p4 c presentation by residents 1515 chicago april 8 2014
DESCRIPTION
1515 ChicagoTRANSCRIPT
1515 Chicago
Porous Asphalt
Project Safety
50/50 Alley
NORTH/SOUTH ALLEY
• very degraded
• spauling, fragmented
• paving brick substrate
• brick substrate
• loose, fragmented material
• this gravel like material ends up in sewers
• Edison electric vault impacted by debris
• Inbound traffic to 1515 porous paved lot would be effected
• 50/50 alley program would allow porous paved alley
COMMUNITY SAFETY• 1515 is a very
problematic site
• power pole on alley/project property line
• single pole with multiple(3) lines
• no crane load lines within 20 ft. of any power line or supports
• notice power pole guy line extends from power pole through the tree, across Chicago, well down opposite alley
• constricted use of Chicago Av construction lane?
• crane can only swing 180 degrees west-to-east
Building Over Alley• how does Peak
Construction propose to build over alley areas
• brick wall on east elevation
• scaffold shown 12 ft to lay brick walls
SAFETY QUESTIONS TO PEAK CONSTRUCTION
Do you have a safety plan at this time?Who is your safety director? OSHA trained?When does Peak propose to meet with
community & City to develop 1515 Site Specific Safety Plan
Has Peak Construction built with a tower crane in such a constricted site? Where?