Overbudget of Construction Costs - Introduction EDWARD YIU CHUNG YIM HK LEGISLATIVE COUNCILLOR 2017-2020

Upload: others

Post on 06-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Overbudget of Construction Costs -IntroductionEDWARD YIU CHUNG YIM

HK LEGISLATIVE COUNCILLOR 2017-2020

Page 2: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Major Causes of Overbudget1. Uncontrollable Factors (Force Majeure) -◦ Weather

◦ Natural Disasters

◦ Underground Conditions / Unexpected Situations or Events

◦ Discovery of Monuments

2. External Factors◦ Tender Price Index Change / Construction Cost Change

◦ Inflation Change

◦ Interest Rate Change

3. Internal Factors◦ Required Rate of Return Change

◦ Risk Estimation Errors

◦ Cost Estimation Errors

◦ Design Change

◦ Insufficient Competition in the Market / Excessive Demand

◦ Intentional Underestimation (for Easy Approval, etc)

Page 3: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Systematic Errors vs Non-Systematic ErrorsSystematic Errors Non-Systematic Errors

Force Majeure

External Factors

Internal Factors

Required Rate of Return Change

Risk Estimation Errors

Cost Estimation Errors

Design Change

Insufficient Competition in the Market / Excessive Demand

Intentional Underestimation (for Easy Approval, etc)

Page 4: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Construction Cost Change vs Excessive DemandConstruction Cost Change Cost Change due Excessive Demand

Sys vs Non-Sys Non-Systematic Change Systematic Change

Internal vs External External Factor Internal Factor

• Global Material Cost • Excessive Demand on Certain Materials

• Overall Labor Cost • Excessive Demand on Construction Labor

• General Inflation • Policy Effect on Cost

Cost Adjustment Factor Regress to Normal Insufficient due to exponential growth

Contingency Cater for all uncontrollable and external factors

Insufficient due to unexpected risk

Page 5: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Tender Price Index 1978 - 2016

Page 6: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Tender Price Index Change yoy 2011-2016

• All Positive,• Rate Up and Down• Adjustment Factor

should be able to absorb

Adjustment Factor ~6%

Page 7: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Construction Cost Index yoy

• All Positive,• Rate Up and Down• Adjustment Factor

should be able to absorb

Adjustment Factor ~6%

Page 8: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Construction Material Index yoy

Construction Cost Index from CEDD (http://www.cedd.gov.hk/eng/publications/construction/doc/indices%20aft_00.pdf)

• Positive & Negative• Rate Up and Down• Adjustment Factor

should be able to absorb

Page 9: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Construction Labor Index yoy

• All Positive,• Rate Up and Down• Adjustment Factor

should be able to absorb

Page 10: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Construction Cost of HK Ranks No. 2 Highest Globallyin 2016

https://www.arcadis.com/media/2/C/F/%7B2CFC680C-A57E-43EA-99B4-0F4A784F7D51%7DAG1059_ICC%202017_FINAL_WEB%20SINGLE%20PAGES_NA-Opt.pdf

Page 11: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Excessive Demand1. Hong Kong markets are stabilizing at peak levels of

activity, which have seen projects affected by significant resourcing challenges.

2. Output in 2015 reached yet another record – up by 100% compared with 2010.

https://www.arcadis.com/media/2/C/F/%7B2CFC680C-A57E-43EA-99B4-0F4A784F7D51%7DAG1059_ICC%202017_FINAL_WEB%20SINGLE%20PAGES_NA-Opt.pdf

Page 12: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Excessive Demand of Public Works1. The private sector represents around 30% of overall

activity

2. While big [public works] projects (such as the Zhuhai Macau bridge link and the Guangzhou-Shenzhen High Speed Rail link are well advanced, new programs – the third runway at ChekLap Kok, expansion of the East Kowloon central Business District and maintenance of a large-scale housing programme totalling

480,000 units over 10 years) - are expected to sustain workload at current levels.

https://www.arcadis.com/media/2/C/F/%7B2CFC680C-A57E-43EA-99B4-0F4A784F7D51%7DAG1059_ICC%202017_FINAL_WEB%20SINGLE%20PAGES_NA-Opt.pdf

Page 13: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Increasing Trend of Public Works Expenditure1. Public Works

Expenditure is increasing steadily from $30b in the 1990s to $120b in the 2010s

2. The Rate of Increase is also increasing

Page 14: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Overbudget Situation in 2014

http://www.bauhinia.org/index.php/zh-HK/analyses/99

http://www.mingpaocanada.com/tor/htm/News/20150115/HK-gfp1_er_r.htm

Page 15: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

More Overbudget in 2015

http://hk.apple.nextmedia.com/news/art/20151201/19394841

Page 16: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Total Overbudget 1997 – 2016 (>$1b proj)分類

項目

原本核准預算費

(萬元)

最新核准預算費

(萬元)

差額

(萬元) 超支百分比 文件編號

建築物 63KA-添馬艦發展工程 516,890 552,870 35,980 7 PWSC(2009-10)73

3065KA-位於北角電照街的海關總部大樓 107,340 135,200 27,860 26 PWSC(2008-09)37

3074LC-羅湖懲教所重建工程 137,630 152,450 14,820 11 PWSC(2008-09)37

渠務 103CD-港島北部雨水排放系統改善計劃-港島西雨水排放隧道 304,470 338,130 33,660 11 PWSC(2011-12)38

111CD-荃灣、葵涌及青衣雨水排放系統改善計劃-荃灣雨水排

放隧道 125,950 148,600 22,650 18 PWSC(2011-12)39

329DS-望后石污水處理廠改善工程 136,090 192,050 55,960 41 PWSC(2010-11)12

土木工程

45CG-啟德發展計劃區域供冷系統 167,100 390,570 228,600 137

PWSC(2010-11)31

PWSC(2013-14)12

PWSC(2015-16)29

PWSC(2015-16)62

233DS-污泥處理設施 515,440 536,430 20,990 6 PWSC(2015-16)13

公路 19GB-蓮塘/香園圍口岸與相關工程-工地平整及基礎建設工

程 1,625,320 2,497,310 871,990 54 FCR(2015-16)11

845TH-港珠澳大橋香港口岸-填海及口岸設施 3,043,390 3,589,500 546,110 18 PWSC(2015-16)14

844TH-港珠澳大橋香港接線 1,618,990 2,504,720 885,730 55 PWSC(2012-13)11

579TH-中環及灣仔繞道和東區走廊連接路 2,810,460 3,603,890 793,430 28 PWSC(2013-14)29

819TH-屯門公路市中心段交通改善工程 181,440 196,790 15,350 8 PWSC(2012-13)41

53TR-廣深港高速鐵路香港段-鐵路建造工程 5,501,750 7,040,500 1,538,750 28 PWSC(2015-16)50

57TR-廣深港高速鐵路香港段-非鐵路建造工程 1,180,000 1,601,500 421,500 36 PWSC(2015-16)51

746TH-屯門公路重建及改善工程 462,050 680,430 218,380 47 PWSC(2009-10)5

6711TH -八號幹線青衣至長沙灣段-餘下工程 746,820 806,820 60,000 8 PWSC(2008-09)37

新巿鎮及巿區發展 343CL-中環填海計劃第 III 期工程 356,150 576,150 220,000 62 PWSC(2008-09)51

非經常資助金及主要系統設備 8MA-明愛醫院第二期重建計劃 121,810 171,960 50,150 42 PWSC(2011-12)11

8051MM -威爾斯親王醫院-擴建大樓 188,210 217,070 28,860 15 PWSC(2008-09)37

房屋 564CL-彩雲道及佐敦谷毗鄰的發展計劃 177,930 200,930 23,000 13 PWSC(2005-06)9

Page 17: Overbudget of Construction Costs - ecyY (easy why whY)ecyy.weebly.com › uploads › 1 › 2 › 9 › 3 › 12935669 › over...Total Overbudget 1997 –2016 (>$1b proj) 分類 項目

Total Overbudget 1997 – 2016

Original Approved

Budget ($m)

Latest Approved

Budget ($m)

Overbudget

($m) %

Total 200,252 261,339 61,138 30.5%

Ave 9,536 12,445 2,911 30.5%

SD 13,550 17,401 4,124