

16

17

18

19

20

21

r-i 22LJ

12

What I would like to do now is introduce

Bonnie and let her go through the proposed plan and what

we have available to us.

MS. GROSS: As Bill said, what I am here to do

is explain to you the proposed remedial action we would

like to take at the site.

What I will do first is I will give you a

little bit of background, history, real brief, go

through the preferred alternative and the goals of what

we want to do out there, and conclude it and open it up

for questions.

You have copies of these overheads. If you

can't see them, you can follow along with those.

As I am sure most of you are aware, this is

the Avtex site. It covers approximately 440 acres.

And, just for clarification purposes, we are going to be

talking about actions to take place on the plant portion

of the property, and that is going to be — this is a

railroad line and the tracks, it will be above the

railroad tracks.

EPA first got involved in this site back in

1982 when the Virginia Water Control Board found groundAR500027 "

)

;

;

Page 13: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

13

1 water contamination on the west banks of the Shenandoah

2 River in the Rivermont Acres home wells, over here.

3 Following the discovery of that contamination

4 some of the major activities that have taken place—and

5 these really are just some highlights—in '82, the

6 ground water contamination was discovered, which led to

7 an RIPS and a first operable unit ROD.; - j',..; '''

8 First operable unit dealt with to address the

9 ground water contamination problem that the Virginia

10 Water Control Board originally discovered.

11 And what that did was that it selected a

12 remedy that called for dewatering of three viscose

13 basins, which lets me just kind of bring you back here

14 so you can see what we are talking about. These are

15 down in the disposal area right in here, and pumping

16 ground water.

17 Following that, we issued an administrativei , ^ . ... :

18 order to two of the responsible parties to implement the'" ' •' ." 'V ' ' : . . . '

19 ROD. We are currently in the work plan stage to

20 implement this remedy.

21 In November of '89, Avtex's discharge permit

U22 was revoked following enforcement actions by theAR500028

C

Page 14: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10f\ 11

12

13

14

15

16

17

18

19

20

21

r -i 22i _ 1

14 J^

Commonwealth of Virginia. Following the revocation of

the permit, the facility was abandoned and EPA initiated

an emergency action.

The removal action took place to stabilize a

lot of the contaminated chemicals that were left onsite.

It also maintained freeboard and the sulf ate basins in

the disposal area to protect the Shenandoah River from

continued contamination.

Based on a lot of the work that has been done

by the removal program, we have developed another

operable able unit which is a long-term, what we V

consider to be a more of a long term action to deal with

some of the long term threats.

If you look in your proposed plan, the

proposed plan evaluated only two alternates, basically

taking inaction versus taking no action at this time.

Typically the remedial program goes through a

remedial investigation study which are detailed studies

and evaluate four or five alternatives.

In this case, we have some actions we can take

on specific things that didn't need a lot of design. SoM flRSOOOZPwhat we are doing is we are calling it accelerated - - - . . . T

V-

Fio^nnn^ft

•,j

j

j

Page 15: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

15

1 action.

2 The preferred action addresses ground waste.

3 Approximately 2900 drums have been stabilized and

4 secured and put in a building within the Avtex plant.

5 They now require identification to verify what is in the

6 drums, transportation and disposal.

7 PCB's were also found at the Avtex site,

8 based on some PCS sampling that was initiated in the

9 river. We found two places onsite that contained PCB

10 contaminated soils near the polyester area and the coal

11 yard.

12 This action would allow us to excavate

13 approximately five thousand cubic yards of the PCB

14 contaminated soils and take it to an approved chemical

15 waste land fill for disposal. The action also addresses

16 the acid reclaim facility.

17 The facility structure is in poor condition

18 and continued degradation of the building through the

19 normal weathering process presents a hazard, due to

20 collapse.

21 What we propose to do here is dismantle frB 500030

22 building and demolish the outside structure. Any parts

ARi00030

Page 16: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

l 11

12

13

14

15

16

17

18

19

20

21

r -i 221 __ 1

16

-

that can be resold for value would be sold by the

trustee, who currently is running the site for Avtex,

and some facility components could be sold as scrap.

The rest of the rubble and debris would be left onsite.

And the final element is really contingency,

continued site security control, maintenance, health and

safety. Currently, the trustee is providing this.

It offers protection to human health and environment for

the workers who are currently working on the site.

It also allows us to maintain fire protection,

ventilation systems, and basically to maintain the-

critical systems to keep this plant running and to

prevent any further releases of hazardous substances.

We added this as a contingency because if the

trustee can no longer provide this, we would have the

mechanism to go right in and implement these activities.

The goals of the proposed remedial actions

include the elimination of potential releases of

hazardous substances, specifically the substances that

are contained in drums.

Continued degradation of the building throughAR50003I

the weathering process and an eventual collapse would • -

^

Page 17: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

17

1 cause the release of hazardous substances. We want to

2 eliminate that possibility.

3 The potential collapse of the acid reclaim

4 facility could affect other nearby process buildings

5 which still contain hazardous substances in vessels and

6 process lines.

7 By removing the PCB soils, we also eliminate

8 potential migration of hazardous substances,

9 specifically PCB's into the sewer system, which is

10 currently diverted now into sulfate basins.

i j 11 A good rain or a good flood, right now, that

12 could go into the Shenandoah River, even though FMC is

13 maintaining freeboard, a good storm presents the

14 possibility of introducing more contamination into the

15 Shenandoah River.

16 Dismantling and demolishing acid reclaim

17 facility really provides two benefits to us.

18 It eliminates the safety hazard that would be

19 presented if the facility collapsed. It currently

20 exists as an obstacle for future investigations.

21 We believe this facility to be a siSnif i Pfrl f) f) O p

r i 22 source of ground water contamination. Due to itsO ' ''•"""."

AR§00032

Page 18: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10r ~|1 _ 1 11

12

13

14

15

16

17

18

19

20

21

r -i 221 _ 1

18

^

structural instability, we can't go in there and assess

the ground water condition until we get rid of the

building. So this would allow us to do a more

comprehensive evaluation, as we continue in our actions

at the site.

And finally, the proposed action would

eliminate a reduced potential direct contact threat by

continuing site safety control and maintenance, we

eliminate the possibility of having the public access to

the chemical and physical hazard which still exists at

the site. ^

Estimated costs: this ranges anywhere from $3

million to $1.350 million, as you can see here, and they

are broken down under each activity, keeping in mind

that the site security element here is really a

contingency, but we believe that the estimated costs for

this to be approximately $8.7 million.

In conclusion, I recommend the preference at

this time is to take an action. We think to take an

early action and to continue to deal with the problems

and tackle each one and get the site to a more

manageable state is really our preference.v_

flosnnm

J

J

j

3

Page 19: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

j- T

U

19

1 It achieves the goals I Identified on a couple

2 of slides. It complies with our appropriate

3 requirements .

4 We are required to comply with other laws,-, *

5 such as the Resource Conservation Recovery Act and, in

6 this case, there are PCB's; we have to meet other laws

7 as to what we clean down to and where we dispose of the

8 PCB contaminated soils in a chemically approved

9 landfill. He will be doing that.

10 It also will allow us to do a more

11 comprehensive investigation by getting rid of the acid

12 reclaim facility, and it is consistent with future

13 remedial activities.- . -, .-i1

14 It will contribute to our long-term

15 performance at evaluating and cleaning up the site. The.* ,,i.

16 really good part about this is we feel we can complete

17 this all within a year.fl.:- --- • ., •

18 So it is going to be a quick action and we can

19 see some positive benefits as opposed to, you know, a

20 remedial program is really a long-term program and you

21 don't see things happen typically this quick. -***^.AR50003I*22 And, hopefully, I have made everything - - - -

Page 20: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

i — . 20n1 perfectly clear. We will open it up to any other

2 questions that you might have.

3 MR. TOFFEL: Before you ask your questions, we

4 would appreciate it if you would state your name for the

5 record.

6 MR. GEORGE: I am Ron George, County

7 Administrator of Warren County.

8 In terms of the alternative, we are dealing

9 with none versus one. I assume that staff -wise there

10 were other alternatives considered or obviously there

i _ I 11 had to be something considered in order to come up with

12 this proposal.

13 Are there other things that — I guess when

14 those of us judge, again, a none versus one type of

15 solution, you look at, are there other things that could

16 be done in this first year that would be important that

17 for one reason or another were not included in this

18 proposal? How did this combination of proposal come to

19 be?

20 MS. GROSS: Well, it came to be, I think as I

21 said earlier, these were actions that didn't require a

22 lot of study or design to implement or remedy.r -i

Page 21: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

G 21

1 Most of the situation, the things that exist

2 out there, still require design investigation. We are

3 still finding out about, new things every day.

4 So, in this case, we looked at some actions

5 that we could take that we knew didn't require a lot of

6 design and study time, something we could do quickly,

7 and that is how these came into play. These were some

8 obvious things we could do.

9 MR. GEORGE: So this doesn't preclude other

10 things being done in the future? This is basically the

[ , 11 short-term?\_s ' " .. t - - -12 MS. GROSS: .Yes, this is just a short-term

13 remedial action. Like I said, we still don't have a

14 handle on all of the problems that are out there and

15 there will be a number of more remedial actions to go

16 forth.

17 We have got the whole disposal area to deal

18 with yet. We have got a lot of the plant. There is a

19 lot more work to be done out there. This is just one

20 small piece.

21 MR. CARON: Ron, I will speak to also th(fc D C n n r> /-

r , 22 removal program, the emergency phase. We are not done.

Page 22: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

LJ 11

12

13

14

15

16

17

18

19

20

21

r-i 22i _ I

22

^

Got plenty more work to do.

There are things there, it is a large

facility, it is complex. Time in itself will cause

things to become unstable and then make them

time-critical activities.

We would like to catch things. As I said, way

at the beginning, we are lucky in this site because it

didn't blow up or burn or do the normal things that I'm

used to. We are able to stop it before it actually

happens .

If we can evaluate process lines, structures i

inside the tank and identify things that will become

unstable as time goes, we can deal with them now under

the authorities of emergency, if it's appropriate.

These items, a lot of them you could make into

emergencies. A lot of them also are actions that we can

do with this mechanism in a much more planned approach,

much more formal approach.

I think what we really like about it, it does

allow public input. Now we are working through the

mechanisms we have had during the emergency. It's a

mechanism where we can bring in the input of tneflR500037

'-v

J

)

J

Page 23: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

affected populace in here into the decision-making. We

would like to do that.

MR. TOFFEL: Are there any other questions or

comments? Please.

MR. SEALOCK: Richard Sealock. How come it

took the EPA from 1982 when the ground water was

polluted on the other side of the river , how come it

took until 1988 to realize they had a problem with this

plant? Two questions: how come you haven't done any

study on the Shenandoah River as of yet?

MS. GROSS: ; Well", the Shenandoah River study

is planned in our next remedial investigation which we

will be starting in the next couple of months, where we

do the formal work.

We go through a long-term planning phase and

the Shenandoah River study will be part of that. EPA

goes through a process in order to get the site to where

it is now. !

What happens after 1982 when we found out

about the site, it goes into what we call the

pre-remedial program, 'and what happens there is the v d

a preliminary assessment, site investigation and" then go'

Page 24: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

• -

12

3

4

5

6

7

8

9

10

n12

13

14

15

16

17

18

19

20

21

1 —— 1 221 __ 1

24

^

through a scoring procedure to rank this site for the

NPL, the National Priority List.

Once the site becomes on the National Priority

List, it becomes available for remedial investigation

studies to be done. So the site had to get up into the

NPL stage before any remedial investigation was done.

In this case, the responsible parties did the

remedial investigation, the first remedial investigation

that was done.

The contamination that was found across the

sJ

Shenandoah River were contaminates directly related to j

the disposal area on the Avtex property, those viscose

basins I was telling you about, that was what was

attributed to the ground water contamination.

So we had a negotiation process to go through

in order to even begin the remedial investigation. The

responsible parties did the remedial investigation which

took, I am not exactly sure of the time, approximately

two years.

And then we went through the record of

decision phase, and now we are into the design phase forAfl500039the implementation of the remedy. So there is a lot' of -^

J

Page 25: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

25

1 different steps that go on in order to get it to the

2 point where it is now. The first study was really

3 limited in focus. :M

4 MR. CARON: I think also you need to

5 understand, we are not the only ones that take

6 enforcement actions when something like this is

7 discovered. ,

8 Back in '82, when the ground water

9 contamination was found, immediate steps taken by the

10 Commonwealth at that time were to have Avtex to provide

11 potable water; in other words, eliminate the threat of

12 people drinking the contaminated water. That was done

13 by the Commonwealth. So the people are immediately

14 protected by being given potable water.

15 As you are probably aware, Avtex later then

16 purchased the properties that removed the people from

17 the threat. That was the mechanism that they chose to

18 use.

19 Since the folks were, their immediate health

20 impacts were being handled by the Commonwealth

21 authorities, we are out of the emergency, I <*orfl$g^QQ^ Q

22 to respond. It's being handled by the state, and we can

Page 26: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

\ 11

12

13

14

15

16

17

18

19

20

21

r-i 22

26

V.

get into this evaluation of why we have a ground water

problem.

And, believe me, it's not small, it's a big

deal and it will require quite a lot of evaluation and

still more to be done to determine how we are going to

deal with it. We don't know right now.

MR. CHRISTENSEN: Merle Christensen, Front

Royal. Does that also apply to the waste basins, that

you don't know how to deal with them? You don't know

what is in them?

MR. CARON: We know what is in, believe me. I »

have done an awful lot of evaluation in my program as to

what is in those things so that we can properly treat

the water prior to discharge.

FMC, as you know, has been given an order by

EPA to operate that waste water treatment plant.

Bonnie's program is presently negotiating with them, as

my program is, as to their long-term plans out there.

We know what is in the basins. We have some

technological ideas about how we are going to get them

closed out.

There is some study work that needs to be 31 5000 U*

J

J

j

AR50001H

Page 27: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

G 27

to determine whether or not those things are feasible.

You know, they are on a flood plain and that is not a

good place to have that stuff.

MR, CHRISTENSEN: They also constitute a much

greater threat to the biology of the river and the

people down the river than the plant site itself.

MR. CARON: I concur with that.' •'" •

8 MR. SEALOCK: The second part of my question,

9 were you people ordered to do a study on the river this

10 spring, or requested to start a study this spring?

[i J 11 MS. GROSS: Yes, that was a bill by Senator

12 Warner, I think you are referring to?

13 MR. TOFFEL: Tacked onto an appropriations

14 bill, yes.

15 MS. GROSS: Yes. The first part of that study

16 has been completed and, the best I know, was sent off to

17 Senator Warner.

18 The first part, I didn't explain what the

19 first part was. The first part of that study was to

20 assess the water quality, and they used past data and

21 did a water quality assessment, a historical jiDc.nft

22 The next part will be done through the RIPS*""

Page 28: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

n " o1 process and will evaluate the sites under Superfund,

2 will evaluate the river that way, and that will be

3 starting in a couple of months.

4 MR. SEALOCK: Has that been published or is it

5 over at the library?

6 MS. GROSS: That, I don't believe, is part of

7 the public record. That was done by a different program

8 within EPA, and if you need a copy of that, I can

9 certainly get your name and send you a copy.

10 MR. FORTUNE: Ken Fortune, Front Royal.

I_| 11 Going back to ground water pollution problem \_

12 caused here at Green Acres, Mr; Ron Napier (ph.), who is

13 a resident, lives over there, approached the county and

14 I think they said a contingency fund of about $250,000

15 for the medical related problems to people who lived in

16 the area, and I was wondering if you all have any plans

17 to carry on a study of the residents of that area over

18 long period of time?

19 MS. GROSS: That would be done by the health

20 organizations, and I do know that health department did

21 a study in the area that was recently completed.AR5000U3

22 Dr. Weiss, I believe, just did that and he '

Page 29: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

rw

- -

0

u

i2

3

4

5

6

7

8

9

10

12

13

14

15

16

17

18

19

20

21

22

29

found that there was no, I think it was in relation to

cancer specifically, but he didn't find any problem

associated with the site and any occurrence of cancer.

MR. SEALOCK: Was Dr. Weiss aware of the fact

out of 1200 residents and 12 weekend residents there,

there was seven cases of cancer, which nearly all of

them are dead now or where they can't do anything?

MS. GROSS: I don't know.

EFA also does do health assessments. The

Agency for Toxic Substances and Disease Registry will do

a health assessment as part of the RTFS process, and I

know preliminary assessment was completed for the Avtex

site. - :

MR. CHRISTENSEN; The $8.7 million, will part

of that be from FMC, or this all federal funds?

MS. GROSS: This is a fund financed action.

EPA does take enforcement actions when they have the

legal jurisdiction. In this case, we don't have that

right now. ,

MR. CARON: * FMC is presently incurring all of

the cost associated with the water treatment now fftfSGDQUIi

have been since February, February 26th.

Page 30: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

l 11

12

13

14

15

16

17

18

19

20

21

i — i 221 _ 1

MR.

MS.

30

^

TOFFEL: Yes, ma'am?

CASSIDY: Pat Cassidy from Berryville. As

part of the health assessment that would be done, is

there a contact person that we could share information

with about known health problems we feel are related?

MS. GROSS: You can give me your name and

number and address and I can find out who you can talk

with.

MR. TOFFEL: Are there any other questions

related to the proposed plan?

Yes, sir.S«

MR. FORTUNE: Do you have any idea how many

years it will take for the biological problems in the

river to correct themselves?

MS.

MR.

GROSS: No, I don't, not at this time.

FORTUNE: Are you in contact with the Fish

and Game Commission?

MS.

agencies when

MR.

there a time

MS.

GROSS: We do coordinate with those

we do our work, yes.

SEALOCK: I may have missed it. Is

frame on this next stage?AR5000l*5

GROSS: It will be implemented and " ~ ' •

V_

Page 31: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

31

completed within a year.

MR. CARON: I think also in answer to the

gentleman's question about the river, the Commonwealth

is to establish another round of the fish sampling in

the last two months, so they are keeping an eye on

things in relation to the existing ban on fishing.

I would look at that as a monitoring effort at

this point. That is not a study.

MR. TOFFEL: I really appreciate the fact that

you have kept the questions on the proposed plan.

I would open it up now if you have any

questions pertaining to the site since we do have Bob

here, who has been practically living down there. We

could probably approach some of those questions, too, so

if you have additional questions, please feel free at

this time.

If we have no questions, I will say that we': *".•!":: i * -:

would be dismissed, but we will stay here and answer any

questions if you would like to come up and talk to us

one on one and we will stay around as long as you keep

asking the questions, we'll be here.

Wait, we have one more here, sir.

Page 32: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

r - 22

32^

MR. CHRISTENSEN: Is there any likelihood with

the present problems in the Mideast that funding may be

cut for such operations as this?

MR. TOFFEL: There is always that possibility.

We are up now. You know, our five year period, we were

refunded in '86, so that will be coming up. The number

of dollars that go into the pot are being considered,

although this is, let's call it a priority site, I am

sure we will continue here.

MR. GEORGE: Bill, certainly, I think that as

far as response to this alternative is obviously one ^-

that favors Alternative II over Alternative I. And I

think the only issue probably among those of us in the

community is, you know, are there other things that can

done and how much can be done in this phase?

And I think certainly we appreciate very much

the fact that EPA is here and you have done what you

have done and are continuing to work on it, and we are

sorry that the situation lends itself to being here for

a long term. And I think you all recognize, and we do,

that is what is called for. AR5000U7

And we certainly hope that you have that

J

J

j

Page 33: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

33

1 commitment to try to stay here through this to get this

2 community through this situation.

3 MR. TOFFEL: I think you can be assured that

4 we will be around for quite some time.

5 MR. SEALOCK: What is your best guess on the

6 time frame, for this thing to be safe, for everybody to

7 go back in there and start another factory?

8 MR. TOFFEL: No idea.

9 MR. CAROK: ;If they let me go and gave me all

10 the money I wanted to clean it up, five years, at least,

L J 11 at least; there is that much to do out there. That's

12 not going to happen, by the way. He are not a

13 bottomless pit. a

14 MR. TOFFEL: Liken it to an iceberg, too. You

15 see about this much of the problem and the further we go

16 the more we find, so we really don't know.

17 Yes, sir.

18 MR. FORTUNE: I read an article in the

19 Northern Virginia Daily the other day, a letter to the

20 editor about recycling.

21 Do you think that the power plant co&f$5S 001*8

22 converted for a burn plant or converted where you could

AR5ooo48

Page 34: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

[H 1112

13

14

15

16

17

18

19

20

21

i —— j 221 __ 1

34

^

burn trash?

MR. CARON: This power plant?

MR. FORTUNE: Yes.

MR. CARON: No, not without a lot of capital

equipment cost, which is probably not worth it. Also,

remember, I have a PCB problem over there and an

asbestos problem, and it's 1949 technology and I think

there is a better way to do it now.

MR. CHRISTENSEN: Who is the contact person

for the TAG grants?

MR. TOFFEL: Please get in touch with me and I ^

will make sure that the right person back in

headquarters will get the information. I will get the

initial information but there are certain people that

handle that sort of thing, and I will get them in touch

with you. Please see me.

Don.

MR. DERNER: I just answered a question that

somebody here was asking and I get asked every day and,

you know, I know the answer to it but I think it ought

to appear, and that is, what is that stinking out there?

MR. CARON: There is a lot of theory. Ju8t*pQOUH9

)

J

j

Page 35: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

35

because this plant was shut down doesn't mean that it is

not going to continue to smell to some degree.

Chemistry, and that's really what I want here,

industry that uses sulphur based compounds, are going to

smell. Their wastes are sulphur based wastes, where we

have got basins out there whose conditions change every

time it rains and when the sun comes out.

We may have aerobic conditions one day and

then it will turn into an anaerobic condition, kind of

like a swamp, and all of a sudden, we have got a major

odor problem out there.

We thought at first that it might be our

activities or FMC's activities in draining or providing

freeboard and thereby exposing sludge to the air. We

are not so sure that is what it is any more.

There is a lot of free sulphur compounds that

have very, very low odor thresholds. The folks that

have lived here know exactly what I mean. It doesn't

take very much of that in the air to cause an odor.

What we are doing right now is, some of those

days, we have been aware of some of the complaints. j$%°H n r\ c r\

some of the folks that live near the site. We are going

Page 36: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10

[J12

13

14

15

16

17

18

19

20

21

n 22

36

-

to try our very best to characterize exactly what is in

the air in terms of chemical compounds so we can see, in

fact, those compounds are going to cause any kind of

health problem.

The other thing we are doing is working with

FMC and their contractors on interim measures that we

can take to control the odor, and we are looking at

those things now. There are things that can be done.

We are acutely aware of the problem. If you

can smell it outside of the site, you can imagine what

it smells like on the site.V*.

MR. GEORGE: Let me ask one other thing.

Did this proposal, as far as the Virginia

Department of Waste Management is concerned, have they

sort of signed off on this as also being part of their

proposal or is this something that you propose and they

evaluate?

MR. MARTIN: I am John Martin from the

Virginia Department of Waste Management.

We concur that these actions are actions

necessary to be done now, immediately, to clear, the wayAH50005I

to do the longer term studies. So we do concur with EPA

v_.

J

)

j

Page 37: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

37

1 that these are actions that are necessary that should be

2 done now. We have no problem with that.

3 We have some questions procedurally about how

4 the actions be completed. Right now we believe that

5 they were started as removal actions, really following

6 the removal process, and we believe they should be

7 completed in Bob Caron's program as removal actions.

8 One sidelight of going to remedial actions is

9 that the state has to -come up with the ten percent cost

10 share, and I am sure everybody knows here, the state has

11 been having a considerable budget crunch.

12 So we are working with EPA on this issue,

13 remedial actions versus removal action. In the

14 meantime, we are going forward to try to find funding to

15 get is a ten percent match and make sure this action is

16 not delayed.

17 MR. GEORGE: . So if this went ahead under her

18 program, then the going ahead is something going to be

19 subject to ten percent state money?

20 MR. MARTIN: That is right, the state will

21 come up with $870,000, which is not budgeted and nflto <?f) n n C9

22 item already put into a budget.

Page 38: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10ii 11

12

13

14

15

16

17

18

19

20

21

! — | 22i _ i

38

-

We are talking with EPA and I think it will be

worked out. But just right now we believe it's a

continuation of a removal action and it should go

forward as a removal action.

MR. CARON: Very much procedural related. My

budgets on a national scale in the region are extremely

small. We are small potatoes. We are meant for

emergencies. We don't have that kind of dollar hanging

around. That is not to say that our pot can't be

sweetened.

But, in general, on a yearly basis, I don't .

have much money to work with. We got $13 million for

five states, and we will do, on the average, anywhere

from 24 to 52 actions in the course of a year.

And, of course, this site, we obligated $9

million of our $13 million ceiling here. It made a

severe dent in our ability to respond to anything else

that was happening. And, believe me, there is stuff

happening every day that we are spending money on.

MR. SEALOCK: What happened to all that money?

I thought the fund had quite a few billion dollfl1ffc: n n n c o

They done Love Canal, which they are selling back againV-

J

J

J

Page 39: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

r-i 39

1 to the people that are crazy enough to move back on it.

2 MR. CARON: It's still there. The money is

3 not in my program. It all went to Bonnie's. (Laughter.)

4 MR. SEALOCK: Who actually owns the Avtex

5 property? Wouldn't the state get some money back out of

6 that eventually when it was cleaned up? Would it be

7 worth something? :;

8 MR. MARTIN: I don't think the value of the

9 property is anywhere close to the magnitude of the

10 dollar we are talking about.

11 MR. CARON: The legal situation there is

12 extremely complicated right now. As you know, Avtex

13 declared Chapter 11 bankruptcy, which is a

14 reorganization, protection of the assets, things like

15 that, and the list of creditors in this particular

16 instance was rather long.

17 The bankruptcy Judge has appointed a federal

18 trustee to administer the bankruptcy in general, and

19 that gentleman definitely has his hands full with a

20 great many legal issues.

21 He has got liquidation to perform out thetOT500051*

22 It's a difficult and complex task. So, who owns it? I

G

uAR§0005l»

Page 40: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

ni2

3

4

5

6

7

8

9

10n12

13

14

15

16

17

18

19

20

21

r-i 22U

40

^

would say, eventually, we do. The Federal Government

does.

Part of the requirements of the Superfund law

is that, as Bonnie said earlier, we don't just run

around spending taxpayer money cleaning stuff up.

It's a law that we enforce. If we can't get

the responsible parties to do the clean up, then we will

do it, but we will, where possible, take civil action to

recover our money so it goes back in the coffer so we

can use it on another site.

So when all of this shakes out in the wash,'

and who gets what and all that other stuff, there's a

lien that is on from the state which covers some county

activity. Of course, we have a very large lien in place

right now. There are secured creditors. The list is

long.

MR. TOFFEL: Where does that all money go in

region III, which is Pennsylvania, Maryland, Delaware,

Virginia, West Virginia And the District. We have over

180 Superfund sites that we are working on at this time,

and obviously there are 10 regions in the country. This

money is divided up among those regions. AnpUUUuD

V

J

J

y

Page 41: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

22

41

When you throw in Pennsylvania and this area,

you are talking about the industrial rust belt, where we

have a number of very, very expensive sites, such as

Avtex or Publicar (ph.) in Philadelphia, or some severe

lead problem sites, an old battery crushing facility up

in northeast Pennsylvania.

So the money is being is spent and I might say

despite the things you see in the papers or some

editorial cartoons, rather prudently. We are watched

extremely carefully on how we spend these dollars.

But there are an awful lot of sites, and we

keep finding new ones.

If we have no addition questions, I will say

that I thank everyone for being very, very cooperative.

As I said before, we will be up here to answer

any one on one questions to help you out. We will be

here as long as need be.

Thank you very much.

(Whereupon, the hearing was concluded at

approximately 7:55 p.m.)

1R500056

Page 42: ORIGINALORIGINAL THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY-REGION III IN RE: : AVTEX FIBERS SUPERFUND SITE : PUBLIC MEETING : August 22, 1990.*,.•,: Front Royal, Virginia

n

1

i _ r

42

s-

CERTIFICATE OF REPORTER

I, Carolyn P. Stabner, a court reporter, do

hereby certify that I reported, by stenotypy, the

proceedings had and/or testimony adduced, upon hearing

in the above-styled case.

I further certify that I have caused to be

transcribed the foregoing proceedings to the best of my

ability, as taken from my stenotype notes.

,s\ / ft

t/Carolyn P. Stabner

S

AR500057

V-j