pa chemical facility - apc/penndot fall...
TRANSCRIPT
www.jacobs.com | worldwide
PA Chemical FacilityDesign and Construction of Heavy Haul Bridge
November 17, 2016
Presented by: David J. Phelan, PEDaniel Noecker, PE
Agenda
2
1. Project Overview2. Design Phase3. Construction Phase4. Lessons Learned5. Question and Answer
Project Overview
3
Project Overview
4
I-376PROPOSED
PA CHEMICAL FACILITY
Project Overview• Relocate portion of SR 0018 south by 950 feet• New alignment cuts through mountainous terrain• Move 7M CY of excavated material to cap site• Aggressive design & construction schedule
5
Project Overview (con’t)• Road/bridge necessary across existing SR 0018,
relocated CSX Railroad, and future Rail Lines– Coordination with PennDOT 11-0 (HOP) and CSX– Temporary condition – hauling operation– Permanent condition – site access road
6
Project Overview
7
West Haul Bridge East Bridge
PROPOSED PA CHEMICAL FACILITY
Ohio River
Project Overview
8
``
West Haul Bridge
Design Phase
9
Design Phase• Challenges
– Compressed design schedule– Short construction duration over Western PA winter– Heavy vehicular load– Impact load
10
Design Phase• Design Criteria
– 75 year permanent design life– 2 year temporary design life (Hauling Operation)– Heavy Haul Considerations Alternatives
• Prefabricated temporary haul bridge• Permanent bridge• At-grade crossing• Conveyor belts
11
Design Phase
12
• Design Criteria (con’t)– Bridge Geometry
• No skew• Three (3) – 115 ft Spans
• Two (2) – 30 ft Lanes• 66 ft Overall Width
Design Phase• Design Criteria (con’t)
– Design Loads• Standard PennDOT/AASHTO Highway Loads• Caterpillar 777G (360 k GVW)
– Use of Standard PennDOT Details to the extent possible
13
Design Phase
14
CAT 777G (360,000 lbs GVW) PHL-93 (72,000 lbs GVW)
Design Phase• Proposed Bridge Superstructure
– P/S Concrete PA Bulb-Tee Beams 33x71.5• Simple Spans made Continuous for Live Load• Cost effective• Low future maintenance• Common bridge beam type in PA for these spans• Quicker fabrication turn-around time compared to steel
beams
15
Design Phase• Proposed Bridge Superstructure (con’t)
– 10 Beams– 6.5’ Spacing– 10,000 psi concrete– 0.6” diameter strands
16
Design Phase• Proposed Bridge Superstructure (con’t)
– Reinforced Concrete Deck & Approach Slabs• Special designs for heavier loads• 12” thick concrete deck with future LMC overlay• 30” thick approach slabs• Steel plate over neoprene strip seal
17
Design Phase
18
Design Phase• Proposed Bridge Superstructure (con’t)
19
– Enhanced AASHTO yield line analysis using assumed impact loads from design haul vehicle.• 8’-8” barrier and rail
combination• 14’-0” debris shield
Design Phase• Proposed Bridge Superstructure (con’t)
20
– 3D Finite Element Analysis for Deck and Approach Slab Design• 12” Class AAAP
Concrete Deck• 30” Class AAAP
Concrete Approach Slab
Design Phase• STAAD – Concrete Stress Output
21
Design Phase• Proposed Bridge Substructure
– Pile Stub Abutments behind MSE Walls (BC-799M)• Cost effective• Quick construction• Minimize concrete pours in winter• Integral CIP concrete crash wall for adjacent railroad• Predrilling to eliminate pile downdrag
22
Design Phase• Proposed Bridge Substructure (con’t)
– Wall Piers• Simple construction• Integral crash wall for adjacent railroad
23
Design Phase• Structural Design Considerations
– Two 30-0” bi-directional loaded lanes, limiting only one CAT 777G in each lane.
– Pile design (S.O.L. 483-13-12) • 50 ksi pile capacity• Temporary haul condition – Full pile section• Permanent condition – Reduced section accounting for
1/16” loss due to corrosive soils
24
Construction Phase
25
Construction Phase• MSE Wall Embankment Fill
– Contract drawings specified AASHTO NO. 57– Standard PennDOT Special Provisions allow for varying
types of fill materials with up to 15% fines– Special provisions take precedence in hierarchy of
contract documents in case of a discrepancy– Contractor’s bid based on sand
26
Construction Phase
27
Construction Phase• Request to run larger equipment across bridge
– CAT 785C• 550 k GVW (compared to 360 k GVW for CAT 777G)• 50% heavier than CAT 777G design• Bridge did not rate
– Various additional equipment loads evaluated– Signs installed at bridge approaches
• One vehicle in each direction at a time (200’ spacing)• Limit equipment on bridge & speed to 15 MPH
28
Construction Phase• Future Pipe Rack
– Additional 1.5 k/ft– Evaluate for final condition– Design modifications to accommodate
29
Construction Phase
30
January 2016 Field Visit
West Haul BridgeOhio River I-376
Construction Phase
31
January 2016 Field Visit
Construction Phase
32
January 2016 Field Visit
Construction Phase
33
March 2016 West Haul Bridge in Use
Lessons Learned
34
Lessons Learned• Review special requirements closely against
contract documents (MSE Fill)• Ensure design limitations are clear on plans• Consider modifying design criteria for temporary
conditions• Consider future potential uses and loadings
35
www.jacobs.com | worldwideNovember 21, 2016© Copyright Jacobs
Questions and Answer