1 MINISTRY OF PLANNING AND INVESMENT PUBLIC PROCUREMENT AGENCY OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018

Upload: others

Post on 29-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

1

MINISTRY OF PLANNING AND INVESMENT

PUBLIC PROCUREMENT AGENCY

OVERVIEW OF PPP IN VIET NAM

HCM city, 22 May 2018

Page 2: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

2. Overview of potential projects

Content

1. PPP decree and Investor selection decree

2

Page 3: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

1. CURRENT DECREES

3

Page 4: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

PPP

Definition:

Investment based on contract between ASA

(authorized state agency) and investors/SPV to

build, renovate, operate, manage public

infrastructure or services.

[concession]

4

Page 5: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

2009

2007

1997

Decree 77/CP (1997) on BOT for domestic investors

Decree78/2007/ND-CP on BOT, BTO, BT

2015

Decree 108/2009/ND-CP on BOT, BTO, BT

Decree 15/2015/ND-CP on PPP

and Decree 30/2015/ND-CP on investor selection

20182020 …

Decree No.63/2018/ND-CP on PPP

and Decree… on investor selectionTo-be Law on PPP

LEGAL FRAMEWORK: DEVELOPMENT

5

Page 6: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

6

LAW Procurement

Law

CIRCULAR

Circular

06 on

general

issues

Circular

15/2016/TT-

BKHĐT dated

29/9/2016 on

RFQ, RFP

DECREE

Decree

replacing

30/2015/NĐ-CP on

investor selection

Decree

63/2018/NĐ-CP

on PPP

Public

Investment

Law

Construction

LawInvestment

Law

Circular

02 on

Pre-FS,

FS

Circulars

of MOF,

MOIT,

MOT,

MIC

Circular

183/2015/

TT-BTC

on BT

Law on

management

and use of

public assets

LEGAL FRAMEWORK: at a glance

Page 7: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Investment sectors

- Transportation

- Power plants, power transmission lines;

- Public lighting system, water supply, drainage, waste watertreatment facilities, solid waste treatment, park, parking areas;cemetery

- Office buildings of state agencies; public housing, resettlementshelter

- Healthcare, education, training, vocational training, culture,tourism, sports, hydro-meterology;

- Infrastructure for commercial zone, urban area, economic orindustrial zone, information technology parks; start-up supports;

- Agricultural and rural development; services for connecting theproduction with the processing and sales of agricultural products

- Other sectors pursuant to Prime Minister’s decision.

7

Page 8: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

PPP project

• In conformity with master plan

• Of the eligible sectors

• Economically feasible

• Financially feasible

• Environmentally viable

• Affordable

8

Page 9: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Public participation

• Capital contribution

– Types: in cash, in kind

– Sources: public investment fund, public assets

• Availability payment

– Sources:

• Public investment fund

• Public recurrent expenditure fund

• Revenue from public services

• Land compensation/clearance costs, auxiliary works

Not apply to single source selection of investor9

Page 10: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Private participation

(apart from public capital and land clearance supports)

• Equity

– 20% [for investment size of up-to VND 1500 billion ~ US$ 70 million]

– And 10% [for the part of investment above VND 1500 billion]

• Debt

– Remaining %

– Commercial

10

Page 11: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Procedures

Pre FS stage

FS stage

Design stage

Construction stage

Operation stage

Project development

Investor selection

Normal High-tech promotion Some

Investor selection

Investor selection

Solicited or Unsolicited 11

Page 12: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Preferred treatment to unsolicited proponent

Incentives

Service price

5% of the service price to

the investors

not entitled to incentives

State capital contribution

5% of the proposed

State capital

contribution to the

investors not

entitled to incentives

Social and State benefit

5% of the amount

contributed to the State

budget to project

proponent

Combined method

incentives in proportion to the combined

method, however the total value not exceed

5%.

12

Page 13: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Classification

Project of national

importance

Pre-FS approved by

NA

FS by Minister

/ Chairman of Province

Group ASome Pre-FS approved by

PM

FS by Minister / Chairman of

Province

OthersPre-FS by Ministry / Province

FSby Ministry /

Province

Abolishment of investment certificate13

Page 14: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Transparency

• Pre-FS and FS info after

approval (pipeline)

• Bidding plan, opportunities,

selected investors (deal)

• Basic contract info for

supervision

muasamcong.mpi.gov.vn ppp.mpi.gov.vn14

Page 15: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

New chapter for BT

• Procedure

• Payment scheme: land, other rights

• Principles:

– Pre-identifying resources

– Bidding upon FS/design

– Detailed master plan of land use

15

Page 16: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Investment incentives, tax incentives

Incentives

Tax incentives

Incentives on corporate income tax imposed on investor, project

enterprise

Incentives on import and export duties imposed on goods

imported to implement a project

Tax incentives for foreign and domestic contractors

participating in implementation of a project

exemption from or reduction of land rent or land use fees for the area of land allocated by the

State

Other incentives

16

Page 17: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

17

Investment guarantees and support

- Allow for mortgaging assets or the rights to commercially operate

the project facility

- Guarantee that the land use purpose of the project shall remain

unchanged in the entire implementation term of the project

contract

- Support land clearance and completing procedures for land

allocation or lease of land to implement the project

Assigment / transfer of equity: after completion of construction phase

Page 18: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

18

Step-in right of lenders

Lenders

ASAs

Agreement on step-in

right

The lender shall have the right to take over on its own, or to appoint another

competent organization to take over, all or some of the rights and obligations of the

investor, project enterprise (hereinafter referred to as Step-in-Rights) in the event

that the investor or the SPV fails to fulfill obligations under the project contract or

loan agreements

Page 19: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

19

Guarantee on foreign currency conversion

Permitted transactions

Buy foreign currency

Conduct foreign exchange

activities to satisfy current

transactions, capital

transactions and other

transactions; remittance

abroad of capital, profit,

proceeds from investment.

Projects to be considered for

guarantee on foreign currency conversion

Infrastructure projects of national importance or with Pre-FS approved by

PM

Other important projects

Procedure

Initiated by

Ministry /

Local People

Committee

Reviewed by /

co-ordinated

with SBV

Approved by

PM

• No guarantee on Foreign Exchange Rate

Page 20: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

20

Dispute settlement

Dispute Settlement

- Mode of dispute settlement: negotiation, conciliation, by arbitration or by

the courts

- Dispute arising between the authorized state agency and a foreign

investor or the project enterprise shall be settled by arbitration or by the

courts of Vietnam or by an arbitral tribunal established by the parties

Project contracts to which

one party is foreign

investor

Contracts for which the

GOV guarantees the

performance of

obligations

The signing parties may agree

on the application of foreign

law governing the 02

contracts, which must not

contradict the provisions of the

laws of Vietnam on selection

and application of foreign law

Page 21: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

2. POTENTIAL PROJECTS

21

Page 22: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

22

66 dự án ưu tiên

17 considered

383proposed projects

PDF VGF

8 projects of North –

South highway

9 by ASAs: MARD,

MIC, Ha Noi, HCM

city, Quang Ninh, Da

Nang

Potential projects

On-going process, more to come

Page 23: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

MOT: North-South express way

No. Project Length

(km)

B (m) Total

Investment

(US$ bil.)

Capital

(US$ bil.)

Investment

form

State budget Investor capital

Site

Cl.

VGF Total Owner’s Loan Total

1 Cao Bo – Mai Son 15 32 17 0.07 0.01 0.03 0.04 Public

2 Mai Son – NH45 63 32 17 0.64 0.08 0.14 0.22 0.08 0.34 0.42 PPP

3 NH45 – Nghi Son 43 32 17 0.34 0.06 0.04 0.1 0.05 0.19 0.24 PPP

4 Nghi Son – Dien Chau 50 32 17 0.38 0.04 0.08 0.12 0.05 0.19 0.24 PPP

5 Dien Chau – Bai Vot 50 32 17 0.6 0.05 0.25 0.3 0.06 0.24 0.3 PPP

6 Cam Lo – La Son 102 22 17 0.35 0.04 0.31 0.35 Public

7 Nha Trang – Cam Lam 29 32 17 0.23 0.03 0.08 0.11 0.02 0.09 0.11 PPP

8 Cam Lam – Vinh Hao 91 32 17 0.66 0.09 0.22 0.31 0.07 0.28 0.35 PPP

9 Vinh Hao – Phan Thiet 106 32 17 0.87 0.10 0.25 0.35 0.1 0.41 0.51 PPP

10 Phan Thiet – Dau Giay 98 32 25 0.94 0.10 0.14 0.24 0.12 0.49 0.61 PPP

11 My Thuan 2 Bridge 7 32 25 0.22 0.02 0.34 0.36 Public

Total 654 5.3 0.62 1.22 1.84 0.56 2.32 2.88

Source: MOT presentation on May 2, 2018 23

Page 24: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

HCM city: investment preparation

▷ Sectors: Transport, environment, urban refurbishment, urban

development: 94 projects; trade and service: 02 projects; education sector:

04 projects; health care: 14 projects; culture and sport sector: 17 projects.

72%

3%

11%

13%

1%

Proportion of PPP projects in investment preparation stage

By sectorTransportation, environment,

urban refurbishment

Education

Health

Culture- sport

Trade and service

Source: HCM city DPI (presentation May 2, 2018) 24

Page 25: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Potential projects

Living lists … (info from different events)

- 50+ projects of Hanoi

- 45+ projects of Quang Ninh

- 12+ projects of MOH

- …

Projects on track / required to publicized online:

http://muasamcong.mpi.gov.vn (source)

http://ppp.mpi.gov.vn (sister site)

Upgrading for English content

25

Page 26: OVERVIEW OF PPP IN VIET NAM · OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018. 2. Overview of potential projects Content 1. PPP decree and Investor selection decree 2. 1. CURRENT

Contacts

Public Procurement Agency

Ministry of Planning and Investment

Tel: 080 44681

Fax: 080 44323

Email: [email protected]

Website: www.ppp.mpi.gov.vn 26