p j frampton proof of evidence -...
TRANSCRIPT
S36 Application Draft v (vi) 1 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
P J FRAMPTON PROOF OF EVIDENCE
ELECTRICITY ACT 1989
SECTION 36 APPLICATION
TO DISMANTLE THE EXISTING SITE AND REMOVAL OF 102 TURBINES;
ERECTION OF 34 (PREVIOUSLY 39, (AS ORIGINALLY SUBMITTED 42
TURBINES)) UP TO 3MW TURBINES ON EXISTING SITE, CRANE HARD
STANDING; ACCESS TRACKS, UPGRADE ACCESS FROM THE A483
SUBSTATION; 2 POWER ASSESSMENT MASTS (ANEMOMETER) AND
ASSOCIATED INFRASTRUCTURE WORKS.
AT LLANDINAM WINDFARM
APPLICANT’S REF: CEL01/PF/8926
S36 Application Draft v (vi) 2 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
PETER JAMES FRAMPTON BSc (Hons), TP MRICS, MRTPI will say:
1.0 INTRODUCTION
1.1 I hold a Bachelor of Science Honours Degree in Town Planning. I am a member of
the Royal Town Planning Institute and the Royal Institution of Chartered Surveyors. I
am a Director in the firm of town planning consultants and chartered surveyors that
bears my name, Framptons Town Planning Ltd trading as ‘Framptons’.
1.2 Framptons has offices at Oriel House, 42 North Bar, Banbury and Aylesford House,
Royal Leamington Spa. I have practised in planning consultancy for over thirty years.
Prior to entering private practice in 1982 I held the position of a Senior Development
Control Officer at Lichfield District Council.
1.3 I have provided planning evidence at the following windfarm inquiries: -
• Carland Cross Cornwall
The dismantling and removal of 15 wind turbines and associated earthworks
and erection of 10 wind turbines (125m) and ancillary works (a repowering
scheme).
S36 Application Draft v (vi) 3 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• Floods Ferry March Cambridgeshire
The erection of 9 wind turbines with a maximum height of not more than
110.5 metres from base to blade tip (when vertical), together with ancillary
development.
• French Farm Thorney Cambridgeshire
Alteration of existing planning consent 98/0094/FUL and re-submission of
application 07/0156/FUL for 2 no. wind turbine generators in existing
consented positions, proposed tower height of 60m (blade tip height of 100m);
and associated works.
• Barmoor between Ford and Lowick, Berwick on Tweed
The proposed development of 6 turbines (up to 110.5m in overall height), on-
site sub-station including electrical control room, temporary construction
compound area, unit transformers, upgrading and providing new access tracks,
and a permanent anemometry mast.
• Hallburn Farm Longtown Carlisle
Erection of six wind turbines, each with a maximum generation capacity of
2MW. Each wind turbine would have a total height to blade tip of no more
than 126.5m. In addition to the turbines, the development would include
access tracks, crane hardstandings & outrigger pads, control building,
underground electrical cables and temporary construction compound.
S36 Application Draft v (vi) 4 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
1.4 The scope of my evidence is as follows: -
(i) To set out in summary form the National, European and International
Obligations to address the impacts of climate change through the
generation of energy from renewable sources.
(ii) To set out national and Welsh Government policy towards renewable
energy development.
(iii) To identify the key planning policy issues that are relevant to this
proposal
(iv) To identify the key site specific planning issues that are raised by this
proposal – for and against the granting of planning permission.
(v) To consider the issues raised by third parties particularly the Alliance.
(vi) To undertake a balanced planning judgement in the overall public
interest.
1.5 I understand my duty to the Inquiry and have complied, and will continue to comply,
with that duty. I confirm that this evidence identifies all facts which I regard as being
relevant to the opinions that I have expressed and that the Inquiry’s attention has been
drawn to any matter which would affect the validity of that opinion. I believe that the
facts stated within this proof of evidence are true and the opinions expressed are
correct.
S36 Application Draft v (vi) 5 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
1.6 My participation in the preparation of the Environmental Statement and the SEIs has
been confined to the preparation of the planning policy update within the 2013 SEI. I
rely upon the ES as updated by the 2011 SEI, and 2013 SEI in forming my judgement
on the overall planning balance. In addressing the site specific issues, I shall further
draw upon the evidence of other witnesses.
1.7 As described in the heading to this proof of Evidence the scheme originally sought
planning permission for the replacement of 102 existing turbines with 42 turbines.
The SEI 2011 reduced the scheme to 39 turbines, by the omission of Turbines T22,
T23 and T24. The SEI submitted in April 2013 omits from the application, turbines
T19, T20, T21, T25 and T26. The determination of the application is sought on this
basis.
1.8 The proposal is not an application for a ‘new’ windfarm in the sense that the land has
hitherto not been developed, but comprises a ‘repowering’ scheme arising from:
• The decommissioning of an existing windfarm which has been in operation for
20 years, pursuant to the provisions of two planning permissions Ref M20962
(43 turbines) and M21043 (60 turbines). Neither consent imposes a condition
limiting the life of the planning permission.
S36 Application Draft v (vi) 6 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• The replacement of 102 turbines of 45.5m in height with 34 turbines of up to
121.2m tip height (except turbines T29, T30 and T42 which would have a
reduced height to blade tip of 111.2m (as proposed in the 2011 SEI)).
1.9 The description of the site and the surrounding area is as set out in the Statement of
Common Ground. Llandinam is situated outside, but close to the Strategic Search
Area C, referred to later, as identified in Technical Advice Note (TAN) 8.
1.10 The Inspector has not required proofs of evidence for the opening inquiry session; nor has the
date for proofs for subsequent sessions yet been reached. Nonetheless, I have been asked to
produce my full proof of evidence – for all future inquiry sessions and making clear my
thinking on the overall planning balance – at this earlier stage with a view to transparency
and in order to provide an overview of the Llandinam case as a whole. In doing so, I
obviously reserve the right to produce such supplementary or rebuttal evidence as may be
appropriate or necessary in the light of any additional circumstances and the evidence of
others. The Summary and Conclusions at the end of this proof have also been appended to
Celtpower’s Statement of Case and serve as the outline statement - on policy matters - which
the Inspector has requested for the opening session of these conjoined inquiries.
S36 Application Draft v (vi) 7 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.0 THE NEED FOR RENEWABLE ENERGY DEVELOPMENT
2.1 I have not attempted to catalogue fully the development of the HM Government’s
energy policy in response to climate change. The Government’s energy policy,
including its policy on renewable energy was comprehensively first set out in the
Energy White Paper 2003. The Energy White Paper 2003 set a target to generate
10% of the UK electricity from renewable sources by 2010.
2.2 In 2006 the Government published ‘The Energy Challenge’. The Report states:
‘The Government therefore proposes to strengthen the framework that supports
the development and deployment of renewable technologies. With this strategy,
the Government believes that we can achieve 20% of our electricity coming from
renewable sources by 2020.’
2.3 The Government gave greater clarity on the strategic issues relating to renewables and
published a “Statement of Need” which is attached as Appendix D to The Energy
Challenge
2.4 In the context of the issues raised by this proposal the following paragraphs from the
Statement of Need are considered especially relevant (third paragraph 205; second
paragraph 206):
S36 Application Draft v (vi) 8 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
‘New renewable projects may not always appear to convey any particular local
benefit, but they provide crucial national benefit (emphasis added). Individual
renewable projects are part of a growing proportion of low-carbon generation
that provides benefits shared by all communities both through reduced emissions
and more diverse supplies of energy, which helps the reliability of our supplies.
This factor is a material consideration to which all participants in the planning
system should give significant weight when considering renewable proposals
(emphasis added). These wider benefits are not always immediately visible to the
specific locality in which the project is sited. However, the benefits to society and
the wider economy as a whole are significant and this must be reflected in the
weight given to these considerations by decision makers in reaching their
decisions’ (pg 205)
2.5 A review of the Government’s international and domestic energy strategy was
announced by the Chancellor of the Exchequer in July 2005, which resulted in the
Stern Review being presented to the Prime Minister and Chancellor of the Exchequer
in autumn 2006. Stern concluded that the scientific evidence of climate change is
overwhelming and that constitutes a serious global threat demanding an urgent global
response. He concluded:
“the investment that takes place in the next 10-20 years will have a profound
effect on the climate in the second half of this century and into the next. Our aims
now and over the coming decades could create risks of major disruption to
economic and social activity on a scale similar to those associated with the great
wars and the economic depression of the first half of the 20th Century. And it will
be difficult or impossible to reverse these changes.”
Stern consequently argued for ‘prompt’ and strong action.
S36 Application Draft v (vi) 9 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.6 The Energy White Paper, Meeting the Challenge Bill (May 2007) set out the
Government’s international and domestic energy strategy to respond to the two main
energy challenges of climate change and energy security. Support for renewable
energy is strengthened as its provision meets the twin strategic goals of attaining a
low carbon economy and security of supply. One of the key elements of the strategy
is to provide legally binding carbon targets for the whole UK economy to
progressively reduce emissions (through the draft Climate Change Bill).
2.7 The White Paper reported that, despite good progress to date in renewables provision,
there are barriers slowing the rate of renewables deployment in the UK in both the
short and long term. Firstly, the most competitive renewable technologies, such as
onshore wind and hydropower, are constrained (amongst other factors) by the
scarcity of suitable sites. Secondly, securing planning consent for renewables, and in
particular onshore wind, can be an especially difficult process, with developers
facing uncertainty and significant risk of delays. Thirdly, there are significant
challenges and delays in connecting renewables generation projects to the
transmission and distribution network, affecting both onshore and offshore
renewables. Grid capacity is available and agreed by contract for this scheme and the
application for the connection infrastructure is reasonably advanced. The granting of
consent is likely to lead to a prompt contribution from this wind energy development
towards achieving renewable energy targets.
S36 Application Draft v (vi) 10 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.8 The White Paper seeks to overcome these barriers and aims to increase the proportion
of energy from renewable sources, predominantly through the Renewables
Obligation, which is to be strengthened by increasing the Obligation up to 20%;
through reform of the planning system; and by removing barriers to decentralised
electricity generation.
2.9 I draw attention to the following content:
• The first quoted paragraph from the Statement of Need in the July
2006 Energy Review Report is restated in this White Paper.
• The White Paper states inter alia that the Government is also (para
5.3.67):
• ‘underlining that applicants will no longer have to demonstrate
either the overall need for renewable energy or for their
particular proposal to be sited in a particular location;
• giving a clear steer to planning professionals and local authority
decision makers, that in considering applications they should look
favourably on renewable energy developments.’
2.10 Proposals to deliver the EU's commitments are set out in the EU Climate and
Energy Package, released in January 2008. The measures will dramatically increase
the use of renewable energy in each country and set legally enforceable targets for
governments to achieve them. The package seeks to reduce greenhouse gas emissions
S36 Application Draft v (vi) 11 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
by at least 20% and increase renewable energies 20% by 2020. The emissions
reduction will be increased to 30% by 2020 when a new global climate change
agreement is reached. The package included a draft Directive on the Promotion of the
Use of Energy from Renewable Sources.
2.11 On 26th November 2008, three Bills which seek to tackle climate change received
Royal assent: the Climate Change Act 2008, the Energy Act 2008 and the Planning
Act 2008.
2.12 The key provisions of the Climate Change Act 2008 are:
Legally binding targets:
• Greenhouse gas emission reductions of at least 80% by 2050, and reductions
in CO2 emissions of at least 26% by 2020, against a 1990 baseline.
• The 2020 target will be reviewed soon after Royal Assent to reflect the move
to all greenhouse gases and the increase in the 2050 target to 80%.
• A carbon budgeting system which caps emissions over five year periods,
with three budgets set at a time, to set out the trajectory to 2050. The first three
carbon budgets run from 2008-12, 2013-17 and 2018-22, and needed to have
been set by 1 June 2009.
S36 Application Draft v (vi) 12 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• The creation of the Committee on Climate Change, a new independent,
expert body to advise Government on the level of carbon budgets and where
cost effective savings could be made. The Committee gained statutory status
on 1 December 2008, and has issued its first report, ‘Building a Low Carbon
Economy - the UK’s contribution to tackling climate change’.
• The aviation and shipping industries to be accountable for their UK
greenhouse gas emissions.
• Five gases other than carbon dioxide, including methane, to be classified as
greenhouse gases.
• Government to report back every five years.
2.13 The Energy Act 2008 implements the legislative aspects of the 2007 Energy White
Paper: Meeting the Energy Challenge. The Act strengthens the Renewables
Obligation to drive greater and more rapid deployment of renewables in the UK with
the aim of increasing the diversity of the UK’s electricity mix, improving the
reliability of energy supplies and helping to lower the carbon emissions from the
electricity sector.
2.14 The EU Climate and Energy Package was formally agreed in April 2009 and
commits the EU to achieving a reduction in EU greenhouse gas emissions of 20% by
S36 Application Draft v (vi) 13 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2020, increasing to up to 30% in the event of an international agreement on climate
change, compared to 1990 levels. The package includes a binding renewables target
of 20%. The UK’s share of this target is to deliver 15% renewable energy by 2020.
2.15 In April 2009 the EU Renewable Energy Directive (2009/28/EC) was issued
committing Member States to set national targets for consumption of energy from
renewable sources in terms of a proportion of total energy consumption. The EU’s
overall 20% renewable energy target for 2020 has been divided into legally binding
targets for the 27 Member States, averaging out at 20%. The Member States are
given an ‘indicative trajectory’ to follow in the period up to 20%. The UK target for
share of energy from renewable sources in gross final consumption of energy by
2020 is 15%.
2.16 In July 2009, The UK Renewable Energy Strategy was published, which sets out
the means by which the UK will meet its legally-binding targets under the EU
Renewable Energy Directive. The UK’s contribution to the EU target is to increase
the share of renewables in the energy mix to 15% by 2020, which represents a seven-
fold increase in UK renewable energy production from 2008 levels. A key element
of the new strategy is it sets out the EU requirement that there will be reporting steps
every two years in which the achievement of delivery against the trajectory set for the
2020 targets has to be tested and reported to the EU.
S36 Application Draft v (vi) 14 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.17 The Renewable Energy Strategy sets out the Government’s comprehensive action
plan for delivering the ‘renewables revolution’. The document sets out the balance of
fuels and technologies that is most likely to achieve this challenging goal and the
strategic role that the UK Government will adopt and the specific actions intended to
lead delivery.
2.18 The UK Government is committed to ensuring that the appropriate regulatory and
financial frameworks are in place to enable the market to deliver the required
increase in renewable energy. This includes:
• Extending and expanding the long-term incentive for major renewable
electricity developments; the Renewables Obligation; to ensure that it can
deliver more than 30% of electricity generated from renewables (it is
anticipated that about two thirds of this will come from on and offshore wind
projects). Renewable energy developments currently deliver around 5.5% of
electricity
• Establishing the Office for Renewable Energy Development to work with all
relevant stakeholders in the planning system, supply chain, connection to the
grid and bio-energy supply. The relevant stakeholders include the Planning
Inspectorate; local and regional authorities; Government offices and bodies
such as the Carbon Trust
• Ensuring a strategic approach to planning, working with regional authorities to
develop robust evidence-based strategies for delivering each region’s
renewable energy potential in line with the 2020 target;
S36 Application Draft v (vi) 15 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• Supporting swifter delivery of renewable and low carbon energy applications;
• Investing in the UK renewables industry to develop the wider renewables
supply chain and to develop next-generation technology development and
generation;
• More strategic investment in the grid;
• Developing a system for a quicker and fairer connection to the grid; and
• Highlighting the new requirement of the EU Directive that there will be two
year reporting stages to the EU to show that each country is on target to meet
the trajectory for the 2020 targets – it is no longer a case of working towards a
distant target, as there are effectively now several closely spaces interim
targets to be met.
2.19 The Renewable Energy Strategy 2009 is also intended to tackle climate change,
reducing the UK’s emissions of carbon dioxide by over 750 million tonnes between
2009 and 2030. It will also promote the security of the UK’s energy supply, reducing
overall fossil fuel demand by around 10% and gas imports by 20–30% against what
they would have been in 2020.
2.20 The Government summarises the significance in increasing the use of renewable
energy stating:
“The UK needs to radically increase its use of renewable energy, on account of:
S36 Application Draft v (vi) 16 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• The impending threat of dangerous climate change
• the growth in global demand for energy over the next few decades, and
the depletion of our North Sea oil and gas resources
• the requirement for the UK to recover some of its energy self-sufficiency,
while assuring that more of our imported energy comes from reliable
sources
• the UK needing a robust and thriving renewable energy sector to
maximise the economic and employment opportunities that may be
derived therefrom.”
2.21 The commitment within the EU Directive requires ‘an increase in the share of
renewable energy by almost a factor of seven from about 2.25% in 2008. ‘The Path
to 2020’ (UK-Renewable Energy Strategy) (UK-RES) states:
“The precise breakdown of the 2020 renewable energy target between
technologies will depend upon how investors respond to the incentives we put in.
However, our modelling suggests that renewables could provide more than 30%
of our electricity (compared to around 5.5% today); more than two thirds of that
could come from on and offshore wind.”
2.22 Chart 2.4 displayed in the UK-RES at page 44 – reveals that some 14GW – about
37% is expected to be sourced from on-shore windfarms in the period to 2020. A
similar contribution is anticipated from offshore wind. Other technologies amount
individually to very small percentage contributions.
2.23 The Government states that ‘delivering such a significant level of renewable energy
will be very challenging but we are fully committed to making it happen’ (para 2.4).
S36 Application Draft v (vi) 17 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Four key actions are identified to achieve a ‘swifter delivery’ of renewable energy
projects namely:
1) Better planning for delivery
2) Stronger renewable industry
3) Quicker smarter grid connection
4) Using more sustainable bioenergy
2.24 In ‘Better Planning for Delivery’ the Government states (Executive Summary Para
3.6):
“Our planning system must enable renewable deployment in appropriate places,
at the right time, and in a way that gives business the confidence to invest. Thus
we must speed up the system and make it more predictable, while ensuring that
we continue to protect our environment and natural heritage and respond to the
legitimate concerns of local communities. Clearly we do not want to see large-
scale renewable deployment in places where it is inappropriate. But in many
more places where such deployment is both appropriate and desirable, we are
determined to make faster progress”.
2.25 The Renewable Energy Strategy is an integral part of the UK Government’s overall
UK Low Carbon Transition Plan July 2009 to ensure delivery of the clean, secure
and affordable energy of the future. The UK Low Carbon Transition Plan establishes
a roadmap for the decarbonisation of the UK. The White Paper sets out the actions
we are going to take to achieve this in practice while maximising economic
opportunities, spreading the costs fairly, and keeping energy supplies safe and secure.
S36 Application Draft v (vi) 18 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
The approach will be based around measures to promote a competitive energy
market, making polluters pay for the carbon they use, supporting technological
development and helping people make low carbon choices. Amongst other things, it
confirms a policy imperative to produce around 30% of our electricity from
renewables by 2020 by substantially increasing the requirement for electricity
suppliers to sell renewable electricity. (Summary at page 4).
2.26 The 2nd Progress Report of the UK Committee on Climate Change of June 2010
reiterates that a “step change” in the pace of emissions reductions is required to meet
carbon budgets and the implementation of measures designed for the next carbon
budget period, including increasing installed capacity from renewable sources.
2.27 In his speech to UK Energy Summit – Department of Energy and Climate Change the
Secretary of State said on 24th June 2010:
‘The real challenge is to build a different kind of economy. One that cuts our
carbon emissions to tackle climate change and which makes our energy secure in
a volatile world.’
2.28 The Renewable Energy Action Plan (July 2010) reiterates support for renewable
energy and reinforces the need to meet the EU targets through development of
renewable energy sources. The Government’s commitment extends to engaging with
the independent UK Committee on Climate Change to advise on scope for a more
ambitious target for renewables.
S36 Application Draft v (vi) 19 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.29 The first Annual Energy Statement was presented to Parliament by the Energy and
Climate Change Secretary on the 27th July 2010. The Secretary of State identified a
‘challenge’ as being ‘to spur the capital investment required for new energy
infrastructure.’ The Coalition intends to increase the target for energy from
renewable sources subject to the advice of the Climate Change Committee. The
Statement states:
‘This Government is committed to being the greenest Government ever, which
includes a firm commitment to renewable energy. The Coalition document sets
out a wide range of policies that will enable us to go further. This includes
engaging with the independent UK Committee on Climate Change to advise on
whether it is possible to increase our ambition for the level of energy from
renewables for 2020 and beyond.’
2.30 The Committee on Climate Change published the Renewable Energy Review on 9
May 2011. This expresses the view that whilst the UK Government’s 2020 ambition
is appropriate, its achievement will require large-scale investment and new policies to
help support technology innovation and to address barriers to uptake in order suitably
develop renewables as an option for future decarbonisation. The Renewable Energy
Review also acknowledges that, compared with onshore wind, most other renewable
energy generation technologies are expensive and likely to remain so until at least
2020, and in some cases, considerably later.
S36 Application Draft v (vi) 20 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.31 As a result, onshore wind is a key element of the portfolio of low carbon generation
technologies which the Climate Change Committee says is required to ensure that the
UK’s renewable energy targets and climate change commitments are met.
2.32 The Government issued the Electricity Market Reform White Paper (EMR) on 12
July 2011. Government intends to finalise the proposed policy by the end of 2011,
with its legislating for the “key elements” in the package to occur in the second
session of May 2012. It is anticipated that such legislation will reach the statute book
in April 2013. The first low carbon projects to be supported under such provisions
are anticipated to occur in 2014.
2.33 Onshore wind is described as a “mature technology” (paragraph 2.3.25), in which the
market can be prepared to invest with some certainty.
2.34 It is stated that, “The policy proposals within this White Paper form part of a much
wider DECC agenda aimed at energy decarbonisation and security of supply”. The
decarbonisation of electricity generation informs one of the three “key objectives” of
the EMR (1.3) and it is acknowledged that such an objective is implicitly linked to
the issue of climate change and the achievement of national and European renewable
energy targets.
S36 Application Draft v (vi) 21 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.35 Chapter 1 describes the “vision” to be achieved by 2030 in Box 1:
“By 2030, we will have achieved a reduction in our greenhouse gas emissions
across the whole economy in line with our carbon budgets and will be firmly on
track to achieving at least an 80 per cent reduction by 2050. We have
substantially decarbonised electricity supply and also get more than one third of
electricity generation from renewable sources… Wind power forms a substantial
part of our generation mix with cost competitive wind turbines both on and
offshore”. (emphasis added).
2.36 “Ensuring the future security of electricity supplies” is the first of the primary
objectives in the EMR. Wind power is seen as being a reliable and stable future
technology, which should inform part of the “generation mix” in accordance with a
range of advancing and currently infant renewable technologies. It is acknowledged
that onshore wind will only form part of a series of technologies.
2.37 Key to both investment and security supply rests in certainty. At para 1.6 it is stated
that “investors also need to have confidence in the planning system for major
infrastructure projects…This means giving developers greater certainty on the policy
framework for decision-making on major infrastructure projects. The Government
has therefore put before Parliament six energy National Policy Statements (NPSs)
for approval”. The EMR is considered to form “part of a much wider DECC agenda”
aimed at energy decarbonisation. The Renewables Roadmap is considered a parallel,
complimentary publication to the EMR (stated to be “published alongside this white
paper”) and outlines the strategy for deployment, in accordance with the challenge of
S36 Application Draft v (vi) 22 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
overcoming the non-financial barriers (as opposed to the consideration of
overcoming financial challenges in the EMR), (see paragraph 1.43).
2.38 The White Paper is an expression of Government policy and illustrates a direction of
travel intended by Government. The draft Energy Bill was published on the 22nd May
2012 with measures necessary to reform the electricity market to deliver secure,
clean and affordable electricity.
2.39 The Promotion of the Use of Energy from Renewable Sources Regulations 2011
(S1243/2011)
Regulation 3 states: -
‘it is the duty of the Secretary of State to ensure that the renewables share in 2020
is at least 15%’ (Regulation 2 defines “renewables share” as the share of energy
from renewable sources in the United Kingdom as calculated in accordance with
Article 5 of the Directive0.
2.40 The Department of Energy and Climate Change (DECC) issued the ‘UK Renewable
Energy Roadmap’ in July 2011, alongside the Government’s Electricity Market
Reform White Paper. The foreword explains that the document is “the UK’s first
Renewable Energy Roadmap” and that it “sets out our shared approach to unlocking
our renewable energy potential”.
S36 Application Draft v (vi) 23 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.41 The introduction explains that the goal is to ensure that 15% of UK energy demand is
met from renewable sources by 2020. At 1.3 the Roadmap explains that the ambition
extends beyond 2020 and there is reference to the recent advice from the Committee
on Climate Change (CCC) which has concluded that there is scope for penetration of
renewable energy to meet 30 – 45% of all energy consumed in the UK by 2030.
2.42 The document sets out analysis of recent trends in renewables deployment and the
pipeline of projects that could come forward before 2020, as well as barriers to be
overcome. The Roadmap sets out a targeted programme of action that the
government is taking to increase renewables deployment (para 1.8).
2.43 The Roadmap sets out a delivery plan to achieve the UK’s renewable energy target
over the next decade, based upon potential deployment levels and current constraints.
In the main, the “actions to address barriers” summarise policy measures already
being undertaken, with some new ones. The foreword states the actions are intended
to “accelerate renewable energy in the UK” (p4).
2.44 The more significant parts of the document relate to forecast costs and deployment
levels. The document will be reviewed and refreshed annually.
2.45 In terms of the most recent national renewable energy policy document, the Coalition
Government issued the Carbon Plan ‘Delivering our Low Carbon Future’ in
S36 Application Draft v (vi) 24 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
December 2011. It sets out the Government’s plans for achieving the emissions
reductions committed to the first four Carbon Budgets covering the overall period
from 2008 to 2027. These are related to the legally binding targets to reduce the
UK’s greenhouse gas emissions as set out in the Climate Change Act 2008. The Plan
also sets out how the UK will achieve decarbonisation within the framework of the
Government’s overall energy policy.
2.46 The vision, summarised at paragraph 10 (page 4) states: “if we are to cut emissions
by 80% by 2050, there will have to be major changes in how we use and generate
energy.... electricity will need to be decarbonised through renewable and nuclear
power, and the use of carbon capture in storage (CCS)”.
2.47 With regard to electricity, paragraph 16 sets out the three parts of the Government’s
expected generation portfolio, namely renewable power, nuclear and coal and gas
fired power stations filled with CCS. Paragraph 43 states that the power sector
accounts for some 27% of UK total emissions by source and that by 2050, emissions
from the sector need to be close to zero. Added to this, with the potential
electrification of heating, transport and industrial processes it is estimated that
electricity demand may rise between 30 and 60% and in such circumstances, “we
may need as much as double today’s electricity capacity to deal with peak demand”
(paragraph 44).
S36 Application Draft v (vi) 25 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.48 Paragraph 45 reiterates that while the overall direction is clear, there are major
uncertainties over both the most cost effective mix of technologies and the pace of
transition. It adds that “the Government is committed to ensuring that the low
carbon technologies with the lowest costs will win the largest market share”.
Therefore whilst there is some flexibility in the overall eventual mix that will
constitute the future UK generation platform, wind energy as a low cost renewable
technology has an important place.
2.49 The Coalition Government issued the Carbon Plan ‘Delivering our Low Carbon
Future’ in December 2011. It sets out the Government’s plans for achieving the
emissions reductions committed to the first four Carbon Budgets covering the overall
period from 2008 to 2027. These are related to the legally binding targets to reduce
the UK’s greenhouse gas emissions as set out in the Climate Change Act 2008. The
Plan also sets out how the UK will achieve decarbonisation within the framework of
the Government’s overall energy policy.
2.50 The vision, summarised at paragraph 10 (page 4) states: “if we are to cut emissions
by 80% by 2050, there will have to be major changes in how we use and generate
energy.... electricity will need to be decarbonised through renewable and nuclear
power, and the use of carbon capture in storage (CCS)”.
2.51 Paragraph 45 reiterates that while the overall direction is clear, there are major
uncertainties over both the most cost effective mix of technologies and the pace of
S36 Application Draft v (vi) 26 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
transition. It adds that “the Government is committed to ensuring that the low
carbon technologies with the lowest costs will win the largest market share”.
Therefore whilst there is some flexibility in the overall eventual mix that will
constitute the future UK generation platform, wind energy as a low cost renewable
technology has an important place.
2.52 The UK Renewable Energy Road Map Update 2012 published in December 2012, is
endorsed by a Ministerial Foreword including the First Minister for Wales. The Road
Map update states: -
‘Whilst this Renewable Energy Roadmap focuses on reaching our 2020 targets, it
is clear that renewables will have a pivotal role to play in the UK energy mix in
the decades beyond.’ (para 1.3)
2.53 In respect of development of renewable energy to 2020 para 2.5 states:-
‘It remains true, as stated in the Overarching National Policy Statement for
Energy, that there is an urgent need for new large-scale renewable energy
projects to ensure that we meet the 2020 target and wider decarbonisation
ambitions.’
2.54 Para 2.10 states:-
‘Last year’s Roadmap suggested that we could see up to around 13GW of onshore
wind capacity by 2020. Since last year we have had an increase of 1.3GW in
operational capacity (between January 2011 and end of June 2012) and the
S36 Application Draft v (vi) 27 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
onshore wind pipeline holds an additional 6.1GW of projects awaiting or under
construction as well as 7GW awaiting planning approval. The current pipeline is
likely to have the potential to provide the appropriate quantity of deployment to
fulfil our ambition outlined last year. However, we cannot be certain how much of
the capacity in the pipeline projects will go forward as not everything in the
pipeline will be consented and not everything consented will be built.’
2.55 The Update refers to onshore wind at page 36. The following considerations are
considered of relevant to this Inquiry.
‘The UK has some of the best wind resources in Europe, and onshore
wind is one of the most cost-effective large-scale renewable energy
technologies. The Government is committed to onshore wind as part of a
diverse energy mix contributing to our security of supply and carbon
reduction targets. Between July 2011 and end of June 2012, onshore wind
deployment has increased by over 1GW to a total installed capacity over
5.3GW.
Onshore wind provides substantial economic benefits. In 2011 onshore
wind supported more than 8,600 jobs contributing over £500 million to
the UK economy. By 2020 there could be around 11,600 direct and supply
chain jobs rising to around 15,500 total jobs if wider quantifiable impacts
are taken into account.
The Government is seeking to remove barriers to the development of
appropriately-sited projects, while giving local communities more
influence.
Results of the DECC Public Attitudes Tracking Survey show that the
majority of the public support the growth of onshore wind in the UK. With
this in mind, the Government is sympathetic to the concerns of
communities about developments in their areas.’
S36 Application Draft v (vi) 28 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2.56 At paragraph 2.33 the Update states: -
‘While we cannot be certain which projects will go forward, the current
pipeline is likely to represent the appropriate quantity of deployment to
fulfil the central estimated range in the 2011 Renewable Energy Roadmap
for onshore wind deployment (around 10-13GW capacity).’
Conclusions
2.57 The UK Government is committed to binding obligations to tackle the adverse effects
of climate change made at an international, European and national level. In addition
at a national level there is a further fundamental issue to ensure security of energy
supply. Recent pronouncement on renewable energy policy notably the Renewable
Energy Review 2011 acknowledged that the commitment to achieve a reduction in
C02 emissions of at least 26% by 2020 against a 1990 requires large-scale investment
in renewable technologies. The Review recognised the reliance that is placed upon
on-shore wind to achieve this commitment. The Renewable Energy Roadmap
emphasises that the goal to ensure that 15% of the UK energy demand is met from
renewable sources by 2020 is not an ‘end date’. The ambition to increase the reliance
upon renewable energy sources extends well beyond 2020. Stated in the Overarching
National Policy Statement for Energy – and repeated in the UK Renewable Energy
Road Map 2012, ‘there is an urgent need for new large-scale renewable energy
projects to ensure that we meet the 2020 target and wider decarbonisation ambitions.’
S36 Application Draft v (vi) 29 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2020 is not an end date in itself. Renewable energy development will have a ‘pivotal
role’ in the decades beyond.
2.58 The policies set out within the various documents I have referred are positively
encouraging towards renewable energy development in order to fulfil the
Governments’ legally binding commitments to reduce greenhouse gas emissions, and
to safeguard the security of our nation’s energy system. The White Papers and other
policy documents I have referred to emphasise the importance for an accelerated
provision of renewable energy development in an endeavour to meet the UK’s
obligations on renewable energy targets.
S36 Application Draft v (vi) 30 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.0 RELEVANT PLANNING POLICIES
(i) National Planning Policy
Overarching National Policy Statement for Energy (EN-1)
3.1 This NPS sets out national policy for nationally significant energy infrastructure
projects. In the context of the proposal for Llandinam the scope of the NPS relates to:
• (The repowering of) An electricity generation station with a capacity of more
than 50 megawatts
• An electricity line of 132kw – which is the subject of an application under
Section 37 of the Electricity Act.
3.2 Part 3 of NPS EN-1 addresses ‘the need for new nationally significant energy
infrastructure projects; and explains ‘that, without significant amounts of new large-
scale energy and climate, policy cannot be fulfilled’ (para 3.2.3).
3.3 Paragraph 3.2.3 continues: -
‘it will not be possible to develop the necessary amounts of such infrastructure
without some significant residual adverse impacts. This Part also shows why the
Government considers that the need for such infrastructure will often be urgent.
S36 Application Draft v (vi) 31 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
The IPC should therefore give substantial weight to considerations of need. The
weight which is attributed to considerations of need in any given case should be
proportionate to the anticipated extent of a project’s actual contribution to
satisfying the need for a particular type of infrastructure.’ (emphasis added)
3.4 The need for new nationally significant electricity projects is addressed under the
following topics.
• Meeting energy security and carbon reduction objectives
• The need to replace closing electricity generating capacity.
• The need for more electricity capacity to support an increased supply from
renewables.
Para 3.3.10 states: -
‘As part of the UK’s need to diversify and decarbonise electricity generation, the
Government is committed to increasing dramatically the amount of renewable
generation capacity (see Section 3.4). In the short to medium term, much of this
new capacity is likely to be onshore and offshore wind.’ (emphasis added)
• Future increase in electricity demand.
• The urgency of the need for electricity capacity.’
Para 3.3.15 states: -
‘In order to secure energy supplies that enable us to meet our obligations for
2050, there is an urgent need for new (and particularly low carbon) energy NSIPs
to be brought forward as soon as possible, (emphasis added) and certainly in the
S36 Application Draft v (vi) 32 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
next 10 to 15 years given the crucial role of electricity as the UK decarbonises the
energy sector.’
3.5 The NPS refers to the role of renewable electricity generation in para 3.4 stating inter
alia: -
• The UK has committed to sourcing 15% of its total energy (across the
sectors of transport, electricity and heat) from renewable sources by 2020
(para 3.4)
• Large scale development of renewables will help the UK to reduce its
emissions of carbon dioxide by over 750m tonnes by 2030 (para 3.4.2)
• The UK has substantial renewable energy resources for example the
British Isles have 40% of Europe’s wind, on-shore wind is the most well
established and currently the most economically viable source of
renewable electricity available for future large scale development in the
UK (para 3.4.3)
• It is necessary to bring forward new renewable electricity generating
projects as soon as possible. The need for renewable electricity generating
projects is therefore urgent (para 3.4.5)
3.6 The NPS addresses the issue of grid connection at Section 4.9.1, and states inter alia: -
S36 Application Draft v (vi) 33 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
‘The connection of a proposed electricity generation plant to the electricity
network is an important consideration for applicants wanting to construct or
extend generation plant. In the market system, it is for the applicant to ensure that
there will be necessary infrastructure and capacity within an existing or planned
transmission or distribution network to accommodate the electricity generated.’
‘The Planning Act 2008 aims to create a holistic planning regime so that the
cumulative effect of different elements of the same project can be considered
together. The Government therefore envisages that wherever possible,
applications for new generating stations and related infrastructure should be
contained in a single application to the IPC or in separate applications submitted
in tandem which have been prepared in an integrated way.’
3.7 The submission of a tandem application – albeit under the earlier regime of the
Electricity Act 1989 - for the grid connection has occurred with the Section 37
application by SP Manweb.
DECC National Policy Statement for Renewable Energy Infrastructure (EN-3) July
2011
3.8 This NPS covers three types of nationally significant renewable energy infrastructure
including onshore wind for projects with a generating capacity in excess of 50MW.
NPS EN-3 identifies factors that influence site selection and a range of technical and
environmental considerations which should be taken into account when determining
planning applications. Paragraphs 2.7.25 – 2.7.28 refer to the anticipated
circumstances arising from repowering of an existing windfarm.
S36 Application Draft v (vi) 34 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Technical Advice Note 8 Planning for Renewable Energy July 2005
3.9 The Welsh Government made a commitment to delivering renewable energy targets
published in the Government’s Energy White Paper 2003. This included a specific
renewable energy target of 4TWh per annum by 2010 as part of the wider UK national
target of generating 10% of electricity consumption from renewable sources, and
7TWh per annum 2020. The Welsh Government announced the need to plan for
between 800-1000 MW of installed capacity of onshore wind (some 400-600
additional turbines approximately) by 2010. The brief provided by the Welsh
Government to ARUP was to provide a map for Wales identifying ‘strategic search
areas’ capable of delivering the energy target of 4TWh by 2010. The fundamental
objective was to ascertain the most appropriate areas of Wales in which to locate the
800MW of onshore wind turbines minimising direct land take.
3.10 The Ministerial Interim Planning Policy Statement 01/2005 stated inter alia: -
‘The Welsh Government is committed to playing its part by delivering an energy
programme which contributes to reducing carbon emissions. It has established
specific renewable electricity production targets for Wales of 4TWh per annum by
2010 and 7TWh per annum by 2020.
Therefore, the land use planning system should actively steer developments to the
most appropriate locations. Development of a few large scale (over 25MW) wind
farms in carefully located areas offers the best opportunity to meet the national
renewable energy target.’
S36 Application Draft v (vi) 35 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.11 The underlying purpose of the study was to identify strategic search areas for the
concentration of new wind farm development (i.e. additional installed capacity and
ignoring existing capacity) in areas that are on balance technically, practically and
environmentally better able to accommodate such impacts than other parts of Wales.
As such ARUP did not focus their studies upon potential opportunities for repowering
existing wind farms.
3.12 TAN8 relates to the land use planning considerations of renewable energy Para 2.2
states:
‘As noted above and in the Ministerial Interim Planning Policy Statement on
Renewable Energy 2005, onshore wind power offers the greatest potential for an
increase in the generation of electricity from renewable energy in the short to
medium term. In order to try to meet the target for onshore wind production the
Welsh Government has commissioned extensive technical work, which has led to
the conclusion that, for efficiency and environmental reasons amongst others,
large scale (over 25MW) onshore wind developments should be concentrated into
particular areas defined as Strategic Search Areas (SSAs).’
3.13 TAN8 refers to the following characteristics of SSAs.
(i) The SSA boundaries are broad brush (para 2.4)
(ii) It is a matter for the LPAs to undertake local refinement within each of the
SSAs in order to guide and optimise development within each of the areas
(para 2.4)
S36 Application Draft v (vi) 36 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
(iii)If there is robust evidence that land outside (but also close to) the SSA is
suitably unconstrained, LPAs might wish to consider the possibility of
development of windfarms in these areas as well (para 2.4)
(iv)For each of the SSAs there are indicative targets of installed capacity. ‘The
installed capacity targets are intended to assist the planning process and are
not to be seen as the definitive capacity for the area. There may be practical,
technical and/or environmental reasons why the capacity may be more or less
than that indicated.’ (para 2.5)
(v) Table 1 listed indicative capacities, representing a 1/3 reduction on the
maximum capacity identified by Garrad Hassan as reviewed by Arup in their
2005 Report.
3.14 TAN8 refers to onshore wind in other areas including repowering schemes. Para 2.14
states:
‘There will also be opportunities to repower and/or extend existing windfarms which
may be located outside SSAs and these should be encouraged provided that the
environmental and landscape impacts are acceptable.’ (emphasis added)
3.15 The existing windfarm at Llandinam lies within 2.3 km to the west of SSA C as
shown on Map 4 within TAN8. In August 2012 Powys CC published a plan that
identifies the location of windfarm developments in their geographical context with
the boundaries of the SSAs as shown in TAN8. This plan is shown as APPENDIX 1
S36 Application Draft v (vi) 37 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.16 Para 2.4 of TAN8 states that 'It is a matter for local planning authorities to undertake
local refinement within each of the SSAs in order to guide and optimise development
within each of the areas.’ If there is robust evidence that land outside (but close to) the
SSA is suitably unconstrained local planning authorities might wish to consider the
possibility of development of windfarms in these areas as well’.
3.17 A ‘Potential Methodology for Local Planning Authorities with Strategic Search Areas
is set out at Annex D to TAN8. Para 1.2-1.3 states:
‘1.2 The purpose of the local planning exercise is to achieve a finer grain of
development allocation within the SSA, taking into account landscape, visual and
cumulative impacts. It is not intended for use in the negotiation of the SSA
capacities indicated in the Final TAN 8; since this would risk the achievement of
renewable energy target delivery.
1.3 It is anticipated, however, that the Final TAN 8 will allow the local planning
authorities to make minor adjustments to the SSA boundaries when translated into
their local planning documents. This will facilitate the inclusion of development
on the margins of SSAs where local conditions recommend.’
3.18 An ‘overall study area’ of some 5km radius from the margins of each SSA is
recommended at Annex D ‘to allow consideration of technically feasible areas for
possible wind turbines’ (para 2.2).
Interim Development Control Guidance – Onshore Wind Farm Developments
3.19 In 2006 Powys CC commissioned consultants, including ARUP to undertake a local
assessment on SSAs B and C. Following consultation, the study also included a
S36 Application Draft v (vi) 38 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
refinement exercise for SSA D. The assessments carried out included a 5km band
around each thereby facilitating assessment of potentially suitable areas adjacent to
each SSA – in line with TAN 8 requirements. The assessments took into account the
following factors, in line with the advice contained in TAN 8:
• Landscape factors (this was a primary consideration in the study);
• Proximity to and impact upon residential buildings;
• Statutory and non-statutory designation within the SSA;
• Biodiversity impact;
• Potential highways constraints and access issues;
• Wind speed;
• Land ownership and constraints;
• Topography;
• Archaeology;
• Hydrology;
• Connection to the electricity grid.’
3.20 Powys CC published the consultants’ assessment by way of an Interim Development
Control Guidance – Onshore Wind Farm Development (Second Draft) - (IDCG). The
IDCG was referred to in the Officer’s Report to the Powys County Council's Cabinet
on the Llandinam proposal and states on page 47.
‘…. The refinement study has not been adopted by PCC as planning policy or as
Interim Planning Control Guidance.’
S36 Application Draft v (vi) 39 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.21 The Council’s website states: -
‘The County Council published a revised IDCG in 2008 for public consultation.
At the same time the IDCG was authorised for development control use. The
weight attached to the IDCG in decision making should reflect this position.’
3.22 The IDCG as drafted states at para 2.1: -
‘Although the content of the IDCG does not carry the same weight as
Development Plan policy, it will be taken into account by the local planning
authority when determining planning applications and when responding to the
Secretary of State for Business Enterprise & Regulatory Reform on proposed
developments in excess of 50MW. It will also be a consideration for Welsh
Government Planning Inspectors in relation to appeals.’
3.23 The Planning Officer’s report to the Powys County Council Cabinet (25 September
2012) states: -
‘This study (the refinement study) included much of the land within the turbine
envelope of the proposed Llandinam windfarm within the refined SSA boundary'
3.24 The 2013 SEI has resulted in the deletion of 5 turbines in the north-western part of the
site. The drawing attached as APPENDIX 2 shows:
• TAN8 SSA C boundary – blue
• TAN8 SSA C Refinement boundary – purple
• Llandinam Repowering planning application – red.
• The proposed 34 turbines – red crosses.
S36 Application Draft v (vi) 40 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
All of the proposed turbines now lie within the refinement to the SSA C boundary.
Renewable Energy – Route Map for Wales 2008
3.25 The Route Map states:
‘Wind energy is the most readily available commercial renewable technology and
Wales weather and geography means we are well placed to use it.’ (para 7.1)
3.26 Annex E outlines the scale of the potential plans for commercial windfarms in the
seven strategic search areas identified through the 2005 TAN8 Planning for
Renewable Energy guidance as being the most appropriate locations for larger scale
windfarms in Wales outside of brownfield sites. These strategic search areas
constitute a few percent of the land mass of Wales.
3.27 Annex E identifies that the MW total of potential windfarm projects exceeds the
TAN8 2010 targets within all SSAs. The Route Map acknowledges that ‘windfarms
mean changes to landscapes… and can have localised impact on habitat and soils
during the construction phase’ (para 7.7). The Welsh Government stated:
‘We will continue to pursue the proposals in TAN8 and monitor the uptake of
windfarm sites before undertaking a further review in the light of this and related
consultations.’
S36 Application Draft v (vi) 41 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.28 In seeking to overcome barriers / timescales and targets, the Route Map states:
‘We will review TAN8 revising upwards the old targets for renewables – drawn
from a range of sources, following the publication of the Welsh Governments’
energy strategy in 2008.’
3.29 The Route Map concludes: (para 7.17)
‘If all potential projects were to go ahead in full, windfarms within the TAN8
SSAs could produce up to 2500MW of capacity, three times the existing TAN8
target for 2010. This could create almost 7 TWhr per annum from onshore wind
by 2015 – almost a third of Wales' current electricity demand.’
These potential capacities are shown in the table at Page 29. The Route Map does not
suggest that the principle of sustainable capacity provision above the TAN8 targets is
in itself objectionable.
A Low Carbon Revolution: The Welsh Government Energy Policy Statement March
2010
3.30 The Foreword by the Cabinet states, inter alia:
‘Our future well-being both material and social, will be dependent on achieving
sufficient supplies of affordable, low carbon energy. This move to a low carbon
economy is an essential part of our commitment as a Government to sustainable
development. Done successfully it will strengthen our economic well-being,
S36 Application Draft v (vi) 42 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
improve the environment and help to address key social issues such as fuel
poverty.
This statement also reflects the UK policy position, the work of the UK Climate
Change Commission and the UK National Policy Statements on Energy and
Renewables.
Wales once led the world in carbon-based energy. Our goal now is to do the same
for low carbon energy. This is a challenge but exciting and vital agenda. We are
committed to work with all sectors and across all aspects of the Welsh
Government’s responsibilities within a very strong sustainable development
framework in order to make it a reality.’
3.31 The actions to produce low carbon electricity on a large scale by onshore wind
include an aim to 4.5kwh/d/p of installed onshore wind generation capacity by
2015/2017.
3.32 The Welsh Government aim to do this [for onshore wind] by:
• Optimising the use of the existing strategic search areas set out in TAN8 on
Planning for Renewable Energy and keeping the TAN under review in the light of
progress towards these targets.
• Ensuring that windfarms fully deliver wider community benefits, through our
Forestry Commission based schemes and through the planning system.
• Addressing any transportation concerns associated with larger wind turbines.
• Working closely with the grid company and the regulator to ensure new grid
connections are provided sensitively, including seeking what connections should
run underground where they would otherwise impact on protected landscapes.
• Promoting further use of brownfield or local sites for smaller scale projects
appropriate to their locations.
S36 Application Draft v (vi) 43 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• Supporting local authorities in dealing with applications.
Written Statement by the First Minister Welsh Government. Planning for Renewable
Energy in Wales 17th June 2011
3.33 The First Minister referred to the Welsh Government’s Energy Policy Statement
published in March 2010, and stated, inter alia:
‘[However], while we continue to promote all forms of renewable energy onshore
wind is currently the most commercially mature form of renewable energy. The
Welsh Government remains committed to the principles of planning for onshore
wind in a strategic way, which seeks to optimise the production of renewable
energy whilst protecting Wales’ environment.
Our policy in TAN 8 seeks to restrict the proliferation of large scale wind farms
across the whole of Wales and focuses on the Strategic Search Areas which were
derived following an independent assessment.
The indicative capacities set out in TAN8 in 2005 reflected a considered view of
the potential impact of grid and transport connections. However, in a number of
the SSAs, developer interest has now greatly exceeded those indicative figures.
The Welsh Government believes this level of development is unacceptable in view
of its wider impacts on the local area.
In our view the TAN 8 capacities should be regarded as upper limits and we call
upon UK Government to respect this position when they finalise the Renewable
Energy National Policy Statement and to not allow proliferation when they take
decisions on individual projects in Wales.
It is this overcapacity which has led to proposals for major new overhead grid
infrastructure. We contend that the level of capacity within the Strategic Search
Areas which we set in 2005 would negate the need for the large obtrusive pylons
which are causing such concern. My Government would not support the
S36 Application Draft v (vi) 44 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
construction of large pylons in Mid Wales and my Ministers are pressing this case
with National Grid Transmission and with Ofgem.
It has always been our position, as set out in our Energy Policy Statement that
such connections should be delivered by less intrusive techniques, and as
sensitively as possible, including the use of undergrounding.’
Letter to Local Planning Authority by the Welsh Minister for Environment and
Sustainable Development July 2011
3.34 In this letter the Minister stated: (inter alia)
‘The Welsh Government’s energy policy and aspirations are set out in “A Low
Carbon Revolution” which identifies Wales’ sustainable renewable energy
potential to 2020/2025. We remain committed to pursuing these aspirations and
promoting all forms of renewable energy with onshore wind as currently the most
viable technology.
Within the aspirations set out in “A Low Carbon Revolution” is a specific
reference to the contribution which can be made by onshore wind in Wales, which
we believe has the potential to provide 2 gigawatts of capacity. These figures set
the context for the revision of Planning Policy Wales (PPW) which was
undertaken in February this year. PPW is the parent document to Technical
Advice Note 8 (TAN 8) and both of these seek to facilitate Wales’ potential output
of renewable energy.
An important function of TAN8 is to restrict the proliferation of large scale wind
farms in other parts of Wales. We also need to ensure the windfarm development
S36 Application Draft v (vi) 45 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
within the SSAs is proportionate and balanced with other needs in these areas.
Our approach is to limit the development of large scale wind farms to the area of
Wales which were independently and empirically assessed to be the most suitable.
These are the seven Strategic Search Areas (SSAs) in TAN 8. Further, wind farm
development should not reach such a scale that it would necessitate other
developments that would run counter to the policy positions set out in TAN 8, for
example on transmission network reinforcement.
… in the light of recent media coverage, I thought it would be helpful to write to
stakeholders to provide further clarity on the issues of maximum installation
capacities for onshore wind within the Strategic Search Areas (SSAs) identified in
TAN 8 in 2005.
The potential estimated in the Low Carbon Revolution Energy Policy Statement
was based in the maximum capacities that we considered appropriate for the
SSAs in TAN 8 in 2005. The maximum capacities of the SSAs as provided for and
referenced in TAN 8, were assessed by independent consultants Garrad Hassan
and provide for almost 1700 megawatts of onshore wind across all our SSAs. The
remaining 300MW are anticipated to come from a combination of development
under 25MW, brownfield sites as well as community and local schemes and a
contribution from micro-generation. We remain committed to achieving this
potential.
For ease of reference, the identified maximum capacities for each of the SSAs as
identified by Garrad Hassan were as follows: SSA A 212MW; SSA B 430MW;
SSA; C 98MW; SSA D 212MW; SSA E 152MW; SSA F 430MW and SSA G
132MW.
TAN 8 fully recognised the reinforcement of the transmission network in Mid
S36 Application Draft v (vi) 46 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Wales as necessary to the realisation of additional generating capacity in the
area, as well as providing a stronger more reliable network for energy users.
TAN 8 set out the Welsh Government’s view that connections from the individual
turbines to a substation is “via underground cables”. TAN 8 details that any
connection from a substation to the nearest point of the distribution network
would be “achieved by a standard 3 wire system on wooden poles or by
undergrounded lines”. This remains the Welsh Government’s view and is
reinforced by the approach set out within the Renewable Energy Route Map for
Wales in 2008, and the Energy Policy Statement 2010. Provided development is
limited to the maximum capacities above, we do not believe that there is a need
for the large, visually intrusive, high voltage grid network infrastructure and
associated substation of the kind proposed within Mid Wales. Where new grid is
required, we expect the grid company and regulator to ensure that it is located,
designed and installed as sensitively as possible, using appropriate techniques,
including the use of undergrounding.’
Energy Wales: A Low Carbon Transition March 2012
3.35 The First Minister for Wales states inter alia in the Foreword:
‘Energy is a defining issue for our generation and an issue on which, as a
Government, I am determined that Wales will lead.
As a nation, we are rich in energy resources and this provides a tremendous
opportunity to fuel our drive for a fairer and more prosperous Wales and to achieve
a better quality of life for our own and future generations.’
S36 Application Draft v (vi) 47 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.36 The Welsh Government’s aim is to ‘enhance the economic, social and environmental
well being of the people and communities of Wales – to achieve a better quality of life
for our own and future generations’. The ambition is to ‘create a sustainable low
carbon economy for Wales’. The document states (page 6):
‘Our commitment to working with business to deliver these aims is a major priority.
In addition, in working to make this a reality, we will also seek to ensure that the
people and communities of Wales derive benefits over and above decarbonising our
energy system. We want a genuinely sustainable approach to transition in line with
our commitment to sustainable development as our central organising principle. By
working to deliver wider benefits for Wales, we believe this will be good for both the
long-term interests of business as well as our communities. Our aims in this respect
are threefold.
Firstly, we want to maximise the long-term economic benefits, and in particular the
job creation potential, for Wales. In the UK, it is predicted that 250,000 new jobs will
be created by 2020 in the energy sector and with its energy resources and significant
academic and operational expertise, we believe that Wales has the potential to
generate far more than a proportional share of these new jobs.
Secondly, we want to ensure that communities benefit from energy infrastructure
developments. Any significant infrastructure developments, whilst important to the
transition to a low carbon economy, will impact on communities and their local
environments. We believe that ensuring there are clear community benefits from such
developments is a critical part of the dialogue and engagement, particularly for those
developments which have a large spatial impact.
Finally, we want to carefully plan and manage the relationship between energy
development and our natural environment in line with the ambition of ‘Sustaining a
Living Wales.’’
S36 Application Draft v (vi) 48 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.37 Under the heading ‘Ensuring Wales’ communities benefit from energy developments’
it is stated:
‘If our transition to a low carbon future is to be successful we must ensure that our
communities are fully engaged and that they receive long-term positive benefits.
Energy presents a significant opportunity to bring wealth and long term benefit to
urban and rural areas, thus safeguarding the long term viability of our communities.
Not only do energy developments offer our businesses and workers significant
opportunities, they also offer the opportunity to secure investment into our
communities.’
3.38 In ‘Delivering renewable energy’ it is stated (p.19):
• ‘the renewable sector supported around 13,000 jobs in Wales in 2009/10
• 62% of renewable generation stems from sources such as wind and solar’
Written Statement by the Welsh Government Minister for Environment and
Sustainable Development 15th October 2012
3.39 Looking ahead, we will continue to enhance our efforts to reduce greenhouse gas
emissions in Wales and look to ensure that Wales is well-prepared to manage the impacts
of climate change. Our Climate Change Strategy confirms the approach and policies for
delivering our commitment to reduce emissions by 3% per year from 2011 in areas of
devolved competence, against the baseline of average emissions between 2006 and 2010.
S36 Application Draft v (vi) 49 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
The Strategy sets out the Welsh Government’s commitment to lead action in tackling
climate change and we are already making good progress in this area. But our
targets can only be achieved if everyone – government at all levels, people,
communities and businesses – all play their part. This is why we are working across
government, with the wider public sector and with businesses and communities to
help deliver on this agenda. It is this partnership approach that will help us to meet
the challenging emission reduction targets that the science demands.’
Planning Policy Wales (PPW) Edition 5 November 2012
3.40 PPW sets out the land use planning policies of the Welsh Government. It is
supplemented by a series of Technical Advice Notes (TANs – including TAN8
Renewable Energy 2005). PPW translates the commitment of the Welsh Government
to sustainable government into the planning system. Paragraph 12.8.1 states:
‘Our approach is to reduce energy consumption and improve energy efficiency first
and maximise renewable and low carbon energy generation at every scale across
Wales.’ (emphasis added)
3.41 Paragraph 12.8.2 states:
‘The Welsh Government’s Energy Policy Statement identifies Wales’ sustainable
renewable energy potential to 2020/2025… (which refers to a total capacity of
2GW). Planning policy at all levels should facilitate delivery of both the Welsh
Government’s overall Energy Policy Statement, and UK and European targets on
renewable energy… The issues at the heart of these duties are an established
focus of planning policy in Wales and in this context both local planning
S36 Application Draft v (vi) 50 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
authorities and developers should have regard in particular to the guidance
contained in Technical Advice Note 8: Planning for Renewable Energy – A Tool
Kit for Planners (para 12.8.2)’
3.42 The stated operational or consented capacity stated in PPW (figure 12.1) is 0.7 GW.
The Welsh Government is committed to using the planning system, inter alia, to:
- Optimise renewable energy generation
- Recognise that the benefits of renewable energy are part of the overall
commitment to tackle climate change by reducing greenhouse gas emissions
as well as increasing energy security.
3.43 Para 12.8.12-13 states:
12.8.12‘The potential for renewable and low carbon energy in Wales as
established in the Energy Policy Statement (see Figure 12.1) demonstrates that
strategic scale wind energy continues to offer the greatest potential (for activities
within the control of the planning system in Wales). Wales has an abundant wind
resource and power generation using this resource remains the most
commercially viable form of renewable energy. The Welsh Government accepts
that the introduction of new, often very large structures for onshore wind needs
careful consideration to avoid and where possible minimise their impact.
However, the need for wind energy is a key part of meeting the Welsh
Government’s vision for future renewable electricity production as set out in the
Energy Policy Statement (2010) and should be taken into account by decisions
makers when determining such applications.’
12.8.13 ‘The most appropriate scale at which to identify areas for large scale
onshore wind energy development is at an all-Wales level. Technical Advice Note
S36 Application Draft v (vi) 51 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
8: Planning for Renewable Energy (2005) identifies areas in Wales which, on the
basis of substantial empirical research, are considered to be the most appropriate
locations for large scale windfarm development; these areas are referred to as
Strategic Search Areas (SSAs). The detailed characteristics of SSAs and the
methodology used to define them are outlined in TAN 8 and its Annexes.
Development of a limited number of large-scale(over 25MW) wind energy
developments in these areas will be required to contribute significantly to the
Welsh Government’s onshore wind energy aspiration for 2GW in total capacity
by 2015/17 (see Figure 12.1); UK and European renewable energy targets; to
mitigate climate change and deliver energy security.’
Letter from the Deputy Director, Energy, Water and Flood for the Welsh Government
dated 21st January 2013.
3.44 This letter (to the conjoined Inquiries) states inter alia:
‘The Welsh Government remains committed to the planning policies contained in
PPW and TAN8. In July 2011 the Minister for Environment and Sustainable
Development wrote to all Local Authorities to clarify the issue of maximum
installation capacity within the SSAs identified in TAN8. The Minister’s circular
set out the identified maximum capacities for each of the SSAs as identified by the
independent consultants, Garrad Hassan.’
3.45 Two of the applications being considered by the Mid Wales Inquiry namely –
Llanbrynmair and Carnedd Wen - fall within SSA B.
S36 Application Draft v (vi) 52 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.46 As the Welsh Government makes expressly clear in its letter:
‘of the remaining three applications being considered by the Inquiry, Llandinam (as
referred to in the correspondence 23rd January 2013 - 126MW) falls just outside SSA
C. The Llandinam application is a repowering of an existing development. The Welsh
Government’s continuing policy in relation to the repowering of existing
developments which fall outside SSAs is that they should be encouraged provided
that the environmental and landscape impacts are acceptable (Section 2.14 TAN8
July 2005).’
Local Planning Policies
Powys Unitary Development Plan
3.47 In March 2010 Powys County Council adopted the UDP 2001-2016 The UDP
contains a number of policies which ‘touch upon’ the planning issues raised by this
proposal. The dominant policy is Policy E3 Wind Power which is a criteria based
policy conveying approval for windfarm development where a development will not
unacceptably adversely affect:-
- Environmental and landscape quality – either on an individual basis or
cumulatively
- Wildlife habitats
- Occupants / users of sensitive properties
- Buildings or features of conservation of archaeological interest
S36 Application Draft v (vi) 53 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
- Enjoyment and safe use of highways and public rights of way.
Applicants are required to demonstrate that proposed developments can be served by
an acceptable means of access; adequate mitigation for adverse impacts is provided
for, and that ancillary structures are so sited and designed to blend into their setting.
3.48 The UDP states (para 12.9.1)
‘A careful balance needs to be struck between the pressing need to combat
climate change and the need to protect a valued and attractive landscape.’
3.49 The Council believes that a criteria based policy does not, on its own, represent a
particularly good basis for future decision making and intends to discuss with the
Welsh Government and the others the obtaining of more detailed information in an
endeavour to reach views as to the ‘most appropriate (and conversely the most
inappropriate) locations and the terms under which such developments would be
acceptable.’ (para 12.9.1.)
3.50 Policy E4 refers to an advantage that wind power developments hold over most of the
other electricity generation technologies – namely the ease with which turbines and
towers may be removed and the land reinstated. Policy E4 refers to the imposition of a
planning condition on a grant of planning permission to remove turbines which have
ceased to generate electricity after a period of 6 months.
S36 Application Draft v (vi) 54 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
3.51 Policy E5 addresses off-site works that may be required to ‘either facilitate wind farm
development or to ameliorate some adverse effects’. The supporting text at para
12.9.5 states:
’Highway improvements are often required to provide adequate access to the site
during construction.’
Policy E5 provides the basis upon which PCC may impose planning obligations to
either facilitate windfarm development or ameliorate their impact.
3.52 The Statement of Case issued by Powys CC identifies a list of policies from the UDP
which the Council will rely upon. In the context of the Llandinam proposal I consider
that the following policies are relevant when considering the site specific issues
arising from the proposal to repower an existing windfarm:
SP1: Social, Community and Cultural Sustainability
SP3: Natural, Historic and Built Heritage
SP12B: Energy Conservation and Generation
GP1: Development Control
ENV2: Safeguarding the Landscape
ENV3: Safeguarding Biodiversity and Natural Habitats
ENV4: Internationally Important Sites
ENV6: Sites of Regional or Local Importance
ENV7: Protected Species
S36 Application Draft v (vi) 55 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
RL6: Rights of Way and Access to the Countryside
DC9: Protection of Water Resources
DC12: Overhead Lines and Pipelines
DC13: Surface Water Drainage
Conclusions
3.53 Conclusions to be drawn from the relevant planning policy.
(i) That there is an urgent need for new nationally significant infrastructure
projects to be brought forward as soon as possible (NPS EN-1; UK renewables
Energy Road Map Updated 2012) in the interests of:
- Meeting energy security and carbon reduction objectives
- The need to replace closing electricity generating capacity
- The need for more electricity capacity to support an increased supply
from renewables.
(ii) That the weight which is attributed to considerations of need in any given case
should be proportionate to the anticipated extent of a projects actual
contribution to satisfying the need for a particular type of infrastructure (NPS
EN-1).
(iii)That on-shore windfarm development is regarded as being the most
established large-scale source of renewable energy in the UK.
S36 Application Draft v (vi) 56 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
(iv)That Wales has an abundant wind resource, and power generation using this
resource remains the most commercially viable form of renewable energy.
(v) That the UK Government acknowledges it will not be possible to develop the
necessary amounts of large-scale infrastructure without ‘some significant
residual adverse impacts’ (NPS EN-1 para 3.2.3).
(vi)That the Welsh Government maintains the most appropriate scale at which to
identify large-scale onshore wind energy development is at an all-Wales level
(TAN8).
(vii) That the Welsh Government does not support the – new as opposed to re-
powering - generating capacity within SSA C beyond the maximum of
98MW identified by Garrad Hassan (23/1/13 correspondence to the Inquiry).
(viii)That the Welsh Government’s policy in relation to the repowering of existing
wind farm developments is that they should be encouraged provided the
environmental and landscape impacts are acceptable (21/1/13
correspondence to the Inquiry). (TAN8 para 2.14).
It is in the context of these principles that I consider the merits of the proposal.
S36 Application Draft v (vi) 57 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.0 THE PLANNING CONSIDERATIONS
Introduction
4.1 At the outset of this section of my proof of evidence it is appropriate to set out a basic
principle for this Inquiry regarding on shore wind development, lest it be advanced to
the contrary by third parties within written evidence or oral submissions. The
Government’s policy support for onshore windfarm development, as a contribution
towards the generation of energy from renewable sources is not open to review
through this procedure. Rather the issue for determination is the land use planning
consequences of the windfarm proposals considered on an individual and cumulative
basis.
TAN8 issues
(i) Capacity of SSAs
4.2 In May 2004 the Welsh Government set a target of 4TWh/annum to be produced by
renewable energy by 2010, part of the wider UK national target of generating 10% of
electricity consumption from renewable sources by 2010. In the light of the need for
new renewable energy installations, the Welsh Government Planning Division
commissioned work at a strategic level (from ARUP) to determine the potential for
wind energy development in Wales.
S36 Application Draft v (vi) 58 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.3 The brief given to ARUP was to provide a map for Wales identifying ‘strategic search
areas’ capable of delivering the Welsh Government’s Renewable Energy target of
4TWh by 2010. The ‘fundamental objective was to ascertain the most appropriate
areas of Wales in which to locate 800MW of onshore wind turbines minimizing direct
land take.’ (ARUP Review of Final Reports June 2005)
4.4 ARUP produced a ‘decision support tool’ which was essentially a collation of relevant
information to date, techniques and research in order to document and clarify relevant
issues relating to wind farm development in Wales. The work culminated in the
identification of seven separate areas considered capable of accommodating large-
scale (> 25MW) wind farms. The seven areas were identified as Strategic Search
Areas and subject to wide consultation.
4.5 The Welsh Development Agency subsequently commissioned Garrad Hassan and
Partners (GH) to carry out a more detailed technical feasibility study of the generating
potential of the seven SSAs. GH state in their report ‘Energy Assessment of TAN8
Wind Energy Strategic Search Areas’:
‘The work does not seek to pre-empt detailed on the ground strategies that would
typically be undertaken by wind farm developers when assessing the sites. Rather,
it provides an informed view of the broad capacity limits of the areas (emphasis
added) and the headline, common factors which are likely to influence these
limits.’ (para 1.1)
S36 Application Draft v (vi) 59 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
GH further state:
‘The terms of reference did not include any input by GH into the definition of the
SSA areas, or any assessment of planning matters such as landscape capacity.’
(emphasis added)
4.6 The methodology of the study involved establishing an initial Base Case layout to
determine a ‘reference case for feasible maximum capacity of each SSA’ (para 2.1). A
range of constraints were identified under the following headings namely:
• Practical / Technical
• Military / Aviation
• Environmental
(attached as APPENDIX 3)
4.7 The majority of the constraints had been considered in the original identification of
the SSAs and hence did not materially impact upon the land available within the
SSAs. The main material difference was the identification of buffers (700m radius)
for dispersed dwellings which was omitted from the ARUP study. GH stated ‘It
[buffer to a dispersed dwelling] forms the main locational driver for turbine
placement within each SSA’.
4.8 The turbine assumption was a ‘typical 2MW wind turbine with an 80m hub height and
80m rotor diameter’ – as a ‘typical onshore turbine specification for use in relatively
complex terrain, up to the year 2010.’ (emphasis added) (para 2.12)
S36 Application Draft v (vi) 60 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.9 GH thereafter sought to define a Noise Constraint Case and stated:
‘… it is not possible to undertake a definitive assessment of noise until detailed
background noise measurements have been made at nearby residences. Such an
approach is clearly outside the scope of this study. GH have therefore made the
assumption that a wind farm development is likely to meet the relevant planning
guidance provided predicted noise levels at dwellings are less than 40dB(A) at a
reference wind speed of 8m/s at 10m height. (emphasis added) The noise
calculations were based on a noise source power of 105dB(A) for the ‘normal’
turbine and 101dB(A) for the ‘quieter’ turbine at this condition with an
assumption of no tones.’
4.10 For SSA C GH reached the following analysis:
No of turbines Rated Capacity (MW)
Base Case 74 148
Base Case + Noise 49 98
The Base Case + Noise capacity for all the SSAs was established as being:
Area A 212
Area B 430
Area C 98
Area D 212
Area E 152
Area F 430
Area G 132
S36 Application Draft v (vi) 61 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.11 These figures total 1666 MW and form the basis of the reference to 1700MW in the
Minister’s letter of July 2011. The Minister’s letter refers to this capacity as being the
‘maximum’, whereas the purpose of the GH report was to provide an ‘informed view
of the broad capacity limits of the areas’ (emphasis added). The initial technical
capacity was identified as being 2104MW (sec 4.1) which is the summation of the
Base Case capacities).
4.12 ARUP concluded in the report to the Welsh Government (Facilitating Planning for
Renewable Energy in Wales: Meeting the Targets Final Review June 2005):
• ‘The decision to develop SSAs, and the method used to identify them remains
valid.
• Excluding landscape and visual issues (to a degree) in the initial identification of
the SSAs was the correct approach.
• The boundaries of the current SSAs should remain largely unchanged, but
assessment suggests modifications, as indicated, to better reflect the areas of
potentially developable resource.
• There are no new SSAs required, and that none of the SSAs require removal.
Having taken all the renewed factors and suggested boundary modification into account
it is predicted that:
• the SSAs remain capable of delivering the government target (800MW) for
renewable energy in Wales; and
• the largest capacity for allocation in LPA plans will fall somewhere between the
government target (800MW) and the maximum capacity identified in the Garrad
Hassan study (1666MW) – to take account of site specific factors limiting
availability and LPA consideration of landscape and visibility matters.
S36 Application Draft v (vi) 62 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.13 In issuing the renewable Energy Route Map for Wales, the Welsh Government set out
its approach to ‘overcoming barriers/ timescales and targets; stating at paras 7.16-7.17
7.16 We will:
• review TAN 8, revising upwards the old targets for renewables- drawn from a
range of sources- following the publication of the Welsh Government’s energy
strategy later in 2008.
• support UK work on a strategic environmental assessment (SEA) for offshore
wind generation in English and Welsh territorial waters.
7.17 If all potential projects were to go ahead in full, wind-farms within the TAN 8
strategic search areas could produce up to 2500MW of capacity: three times the
existing TAN 8 indicative target for 2010. This could create almost 7TWhr per
annum from onshore wind by 2015 – almost a third of Wales’ current electricity
demand. Major new offshore wind projects could add at least another 3 TWhr
annually.
4.14 It appears from the Ministerial Statement June 2011 and the Minister’s letter to the
LPAs (July 2011) that the concern regarding ‘overcapacity’ is directed at the
environmental consequences from grid connections. The Minister stated (June 2011):
‘It is this overcapacity which has led to proposals for major new overhead grid
infrastructure. We contend that the level of capacity within the SSAs which we set
out in 2005 would negate the need for the large obtrusive pylons which are
causing such concern.’
S36 Application Draft v (vi) 63 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.15 It remains the view of the Welsh Government that connection from the individual
turbines to a substation should be via underground cables, and that ‘any connection
from a substation to the nearest point of distribution network’ should be ‘achieved by
a standard 3 wire system on wooden poles or by undergrounded lines.’ I refer to the
grid connection which is subject to a Section 37 application later in this evidence.
4.16 In a recent decision for a Consent Order under the Planning Act 2008 (S31 –
Nationally Significant Infrastructure Project) at Brechfa Forest (BFWWF),
Camarthenshire, the Examining Authority (ExA) considered the ‘TAN8 Capacity
Limits’. He stated at paragraphs 4.169 – 4.172:
‘TAN8 identified Brechfa Forest as an area deemed suitable for large-scale wind
farms. TAN8 also identified indicative capacity targets for each SSA, with these
intended to assist the planning process and not to be seen as the definitive
capacity for the area. In July 2011 the WG’s Minister for Environment and
Sustainable Development wrote to local authorities in Wales. This identified the
maximum capacity of Brechfa Forest as 132MW (REP260 LA, appendix 13).
The maximum capacity of the Alltwalis wind farm is 23 MW and the maximum
proposed capacity of BFWWF is 84MW. The maximum capacity of the proposed
Bryn Llewelyn Wind Farm is 48MW and that at Brechfa Forest East 36MW
(REP260 LA, appendix 4.2). If all proposed wind farms were constructed to their
maximum capacity, then the capacity limits proposed by the WG would be
exceeded.
The key issues relevant to my consideration are:
• There can be no guarantee that the proposed wind farms will be
consented and built.
S36 Application Draft v (vi) 64 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
• In the case of BFWWF there is a thorough environmental assessment (the
ES) which considers the impact of the proposal for BFWWF, and includes
consideration of other actual and potential wind farms.
• While TAN8 is a relevant material consideration the main policy
considerations are the national policy statements (NPS EN-1 and NPS
EN-3) which identify the need for additional capacity.
I conclude that TAN8, as modified by the WG in 2011, does not provide grounds for
rejecting the proposal for BFWWF.’
4.17 The Secretary of State in issuing the Consent Order stated at para 23:
‘There were concerns that the generating capacity of the Brechfa project when
taken with the built Alltwalis wind farm (23MW) and the proposed Bryn Llewelyn
(48MW) and Brechfa Forest East (36MW) wind farms would breach the
maximum wind farm generating capacity limits for the Strategic Search Area
(SSA) within which the wind farms are sited (or would be sited if consented) as
identified by the Welsh Government (see paragraphs 4.169 – 4.172 of the ER).
The nominal capacity of the SSA in question is 132MW and that total would be
breached if the Brechfa project and the other unconsented projects were to be
built. The ExA notes, however, that there is no guarantee that the Bryn Llewelyn
and Brechfa Forest East projects will be built and that the Applicant for the
proposed Development has provided a thorough assessment of impacts arising
from the project including consideration of the other similar schemes. The
Secretary of State, therefore, agrees with the ExA’s conclusions that TAN8, as
modified by the Welsh Government in 2011, does not provide grounds for
rejecting the proposal for Brechfa Forest West (ER 4.172).’
(ii) Repowering of an existing windfarm
S36 Application Draft v (vi) 65 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.18 As stated earlier when examining relevant planning policy, neither the existing
Llandinam windfarm nor the proposed repowering lies within the boundary of SSA-C
as drawn on Map 4 in TAN8. Para 2.14 of TAN8, and as recognised by the Welsh
Government in the correspondence dated 21st January 2013, encourages repowering in
areas outside the SSAs provided that the environmental and landscape impacts are
acceptable. These impacts are addressed in the ES, 2011 SEI and 2013 SEI. The
impacts arising from the proposed grid connection at Welshpool are addressed in the
submissions made by SPManweb.
4.19 Providing that the environmental and landscape impacts are acceptable the
repowering of Llandinam should be encouraged as a matter of principle through the
provision of TAN8. The repowering of an existing windfarm should be considered in
the context of the current physical and environmental context of the site (existence of
wind turbines in the landscape; existence of tracks and other infrastructure associated
with the windfarm).
4.20 It is clearly to be accepted that the repowering of an existing windfarm may give rise
to different environmental impacts from those of the existing situation particularly as
the change in windfarm technology has led to taller wind turbines, larger rotor blades,
bigger capacity turbine generators and slower rotation of blades. Repowering
generally, as is the case at Llandinam, involves the replacement of the existing array
with a smaller number of larger turbines.
S36 Application Draft v (vi) 66 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.21 The consideration as to whether the environmental and landscape impacts are
‘acceptable’ does not require the impacts of the proposal to be maintained as they
currently exist. Rather it has to be acknowledged that modern turbines fewer in
number will necessarily have a different impact upon landscape character and visual
amenity than the existing array. Similarly the proposal may give rise to different
effects on the level of amenity enjoyed by occupiers of nearby sensitive properties.
During the periods of construction and decommissioning there will be different
environmental effects arising from the transportation of plant, machinery and
component parts of the turbines.
4.22 A planning judgement has to be formed as to the degree or extent, to which this
proposal would give rise to adverse impacts, and whether in the subsequent planning
balance, weighing the benefits from allowing the development to proceed; these
impacts would be acceptable or unacceptable in the overall public interest.
4.23 In the context of a repowering scheme it is a material consideration to have regard to
the impacts arising from the existing array, as a genuine ‘planning fall back’. While
repowering is desirable in order to introduce more efficient wind turbines. The
existing array has a generating output of 31MW. The subsisting planning consent
contains no planning condition that determines the life of the consent or requires
decommissioning. The balance of probability is that in the event planning permission
is refused for the repowering, the existing array would be maintained. Works to the
existing array would be able to be undertaken as a maintenance operation, and hence
S36 Application Draft v (vi) 67 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
the renewal of component parts would not necessarily require a new grant of planning
permission.
(iii) The geographical extent of SSAs
4.24 The underlying purpose in the identification of Strategic Search Areas is to focus new
large-scale windfarm development – as opposed to re-powering schemes - to areas of
Wales considered most suitable for large-scale windfarm development (Renewable
Energy Route Map for Wales para 7.4) and avoid a proliferation of large-scale
windfarms across the whole of TAN8. The SSA boundaries were drawn at a ‘broad
brush’ scale, and it was acknowledged that not all the land within the SSAs ‘may be
technically, economically and/or environmentally suitable for major wind power
proposals.’ TAN8 acknowledged that it would be a matter for LPAs to undertake local
refinement within each of the SSAs ‘in order to guide and optimise development
within each of the areas’ (TAN8 para 2.4).
4.25 Powys CC undertook such an exercise engaging the same consultants, ARUP, who
had identified the SSAs boundaries within the TAN8. The refinement exercise
followed the guidance set out at Annex D of TAN8 and resulted in a significant
redrawing of the ‘western half’ of the TAN8 SSA C boundary to the west. (Refer Map
2 IDCG)
S36 Application Draft v (vi) 68 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.26 The study did not seek to identify the indicative capacity target of the refined SSAs
(to compare against Table 1 TAN8). The study stated (para 6.6):
‘A representative energy yield based on an average of 6.5MW/sqkm of
unconstrained land has been applied as a gauge to identifying the capacity within
each SSA.’
4.27 It is acknowledged that the IDCG has remained as a draft document and has not been
adopted by the Powys CC. The report states at para 6.6:
‘Powys County Council has now indicated that these are the preferred areas for
large windfarm proposals.’
The IDCG is referred to by Powys CC as being used for development control
purposes. Para 2.2 of the IDCG states:
‘This second draft of the IDCG was formally authorised by Powys County
Council Board on 22nd April 2008 for use in development control with immediate
effect.’
Conclusions on TAN8
4.28 I draw the following conclusions for the planning policy context of Llandinam
repowering at a strategic level for Wales.
S36 Application Draft v (vi) 69 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
1. That the repowering of the existing windfarm at Llandinam should be
encouraged provided that the environmental and landscape impacts are
acceptable, (TAN8 para 2.14) and
2. That in having regard to the IDCG for development control, the location of
Llandinam repowering lies within a refined SSA C where large-scale
windfarm development should be focussed because of the suitability when
assessed against a range of environmental and technical considerations. (IDCG
para 6.4)
3. That the Secretary of State agreed with the Examining Authority (Brechfa
Forest) that the indicative targets for TAN8 were ‘intended to assist in
planning process and not be seen as the definitive capacity for the area’. The
Secretary of State referred to TAN8 capacity limits as ‘the nominal capacity’.
4. That TAN8 as modified by the Welsh Government in July 2011 does not
provide grounds for rejecting Llandinam as a matter of principle, if Llandinam
is regarded as being within SSA C as a result of the refinement assessment by
PCC (Refer Appendix 1 para 5 SOCG).
5. That the intention of the Welsh Government as set out in Renewable Energy
Route Map for Wales is ‘to review TAN8 revising upwards old targets for
renewables.’ (para 7.16)
6. That while TAN8 is a relevant material consideration, the main policy
considerations are the National Policy Statements which identify the need for
additional capacity. The overarching NPS (EN-1) states that the NPS provides
the ‘primary basis for decisions’. (para 1.1.1)
S36 Application Draft v (vi) 70 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
The environmental and landscape impacts of the repowering of Llandinam
4.29 I propose to consider the environmental and landscape impacts firstly in response to
the matters raised by the PCC. I have acknowledged where such concerns are raised
by other objectors, such as the Countryside Council for Wales (now known as Natural
Resources Wales (NRW)) and the Alliance.
Impacts of the Transportation Route
4.30 I rely upon the expert evidence of Mr David Tucker, DTA. The 2013 SEI sets out a
review of the Strategic Traffic Management Plan (STMP), and refers to the
preparation of a detailed Draft Traffic Management Plan (TMP) for the Revised
Southern Transport Route, which is relied upon to serve Llandinam (replacing the
Draft TMP presented with the 2011 SEI).
4.31 The assessment of the impacts arising from traffic associated with the construction
and decommissioning of the existing windfarm was undertaken in the original ES and
2011 SEI in the context of criteria including community severance, driver delay,
pedestrian amenity accidents / safety considerations, traffic noise and vibration. Given
the temporary nature of these operations and the absence of a requirement for major
works to the highway infrastructure, many of these issues were assessed under the
relevant guidance as not causing a significant effect. The assessment has therefore
focussed on the potential impacts to the road network associated with the construction
phase traffic including the impact of abnormal indivisible loads (AIL) convoys.
S36 Application Draft v (vi) 71 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.32 Llandinam is being progressed on the basis of the Revised Southern Transport Route
for abnormal load deliveries. With the implementation of a range of measures
described at Section 9.6.5 of the 2013 SEI, the judgement is reached that delays
incurred by other road users in the route will not exceed 10 minutes, with no more
than one convoy (comprising a maximum of three abnormal loads) a day. The
conclusion [2013 SEI] reached is that the residual effects are negligible. In a land use
planning judgement I conclude that the proposals have satisfactorily taken into
account ‘the effects of the safety and convenience of other road users of the transport
network’ (PPW para 8.7.1) during the construction phase.
Impacts on Landscape and Visual Amenity
4.33 This objection is supported by NRW and the Alliance. I rely upon the expert evidence
of Mr James Welch, Optimised Environments Ltd. The 2013 SEI analyses the
landscape and visual impact arising from the amended scheme for 34 turbines,
including cumulative impacts, upon a wide range of landscape and visual receptors
surrounding the site, including the Caersws Basin.
4.34 The 2013 SEI explains that the removal of 5 turbines to the north and northwest
extent of the proposed windfarm layout has been undertaken in response to
stakeholder concerns with regard to landscape and visual effects on the Caersws Basin
and associated sites such as Plas Dinam House and Garden. The removal of the 5
turbines reduces the predicted effects on landscape character and visual amenity from
S36 Application Draft v (vi) 72 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Viewpoints 1, 20, 26 and 27 as these turbines were the most prominent turbines on the
northern end of the Waun Ddubarthog ridgeline. From other viewpoints the removal
of the 5 turbines has much less of a pronounced effect on the appearance of the
development (2013 SEI para 6.7.3.2).
4.35 The 2013 SEI concludes that the removal of the 5 turbines would result in:
a) the removal of significant landscape effects at 4 viewpoint positions
(viewpoints 1, 20, 26 and 27)
b) the removal of significant effects on visual amenity at 3 viewpoint positions
(viewpoints 1, 20 and 27)
c) a general reduction in the prominence of visible turbines across the Caersws
Basin; and
d) reduced cumulative effects to the east when application stage windfarms are
considered.
4.36 The 2013 SEI refers to ‘significant landscape and visual effects’ occurring at 14 of the
27 viewpoints.
4.37 No significant landscape or visual effects are predicted upon the Snowdonia National
Park or the Shropshire Hills AONB due to the development. However there will be
significant effects upon the access land spanning the development site itself as well as
that on the north face of Garreg Lwyd, 5 km northwest of Rhayader.
4.38 NPS-EN3 acknowledges (paras 2.7.48 – 2.7.49) that:
S36 Application Draft v (vi) 73 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
‘Modern onshore wind turbines that are used in commercial windfarms are large
structures and there will always be significant landscape and visual effects from
their construction and operation for a number of kilometres around a site.
The arrangement of wind turbines should be carefully designed within a site to
minimise effects on the landscape and visual amenity while meeting technical and
operational siting requirements and other constraints.’
4.39 I conclude that on the basis of the assessment within the 2013 SEI, the Applicant has
minimised the landscape and visual effects of the windfarm. The omission from the
proposal of 8 turbines (3 – 2011 SEI; 5 – 2013 SEI) has reduced the maximum
generating capacity from 126MW as originally proposed to 102MW as currently
proposed, a 19% reduction in capacity from the original proposal.
4.40 NRW asserts an additional landscape and visual impact due to the dedicated 132 kv
grid connection to Welshpool substation. The overhead line design as described in the
Planning Officer’s report (25th October 2012) refers to the installation of
approximately 35km of 132kv single current overhead lines supported in
approximately 394 new timber pole supports. The minimum ground clearance is
6.7m. Span lengths vary from 53m to 110m with an average span of 85m between
supports. Pole heights vary from 11.5m to 15m.
4.41 In Annex C of TAN8 ‘Description of Renewable Energy Technologies’, reference is
made to grid connections being ‘achieved either by a standard 3 wire system on
wooden poles (as proposed by SP Manweb plc.) or by underground lines’. This form
S36 Application Draft v (vi) 74 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
of installation is referred to by The First Minister in his letter to LPA’s of July 2011.
He stated:-
’TAN8 details that any connection from a substation to the nearest point of
distribution network would be ‘achieved by a standard 3 wire system on wooden
poles or by underground lines’. This remains the Welsh Government’s view and
is reinforced by the approach set out within the Renewable Energy Route Map
for Wales in 2008, and the Energy Policy Statement in 2010.’
4.42 The 132 kv overhead line is required to connect the repowered Llandinam windfarm
to the existing Welshpool substation. The infrastructure does not require large visually
intrusive, high voltage grid network infrastructure. The environmental impacts of the
proposed overhead lines are addressed by SP Manweb and referred to at Section
6.6.5.1 of the 2013 SEI. The NTS to the Addendum to the Llandinam Grid
Connection Environmental Statement acknowledges that there would be some
‘significant residual effects remaining’, including ‘visual effects on the visual amenity
of some residents near Forden, users of some short sections of public footpaths and
roads in both areas and users of the public forest near Bryn Pica.’ In the context of the
overhead line extending over 35km, some significant residual effects are probably
inevitable. The physical form of the overhead line comprising wooden poles has
sought to minimise its effects on the surrounding landscape and visual amenity.
Impacts upon Biodiversity
S36 Application Draft v (vi) 75 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.43 This objection is also raised by NRW and the Alliance. I rely upon the evidence of
David McArthur, Phil Whitfield and Stephen Holloway in respect of the assessment
of the impacts on biodiversity particularly on curlew and bats and the River Wye SAC
and have considered the 2013 SEI.
4.44 The 2013 SEI has specifically considered the position taken against the proposal by
NRW which refers to a lack of mitigation to offset potential adverse displacement
effects on breeding curlew. Appendix 7.2 to the 2013 SEI comprises a Breeding Birds
Protection Plan.
4.45 Natural Research conclude (2013 SEI para 7.6.5):
‘Embedded mitigation, through the BBPP will ensure that breeding curlew will
not be adversely affected by the Development through disturbance creating
potential adverse displacement effects during decommissioning of existing
turbines, construction of the proposed turbines and decommissioning of the
proposed turbines. It is arguable as to whether any displacement of curlew will
occur during these phases on available evidence; nevertheless the embedded
mitigation of the BBPP will prevent even the worst case possibility of
displacement occurring.’
4.46 In respect of the impact of the windfarm on bats the 2013 SEI concludes (para
3.6.8(2)):
‘… the repowering and extension of the Development, utilizing larger but fewer turbines
would not have a significant effect on the sustainment of local bat populations. As such
the conclusions of the original ES, that any residual impact would be minor, stand.’
S36 Application Draft v (vi) 76 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.47 The design changes to the proposed windfarm are considered to result in a lesser
impact than the original scheme. I conclude that there is no serious harm to interests
of significant biodiversity value.
Impacts on hydrology, hydrogeology and peat resource
4.48 This issue has been further addressed in the SEI submitted April 2013.
4.49 The removal of approximately 1.8km of track (including turning areas) and 5 turbines
and hardstanding is a positive effect since the 2011 SEI amendment to the scheme,
reducing the overall magnitude of impact upon geological, hydrological and
hydrogeological considerations. The 2013 SEI describes the residual effects and
conclusions of the design changes. The significance of the impact of the wind farm on
the geology, hydrology and hydrogeology of the site and associated water dependant
habitats and designations would be negligible to minor.
4.50 I conclude from the specialist assessment that there is no serious land use objection
based upon the impact of the proposed wind farm, on the geology, hydrology and
hydrogeology of the site. The 2013 SEI addresses the potential impact of the
development on the River Wye SAC on an individual basis for Llandinam
repowering, and on a cumulative basis with other wind farms. The assessment
concludes that this is the case even in the absence of mitigation measures. The 2013
SEI concludes that with good practice construction methods and the proposed
S36 Application Draft v (vi) 77 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
drainage practice, the risk of any sediment transport to the River Wye SAC would be
reduced to negligible. I conclude that the concerns raised as to the impact on the SAC
are unfounded with robust evidence.
Impact arising from noise emissions
4.51 I rely upon the expert evidence of Dr Matthew Cand, Hoare Lea Consulting. The SEI
submitted in April 2013 addressed the noise impact arising from the amended scheme.
4.52 The decommissioning and construction noise assessment has determined that noise
emissions during these activities may be audible at various times throughout these
operations, but will remain within set limits. The operational noise assessment also
demonstrated that the noise limits would be met at all of the neighbouring residential
properties identified.
4.53 The cumulative effect of noise emissions from other existing consented or proposed
wind farms in the area has been considered along with Llandinam repowering. The
assessment has shown that the derived operational limits would be met at nearby
dwellings.
4.54 I conclude from the specialist evidence that Llandinam repowering, considered
individually or on a cumulative basis, would not give rise to serious levels of noise
disturbance during the decommissioning / construction phases, or when operational.
S36 Application Draft v (vi) 78 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Impact upon cultural heritage assets
4.55 I rely upon the assessment undertaken in the SEI submitted in April 2013.
4.56 The 2011 SEI responded to comments made to the original ES with the removal of
three turbines in the north-west of the site to reduce the potential impact upon the
Caersws Basin Historical Landscape. The 2013 SEI has reduced this impact further,
through the removal of a further five turbines. The consultants conclude that
following the implementation of the mitigation measures outlined in the ES and 2011
and 2013 SEIs, no significant effects are predicted on any cultural, heritage or
archaeological sites associated with the development.
4.57 I conclude that the significance of the historic environment is preserved by this
proposal (CCW para 6.1.1). I consider that the development secures ‘the conservation
of the historic environment while ensuring that it accommodates and remains
responsive to present day needs.’ (CCW para 6.1.2)
Other concerns raised by the Alliance
4.58 In the Alliance statement dated 24th February 2013, reference is made to the calling of
evidence on the following topics, which hitherto have not been referred to in this
proof of evidence, namely:
(i) Community consultation
S36 Application Draft v (vi) 79 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
(ii) Tourism and local economy
(iii)Community costs and benefits
(iv)Health and well-being
(v) Community effects in the Uplands
(vi)Community effects in the Lowlands
4.59 Presently I remain unclear as to the basis of the case to be advanced by the Alliance
under each of these topics in respect of the Llandinam proposal. As such I respond
within this proof of evidence to the planning position as I see it.
Community Consultation
4.60 The ES refers at Section 2.5 to Scoping and Consultation. Table 2.1 identifies a list of
statutory and non-statutory consultees notified of the proposals. Public consultation
was undertaken during December 2007 over 3 days. Over 100 people attended the
first round of public consultation.
It seems to me that over the past 5 years, the public has had ample opportunity to
ventilate opinions on the merits or otherwise of this proposal. As such I cannot
identify any deficiency in community consultation, the deficiencies of which might
form a basis for refusal of this application. A second round of consultation occurred
following the submission of the planning application.
Tourism and the Local Economy
S36 Application Draft v (vi) 80 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.61 The Planning Officer’s report to the Committee 25th September 2012 makes reference
to concerns raised as to the impact of the proposed development on tourism. The
Planning Officer refers to the 2011 SEI and rebuttal information provided by the
Applicant.
4.62 Various studies have been undertaken to assess the economic impact of windfarms on
tourism, including:
• Investigation into the potential impact of windfarms on tourism in Wales –
October 2003
• The economic impacts of windfarms on Scottish tourism – March 2008
• The impact of wind turbines on tourism – a literature review for Isle of
Anglesey County Council – February 2012
• Tourism impact of windfarms submitted to Renewables Inquiry Scottish
Government – April 2012
4.63 The conclusions of Professor Cara Aitchinson in her report to the Renewables Inquiry
provide an appropriate summary of the findings of the research that has been
undertaken to date namely:
3.1 ‘Although tourism research relating to windfarm developments is limited
compared with that on policy, landscape, ecology and noise it is increasingly
evident that there is an emerging consensus within the research examining the
actual and potential impact of windfarms on tourism. The clear consensus is that
S36 Application Draft v (vi) 81 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
there has been no measurable economic impact, either positively or negatively, of
windfarms on tourism. Similarly, there is consensus among researchers of studies
that have sought to predict the more specific potential economic impact of
windfarms on tourism. Here again, there is no evidence to support the assertion
that windfarms are likely to have a negative economic impact on tourism.’
3.2 ‘The opposition to windfarms on tourism grounds is informed more by fear
than fact. The research conducted by GCU stated that ‘Importantly, respondents
that had seen a windfarm were less hostile than those who had not’ (Glasgow
Caledonian University, 2008: 3). Starling’s and Glasgow Caledonian
University’s findings therefore lend support to Young’s (2003) research; namely,
that opposition to windfarms tends to fall after construction.’
3.6 ‘Taking the above factors into account in a critical review of previous
research, and contextualising such research in relation to both the tourism
geography of Scotland and wider Visit Scotland tourism policy, it can be
concluded that:
• A managed and sustainable approach to windfarm development in
Scotland is likely to have little or no impact on tourist numbers (volume),
expenditure (value) or experience (satisfaction)
• Any impact is as likely to result in more tourist visitors as it is fewer
tourists
• Although a very small number of current visitors might choose not to
repeat their visit because of the presence of a windfarm this number is
likely to be off-set by additional tourists who visit irrespective of the
presence of a windfarm, return because of the windfarm or visit for the
first time because of the windfarm
• Tourist numbers are likely to increase significantly if the windfarm is
accompanied by a visitor attraction.’
3.8 ‘In conclusion, the findings from both primary and secondary research
relating to the actual and potential tourism impact of windfarms indicate that
there will be neither an overall decline in the number of tourists visiting an area
S36 Application Draft v (vi) 82 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
nor any overall financial loss in tourism-related earnings as a result of a
windfarm development.’
4.64 In April 2013 YouGov Plc were commissioned by Renewable UK Cymru to
undertake an on-line survey to establish public attitudes towards large scale energy
projects. The survey results suggest that almost two-thirds of people in Wales support
the development of wind power as part of a mix of renewable and conventional
energy production. Two-thirds of people who responded to the survey indicated that
the presence of a wind farm would not affect their decision to visit an area. The
datasheet from the survey is attached as APPENDIX 4
4.65 NPS EN-1 states at (para 5.12.7) that ‘limited weight is to be given to assertions of
socio-economic impact that are not supported by evidence (particularly in view of the
need for energy infrastructure as set out in this NPS)’. I conclude that there is no
robust evidence to substantiate an objection to the granting of consent for Llandinam
on the basis that this proposal would give rise to unacceptable effects on local
tourism. In that Llandinam is a repowering of an existing windfarm with fewer, but
taller wind turbines, the existence of wind turbines forms part of the established rural
scene for tourists. The Welsh Government refer generally to the benefits of the
renewable sector in supporting 13,000 jobs in Wales 2009/10 (Energy Wales: A Low
Carbon Transition March 2012).
Community Costs and Benefits
S36 Application Draft v (vi) 83 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.66 The UK Renewable Energy Road Map 2012 Update states ‘onshore wind provision
substantial economic benefit’. In January 2013 Regeneris Consulting and the Welsh
Economy Research Unit at Cardiff Business School published a report titled
Economic Opportunities for Wales from Future Onshore Wind Development. The
summary of Local Economic Benefits is set out at APPENDIX 5.
4.67 The findings of the research indicate that overall there are benefits to local
communities from hosting windfarms. The report concludes that:
(i) If Welsh Government ambitions for onshore wind are met, significant
economic opportunities exist for the Welsh economy.
(ii) The Report indicates that £2.3 billion GVA could be added to the Welsh
economy between 2012 and 2050 with over 2000 jobs on average per annum.
4.68 I conclude that the impact of the proposed repowering of Llandinam on the local
community is acceptable.
Health and Well-being
4.69 Presently in the absence of the Alliance setting out in a statement of case the precise
issues related to ‘health and well-being’ which are to be called in evidence, I am not
in a position to consider the substance thereof. I will consider this matter further when
the case has been particularised. In so far as I anticipate that these assertions may be
S36 Application Draft v (vi) 84 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
derived from noise levels this matter is probably addressed adequately through the
evidence of Dr Cand.
1) Community effects in the Uplands
2) Community effects in the Lowlands
4.70 For similar reasoning to the matters referred to above, I am not aware of any
substance to the case proposed to be advanced by the Alliance. I will consider this
matter further if and when the Alliance outline the substance of their planning
arguments.
S36 Application Draft v (vi) 85 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
Third Party Representations
4.71 I believe that I have read all letters received by DECC from members of the public
which set out objections to this repowering proposal. The most prevalent concern
appears to be the assertion that the proposal will harm the local economy, with its
particular reliance upon tourism. For the reasoning that I have set out above I consider
that there is no robust and cogent evidence that this development will have a harmful
effect upon the local economy or harm the attraction of Mid Wales to tourism.
4.72 Other recurring themes in the letters of representation include:
- Landscape and visual concerns
- Impacts on ecology
- Impact of noise
- Impact of traffic movement particularly during construction
- The weight to be given to TAN8
- Property devaluation
- Impact of grid connection
4.73 I have addressed most of these matters in the preceding sections of this proof of
evidence. TAN8 remains extant planning policy for the Welsh Government, and its
guidance is referred to in the recently published Planning Policy for Wales Edition 5
November 2012.
S36 Application Draft v (vi) 86 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
4.74 I consider that the contention the repowering of Llandinam, as a new development,
would in itself cause a general devaluation in property values is neither substantiated
by cogent evidence, or even if there is some general effect on values would be
regarded as amounting to a land use planning consideration. The ES has established
that the repowering of Llandinam would not have a direct impact upon the level of
amenities enjoyed by occupiers of nearby property, such as to make living in these
properties unattractive.
S36 Application Draft v (vi) 87 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
5.0 THE PLANNING BALANCE
5.1 Within the context of the national commitment to address the effects of climate
change, and the UK’s international obligations it is recognised that some people
question the deployment of onshore wind farm development as a matter of principle.
A large modern wind turbine has a ‘Marmite’ characteristic; to some the scale and
physical form is iconic, to others, wind turbines are regarded as being alien
monstrosities in the open countryside.
5.2 The submission of an application for wind farm development under Section 36 of the
Electricity Act, or indeed under Section 78 of the Town and Country Planning Act
1990, is not a forum for challenging established Government policy. Onshore wind
farm development forms a significant part of the ‘mix’ of renewable energy
infrastructure which Parliament and the Welsh Government relies upon to deliver the
agenda to address the adverse effects of climate change. Indeed Planning Policy
Wales issued November 2012, the most up to date statement of planning policy by the
Welsh Government, states: (para 12.8.12)
‘The potential for renewable and low carbon energy in Wales as established in
the Energy Policy Statement 2010 demonstrates that strategic scale wind energy
continues to offer the greatest potential (for activities within the control of the
planning system in Wales). Wales has an abundant wind resource and power
generation using this resource remains the most commercially viable form of
renewable energy.’
S36 Application Draft v (vi) 88 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
5.3 Some local residents question the reliance to be placed on TAN8: Planning for
Renewable Energy in the determination of this application. Nevertheless, it is quite
clear that the guidance in TAN8 remains apposite in its expression of the Welsh
Government’s policy for onshore wind farm development. The submission of this
application is not an opportunity for opponents of the proposal to seek to re-write or
redirect the advice within TAN8.
5.4 The Welsh Government accepts that the introduction of ‘new, often very large
structures for onshore wind needs careful consideration to avoid and where possible
minimise their impact.’ (PPW para 12.8.12) TAN8 has identified broad-brush areas
where large scale onshore wind developments should be concentrated (SSAs).
Indicative capacities are identified representing ‘a 1/3 reduction on the maximum
capacities identified by Garrad Hassan as reviewed by ARUP in their 2005 Report.’
(Footnote to Table 1: TAN8)
5.5 Llandinam lies outside of SSA C: Newton South as illustrated on Map 4 in TAN8.
The proposal is not for a new wind farm, in the sense of the installation of a wind
farm in an otherwise undisturbed tract of open countryside, but is the re-powering of
an existing wind farm. The Welsh Government particularly foresaw the circumstance
of ‘ageing’ established wind farms in the context of duration and evolving technology.
Para 2.14 of TAN8 states:
‘There will also be opportunities to re-power and / or extend existing wind farms
which may be located outside SSAs and these should be encouraged provided that
the environmental and landscape impacts are acceptable.’ (emphasis added)
S36 Application Draft v (vi) 89 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
5.6 The Welsh Government maintains this position, as evidenced by the correspondence
to this Inquiry dated 21st January 2013. I, of course, note the emphasis placed within
the text of the letter in the worded ‘provided’ (that the environmental landscape
impacts are acceptable). Subject to this important caveat, the principle of re-powering
and / or extending of an existing wind farm which may be located outside of a SSA is
to be ‘encouraged’ as a matter of national planning policy. I consider that subject to
this caveat, the policy encouragement for repowering as a matter of principle is a
feature that weighs in favour of the Llandinam proposal whether regarded as being
located within SSA-C or outside.
5.7 I consider that the repowering of Llandinam is to be supported in principle whether
Llandinam is to be regarded as being located outside SSA C – as it is on the ‘broad
brush’ map contained within TAN 8, or within the refined SSA C as assessed by PPC.
I have noted the statement in the Planning Officer’s Report that ‘the refinement study
has not been adopted by PCC as planning policy or as Interim Planning Control
Guidance’ (p.47). However the report refers at para 2.2 to a Board authorisation for
the IDCG ‘for use in development control with immediate effect’. This is consistent
with the reference to this document on the Council’s website. If Llandinam
repowering is reasonably to be regarded as being within a Strategic Search Area, then
the encouragement for repowering should be given added weight in its locational
advantage as one of the areas of Wales considered to be strategically most suitable to
accommodate large scale wind farm development.
S36 Application Draft v (vi) 90 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
5.8 The need for wind energy is a key part of meeting the Welsh Government’s vision for
future renewable electricity production as set out in the Energy Policy Statement 2010
(PPW para 12.8.12). The Welsh Government is committed to using the planning
system to ‘optimise renewable generation and recognises that the benefits of
renewable energy are part of the overall commitment to tackle climate change by
reducing greenhouse gas emissions as well as increasing energy security.’ (PPW
12.8.8)
5.9 The overarching National Policy Statement for Energy (NPS EN-1) refers to the UK
commitment to sourcing 15% of energy from renewable sources by 2020. Para 3.4.5
states:
‘To hit this target and to largely decarbonise the power sector by 2030, it is
necessary to bring forward new renewable electricity generating projects as soon
as possible. The need for new renewable electricity generation projects is
therefore urgent.’
5.10 A distinct and advantageous feature of the Llandinam repowering project is the fact
that the Applicant has a contractual provision for a grid connection at the existing
Welshpool 132Kv substation. The connection between a new onsite substation and
Welshpool via an overhead wood pole line is the subject of a separate application at
this Inquiry under Section 37 of the Act.
5.11 It is understood that the Llandinam repowering project could be commissioned within
a period of 25 months as identified at Table 4.1 of the ES. I believe Llandinam
S36 Application Draft v (vi) 91 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
repowering would be able to contribute to the ‘urgent need’ through the availability of
the Grid connection earlier.
5.12 It forms no part of Welsh Government policy, or the provisions of the National Policy
Statements, that the ‘urgent need’ for new renewable electricity generation projects
should necessarily outweigh all other land use planning considerations. NPS EN-1
acknowledges that a wind farm of 50MW capacity or greater will ‘inevitably have
some visual and/or noise impacts particularly if sited in rural areas.’ (para 2.7.2)
5.13 In undertaking the planning balance I have relied upon the specialist advice of other
consultants whose assessments under a range of environmental topics are addressed
within the ES and accompanying SEIs. I have not identified any ‘environmental and
landscape impacts’ arising from this proposal which should outweigh the
encouragement given to repowering projects.
5.14 I have subsequently considered the arguments that are to be presented by the Alliance,
and those that have been expressed by third parties against the granting of consent.
Planning decisions are not determined by way of a plebiscite. No matter how many
letters of objection may be submitted to a particular development project it is always
important to examine the substance of objections to form a judgement as to whether
the argument against the granting of consent is supported by cogent evidence.
Tackling climate change is a fundamental part of delivering sustainable development.
(PPW para 4.5.1) The consequences for Wales arising from the impact from climate
change for Wales are set out at PPW para 4.5.4.
S36 Application Draft v (vi) 92 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
5.15 I have considered each of the topics identified by the Alliance, and particularly the
concerns of third parties who contest that the granting of consent would harm the
local economy and damage its propensity to attract tourists. For the reasons I have set
out I conclude that the fears expressed are not supported by robust evidence which
could begin to outweigh significant planning advantages from allowing this
development in the wider public interest. I acknowledge that during the
decommissioning and construction period of some 25 months, there will inevitably be
some degree of disturbance to local people living their daily lives. I similarly
acknowledge that when operational there will be some environmental effects, and
there will be people who will never be content that planning permission has been
granted for repowering of Llandinam.
5.16 All development brings about change to the local environment in which it is situated.
The planning objective is to seek to avoid and, where possible, minimise the impact of
large-scale wind turbines. The Applicant has reasonably and properly responded
during the consultation process and has omitted 8 turbines from the original proposal
in an endeavour to reach an acceptable scheme. In my judgement the environmental
and landscape impacts which cannot be mitigated (as set out in the ES and SEIs) are
acceptable within the land use planning system.
5.17 I am hence firmly of the opinion that Llandinam Repowering is to be encouraged and
planning permission granted accordingly. It seems to me that the Llandinam proposal
accords with the relevant policy matrix. In any event, even if someone takes a
S36 Application Draft v (vi) 93 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
different view from me and asserts some material failure to accord with the prevailing
policy matrix, the other material considerations here militate decisively in favour of
consent being granted under the Section 36 application under the 1989 Act, and
planning permission being deemed to be granted under section 90(2) of the 1990 Act.
S36 Application Draft v (vi) 94 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.0 SUMMARY AND CONCLUSIONS
6.1 I have structured the summary and conclusions arising from my proof of evidence into
three parts namely:
• A summary of the legislative and planning policy considerations which are
relevant to this proposal.
(The above summary forms the Statement of Case for consideration at the
Hearing session).
• A summary of the site-specific considerations arising from the proposal to
repower Llandinam wind farm.
• The undertaking of the planning balance, reaching a conclusion on the
overall planning merits of this proposal.
Summary of the legislative and planning policy considerations which are relevant to this
proposal
6.2 The courts have indicated that, in the context of an application submitted under
Section 36 of The Electricity Act (with a parallel request for a direction under section
90(2) of the 1990 Act that planning permission be deemed to be granted), statutory
S36 Application Draft v (vi) 95 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
primacy is not given to the provisions of the development plan in that section 38(6) of
the 1990 Act is not engaged. Even were one, however, to apply the section 38(6) test,
there is no material failure here to accord with the development plan; and, further,
even were one to find some failure to accord, the other material considerations here
still result in a positive overall balance such that consent and deemed permission
should issue. The development plan is the adopted Powys UDP 2001 – 2016 which
was adopted in 2010. The UDP is a material consideration; the dominant policy is
Policy E3 – Wind Power. Policy E3 does not provide spatial planning guidance for
the location of wind farm development, but sets out a range of environmental and
technical considerations which should be addressed in order to determine whether a
particular proposal will be approved. These criteria have all been taken into account
within the ES, 2011 SEI and 2013 SEI. I will address these considerations in the
second part of my Summary.
6.3 It forms no part of this Inquiry to challenge the assumptions made and conclusion
reached by Government as to the response to climate change, or to the inclusion of
on-shore wind as a component of renewable energy technology. Similarly the
controversy as to the efficiency of wind turbines as a contributor to renewable energy
development is not a matter for this Inquiry.
6.4 The position of the UK Government may be summarised as follows:
1) Large-scale energy infrastructure development has ‘a vital role in ensuring
we have the secure energy supplies we need’ NPS EN-1 para 2.1.2.
S36 Application Draft v (vi) 96 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
2) This need arises from:
• meeting energy security and carbon reduction objectives.
• the need to replace closing electricity generating capacity.
• the need for more electricity capacity to support an increased
supply from renewables. The Government states that ‘in the short
to medium term, much of this new capacity is likely to be onshore
and offshore wind.’ (NPS-EN1 para 3.3.10)
• the urgency of the need for new electricity capacity. The
Government states:
‘In order to secure energy supplies that enable us to meet our
obligations for 2050, there is an urgent need for new (and
particularly low carbon) energy NSIPs to be brought forward as
soon as possible, and certainly in the next 10 to 15 years, given
the crucial role of electricity as the UK decarbonises its energy
sector.’ (NPS-EN1 para 3.3.15)
3) The Government acknowledges that it will not be possible to develop the
necessary amounts of such infrastructure without some significant residual
adverse impacts. (NPS EN-1 para 3.2.3.
It is stated in NPS EN-1 para 1.7.2: -
‘The development of new energy infrastructure, at the scale and speed
required to meet the current and future need, is likely to have some
negative effects on biodiversity, landscape / visual amenity and cultural
heritage… Short term construction impacts are also likely through an
increased use of raw materials and resources and negative effects on the
economy due to impacts on existing land and sea uses. In general it
S36 Application Draft v (vi) 97 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
should be possible to mitigate satisfactorily the most significant potential
negative effects of new energy infrastructure…’
6.5 As a matter of relevant planning policy it is considered that the main policy
considerations for this proposal (and others at the conjoined inquiry) are the national
policy statements NPS EN-1 and NPS EN-3. NPS EN-3 acknowledges that on-shore
wind farms are the ‘most established large scale source of renewable energy within
the UK’ and ‘will continue to play an important role in meeting renewable energy
targets’ (para 2.7.1).
6.6 NPS EN-3 has identified a range of impact assessment principles relating to on-shore
wind development including:
- Biodiversity and geological conservation
- Historic environment
- Landscape and visual
- Noise and vibration
- Shadow flicker
- Traffic and transport
6.7 The significance of the effect of the proposed repowering of Llandinam windfarm has
been addressed in the ES, 2011 SEI and 2013 SEI. The fact that the proposal may give
rise to significant effects, which have an adverse impact, is not to be equated with the
impacts being unacceptable, justifying the refusal of planning permission. It is
necessary to undertake an overall balance to establish where the advantage lies on the
overall public interest. The list of assessment effects identified in NPS EN-3 is
S36 Application Draft v (vi) 98 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
accepted as not being conclusive. Other issues, including, for example, the concern
that the development will adversely impact upon tourism, need to be accounted for in
the planning balance (addressed later).
6.8 The overall objectives of the UK Government to address the effects of climate change
are shared by the Welsh Government. The Cabinet Foreword to the Energy Policy
Statement March 2010 (EPS) states:
‘Climate change is the greatest environmental, economic and social challenge facing
the planet. Unless the global emissions of carbon dioxide and other greenhouse
gases from energy generation and other human activities peak by around 2015 and
then rapidly diminish, the world will probably see a global temperature rise of 4°C
by around 2060 resulting in famine and droughts in many parts of the world,
significant sea level rises, and an increasing risk of further catastrophic climate
changes.
Our future well-being, both material and social, will be dependent on achieving
sufficient supplies of affordable low carbon energy. This move to a low carbon
economy is an essential part of our commitment as a Government to sustainable
development. Done successfully it will strengthen our economic well-being, improve
the environment and help to address key social issues such as fuel poverty.
This statement also reflects the UK policy position, the work of the UK Climate
Change Commission and the UK National Policy Statements on Energy and
Renewables.
Wales once led the world in carbon-based energy. Our goal now is to do the same
for low carbon energy. This is a challenging but exciting and vital agenda. We are
S36 Application Draft v (vi) 99 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
committed to work with all sectors and across all aspects of the Assembly
Government’s responsibilities within a very strong sustainable development
framework in order to make it a reality.
6.9 The EPS continues:
‘Our commitment to action on climate change here in Wales is based on a
scientific imperative to act urgently to reduce emissions.
That scientific imperative remains and the absence of an international agreement
should not deflect us from being as ambitious as possible. Indeed, the importance
of demonstrating continued leadership on climate change is perhaps greater than
ever.’
6.10 The aim of the EPS is to have 4.5KWh/d/p of installed on-shore wind generation
capacity by 2015/2017. This aim requires a total capacity of 2GW (Appendix 1 to the
EPS). In October 2012 a Review of Wind Farm Developer Interest published by the
Welsh Government recorded an operational capacity of 388.3MW for wind farm
development of over 5MW. The capacity of schemes ‘in planning’ amounts to almost
2GW (in planning 1068.5MW, consented 963.8MW). The task to achieve the aim of
the Welsh Government is undoubtedly very substantial and an urgent one.
6.11 Spatial planning guidance for the location of large-scale wind farms is provided by
TAN8. The underlying purpose of the brief provided to consultants ARUP by the
Welsh Government was to identify areas of Wales which are considered the most
S36 Application Draft v (vi) 100 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
suitable to accommodate large scale wind farms in response to the Welsh
Government’s aim to achieve a renewable energy target of 4TWh per annum by 2010.
6.12 The Welsh Government announced the need to plan for between 800 – 1000 MW of
installed capacity of on-shore wind (some 400 – 600 additional turbines
approximately) by 2010 if there was to be a realistic chance of achieving the 4TWh
target. (Facilitating Planning for Renewable Energy in Wales Review of Final Report
June 2005)
6.13 It is clearly evident that the focus of the ARUP study to identify SSAs was to identify
new locations for large-scale wind farm development. As such it is entirely logical
that TAN8 makes a separate reference (para 2.14) to the potential opportunities to
repower and/or extend existing wind farms which may be located outside SSAs.
TAN8 para 2.4 states:
‘… these should be encouraged provided that the environmental and landscape
impacts are acceptable.’
6.14 NPS EN_3 similarly recognises the likelihood of applications being prepared for the
repowering of existing sites (paras 2.7.25 – 27, 28). It is stated:
‘In determining an application for the repowering of a site, the proposed
replacement scheme should be determined by the IPC on its individual merits.’
S36 Application Draft v (vi) 101 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.15 The environmental and landscape impacts arising from a repowering scheme are
likely to be different to a proposal for a new wind farm in that:-
1) a repowering project involves the installation of modern turbines, fewer but
larger, in a locality that has already accommodated wind turbine technology.
2) the existence of a wind farm will be an established component of community
life within its locality.
3) a repowering project may provide the opportunity for existing infrastructure to
be re-used. In the case of Llandinam c 10km of existing roadways are to be re-
used.
4) an existing wind farm will already have a grid connection, albeit as in the case
of Llandinam a new connection to the grid may be required to serve the
increased power rating, with consequential environmental effects in the
provision of new infrastructure.
In short it is considered that, in the context of Llandinam, there is a genuine planning
fall-back situation, the continuance of the existing wind farm, which should be
factored into the overall planning balance when considering the ‘environmental and
landscape impacts’ of the repowering proposal (particularly in the context of the
subsisting planning permission not being conditioned to a limited period).
6.16 The SSAs boundaries identified in TAN8 were drawn at a ‘broad brush’ scale (para
2.4). The existing Llandinam wind farm lies within 2km of the western boundary of
SSA-C as may be interpreted from Map 4 (TAN8). TAN8 states that it is a matter for
LPAs to undertake local refinement within each of the SSAs in order ‘to guide and
optimize development with each of the SSAs’ (para 2.4).
S36 Application Draft v (vi) 102 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.17 Powys CC engaged upon such an exercise in 2006 and commissioned ARUP (the
same consultants for the identification of SSAs in TAN8) to undertake a ‘local
assessment / refinement exercise’ of SSA-B and C within a 5km band of the SSAs
identified in TAN8. The refinement exercise had regard to the following factors:
• Landscape factors (this was a primary consideration in the study);
• Proximity to and impact upon residential buildings;
• Statutory and non-statutory designation within the SSA;
• Biodiversity impact;
• Potential highways constraints and access issues;
• Wind speed;
• Land ownership and constraints;
• Topography;
• Archaeology;
• Hydrology
• Connection to the electricity grid.
6.18 The results of the refinement exercise show a redrawing of the western boundary of
SSA-C which now entirely includes the amended scheme for Llandinam. (IDCG Map
2) The relationship of the Llandinam application site; the existing array; the amended
proposals for 34 turbines, and the boundary of SSA C as shown in TAN8 and the
IDCG are shown on the drawing attached as APPENDIX 2 to this evidence.
S36 Application Draft v (vi) 103 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.19 It is acknowledged that the IDCG has not been formally adopted by Powys CC as a
supplementary planning document. The IDCG has been subject to two periods of
public consultation (2006 / 2008). Prior to the second period of consultation the PCC
board formally authorised the second draft IDCG for use in ‘development control with
immediate effect’. This remains the status of the IDCG as explained on the Council’s
website.
6.20 It is considered that the Llandinam proposal has strategic planning encouragement in
principle, as a repowering project, and in response to the local refinement assessment
undertaken by Powys CC pursuant to the guidance of TAN8, lies within a geographic
area of Wales that is considered to be the most suitable to accommodate large scale
wind farm development – a SSA.
6.21 The site-specific landscape and environmental effects are addressed in the second part
of this Summary. A second matter of principle centres on the issue of the ‘TAN8
targets’. Table 1 of TAN8 refers to ‘indicative targets’. The footnote to Table 1 states
that the figures ‘represent a 1/3 reduction on the maximum capacities identified by
Garrad Hassan (GH) as reviewed in their 2005 Report.’
6.22 It is evident by referring back to the GH report that its work provides an ‘informed
view on the broad capacity limits of the areas and the headline common factors which
are likely to influence these limits.’ GH assumed a Base Case capacity as a ‘feasible
maximum capacity of each SSA’ (para 2.1) with the assumption of a 2MW turbine
with an 80m hub as a ‘typical onshore turbine specification for use in relatively
S36 Application Draft v (vi) 104 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
complex terrain, up to the year 2010’. The Llandinam repowering is for turbines up to
3MW. The capacity identified by GM would be different if the assumption had been
made for the use of turbines up to 3MW.
Para 2.5 of TAN8 makes the point that:
‘There may be practical, technical and/or environmental reasons why the
capacity may be more or less (emphasis added) than that indicated.’
6.23 The Welsh Government, in the Written Statement of 17th June 2011 and the letter to
Local Planning Authorities in July 2011, has raised concern that developer interest in
the SSAs has ‘greatly exceeded these (TAN8) indicative figures’. The Welsh
Government believes that this level of development is unacceptable in view of its
wider impacts on the local scene. In the correspondence to the LPAs the Minister for
Environmental and Sustainable Development stated:
‘TAN8 fully recognised the reinforcement of the transmission network in Mid
Wales as necessary to the realisation of additional generating capacity in the
area as well as providing a stronger more reliable network for energy users.
TAN8 set out the Welsh Government’s view that connections from the individual
turbines to a substation is “via underground cables”. TAN8 details that any
connection from a substation to the nearest point of the distribution network
would be “achieved by a standard 3 wire system on wooden poles or by
undergrounded lines”. This remains the Welsh Government’s view and is
reinforced by the approach set out within the Renewable Energy Route Map for
Wales in 2008, and the Energy Policy Statement in 2010. Provided development
is limited to the maximum capacities above, we do not believe that there is a need
for the large, visually intrusive, high voltage grid network infrastructure and
S36 Application Draft v (vi) 105 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
associated sub station of the kind proposed within Mid Wales. Where new grid is
required, we expect the grid company and regulator to ensure that it is located,
designed and installed as sensitively as possible, using appropriate techniques,
including the use of undergrounding.’
6.24 The proposed grid connection for the Llandinam repowering, which is subject to a
Section 37 application is achieved by infrastructure that would appear to accord with
the Minister’s preference for a ‘standard 3-wire system on wooden poles’. The fact
that the grid connection for the Llandinam repowering is well advanced in the
planning process is significant for the delivery timescale to respond to the urgent
requirement for additional energy production from renewable sources.
6.25 TAN8, and the Welsh Government in the Ministerial Statement referred above, are
material planning considerations. However, TAN8’s content should be set into
context with the primacy of the national policy statements (NPS EN-1 para 1.1.1).
The Secretary of State has recently endorsed the conclusions of an Examining
Authority that:
‘TAN8 [also] identified indicative capacity targets for each SSA, with these
intended to assist the planning process and not to be seen as the definitive
capacity for the area.’ (para 4.169 Brechfa Forest West Wind Farm)
The Secretary of State in his decision letter referred to the ‘nominal capacity of the
SSA.’ (para 23)
S36 Application Draft v (vi) 106 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.26 For similar reasoning to the conclusions reached in the Brechfa Forest West Wind
Farm proposal, Llandinam Repowering, and indeed other proposals within SSA C are
subject to environmental assessment, on an individual and cumulative basis. Even if
consent is granted for Llandinam repowering there is no guarantee that all the
proposed wind farms will be consented and built. As such TAN8, viewed with the
Welsh Government statement in 2011, does not provide a policy objection in principle
to wind farm developments that exceed the ‘maximum capacities’ identified by GH.
Furthermore it is evident the reference made by Welsh Government in this statement
is directed to the SSAs as identified in TAN8 (SSA-C Map 4) and not to the
boundaries as identified by PCC in the subsequent refinement exercise. In any event,
as acknowledged by the Welsh Government in its letter of 21st January 2013,
Llandinam repowering falls to be viewed apart from any such debate since it is a
repowering scheme.
6.27 Planning Policy Wales states that the approach of the Welsh Government is ‘to
reduce energy consumption and improve energy efficiency first and maximise
renewable and low carbon energy generation at every scale across Wales. This is part
of a concerted effort to tackle climate change’ (November 2012). In this policy
context the targets referred to in TAN8 for the SSAs should not be considered as
‘ceilings’, but rather – as stated by the Secretary of State in the decision at Brechfa
Forest – a ‘nominal capacity’. The fundamental planning consideration is whether the
landscape and environmental impacts on the various schemes before this conjoined
inquiry are individually and cumulatively acceptable.
S36 Application Draft v (vi) 107 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
6.28 Since Llandinam is a repowering project of an existing windfarm I consider that the
guidance in TAN8 encourages the development whether a windfarm is located within
a SSA or outside. I conclude that as a matter of fact Llandinam is situated outside
SSA-C as identified in TAN8 (Map 4) but within the refined SSA-C as identified by
Powys CC in its refinement study. I have understood the comments made by the
Welsh Government in the June 2011 statement, and January 2013 correspondence to
the conjoined Inquiry to relate to the SSAs as shown in TAN8 and not the refinement
study.
Summary of the site specific considerations arising from the proposal to repower
Llandinam wind farm.
6.29 I have considered the environmental and landscape impacts that have been raised by
PCC, NRW, the Alliance and third parties under a range of topic headings. I rely upon
the specialist evidence of witnesses as I have described in Section 4 of this Proof of
Evidence, and the conclusions reached particularly in the 2013 SEI as a consequence
of the proposal being reduced to 34 turbines.
6.30 I readily acknowledge that this proposal will give rise to some landscape and
environmental effects. The Welsh Government accepts that ‘there will always be
significant landscape and visual effects from their construction [commercial
windfarms] and operation for a number of kilometres’ (NPS EN-3). I further
recognise that there will inevitably be some disturbance to the local community
during the period of construction. Such a consequence is unavoidable. The approach
S36 Application Draft v (vi) 108 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
taken has been an endeavour to minimise all landscape and environmental effects,
hence the decision to reduce the number of turbines from 42 to 34, in the 2013 SEI.
6.31 I have not identified any impact from the proposal which I consider would cause
substantial harm whether considered on the basis of Llandinam repowering alone or
cumulatively. When considering the impacts overall, rather than under the separate
headings in this Proof of Evidence, I am similarly of the opinion that overall the
impacts would not cause substantial harm.
The undertaking of the planning balance, reaching a conclusion on the overall planning
merits of this proposal
6.32 It forms no part of the Welsh Government’s policy, or the provisions of the National
Policy Statements, that the ‘urgent need’ for new renewable energy generation
projects should outweigh all other land use planning considerations. I consider that
the repowering of Llandinam accords with the relevant policy matrix which I have set
out in this Proof of Evidence. The repowering of an existing windfarm is to be
encouraged, whether located within a SSA or outside a SSA, provided that the
landscape and environmental effects are acceptable.
6.33 In undertaking the planning balance, weighing the advantages from allowing this
development to proceed, including the advantage of delivering a renewable energy
development in a shorter period of time relative to other proposals, I believe the
balance of planning advantage in the overall public interest lies firmly in favour of
S36 Application Draft v (vi) 109 FramptonsApplication by Celt Power Limited Town Planning Consultants
May 2013Land at Llandinam Windfarm PJF/icp/CEL01/PF/8926
this application being approved and a deemed planning permission granted. I have not
identified any landscape or environmental effects from this development which I
would consider are not acceptable.