9
PRESENTATION OF OT CONTROL

Upload: robin-bhuiyan

Post on 10-Apr-2017

65 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: OT CONTROL

PRESENTATION OF OT CONTROL

Page 2: OT CONTROL

WHY EXCESS OT

1. Not fulfill Hourly Target.2. Not so good Relation with operator.3. Tendency to get excess OT.4. INPUT DELAY from Cutting Section5. Hourly Packing Production

Monitoring

Page 3: OT CONTROL

EFFECTS OF OT

Page 4: OT CONTROL

OT CONTROL

Page 5: OT CONTROL

OT CONTROL POLICY IN MIPayroll/Floor 275 OP

10% absentism 250 op

Budgeted OT wh 2.5 Hr

Working Day,feb'2016 24 days

Budgeted OT with 10% Absentiesm, Feb'2016 15000 hrs

So , Budgeted OT 625 hrs /Day

Page 6: OT CONTROL

What to do for controlling OT1. Try to meet the target within 10 hrs or 10.5 hrs

2. Everyday Leave Operator after 5 pm.

Page 7: OT CONTROL

What to do for controlling OT

3. During Layout leave the operator after 5.oo PM. Technician will complete the layout

4. Check the input during 3 to 4 pm ,if input is delay for upcoming hrs or next day ,leave the

operator after 5 PM

5. IF Backlog is occur in the middle of the line, leave the operator before backlog of the process

Page 8: OT CONTROL