OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office of Project Letting Manager; Wynnette Gentemann, Procurement Oversight & Construction Mngr December 10, 2008 Bid & Award Construction Contract Phase 4

Upload: christine-griffin

Post on 18-Jan-2018

218 views

Category:

Documents


0 download

DESCRIPTION

OTC Pres: Bid & Award Phase 4 12/08 Page 3 Bid & Award PS&E Review Estimate Advertisement Procurement Award Stakeholder Involvement Small Contracting

TRANSCRIPT

Page 1: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 1

Project Delivery Performance ImprovementReport to the

Oregon Transportation Commission

Eryca McCartin,Office of Project Letting Manager;

Wynnette Gentemann, Procurement Oversight & Construction Mngr

December 10, 2008Bid & Award Construction Contract

Phase 4

Page 2: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 2

Project Delivery Process

Page 3: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 3

Bid & Award

• PS&E Review• Estimate• Advertisement• Procurement

• Award • Stakeholder

Involvement• Small Contracting

Page 4: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 4

PS&E Review/Estimate • Review of project package from region• PS&E checklist• Final engineer’s cost estimate

– Confidential• Final estimate lines up with project

funding

Page 5: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 5

Final Engineers Estimate

• Confidential• Created prior to bid opening, used as

comparison with low bid• Evaluate market value of bid

items/monitor commodities pricing information for cost escalation items

• Provides unbiased economic evaluation and recommendations

Page 6: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 6

PS&E Review/Estimate • Approval to advertise• Provide contract documents to OPO

and Project Managers Office• PS&E review process and final

engineer’s estimate completed in 2 weeks

• Coordinate additional 3 week review period by FHWA on full federal oversight projects

Page 7: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 7

Advertisement • Printing – state printer (2 weeks)• Copy of ad for each project to be bid for

publication to Daily Journal of Commerce– Hard copy & electronic

• Ad posted on OPO Website and Bid Express• Communication with bidders exclusively

through OPO and Project Manager’s Office

Page 8: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 8

Procurement• Bid opening • Bid review for responsiveness and

responsibility• Bid analysis to determine if award or

rejection is in the best interest of the public

• Recommendation to award or reject

Page 9: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 9

Procurement: Bid Opening Schedule

• Bid openings primarily on Thursdays• Encourage competition by

– Less 10 projects per bid opening– Restricted bid dates for select projects

(generally high complexity or high $$)– Balance location and primary work type– Electronic bidding capability– Continually monitoring bid pool and results

and making adjustments if warranted

Page 10: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 10

Procurement• Notice of intent to award• 3 day timeframe for protest filing• Construction authorization• Review and execution of contract

Page 11: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 11

Construction Authorization

• Prepared by OPO• Provide overview of costs that will be incurred• Informational items

– Engineer’s estimate– Name of low bidder– Funding deposits received from others

• Construction authorization– Lowest responsive bid– Construction engineering budget– Contingencies– Anticipated items

Page 12: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 12

Final Approval

• Chief Engineer• Deputy Director• OTC• FHWA• Notice to Proceed

Page 13: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 13

Award • Contract executed within 57 days of bid

opening• 200599% executed within 57 days• 200691% executed within 57 days• 200798% executed within 57 days• 200895% executed within 57 days• Most are executed in 40 days or less

Page 14: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 14

Timeframes• PS&E to bid opening - 45 days to 80 days

– PS&E review, estimate, approvals (2w)– FHWA oversight review (3w) (only specific projects)– Print, send to advertisement, distribute plans (2w)– Advertisement (3-5w) based on project size and

complexity)• Bid opening to notice to proceed – 57

days • Bid and award (Total)

– 85 days or less is typical project– 137 days maximum

Page 15: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 15

Reasons for delay• Protest• Lawsuit• High bid price (analysis/justification)• Local agency project budget approval• Disadvantaged Business Enterprise

goal compliance• Receipt of Insurance Certificate

Page 16: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 16

Stakeholders(construction contractors)

• Coordination via Association of General Contractors

• Key issues– Bid advertising– Rejection of bids– Protest filings

Page 17: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 17

CostsPhase Modernization Bridge Preservation Safety/Ops

Planning 9.1% 5.2% 0.4% 3.0%

Design 9.1% 5.4% 6.7% 13.0%

RoW / Utility Relocation 3.4% 1.3% 1.6% 4.5%

Bid & Award 0.1% 0.1% 0.2% 0.8%

Construction Engineering        

Construction        

Total (%) 21.7% 12.0% 8.9% 21.3%

Page 18: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 18

Continuous Improvements

completed• Electronic bidding (Bid Express)• Contractors web portal • Streamlined PS&E review phase• Close coordination on bid planning with

OTIA projects• PS&E metrics• PS&E checklist

Page 19: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 19

Continuous Improvements

Future• Electronic bid document distribution• Continue to streamline process from

PS&E submission to award for small projects

• OPO procurement vs region procurement

• Small contracting web presence

Page 20: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 20

Continuous Improvements

Small Contracting• Directors commitment to diversity• 9th Circuit ruling impacts• Disparity study (African American /

Asian)• FHWA waiver• Assistance for small business to get

involved with electronic bidding

Page 21: OTC Pres: Bid  Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office

OTC Pres: Bid & Award Phase 4 12/08 Page 21

Discussion