Pakefield Temporary Protection works Pakefield, Suffolk What are we updating you about? What will we be doing? When are we doing the work? Contact us Where is this work happening? How can you find out more? Why are we doing this work? Coastal Partnership East are part of East Suffolk Council (ESC) and are responsible for coastal management. They have appointed the Water Management Alliance (WMA) to carryout Beach Protection works. The WMA will be completing works at Pakefield as part of that contract. A map of where the work is taking place is on the back of this factsheet. The work is spread along the beach from Rectory Road, Lowestoft to the beach south of Arbor Lane, Pakefield. There will be a temporary site set up established at All Saints Road. The WMA will be extracting a small amount of beach material from Lowestoft South Beach between Rectory Road and Kensington Road. Beach material will be transported along the beach by dumper truck to Pakefield and used to fill several one tonne bags and placing them in a 100m length protection at the base of the cliff and beach south of Arbor Lane, Pakefield. Coastal Management, Riverside 4 Canning Road, Lowestoft NR33 0EQ If you would like this factsheet in another format please do let us know by emailing: [email protected] December 2020 The temporary protection work will likely start from 7th December 2020 onwards, allowing our maintenance contractor to maximise work around daily low ides. This work will last approximately five days. All work is subject to safe working conditions i.e. tide and weather condition dependent. This work will provide temporary protection to the base of the cliffs and beach in the location of residential properties for this Winter. This part of the Coast has experienced erosion of the soft sandy cliffs. We have been working closely with the Pakefield Community Steering Group helping to protect homes and our beautiful and important coastline economically and environmentally and for the enjoyment of communities and visitors for generations to come. Ali Bloomfield, Operations Manager (Suffolk) Tel: 07775 662806 Email: [email protected] To ensure the safety of workers we kindly ask members of the public to maintain the correct social distance in accordance with the latest government guidelines. Please be aware of the use of heavy plant in the area. We will work hard to keep any inconvenience to a minimum and ask the public to please take note of the contractors signage when work is happening.

Upload: others

Post on 27-Mar-2022

7 views

Category:

Documents


0 download

TRANSCRIPT

Pakefield Temporary Protection works Pakefield, Suffolk

What are we updating you about?

What will we be doing?

When are we doing the work?

Contact us

Where is this work happening?

How can you find out more?

Why are we doing this work?

Coastal Partnership East are part of East Suffolk

Council (ESC) and are responsible for coastal

management. They have appointed the Water

Management Alliance (WMA) to carryout Beach

Protection works. The WMA will be completing

works at Pakefield as part of that contract.

A map of where the work is taking place is on the

back of this factsheet. The work is spread along the

beach from Rectory Road, Lowestoft to the beach

south of Arbor Lane, Pakefield. There will be a

temporary site set up established at All Saints

Road.

The WMA will be extracting a small amount of

beach material from Lowestoft South Beach

between Rectory Road and Kensington Road.

Beach material will be transported along the beach

by dumper truck to Pakefield and used to fill

several one tonne bags and placing them in a

100m length protection at the base of the cliff and

beach south of Arbor Lane, Pakefield.

Coastal Management, Riverside

4 Canning Road, Lowestoft

NR33 0EQ

If you would like this factsheet in another

format please do let us know by emailing:

[email protected]

December 2020

The temporary protection work will likely start from

7th December 2020 onwards, allowing our

maintenance contractor to maximise work around

daily low ides. This work will last approximately five

days.

All work is subject to safe working conditions i.e.

tide and weather condition dependent.

This work will provide temporary protection to the

base of the cliffs and beach in the location of

residential properties for this Winter. This part of

the Coast has experienced erosion of the soft

sandy cliffs.

We have been working closely with the Pakefield

Community Steering Group helping to protect

homes and our beautiful and important coastline

economically and environmentally and for the

enjoyment of communities and visitors for

generations to come.

Ali Bloomfield, Operations Manager (Suffolk)

Tel: 07775 662806

Email: [email protected]

To ensure the safety of workers we kindly ask members of the public to maintain the

correct social distance in accordance with the latest government guidelines.

Please be aware of the use of heavy plant in the

area.

We will work hard to keep any inconvenience to a

minimum and ask the public to please take note of

the contractor’s signage when work is happening.

Follow us on Twitter:

@CPE_NandS | @The_WMA | @EastSuffolk

Pakefield Temporary Protection works — location map

www.coasteast.org.uk

www.wlma.org.uk

www.eastsuffolk.gov.uk

Red arrow showing donor location for beach material to

be extracted and transported from.

Yellow arrow showing approximate extent of the

100m temporary defence.