paradip refinery the energy gateway to eastern...
TRANSCRIPT
Paradip Refinery The Energy Gateway to Eastern India
Content of Presentation • Indian oil- Overview
• About Paradip Refinery- Brief Introduction & Job Quantum
• Safety Management System of Paradip Refinery
• Initiatives taken for Zero Accident at Paradip Refinery
• Emergency Preparedness
• Occupational Health & Hygiene
AVU
MS & Naphtha Tank Farm
IndianOil - Overview
Brief History of IndianOil Birth of IndianOil
• 1958 (Aug) – Indian Oil Refineries Ltd formed
to erect refineries & laying petroleum pipelines
• Chairman: Shri Feroze Gandhi
• 1959 (June 30th) – Indian Oil Company Ltd formed
for marketing and distribution of petroleum products
• Chairman: Shri S Nijalingappa
Indian Oil Corporation Limited
Indian Oil Corporation Ltd. 1st Sept 1964
Indian Oil Company Ltd. 1959
Merger
❑ Assam Oil Company Ltd. merged in 1981 ❑ IBP Co. Ltd. merger effective May 2007 ❑ BRPL merger effective March 2009
Indian Refineries Ltd. 1958
IndianOil’s Value-chain
Key product portfolios / functions / groups
7
Paradip Refinery ❖ Capacity:- 15.0 MMTPA (Grass-root Refinery)
❖ Investment Approval : 28th February 2009
❖ Project Cost : Rs. 34,555 Crores
❖ IOC’s largest investment in a single Project
Job Quantum
• Land Reclamation/Dredging/Filling : 27.4 Mn M3 (2,366 Acres) (3 - 4 M sand fill)
Dredger
• Piling : 1.0 Lac (Max Dia-1400 mm, Depth-40 M)
Piling Rigs
Job Quantum
• Concreting (RCC & PCC) : 11.6 Lakh M3
(3 times volume of Burj Khalifa, Dubai)
Concrete: 3.3 Lac M3
Eiffel Tower, Paris : 9,441 MT
• Structural Steel (incl. Tor Steel): 2.8 Lac MT
(Equivalent to 30 Eiffel
Towers or about 350 Rajdhani Trains)
Job Quantum
• Pipes Consumed: 2,400 KM
(almost the length of Ganges, 2,525 KM)
- Piping Fabrication 60.0 Lac Inch Dia
- Piping Erection 112 Lac Inch Metre
•Largest Dia Pipe: 104” (8.7’)
(Mercedes-Benz “S’” can pass through )
Largest Diameter Pipe
Job Quantum
• Tanks/Mounded Bullets: 79 Nos.
• Cables: 20,000KM (about 1.8 times Dia of Earth:12,756 KM)
Largest Bullet (L-99.4m, D-6.4m)
Job Quantum
• Equipment (Static & Rotary): 3,300
Nos.
• 32 heavy equipment (weighing >300 MT)
• Transported via sea route from vendors shop on self propelled/ pulled barges up to Paradip Port
• Erection by M/s Mammoet using 4 Heavy Duty Cranes of capacity – 2000 MT, 1600 MT, 1200 MT & 600 MT (brought from Singapore/ Netherland/ Middle East etc)
Vacuum Distillation Column (M/s L&T, Wt.:
1208 MT, Ht.: 57 M, Dia.: 14 M )
- on Self-Propelled Barge - Aug’11
Erection of VDU Column – Nov’ 11
Paradip Refinery – Process Units PROCESS UNITS CAPACITY (’000 TPA) PROCESS LICENSOR
Primary Processing Unit
Atmospheric & Vacuum Unit (AVU) 15,000 Open art by FWEL
Secondary Processing Units
Indmax (Fluidized Catalytic Cracking Unit) 4,170 IOC R&D
Delayed Coking Unit (DCU) 4,400 Foster Wheeler, USA
VGO Hydro Treating Unit (VGO-HDT) 5,400 Axens, France
Other Major Processing Units
Diesel Hydro Treating Unit (DHDT) 5,200 Shell Global, Netherlands
Propylene Recovery Unit (PRU) 1900 Basell, Italy
Naph. Hydrotreater /Catalytic Reformer (NHT/CCR) 3,900 / 2,900 UOP, USA
Alkylation Unit 650 ExxonMobil, USA
Butane Isomerization Unit (Butamer) 300 UOP, USA
Sulfur Recovery & Tail Gas Treating (SRU/TGTU) 2 x 525 TPD Black & Veatch, USA
Kero / FCC LPG/ FCC Gasoline Treating Units 1,200/1,850/400 Merichem, USA
SR LPG Treating unit 210 UOP, USA
Sulfuric Acid Regeneration Unit 185 TPD MECS
Sour Water Stripper (SWS) Train 1/2 402.6 / 228.8 TPH Open Art
Amine Regeneration Unit (ARU) Train ½ 478.8 / 947.9 TPH Open Art
Crude Oil Terminal & Handling Facilities
• Crude oil is imported by marine VLCC tankers.
• Crude oil unloading: via SPM-1 and 48”Ø sub-sea pipeline - to Crude Storage Tanks
• SPM-2 & SPM-3 – Envisaged at Paradip.
1 VLCC = 3,20,000m3 1 VLCC = 7 Crude oil tanks 1 VLCC Crude oil - ~ 7 days of AVU T’put).
Crude Oil Terminal & Handling Facilities
Crude Oil Terminal
and Pump Station
SPM-1
SPM-2
SPM-3
Paradip
Refinery
Paradip Port
Crude Unloading Source
Line Size ( inch)
Avg Parcel Size (m3)
Disch Press Kg/cm2
Discharge Rate (m3/hr)
Pumping Time Reqd. (hr)
Total Time Reqd. (hr)
SPM 48” 3,20,000 8-11 8,000-12,000 38-40 46-48
SOUTH JETTY 38” 1,00,000 10 4,000 25 30-38
SOUTH OIL JETTY
Crude Unloading Source
Line Size ( inch)
Avg Parcel Size (m3)
Disch Press Kg/cm2
Discharge Rate (m3/hr)
Pumping Time Reqd. (hr)
Total Time Reqd. (hr)
SPM 48” 3,20,000 8-11 8,000-12,000 38-40 46-48
SOUTH JETTY 38” 1,00,000 10 4,000 25 30-38
Aromatics Units
Refinery Units
Buildings
Utilities
Future Expansion
Offsite
BOO-1: H2 & N2
BOOT-3 Tankage
BOO T-4: Raw Water
Deferred Units
N
Total Area : 3,344 acres (Township/ Approach Road – 399 acres, Plant – 2945 acres (incl. 580 acres for Green Belt))
Plot Plan
• Block layout adopted for plant as per OISD-STD-118. • Separation distances maintained as per OISD-STD-118. • Risk analysis carried out . • EIA study carried out. • ERDMP approved by DMI, Bhopal • Mutual aid with neighboring Industries established. • OISD PCSA carried out for facilities ready for commissioning. • PESO clearance obtained for storage of Cl2, LPG, H2,
Plant Layout
Safety Management Systems of Paradip Refinery has been
prepared on the basis of :-
• Process Safety Management of Occupational Safety &
Health Administration (OSHA), USA
• Corporate Guidelines on Safety, Health and Environment Management System of Indian Oil
• OISD Guidelines on Safety Management System in Petroleum Industry (OISD-GDN-206)
The Energy Gateway to Eastern India
Paradip Refinery
Safety Management System of Paradip Refinery
• To prevent any unsafe condition and eliminate or mitigate
their probable consequences.
• To control loss to personnel, equipment, material and
environment.
• To standardize the procedures which should continue to be
followed by one and all unless a change in the system is
duly authorized by a competent person.
HSE Management System of Paradip Refinery
The Energy Gateway to Eastern India
Paradip Refinery
SAFETY
• Zero Accident.
• Zero Fire.
• OPL Sharing.
• Increasing Near miss
Incident Reporting.
• Improve Housekeeping.
• Raise safety awareness through safety education & Training.
HEALTH
• Monitor & maintain for hygiene at work place.
• Carry out pre-employment, & periodic medical health check up of employees.
• Conduct surveys &
investigations on potential health hazards.
• Train employees in First-
Aid, Occupational Health & hygiene.
ENVIRONMENT
• Carry out continuous Stack monitoring & ensure emission is within the stipulated norms.
• Reduce CO2 emission from the plant.
• Reduce consumption in
fresh water .
• Increase the re-use of treated water.
A I M
The Energy Gateway to Eastern India
Paradip Refinery
17 Elements of Safety Management System of Paradip Refinery
1. Safety Organization & Leadership
2. Process Safety Information (PSI)
3. Process Hazard Analysis (PHA)
4. Standard Operating Procedures(SOPs)
5. Pre-startup Safety Review (PSSR)
6. Mechanical Integrity (MI)
7. Management of Change (MOC)
8. Permit to Work System (PTW)
9. Incident Investigation and Analysis
10.Emergency Planning and Response
11. Contractors Safety Management
12. Safety Training & Development
13. Transportation & Traffic Safety
14. Compliance Audit & Assurance
15. Occupational Health Management
16. Employees Participation
And
17. Off-the Job Safety
HSE Organisation & Leadership of Paradip Refinery
Executive Director
General Manager ( HSE)
Chief Manager (F&S)
Dy. General Manager (HSE)
Chief Manager (HSE)
Manager ( Safety)
Engineers, Sr. Engineers Dy. Managers
CISF (Fire Wing) 111 Nos.
Sr. Manager ( Fire Protection) Dy. Manager
( Process Safety) Dy. Manager
( Environment)
The Energy Gateway to Eastern India
Paradip Refinery
Process Safety Information
Process Hazard Analysis &
Operating Procedures
The Energy Gateway to Eastern India
Paradip Refinery
Process Safety Information / Process Hazard Analysis & Operating Procedures
Complete and accurate written information is compiled for the following three categories:
1) Process chemicals
2) Process technology
3) Process equipment
The information represents current operation. All data sheets, drawings, specifications and other documents are updated / revised based on the present condition of the process. MOC is enforced for incorporation of all modifications.
Computerization of the information has been done & is available through
RDBMS facilitating easy up-dation and retrieval. It is put on local network for
easy accessibility of all concerned.
The Energy Gateway to Eastern India
Paradip Refinery
Process Chemicals - MSDS
Process chemicals include all raw materials, intermediates / finished products and chemicals used in the refining process. For each process chemical, following information is made available through MSDS:
Physical properties
Fire & explosion Hazards
Reactive Hazards
Health Hazard Data:
Corrosive properties of the chemical, runaway reaction and over-
pressure hazards
Information on fire fighting media, use of personal protective equipment
(PPE), emergency treatment for exposure and release / spill
containment.
The Energy Gateway to Eastern India
Paradip Refinery
Process Technology
Process technology information of all the process including the following
are available both in Soft & hard Fashion:
1. Written process descriptions
2. Process chemistry
3. Block Flow Diagram(BFD), Process Flow Diagrams (PFD) & Process & Instrumentation Diagrams.(P&ID)
4. Safe operating limits of process parameters like pressure, temperature, flow rate etc. and the consequences or results of deviation that could occur if operating beyond the established process limits
5. Maximum inventory levels for process chemicals
6. Material and energy balances.
The Energy Gateway to Eastern India
Paradip Refinery
Process Equipment
Process equipment include columns, vessels, heat exchangers, reactors, pumps & compressors, valves, piping; drilling rigs & work-over rigs; cross country pipelines; tanks, loading & un-loading facilities and other equipment that contain process chemicals. Design data of all process equipments area documented and include the following:
Materials of construction
Design specifications
Codes, standards and industry accepted engineering practices used for design and fabrication
Electrical classification
The Energy Gateway to Eastern India
Paradip Refinery
Process Hazard Analysis
The PHA is done by a multidisciplinary team using one or more of the following methodologies that are appropriate to identify, determine and evaluate the hazards of the process being analyzed.
•What if, checklist
•Hazard and Operability Study( HAZOP)
•Failure Mode and Effects Analysis
•Fault Tree Analysis
PHA is carried for all new process, any modifications in the existing process & on processes depending on age and operating history of the process
The Energy Gateway to Eastern India
Paradip Refinery
Operating Procedures
Written down operating procedures are available for all process plants for safe operation . The operating procedures provide specific instructions on what steps to be taken or followed while carrying out the following:
Startup - including procedure for initial startup of the process or equipment as well as startup after normal and emergency shut downs. Normal operation - including limits of the "normal" operating ranges for parameters such as pressure, temperature and flow, the consequences of operating outside these limits, and the actions that should be taken to correct or avoid deviation from the normal ranges.
Temporary operation - Including special requirements while operating in the temporary mode and the acceptable duration of the temporary operating mode.
Normal shut-down - Including actions to be taken to safely shut down the process or equipment and conditions to be avoided
Emergency operation and shut-down - Including the conditions under which an emergency shut-down is required along with assignment of authority and responsibility to ensure that shutdown is executed in a safe and timely manner
• Monthly Safety Day celebrated on 1st working day of every month at 10 Zones on different safety themes.
• Lessons learnt from Hi-Po near miss incidents of previous month shared. • On spot quiz is conducted & prizes distributed.
SAFETY THROUGH INVOLVEMENT & PARTICIPATION
• Demonstration of Safety Equipment in line with MSD theme carried out at site during Monthly Safety Day celebration.
• Identified Safe workers recognized by affixing STAR sticker on helmet during Monthly Safety Day celebrations.
SAFETY THROUGH INVOLVEMENT & PARTICIPATION
• Recognition given to winners on Housekeeping & Near Miss
Competition
The Energy Gateway to Eastern India
Paradip Refinery
SAFETY THROUGH INVOLVEMENT & PARTICIPATION
SAFETY THROUGH INVOLVEMENT & PARTICIPATION
SAFETY THROUGH INVOLVEMENT & PARTICIPATION
The Energy Gateway to Eastern India
Paradip Refinery
• Mandatory HSE induction training to all new entrants.
• 100 % compliance on use of Job specific Personal Protective Equipment.
• System of imparting daily Tool Box Talk prior to start of job is in place.
• Job Safety Analysis of Critical activities carried out.
• Enforcement & Adherence to Work permit system
• Regular Class Room & On Job trainings.
• Daily Safety announcement at main gate & project sites.
Initiatives taken for Zero accident
The Energy Gateway to Eastern India
Paradip Refinery
• System of Award & recognition of safe workers in place.
• Publishing & wide distribution of leaflets/ pocket card on lessons learnt from past incidents
• Publishing and circulation of weekly Safety e- bulletins.
• Discussion of case studies & encouraging workers to report near miss incidents during various safety awareness campaigns.
• Mandatory Health Check up of all contract workers at site. • Celebration of Monthly Safety Day on various themes at 10 different
locations involving Top management.
Initiatives taken for zero accident at Paradip Refinery
The Energy Gateway to Eastern India
Paradip Refinery
• On line near miss incident reporting, investigation & analysis.
• Mandatory use of full body harness & life line while working at height.
• Conduct Mock drills & demonstrations on regular basis.
• Implementation of color coding of helmets for ready identification.
• Implementation of Penalty scheme for safety lapses.
Initiatives taken for zero accident at Paradip Refinery
The Energy Gateway to Eastern India
Paradip Refinery
Safety Inspections
• “NO MOBILE” & “NO CO-PASSENGER” stickers provided in hydras.
Traffic Safety
LOTO System at Paradip Refinery
The Energy Gateway to Eastern India
Paradip Refinery
Paradip Refinery Project A Sunrise Project for a Sunshine Future
Special Training Program for Drivers & Equipment Operators conducted.
Initiatives taken for Zero accident
Demonstration of Safety gadgets &
Enacting stage shows
The Energy Gateway to Eastern India
Paradip Refinery
PROACTIVE SAFETY APPROACH – TRAFFIC SAFETY
The Energy Gateway to Eastern India
Paradip Refinery
Class Room Training To Employees & Contract
Workers on General Loss Control Rules &
Safe Work Procedures.
PROACTIVE SAFETY APPROACH- SAFETY EDUCATION & TRAINING
Contractor workers
Employees CISF
Employees
Employees
Contractor workers
Contractor workers CISF
Paradip Refinery practices the following Audits for improvement in Safety System: • Internal Safety Audit on Half yearly basis as per OISD-145. • Internal System Audit on Yearly Basis. • Internal & External Audit for OHSAS on half Yearly Basis • Surprise Safety Audit by OISD Team on Yearly Basis. • External Safety Audit by OISD team once in Three Years. • Pre-commissioning Safety Audit for each New Facility.
SAFETY AUDITS FOR IMPROVEMNT
The Energy Gateway to Eastern India Paradip Refinery
EMERGENCY PREPAREDNESS
Glimpses of On-Site Disaster Drill
•Emergency Management Plans - on site & - off site
•On-site drills once in 3 months against the statutory norm of once in 6 months
•Off-site drill with Dist. Administration once a year
•Mutual aid Agreements with Neighboring industries
The Energy Gateway to Eastern India Paradip Refinery
Fire protection facilities provided:
•- Fire Water including storage , pump house & network
•- Foam System
•- Clean Agent Fire Protection system
•- Carbon Dioxide System
•- Dry Chemical Extinguishing System
•- Fire Detection and Alarm system
•- Communication System
•- Portable fire fighting equipment
•- Mobile fire fighting equipment
Fire Protection System
• 2 X 14000 m3 capacity
• Storage is for 4 hours of maximum water demand
• During emergency make up from Raw water reservoirs
(Pump Capacity 2000 M3/hr. Header size : 36” Dia)
49
Fire Water Storage
2 water reservoirs ( Capacity 2,65,000 M3 each) Fire Water Storage Tanks
Fire Water Pumps • Jockey Pumps- 02 nos. electrical Drive
• Main Pumps- 14 nos. ( 7 Motor driven & 7 Diesel Engine driven)
• Capacities : Jockey pump - 350m3/hr & Main Pumps 795 m3/hr
• Auto sequential operation provided.
50
51 Clean Agent Flooding for Control Room
Mobile Fire Fighting Equipment 4 nos. of Foam Tenders fabricated on Volvo Chassis Foam tank Capacity 6000 L Pump Capacity 8000 LPM Foam Pump 500 LPM 1 Hydraulic Platform Boom Height : 54 M 2 nos. Foam Nursers : Tank Capacity : 12000 L Pump Capacity : 600 LPM One DCP Tender of 2 spheres each of 2000 KG capacity One Emergency Rescue Tender (ERT) Quick Response Vehicle (QRV) •
52
Fire Stations
• 2 Fire Station one at South site and other at North Site.
• CISF (Fire wing) deployed for Paradip Refinery
53
54
Chlorine Absorption System
Chlorine Absorption System
1. In case of chlorine leaking at 1 PPM from its container / system, the system will automatically start. i.e. blower & pump will start simultaneously.
1. The pump will deliver NAOH from tank through the top of absorption tower & blower will suck the leaked chlorine from bottom of absorption tower.
1. Due to counter current between NAOH & Cl2, chlorine will be neutralized.
1. Neutralized chlorine will be vent out to atmosphere through blower & FRP ducting.
Infrastructure
ASSEMBLY POINTS: Assembly point in North side:
AP-1: Administration building
AP-2: North Fire station
AP-3: OM&S building
AP-4: Tank firm area
Assembly point in South side:
AP-1: Near Technology building
AP-2: CPP Area
AP-3: DM plant area
AP-4: Main control Room
AP-5: CRWS lift station
AP-6: ETP area
Emergency Preparedness Drills
56
• Live Demonstration on Fire Fighting & Safety and rescue equipment organized during the Republic Day Function on 26th January 2015 at Township Stadium.
DEMONSTRATION OF EMERGENCY HANDLING CAPABILITIES
58
On the occasion of “ Odisha Disaster Preparedness Day-2014” on 29th October, 2014, Paradip Refinery demonstrated its F&S capability to a large gathering of public at the Collectorate ground in Jagatsinghpur in presence of Shri Satya Kumar Mallick, Collector & DM, Jagatsinghpur, Ms. Sudha Singh, SP Jagatsinghpur, other officials from Jagatsinghpur The demonstration was also keenly watched by the general public and a large no. of school children. At the end, Collector & DM, Jagatsinghpur Shri Satya Kumar Mallick thanked all the participants & appreciated the emergency handling capability developed by Paradip Refinery.
Participation in Odisha Disaster Preparedness Day
DEMONSTRATION OF EMERGENCY HANDLING CAPABILITIES
• Objective
• Promote health care of the man behind the machine
• Early detection of occupational disease
• Occupational health monitoring is in line with OISD-GDN-166
• Major activities are
• Pre-employment medical examination
• Periodical medical examination - target organs
• Well person screening of employees above 40 years
• Thorough examination of food handlers - skin infection, chest infestation, worm infestations
• Sound level monitoring in high noise areas - once in 6 months
• Checking and surveillance of First Aid boxes
• Provision of safe drinking water
• Proper disposal of Bio-medical waste
• External Auditing – Twice in a year
OCCUPATIONAL HEALTH & HYGIENE
The Energy Gateway to Eastern India Paradip Refinery
Thank You