other samples
DESCRIPTION
ÂTRANSCRIPT
Other Samples Andrew Hansen
Contents
Architecture
02 Fire Station Document Set_Revit14 Wall Sections / Assemblies_Revit16 Daylighting Analysis_Ecotect20 Computational Design_Grasshopper26 Drafting_AutoCAD28 Structural Detailing_AutoCAD
Construction Management
34 Sustainability Assessment_LEED v.340 Scheduling / Estimating_Primavera46 BIM Use Plan_Process Design48 MRW Facility_Design/Build
01
EXISTING BUILDING
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1" = 40'-0"
8/15
/201
2 8:
09:5
1 PM
A-000
COVER SHEET
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
A-302 WALL SECTIONSA-503 INTERIOR ELEVATIONSA-502 INTERIOR ELEVATIONSARCHITECTURALA-000 COVER SHEETA-101 LEVEL 1 FLOOR PLANA-102 LEVEL 2 FLOOR PLANA-103 ROOF PLANA-201 BUILDING ELEVATIONSA-202 BUILDING ELEVATIONSA-211 BUILDING SECTIONSA-212 BUILDING SECTIONSA-301 WALL SECTIONSA-311 EXTERIOR DETAILSA-401 ENLARGED PLANSA-411 VERTICAL CIRCULATIONA-501 INTERIOR ELEVATIONSA-511 INTERIOR DETAILS
A-601 SKYLIGHTA-602 CUSTOM HANDRAILA-603 TERRA COTTA RAINSCREENA-605 RENDERINGSA-604 ALUMINUM RAINSCREEN22
SHEET INDEXCONSULTANT LIST
No. Description Date
Perspective - NE corner
SITE PLAN - PROJECT NORTH
0' 20' 40' 80'
Perspective - Interior
Fire Station Document Set_Revit
02
UP
UP
2A-211
1A-211
2615 SF
APP BAY
161 SF
AES Ladder
96 SF
AES Engine
211 SF
DecontaminationRoom
333 SF
Station Office
484 SF
Lobby
106 SF
Restroom
166 SF
Restroom
215 SF
Bunk
211 SF
Office699 SF
Bunker Gear278 SF
Maintenance WorkArea
69 SF
Comp
117 SF
Hose
148 SF
EMS Storage
1 2 3 4 5 6
A
B
C
E
79 SF
DisasterSupply
98 SF
Janitor
D
112 SF
CommRoom
154 SF
Stor
3A-211
143
573' - 0"
EQ EQ57
3' - 0"
573' - 0"
EQ EQ EQEQ
1A-302
2A-301
3A-301
A-501
4
1
2
3
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
09:5
4 PM
A-101
LEVEL 1 FLOORPLAN
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
LEVEL 1
0' 4' 8' 16'
03
DN
DN
REF. REF.
REF
.
REF.
2A-211
1A-211
1 2 3 4 5 6
A
B
C
E
D
93 SF
Double Bunk
83 SF
Janitor
93 SF
Double Bunk
109 SF
Laundry
93 SF
Double Bunk366 SF
Fitness
215 SF
Day Room
393 SF
Kitchen/Dining
573' - 0"
573' - 0"
573' - 0"
573' - 0"
573' - 0"
573' - 0"
573' - 0"
573' - 0"
109 SF
Single Bunk 108 SF
Single Bunk
109 SF
Single Bunk
68 SF
Single Bunk
68 SF
Single Bunk
68 SF
Single Bunk
55 SF
Lockers
54 SF
Lockers
55 SF
Lockers
53 SF
Lockers
53 SF
Lockers
53 SF
Lockers
78 SF
Toilet
76 SF
Toilet
78 SF
Toilet
179 SF
Storage
3A-211
573' - 0"
573' - 0"
11957
3' - 0"
653' - 4"
653' - 4"
613' - 0"
613' - 0"
3' - 9 3/8" 3' - 9"
1A-302
2A-301
3A-301
Open
EQ EQ EQ EQ EQ EQ
EQ EQ EQ EQ EQ EQ
EQ EQ EQ EQ EQ EQ
A-502
EQEQ
EQEQ
EQEQ EQ
EQEQ
EQEQ
EQ
EQEQ
EQ
653' - 4"
EQ EQ
EQ EQ
2
3
4
A-5025
6
7
8
A-5031
2
4
3
A-503 5
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
09:5
6 PM
A-102
LEVEL 2 FLOORPLAN
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
LEVEL 2
0' 4' 8' 16'
04
2A-211
1A-211
1 2 3 4 5 6
A
B
C
E
D
1" /
12"
1/4"
/ 12
"1/
4" /
12"
1/2" / 12"
3A-211
1/4" / 12"
1A-302
6A-601
8A-601
5A-601
7A-601
1A-601
2A-601
4A-601
3A-601
2A-301
3A-301
1/4"
/ 12
"1/
4" /
12"
1/2" / 12"1/2" / 12"
A-503
2
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
09:5
6 PM
A-103
ROOF PLAN
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
ROOF
0' 4' 8' 16'
05
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
123456
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
ABCE D
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
10:0
3 PM
A-201
BUILDINGELEVATIONS
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
NORTH ELEVATION
EAST ELEVATION
06
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
1 2 3 4 5 6
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
A B C ED
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
10:0
9 PM
A-202
BUILDINGELEVATIONS
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
SOUTH ELEVATION
WEST ELEVATION
07
LEVEL 168' - 0"
2A-211
LEVEL 284' - 0"
ROOF100' - 0"
1 2 3 4 5 6
3A-211
5A-6012
A-601
2A-301
3A-301
LEVEL 168' - 0"
1A-211
LEVEL 284' - 0"
ROOF100' - 0"
ABCE D
LEVEL 168' - 0"
1A-211
LEVEL 284' - 0"
ROOF100' - 0"
A B C ED
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/8" = 1'-0"
8/15
/201
2 8:
10:1
1 PM
A-211
BUILDING SECTIONS
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
SECTION 1
SECTION 2 SECTION 3
08
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
A
A-3011
W22
W21
653' - 4"
W21
F10
R10
LEVEL 168' - 0"
LEVEL 284' - 0"
ROOF100' - 0"
A
A-3014
CW1
F11
HSS6X6X1/2
W22
LEVEL 284' - 0"
A
W21
F10
W22
EXTRUDED ALUMINUM CAP
2x14 MOUNTING PLATE
NBK MOUNTING CLIP@EACH PANEL CORNERTYP.NBK VERTICAL CARRIER TRACKALUMINUM40mm THK. NBK TERRACOTTA TILE
2x8 TOP PLATE
LEVEL 284' - 0"
A
5/8" GYPSUM WALL BOARD2" RIGID INSULATION2" AIR GAPBRICK, BROWN
NBK VERTICAL CARRIER TRACKALUMINUM
8" METAL STUD
40mm THK. NBK TERRACOTTA TILE
NBK MOUNTING CLIP@ EACH PANEL CORNERTYP.
W21
F10
W22
L6x4x1/2 STEEL ANGLE
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
As indicated
8/15
/201
2 8:
10:1
2 PM
A-301
WALL SECTIONS
0800
Fire StationT4_Graesser/Hansen
08 August 2012ANDREW HANSEN
Checker
No. Description Date
Wall Section 2 Wall Section 3 Detail - Parapet
Detail - Stacked Wall
09
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/2" = 1'-0"
8/15
/201
2 8:
10:1
6 PM
A-501
INTERIORELEVATIONS
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
OFFICE - WEST OFFICE - NORTH
OFFICE - EAST OFFICE - SOUTH
10
W22
CW1
W21
NBK Vertical Carrier Track@ max 10'-0" O.C.
NBK 40mm Thick Terra CottaRainscreen Panel
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
8/15
/201
2 8:
10:3
7 PM
A-603
TERRA COTTARAINSCREEN
0800
Fire StationT4_Graesser/Hansen
08 August 2012Andrew Hansen
Checker
No. Description Date
Perspective - Terra Cotta Rainscreen
Axon - Terra Cotta Rainscreen
11
Aluminum PanelPowdercoat Painted
Aluminum Carrier Track
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
3" = 1'-0"
8/15
/201
2 8:
10:4
0 PM
A-604
ALUMINUMRAINSCREEN
0800
Fire StationT4_Graesser/Hansen
08 August 2012ANDREW HANSEN
Checker
No. Description Date
Perspective - Aluminum Rainscreen
Detail - Aluminum Rainscreen Joint
12
www.autodesk.com/revit
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
12" = 1'-0"
8/15
/201
2 8:
10:4
2 PM
A-605
RENDERINGS
0800
Fire StationT4_Graesser/Hansen
08 August 2012Author
Checker
No. Description Date
Perspective - NE corner_3
Perspective - Stair
Perspective - Entry
LobbyKitchen
13
Level 10' - 0"
Level 212' - 0"
Roof @ Writing Den24' - 0"
1
1/4" 1'-0"
ALUMINUM PARAPET CAP
ALUMINUM SCUPPER
MOISTURE BARRIER
1/4" BITUMINE BASED SHEET
6" RIGID INSULATION
2x12 @ 24" OC5/8" GYPSUM BOARD
3/4" OAK FLOORING5/8" PLYWOODBATT INSULATION12" TJI @ 2'-0" OC
5/8" PLYWOOD
5/8" GYPSUM BOARDPAINTED WHITE3/4" PLYWOOD SHEATHING
2x6 STUDS @ 16" OCBATT INSULATION
3/4" PLYWOOD SHEATHING1x3 BATTENS @ 24" OC
1x6 REDWOOD CLADDING
13
10
2x14 FASCIA BOARD5/8" GYPSUM BOARD
8" CONCETE, CAST-IN-PLACE2" RIGID INSULATION
1" AIR GAP
STONE CLADDING
6" CONCRETE SLAB, CAST-IN-PLACE
3" SAND3" GRAVEL
MOISTURE BARRIER
Level 212' - 0"
Roof @ Writing Den24' - 0"
5/8" GYPSUM BOARDPAINTED WHITE
2x6 STUD @ 16" OC
5/8" GYPSUM BOARDPAINTED WHITE
Scale
Date
Drawn By
Checked By
Project Number
ConsultantAddressAddressAddressPhone
ConsultantAddressAddressAddressPhone
ConsultantAddressAddressAddressPhone
ConsultantAddressAddressAddressPhone
ConsultantAddressAddressAddressPhone
3/4" = 1'-0"
3/15
/201
3 3:
51:0
9 PM
A101
Wall Sections
Jones
Jones Residence
Bill ZimmermanAndrew Hansen
3/12/13007
3/4" = 1'-0"1 Exterior Wall Section
Window Schedule
CladdingDaylight
Area Description Glass TypeHeadHeight Lites High Lites Wide
Manufacturer Mark Model
NominalHeight
NominalWidth Sill Height Type Mark URL
WindowType
Aluminum-Marvin-Bronze
11 SF 3664 DBHG IG Low E IIwith Argon
8' - 1011/16"
1 1 MarvinWindowsand Doors
10 CUDH3028 5' - 4" 3' - 0" 3' - 6 5/16" 13 www.marvin.com
CladUltimateDoubleHung
Railing ScheduleAssembly
Code ManufacturerManufacturer Website Mark Model
ProductData
RailingHeight
TypeComments Type Mark URL
C2010400 Seco South, Inc. www.secosouth.com
10 Seco South- 36" -FB3-2000 -w/3/16"Cable andStudTerminations - FasciaMount
http://www.arcat.com/arcatcos/cos35/arc35411.html
3' - 0" 2000 Series 10 www.secosouth.com
3/4" = 1'-0"2 Interior Wall Section
No. Description Date
3 Axonometric
Wall Sections / Assemblies_Revit
14
KOLSTRAND BLDGGraham Baba Architects
Revit Assembly Model_Andrew Hansen
KOLSTRAND BLDGGraham Baba Architects
Revit Assembly Model_Andrew Hansen
15
PERFORMANCE OF ORIGINAL DESIGN PAGE 5
DESCRIPTION
Solar AnalysisThe analysis of the modular classroom includes lighting performance and illuminance levels throughout the space as well as insolation and thermal analysis.
The goal of this analysis is to determin if the lighting levels are adequate for a learning environment.
Shadow RangesThe operating hours of the classroom typically occur during normal school hours. For the purposes of this shadow range study, the hours were limited from 9am to 5pm. The surrounding context did not come into consideration for this example due to the fact that a portable classroom could be placed anywhere on a given site.
One notable thing is that the north side of the building is shaded throughout the year giving students a comfortable place to enjoy the outside without direct sunlight.
Shadow Ranges
June
21
9am
-5pm
Dec
embe
r 21
9am
-5pm
Daylighting Analysis_Ecotect
16
PERFORMANCE OF RE-DESIGNED BUILDING PAGE 14
DESCRIPTION
Re-DesignFor the purposes of this analysis, I am choosing to focus on the lighting levels for the space as it would seem to have the greatest impact on the performance of the learning environment and was identified as a problem area from initial analysis results.
Re-Designed Building Strategy
17
PERFORMANCE OF RE-DESIGNED BUILDING PAGE 16
DESCRIPTION
Re-DesignEach solution on its own is not sufficient. A combination of solutions to address specific condition yields a combined result that edges toward acceptability.
Re-Designed Building Strategy
18
PERFORMANCE OF RE-DESIGNED BUILDING PAGE 17
DESCRIPTION
Re-DesignWith all three systems combined, the lighting inside the space is controled in a manner that provides relatively even light across the space and addresses the needs of the classroom.
Re-Designed Building Strategy
19
The initial sketch provides constraints and basic geometry for the pieces of the assembly. Each dimensional constraint can be controlled via a data table.
Computational Design_Grasshopper
20
“Connecting the Dots”
Deviating slightly from the tutorial, the option to right click and select “shortest list” was not available in the most recent release of Grasshopper.
The “shortest list” option had to be inserted as a separate component to achieve the desired effect. This eliminated any extraneous lines between non-matching points
21
Forming the tricordal truss
I added a truss width calculation to form the second top cord of the tricordal truss.
This same width value was related to the bottom chord “x” position by a value of .5, thereby always centering the bottom chord as the width changes.
22
A vertical shading device made out of sheet metal could provide varying degrees of shading by adjusting the depth, and angle at various points along its length.
This illustrates the basic parameters and assembly relationships.
23
Various plug-ins exist which facilitate interoperability between grasshopper and Revit. Namely, Chameleon and Hummingbird are the two that I explored for this exercise.
Chameloeon (Left) has curtain grid generation tools as well as the ability to import geometric data from the revit environment into grasshopper.
24
Chameleon also exploits the adaptive component functionality within Revit. The creation of a simple adaptive component is shown on to the left. Essentially, various surfaces or forms can be controlled and placed in the model using dynamicly adjustable control points at the vertices. As with any other family in Revit, parameters and constraints can be added to increase intelligence of the model and provide ease of fexibility in a controlled manner. For instance, an elevation offset point, hosted by an adaptive point had been assigned an instance parameter for “offset”, allowing this dimension to be controlled in the Revit project.
25
03
04 05
02
01
0908
07
06
1
FLOOR PLANSCALE 1/8"=1'-0"
N
ANDREW HANSENCONTSRUCTION TECHNOLOGIES IIUNLV - SPRING 2010PROFESSOR JAY BARRY
1. USE NOM. 4' CROSS TEE SPACED2'-0" O.C. ARMSTONG PRELUDE XL
2. INSTALL PER ASTM C636
3. FIELD VERIFY ALL CONDITIONSAND DIMENSIONS
SYMBOL LEGEND
WALL SCONCE
PENDANT LIGHT
TRACK LIGHT
CHANDELIER
RECESSEDFLUORESCENT LIGHT
RECESSED CAN LIGHT
FIRE SPRINKLER
NIGHT CLUB
NIGHT CLUB
4/22/2010
AS NOTED
REFLECTED CEILING PLANSCALE 1/8"=1'-0"
A1
A1 - BAR ELEVATIONSCALE 1/8"=1'-0"
A2 - LOUNGE ELEVATIONSCALE 1/8"=1'-0"
A2
DANCE FLOOR
LOUNGE
BAR
KITCHEN
LOCKERSBATH
MEN'S ROOM WOMEN'S ROOM
ENTRY
PATIO
DINING ROOM
DOOR AND FRAME SCHEDULEDOOR FRAME
NOTESMARK
SIZEMATL MATL
WD HGT THK
01 8'-0" 6'-8" 2" STEEL STEELDOUBLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
02 3'-0" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
03 3'-0" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
04 2'-6" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
05 3'--0" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
06 2'-6" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
07 2'-6" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
08 3'--0" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
09 3'--0" 6'-8" 2" STEEL STEELSINGLE HUNG DOOR
IN WRAP AROUNDMETAL FRAME
FLOORING SCHEDULEMARK MATL NOTES
PATIO CONCRETE CAST IN PLACE, BRUSHED FINISH
ENTRY NATURAL STONETILE
DAL-TILE HIGH-LOW SPLIT FACEURBAN BLUESTONE
DANCEFLOOR MAPLE LAID AT 112 DEG AND STAINED
FINISHED NATURAL
WOMEN'SROOM CERAMIC TILE DAL-TILE MOKA CROSS-CUT Si 32;
OFFSET SEAMS AS SHOWN
MEN'SROOM CERAMIC TILE DAL-TILE MOKA CROSS-CUT Si 32;
OFFSET SEAMS AS SHOWN
KITCHEN CERAMIC TILE DAL-TILE GOLD GLAM P264
BAR NATURAL STONETILE
DAL-TILE HIGH-LOW SPLIT FACEURBAN BLUESTONE
LOUNGE STEEL DAL-TILE LINEAR POLISHEDURBAN BLUESTONE
D1
D1 - ACOUSTICAL TILE CEILINGSCALE 3"=1'-0"
JAMB CONDITION
SILL CONDITION
D2 - FRAMELESS GLAZING DETAILSCALE 1 1/2"=1'-0"
30" S
ILL
CHERRY SHELVING, NATURAL
CHERRY CABINETRY WITHFROSTED GLASS INLAY
CHERRY CABINETRY BAR
1x4 CHERRY PANELINGWITH 1x4 CHERRY CAP
BAMBOO SCREEN
LEATHER BOOTH SEATING
2 E
Q R
@ 6
"
1 T @ 12"
1' T
OTA
L R
ISE
D3 - STAIR PROFILESCALE 1 1/2"=1'-0"
DAL-TILE LINEAR POLISHEDURBAN BLUESTONE
D3
D2
1/2" CHERRY CAP
SCALE: 1/8' = 1'-0"
1/2" 1"0 2"
13'
13'
Drafting_AutoCAD
26
14" CONCRETE FLOORR14 BATT INSULATION
2X6 WOOD STUD@16" O.C.
2" LAYER OF SAND
6-mil POLYETHELYNEMOISTURE BARRIER
WELDED WIRE FABRIC
1x LEDGERLET INTO STUDS
2x BLOCKING
ROOF JOISTS
4" LAYER OF GRAVEL
5" RIGID INSULATION
REINFORCED EPDM
OSB OR PLYWOODSHEATHING
ZINC COPINGSee Detail 1
EXTRUDED ZINCRAINSCREEN SYSTEM
See Detail 2
1/2" DRYWALL
4" CONCRETE FLOORR14 BATT INSULATION
2X6 WOOD STUD@16" O.C.
2" LAYER OF SAND
6-mil POLYETHELYNEMOISTURE BARRIER
WELDED WIRE FABRIC
4" LAYER OF GRAVEL
OSB OR PLYWOODSHEATHING
1/2" DRYWALL
WEEP HOLES @ 24" O.C.
FLASHING
BUILDING PAPERLAPS FLASHING
LIMESTONE VENEER
BUILDING PAPER
1" MIN CLEARAIR SPACE
ALUMN. FASCIA &VENTED SOFFIT
DRIP FLASHING
VENT BLOCK
CORUGATED METAL ORADJUSTABLE WIRE TIESFASTENED TO WALLSTUDS; SPACE NOMORETHAN 16" HORIZONALLYAND 24" VERTICALLY
ROOF FELTUNDERLAYMENT
LOCKED SEAMCOPPER ROOF
OSB ROOF DECKING
LAP SEALANTSPLICING CEMENT
MECH. FASTENERS @12" O.C. MUSTPENETRATE INTOROOF DECK
4" CONCRETE FLOORR14 BATT INSULATION
2X6 WOOD STUD@16" O.C.
2" LAYER OF SAND
6-mil POLYETHELYNEMOISTURE BARRIER
WELDED WIRE FABRIC
4" LAYER OF GRAVEL
OSB OR PLYWOODSHEATHING
1/2" DRYWALL
ALUMN. FASCIA &VENTED SOFFIT
VENT BLOCK
CONCRETESHINGLE TILES
PLYWOOD DECK35LB ROOFING FELT
4" CONCRETE FLOOR
BUILT-UP POST @ 10' O.C.W/ CONTINUOUS EDGE
MEMBERS
6" MIN
2" LAYER OF SAND
6-mil POLYETHELYNEMOISTURE BARRIER
GRADE
WELDED WIRE FABRIC
4" LAYER OF GRAVEL
1x6 CEDAR ROOFDECKING
No.1 CEDAR SHINGLES30LB ASPHALTSATURATED FELT@ 18" WIDE UNDERLAYMENT
4x10 RAFTERW/ DECORATIVELYSHAPED END
1/4" THROUGHBOLTS AS SPEC'D
BY ENGINEER
FASCIA TRIM
ANCHOR GUTTER BAR
ANCHOR BOLTS@ 24" O.C.
EXTRUDED ALUMINUMCOPING SUPPORT
EXTRUDED ZINCPANELS
EXTRUDED ALUMINUMCARRIER TRACK
2x6 WOOD STUD
EXTERIOR SHEATHING
EXTRUDEDZINC PANEL
CARRIER TRACK
MOUNTING BRACKET
6" MIN
GRADE
6" MIN
GRADE
6" MIN
GRADE
20'-0"17'-0"
10'-0"
15'-0"13'-0"
20'-0"
20'-0"
10'-0"
20'-0"
20'-0"
13'-0"10'-0"
15'-0"
124
126
126
122
126
DR
AIN
AG
E
DR
AIN
AG
E
10'-6"
8'-5"
17'-6"
15'-3"
SCUPPERS
MOISTURE BARRIER
STUCCO FINISH
2
3
4
1
DETAIL 1 - PARAPET COPING DETAILSCALE 3"=1'-0"
DETAIL 2 - RAINSCREEN ATTACHMENT COND.SCALE 3"=1'-0"
WALLL SECTION 1SCALE 1/2"=1'-0"
WALL SECTION 2SCALE 1/2"=1'-0"
WALL SECTION 3SCALE 1/2"=1'-0"
WALL SECTION 4SCALE 1/2"=1'-0"
EAST ELEVATIONSCALE 3/32"=1'-0"
SOUTH ELEVATIONSCALE 3/32"=1'-0"
WEST ELEVATIONSCALE 3/32"=1'-0"
NORTH ELEVATIONSCALE 3/32"=1'-0"
ROOF PLANSCALE 3/32"=1'-0"
N
ANDREW HANSENCONTSRUCTION TECHNOLOGIES IUNLV - FALL 2009PROFESSOR JAY BARRY
1. THIS OPEN-AIR SEATING ANDGATHERING AREA IS COVERED BY APOST AND BEAM ROOF SYSTEMWITH CEDAR PLANKS AND SHINGLES
2. THE MAIN ENTRY FEATURES A HIPROOF WITH OVERLAPPINGCONCRETE SHINGLES.
3. THE MAJORITY OF THESTRUCTURE IS BUILT USING ASINGLE-PLY FLAT ROOF SYSTEM.THIS AREA IS ALSO CLAD WITH ANEXTRUDED ZINC RAINSCREENSYSTEM THAT UTILIZES CHANNELDRAINAGE TRACKS AND CARRIERTRACKS. THE SYSTEM ATTACHESDIRECTLY TO THE SUPPORTSTRUCTURE OF THE BUILDING ASSHOWN IN DETAIL 2.
4. THE HIGHLIGHT OF THERESTAURANT IS THE KITCHEN. THISCAN BE SEEN FROM BOTH THEINSIDE AND THE OUTSIDE. ITFEATURES A LOCKED SEAM COPPERROOF SYSTEM AND TIGHTLYSTACKED LIMESTONE VENEER ASCLADDING.
THE WALL RESTAURANT1234 RESTAURANT BLVDLAS VEGAS, NV 12345
THE WALL
11/24/2009
AS NOTED
27
Structural Detailing_AutoCAD
28
29
30
31
32
33
1
Team:Debra MarkertJosee GoldinWill Lippitt
Bradley AllenAndrew Hansen
UW BothellStudent Activities Center
Sustainability Assessment_LEED v.3
34
1. Located 225 feet upslope from the North Creek Wetland
2. Surrounded by other Campus Buildings
3. East-West Axis• Reduce Glare• Reduce Heating/Cooling• Optimize Daylighting• Passive Ventilation
Site Selection
2
LOCATIONUW Bothell / Cascadia Community College Campus
35
LEED 2009 for New Construction and Major Renovations UW Bothell Student Activities Center
Project Checklist 3/19/14
13 13 Possible Points: 26Y ? N Y ? N
Y Prereq 1 2 Credit 4 1 to 21 Credit 1 1 2 Credit 5 1 to 2
5 Credit 2 5 1 Credit 6 Rapidly Renewable Materials 11 Credit 3 Brownfield Redevelopment 1 1 Credit 7 1
6 Credit 4.1 61 Credit 4.2 1 7 8 Possible Points: 15
3 Credit 4.3 Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles 32 Credit 4.4 2 Y Prereq 1
1 Credit 5.1 Site Development—Protect or Restore Habitat 1 Y Prereq 2
1 Credit 5.2 Site Development—Maximize Open Space 1 1 Credit 1 11 Credit 6.1 Stormwater Design—Quantity Control 1 1 Credit 2 11 Credit 6.2 Stormwater Design—Quality Control 1 1 Credit 3.1 1
1 Credit 7.1 Heat Island Effect—Non-roof 1 1 Credit 3.2 11 Credit 7.2 1 1 Credit 4.1 1
1 Credit 8 Light Pollution Reduction 1 1 Credit 4.2 11 Credit 4.3 1
4 6 Possible Points: 10 1 Credit 4.4 11 Credit 5 1
Y Prereq 1 1 Credit 6.1 Controllability of Systems—Lighting 14 Credit 1 Water Efficient Landscaping 2 to 4 1 Credit 6.2 12 Credit 2 Innovative Wastewater Technologies 2 1 Credit 7.1 1
4 Credit 3 2 to 4 1 Credit 7.2 Thermal Comfort—Verification 11 Credit 8.1 1
12 23 Possible Points: 35 1 Credit 8.2 1
Y Prereq 1 1 5 Possible Points: 6Y Prereq 2
Y Prereq 3 1 Credit 1.1 110 9 Credit 1 1 to 19 1 Credit 1.2 1
7 Credit 2 1 to 7 1 Credit 1.3 12 Credit 3 2 1 Credit 1.4 1
2 Credit 4 2 1 Credit 1.5 13 Credit 5 3 1 Credit 2 12 Credit 6 2
2 2 Possible Points: 414 Possible Points: 14
1 Credit 1.1 1Y Prereq 1 1 Credit 1.2 1
3 Credit 1.1 1 to 3 1 Credit 1.3 11 Credit 1.2 Building Reuse—Maintain 50% of Interior Non-Structural Elements 1 1 Credit 1.4 12 Credit 2 1 to 22 Credit 3 1 to 2 39 71 Possible Points: 110
Regional Priority: SSc1 Site SelectionRegional Priority: EAc1 Optimize Energy PerformanceRegional Priority: Specific CreditRegional Priority: Specific Credit
Measurement and Verification
Innovation in Design: Exemplary Performance SSc4.1Innovation in Design: Specific TitleInnovation in Design: Specific TitleInnovation in Design: Specific TitleInnovation in Design: Specific Title
Materials Reuse
Storage and Collection of Recyclables
Materials and Resources
Fundamental Commissioning of Building Energy Systems
TotalConstruction Waste Management
Enhanced CommissioningOn-Site Renewable Energy
Enhanced Refrigerant Management
Construction IAQ Management Plan—Before Occupancy
Materials and Resources, Continued
Water Efficiency
Building Reuse—Maintain Existing Walls, Floors, and Roof
Alternative Transportation—Parking Capacity
Heat Island Effect—Roof
Recycled ContentRegional Materials
Certified Wood
Alternative Transportation—Bicycle Storage and Changing Rooms
Sustainable Sites
Alternative Transportation—Public Transportation Access
Site SelectionDevelopment Density and Community Connectivity
Construction Activity Pollution Prevention
Low-Emitting Materials—Adhesives and SealantsLow-Emitting Materials—Paints and Coatings
Optimize Energy Performance
Energy and Atmosphere
Water Use Reduction—20% Reduction
Low-Emitting Materials—Composite Wood and Agrifiber ProductsLow-Emitting Materials—Flooring Systems
Indoor Chemical and Pollutant Source Control
Thermal Comfort—DesignControllability of Systems—Thermal Comfort
Green Power
Water Use Reduction
Minimum Energy PerformanceFundamental Refrigerant Management
Daylight and Views—Views
LEED Accredited Professional
Daylight and Views—Daylight
Certified 40 to 49 points Silver 50 to 59 points Gold 60 to 79 points Platinum 80 to 110
Construction IAQ Management Plan—During Construction
Outdoor Air Delivery Monitoring
Indoor Environmental Quality
Minimum Indoor Air Quality PerformanceEnvironmental Tobacco Smoke (ETS) Control
Increased Ventilation
Regional Priority Credits
Innovation and Design Process
Sustainable Sites 13
WaterEfficiency 4
Energy & Atmosphere 12
Materials & Resources 0
Indoor Environmental Quality 7
Innovation in Design 1
Regional Priority 2
LEED Score
*13 points of the 110 total points possible are not attainable as New Construction.
12
PROJECT SUMMARY “AS-IS”UW Bothell Student Activities Center
Pts: 39/110
36
Keep Pipe Within 40’ Disturbance Boundary
WasteComposting Area
Educational Awareness
2
3
4
1
LEED GoldSustainable Sites• c5.1: Protect Habitat 1
WaterEfficiency• c2: Innov Wastewater Tech 2
Energy & Atmosphere• c3: Enhanced Commissioning 2• c5:Mesurement&Verification 3
Materials & Resources• c2: Waste Management 2• c4: Recycled Content 2• c5: Regional Materials 2• c6: Rapid Renewables 1• c7:CertifiedWood 1
Indoor Environmental Quality• c3.1: IAQ Plan, Construction 1• c3.2: IAQ Plan, Before Occ 1• c4.2: Low-Emitting Materials 1• c6.1: Control, Lighting 1• c7.1: Thermal, Design 1• c7.2:Thermal,Verification 1
Innovation in Design• c1: Educational Program 1• c1: Waste Mgmt Composte 1• c2: LEED AP 1
Regional Priority• Materials & Resources c7 1
15
LEED GOLDRecommendations
Pts: 65/110
37
Keep Pipe Within 40’ Disturbance Boundary
WasteComposting Area
Educational Awareness
2
3
4
1
LEED PlatinumSustainable Sites• c5.1: Protect Habitat 1• c6.1: Stormwater, Quantity 1• c6.2: Stormwater, Quality 1• c8: Light Pollution Reduction 1
WaterEfficiency• c1: Landscaping 2• c2: Innov Wastewater Tech 2
Energy & Atmosphere• c1: Optimize Energy Perf 9• c2: On-Site Renewables 7• c3: Enhanced Commissioning 2• c5:Mesurement&Verification 3
Materials & Resources• c2: Waste Management 2• c4: Recycled Content 2• c5: Regional Materials 2• c6: Rapid Renewables 1• c7:CertifiedWood 1
Indoor Environmental Quality• c1: Outdoor Air Delivery 1• c3.1: IAQ Plan, Construction 1• c3.2: IAQ Plan, Before Occ 1• c4.2: Low-Emitting Materials 1• c6.1: Control, Lighting 1• c7.1: Thermal, Design 1• c7.2:Thermal,Verification 1
Innovation in Design• c1: Exemplary Perf SSc5.1 1• c1: Exemplary Perf SSc6.2 1• c1: Educational Program 1• c1: Waste Mgmt Composte 1• c2: LEED AP 1
Regional Priority• Materials & Resources c7 1• Sustainable Sites c6.1 1
16
Pts: 90/110
LEED PLATINUMRecommendations
38
Certainly Educational and
Good Publicity
May Set an Unwanted Precededent for Future Buildings
QuestionalbleCost-to-Benefit
Allows Education and Good Publicity
Acceptable Standard for Future Buildings
GoodCost-to-BenefitRatioforFirst Costs and Lifecycle Costs
28
CONCLUSIONFinal Considerations
39
CS Bridge Project
Project Initiation
Management & Mobilization
Abutment #1
Piles
Footings
Walls
Abutment #2
Piles
Footings
Walls
Bridge Deck
Girders
Deck Slab
Guardrails
Project Completion
Completion & Commissioning
WBS Name A65 Hansen
CS D1
CS Bridge Project
Data Date: 16-Jun-08
Completion Date: 23-Sep-08
WBS
Scheduling / Estimating_Primavera
40
Activity ID Activity Name OriginalDuration
Budgeted Total Cost
15 22 29 06 13 20 27 03 10 17 24 31 07 14 21June July August September
2008
CS BCS Bridge Project 70d $556,550 $19,982 $12,212 $83,767 $96,556 $38,434 $34,354 $50,230 $29,198 $158,688 $19,767 $8,408 $4,954
ExExcavation, unclassified 4d $6,102 $3,051 $3,05190 Excavate footings #1 (unclassifi... 2d $3,051 $3,0511 Excavate footings #2 (unclassifi... 1d $3,051 $3,051
ExExcavation, structural 3d $5,876 $5,87692 Excavate footings #1 (structural) 1d $2,938 $2,9381 Excavate footings #2 (structural) 1d $2,938 $2,938
BaBackfill, compacted 12d $5,842 $2,921 $974 $1,9472 Backfill abutment #1 3d $2,921 $2,9213 Backfill abutment #2 3d $2,921 $974 $1,947
PiPiling, steel 22d $138,910 $10,361 $82,125 $46,42430 Order Deliver Piles 15d $01 Mobilize pile driving rig 2d $10,361 $10,3611 Drive piles footing #1 3d $64,094 $64,0941 Drive piles footing #2 3d $54,094 $18,031 $36,0631 Demobilize pile driving 1d $10,361 $10,361
CoConcrete, footings 21d $23,496 $1,642 $11,748 $10,10670 Fab & deliver footing rebar 7d $01 Forms & rebar footing #1 1d $1,642 $1,6421 Pour footing #1 1d $9,972 $9,9721 Strip footing #1 1d $134 $1341 Forms & rebar footing #2 (forms) 1d $1,642 $1,6422 Pour footing #2 1d $9,972 $9,9722 Strip footing #2 1d $134 $134
CoConcrete, abutments 43d $104,319 $6,570 $3,285 $9,136 $34,354 $28,117 $20,363 $2,49580 Pre-fabricate abutment forms 3d $9,855 $6,570 $3,2851 Forms & rebar abutment #1 (for... 2d $9,136 $9,1362 Pour abutment #1 2d $30,477 $30,4772 Strip and cure abutment #1 3d $3,877 $3,8772 Rub concrete abutment #1 3d $3,742 $3,7422 Forms & rebar abutment #2 (for... 2d $9,136 $9,1362 Pour abutment #2 2d $30,477 $15,239 $15,2392 Strip and cure abutment #2 3d $3,877 $3,8773 Rub concrete abutment #2 3d $3,742 $1,247 $2,4953 Milestone #1: Abutments backfi... 0d $0
CoConcrete, deck slab 10d $29,829 $9,085 $19,767 $9773 Deck forms and rebar (forms) 2d $9,085 $9,0853 Pour and cure deck 3d $17,043 $17,0433 Strip deck forms 3d $2,930 $1,953 $9773 Saw joints 1d $771 $771
ReReinforcing Steel 49d $95,960 $38,384 $19,192 $19,192 $19,19220 Prep/approve S/D foot rebar 5d $010 Prep/approve S/D abutment Rebar 10d $060 Fab/deliver abut/deck rebar 15d $01 Forms and rebar footing #1 (reb... 1d $19,192 $19,1921 Forms and rebar footing #2 (reb... 1d $19,192 $19,1921 Forms and rebar abutment #1 (r... 2d $19,192 $19,192
Labor Efforts Daily Usage A65 Hansen
CS D5
Start Date: 16-Jun-08
Completion Date: 23-Sep-08
Activity ID Activity Name OriginalDuration
Budgeted Total Cost
15 22 29 06 13 20 27 03 10 17 24 31 07 14 21June July August September
2008
2 Forms and rebar abutment #2 (r... 2d $19,192 $19,1923 Deck forms and rebar (rebar) 2d $19,192 $19,192
StSteel, structural 45d $114,711 $114,71150 Prep/approve S/D girders 10d $02 Fab/deliver girders 25d $03 Set girders on bearing plates (b... 1d $114,711 $114,711
BeBearing plates 1d $7,861 $7,8613 Set girders on bearing plates (b... 1d $7,861 $7,861
GuGuardrail 3d $11,258 $11,2583 Guardrails 3d $11,258 $11,258
PaPainting 5d $12,386 $7,432 $4,9543 Paint 5d $12,386 $7,432 $4,954
NoNo A65 Bid Items 70d $00 Project Start [start milestone] 0d $040 Move in 3d $05 Project Management [level of ef... 70d $03 Clean up 3d $04 Final inspection 1d $04 Contingency 6d $04 Finish [finish milestone] 0d $0
Labor Efforts Daily Usage A65 Hansen
CS D5
Start Date: 16-Jun-08
Completion Date: 23-Sep-08
41
2013A65CM450CS CS Bridge Project2013A65CM450CS.1 Project Initiatio
2013A65CM450CS.2 Abutment #1
2013A65CM450CS.3 Abutment #2
2013A65CM450CS.4 Bridge Dec
2013A65CM450CS.5 Project Completio
0Project Start [start milestone]
500Project Management [level of effort]
40Move in
10Prep/approve S/D abutment Rebar
30Order Deliver Piles
20Prep/approve S/D foot rebar
90Excavate footings #1 (unclassified)
100Mobilize pile driving rig
80Pre-fabricate abutment forms
70Fab & deliver footing rebar
92Excavate footings #1 (structural)
110Drive piles footing #1
130Forms & rebar footing #1
132Forms and rebarfooting #1 (rebar)
150Pour footing #1
170Strip footing #1
180Forms & rebar abutment #1 (forms)
182Forms and rebarabutment #1 (rebar)
200Pour abutment #1
220Strip and cure abutment #1
280Backfill abutment#1
270Rub concrete abutment #1
120Excavate footings #2 (unclassified)
122Excavate footings #2 (structural)
140Drive piles footing #2
160Demobilize pile driving
190Forms & rebar footing #2 (forms)
192Forms and rebarfooting #2 (rebar)
210Pour footing #2
230Strip footing #2
240Forms & rebar abutment #2 (forms)
242Forms and rebarabutment #2 (rebar)
250Pour abutment #2
290Strip and cure abutment #2
310Backfill abutment#2
300Rub concrete abutment #2
315Milestone #1: Abutments backfilled
50Prep/approve S/D girders
60Fab/deliver abut/deck rebar
260Fab/deliver girders
320Set girders on bearing plates (bearing plates)
322Set girders on bearing plates (bearing plates)
330Deck forms and rebar (forms)
360Guardrails
332Deck forms and rebar (rebar)
340Pour and cure deck
350Strip deck forms
380Saw joints
370Paint
390Clean up
400Final inspection
410Contingency
420Finish [finish milestone]
Activity IDActivity Name
A65 Hansen
CS D2
CS Bridge Project
Data Date: 16-Jun-08
Project Completion: 23-Sep-08
Activity Network by WBS
42
2013A65CM450CS CS Bridge Project2013A65CM450CS.1 Project Initiatio
2013A65CM450CS.2 Abutment #1
2013A65CM450CS.3 Abutment #2
2013A65CM450CS.4 Bridge Dec
2013A65CM450CS.5 Project Completio
0Project Start [start milestone]
500Project Management [level of effort]
40Move in
10Prep/approve S/D abutment Rebar
30Order Deliver Piles
20Prep/approve S/D foot rebar
90Excavate footings #1 (unclassified)
100Mobilize pile driving rig
80Pre-fabricate abutment forms
70Fab & deliver footing rebar
92Excavate footings #1 (structural)
110Drive piles footing #1
130Forms & rebar footing #1
132Forms and rebarfooting #1 (rebar)
150Pour footing #1
170Strip footing #1
180Forms & rebar abutment #1 (forms)
182Forms and rebarabutment #1 (rebar)
200Pour abutment #1
220Strip and cure abutment #1
280Backfill abutment#1
270Rub concrete abutment #1
120Excavate footings #2 (unclassified)
122Excavate footings #2 (structural)
140Drive piles footing #2
160Demobilize pile driving
190Forms & rebar footing #2 (forms)
192Forms and rebarfooting #2 (rebar)
210Pour footing #2
230Strip footing #2
240Forms & rebar abutment #2 (forms)
242Forms and rebarabutment #2 (rebar)
250Pour abutment #2
290Strip and cure abutment #2
310Backfill abutment#2
300Rub concrete abutment #2
315Milestone #1: Abutments backfilled
50Prep/approve S/D girders
60Fab/deliver abut/deck rebar
260Fab/deliver girders
320Set girders on bearing plates (bearing plates)
322Set girders on bearing plates (bearing plates)
330Deck forms and rebar (forms)
360Guardrails
332Deck forms and rebar (rebar)
340Pour and cure deck
350Strip deck forms
380Saw joints
370Paint
390Clean up
400Final inspection
410Contingency
420Finish [finish milestone]
Activity IDActivity Name
A65 Hansen
CS D2
CS Bridge Project
Data Date: 16-Jun-08
Project Completion: 23-Sep-08
Activity Network by WBS
43
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 6Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun n
Jun 15 Jun 22 Jun 29 Jul 06 Jul 13 Jul 20 Jul 27 Aug 03 Aug 10 Aug 17 Aug 24 Aug 31 Sep 07 Sep 14 Sep 21 Sep 28
Order Deliver Piles
Prep/approve S/D foot rebar
Prep/approve S/D abutment Rebar
Prep/approve S/D girders
Project Start [start milestone]
Move in
Project Management [level o
Excavate footings #1 (unclassified)
Mobilize pile driving rig
Pre-fabricate abutment forms
Excavate footings #1 (structural)
Fab & deliver footing rebar
Excavate footings #2 (unclassified)
Excavate footings #2 (structural)
Fab/deliver abut/deck rebar
Fab/deliver girders
Drive piles footing #1
Drive piles footing #2
Forms & rebar footing #1
Forms and rebar footing #1 (rebar)
Pour footing #1
Demobilize pile driving
Strip footing #1
Forms & rebar footing #2 (forms)
Forms and rebar footing #2 (rebar)
Pour footing #2
Strip footing #2
Forms & rebar abutment #1 (forms)
Forms and rebar abutment #1 (rebar)
Pour abutment #1
Strip and cure abutment #1
Backfill abutment #1
Rub concrete abutment #1
Forms & rebar abutment #2 (forms)
Forms and rebar abutment #2 (rebar)
Pour abutment #2
Strip and cure abutment #2
Backfill abutment #2
Rub concrete abutment #2
Set girders on bearing plates (bearing plates)
Set girders on bearing plates (bearing plates)
Deck forms and rebar (forms)
Milestone #1: Abutments backfilled
Guardrails
Deck forms and rebar (rebar)
Pour and cure deck
Strip deck forms
Saw joints
Paint
Clean up
Final inspection
Contingency
Finish [finish milestone]
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 6Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun n
Jun 15 Jun 22 Jun 29 Jul 06 Jul 13 Jul 20 Jul 27 Aug 03 Aug 10 Aug 17 Aug 24 Aug 31 Sep 07 Sep 14 Sep 21 Sep 28
30.0h
60.0h
90.0h
120.0h
150.0h
500.0h
1000.0h
1500.0h
2000.0h
2500.0h
Remaining Level of EffortActual WorkRemaining WorkCritical Remaining WorkMilestone
A65 Hansen
CS D4
CS Bridge Project
Start Date: 16-Jun-08
Completion Date: 23-Sep-08
Labor Efforts Daily Usage
44
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 6Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun n
Jun 15 Jun 22 Jun 29 Jul 06 Jul 13 Jul 20 Jul 27 Aug 03 Aug 10 Aug 17 Aug 24 Aug 31 Sep 07 Sep 14 Sep 21 Sep 28
Order Deliver Piles
Prep/approve S/D foot rebar
Prep/approve S/D abutment Rebar
Prep/approve S/D girders
Project Start [start milestone]
Move in
Project Management [level o
Excavate footings #1 (unclassified)
Mobilize pile driving rig
Pre-fabricate abutment forms
Excavate footings #1 (structural)
Fab & deliver footing rebar
Excavate footings #2 (unclassified)
Excavate footings #2 (structural)
Fab/deliver abut/deck rebar
Fab/deliver girders
Drive piles footing #1
Drive piles footing #2
Forms & rebar footing #1
Forms and rebar footing #1 (rebar)
Pour footing #1
Demobilize pile driving
Strip footing #1
Forms & rebar footing #2 (forms)
Forms and rebar footing #2 (rebar)
Pour footing #2
Strip footing #2
Forms & rebar abutment #1 (forms)
Forms and rebar abutment #1 (rebar)
Pour abutment #1
Strip and cure abutment #1
Backfill abutment #1
Rub concrete abutment #1
Forms & rebar abutment #2 (forms)
Forms and rebar abutment #2 (rebar)
Pour abutment #2
Strip and cure abutment #2
Backfill abutment #2
Rub concrete abutment #2
Set girders on bearing plates (bearing plates)
Set girders on bearing plates (bearing plates)
Deck forms and rebar (forms)
Milestone #1: Abutments backfilled
Guardrails
Deck forms and rebar (rebar)
Pour and cure deck
Strip deck forms
Saw joints
Paint
Clean up
Final inspection
Contingency
Finish [finish milestone]
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 6Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun n
Jun 15 Jun 22 Jun 29 Jul 06 Jul 13 Jul 20 Jul 27 Aug 03 Aug 10 Aug 17 Aug 24 Aug 31 Sep 07 Sep 14 Sep 21 Sep 28
30.0h
60.0h
90.0h
120.0h
150.0h
500.0h
1000.0h
1500.0h
2000.0h
2500.0h
Remaining Level of EffortActual WorkRemaining WorkCritical Remaining WorkMilestone
A65 Hansen
CS D4
CS Bridge Project
Start Date: 16-Jun-08
Completion Date: 23-Sep-08
Labor Efforts Daily Usage
45
Level 1: BIM Execution Planning ProcessEcoMod Classroom
INFO
. EXC
HA
NG
EB
IM U
SES
Developed with the BIM Project Execution Planning Procedure by the Penn State CIC Research Team.http://www.engr/psu.edu/ae/cic/bimex
Owner
Planning
Design Authoring
Programming
Architect
Schematic Design
Design Authoring
Author Schematic Design
Architect
Schematic Design
Cost 3D Macro Coordination
Perform 3D Coordination
Contractor
Schematic Design
4D Modeling
Create 4D Model
Fabricator
Schematic Design
Construct-ability
Perform Fabrication Analysis
Architect
Schematic Design
Sustainability
Perform Sustainability Analysis
Contractor
Schematic Design
Maintenance
Perform Facilities Mgmt Analysis
Architect
Design Development
Design Authoring
Author Design Development
Architect
Design Development
Cost 3D Macro Coordination
Perform 3D Coordination
Contractor
Design Development
4D Modeling
Create 4D Model
Fabricator
Design Development
Construct-ability
Perform Fabrication Analysis
Architect
Design Development
Sustainability
Perform Sustainability Analysis
Contractor
Design Development
Maintenance
Perform Facilities Mgmt Analysis
Fabricator
Construction Documents
Cost Estimation
Perform 3D Coordination
Fabricator
Construction Documents
3D Macro Coordination
Create 4D Model
Architect
Construction Documents
Virtual Prototyping
Perform Fabrication Analysis
Architect
Construction Documents
4D Modeling
Perform Sustainability Analysis
Contractor
Construction Documents
Engineering Analysis
Perform Facilities Mgmt Analysis
Contractor
Operations
Record Model
Compile Record Model
Program Model Architectural Model
MEP Model
Structural Model
Civil Model
Schematic Design
Schematic Design Cost Estimation
Schematic Design 4D Model
Schematic Design 3D Macro Coordination
ModelSchematic Design Virtual Prototypes
Schematic Design Engineering Analysis
Model
Architectural Model
MEP Model
Structural Model
Civil Model
Design Development
Design Development Cost Estimation
Design Development 4D Model
Design Development3D Macro Coordination
Model
Design Development Virtual Prototypes
Design DevelopmentEngineering Analysis
Model
Architectural Model
MEP Model
Structural Model
Civil Model
Construction Documents (WP)
Construction Documents (WP)
3D Micro CoordinationModel
Record Model
End Process
Contractor
Schematic Design
Cost Estimation
Perform Cost Estimation
Contractor
Schematic Design
Cost Estimation
Perform Cost Estimation
Fabricator
Construction Documents
Cost Estimation
Perform Cost Estimation
Architect
Construction Documents
Design Authoring
Author Construction Documents
Fabricator
Construction Documents
Design Authoring
Author Shop Drawings
Architectural Model
MEP Model
Structural Model
Civil Model
Shop Drawings
BIM Use Plan_Process Design
46
47
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
Dependable Design& Construction, Inc.
6/7/
2013
5:1
5:25
PM
A107
Interior Renderings
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
No. Description Date
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
Dependable Design& Construction, Inc.
6/7/
2013
5:1
5:25
PM
A107
Interior Renderings
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
No. Description Date
MRW Facility_Design/Build
48
Construction Estimate
Qty Craft Hours Unit Material Labor Equipment Total
SITE AMENITIES
Silt fence - Erosion Control 1,400.00 BL 91.00 LF 756.00 2,590.00 - $! 3,346.00
Equipment Mobilization 1.00 B7 - Ea - - - $! 15,000.00
3,500-gallon water tank 2.50 - - Ea - - 16,236.25 $! 16,236.25
Temporary structures 28' x 10' x 10' high (360 SF) 2.50 - - Mo - - - $! 1,282.43
Trailer-mounted M/F double toilet 12.00 - - Wk - - - $! 3,917.86
Electric generator rental 2.50 - - Ea - - 5,454.00 $! 5,454.00
Subtotal 91.00 756.00 2,590.00 21,690.25 $! 45,236.54
BUILDING
Footings 18" W x 24" D (0.117 CY per LF) 240.00 B4 101.00 LF 7,756.80 3,448.80 1,144.80 $! 12,350.40
Excavate gravel or loose sand (29 CY per hour) 240.00 TO 17.28 CY - 916.80 424.20 $! 1,341.00
Backfill trenches with D-3 crawler dozer 240.00 B8 19.20 CY - 657.60 426.62 $! 1,084.22
Trenching with a 1/2 CY utility backhoe 24" x 36" depth, .222 CY per LF (68 LF/Hr) 240.00 S1 28.08 LF - 1,281.60 374.40 $! 1,656.00
Foundation/Slab 3,200.00 B5 508.80 SF 29,152.00 17,408.00 - $! 46,560.00
Panelized 2” x 4” studs 16” OC 1/2" wallboard and 1/2" CDX plywood 1,850.00 - - SF 6,715.50 - - $! 6,715.50
2-1/2" steel interior wall framing, 16" OC, 1-1/4” flange 250S125-27 (22 gauge, .49 Lbs./ SF) 840.00 B1 68.04 SF 1,999.20 2,167.20 - $! 4,166.40
Concrete block wall assemblies 8" thick wall 840.00 M1 157.00 SF 5,384.40 7,039.20 - $! 12,423.60
Metal sheet Siding 1,890.00 R1 166.30 SF 7,560.00 5,670.00 - $! 13,230.00
Steel Roof 3,200.00 R1 281.60 SF 12,800.00 9,600.00 - $! 22,400.00
Steel Structural Framing 360.00 B1 92.52 LF 5,734.80 2,948.40 - $! 8,683.20
Overhead roll-up doors, Chain hoist operated 3.00 F7 98.70 Ea 19,400.40 4,695.00 860.52 $! 24,955.92
Prep concrete floor for Epoxy Coating 3,200.00 PA 147.20 SF 6,496.00 7,328.00 - $! 13,824.00
Polyurethane epoxy floor system 3,200.00 PA 185.60 SF 13,760.00 9,216.00 - $! 22,976.00
Subtotal 1,871.32 116,759.10 72,376.60 3,230.54 $! 192,366.24
HVAC / ELEC / PLUMB etc
Complete electrical systems for buildings 3,200.00 - - - - - $! 64,000.00
Fire alarm and detection systems 1.00 E4 3.89 2,387.20 184.20 - $! 2,571.40
Exposed fire protection sprinkler system 3,200.00 - - - - - $! 27,360.00
Ventilation System 1.00 P1 - - - - $! 50,000.00
Single story plumbing rough-in 1.00 P1 122.00 4,951.26 4,206.00 - $! 9,157.26
Interior finishing 1.00 P1 - - - - $! 12,000.00
Photovoltaic roofing panels, 85 watt 192.00 RR 50.30 20,369.28 1,992.96 - $! 22,362.24
Subtotal 176.19 27,707.74 6,383.16 0.00 $! 187,450.90
Totals 2,138.51 145,222.84 81,349.76 24,920.79 $! 425,053.68
CONSTRUCTION COST $! 425,053.68
WASHINGTON STATE SALES TAX $! 40,380.10
TOTAL CONSTRUCTION COST $! 465,433.78
Design/Build Estimate
Total
SITE AMENITIES
Subtotal $! 45,236.54
BUILDING
Subtotal $! 192,366.24
HVAC / ELEC / PLUMB etc
Subtotal $! 187,450.90
PROJECT PLANNING and DESIGN
Planning $! 70,000.00
Engineering and Design $! 110,000.00
Permitting $! 8,000.00
Subtotal $! 188,000.00
OTHER DIRECT and INDIRECT COSTS
Administrative $! 180,000.00
Insurance $! 80,000.00
Record Drawings, O&M Manuals and Training $! 15,000.00
Payment and Performance Bond $! 55,000.00
LEED-NC Documentation and Certification $! 40,000.00
Subtotal $! 370,000.00
COMMISSIONING AND ACCEPTANCE TESTING
Pre-Start-Up Inspection $! 8,000.00
Commissioning $! 6,000.00
Acceptance Testing $! 10,000.00
Subtotal $! 24,000.00
Totals $! 1,007,053.68
DESIGN-BUILD PRICE $! 1,007,053.68
WASHINGTON STATE SALES TAX $! 95,670.10
TOTAL DESIGN-BUILD PRICE $! 1,102,723.78
49
OFFICE
TOILET
LUNCHROOM
ELECTRICAL
MECHANICAL
LAB
H-2 OCCUPANCY
STOR STOR
23' - 8" 30' - 5" 6' - 2" 11' - 2" 9' - 3"
80' - 8"
9' - 10" 7' - 4" 39' - 2" 11' - 7" 5' - 11" 6' - 10"
13' -
7 3
1/32
"5'
- 4"
8' -
9"9'
- 11
"5'
- 5
3/16
"5'
- 0"
14' -
10
3/16
"9'
- 10
"23
' - 4
31/
32"
48' -
2"
17' - 4" 9' - 9" 5' - 4" 6' - 11" 7' - 6" 17' - 5" 11' - 4" 5' - 1"
53' - 4" 27' - 4"
80' - 8"
10' -
0"
35' -
4 3
/16"
5' -
4"7'
- 5
15/1
6"
40' -
8 3
/16"
7' -
5 15
/16"
58' -
2 1
/8"
2' -
8"14
' - 1
0"5'
- 5
1/2"
8' -
4 1/
2"8'
- 0
3/16
"4' -
0 3/
16"
10' -
2"
4' -
5"5'
- 5"
15' -
4"
5' - 1" 5' - 6" 9' - 2"
10' -
0"
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/4" = 1'-0"
6/10
/201
3 6:
02:0
7 PM
A101
Floor Plan - Level 1
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
-
1/4" = 1'-0"1 Level 1
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
50
OVERHEADSTORAGEOPEN TO BELOW
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/4" = 1'-0"
6/10
/201
3 6:
02:0
7 PM
A102
Floor Plan - Level 2
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
1/4" = 1'-0"1 Level 2
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
51
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1/4" = 1'-0"
6/10
/201
3 6:
02:1
2 PM
A103
Sections
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
1/4" = 1'-0"1 Section 1
1/4" = 1'-0"2 Section 2
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
52
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
6/10
/201
3 6:
02:0
4 PM
A000
Cover
1
MRW FacilityThurston County
June 7, 2013Author
Checker
No. Description Date
1 Isometric
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
53
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
6/10
/201
3 6:
02:2
4 PM
A104
Elevations
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
1 Elevation - North
2 Elevation - South
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
54
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
6/10
/201
3 6:
02:3
6 PM
A105
Elevations
1
MRW FacilityThurston County
June 7, 2013Andrew Hansen
Checker
1 Elevation - East
2 Elevation - West
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
55
December 23June 27
4:00 PM
12:00 PM
7:23 PM
4:11 AM
12:00 PM
W
S
E
N
December 23June 27
4:00 PM
12:00 PM
4:12 PM
December 227:12 AM
12:00 PM
W
S
E
N
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
6/10
/201
3 6:
02:5
2 PM
A108
Solar Studies
1
MRW FacilityThurston County
June 7, 2013Author
Checker1 Solar Study - Summer Solstice
2 Solar Study - Winter Solstice
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
56
OFFICE
TOILET
LUNCHROOMELECTRICAL
MECHANICAL
LAB
H-2 OCCUPANCY
STORSTOR
Scale
Project number
Date
Drawn by
Checked by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
As indicated
6/10
/201
3 6:
02:5
5 PM
A109
SustainabilityMeasures
1
MRW FacilityThurston County
June 7, 2013Author
Checker
1/8" = 1'-0"1 Level 1 - Diagram
3/16" = 1'-0"2 Section - Diagram_Thermal Mass
3/16" = 1'-0"3 Section - Diagram_Passive Ventilation
Passive VentillationTaking advantage of the stackeffect, casing hot air to rise, theshed roof directs the heated airto the highest point of thebuilding, from which it isexhauseted through passivevents
Thermal MassDuring the summer months, the interior is mostly shaded. However,during the winter months, the low sun streams through the abundantsouth facing glazing and falls directly on the exposed concrete flooras well as the CMU wall within the middle of the strcture. These highmass elements absorb the heat from the sun, slowly releasing itthroughout the day to mediate the interior temperature fluctuation.
Tight ConstructionThe office area, where additional temperature control isdesireable, Structurally Insulated Panels (SIPS) providea "tight" envelope, minimizing air infiltration andunnecessary heat loss or gain. The temperature withinthis space will stay at a more optimal level with lessenergy input required.
No. Description Date
D E P E N D A B L ED e s i g n & C o n s t r u c t i o n
57
702
• 510
• 86
61ha
nsen
.and
rew
@ic
loud
.com