8/8/2019 OUTLET REPORT
1/8
From,
Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,Kanya
To
The Administrator/Chief ExecutiveArea Water Board LCC (E) Command.
Faisalabad.
No_________/ Dated___________2010.
Subject: ESTIMATE FOR REPARING OUTLETS OF KILLIANWALA DISTY.
Please find enclosed here with this citied subject estimate amounting to Rs.
46206 /- for favour of sanction and early return please.
Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,
Kanya
-
8/8/2019 OUTLET REPORT
2/8
ESTIMATE FOR REPARING OUTLETS OF KILLIANWALADISTY.
REPORT.
This estimate amounting to Rs. 46206 /- has been framed to cover the probable cost of
cited as subject work.NECESSITY.
The above said channel was handed over to the Farmers Organization of Killianwala Disty. Now
the Chief Executive area Water Board LCC (E) dissolves The F.Os command Faisalabad and charge given
to the Administrator. The Irrigators have tempered the detail of outlets given in estimate. To set right the
Outlets and feeding the tail of Killianwala Disty necessary estimate has been prepared. After the set righting
the outlets it is hoped that tail of the channel will run as per design.
Hence necessity of the estimate.BASIS.
The estimate is based upon the actual requirement at site.CHECK.
The under-signed as required under the codal rule has exercised necessary check.RATES.
Rates provided in the estimate are based on newly approved MARKET
RATE SYSTEM of Faisalabad district of 4th Quarter/2009.TELEGRAM NO
OUTLET RD. T.M WIRE NO. DATE S D O CONFIRM WIRE NO. DATE
1. 860/R 1096 30-12-2009 1099 31-12-2009
2. 3845/R 1096 30-12-2009 1099 31-12-2009
3. 6391/L 1088 23-12-2009 1091 24-12-2009
4. 10000/ R 1088 23-12-2009 1091 24-12-2009
5. 11400/L 1088 23-12-2009 1091 24-12-2009
6. 12500/L 1088 23-12-2009 1091 24-12-2009
7. 15000/R 1088 23-12-2009 1091 24-12-20098. 15063/L 1096 30-12-2009 1099 31-12-2009
9. 19625/L 1096 30-12-2009 1099 31-12-2009
10. 20000/R 1096 30-12-2009 1099 31-12-2009
11. 40620/R 1096 30-12-2009 1099 31-12-2009
12. 49750/R 1090 24-12-2009 1091 24-12-2009
13. 53200/R 1090 24-12-2009 1091 24-12-2009
ALLOCATION.
D>O>C
31-12-2009.
GENERAL.
An early sanction of the estimate is requested pleas.
Technical Manager Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,
-
8/8/2019 OUTLET REPORT
3/8
Kanya
-
8/8/2019 OUTLET REPORT
4/8
ESTIMATE FOR REPARING OUTLETS OF KILLIANWALADISTY.
REPORT.
This estimate amounting to Rs. 32912/- has been framed to cover the probable cost ofcited as subject work.
NECESSITY.
The above said channel was handed over to the Farmers Organization of Killianwala Disty. Now
the Chief Executive area Water Board LCC (E) dissolves The F.Os command Faisalabad and charge given
to the Administrator. The Irrigators have tempered the detail of outlets given in estimate. To set right the
Outlets and feeding the tail of Killianwala Disty necessary estimate has been prepared. After the set righting
the outlets it is hoped that tail of the channel will run as per design.
Hence necessity of the estimate.
BASIS.
The estimate is based upon the actual requirement at site.CHECK.
The under-signed as required under the codal rule has exercised necessary check.
RATES.
Rates provided in the estimate are based on newly approved MARKETRATE SYSTEM of Faisalabad district of 4th Quarter/2009.
TELEGRAM NO
OUTLET RD. T.M WIRE NO. DATE S D O CONFIRM WIRE NO. DATE
1. 58457/L 1098 31-12-2009 1099 31-12-2009
2. 65700/L 1090 24-12-2009 1091 24-12-2009
3. 69450/R 1090 24-12-2009 1091 24-12-2009
4. 69800/ L 1088 23-12-2009 1091 24-12-2009
5. 72956/R 1083 10-12-2009 1084 11-12-2009
6. 79537/R 1083 10-12-2009 1084 11-12-2009
7. 80629/R 1083 10-12-2009 1084 11-12-2009
8. 80637/R 1083 10-12-2009 1084 11-12-20099. 90621/R 1079 30-12-2009 1084 11-12-2009
ALLOCATION.
D>O>C
31-12-2009.
GENERAL.
An early sanction of the estimate is requested pleas.
Technical Manager Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,
Kanya
-
8/8/2019 OUTLET REPORT
5/8
From,
Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,Kanya
To
The Administrator/Chief Executive
Area Water Board LCC (E) Command.Faisalabad.
No_________/ Dated___________2010.
Subject: ESTIMATE FOR REPARING OUTLETS OF KILLIANWALA DISTY.
Please find enclosed here with this citied subject estimate amounting to Rs.
32912/- for favour of sanction and early return please.
Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,
Kanya
-
8/8/2019 OUTLET REPORT
6/8
From, Technical Manager
To,
Dy/Administrator/Sub Divisional Officer,
Kanya Sub Division,
Kanya
Subject: ESTIMATE FOR REPARING OUTLETS OF KILLIANWALA DISTY.
Please find enclosed herewith the cited subject estimate amounting to
Rs 46206 /-for favour of sanction and early return please.
D.A/Estimate.
Technical Manager
-
8/8/2019 OUTLET REPORT
7/8
From,
Technical Manager
To,
Dy/Administrator/Sub Divisional Officer,Kanya Sub Division,
Kanya
Subject: ESTIMATE FOR REPARING OUTLETS OF KILLIANWALA DISTY.
Please find enclosed herewith the cited subject estimate amounting to
Rs 32912 /-for favour of sanction and early return please.
D.A/Estimate.
Technical Manager
-
8/8/2019 OUTLET REPORT
8/8