Project for Capacity Development on Natural Disaster-Resistant Techniques of Construction and Retrofitting for Public Buildings in the Peoples Republic of Bangladesh(CNCRP), and Project on Promoting Building Safety for Disaster Risk Reduction(BSPP) CNCRP / BSPP Outline of Retrofitting

Upload: lamthien

Post on 12-Mar-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

“Project for Capacity Development on Natural Disaster-Resistant Techniques of

Construction and Retrofitting for Public Buildings in the People’s Republic of

Bangladesh”(CNCRP), and

“Project on Promoting Building Safety for Disaster Risk Reduction”(BSPP)

CNCRP / BSPP

Outline of Retrofitting

Page 2: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

1

Table of Contents

1 . Purpose of Retrofitting.........................................................................................................2

2 . Retrofitting Procedure for Existing Buildings. .....................................................................4

2-1 . Assessment ........................................................................................................................7

2-1-1 . Basic Assessment............................................................................................................7

2-1-2 . Simplified Evaluation (SE) .............................................................................................9

2-1-3 . Advance Simplified Evaluation (ASE) ............................................................................9

2-1-4 . Building Survey .......................................................................................................... 10

2-1-5 . Detail Assessment......................................................................................................... 11

2-1-6 . Retrofitting Design...................................................................................................... 12

2-1-7 . Construction ............................................................................................................... 13

3 . Retrofitting Supporting Manuals by CNCRP/BSPP .......................................................... 15

4. Plan for the future ............................................................................................................. 16

4-1. Secure Important Buildings ............................................................................................ 16

4-2. Training .......................................................................................................................... 17

4-3. Future Hypothetical Calculation ..................................................................................... 18

4-4. Sustainable to Future ...................................................................................................... 19

Buildings in developing countries are likely to be vulnerable against earthquakes.

Once large earthquake occurs, tremendous damage to buildings and human casualties

have been often are provided. Bangladesh cannot be outside. In Bangladesh, vast

amount of vulnerable buildings have been built and now continuing construction.

In order to reduce this situation even though a little bit, the technical cooperation

project namely CNCRP started 2011.

This leaflet is drafted intending to inform this effort of promotion of technical

improvement to Bangladesh citizens as far as possible.

January 2017, PWD-JICA Project Team

Page 3: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

2

1. Purpose of Retrofitting

“Earthquakes don’t kill people, buildings do.” It is the famous saying. Unfortunately, this

situation can apply for the buildings in Bangladesh as well. The buildings should supply the

sense of the security to nation. However, Rana plaza disaster occurred in April in 2013 without

any Earthquake. And it was happened by the fact of not compliant with rules of Bangladesh.

After Rana Plaza accident, CNCRP and BSPP have been supporting the safety for Public and

Garment factory buildings. Through the experiences, we can say around 2/3 of the existing

buildings might need retrofitting or rebuilding in compliant with BNBC which became

effective since 2008.

After JICA

Page 4: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

3

Earthquake Hazard & Risk Assessment was carried by CDMP, which means the Government

of Bangladesh had started the preparation for future earthquakes. And the Hazards in Dhaka

caused by a moderate earthquake with seismic intensity VIII were estimated as the following;

Don’t you think is it correct? “We don't do anything, although huge damage appears when

an earthquake occurs.” Again to say that Buildings should provide sense of security.

Kathmandu earthquake in April 2015

CNCRP, “Project for Capacity Development on Natural Disaster-Resistant Techniques of

Construction and Retrofitting for Public Buildings in the People’s Republic of Bangladesh”

was commenced in 2011 to assist the technique dissemination in Bangladesh that the buildings

should supply the sense of the security.

Methods for measures for existing buildings are demolish, relocate, rebuild and retrofit, and

for new buildings compliant with BNBC. And CNCRP and BSPP have focused retrofitting

including Assessment of existing building, Retrofitting Design and Construction Supervision

for following appropriate design.

<Damage in Dhaka>

Building collapse: 72.000 buildings 22% of Dhaka buildings

Building damage: 158,000 buildings 49% of Dhaka buildings

Estimated dead peoples: 88,000 1.3% of Dhaka population

Financial loss:

12.7 Billion US dollars, 1.0 Trillion Taka (13.4% per GDP of Bangladesh 2009)

Page 5: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

4

2. Retrofitting Procedure for Existing Buildings.

Seismic retrofitting is different from new building construction fundamentally targeting

existing building. Therefore its process in the following figure mainly investigation and

assessment of target building are the key processes. And the other highlight is construction

supervision, because even design is excellent construction does not follow it is the fundamental

trigger for vulnerable buildings in Bangladesh. Systemize the improvement is one of the keys

for improvement. Of course seismic design should be disseminate in Bangladesh for seismic

resistant structure.

Retrofitting flow is the following, assessment portion is enlarged the later figure;

<Assessment & Design>

Selection of Existing Building

Simplified Evaluation

Deviation Survey

Advanced Simplified Evaluation

Building Survey

Document

Visula

Site evaluation Rough cost estimation 

Detail Assessment

As‐built drawing Material test (Co, 

rebar) 

Member check, against vertical load Seismic Index of structure. Is Evaluation for retrofit design 

Retrofit Design

Basic Design Detail Design Cost Estimation 

Bidding/Selection of Contractor

Construction

Retrofit Completion

Supervision

To up right

From down left

Page 6: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

5

<Retrofitting Construction Works>

Page 7: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

6

Assessment portions in the Retrofitting Works are carried out the following flow;

All right, as it is 

Demolish &    OrRebuild/Relocate   RETROFIT Or      Or Reduce live load    as it is

Sufficient earthquake proof (BNBC) 

Low earthquake 

proof

Insufficient earthquake 

proof

< Basic Assessment >

< Design & Construction >

< Detail Assessment >

BNBC  load investigation 

Demolish &   Rebuild/Relocate Or Reduce live load

Simplified Evaluation (SE)   by Design drawings On site visual observation Weight (column size, concrete strength)

Advanced Simplified Evaluation (ASE) On site observation   (rebar arrangement,   rebound tests), Base shear 

First Level Inspection

Demolish & Rebuild/Relocate Or Change occupancy

All right, as it is 

As‐built drawingsOn site observation & test (Core sampling &   compression test)

Unbearable to 

Own weight

Bearableto 

Own weight

Sufficient earthquake proof (BNBC) 

Second Level Inspection 

(DEA)

Reinforcement Arrangement   & Strength On site observation &   Detailed Inspection calculation 

Demolish & Rebuild/Relocate Or Reduce live load

SelectionBuilding with Drawings, 

Geographical distribution

Low earthquake 

proof

Deviation SurveyOn site observation   (setback, stairs, etc.)

Page 8: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

7

2-1. Assessment

2-1-1. Basic Assessment

CNCRP established building inventory of Dhaka was prepared to know the conditions of existing

buildings in Dhaka. According to this building inventory data, we can easily understand the

numbers of the building per construction ages, the building structures such as RC frame, number

of stories etc. These are the base data to perform the Basic Assessment in the retrofitting for the

existing buildings.

Sample of inventory

Page 9: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

8

Construction Year of Brick Masonry structure

Construction Year of RC Frame structure

Other Information

Items Data in Dhaka managed by PWD

Type Brick Masonry 1328, RC Frame 827

Usage Residential 1599, Non-Residential 495 and Un-known

Stories Medium Brick Masonry 2 stories, RC Frame 5 stories

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

0

50

100

150

200

250

300

350

befo

re19

50

1951

-195

5

1956

-196

0

1961

-196

5

1966

-197

0

1971

-197

5

1976

-198

0

1981

-198

5

1986

-199

0

1991

-199

5

1996

-200

0

2001

-200

5

2006

-201

0

2010

-

Freq

uenc

y

Construction Year

Brick Masonry

Deviation Survey:

Deviation is difference between Permitted drawing and as-built situation.

Deviation Survey is implemented by visual and measured by ruler.

If surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal.

Therefore, without renovation to satisfy the regulations, the building cannot be passed the

building construction permission.

Page 10: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

9

2-1-2. Simplified Evaluation (SE)

The design of existing building can be evaluated by Simplified Evaluation (SE) method whether

it is satisfied BNBC requirement or not most simply. This evaluation needs architectural and

structure drawings. In other words, SE is suitable for simple design checking based on BNBC.

Evaluation sheet Calculation Sheet

2-1-3. Advance Simplified Evaluation (ASE)

Advance Simplified Evaluation (ASE) method needs not only architectural and structure

drawings but also site characteristics by non-destructive methods such as rebar arrangement,

estimated concrete strength by rebound test. ASE estimates whether it has BNBC functionalities

or not. In other words, this evaluation is suitable for design and construction quality as

simplified checking based on BNBC.

Advance Simplified Evaluation uses site data, comparing with design documents

Page 11: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

10

2-1-4. Building Survey

Detail Assessment is performed based on Building Survey results. It is including As-Built

drawing, concrete core sample and compression test. Rebar strength test etc. For getting actual

Bangladesh building characteristics, structural test and concrete test are performed.

Concrete test results show lower values comparing with BNBC requirement

Structural test to know the building behavior during the BNBC load

Constructed

Year1964 1970 1977 1984 1985 1999 2006 Japanese Case

Compressive

 Stren

gth (M

Pa)

? LOW

Almost Impossible

MODERATE

HIGH

Japa

nese Case

30

2928

2726

25

24

23

22

21

20

19

18

17

16

15

14

13

12

11

10

9

8

7

6

5

4

3

2

1

0

Required   

Design Strength   

of Concrete 

Page 12: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

11

2-1-5. Detail Assessment

To know the actual conditions of the target buildings, Detail Assessment of existing buildings is

performed for more accurate Retrofit Design based on Building Survey.

“Is” is the index to show the strength / vulnerability of buildings. If “Is” is larger, the building

has an enough resistance against earthquake. In Japan, “0.6” is adopted as index “Is”.

Comparing the seismic situation between Japan and Bangladesh, “0.3” can be used in

Bangladesh. It means the buildings strength of Bangladesh is required almost half of the

Japanese ones. The above graph is a sample of the survey in Dhaka, the situation of this

building has a half of Bangladesh standard, and a quarter of Japanese standard. “Is” method is

based on Bangladesh characteristics.

Concrete core sampling (left) and rebar detection (right)

0

1

2

3

4

5

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8

Sto

ry

Is

Bangladesh  Japan 

If “Is” index is less than 0.3,   

Retrofitting Works will be done.   

After  Retrofitting  Works,  the  building 

should have “Is “ index is 0.3 or more. 

Page 13: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

12

2-1-6. Retrofitting Design

Retrofitting Design starts from forming the total

plan (Basic Design) considering owner’s and others

requirements. Then, to get enough strength as a

building, seismic assessment results are applied. As

a solution, retrofitting methods and their

effectiveness, cost and materials procurement

condition etc. are investigated (Detail Design).

Finally, a design drawing of retrofitting based on

the seismic assessment shall be prepared, and Cost

Estimation will assist decision of retrofitting and

budget allocation.

Sample of retrofitting

During Design stage, construction cost is also estimated for retrofitting. Through the experience

of CNCRP, retrofitting cost is usually 30-40% comparing with new building construction.

For retrofitting existing building, it is important to tale the current building situation and

working activities of people into consideration before and during construction. It is

recommended to conduct the building assessment at least as soon as possible.

Page 14: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

13

2-1-7. Construction

To realize sufficient strength as a building,

compliant with BNBC, we shall perform the

construction works based on Retrofitting Design.

To keep quality of construction, CNCRP and BSPP

developed the quality control method for

Bangladesh. Daily Report and inspection are

typical ones

Daily Report

Inspection

Construction stage will start from selection of appropriate

contractor, as well as proper cost estimation, budget

preparation will be required. During construction, quality

control by inspection is important. Also, both safety control

and schedule control are also inevitable.

Page 15: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

14

Safety Drills Site Instruction

Foundation work Column Jacketing

Column Jacketing Steel Bracing

Steel Bracing Steel Bracing

Shear wall Shear wall

Page 16: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

15

3. Retrofitting Supporting Manuals by CNCRP/BSPP

Retrofitting is a new technology for Bangladesh and written in BNBC only a little. CNCRP

prepared Retrofitting supporting manuals.

3 main Retrofitting factors are “Seismic Assessment/Evaluation”, “Seismic Retrofit Design” and

“Construction Supervision”. Other than that new building design, quality control and

non-seismic issues are covered by 6 manuals and guidelines.

To make strengthen city against natural disaster, we must follow BNBC when we construct new

buildings. There are thousands of vulnerable buildings in Bangladesh. And many of them

should be demolish, rebuild, relocate or retrofit by Bangladesh building Engineers.

More than 3,000 new buildings have been newly constructed every year in Dhaka (RAJUK) that

should be compliant with BNBC, and the above Manuals can support effectively.

We need to take a license to work in society. The buildings also need the license.

These Manuals are uploaded PWD’s web page, and will be revised during BSPP.

Manual for Seismic Retrofitting Evaluation of Existing Reinforced Concrete Buildings Manual for Seismic Retrofit Design of Existing Reinforced Concrete Buildings Manual for Retrofit Construction and Supervision of Reinforced Concrete Buildings Guidelines for Quality Control of Design and Construction of Reinforced Concrete Buildings Manual for Seismic Design of Reinforced Concrete Buildings Manual for Vulnerability Assessment and Damage Prediction of Reinforced Concrete Buildings

Page 17: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

16

4. Plan for the future

4-1. Secure Important Buildings

Even in the disasters, the fire-department must keep the normal functions.

CNCRP conducted the retrofit work for one of the old fire stations as a pilot project.

New JICA project will succeed the activities and will implement demolish/rebuild old fire

stations, and retrofit and newly build fire stations in Dhaka.

before

after

Activities of FSCD

Page 18: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

17

4-2. Training

The dissemination of the technology regarding to retrofitting

works, is important to make a resistant city against the natural

disasters in Bangladesh. More than 60 engineers of Bangladesh

learn the retrofitting technology in CNCRP project every year

Not only engineers, but people including building owners

should raise awareness on disasters, and government officers

should get knowledge on retrofitting through trainings and

lectures etc.

<Training Material & Conditions of Training> 

<Certificate Awarding Ceremony > 

Page 19: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

18

4-3. Future Hypothetical Calculation

Regarding to Public building, a new construction

cost depends on the conditions. Then we can't

estimate exact price without the detail design.

However, considering PWD’s experience, the

general cost is approximately TK 2,000 per

square feet. It is rough estimation. On the other

hand, the cost of retrofitting price is ongoing to

estimate. In our few experience, the cost is

30-40% of the new construction building.

Can we consider the following issue?

77,700 sft.

average of floor area of RCC buildings

62,160,000 Taka

roughly estimate retrofitting cost

Per One RCC

Per One RCC

Loss of One trillion Taka caused by CDMP Earthquake

16,000

damaged buildings

If we have one trillion Taka, we can retrofit 16,000 buildings

Due to CDMP Earthquake

Page 20: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

19

4-4. Sustainable to Future

Regarding the role of school, it is very important for save children from disasters. Children will

teach parents and will grow to adults and will load the society. Therefore, retrofitting school

buildings and conduct evacuation training in the school are also highly required in Bangladesh

to secure children, as well as to save the future of Bangladesh.

<Building survey> 

Survey location of Coring and so on Drilling survey in school

Evaluation results compare with BNBC 1993

1. Though stone chips were used  in concrete, low concrete strength have been found from core test result.   

2. Column size is smaller compared to the long span. 3. Existing  columns  capacities  are  inadequate  according  to  BNBC  code.  Even 

some  of  the  column  doesn’t  meet  the  requirement  of  minimum reinforcement as per code. 

4. Columns are not satisfactory even for vertical load only as per BNBC.

To be an evacuation center, the activities by students have provided an opportunity for the

residents to think about DRR (Disaster Risk Reduction). After town watching, the students

developed hazard map for evacuation drills. The DDR of school is necessary to promote a

relationship between education of disaster management and building safety.

Hazard mapping, after town watch Evacuation Drill at School

Page 21: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

20

Memo:

Page 22: Outline of Retrofitting 20170112 - pwd.gov.bdpwd.gov.bd/cncrp/Outline_of_Retrofitting_20170112.pdfIf surveyed Deviation violates BNBC, Building Rules and regulations, it becomes illegal

21

Md. Ahsan Habib, Project Manager of CNCRP Mr. Shakhawat Hossain, Deputy Project Manager of BSPP E-mail [email protected], [email protected]

Unfortunately,  Rana  Plaza collapsed in April 2013 that caused  a  huge  number  of victims  by  the  building collapse.  The  survey  after the collapse, experts said, “The  building  was  not compliant  with  BNBC (Bangladesh  National Building Code)."   

There are many houses and buildings  in  Bangladesh. However,  many  of  them are  currently  vulnerable and  not  compliant  with BNBC, unfortunately. 

You  can  have  a  chance  to live  in  a  building,  to construct your house. Surely  you  will  live  and construct  your  house compliant  with  BNBC,  we believe.