overview of the international seismic safety centre siting ... · overview of the international...

34
Overview of the International Overview of the International Seismic Safety Centre Siting Activities Seismic Safety Centre Siting Activities Technical Meeting on Challenges on Site Selections for Nuclear Power Plants Ovidiu Coman INTERNATIONAL SEISMIC SAFETY CENTRE, NSNI/IAEA

Upload: dongoc

Post on 13-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Overview of the International Overview of the International Seismic Safety Centre Siting ActivitiesSeismic Safety Centre Siting Activities

Technical Meeting onChallenges on Site Selections for Nuclear Power Plants

Ovidiu Coman

INTERNATIONAL SEISMIC SAFETY CENTRE, NSNI/IAEA

2

IAEA – INTERNATIONAL SEISMIC SAFETY CENTRE (ISSC)

The ISSC was established (Sept 2008) within the IAEA-Department of Nuclear Safety and Security as a global focal point on seismic safety for nuclear installations worldwide.Currently (since July 2009), ISSC is part of the organizational structure of IAEA.According to its established functions the IAEA ISSC is contributing to enhance Member States capabilities to adequately monitor their nuclear installations with respect to site safety related aspects and external and internal hazards, including the engineering aspects of the protection against sabotage.

3

IAEA NS – NSNI - ISSC

Departmentof

Safeguards

Departmentof

Nuclear Science and Applications

Department of

Management

Departmentof

Nuclear Safety and

Security(NS)

Departmentof

Nuclear Energy

Departmentof

Technical Cooperation

NSNINSNIISSCISSC

DIRECTOR GENERAL

4

DIR-NSNI

International Seismic

Safety Centre

RegulatoryActivities Section

Safety AssessmentSection

Operational SafetySection

Research ReactorSafety Section

NS – NUCLEAR SAFETY INSTALLATION DIVISIONCurrent status since 1st July 2009, IAEA DG Sec/Dir/73:

5

STRUCTURE OF ISSC

The ISSC is a Section within the organizational The ISSC is a Section within the organizational structure of the Nuclear Safety Installation structure of the Nuclear Safety Installation Division, and is constituted by:Division, and is constituted by:

1. IAEA Staff Members ;2. A roster of international specialists in all

disciplines of seismic safety and earthquake engineering;

3. The Scientific Committee, constituted by highly recognized international scientists in all related fields.

6

ISSC – BACKGROUND

• Owing to the complexity of these multidisciplinary problems they should be resolved using the experience and contribution of the whole related international scientific community as well as sharing the lessons learned in order to avoid or mitigate the consequences of such extreme natural events.

7

ISSC - SCOPE

1.1. Site Selection (Site Selection (SitingSiting) and Site Evaluation) and Site Evaluation2.2. Safety against external hazards to nuclear installations: Safety against external hazards to nuclear installations:

earthquakes, flooding, tsunamis, volcanic and earthquakes, flooding, tsunamis, volcanic and meteorological hazards, human induced events including meteorological hazards, human induced events including those of malevolent origin (e.g. aircraft crash, explosions, those of malevolent origin (e.g. aircraft crash, explosions, toxic releases, etc.)toxic releases, etc.)

3.3. Site related aspects of environmental impact assessment, Site related aspects of environmental impact assessment, e.g. dispersion in air and surface and ground watere.g. dispersion in air and surface and ground water

4.4. Design related aspects Design related aspects -- Chapters 2 and 3 of Safety Chapters 2 and 3 of Safety Analysis Report. Analysis Report.

. . . geosciences, earthquake and structural engineering . . . geosciences, earthquake and structural engineering aspects, design and layout engineering . . .aspects, design and layout engineering . . .

88

STRUCTURE OF ISSC-INTEGRATION OF REGULAR AND EXTRABUDGETARY ACTIVITIES

Develop. of Safety

Standards

INTERNATIONAL SEISMIC SAFETY CENTRE

(ISSC)

Applicat. of Safety

Standards SRM/PRM

SCIENTIFIC COMMITTEE

(ScC)

IAEA Regular Budget Programme EBP TOPICAL TECHNICAL PROJECTS

1. SEISMIC SAFETY:1. WA12. WA23. . . . .

2. TSUNAMI SAFETY3. OTHER EXTERNAL FLOODS4. VOLCANIC HAZARDS5. INFORMATION SYSTEM6. EXTERNAL EVENTS

NOTIFICATION SYSTEM

IAEA MEMBER STATES

(MSs)

Services to Member States

Supports Advice

Capacity Building

E&T

Foster of R&D and informat. exchange

9

ISSC ACTIVITIES• Regular budget activities: “core” activities• Development of Safety Standards.• Assistance to Member States for application of safety standards: training, advisory and review safety services (mainly, Site Safety Review Missions).

• Activities with extra-budgetary resources:• Capacity building: workshops, training courses.• Development of topical technical projects and support to research studies.

• Knowledge management: collection and dissemination of information, Information System (database).

• External Events Notification System.

10

ISSC – REGULAR BUDGET ACTIVITIES 2009

DEVELOPMENT OF SAFETY STANDARDS:DEVELOPMENT OF SAFETY STANDARDS:•• 6 Safety Guides were revised, developed, approved, or 6 Safety Guides were revised, developed, approved, or

published during 2009published during 2009--2010.2010.•• A number of supporting documents (Safety Reports, A number of supporting documents (Safety Reports,

TECDOCsTECDOCs) were initiated and some completed.) were initiated and some completed.

ASSISTANCE TO MEMBER STATES FOR APPLICATION OF THE SAFETY STANDARDS (SITE AND SEISMIC SAFETY REVIEW SERVICES).

1111

IAEA SAFETY STANDARDS ON SITE EVALUATION

SITE EVALUATION

REQUIREMENTS

GUIDES

SAFETY GUIDES

8/25/2005 12 International Atomic Energy Agency

Safety Standards Series hierarchySafety Standards Series hierarchy

Safety GuidesSafety Guides

RequirementsRequirements

Safety FundamentalsSafety Fundamentals

New SGNew SG--DS417DS417DS422 DS405 DS433

12

IAEA SAFETY STANDARDS - SEISMIC SAFETYSITE EVALUATION

DESIGN OPERATION

SeismicHazardNS-G-3.3

Seismic Design andQualificationNS-G-1.6

PeriodicSafetyReview

new installations operating/existing installations

(t)The complete lifetime of the installation

Evaluation of Seismic Safety - Existing NINS-G-2.13

NEW

13

DEVELOPMENT OF SAFETY STANDARDSSAFETY GUIDES SAFETY GUIDES -- Activities during 2009Activities during 2009--2010:2010:1.1. Seismic evaluation of Existing Nuclear Installations (NSSeismic evaluation of Existing Nuclear Installations (NS--GG--2.13), 2.13), published.published.2.2. Seismic Hazard Assessment for Nuclear Installations Seismic Hazard Assessment for Nuclear Installations

(NS(NS--GG--3.3, DS422), 3.3, DS422), approved for publicationapproved for publication3.3. Volcanic Hazards Assessment for Nuclear Installations Volcanic Hazards Assessment for Nuclear Installations

(DS405), (DS405), to to MSsMSs for commentsfor comments..4.4. Meteorological and Hydrological Hazards for Nuclear Meteorological and Hydrological Hazards for Nuclear

Installations (DS417) Installations (DS417) to to MSsMSs for commentsfor comments..5.5. Dispersion in Air and Water and Environmental Impact Dispersion in Air and Water and Environmental Impact

Assessment (DS427), Assessment (DS427), draft in preparation.draft in preparation.6.6. Site Survey and Site Selection (50Site Survey and Site Selection (50--SGSG--S9), S9), draft in draft in

preparation (DS433).preparation (DS433).

Site Safety Review Services

• The objective of the SSRS is to provide upon request from a Member State an independent review and assessment of the site and nuclear installation safety in relation to external natural and man induced hazards and to make recommendations on additional analysis or plant modifications to be carried out in order to comply with the IAEA Safety Standards and to enhance safety.

Site Safety Review Services• A Site and Seismic Safety Review Services (SSRS) is a multidisciplinary review aimed to assess the safety of a nuclear installation site during the complete life cycle of the facility• Currently the SSRS are carried out by the International Seismic Safety Centre within the structure of NSNI while previously were under responsibility of the Engineering Safety Section. • All these safety review services are supported and correspond to the application of a complete and comprehensive set of safety requirements and safety guides documents of the IAEA• SSRS integrates with the Design Safety Review Service, with the Probabilistic Safety Review Service (IPSART) and with the Safety Assessment of Long Term Operation (SALTO).

16

SITE AND SEISMIC SAFETY REVIEW SERVICES

More than 240 site and seismic safety site and seismic safety review missionsreview missions were conducted since 1980, to ~50 MSs. Site Safety Review Missions in 2009 :• To MSs embarking in NPP site selection: Egypt, Jordan, Vietnam, Nigeria, Tunisia, Belarus, Turkey.

• To others: Iran, Armenia.

SSRS output-Mission report

Field Activities During the K-K Mission: Geological investigations at the site area

SSRS Meetings

SSRS Work under press’s pressure

21

CURRENT EBPs1. Tsunami EBP - TIPEEZ:

• Started in 2007. Finalize in March 2010. • The concept of integration into other ISSC extra budgetary activities, after March 2010, was agreed at March 2009 StC.

2. Seismic EBP:• Started in 2007. Finalize in September 2010• At September 2009 StC Meeting, it was agreed that Seismic EBP is

a part of ISSC and the participating organisations are considered as ISSC participants. 3. ISSC EBP:

• Started in 2008, supported by NISA/JAPAN, US/NRC and Argentina.

4. ISSC EC:• In final stage of contract negotiation with EC -3 years -2 MEuros.

22

Current topical technical projects•• Research on Research on seismic damage indicatorsseismic damage indicators (e.g. CAV) and ground (e.g. CAV) and ground

motionmotion--distance attenuation relationships.distance attenuation relationships.•• Research on Research on simulation of structures and equipment of simulation of structures and equipment of NPPsNPPs under under

earthquakes (earthquakes (KARISMA benchmarkKARISMA benchmark project).project).•• Development of Development of prepre--earthquake planning and postearthquake planning and post--earthquake earthquake

actionsactions criteria criteria –– a Safety Reporta Safety Report..•• Development of Development of databases, information system and notification databases, information system and notification

systemsystem on external events related fields.on external events related fields.•• Development on detailed Development on detailed guidelines for seismic instrumentationguidelines for seismic instrumentation and and

plant shutdown criteria plant shutdown criteria -- a TECDOCa TECDOC..•• Development of detailed Development of detailed guidelines for seismic reguidelines for seismic re--evaluationevaluation for for

existing nuclear installations existing nuclear installations –– a Safety Reporta Safety Report for supporting NSfor supporting NS--GG--2.13 (updating of current SR28).2.13 (updating of current SR28).•• Tsunami Tsunami hazard assessment.hazard assessment.

IAEA Safety Review Service onIAEA Safety Review Service on

May 2010 – ChileMay 2010 – Chile

ASSISTANCE TO MEMBER STATES- SITING AND DESIGN PROCESS -2010 M 8.8 Earthquake in Chile

Invited by Chilean Nuclear Energy Commission

•• Findings from the occurred event how to deal with the Findings from the occurred event how to deal with the extreme external hazardsextreme external hazards in in sitingsiting and design of NPPand design of NPP

•• LessonLessonss learned from past events in Japanlearned from past events in Japan

24

• Other activities:• Asia Nuclear Safety Network workshop in

South-east Asia• Date: June 2010• Scope: Safety Requirements of NPP Siting

• 20th Structural Mechanics in Reactor Technology(SMiRT 20) : • An Special Session regarding the KK NPP experience

(Aug. 2009, Finland) • Collaboration with IASMiRT on Database platform for

permanent repository of all documentation.

CAPACITY BUILDING - EDUCATION AND TRAINING

257/9/2010 25

• A need to know latest developments in relation to external hazards at global scale and which may be their effects in nuclear installations (data collections, lessons learned, benchmarks, R&D, etc.)

• A tool for communication to the media and to the public.

• A repository of data, information, documentation in all related fields.

IAEA/ISSC INFORMATION SYSTEM AND EXTERNAL IAEA/ISSC INFORMATION SYSTEM AND EXTERNAL EVENTS NOTIFICATION SYSTEMEVENTS NOTIFICATION SYSTEM

267/9/2010 26

The main objective of the “External Event Notification System” is to receive at real time at the IAEA-ISSC, information on the occurrence of external events at the world which could affect operating nuclear installation sites, through a web based online monitoring system. This information may be used as appropriate for communicating with the IAEA staff, the Member States, the public and the media through an adequate product such as an “External Events Notification Report”.

IAEA/ISSC EXTERNAL EVENTS NOTIFICATION IAEA/ISSC EXTERNAL EVENTS NOTIFICATION SYSTEMSYSTEM

27

IAEA/ISSC EXTERNAL EVENTS NOTIFICATION IAEA/ISSC EXTERNAL EVENTS NOTIFICATION SYSTEM SYSTEM –– current statuscurrent status

28

Hokkaido earthquake (M=5.0) in Japan in 21.11.2009 and Tomari NPP sites

Criteria for Earthquake Concern Region dx = 50 km 5 > M ≥ 4dx = 300 km 7 > M ≥ 5dx = 1000 km M ≥ 7

dx

29

IAEA/ISSC EXTERNAL EVENTS NOTIFICATION SYSTEM IAEA/ISSC EXTERNAL EVENTS NOTIFICATION SYSTEM ––current statuscurrent status

• Full synergy between participatingInstitutions: ISSC/US-NRC/USGS/USNOA• Working at different ‘layers’: international, regional, national, local (NPPsite)• A part of our Incident Emergency Centre• A notification formal tool• Criteria defined for installation fragility

NPP Site 1NPP Site 2

NPP Site 1NPP Site 2NPP Site 3NPP Site 4

NPP Site 1NPP Site 2NPP Site 3NPP Site 4

SL2 exceededSL1 exceededFelt at site

NPP Sites

Estimated Levels

NOTIFICATIONSNPP Sites

TSUNAMICAST

TSUNAMICAST

3333

FINAL REMARKS

•• Sharing of Sharing of ““Lessons learnedLessons learned”” from the occurrence of from the occurrence of strong natural events, (tsunamis, earthquakes, strong natural events, (tsunamis, earthquakes, hurricanes, etc.). Unresolved issues.hurricanes, etc.). Unresolved issues.

•• Impact on site selection and site evaluation criteria and Impact on site selection and site evaluation criteria and methodologies.methodologies.

•• A need for international cooperation, openness and A need for international cooperation, openness and transparency transparency –– Sharing of experience.Sharing of experience.

•• The INTERNATIONAL SEISMIC SAFETY CENTRE is now The INTERNATIONAL SEISMIC SAFETY CENTRE is now a global focal point for the nuclear engineering a global focal point for the nuclear engineering community in relation to community in relation to SitingSiting, Site Evaluation and , Site Evaluation and External Hazards.External Hazards.

34

International Atomic Energy Agency

Thank you for your attention