part 2 - jica · rehabilitation programme is described in the final report part 1, which was...

90
S D J R 05-005 No. JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) URGENT REHABILITATION SUPPORT PROGRAMME IN KANDAHAR (URSP-KDH) Part 2 FINAL REPORT ON THE URGENT REHABILITATION PROJECTS MARCH 2005 PACIFIC CONSULTANTS INTERNATIONAL

Upload: others

Post on 30-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

S D

J R

0 5 - 0 0 5

No.

JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)

URGENT REHABILITATION SUPPORT PROGRAMME IN KANDAHAR (URSP-KDH)

Part 2FINAL REPORT ON

THE URGENT REHABILITATION PROJECTS

MARCH 2005

PACIFIC CONSULTANTS INTERNATIONAL

Page 2: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation
Page 3: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

PREFACE

In response to a request from Transitional Islamic State of Afghanistan, the Government of Japan decided to conduct the Urgent Rehabilitation Support Programme in Kandahar and entrusted the programme to Japan International Cooperation Agency (JICA).

JICA selected and dispatched a study team headed by Mr. Shozo KAWASAKI at Pacific Consultants International from August 2002 to March 2005.

The team held discussions with the officials concerned of Islamic Republic of Afghanistan and other international donors, and conducted field surveys as well as rehabilitation programme such as construction of school and roads in Kandahar City. Upon returning to Japan, the team prepared this final report to summarize the result and impacts of the programme.

I hope that this report will contribute to the enhancement of friendly relationship between our two countries.

Finally, I wish to express my sincere appreciation to the officials concerned of Islamic Republic of Afghanistan for their close cooperation extended to the study.

March 2005

Kazuhisa MATSUOKA,

Vice President

Japan International Cooperation Agency

Page 4: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

March 2005

Mr. Kazuhisa Matsuoka

Vice-President

Japan International Cooperation Agency

Tokyo, Japan

Letter of Transmittal

Dear Sir;

We are pleased to submit herewith the Final Report of “Urgent Rehabilitation Support Programme in

Kandahar (URSP-KDH)” which is the third package of URSP committed by the Government of

Japan in March 2002.

This report compiles the process and results of the study and rehabilitation projects, which were

conducted from September 2002 through February 2005 by the Study Team organized by Pacific

Consultants International.

During the period of project implementation, URSP-KDH faced many difficulties such as unstable

security situation, and insufficient human and social capital in the post-conflict situation.

Nevertheless, URSP-KDH was completed successfully totally owing to the effective assistance

given by all parties concerned, including JICA, the Japanese Embassy, counterpart agencies, and the

untiring efforts exerted by the Team and Afghan Contractors involved.

Afghanistan is still faced with a severe situation requiring further reconstruction and development,

and so we truly hope for your continuous concern and support to future projects in Afghanistan.

We would like to express our sincere appreciation to all the parties concerned and for your kind and

effective cooperation for the successful implementation of URSP-KDH.

Very truly yours,

Shozo KAWASAKI

Project Leader,

Urgent Rehabilitation Support Programme

in Kandahar (URSP-KDH)

Page 5: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Project Maps

MAP OF SOUTHERN REGION OF AFGHANISTAN

Malalai School

Ahmad Shah Baba School

Mirwais Hospital

LOCATION MAP OF URGENT REHABILITATION PROJECT IN KANDAHAR CITY

Roads for Paving

To Kabul

To AirportTo Spin Boldak

LEGEND

JICA/PCI Project Office

Batch1 ProjectBatch 2 Project

Page 6: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation
Page 7: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

i

ABBREVIATION LIST 

AACA Afghan Assistance Coordination Authority AG Advisory Group AIA Afghan Interim Administration AIMS Afghanistan Information Management System ANA Afghan National Army ARI Acute Respiratory Infection ATA Afghan (Islamic) Transitional Authority CG Consultative Group CMS Construction Management Service(s) DF/R Draft Final Report DOE Department of Education DOPH Department of Public Health F/R Final Report GOJ Government of Japan HABITAT United Nations Centre for Human Settlement (UNCHS Habitat)/ United Nations

Human Settlements Programme IA Implementation Arrangement ICMC International Catholic Migration Commission IC/R Inception Report ICRC International Committee of Red Cross IT/R Interim Report JICA Japan International Cooperation Agency KDH Kandahar K-K Kabul-Kandahar LCB Local Competitive Bidding MOPH Ministry of Public Health MSF Medicine Sans Frontieres NDB National Development Budget NDF National Development Framework NGO Non-governmental Organization PAMA Department of Housing and Town Planning PCI Pacific Consultants International PIMA Pakistan Islamic Medical Association PR/R Progress Report

Page 8: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

ii

UN Habitat United Nations Centre for Human Settlement (UNCHS Habitat)/ United Nations Human Settlements Programme

UNICEF United Nations Children’s Fund URSP Urgent Rehabilitation Support Programme URSP-EHB Urgent Rehabilitation Support Programme in Afghanistan, Education, Health,

and Broadcasting Sectors URSP-KDH Urgent Rehabilitation Support Programme in Kandahar URSP-SWPT Urgent Rehabilitation Support Programme in Afghanistan, Rehabilitation Study

for South-Western Area & Public Transportation Study of Kabul WFP World Food Programme

Page 9: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (1)

EXECUTIVE SUMMARY OF THE FINAL REPORT, PART 2, ON THE URGENT REHABILITATION SUPPORT PROGRAMME

IN KANDAHAR (URSP-KDH)

1. BACKGROUND  

The  international  community has  been  at the  forefront  in  the  effort  to  rebuild Afghanistan  after  the  collapse  of  the Taliban  regime.  At  the  International Conference  on  Reconstruction  Assistance to  Afghanistan  held  in  January  2002  in Tokyo,  financial  assistance  amounting  to about US$ 4.5 billion was pledged  for  the next two‐and‐a‐half years toward this end. Of this amount, the Japanese Government has  pledged  the  amount  of  US$  500 million over the said period toward urgent humanitarian  assistance  in  the  sectors  of education,  health  and  medical  care, resettlement  of  repatriated  refugees, landmine clearance, and empowerment of women’s participation in society. 

Since  April  2002,  Japan  International Cooperation  Agency  (JICA)  has  been conducting  what  is  called  Urgent Rehabilitation  Support  Programme (URSP).  First  to  benefit  is  Kabul  city, which has seen the programme embark on urgent  rehabilitation  for  school  buildings and medical  facilities, broadcasting of  the Emergency  Loya  Jirga,  teacher  training and so on. 

Following the URSP in Kabul is the Urgent Rehabilitation  Support  Programme  in Kandahar  city  (hereinafter  called “URSP‐KDH”), which  is  the  centre of  the south‐western  region  of  Afghanistan. URSP‐KDH was  formulated  according  to the  Implementing  Arrangement  (IA) agreed  upon  by  the  Afghan  Assistance Coordination  Authority  (AACA), Kandahar  Provincial  Government, Ministry  of  Planning  and  Ministry  of 

Reconstruction of  the Afghanistan  Islamic Transitional Authority (ATA) on 8 August 2002. 

This  report  summarizes  the  Urgent Rehabilitation  Projects  of  URSP‐KDH covering  education,  health,  road  and sanitation,  the  constraints  of implementation  and  measures  taken  to address  these  constraints,  and  the  school maintenance  improvement  programme, which  constitutes  the  soft  component  of URSP‐KDH. An  evaluation  of  the  urgent rehabilitation projects is also included. 

1.1  Scope of URSP‐KDH 

The following tasks are covered under the URSP‐KDH: 

(1) Establishment  of  Urgent Rehabilitation  Programme:  This  is  to formulate  a  short‐term  rehabilitation programme  covering  not  only  the physical infrastructure sectors but also other  pertinent  sectors,  in  order  that the  urgent  rehabilitation  projects  are rightly  positioned  and  seamlessly sustained  towards  future reconstruction.  (Proposed  Urgent Rehabilitation  Programme  is described  in  the  Final  Report  Part  1, which  was  submitted  in  February 2003 by the Study Team.) 

(2) Implementation  of  Urgent Rehabilitation  Projects:  This  is  to rehabilitate/ reconstruct damaged and destroyed  facilities  and  structures, especially  roads,  educational  and medical facilities. 

 

Page 10: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (2) 

1.2  Urgent Rehabilitation Projects 

The  table  below  shows  the  list  of Urgent Rehabilitation Projects, which are divided into two batches. Both Batch 1 and Batch 2 cover education, health, and  road  sectors; sanitation sector  is  included only  in Batch 2. Moreover,  Batch  2  projects  are  linked with  Urgent  Rehabilitation  Programme, and  consolidated  in  coordination  with other donors’ activities. 

Sector  Batch 1  Batch 2 Education  Construction of:   

• Ahmad Shah Baba High School (including rehabilitation for destroyed roof of existing building) 

• Zahir Shahi High School 

• Malalai High School 

Construction of: • Sufi Saheb High School 

• Aino Middle School 

• Kaka Sayed Ahmad School 

• Mirwais Mena School 

Health  • Rehabilitation of building and supply of new equipment for kitchen and laundry in Mirwais hospital   

• Supply 5 commuter buses for the Kandahar Nursing School   

Road  • Construction of 6‐km By‐pass City Road 

• Rehabilitation of Kabul‐Kandahar Road (K‐K Road) 

• Construction of 2.3‐km City road reaching from the city centre to the Mirwais Hospital.

Sanitation    • Supply 3 cargo vehicles for collecting solid waste for Kandahar Municipality   

 2. IMPLEMENTATION OF URGENT

REHABILITATION PROJECTS

In  the  process  of  construction  and rehabilitation,  the  URSP‐KDH  sought  to revive  the  Afghan  economy  through employment  of  Afghan  contractors  by local  competitive  bidding.  However,  the Study Team realized that the decades‐long conflicts  have  eroded  the  technical capacity of  local  contractors and  laborers. To  address  this  issue,  the  Study  Team established the Construction Management 

Services  Team  to  not  only  manage  and supervise the work of Afghan Contractors, but most  importantly,  to  train  the Afghan engineers  through  “on‐the‐job  training.” In  addition,  materials  available  in  local market  or  neighbouring  countries  are given  top priority  for  construction use  to provide  ease  and  economy  of  operation and  maintenance.  This  arrangement  was adopted  in  the  implementation  of  the Urgent Rehabilitation Projects below. 

2.1  Education Sector 

The  plight  of  education  in  Afghanistan was evident immediately from a UNESCO report, which  showed  that Afghanistan  is expecting  the  worst  education  indicators in  the world,  especially  the  indicators  on education  of  girls  and  rural  populations. The years of conflict and destruction have taken  their  roll  on  school  facilities, teachers and pupils. 

UNICEF made education a key priority in post‐war  Afghanistan.  Their Back‐to‐School  Campaign  saw  the returning  to  school  of  a  large  number  of children  when  the  new  school  year commenced  on  September  7,  2002  in Kandahar.  Available  teachers  also  went back  to  teaching.  Due  to  natural population  growth  and  rapid  inflow  of returnees  into  the  cities,  Kandahar  City faced the need for thousands of additional classrooms by year 2004. 

As of 2002, there were 211 primary schools in  the  province.  An  estimated  80%  of school  buildings  at  all  levels  were damaged  or  destroyed.  Particularly,  the surrounding  area  of  the  City were more heavily damaged and destroyed. The work of  rehabilitating  schools  was  a  long  and arduous task. 

In  the selection of schools  for Batch 1,  the Study  Team  placed  a  priority  on  heavily damaged  schools  or  those  schools  that 

Page 11: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (3)

needed  rebuilding  or  additional classrooms;  the  reason  for  this  was  to complement  the  work  of  international donor  agencies  and  NGOs  that  were choosing  only  slightly  damaged  schools for quick results. 

After discussions with the DOE and other donors  in October  2002,  the  Study  Team was able to set the criteria for the selection of  schools.  In  the  end,  one  girls  school (Malalai  High  School)  and  two  boys schools  (Ahmad  Shah  Baba  and  Zahir Shahi)  were  selected  for  construction. Work was carried out from December 2002 to October 2003. 

For Batch 2, the Study Team, together with some  DOE  personnel,  visited  candidate sites,  as  well  as  other  schools  within Kandahar  city  and  surrounding  areas  of the  city,  to  see how  other donor  agencies were  going  about  their  construction projects  and  to  assess  the  technical practicability for construction work within a  set  timeframe.  After  assessing  the situation,  the  Study  Team  selected  four schools:  namely,  Sufi  Saheb High  School, Mirwais Mena School, Kaka Sayed Ahmad School  and  Aino  Middle  School. Construction commenced in June 2003 and was completed in September 2004. 

In  general,  the  design  criteria  of  the selected  schools  is  as  follows:  (i) seismically  sound  school  structure;  (ii) appropriate number of rooms (40 students per  room);  (iii)  two‐story  building  to accommodate an increasing demand while having  more  playground  space  for children;  (iv)  a  fence/boundary  wall;  (v) separate  toilets  for  male  and  female students and teachers; and (vi) a deep well for  water  supply.  In  addition,  Batch  1 schools have a storeroom and a staff room and Batch 2 schools have a Head Teacher’s Room,  a  Teachers’  Room/Meeting  Room and a storeroom.   

2.2  Health Sector 

Afghans  used  to  depend  on non‐governmental  sources  for  much  of their health concerns. This was during the pre‐war  period  when  popular  medical alternatives  included  local  healers, traditional midwives, and bonesetters. The health  services  at  that  time were  curative based and clinically oriented. 

The southern region has 83 health facilities in  total. Out of  this number, 65  (82%) are managed  by  NGOs,  and  only  18  are managed by DOPH. 

Kanadahar  City  has  13  health  facilities, which  are  categorized  as public hospitals and  clinics,  6  facilities  are  managed  by DOPH  and  7  are  overseen  by  NGOs. Health  service  in  government  facilities  in Afghanistan  are  free  of  charge,  but  in Mirwis  Hospital,  patients  have  to  pay 1,000  afg  (1  new  afg)  for  the  first examination and direct expense of X‐rays. 

For  human  resources  development  of medical  staff,  the  faculty  of medicine  of Kandahar  university  accepts  both  male and female students. It operates under the ministry of higher education, and teaching doctors come from Mirwis Hospital. Also, there are 5 nursing schools in the country, one of them being in Mirwis hospital. 

Under  Batch  1,  the  target  of  urgent rehabilitation  is  Mirwais  Hospital—the biggest hospital in the southern region and the  top  referral  hospital  in  Afghanistan. However,  no  rehabilitation  work  on  the building  facilities  or  upgrade  of  its medical  equipment  has  been  performed since 1980. The hospital survey conducted by  the  Study  Team  revealed  that  total renovation  of  the  hospital would  need  a long  time  and  serious  consideration. Considering  the  limited  timeframe,  the Study Team decided only  to  renovate  the Kitchen  &  Laundry  facilities  of  Mirwais Hospital,  including  supplying  them with 

Page 12: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (4) 

new  equipment,  in  order  to  improve  the food  service  and  hygiene  of  the  hospital. This whole process took just three months, from December 2002 to March 2003. 

For Batch 2 health sector project, the Study Team  turned  its  attention  to  the transportation  of  female  students  and teachers  from  their  houses  to  Kandahar Nursing  School.  (This  is  a  problem brought  about  by  custom,  making  it difficult for women to travel alone even  if they live nearby the school.) The answer to this  problem  was  to  supply  the  school with  three  commuter  buses  and  two microbuses  to  transport  91  students  and teachers  of  Kandahar  Nursing  School. Seats  could  be  added  in  case  of  student increase  in  the  future.  The  vehicles were delivered in June 2003. 

2.3  Road Sector 

Kandahar  connects  two  national  roads. One of them is the Kabul‐Kandahar‐Heart road, which is approximately 600 km. The other  is  the  Kanhdar‐Spin  Boldak  Road extending  to Pakistan, which  is about 180 km. 

There  are  about  100  km  of  city  roads  of which approximately 30 km are paved by asphalt  and  the  remaining  70 km  are not yet paved. 

The  following  are  the  roads  selected  for urgent rehabilitation: 

1) 6.0‐km  By‐pass  Road.  This  by‐pass road  is  formed  by  five  roads  with  a total length of 6.0 km. Many trucks use this road, which serves as a by‐pass of the existing national highway running through  the  city  centre.  Most  of  the sections  of  this  by‐pass  road  are  not paved. 

2) Kabul‐Kandahar  Road.  The  Study Team decided  to  rehabilitate  this  road from  5  km  point  to  20  km  point  to meet the growth of long‐haul traffic. 

3) 2.3‐km  City  Road.  This  road  passes from  the  city  centre  to  Mirwais Hospital.  Many  people  go  to  the hospital by vehicle, are dropped off  in front of the hospital, and later wait for their  rides  in  front  of  the  hospital. There  are  also  many  buildings  that house donor agencies and NGOs along this  road.  With  traffic  being  busy throughout  the  day  and  considering the  unpaved  condition  of  the  road,  a large amount of dust  is generated and becomes a serious problem. 

Planning and design of the first two roads were  commenced  from  September  2002, and  the  implementation was  started  from December  2002.  Three  months  after  the URSP‐KDH  began,  rehabilitation  of Kabul‐Kandahar road was completed and in  September  2003,  construction  of  the 6.0‐km by‐pass road was completed. 

2.4  Sanitation Sector 

Solid waste  of Kandahar  city  is  classified as  scrap  of  sundry  bricks  and mud  from construction  sites,  agro‐wastes  including kitchen waste, plastics and night soil from houses. The garbage is not removed totally and much  remains  on  the  roadsides  and gutter. 

Kandahar has no solid waste management plan  and  the  trucks used  to  collect waste are  old  and  dilapidated.  The  problem  of solid  waste  is  adversely  affecting  the environment  as well  as  the  health  of  the urban population of the municipality. 

Based  on  the  estimations  of  the  Study Team, it was decided to supply the urgent need of three trucks for waste collection to Kandahar municipality.   

Page 13: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (5)

3. CONSTRAINTS AND MEASURES TO IMPLEMENT THE URGENT REHABILITATION PROJECTS

The URSP‐KDH Project Team had  to  face challenges  presented  by  the  following constraints  during  the  course  of implementation.  The  corresponding measures taken to deal with them are also given  below. Obviously,  there were  some things that the Project Team members  just had to cope with the best they could. 

• Contractorʹs absolute  lack of  financial capacity to sustain project cash flow.   

This  matter  was  taken  care  of  by cancelling advance payments and 10% retention  was  applied  from  each payment instead of a bank guarantee. 

• Limited ability of local contractors. 

The  CMS  Team  arranged  on‐the‐job training for concrete mixing, sampling specimen of concrete cube, slump test, re‐bar  arrangement,  form works  and so  on.  Furthermore,  the  CMS  Team provided detailed drawings and shop drawings  for  the  construction  works to local contractors for easy reference. 

• Lack of skilled labourers   

Foreign  workers  were  hired  for  jobs that required advanced skills. But  the consequence  is that construction costs become  inflated  because  wages  for skilled labour goes up. This constraint affected construction schedules. 

• Unstable  price  of  construction materials. 

The  CMS  Team  set  up  a  special advanced payment arrangement to be able  to  keep  an  adequate  stock  of construction material. 

• Rising  temperatures  during  the months  of  June‐August  that  could adversely affect concreting works.   

The  temperature  of  concrete  casting was  carefully and  frequently  checked at the site during the summer season. 

The  concrete  compression  testing equipment  brought  in  by  the  CMS Team  was  used  to  check  the  actual concrete  strength  of  the  concrete  test pieces  from  every  site. The one‐week concrete  strength  and  the  four‐week concrete strength were checked by the test  machine,  and  the  proper measures were  executed  to  solve any insufficient  grade  of  the  concrete casting. 

• Lack of banking system in Kandahar. 

• Unstable  security  situation  in Afghanistan 

Note:  The  building  the  capacity  of contractors  and  adopting  a multi‐criteria approach  to  contractor  selection  (ex.  cash flow  management,  project  portfolio,  and organizational  abilities)  are  key  to  the satisfactory  outcome  of  the  Urgent Rehabilitation Projects implementation. 

 4. SCHOOL MAINTENANCE

IMPROVEMENT PROGRAMME

The  construction  and  rehabilitation projects  were  complemented  by  a  soft component  of URSP‐KDH  named  School Maintenance  Improvement  Programme. The programme sought to enable teachers, students  and other  stakeholders  to utilise the  rehabilitated  school  facilities effectively;  to  establish  a  maintenance system  for  the  effective  use  of  school facilities in Kandahar city; and to improve the hygiene conditions in the community. 

The main  components  of  the  programme were: 

Component  1:  Study  of  an  appropriate maintenance system for school facilities in Kandahar city 

Page 14: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (6) 

Component  2:  Training  on  operation  and maintenance of the school facilities 

Component 3: Hygiene education 

The  Study  Team  subcontracted  the programme  to  a  capable  international NGO  named  International  Catholic Migration  Commission  (ICMC)  as  the implementing  partner.  Training  courses were  conducted  at  three  schools:  namely, Ahmad  Shah  Baba  School,  Zahir  Shahi School, and Malalai School.   

The Department of Education  (DOE) was involved  in  the  programme  because  it  is expected  to play  a key  role  in  expanding the programme to all schools in Kandahar city in the future. 

4.1  Results of the Programme 

• The interviews and group discussions carried  out  by  ICMC  under Component  1  all  pointed  out  lack  of resources  as being  the major obstacle to  proper  maintenance  of  schools. Taking  this  into  consideration,  the ICMC  proposed  a  maintenance  plan to  cover  their  lack  of  resources  that emphasised  the  importance  of community  involvement,  school initiative  to  undertake  minor maintenance  activities,  and maintenance training.   

There were  36  teachers  and  students  that attended  Component  2.  They were  there because  they  are  expected  to  be responsible  for  maintenance  activities  in their  schools.  The  training  curriculum covered  the  “why’s”  and  “how’s”  of maintenance,  the  use  of  maintenance tools/materials,  and  budgeting,  among other  important  topics.  Trainees  were provided  maintenance  kits  for  a  better understanding of topics under discussion. 

A  total  of  36  participants  comprising headmasters,  teachers,  and  students were taught proper hygiene under Component 

3.  Besides  personal  hygiene,  the training‐seminar  covered  such  areas  as drug  abuse,  proper  use  of  toilets,  and importance  of  daily  habits  and  clean environment  for  good  hygiene.  Training handouts prepared by “Save  the Children Alliance”  in  Kabul  and  UNICEF  were distributed to the attendees. 

4.2  Conclusion and Recommendations 

According to the observation by the Study Team  in  January  2005,  the  three  schools are  implementing  the  programme  on maintenance,  hygiene,  and  keeping  the facilities  clean,  despite  some  problems. The  proposed  maintenance  plan,  on  the other  hand,  has  been  mentioned  by  the DOE  staff  since  its  submission. However, the plan has not been institutionalised as a maintenance system of DOE yet because of the  frequent  replacement of directors and lack  of  their  support.  It  is  necessary  for DOE  to  integrate  the  plan  into  its maintenance system.  5. EVALUATION OF URGENT

REHABILITATION PROJECTS

This  chapter  brings  together  the comprehensive  evaluation  for  all  projects and  consolidates  future  aid  activities  in post‐war Afghanistan.   

Government  policy  and  peacebuilding needs to play a large part in the evaluation of the Urgent Rehabilitation Projects. With that  in  mind,  it  can  be  said  that  the projects are relevant, that they contributed to  not  only  increasing  the  number  of facilities but also  recovering  the  functions of schools and medical institutions. To the people  of  Kandahar,  the  projects,  which were  completed  in  a  relatively  short amount  of  time,  were  visible  proof  of positive  changes giving  them  a  feeling of hope.   

Page 15: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (7)

A  summary  of  the  evaluation  of  urgent rehabilitation projects is given in the Table below. 

5.1  Education Sector 

The  situation  of  the  Education  Sector  is much  improved  by  the  additional  98 classrooms  built  by  the  Urgent Rehabilitation  Projects,  even  though problems  still  exist  such  as  double/triple sessions,  overcrowded  classrooms  and tent classrooms. 

There are  concerns  that bad behaviour of students may  have  caused  some  damage in  the  completed  school  facilities  like broken  handles,  desks  and  toilet  flushes. Teachers  and  parents  can  meet  for discussion  of  this  issue  and  teachers  can give  some  guidance  to  parents  in  order that  they  will  impact  their  children.  In addition,  teachers  and older  students  can help  through  monitoring  of  the maintenance activities. 

The  Study  Team  also  found  that  some schools have decided to use the additional rooms  differently  from  their  original design  in  order  to meet  their  needs,  the number of pupils and shifts they have, and their syllabus and curriculum. 

5.2  Health Sector 

The  newly  renovated  kitchen  facility  and laundry  room  have  tremendously improved  services  and  sanitation  in Mirwais Hospital.  There  are  better meals served  to patients, and  linens are washed by  washing  machines  with  hot  water rather  than  by  hand.  It  is  recommended, however, that Mirwais Hospital establish a “preventive  maintenance  system”  for sustainable use of the facilities. Training of managers  as  well  as  staff  on  hospital management may  have  to  be  considered as well. 

5.3  Road Sector 

The road paving project  in Kandahar city, which  involves  a  6  km  by‐pass  road, recently named Ogata road, has drastically improved road and traffic conditions. Now, Kandahar Municipality has started to pave other roads on  their own  to create a good environment  and  smooth  flow  of transportation. 

5.4  Sanitation Sector 

The trucks travel more than 75 km per day collecting  and  disposing  of  garbage  in Kandahar  city.  However,  it  is  still necessary for the municipality to establish a solid waste management programme. 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 16: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (8) 

Evaluation Summary of the Urgent Rehabilitation Projects 

Evaluation Items 

Rehabilitation of seven schools and Soft Component 

Renovation of kitchen and laundry at Mirwais Hospital 

Commuter Buses 

Pavement of City Roads 

Garbage Trucks 

Relevance    Meet the NDB and huge needs of classrooms in Kandahar City 

  Meet the NDB and needs of Improved Equitable Distribution of Quality Health Services 

  Meet the NDB and needs of Improved Equitable Distribution of Quality Health Services 

  Meet the NDB and needs of urban infrastructure 

  Meet the NDB and needs of Urban Planning & Management 

Effectiveness    Constructed 98 classrooms accommodating pupils who were in temporary classrooms (tents)   More than 18,000 

students (including 4,500 girls) can study at the constructed classrooms   Teachers have positive 

ideas for maintenance of school facilities 

  Improvement of food services and hygiene condition in the hospital   Kitchen provides 

meals for 410 (300 inpatients and 110 duty staffs)   More than 180 linens 

and gowns are washed by provided washing machine 

    72 female students and 16 female teachers are using the provided 5 commuter buses.

  6.0‐km By‐pass road and 2.3 km road was paved   Creation of 

the smooth transportation   Reduction of 

clouds of sand dust caused by the vehicular traffic. 

  3 trucks collect garbage in Kandahar city running 75km/day/each

Efficiency    There were delays of construction or implementation due to unstable security conditions   Scale and design of 

school building seem to be over local capacity (capacity of local contractors was insufficient) 

  There were delays of construction or implementation due to unstable security condition 

  There were delays of distribution due to unstable security condition 

    There were delays of construction due to unstable security condition 

  There were delays of distribution due to unstable security condition 

Impact    Increase enrolment and attendance of pupils   Capacity building of 

local contractors through construction works   Generate employment 

  Renovated dining room is used as place for workshops which are conducted by donors and government agencies   Capacity building of 

local contractors through construction works   Generate employment

  ‐    Reduce dust   Capacity 

building of local contractors through construction works   Generate 

employment 

  ‐ 

Sustainability    Maintenance of school buildings seems to be insufficient   Some of facilities are 

broken especially in toilet 

  Insufficient use of renovated dining room     Some provided 

machines are broken sometimes 

  There is an out of operation bus due to lack of budget 

  Kandahar municipality continues to pave city roads by its own initiative 

  UN Habitat supports Municipality financially 

Quick Response 

  Yes    Yes    Yes    Yes    Yes 

Visibility    Yes    Yes    Yes    Yes    Yes 

Page 17: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

Executive Summary 

       

URSP-KDH Final Report Part 2 (9)

5.5  Recommendations 

The Study Team faced many challenges in the URSP‐KDH projects experience.  It has therefore  come  up  with  the  following recommendations  by  group  for  better project implementation in the future. 

1)  For  the  Stakeholders  of  URSP‐KDH Projects 

• To share their experience and provide facilities to other projects/programmes in the future; 

• To  establish “Preventive Maintenance System”  for  better  maintenance  and sustainable  use  of  the  constructed facilities  and  provided  equipment, and to perform regular monitoring; 

• To be involved in the planning, design and  implementation  phases  to enhance  sense  of  ownership  of  and responsibility  to  the  rehabilitated facilities,  and  to  hold  regular stakeholder  meetings  before implementation  to  discuss  the activities and maintenance issues after construction   

2)  For  the  Local  government  in Kandahar 

• To  take  the  initiative  for reconstruction  and  development  of the region;   

• To  participate  in  the  process  of planning, monitoring  and  evaluation to secure sustainability of the projects; 

• To  enhance  its  institutional  capacity especially  for monitoring,  accounting and management  by  inviting  foreign experts  and  participating  in domestic/overseas training.   

3)  For Donors 

• To  decide  the  scale  and  design  of support  projects  considering  capacity of  counterparts,  national  staff,  and local contractors or NGOs; 

• To secure quality, in the strictest sense, in  construction,  training,  and institutional building; 

• To  collaborate  on  the  different schemes  of  donor  support  such  as dispatching  experts,  grant  aid,  and overseas  training  to  succeed  in  the outcomes of URSP‐KDH; 

• To  place  in‐house  consulting engineers  (CEs)  in  the  country  office instead  of  bringing  in  CEs  from abroad,  for  quick  and  flexible response;   

• To exercise  flexibility  in project scope to respond to changing situations. 

• To  increase  their  security  information gathering  capacity  to  reduce  risks, because security is the most important issue for aid workers. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 18: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

- i -

Table of Contents for URSP‐KDH Report Part 2 Final Report on the Urgent Rehabilitation Projects 

Preface Letter of Transmittal Map of Southern Region of Afghanistan / Location Map of Urgent Rehabilitation Project in Kandahar City 

History of URSP‐KDH Abbreviation List 

EXECUTIVE SUMMARY 

  Page 

CHAPTER 1  INTRODUCTION ..........................................................................................  1 ‐ 1 

1.1.  Background ...............................................................................................................  1 ‐ 1 1.2.  Scope of URSP‐KDH................................................................................................  1 ‐ 2 1.3.  Formulation of the Urgent Rehabilitation Programme.......................................  1 ‐ 2 1.4.  Selection of the Urgent Rehabilitation Projects ....................................................  1 ‐ 3 1.5.  Implementation of the Urgent Rehabilitation Projects........................................  1 ‐ 3 

CHAPTER 2  IMPLEMENTATION OF URGENT REHABILITATION PROJECTS .................  2 ‐ 1

2.1.  Approach and Methodology for the Implementation.........................................  2 ‐ 1 2.2.  Education Sector .......................................................................................................  2 ‐ 2 

2.2.1.  Overall View of the Education Sector ......................................................  2 ‐ 2 2.2.2.  Selection of the Projects ..............................................................................  2 ‐ 5 2.2.3.  Post‐Implementation Review of Selection Criteria.................................  2 ‐10 2.2.4.  Design Policy and Concept ........................................................................  2 ‐13 2.2.5.  Determination of Facility Scale..................................................................  2 ‐16 2.2.6.  Contractual Arrangement ..........................................................................  2 ‐19 2.2.7.  Implementation of the Projects .................................................................  2 ‐20 2.2.8.  Operation and Maintenance ......................................................................  2 ‐24 2.2.9.  Workshop on Effective School Management...........................................  2 ‐25 

2.3.  Health Sector .............................................................................................................  2 ‐27 2.3.1.  Overall View of the Health Sector ............................................................  2 ‐27 2.3.2.  Selection of the Projects ..............................................................................  2 ‐33 2.3.3.  Design Policy and Concept ........................................................................  2 ‐34 2.3.4.  Contractual Arrangement ..........................................................................  2 ‐34 2.3.5.  Implementation of the Projects .................................................................  2 ‐35 2.3.6.  Operation and Maintenance ......................................................................  2 ‐37 

2.4.  Road Sector................................................................................................................  2 ‐37 2.4.1.  Overall View of the Road Sector ...............................................................  2 ‐37 

Page 19: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

- ii - 

2.4.2.  Selection of the Roads.................................................................................  2 ‐40 2.4.3.  Design Policy and Concept ........................................................................  2 ‐40 2.4.4.  Implementation of the Projects .................................................................  2 ‐41 2.4.5.  Operation and Maintenance ......................................................................  2 ‐42 

2.5.  Sanitation Sector .......................................................................................................  2 ‐42 2.5.1.  Overall view of Sanitation Sector/ Garbage of Kandahar City .............  2 ‐42 2.5.2.  Selection of the Project................................................................................  2 ‐44 2.5.3.  Design Policy and Concept ........................................................................  2 ‐44 2.5.4.  Implementation of the Project ...................................................................  2 ‐45 2.5.5.  Operation and Maintenance ......................................................................  2 ‐45 

CHAPTER 3  CONSTRAINTS AND MEASURES TO IMPLEMENT THE URGENT REHABILITATION PROJECTS.......................................................................  3 ‐ 1 

3.1.  Introduction...............................................................................................................  3 ‐ 1 3.2.  Constraints ................................................................................................................  3 ‐ 3 3.3.  Measures Against the Constraints .........................................................................  3 ‐ 5 3.4.  Conclusions and Recommendations......................................................................  3 ‐ 7 

CHAPTER 4  SCHOOL MAINTENANCE IMPROVEMENT PROGRAMME (SOFT COMPONENT)...................................................................................  4 ‐ 1 

4.1.  Introduction...............................................................................................................  4 ‐ 1 4.2.  Scope of the Programme..........................................................................................  4 ‐ 1 4.3.  Implementation of the Programme........................................................................  4 ‐ 2 4.4.  Conclusions and Recommendations......................................................................  4 ‐ 4 

CHAPTER 5  EVALUATION OF URGENT REHABILITATION PROJECTS ..........................  5 ‐ 1 

5.1.  Introduction...............................................................................................................  5 ‐ 1 5.2.  Rationale ....................................................................................................................  5 ‐ 1 

5.2.1.  Conflict Prevention .....................................................................................  5 ‐ 1 5.2.2.  Government Policy......................................................................................  5 ‐ 2 

5.3.  Evaluation of Urgent Rehabilitation Projects .......................................................  5 ‐ 3 5.4.  Seminar on URSP‐KDH...........................................................................................  5 ‐ 7 5.5.  Recommendations ....................................................................................................  5 ‐ 8 

Page 20: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

 

   

1-1

CHAPTER 1 

INTRODUCTION 1.1. Background 

After  the  collapse of  the Taliban  regime,  the Afghan people have been  struggling  to reconstruct  Afghanistan  in  collaboration  with  the  international  community.    The international  community  agreed  to  seriously  address  the  urgent  rehabilitation  and reconstruction  of  the  country  by  pledging  financial  assistance  amounting  to  about US$ 4.5 billion over  two and a half years as  the  transitional period.    The pledge was made at the International Conference on Reconstruction Assistance to Afghanistan held in January 2002 in Tokyo.   

Accordingly,  the Government of  Japan  (GOJ) pledged  to share  financial assistance of US$ 500 million for the said period particularly for urgent humanitarian assistance  in the sectors of education, health and medical care, resettlement of repatriated refugees, landmine clearance, and empowerment of women. 

Japan  International  Cooperation  Agency  (JICA)  has  conducted  the  Urgent Rehabilitation  Support  Programme  (URSP)  since  April  2002.    The  first  URSP  was commenced under the chaotic situation in Kabul immediately after the collapse.    The URSP quickly responded to the changeable needs in the post‐conflict situation in Kabul city  including  situation  analysis,  establishment  of  short‐term  rehabilitation  plans  in several sectors, urgent rehabilitation for roads, school buildings and medical facilities, broadcasting of the Emergency Loya Jirga, teacher training and so on.   

Following  the  commencement of URSP‐EHB and URSP‐SWPT  in Kabul,1  the Urgent Rehabilitation  Support Programme  in Kandahar  (hereinafter  called  “URSP‐KDH”  or simply  “Programme”)  was  formulated  to  cover  Kandahar  city  (the  centre  of  the south‐western  region  of  Afghanistan)  according  to  the  Implementing  Arrangement (IA)  agreed  upon  by  the  Afghan  Assistance  Coordination  Authority  (AACA), Kandahar  Provincial  Government,  Ministry  of  Planning  and  Ministry  of Reconstruction of the Afghanistan Islamic Transitional Authority (ATA) on 8th August 2002. 

URSP‐KDH includes the following projects/programme: (1)  Establishment of Urgent Rehabilitation Programme   (2)  Implementation of Urgent Rehabilitation Projects 

                                                      1  Urgent Rehabilitation Support Programme in Afghanistan – Education, Health and Broadcasting Sectors (URSP‐EHB), Duration: April  2002  – August  2004,  and Urgent Rehabilitation  Support Programme  in Afghanistan  – Rehabilitation  Study  for  South‐Western Area &  Public Transportation  Study  of Kabul (URSP‐SWPT), Duration: July 2002 – February 2003. 

Page 21: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

1-2

Under  the  existing unstable  and  changeable  situation,  it might be difficult  to  set up quantitative  or  qualitative  data  to  justify  project  formulation  or  feasibility.   Nevertheless, the Study Team tried to plan or design the urgent rehabilitation projects based  on  the  available  very  limited  information  for  better  project  formulation  and implementation. One of  the objectives of  this  report  is  to present  the  challenges and struggles of post‐conflict reconstruction in Afghanistan and their lessons. 

1.2. Scope of URSP‐KDH 

Along the line of the commitment made by the GOJ, the Programme aims at realizing the earlier implementation of URSP‐KDH, with the scope as follows: 

• Establishment  of  Urgent  Rehabilitation  Programme  to  formulate  a  short‐term rehabilitation programme covering not only the physical infrastructure sectors but also  other  pertinent  sectors,  so  that  the  urgent  rehabilitation  projects  should  be rightly  positioned  and  seamlessly  sustained  towards  future  reconstruction  and development   

• Implementation  of  Urgent  Rehabilitation  Projects  to  rehabilitate/reconstruct damaged and destroyed facilities and structures, especially roads, educational and medical facilities 

1.3. Formulation of the Urgent Rehabilitation Programme 

The urgent rehabilitation programme  is a support strategy and a  list of rehabilitation and  development  projects  for  Kandahar  region  recommended  by  the  Study  Team.   The  programme  is  expected  to  be  utilised  as  a  strategic  support  framework  to  the region, formulating projects and programmes, which will be supported and funded by donor agencies. 

Considering  the National Development Framework  (NDF) prepared by  the Board of AACA, discussions for the regional rehabilitation by the local government, donors and NGOs, and Japan’s assistance policy for Afghanistan, the following five pillars can be set as essential support strategy to Kandahar region: 

• Responding transition from relief, rehabilitation to development 

• Building efficient institutions 

• Enhancing regional stability 

• Creation of sustainable livelihoods 

• Promoting equality between urban and rural as well as regions 

Page 22: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

1-3

Proposed Urgent  Rehabilitation  Programme  is  described  in  the  Final  Report  Part  1 published in February 2003 by the Study Team. 

1.4. Selection of the Urgent Rehabilitation Projects 

In  order  to  achieve  expeditious  implementation,  the  Study  Team  divided  urgent rehabilitation projects  into  two components, namely batch 1 and batch 2.    The Study Team selected proposed projects for education, health, and road sectors during the first field survey as Batch 1 Component.    For Batch 2 Component, the Study Team selected proposed  projects  linked  with  the  Urgent  Rehabilitation  Programme,  and  in coordination  with  other  donors’  activities.  Table  1.1  lists  the  Urgent  Rehabilitation Projects. 

Table 1.1 Urgent Rehabilitation Projects 

Sector  Batch 1 Component (from Sep 2002)  Batch 2 Component (from Nov 2002) Education  Construction of   

• Ahmad Shah Baba High School (including rehabilitation of a destroyed roof) 

• Zahir Shahi High School • Malalai High School 

Construction of • Sufi Saheb High School • Aino Middle School • Kaka Sayed Ahmad School • Mirwis Mena School 

Health  • Rehabilitation of building and supply of new equipment for kitchen and laundry in Mirwis hospital   

• Supply 5 commuter buses for the Kandahar Nursing School   

Road  • Construction of 6.0 km By‐pass City Road 

• Rehabilitation of Kabul‐Kandahar Road (K‐K Road) 

• Construction of 2.3 km City road reaching from the city centre to the Mirwis Hospital. 

Sanitation    • Supply 3 cargo vehicles for collecting solid waste for Kandahar Municipality   

1.5. Implementation of the Urgent Rehabilitation Projects 

(1)  Batch 1 Component 

Planning and design was commenced  from September 2002, and  the  implementation was  started  from December 2002.    Just  three months after  the URSP‐KDH began,  in March 2003, projects of  the  rehabilitation of Mirwis hospital and  the K‐K Road were completed.    Construction of  the school buildings and  the 6.0 km By‐pass Road were completed in May 2004 and September 2003, respectively. 

Page 23: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

1-4

(2)  Batch 2 Component 

Commuter  Buses  for  Kandahar  Nursery  School  and  Cargo  Trucks  for  Kandahar Municipality were delivered  in  June 2003.    Construction of  the school buildings and the 2.3 km Road were started from June 2003.    The road was completed in September 2003 and the school buildings were completed in September 2004. 

(3)  Soft Component 

The Study Team conducted the School Maintenance Improvement Programme as a soft component programme.    The purpose of  the programme was  effective utilisation of the school facilities that were rehabilitated/reconstructed by the Urgent Rehabilitation Projects. The programme was  implemented  from August  to November 2003 after  the completion of the construction of school buildings under the Batch 1 Component. 

 

 

 

 

 

 

 

 

 

 

 

Figure 1.1 Schedule of Implementation of Urgent Rehabilitation Projects 

 

2002 2003 2004 2005

Sep. Dec.Jan. Dec.Jan. Dec.Jan. Mar.

Batch-1 ComponentBasic DesignDetailed DesignCost Estimate

Tender / Tender EvaluationSite Preparation

Construction & Renovation Work

Batch-2 ComponentBasic DesignDetailed DesignCost Estimate

Tender / Tender EvaluationSite Preparation

Construction

Installation of Farniture

Supply of Vehicles

Soft ComponentInstallation of Farniture

△ △ △ △ △IC/R PR/R IT/R DF/R F/RReporting

Ramadan

Winter

Ramadan

Winter

Ramadan

Winter

Page 24: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

 

   

2-1

Chapter 2 Implementation of   

Urgent Rehabilitation Projects 2.1. Approach and Methodology for the Implementation 

The construction industries in Afghanistan were completely devastated, both in terms of human  resources  and  technical  expertise  along with  the destruction  of  their  own construction equipment.    After collapse of Taliban  regime, many Afghan contractors who escaped to the neighbouring countries, have come back to Afghanistan and begun works.    However  their  skill  tends  to  be  insufficient  for  the  huge  demand  for reconstruction of country because of  lack of experienced engineers and technicians as well as their low financial capacity. 

In September 2002,  the provincial government of Kandahar  focused on  rehabilitation and  rebuilding  activities  assisted  by  international  donor  agencies.    Their  goal  is  to revive  the destroyed economy of  the region.   However,  international donor agencies have  faced problems  in  that  the progress and quality of  their activities had not been appropriate  in accordance with  their  specifications, although  they  employed Afghan contractors to implement the works.    Thus, there is the need to strengthen the capacity of Afghan contractors in parallel with implementation of rehabilitation and rebuilding activities. 

As  part  of  the  project,  the  Study  Team  has  employed Afghan  contractors  and  local engineers for the rehabilitation works such as rehabilitation of seven selected schools, Mirwis Hospital, the roads, and so on.    To implement the urgent rehabilitation project in Kandahar and provide extra technical training which is missing in Afghanistan, the Study Team organized the CMS (Construction Management Services) team.    The team plans  not  only  to manage  and  supervise  the work  of Afghan Contractors,  but most importantly,  to  train  the  Afghan  engineers  through  “On‐the‐job  training”  such  as leveling, marking,  and  concrete mixing  to  assure  that  the  quality  of  their work  is maintained in accordance with contract the documents. 

 

Page 25: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-2

2.2. Education Sector 

2.2.1. Overall View of the Education Sector 

(1) General 

By  any  statistical  measure,  the  educational  system  in  Afghanistan  was  seriously undermined  by  more  than  20  years  of  war.    A  UNESCO  report 1   showed  that Afghanistan’s education indicators were among the worst in the world, with girls and rural  populations  had  been  particularly  disadvantaged.    Even  before  the  war,  the gross enrolment rates (GER) for boys and girls at the primary level were 54% and 12% respectively.    This was especially in the southern region such as Kandahar, given that girl’s enrolment was negligible even prior to the Taliban regime.    During the 6 years of Taliban regime, educational standards clearly deteriorated as girls and female teachers were not allowed  in schools, nothing secular was allowed to be taught  in educational institutions, and most schools were essentially converted  to  religious  schools  leaving no  room  for  school  rehabilitation or  teacher development or  training.    In  fact,  there was only one formal school called “Shpay Lyee School” in Kandahar. 

It  is  widely  recognized  that  the  situation  of  the  education  sector  infrastructure  in Afghanistan, as a whole, and within Kandahar,  in particular, was quite dismal.    The more  than  20 years of war  either badly damaged or destroyed  almost  all  schools  in Kandahar.    As  the situation worsened, many good  teachers  left  the country  in hopes of getting  jobs  in  the  refugee camps where  international NGOs were  financing some type of schooling for refugee children. 

However,  after  the  September  11  attack, when  the  Taliban  regime  fell  and  donors flocked  into Afghanistan,  education  became  a  priority  issue  for  all,  including  local NGOs  and  the  interim  government  of Afghanistan.    A  large  number  of  children  of school  age  and  available  teachers  went  back  to  school  since  the  Back‐to‐School Campaign2  commenced  in March 2002.    Considering  the natural population growth and rapid inflow of refugees into the cities, it was likely that Kandahar city would face a need  for  thousands of additional classrooms by year 2004 based on  the number of destroyed  classrooms,  plus  the  accelerated  population  growth  due  to  returning refugees.    The  latest  information  showed  that  894,020  girls were  attending  classes, making up 30% of  the  total number of pupils  in Afghanistan as a whole.    The  ratio between girls and boys was relatively similar across the country.    However there were some differences between  certain  sectors  of Afghanistan  –  in Kabul,  girls  enrolment 

                                                      1  UNESCO, EFA (2000) Afghanistan Draft Final Report 2  Back‐to‐School Campaign: Spear‐headed by UNICEF and financed by several donor agencies, including 

the GOJ, aimed to bring a large number of children of school age and available teachers back to schools. The campaign has supported school‐age children and teachers in Kandahar since its commencement, although the new school year in Kandahar started on 7th September 2002. 

Page 26: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2  

   

2-3

made up over  40% of pupils, while  in Kandahar  rates were  just  10% of  the  student population.    Although Kabul  established  a  co‐education  system which  include  girls and boys from grades 1 through 6, Kandahar had co‐education school only for grades 1 through  3;  there was  not  enough  school  capacity  for  girls.    Nonetheless,  given  that girl’s enrolment was negligible in the southern region even prior to the Taliban regime, some comfort should have been taken from these figures.    According to a World Bank report3,  the primary gross enrolment  rate was estimated as 43%  for boys and 3%  for girls. 

As  the  number  of  students  and  teachers  increased,  the  educational  infrastructure needed to be rehabilitated on urgent basis in Kandahar city.   Most donor agencies and NGOs that were working in Kandahar city made school rehabilitation a priority so that students and  teachers could have  some  shelter.    Although a  lot  remains  to be done, signs  of  progress  in Kandahar  city were  obvious,  and  slowly  but  surely  the  city  is coming back to life. 

The  following  section  provides  a  summary  of  situation  at  that  time  and  available statistics  (however  not  completely  reliable)  for  primary  and  secondary  education  in Kandahar city and  lay out  the basis for  the Education Rehabilitation Programme and future intervention by stakeholders. 

(2) Primary and Secondary Education 

1) School Facilities in Kandahar 

It was said that some 2,000 schools were destroyed during the turmoil in Afghanistan and  there was a vast need  for school rehabilitation and reconstruction everywhere  in the  country.    In Kandahar  province,  there were  211  schools.    An  estimated  80%  of school buildings at all levels were damaged or destroyed due to more than 20 years of conflict.    Particularly,  the  surrounding  area  of  Kandahar  city  was  more  heavily damaged  and  destroyed.    Table  2‐1  shows  the  damage  levels  of  the  schools  in Kandahar province at that time.    Table 2‐2 shows the results of the Rapid Assessment of Learning Spaces in Afghanistan (RALS) implemented by UNICEF in June 2002. 

Table 2‐1  Damage Level of School for Kandahar Province Level  1  2  3  4  5  N/A 

No. of School  33  51  29  24  65  9 Source:  UNICEF, Kandahar, * Damage Level: Level 1 ‐ Minor cosmetic repair only, Level 2 ‐ Minor damage only, Level 3 ‐ Partially destroyed building, Level 4 ‐ Mostly destroyed building,   Level 5 ‐ Completely destroyed 

                                                      3  World Bank (2002) Technical Annex for an Emergency Education Rehabilitation and Development 

Project 

Page 27: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-4 

Table 2‐2  Summary of Second School Assessment for Kandahar Province   (As of July 2002) 

No.  Name of District  Total Number of Schools 

Total Number of Girl Pupils

Total Number of Boy Pupils

Total Number of Female Teachers 

Total Number of Male Teachers 

1  City  35  7,415  25,368  193  664 2  Panjwai  39  150  6,611  7  222 3  Dand  25  42  3,759  2  134 4  Arghandahb  16  6  4,300  0  125 5  Maruf  31  98  4,179  0  138 6  Arghistan  11  0  1,241  0  46 7  Spin Boldak  7  258  2,758  0  83 8  Maiwand  7  18  1,221  1  48 9  Nish  8  0  965  0  23 10  Shahwali  8  12  750  0  36 11  Khak Riz  6  0  695  0  25 12  Shiga  9  68  404  3  18 13  Daman  3  64  220  0  9 14  Ghorak  5  0  224  0  14 15  Mian Nishin  1  0  100  0  3 

Total  211  8,131  52,795  206  1,588 Source:    UNICEF Kandahar 

Several NGOs  and donor  agencies  started  rehabilitation of  schools  in Kandahar  city and  the  rehabilitation  work  is  at  various  stages  of  completion.    In  October  2002, UNICEF  and  other  concerned  donors,  in  collaboration  with  the  Department  of Education (DOE), decided to coordinate school rehabilitation efforts by preparing a list of schools where rehabilitation was needed and which donor was contributing to each school.    This list was updated on a regular basis to reflect the changing situation and time. 

2) Girls School 

As mentioned above,  formal education was strictly prohibited  for about 6‐7 years by the Taliban  government.    Students,  especially  girl  students had huge  gap  of  formal education.    There were eight schools in Kandahar city.    Zhainab, Kaka Sayde Ahmad, Aino Middle were closed for various reasons.    For example, in Zainab School, people had been  living  illegally  in  the school  facilities since  the school closed caused by  the prohibition of  the  female  education.    Even  though  the girls  schools  reopened,  some schools  tended  to  be  co‐educational  or  boys  schools.    In  addition,  there  were  no female students over 9th grade due to the huge gap created during the Taliban regime.   Table 2‐3 shows the situation of girls schools at that time in Kandahar city. 

Page 28: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2  

   

2-5

Table 2‐3  Profile of Girls Schools in Kandahar City   (As of September and December, 2002) 

Name    G‐1  G‐2  G‐3 G‐4 G‐5 G‐6 G‐7 G‐8 G‐9 G‐10 G‐11  G‐12  Total

M 730* (120)** 

1000 (100) 

100(120)

50 (60)

‐ (60)

‐ (60)

‐  ‐  ‐  ‐  ‐  ‐ 1880(520)Zhagona Ana 

Middle F 

300 (360) 

600 (980) 

100(120)

50 (60)

40( ‐ )

30( ‐ )

‐  ‐  ‐  ‐  ‐  ‐ 1120(1520)

M  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ Zhagona Ana High  F 

380 (210) 

880 (920) 

220(250)

220(150)

90(80)

45(50)

40(40)

20( ‐ )

‐  ‐  ‐  ‐ 1895(1700)

M 326 (194) 

424 (341) 

‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 750 (535)

Malalai High 

F 228 (244) 

238 (220) 

55 (70)

53 (50)

‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 574 (584)

M  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ Aeno High 

F 380 

(1500) 786 (25) 

137( ‐ )

120( ‐ )

40( ‐ )

25( ‐ )

15(23)

‐  ‐  ‐  ‐  ‐ 1503(1550)

M 825 (270) 

794 (590) 

200(130)

150(138)

50(50)

30(35)

20 20 ‐  ‐  ‐  ‐ 2089(1213)

Sufi Sahib High 

F 316 (120) 

295 (280) 

70 (20)

2 (2) 

‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 683 (422)

M 160 (130) 

519 (440) 

101(90)

59 (72)

19(32)

11(15)

13(15)

‐  ‐  ‐  ‐  ‐ 882 (794)Mirwis Mena 

High F 

56 (62) 

97 (88) 

25 (40)

26 (35)

‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 204 (225)

Source: URSP Team;                * Upper; Data in December, ** Lower; Data in September 

3) Learning and teaching materials 

Distribution of learning and teaching materials was completed to the primary sections of almost all schools in Kandahar city and was in progress in Kandahar province as a whole under UNICEF’s Back‐to‐School Campaign.    During  the  Study Team’s  school visits, it was found that, as the enrolment continued to increase on a daily basis, and so there was a lack of UNICEF kits for the newcomers.    As a result, schools were trying to maximise  the usage by asking  the old  students  to  share  stationeries with  the new students. 

2.2.2. Selection of the Projects 

(1) Batch 1 Component 

Given  the  circumstances  in  September  2002, URSP‐KDH  placed  great  emphasis  on coordination  with  other  agencies  involved  in  school  rehabilitation  in  the  city. Discussions with NGOs and donor agencies revealed that many of them are choosing to  help  schools with  relatively  lighter  damage  level  to  obtain  quick  impact  of  their inputs.    Therefore,  the  Study  Team  placed  more  emphasis  in  playing  a complementary role by placing priorities on heavily damaged schools or those schools that needed rebuilding or additional classrooms. 

Page 29: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-6 

The  Study Team  visited many  schools  to  see whether URSP‐KDH  could  cover  their rehabilitation  or  reconstruction,  but  it  seems  that  the  donors  and  local NGOs  have chosen almost all schools in Kandahar city.    Although international donors are doing a more  thorough  job, most NGOs  are  performing minor works  in  schools  such  as painting, installation of windows and doors, basic plastering and other minor repairs. 

The Study Team  focused on  the schools  that require more  than simple rehabilitation, and  they were  selected  as  the  target  sites.    After  discussions with DOE  and  other donors  in October  2002,  the  Study Team  set  criteria  for  the  selection of  schools  that were used in the final investigation as follows: 

• Damage degree/needs for reconstruction • Whether the school includes primary grades • Location of the school • Whether the school have enough students and teachers • Whether the classrooms were severely damaged • Whether they have access roads for rehabilitation /reconstruction activities • Whether there is available space for reconstruction • Whether the land is owned by the DOE • Whether the scale is feasible to consider as an urgent rehabilitation project. • Whether there are assistance in reconstruction/renovation from other donors • Gender equality • The number of existing classrooms • The number of shifts • Availability of water • Availability of latrine • Availability of fence • Availability of electricity 

The Study Team, together with dedicated personnel from DOE, visited sites proposed by DOE, as well as other schools in different districts within Kandahar city in order to find out how other donors and agencies are  implementing  the  construction projects.   The purpose of these visits was to assess technical practicability for construction work within a set timeframe. 

As mentioned above, although all schools were eligible for reconstruction  in  terms of rehabilitation/reconstruction  needs  and  according  to  the  above  criteria,  four  schools were dropped because,  among other  reasons,  they were  already given  assistance by other  donors.  The  final  list  included  one  girls  school  and  two  boys  schools  for reconstruction (see Table 2.1). 

In October 2002, the Study Team and DOE also organized school community meetings for all selected schools and parents of students, teachers and community leaders were 

Page 30: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2  

   

2-7

invited.    Discussions  emphasized  needs  for  construction  and  participants  possible contribution to schools. 

Given  the  needs  of  the  community,  the  Study  Team,  together  with  the  relevant personnel from DOE, carefully revisited each school to investigate needs and came up with  a  viable  school  construction/rehabilitation  option4.    In  accordance  with  the design needs, each school would be provided with the following: 

  Seismically sound school structure 

  Appropriate  number  of  rooms  (big  enough  to  accommodate  40  students  in  one room) 

  Two‐story  buildings  to  accommodate  an  increasing  demand while  having more playground space for children5 

  Fence/boundary wall6 

  Separate toilets for male and female students and teachers 

  Deep Well (water supply) 

On  that occasion,  at  least one of  the  schools  selected was holding  three  shifts,  since there was no  space  for  students  to  sit  in.    Given  the design of  the  school, based on sound  construction,  the  Study  Team  believed  that  it  would  lessen  the  burden  on students  and  teachers  in  terms  of  reduction  in  school  shifts  and  more  space  for students. 

As a result, the following three (3) schools were selected as the Batch 1 component.   

(i)  Zahir Shahi High School 

(ii)  Malalai High School 

(iii) Ahmad Shah Baba High School 

 

                                                      4  UNICEF has made a guidance note for school rehabilitation.    Facilities included in the note such as 

provision of water, toilets and boundary walls have been taken into consideration under URSP‐EHB. 5  A two‐story and strong structured building can be justified from viewpoint of long‐term needs and 

durability, and land use, although small‐scale building may be better as ‘urgent’ rehabilitation. 6  Boundary wall seems to be important to obstruct the view from outside of school, because it is necessary 

especially for female students to secure such space from an Afghan standpoint.   

Page 31: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

 

 

URSP-KDH Final Report Part 2 

2-8 

Table 2‐4 

School Selection Criteria – Batch 1 Component 

Zah

ir Sh

ah

Hig

h Sc

hool

Mal

alai

H

igh

Scho

ol

③ S

ufi S

ahab

H

igh

Scho

ol

④ Z

hago

na

Ana

Hig

h Sc

hool

⑤ Z

hago

na

Ana

Mid

dle

Scho

ol

⑥ S

hah

Hus

ain

Scho

ol⑦

Mirw

is

Min

a Sc

hool

Ahm

ad S

hah

Baba

Hig

h Sc

hool

1.

D

egre

e of

Dam

age/

Nee

ds

for r

econ

stru

ctio

n H

igh

(o

bvio

us la

ck

of c

lass

room

s)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

(obv

ious

lack

of

cla

ssro

oms)

Hig

h

2.

Gra

de L

evel

P

rimar

y,

Mid

dle,

Hig

h P

rimar

y,

Mid

dle,

Hig

h P

rimar

y,

Mid

dle

Prim

ary,

M

iddl

e, H

igh

Prim

ary,

M

iddl

e P

rimar

y,

Mid

dle

Prim

ary,

M

iddl

e P

rimar

y,

Mid

dle,

Hig

h 3.

Lo

catio

n

Dis

trict

6

Dis

trict

5

Dis

trict

6

Dis

trict

6

Dis

trict

6

Dis

trict

6

Dis

trict

6

Dis

trict

6

4.

Stat

us o

f cla

ssro

oms

Parti

ally

but

to

o m

any

stud

ents

ou

tsid

e

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Reh

abili

tate

d bu

t too

man

y st

uden

ts

outs

ide

Yes

5

Num

ber o

f st

uden

ts/G

ende

r (w

ith p

opul

atio

n m

ovem

ent S

ep-O

ct 2

002)

(as

of S

EP

14)

Tota

l: 64

00

M-T

: 72,

F-T

: 43

(as

of S

EP

16)

Boy

s:64

51(1

-12)

Girl

s: 2

52 (1

-3)

M-T

: 73,

F-T

: 37

(as

of S

EP

24)

Boy

s:62

49(1

-12)

Girl

s: 2

52 (1

-3)

M-T

: 73,

F-T

: 39

(as

of O

CT

2)

Boy

s:62

89(1

-12)

Girl

s: 2

75 (1

-3)

M-T

: 73,

F-T

: 42

(as

of S

EP

14)

Boy

s: 6

50

Girl

s: 5

00

M-T

: 18,

F-T

: 7

(as

of S

EP

16)

Boy

s: 4

50 (1

-3)

Girl

s: 4

78 (1

-4)

M-T

: 18,

F-T

: 11

(as

of S

EP

24)

Boy

s: 5

35 (1

-2)

Girl

s: 5

84 (1

-4)

M-T

: 16,

F-T

: 8

(as

of O

CT

2)

Boy

s: 5

19 (1

-2)

Girl

s: 7

30 (1

-4)

M-T

: 15,

F-T

: 9

(as

of S

EP

17)

Boy

s: 1

083

(1-6

)G

irls:

422

(1-4

) M

-T: 2

1, F

-T: 1

1

(as

of S

EP

16)

Boy

s: 0

G

irls:

170

0 (1

-7)

M-T

: 0, F

-T: 3

5

(as

of S

EP

16)

Boy

s: 9

00 (1

-4)

Girl

s: 1

140

(1-6

)M

-T: 3

, F-T

: 31

(as

of O

CT

5)

Boy

s: 0

G

irls:

0

M-T

: 0, F

-T: 0

(as

of S

EP

14)

Boy

s: 2

320

Girl

s: 1

80

M-T

: 24,

F-T

: 1

(as

of S

EP

17)

Boy

s: 1

729

(1-7

)G

irls:

72

(1-2

) M

-T: 2

9, F

-T: 1

(a

s of

SE

P 24

) B

oys:

163

7(1-

7)G

irls:

0

M-T

: 29,

F-T

: 0

(as

of S

EP

14)

Boy

s: 9

57

Girl

s: 1

20

(as

of S

EP

17)

Boy

s: 7

94

Girl

s: 2

25

M-T

: 28

F-T:

0

(as

of S

EP

17)

Boy

s: 1

765(

1-11

) G

irls:

0

M-T

: 50,

F-T

: 0

(as

of S

EP

24)

Boy

s: 1

925(

1-11

) G

irls:

0

M-T

: 50,

F-T

: 0

(as

of O

CT

5)

Boy

s: 2

224(

1-11

) G

irls:

0

M-T

: 50,

F-T

: 0

(as

of O

CT

9)

Boy

s: 2

304

1-11

) G

irls:

0

M-T

: 54,

F-T

: 0

6.

Acc

ess

road

for

reha

bilit

atio

n /re

cons

truct

ion

activ

ities

O

K

O

K

O

K

O

K

O

K

O

K

O

K

O

K

Page 32: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

 

 

2-9 

URSP-KDH Final Report Part 2

Zah

ir Sh

ah

Hig

h Sc

hool

Mal

alai

H

igh

Scho

ol

③ S

ufi S

ahab

H

igh

Scho

ol

④ Z

hago

na

Ana

Hig

h Sc

hool

⑤ Z

hago

na

Ana

Mid

dle

Scho

ol

⑥ S

hah

Hus

ain

Scho

ol⑦

Mirw

is

Min

a Sc

hool

Ahm

ad S

hah

Baba

Hig

h Sc

hool

7.

Sp

ace

avai

labi

lity

for

reco

nstru

ctio

n

OK

OK

OK

OK

OK

OK

OK

R

ecom

men

ded

for

reha

bilit

atio

n 8.

La

nd o

wne

d by

DO

E

OK

O

K

OK

O

K

OK

O

K

OK

. O

K.

9.

Feas

ible

sca

le fo

r urg

ent

reha

bilit

atio

n

OK

OK

OK

OK

OK

OK

OK

OK

10

. O

ther

don

ors’

ass

ista

nce

Non

e U

NIC

EF

has

reha

bilit

ated

ex

istin

g cl

assr

oom

s bu

t the

re a

re

still

man

y cl

asse

s w

ithou

t cl

assr

oom

s.

U.S

.A. h

as

reha

bilit

ated

ex

istin

g cl

assr

oom

s bu

t the

re a

re

still

man

y cl

asse

s w

ithou

t cl

assr

oom

s.

Turk

ish

Gov

. ha

s re

habi

litat

ed

exis

ting

clas

sroo

ms

but t

here

are

st

ill m

any

clas

ses

with

out

clas

sroo

ms.

Isla

mic

Rel

ief

has

reha

bilit

ated

ex

istin

g cl

assr

oom

s bu

t the

re a

re

still

man

y cl

asse

s w

ithou

t cl

assr

oom

s.

UN

ICE

F ha

s re

habi

litat

ed

exis

ting

clas

sroo

ms

but t

here

are

st

ill m

any

clas

ses

with

out

clas

sroo

ms.

UN

ICE

F ha

s re

habi

litat

ed

exis

ting

clas

sroo

ms

but t

here

are

st

ill m

any

clas

ses

with

out

clas

sroo

ms.

Non

e

11.

Gen

der

Boy

s S

choo

l G

irls

Sch

ool

Girl

s S

choo

l G

irls

Sch

ool

Girl

s S

choo

l B

oys

Sch

ool

Girl

s S

choo

l B

oys

Sch

ool

12.

No.

of e

xist

ing

clas

sroo

ms

40

9 12

19

15

13

9

35

13.

No.

of s

hifts

3

2 2

2 2

2 2

2 14

. Av

aila

bilit

y of

wat

er

Yes

Yes

No

Yes

Yes

Yes

Yes

Yes

15.

Avai

labi

lity

of la

trine

Ye

s (b

oys-

girls

to

geth

er)

Yes

Yes

(boy

s-gi

rls

toge

ther

)

Yes

Yes

(boy

s-gi

rls

toge

ther

)

Yes

(boy

s-gi

rls

toge

ther

)

Yes

Yes

16.

Avai

labi

lity

of fe

nce

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

17.

Avai

labi

lity

of e

lect

ricity

Ye

s Ye

s Ye

s Ye

s Ye

s Ye

s Ye

s Ye

s C

oncl

usio

n

S

elec

ted

S

elec

ted

N

ot S

elec

ted

N

ot S

elec

ted

N

ot S

elec

ted

N

ot S

elec

ted

N

ot S

elec

ted

S

elec

ted

Source: Study Team

Page 33: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-10 

(2) Batch 2 Component 

School  construction  projects  were  prioritised  among  the  Urgent  Rehabilitation Programme in the stakeholder meeting in December 2002.    Following the discussions, several schools were nominated as candidates of the project based on the request from the Kandahar provincial government.    URSP‐KDH, together with dedicated personnel from DOE, visited  the candidate sites, as well as other  schools within Kandahar city and surrounding areas of the city in order to find out how other donors and agencies were implementing the construction projects.    The purpose of the visits was to assess technical practicability for construction work within a set timeframe (by the end of year 2003).   

As a result, the following four (4) schools were selected as the Batch 2 component.   

(i)  Sufi Suhab School 

(ii)  Mirwis Mena School 

(iii) Kaka Sayed Ahmad School 

(iv) Aino Middle School 

2.2.3. Post‐Implementation Review of Selection Criteria 

For  the purpose of  future  implementation of “urgent rehabilitation”,  the Study Team evaluated the relevance of the selection criteria as follows: 

• Damage degree/needs for reconstruction 

The  Study  Team  chose  the  schools  whose  buildings  were  severely  damaged  or obviously lack of classrooms.    The conditions dictated they were unsuitable for proper school activities, and buildings were being used without any  repair or maintenance.   Compared  to other  school  renovation projects, which aimed  to  restore  them  to  their original  condition,  rehabilitation  of  those  selected  school  buildings  had much more impact and met the needs of educational activities.    In addition, visible rehabilitation gave positive impact to the people in the surrounding area which had become stagnant due to the effects of war. 

• Whether the school includes primary grades 

A  large  number  of  children  of  school  age  and  available  teachers  returned  to  their schools when the Back to School Campaign was spearheaded by UNICEF and financed by several donor agencies, including the government of Japan, which was commenced in March  2002.    As  the number  of  students  and  teachers  increased,  the  educational infrastructure,  especially  school  buildings  for  primary  grades,  needed  rehabilitation 

Page 34: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-11

and  construction  on urgent basis  in Kandahar  city.    Under  these  circumstances,  the support for primary grades was significantly important7. 

• Location of the school 

The Study Team selected the central area of Kandahar city as a target area, because the area  has  severe  problems  in  regard  to  school  activities, which  is  obviously  brought about by lack of classrooms, although some donors have rehabilitated most of schools.   On  the  other  hand,  the  Team  did  not  select  the  surrounding  area  of Kandahar  city where  there were  few  destroyed  schools,  since  the  Team  had  given  priority  to  the survey and support activities elsewhere. 

• Whether the school has enough students and teachers 

This criterion was very important; the number of students has increased since the first survey  in September 2002 as expected;  therefore,  it was seen  that  the  lack of  teachers might  cause  the  inefficiency  or malfunction  of  educational  activities.    However,  to provide enough classrooms for students is essential. 

• Whether the classrooms was destroyed severely 

This  criterion  is  almost  same  as  “Damage  degree/needs  for  reconstruction”,  it will better to delete for future project. 

• Whether they had assistance for reconstruction/renovation from other donors 

It  was  comparatively  easy  to  renovate  the  classrooms  that  were  damaged  lightly; therefore many  donor  agencies,  which  aimed  at  quick  impact,  had  prioritised  the renovation  of  those  schools.    But  the  Study  Team,  which  had  enough  capacity  to implement  technically difficult and  large construction works, had selected renovation and  reconstruction of schools, whose classrooms were damaged severely or students are having class under tents. 

• Whether there are access roads for rehabilitation /reconstruction activities 

• Whether there is available space for reconstruction 

It  is  indispensable for  large‐scale construction works to keep proper access and space around the construction site to prevent accidents and also to manoeuvre materials and machinery efficiently.    The Study Team checked carefully both access roads and space 

                                                      7  Especially in Kandahar, there were huge demand to enrol schools in primary level not only of children of primary level school ages but also of elder children who were deprived their educational opportunity during the war and the Taliban regime.   

Page 35: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-12 

around the schools for selection; consequently, no accident occurred in all sites during the construction works. 

• Whether the land is owned by the DOE 

The Study Team confirmed that all school sites are owned by DOE, so that there was no conflict or dispute concerning land ownership. 

• Whether the scale is feasible as an urgent rehabilitation project. 

The school buildings of the six schools were two‐story structures, and they contributed to  increase  the number of classrooms.    Reconstruction of school buildings should be considered not only urgent needs but also  long‐term needs, although, the URSP aims to respond urgent needs for improvement of educational environment.    Double story and  strong  structured  building  can  be  justified  from  view  of  long‐term  needs, durability  and  land  use,  although,  small‐scale  building  may  be  better  as  ‘urgent’ rehabilitation. 

• Gender equality 

The Study Team selected three schools for girls as Batch 1 and Batch 2 component for reconstruction  to  contribute  increasing  enrolment  rate  for  girls  in Kandahar.    As  of October  2002,  there were  approximately  1,300  female  students  enrolled  in  the  target schools. As  of  January  2005,  the  rehabilitated  schools  accommodated  approximately 4,500 girls in total. 

• The number of existing classrooms 

Several donors rehabilitated most of school buildings in Kandahar city.    Not only the numbers of students  in each school, but also, existing classrooms  that were available.   This was an essential factor for calculation and adjustment of  the number of planned classrooms. 

• The number of shifts 

Because of  the shortage of classrooms, one of  the selected schools was  running  three shifts, compared to the rest, which were running two shifts due to lack of space to sit in. It was expected that the rehabilitation of the school building could ease this condition, but  contrary  to  expectations,  the  number  of  students  increased  as  soon  as  the rehabilitation finished.    As a consequence, most of the schools are still running two or three shifts.    Although it is clear that the rehabilitation of school buildings contributed to  improving  the educational environment,  the number of  shifts  remained  the  same.   This shows that the number of shifts is not a suitable criterion. 

Page 36: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-13

• Availability of water • Availability of latrine • Availability of electricity 

Facilities of selected three schools of Batch 1 component, such as water supply, latrine, electricity,  were  rehabilitated  by  some  donors.    But  the  school  buildings  of  four schools were designed to be provided with electricity, water supply system, and latrine.   Therefore, these must be checked before examining the appropriateness of each plan. 

• Availability of fence 

According  to  the  survey,  it was  understood  that  the  fences  or  boundary‐walls were indispensable  not  only  for  residential  buildings  but  also  for  the  public  buildings including  school  buildings  in Afghanistan.    Taking  this  cultural  and  specific  social aspect to Afghanistan into consideration, all the school buildings were designed to be provided  with  boundary  fences.    The  DOE  and  UNICEF  also  recommended providing boundary fences to the Team. 

These selection criteria used by the Study Team focused on the two viewpoints of the availability  of  construction  site  and  reliability  of  educational  activities  after reconstruction.    In other words, one is the viewpoint of hardware, such as availability of space and access to sites, and the other one is viewpoint of software including things such  as  gender.    At  the  time  of  the  first  survey  in  September  2002,  the  Team implemented  both  criteria  simultaneously.    This  caused  some  confusion  and inefficiency  for  selecting  schools  for  rehabilitation.    For  effective  selection  of  target schools,  it was  better  to  put  priority within  the  selection  criteria:  the  viewpoint  of software should be assessed prior to viewpoint of hardware. 

2.2.4. Design Policy and Concept 

(1) Batch 1 Component 

The design concepts  for rebuilding  the 3 schools are based on  the results of  the  field investigation  by  the  Study  Team,  and  also,  consideration  of  the  environmental  and socio‐economic  conditions  of  Kandahar,  market  conditions  for  construction  and procurement,  affordability  of  post‐rehabilitation maintenance  and management,  and the implementation schedule of URSP‐KDH. 

Each school should be provided with: 

(i)  Appropriate number of classrooms,   

(ii)  Storeroom, 

(iii) Staff room, 

Page 37: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-14 

(iv) Appropriate number of furniture (shelf, blackboard, etc.), and 

(v)  Playground space. 

1)  The  definitive  structural  plan  and  details  for  the  school  buildings  should  be determined after reviewing the prepared site, subsoil conditions and topographic survey.    The  structure  should  be  designed  after  reviewing  the  soil  bearing capacity  to be  free of defects  such as excessive deflection, settlement, and so on.   In  addition,  the  buildings  should  have  adequate  safety  and  durability  against earthquakes,  strong  winds,  and  other  anticipated  loading  conditions. Consideration should also be given to the technical and financial levels for proper construction and maintenance locally available at present. 

2)  Consideration  of  the  relationship  to  the  existing  buildings  is  important.    There should be proper space orientation  in order to access existing buildings based on their layout orientation taking into consideration the yearly climatic conditions in Kandahar,  in  order  to  take  advantage  of  good  ventilation,  natural  lighting,  and also providing noise barriers without  special measures.    In principle, Kandahar has strong sunlight to consider; therefore, deep eaves are provided for sunshade.   At  the  same  time, open space  should be considered  in order  to  facilitate natural lighting and ventilation. 

3)  In  order  to  shorten  the  construction work  schedule, materials  and  construction methods should be standardised as much as practicable by utilising best possible methods  practiced  locally.    To  achieve  this,  adoption  of  a  standard  classroom module having standardised structural dimensions is essential. 

4)  Locally available construction methods and materials should be mainly considered, and materials available in neighbouring countries should also be given top priority for use, as much as possible,  in order  to encourage  local contractor and supplier participation,  to  reduce  overall  construction  costs,  and  to  provide  ease  and economy of operation and maintenance after construction. 

5)  The building design should take into account potential problems after construction to  enable  easy  maintenance  operations  and  maintenance  costs  to  match  the technical levels and maintenance systems currently available in Afghanistan. 

The renovation of the Ahmad Shah Baba High School is not aimed to restore the school to  its  original  features,  but  rather  to  meet  the  required  minimum  rehabilitation requirements of the building.    The rehabilitation design in the project is based on the following design policies from  the results of  the field survey conducted by  the Study Team,  and  in  consideration  of  the  construction  and  procurement  conditions  in Kandahar, and the implementation schedule of URSP‐KDH. 

Page 38: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-15

(i)  Building  renovation  is planned  taking  into  consideration  the  contents  and levels of the curriculum to be taught in the building. 

(ii)  Building design is planned in compliance with the basic concept of utilising the existing building structure as much as possible. 

(iii) Design  concepts  and materials  selection  were  determined  to  enable  easy maintenance with minimal maintenance  and  operational  costs,  taking  into consideration  the  procurement  conditions  of  materials  as  well  as  the technical  and  financial  levels  currently  affordable  for  operation  and maintenance in Kandahar city. 

(iv) Building materials for renovation works will be selected based on the survey of the existing building, and taking into consideration the local procurement of construction materials, cost  reduction, quality control, as well as ease of maintenance and cleaning. 

(2) Batch 2 Component 

The design concepts for rebuilding the four schools are based on the results of the field investigation  by  URSP‐KDH,  and  also  consideration  of  the  environmental  and socio‐economic  conditions  of  Kandahar,  market  conditions  for  construction  and procurement,  affordability  of  post‐rehabilitation maintenance  and management,  and the implementation schedule of URSP‐KDH as well as the Batch 1 Component.    Each school should be provided with the following facilities together with the design policy and concept of the Batch 1 Component. 

(i)  Head teachers’ room/Meeting Room 

(ii) Male and female students and teachers 

(iii) Water Supply (deep well) 

(iv) Head teachers room/Meeting Room 

The renovation of the existing facilities of the former Aino Middle School is not aimed to restore its original features, but to meet the required minimum rehabilitation of the building.    Aino Middle School was used as the facility of the DOE until February 2003 and some sections will remain in the existing facilities. 

The rehabilitation design in the project is based on the following design policies based on the results of the field survey conducted by the Study Team, and in consideration of the  construction  and  procurement  conditions  in Kandahar,  and  the  implementation schedule of URSP‐KDH. 

(i)  Building  renovation  is planned  taking  into  consideration  the  contents  and levels of the curriculum and activities to be conducted in the building.     

Page 39: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-16 

(ii)  Building design is planned in compliance with the basic concept of utilizing the existing building structure as much as possible. 

(iii) Design  concepts  and materials  selection  were  determined  to  enable  easy maintenance with minimal maintenance  and  operational  costs,  taking  into consideration  the  procurement  conditions  of  materials  as  well  as  the technical  and  financial  levels  currently  affordable  for  operation  and maintenance in Kandahar city. 

2.2.5. Determination of Facility Scale 

(1) Batch 1 Component 

The  design  criteria  described  below  were  considered  to  determine  the  sizes  and dimensions of each school, reflecting to solve its specific conditions and problems. 

1) Standardisation of classroom unit 

DOE has  lost  standard  school drawings during  the  chaotic period  of wartime.   Moreover, DOE has not yet established the educational policy that should cover appropriate classroom‐student ratios, teacher‐student ratios, and so on. 

In Kandahar, the classroom size varies school by school, and narrow spaces such as  corridors  are  often  used  as  classrooms.   Mixed  primary  and middle  high school education  system  is common  in Afghanistan.    Under  this circumstance, students  of  different  ages  and  grades  often  share  one  classroom.   Moreover, since the number of students from Grade‐1 to Grade‐12  is ten times as many as other  higher  Grades,  so  schools  to  accommodate  these  Grades  (primary  and middle/high schools) should be given priority consideration. 

As  a  result  of  discussions with  the DOE,  it was  decided  to  adopt  the  design criteria of 40 students per classroom in this Project. 

2) Application of current operational systems 

In Kandahar, a two‐ or three‐shift operation system has been practiced  in many schools  due  to  shortage  of  classrooms.    The  shortage  of  classrooms  has  also influenced  school hours  in  that  the actual number of  school hours differs  from one school to another. The number of school hours per student shows a reduced tendency  from  the  two‐shift  to  three‐shift  systems.    Moreover,  as  adequate numbers  of  classrooms  are  not  available  in  many  schools  at  the  time  of investigating  the  sites,  lessons  are  often  held  in  destroyed  or  damaged  school buildings  or  even  outside  in  the  schoolyard.    Probably,  increasing  students  of returning  refugees  will  share  considerable  portion  of  the  future  demand  of 

Page 40: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-17

classrooms.    The number of  required  classrooms based on a  current operation basis is to be applied to the Project, even considering the students who are taught outside, in the schoolyard. 

3) Examination for the total number of school children 

Since the number of students in each grade differs greatly and the changes in the required number of classes for each grade also differ significantly every year, the number of classes for each grade is extremely difficult to estimate and therefore, not  taken  into  consideration.    Instead,  the  following  formula will  be  applied: number of classes = total number of students of the school / 40 persons. 

4) Calculation and adjustment of the number of planned classrooms 

(i)  When  existing  classrooms  can  be  used  under  the  present  condition,  the number will be deducted from the number of planned classrooms. 

(Adjusted  number  of  classrooms)  =  (Planned  number  of  classrooms calculated  as  above)  –  (The  number  of  existing  classrooms  in  which continuous use is possible) 

(ii)  Since single‐story classroom buildings cannot be built due to site limitations, two‐story  buildings  should  be  considered.    If  the  total  number  of classrooms  to  be  built  in  two‐story  buildings  is  not  sufficient,  then  the maximum  number  of  classrooms  that  can  be  built  is  fixed  even  though  it cannot meet the number of classrooms required. 

(iii) The  principal  objective  is  to  design  and  provide  a  reasonably  satisfactory building, with size  that can be completed  in  less  than one year,  taking  into consideration the urgency of this Project. 

As per  the discussions  and  studies  as described  above,  the number  and  category of rooms and their floor areas are summarized in Table 2‐5. 

Page 41: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-18 

Table 2‐5  Required Rooms and Floor Areas 

School Name  Room Name Number of Rooms 

Room Area (m2) 

Ahmad Shah Baba High School  Classrooms  20 947.20  Storeroom  1 44.89  Sub‐Total  988.16Zahir Shahi High School  Classrooms  10 473.60  Storeroom  2 17.80  Sub‐Total  491.40Malalai High School  Classrooms  9 426.24

 Staff room Storeroom 

12

71.0464.09

  Sub‐Total  561.37  Total  2,040.93

Source: Study Team 

(2) Batch 2 Component 

The design criteria of Batch 1 component should be applied to determine the sizes and dimensional  requirements  of  each  school,  resolving  its  specific  conditions  and problems  for  the  Batch  2  component. As  per  the  discussions  and  studies  described above,  the  number  and  category  of  rooms  and  their  floor  areas  are  summarised  in Table 2‐6. 

Table 2‐6  Required Rooms and Floor Areas in New Classroom Building 

School Name  Room Name Number of Rooms 

Room Area (m2) 

Sufi Suhab School  Classrooms  21 994.56 m2

  Head Teachers Room  1 47.36 m2

  Teachers Room  1 47.36 m2

  Storeroom  1 47.36 m2

  Others  1,012.84 m2

  Sub‐Total  24 2,149.48 m2

Mirwis Mena School  Classrooms  15 710.40 m2

  Head Teachers Room  1 47.36 m2

  Teachers Room  1 47.36 m2

  Storeroom  1 47.36 m2

  Others  618.28 m2

  Sub‐Total  18 1470.76 m2

Kaka Sayed Ahmad School  Classrooms  15 710.40 m2

  Head Teachers Room  1 47.36 m2

  Teachers Room  1 47.36 m2

  Storeroom  1 47.36 m2

  Others  608.17 m2

  Sub‐Total  18 1460.65 m2

Aino Middle School  Classrooms  8 320.00 m2

  Storeroom  1 60.00 m2

  Sub‐Total  9 380.00 m2

Source: Study Team 

Page 42: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-19

2.2.6. Contractual Arrangement 

(1) Batch 1 Component   

In order  to  commence  the  rebuilding of  the  selected  3  schools  from  early December 2002, arrangements were made  for bid processing.    In accordance with  the ordinary bid processing on a Local Competitive Bidding (LCB) basis, the bid documents are to be prepared for distribution to the contractor(s).    Notice of the Bid was announced to all  the qualified bidders  selected and  short‐listed  in advance, by means of  telephone and direct notification on November 25, 2002. The bid was closed at  the URSP‐KDH Project  Team  Office  in  Kandahar  at  12:00  noon  on  December  2,  2002.    Qualified bidders were  selected  and  short‐listed  through  the  process  of  interviewing,  visiting their construction sites, and meeting  for clarification  in order  to assess  their  technical capacity  and  equipment  availability.  As  a  result,  fourteen  (14)  contractors  were short‐listed, of which all fourteen (14) contractors collected Bid Documents and ten (10) contractors eventually submitted the Bid Documents. 

The assessment of the Bids was made taking the following three steps: 

1)  Documents Compliance 

2)  Technical Evaluation 

3)  Detailed Evaluation 

All  ten  (10)  contractors  passed  the  above  documents  compliance  and  technical evaluation.    As  a  consequence  of  the  bid  evaluation  and  in  accordance  with  the aforementioned procedure, the successful bidders for each sub‐project are listed below. 

Table 2‐7  Conclusion of Bid Bidder’s Name  Sub‐project Name  Reasons for Selection 

Haji Abdul Qayum Construction 

Malalai High School  • The bid price is lowest for all sub‐projects. • The bidder has no capacity to rebuild all 3 sub‐projects. 

• The bidder is keen to do this sub‐project. Arghandab Rehabilitation Organization 

Zahir Shahi High School • The bid price is second lowest for other 2 sub‐projects. 

• The bidder has no capacity to rebuild plural sub‐projects. 

• The bidder is keen to do this sub‐project. Engineer Hayatullah Construction Unit 

Ahmad Shah Baba High School 

• The bid price is third lowest.  

Source: Study Team 

(2) Batch 2 Component 

In  order  to  commence  the  rebuilding  of  the  selected  4  schools  from  May  2003, arrangements  were  made  for  bid  processing.  Qualified  bidders  were  selected  and short‐listed  through  the process of  interviewing, visiting  their construction sites, and 

Page 43: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-20 

meeting  for  clarification  in  order  to  assess  their  technical  capacity  and  equipment availability.    As a result, twelve (12) contractors were short‐listed, of which all twelve (12) contractors collected Bid Documents and ten (10) contractors eventually submitted the Bid Documents.    As a consequence of  the bid evaluation and  in accordance with the  aforementioned procedure,  the  successful  bidders  for  each  sub‐project  are  listed below. 

Table 2‐8  Conclusion of Bid Bidder’s Name  Sub‐project Name  Reasons for Selection 

Bureau of Humanitarian Aid and Development 

Sufi Saheb School  • The bid price is lowest for this sub‐project. • The bidder is keen to do this sub‐project. 

Hayatullah Construction Unit  Aino School  • The bid price is lowest for this sub‐project. • The bidder is keen to do this sub‐project. 

Haqyar Reconstruction Agency for Afghanistan 

Kaka Sayed Ahmad School 

• The bid price is lowest for this sub‐project. 

Afghanistan Society Scientific Association for Development 

Mirwais MenaSchool • The bid price is lowest for this sub‐project. 

Source: Study Team   

2.2.7. Implementation of the Projects 

Constructions of Batch 1 component was completed around middle of May 2004, and the construction of Batch 2 component was completed by the beginning of September 2004.    The completion dates of these works were originally June 2003 and November 2003,  respectively.    The  construction  schedule was  revised due  to  time delay  in  the quality  control of  reinforcement bar  arrangement  for  foundation,  and  lack of  skilled labours. 

(1) Ahmad Shah Baba School(Batch 1) 

The whole construction works including Site Clearing, grading works, electrical works and Supply of Furniture and Installation works were completed by the middle of June 2004.    The concrete strength for each test cube was confirmed safe for construction use by the test equipment purchased by the Study Team. 

The  two‐story  classroom  building  of  Ahmad  Shah  Baba  School  was  planned  as  a facility with enclosed courtyard in order to secure appropriate access from the entrance gate to the main building and to where some community activities will be held.    Also, the roof, windows and doors of the severely damaged existing buildings were mostly rehabilitated under the appropriate supervision. 

Page 44: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-21

     Figure 2‐1  Ahmad Shah Baba School 

(2) Zahir Shahi School(Batch 1) 

The whole construction works including Site Clearing, grading works, electrical works and Supply of Furniture and Installation works were completed by the middle of May 2004.    The concrete strength for each test cube was confirmed safe for construction use by the test equipment purchased by the Study Team. 

The two‐story classroom building has been constructed along the north‐side boundary wall  in  order  to  secure  the  flow  line  between  an  existing  building  and  the  new classroom building.    Also,  the  terrace  in  front of  the playground was considered  for use to avoid circulation problems when crowded with pupils. 

       Figure 2‐2  Zahir Shahi School 

(3) Malalai High School(Batch 1) 

The whole construction works including Site Clearing, grading works, electrical works and Supply of Furniture and Installation works were completed by the middle of May 2004.    The concrete  strength  for each  test cubes was confirmed  safe  for construction use by the test equipment purchased by the Study Team. 

Bearing  in mind the customs of girl’s school, an L‐shaped building was designed and piloti court between new and existing buildings was considered as circulation space for 

Page 45: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-22 

the  new  classroom  building,  and  in  order  to  have  access  to  the  back‐side  and harmonise with the space enclosed by the existing building. 

     Figure 2‐3  Malalai School 

(4) Sufi Saheb School(Batch 2) 

The  whole  construction  works  including  electrical  works,  construction  of  well, boundary wall, guardhouse and toilet, and Supply of Furniture and Installation works were completed by the beginning of September 2004.    The concrete strength for each test cube was confirmed safe for construction use by the test equipment purchased by the Study Team. 

The two‐story classroom building of Sufi Saheb School was planned as a facility with enclosed courtyard in order to secure appropriate access from the entrance gate to the main  building,  and  direct  approach  harmonised  from  the  entrance  gate  to  the playground. 

     Figure 2‐4  Sufi Saheb School 

(5) Aino middle School(Batch 2) 

The whole  construction works  including  electrical works,  construction  of well  and boundary  wall  and  toilet,  and  Supply  of  Furniture  and  Installation  works  were completed by  the end of August 2004.    The concrete strength  for each  test cube was 

Page 46: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-23

confirmed  safe  for  construction  use  by  the  test  equipment  purchased  by  the  Study Team. 

Although the existing building was used as an office of DOE, after dividing the portion with  the  boundary wall  and  securing  the  exclusive  line  of  flow  for  schools,  it was repaired to a classroom.    Furthermore, in order to design comfortable open space and playground,  harmonising  the  layout  of  new  school  buildings with  several  existing buildings was taken into account. 

       Figure 2‐5  Aino Middle School 

(6) Kaka Sayed Ahmad School(Batch 2) 

The whole  construction works  including  electrical works,  construction  of well  and boundary  wall  and  toilet,  and  Supply  of  Furniture  and  Installation  works  were completed by  the end of August 2004.    The concrete strength  for each  test cube was confirmed  safe  for  construction  use  by  the  test  equipment  purchased  by  the  Study Team. 

Kaka  Sayed  School was  located within  the  current  site  of Zahir  Shahi  School.    The girls  school  was  closed  by  the  prohibition  of  female  education  under  the  Taliban regime and so the Zahir Shahi School expanded  into this facility due to a shortage of classrooms.    Although  the  facility  was  available  for  renovation  as  a  classroom building,  a  new  classroom  building  was  constructed  to  alleviate  shortage  of classrooms. 

Page 47: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-24 

     Figure 2‐6  Kaka Sayed Ahmad School 

(7) Mirwis Mena School(Batch 2) 

The  whole  construction  works  including  electrical  works,  construction  of  well, boundary wall, guardhouse and toilet, and Supply of Furniture and Installation works were completed by the beginning of September 2004.    The concrete strength for each test cube has been confirmed safe for construction use by the test equipment purchased by the Study Team. 

Mirwis Mena Girls School was closed by the prohibition of female education under the Taliban  regime.    The  new  Mirwis  Mena  School  was  built  in  the  new  site  by URSP‐KDH.    In  consideration  of  customs  of  girls  school,  an  L‐shaped  classroom building with  circular  playground,  boundary wall  and  guardhouse was  considered within the sloped campus. 

     Figure 2‐7  Mirwis Mena School 

2.2.8. Operation and Maintenance 

Concerning Batch 1 (3 schools), There was no need to add teachers and cleaning staff even  if  the  number  of  classrooms  increases  since  it was  simply  a matter  of moving classes to actual classrooms from the temporary tents, which UNICEF provided. Also concerning Batch 2 (4 schools), the Study Team confirmed that DOE was able to recruit the additional teachers and staffs before completion of construction works.   

Page 48: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-25

However,  lack  of  skills  and  systems  for  school  maintenance  was  obvious  in  each existing  school.    There  was  no  efficient  support  programme  to  develop  the maintenance system of school  facilities.    The Study Team decided  to conduct School Maintenance  Improvement  Programme  as  Soft‐component  Programme  under URSP‐KDH.    Details of School Maintenance  Improvement Programme are contained in Chapter 4. 

In addition, materials available  in  local market or neighbouring countries were given top  priority  for  construction  use  in  order  to  facilitate  and  provide  economy  of operation and maintenance. 

2.2.9. Workshop on Effective School Management 

For  the  purpose  of  effective  and  sustainable  use  of  school  facilities  which  were constructed  by  the  Programme,  the  Study  Team  held  a workshop  on  “Educational Development  in Kandahar”  in  29  January  2005.  The workshop was  held  at Dining room in Mirwis Hospital as half day workshop including presentation of “The History of  Japan’s  Educational  Development”8,  and  discussions  concerning  effective  school management and maintenance.   

 Figure 2‐8  Discussion about school maintenance at the workshop (January 2005) 

Fifteen participants  from  the  seven  schools and DOE exchanged  their experiences  in each  school,  and  discussed  how  to  improve  their  practice  concerning  school management  and  maintenance  after  they  watched  the  video.  The  major  ideas  of participants were the following: 

                                                      8  The presentation was conducted using a video “The History of Japan’s Educational Development (JICA, 

2004)”. 

Page 49: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-26 

Table 2‐9  Ideas for Effective School Management Topics  Ideas Management  Teachers cooperation with each other 

Experienced teachers should try their best for better school management office 

Establishment of teachers committee in each school and then arranging regular meetings to tackle school issues 

Strengthening teachers association for good school administration  Experienced, qualified and hard working principal can make better 

management  Teachers and admin staff should have sympathy to school and students  Teachers should be professional  Control of students attendance to class  Management staff should be more active  Teacher‐Student association should be founded  Selection of students representatives through elections in school, and then 

calling them to regular meetings  Good relations with school neighbours 

Cleanliness  School facilities better maintenance require cleaning at the first stage  School Students Inspection Groups need to cooperate for cleaning with 

school staff  Better discipline creates cleanliness  Students Hygienic Condition inspection by School Teachers  Students cleaning groups and cleaning duty schedules should be made  Creation of Hygiene Training Groups from teachers and senior students  Student participation in cleaning and informing students of their 

responsibilities Maintenance  School Furniture, Teaching Materials, Laboratories and Compound need 

regular maintenance monitoring  Maintenance Training by teachers to students  Each class should have its two oldest students to supervise the facilities 

daily and report to teacher  Good control of primary students in school  Inspection of class furniture and facilities at the end of each shift by 

responsible students  Identifying maintenance faults on time  Maintaining Democratic Environment in School  Establishment of PTA in each school  Regular meetings on maintaining the school in a good way  All school beneficiaries should feel the school is theirs 

Source: Study Team 

Page 50: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-27

2.3. Health Sector 

2.3.1. Overall View of the Health Sector 

(1) General 

In  the  pre‐war  period,  Afghans  used  non‐governmental  sources  for much  of  their health: namely,  local healers, traditional midwives, bone‐setters, medicine sellers, and shopkeepers.    These  were  the  first  line  health  approach  for  the  population.    The health services at that time were highly clinically oriented and curative based. 

In  the mid  1970’s,  centralized, hospital‐oriented  curative  care began  to  shift  to more decentralized,  community‐centered primary  care.    Besides administrative  reforms of health  management,  local  responsibility  for  services  also  made  progress.   Unfortunately,  the  coup  of  1978  changed  the  supportive  environment  for  the  health action.    During the time of the Taliban, in Kandahar, that plan was discontinued. 

In  1995,  the Health  Sectoral Working  Group  (HSWG)  for  the  southern  region was established  in Kandahar.    The HSWG was composed of WHO, Department of Public Health (DOPH), UNICEF, AHDS, Al‐khidmat Al‐hajeri, Guardians, Health Net, Ibnsina, ARCS,  IAHC,  UNOCHS,  WFP,  CI,  ISRA  (and  ADAG,  MSF  IFRC,  ICRC  and  HI attended  as  observers).    The  activities  of major  donors  and NGOs  are  described  in Table 2‐10. 

Table 2‐10  Health Partners in Southern Region   Donor /NGO  Activities 1  WHO    Donor program, Technical and financial support to DOPH, capacity building, 

strengthening primary health care, Polio eradication program, AFP surveillance, Mother child healthcare, Control of endemic diseases, response to the outbreaks, up grading health facilities for essential drugs and equipment.    Coordination of health activities. 

2  AHDS  Primary healthcare program through 37 health facilities in Kandahar and Urozgan provinces.     

3  Ibnsina  Primary healthcare program, in 10 health facilities including IDPs in Helmand and Kandahar provinces. 

4  IAHC  Five Health facilities in Kandahar province (maternity centre, MCH clinics). 5  MSF‐H  Working in emergency healthcare, early warning system, IDPs camp in Zhary 

dasht district, infectious disease ward.     6  MC  Primary healthcare program through five health facilities in Helmand province 

(Garamsir and Khanashin districts).     7  Health Net  Health Net International providing Malaria control program with support of 

WHO through 37 malaria units in the region. 8  Guardians  Providing orthopaedic care for disabilities in the region. 9  ICRC  Supporting surgical ward of Mirwis hospital in Kandahar. 10  IFRC  Providing support to Afghan Red Crescent Society. Emergency healthcare, in 

Provinces of Kandahar, Zarnag, Helmand, Zabul and mobile teams. 11      NGO from Kuwait, providing healthcare through Al‐khidmat hospital (12 beds) 

in Kandahar city. 13  ADAG  NGO running MCH clinic in Kandahar city. 14  MDM  Support to TB program and MCH clinic in Kandahar city. Source: WHO Kandahar 

Page 51: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-28 

The  Department  of  Public Health,  Kandahar,  (DOPH)  is  supposed  to  be  the main implementing body and provides support to all health activities in Kandahar province.   They  have  regular  meetings  every  month  and  the  minutes  are  circulated  to  all concerned  organizations,  and  they  are discussing  the  situations  and  future  plans  in terms of sharing information about health activities. 

The condition of health services in rural areas of the southern region is totally different.   In  the southern region,  there were 52 districts and 21 of  them had no health facilities except for some private pharmacies.    A detailed list of health facilities in May 2002 in southern regions is shown in Table 2‐11. 

There were  in  total,  83  facilities  in  southern  region,  and  65  (82%)  of  facilities were managed by NGOs, and only 18 were managed by DOPH;  this was  less  than  the 36 facilities managed by AHDS.    Even now  there are  imbalances  in both  institutions,  in terms  of  facilities  and  incentives.    For  example,  salaries  and  incentives  in NGO‐managed health facilities were nearly double or three times higher in comparison with DOPH‐run health  facilities, and  they had new equipment because of  the donor support. 

Coordination  of DOPH, Donors  and NGOs  is  very  important  for  equality  in  health services for people as well as cost effectiveness for MOPH and donors, in the future. 

Page 52: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

 

 

URSP-KDH Final Report Part 2 

2-29 

Table 2‐11 Health Resources for Districts of Southern Region Afghanistan Revised on 20 May, 2002 

                                     

gg

yH

ealth

Fac

ility

No.

of b

eds

Hum

an R

esou

rces

/Hea

lth p

erso

nnel

MF

MF

MF

MF

MF

MF

MF

MF

MF

124

01K

anda

har

456,

177

MO

PH, I

AH

C, I

CRC

, IFR

C1

02

00

02

150

213

104

2434

195

887

4413

66

134

01

415

021

814

224

02Bo

ldak

46,2

68M

OPH

00

10

00

018

66

012

31

70

20

10

20

00

10

12

00

00

324

03Sh

ega

8,04

40

00

00

00

00

00

00

00

00

00

00

00

00

00

20

00

04

2404

Dan

d15

3,54

1A

HD

S, Ib

nsin

a0

00

10

00

35

50

101

11

11

01

01

02

00

01

61

201

155

2405

Dam

an31

,361

AH

DS

00

01

12

02

00

00

21

11

20

10

10

00

00

12

14

030

624

06A

rghi

stan

32,6

59A

HD

S0

00

10

20

15

50

101

11

11

01

01

00

00

01

21

40

407

2407

Kha

krez

21,6

43A

HD

S0

00

10

30

10

00

00

00

00

00

00

02

00

00

20

80

08

2408

Gho

rak

9,06

5Ib

nsin

a0

00

10

00

10

00

01

00

01

00

01

00

00

00

20

00

09

2409

Nes

h12

,790

00

00

00

04

00

00

00

00

00

00

00

00

00

00

00

00

1024

10Sh

raba

k10

,876

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

1124

11Re

g1,

814

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

1224

12A

rgha

ndab

82,4

48A

HD

S, IA

HC

00

02

10

02

55

010

21

21

20

20

30

20

00

16

120

130

1324

13Pa

njw

ai12

2,83

2IA

HC,

AH

DS

00

01

10

011

55

010

32

31

20

10

10

00

00

14

120

10

1424

14M

aiw

and

68,4

30A

HD

S0

00

10

00

55

50

104

21

12

01

04

00

00

01

42

10

4015

2415

Shah

wal

ikot

67,5

80A

HD

S0

00

11

60

15

50

101

11

11

01

02

02

00

01

41

140

5016

2416

Mar

uf31

,300

00

00

00

00

00

00

00

00

00

00

00

00

00

02

00

00

Kan

daha

r1,

156,

828

10

310

413

219

924

914

024

413

113

1810

451

276

151

500

94

160

2946

2291

320

5

123

01La

shka

rgan

Bus

t92

,557

MO

PH0

10

00

01

4540

5060

150

276

385

10

40

80

10

40

56

40

050

223

02Re

g28

,063

00

00

10

00

00

00

01

02

00

00

00

00

00

00

00

00

323

03N

ahr-e

-ser

aj11

4,95

7M

OPH

, Ibn

sina

00

10

00

125

24

410

51

30

20

20

50

40

10

52

20

010

423

04Sa

rban

Qal

a27

,046

MO

PH0

00

10

00

320

00

08

13

00

01

05

00

00

03

20

00

05

2305

Mos

a Q

ala

61,0

19M

OPH

00

00

00

015

00

00

52

40

00

20

30

50

10

12

00

00

623

06K

ajak

ai11

4,48

8M

OPH

00

00

00

010

00

00

51

40

00

10

30

20

10

12

00

00

723

07N

auza

d55

,219

MO

PH, I

bnsin

a0

01

00

01

122

44

104

16

01

01

04

04

00

02

11

00

08

2308

Was

her

19,0

130

00

00

00

40

00

00

02

10

00

00

00

00

01

20

00

09

2309

Gar

amse

r83

,316

MC

I0

01

40

01

182

44

104

14

11

01

03

05

01

02

20

00

010

2310

Nad

-e-A

li11

1,97

9Ib

n+M

OPH

00

01

00

06

00

00

10

40

10

20

40

00

00

22

00

00

1123

11N

awa

Bara

kzai

88,0

79M

OPH

00

01

00

05

00

00

31

20

00

00

20

20

00

15

00

00

1223

12Ba

ghra

n77

,265

MO

PH0

00

10

00

30

00

01

02

00

00

01

02

01

01

00

00

013

2313

Des

hu25

,386

00

00

00

01

00

00

00

00

00

00

00

00

00

00

00

00

Hel

man

d89

8,38

70

13

81

04

176

4662

7218

063

1572

96

014

038

025

09

024

267

00

60

Midlevel/Assist/Doctor

X-Ray-Technian

Vaccinators

VHV/BHW/CHW

Female

Children

Total

TBA

Midwife

Physician

Nurse

Pharmacist/Assist

Dentis/Assist

Lab-technician

Pharmacy

Male

District Hospital

BHC

Sub-Center

Health Post

Supporting Agency

Regional hospital

Provincial hospital

Polyclinic

No

District Code

District Name

Population 2002 Unidata

Page 53: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

   

2-30 

URSP-KDH Final Report Part 2 

                                            Source: W

HO Kan

daha

r

Hea

lth F

acili

tyN

o. o

f bed

sH

uman

Res

ourc

es/H

ealth

per

sonn

el

MF

MF

MF

MF

MF

MF

MF

MF

MF

126

01Te

rinko

t71

,468

MO

PH, A

HD

S, IA

HC

01

00

06

033

3010

040

11

42

21

10

20

01

00

12

210

020

92

01

02

2602

Kha

s U

rozg

an64

,874

MO

PH0

00

10

00

1010

100

201

02

01

00

00

00

00

00

20

00

01

00

03

2603

Deh

raud

67,6

17A

HD

S0

00

10

60

3010

100

201

01

11

01

01

00

00

01

20

110

233

10

10

426

04D

aiku

ndi

175,

728

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

526

05Sh

ahris

tan

122,

990

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

626

06C

hora

h39

,520

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

726

07A

jeris

tan

57,5

340

00

00

00

00

00

00

00

00

00

00

00

00

00

20

00

01

00

08

2608

Giz

ab61

,918

00

00

00

00

00

00

00

00

00

00

00

00

00

02

00

00

10

00

926

09K

ejra

n64

,714

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

Uro

zgan

726,

363

01

02

012

073

5030

080

31

73

41

20

30

01

00

210

221

044

26

02

0

125

01Q

alat

32,0

83M

OPH

, IFR

C, A

RC

S0

10

10

00

2230

300

606

09

12

01

03

00

01

02

23

00

02

20

02

2502

Jald

ak16

,247

00

00

00

03

00

00

00

00

00

00

00

00

00

02

00

00

10

00

325

03M

ezan

a12

,950

00

00

00

04

00

00

00

00

00

00

00

00

00

02

00

00

10

00

425

04Sh

ahjo

y55

,424

MO

PH0

00

10

00

200

00

01

14

01

00

01

00

00

00

20

00

01

00

05

2505

Arg

hand

ab30

,939

MO

PH0

00

10

00

40

00

01

04

01

00

00

00

00

00

20

00

01

00

06

2506

Day

e C

hopa

n74

,342

00

00

00

010

00

00

00

00

00

00

00

00

00

02

00

00

10

00

725

07Sh

inka

y22

,279

MO

PH0

00

10

00

60

00

01

04

01

00

01

00

00

00

20

00

02

00

08

2508

Atg

har

8,23

00

00

00

00

30

00

00

00

00

00

00

00

00

00

20

00

01

00

09

2509

Sham

olza

i42

,349

00

00

00

06

00

00

00

00

00

00

00

00

00

02

00

00

10

00

Zab

u l29

4,84

30

10

40

00

7830

300

609

121

15

01

05

00

01

02

183

00

011

20

0

122

01Za

ranj

50,7

41M

OPH

, IFR

C0

10

10

01

2410

103

237

23

324

02

01

01

01

02

42

00

53

00

02

2202

Kan

g49

,382

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

322

03C

hakh

ansu

r38

,515

MO

PH0

00

10

00

10

00

00

01

01

00

00

01

00

00

20

00

21

00

04

2204

Khs

hrod

21,2

94M

OPH

00

01

00

00

00

00

10

10

10

00

10

10

00

02

00

00

10

00

522

05C

harb

orja

k41

,067

MO

PH0

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

00

0N

imro

z20

0,99

90

10

30

01

2510

103

238

25

326

02

02

03

01

02

82

00

75

00

0

124

00K

anda

har

1,15

6,82

81

03

104

132

199

249

140

2441

311

318

104

5127

615

150

09

416

029

4622

913

205

2219

181

223

00H

elm

and

898,

387

01

39

00

417

646

6272

180

6414

747

61

140

380

250

90

2426

70

060

139

62

326

00U

rozg

an72

6,36

30

10

20

120

7350

300

803

17

34

12

03

00

10

02

102

210

442

60

20

425

00Za

bul

294,

843

01

04

00

078

3030

060

91

211

50

10

50

00

10

218

30

00

112

00

522

00N

imro

z20

0,99

90

10

30

01

2510

103

238

25

326

02

02

03

01

02

82

00

75

00

0So

uthe

rn R

egio

n3,

277,

420

14

628

425

755

138

527

299

756

197

3621

165

688

341

980

375

270

5910

836

112

371

457

3026

3

Midlevel/Assist/Doctor

X-Ray-Technian

Vaccinators

VHV/BHW/CHW

EPI Fixed Centers

Malaria Center

MCH Clinics/Services

TB Control Centers

Female

Children

Total

TBA

Midwife

Physician

Nurse

Pharmacist/Assist

Dentis/Assist

Lab-technician

Pharmacy

Male

District Hospital

BHC

Sub-Center

Health Post

Supporting Agency

Regional hospital

Provincial hospital

Polyclinic

No

District Code

District Name

Population 2002 Unidata

Page 54: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-31 

(2) Health Service in Mirwis Regional Hospital 

Within  the health  facilities  in Kandahar  city,  6  facilities were managed  by DOPH,  7 facilities were managed  by NGOs;  all  these  13  facilities were  categorized  as  public hospitals and clinics.    Basically, in government facilities in Afghanistan, health service are  free  of  charge,  but  in Mirwis  hospital,  a  patient  has  to  pay Afg.  1  for  the  first examination  and  direct  expenses  of  X‐rays.    Most  NGOs  collect  some  fee  for laboratory  tests  and  drugs.    Service  and  conditions  of DOPH  facility  are  described below. 

Mirwis Regional Hospital is the biggest hospital in Southern region and the top referral hospital  (listed  as  250  beds,  but  actually  328  beds  are  installed).    The  number  of patients  is  shown  in  Table  2‐12.    The  hospital was managed  by  DOPH  under  the support  of NGOs.    ICRC  provided  support  for  surgery, MSF  provided  support  for infectious  disease.    Other  sections  faced  the  lack  of medical  services  and  employee salaries due to non‐support from NGOs. 

Table 2‐12  Number of Patients in OPD and IPD of Mirwis Hospital (Jan‐Jun 2002) OPD  IPD  Total Ward 

Male  Female  Male  Female  Male  Female 

Surgical  1,600 1,888 300  437 1,900  2,325Gynaecology/Obstetric  0    210 0 99 0  309ENT  220  376 23 47 243  423Eye  827  1,100 8   10 835  1,110Dental  500  511 0   0 500  511Paediatric  1,390  1,000 60 60 1,450  1,060Internal medicine  1,990  85 1,290 700 3,280  785

6,527 5,170 1,681 1,353 8,208  6,523Total 11,697 3,034 14,731

Source: DOPH, HIS Dept 

(3) Human Resources 

Kandahar  University  has  a  medical  school  for  males  and  females.    They  study together in the same class but as the table shows, the number of female students is very low because of rare educational opportunity at high school.    The property belongs to the Mechanical School and the whole university will move to the east part of the city in the near future. 

The medical school is under the Ministry of Higher Education and teaching doctors are from Mirwis Hospital.    The  Principal  expects  to  have  their  own  teaching  hospital under MOHE in the new location and retain doctors or lecturers.     

 

Page 55: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-32 

Table 2‐13  Number of Students in Medical School Year  MPCB  1  2  3  4  5  Master 

Male  50  62  65  51  66  42  55 Female  2  ‐  1  ‐  ‐  ‐  ‐ 

Source: Kandahar University 

In reality, female workers in hospitals and clinics or nursing school students are facing difficulties  to  commute,  the  same  as  female  patients.    Female  doctors,  nurses  and midwives are sorely needed; existing health workers also need further training. 

Concerning  the  number  of  female workers,  there  is  a world  of  difference  between Kandahar  and  Kabul.    In  Kandahar,  it  is  very  difficult  to  find  females  who  have medical  potential  for  becoming  doctors  and  nurses.    Some NGOs  are  hiring  them from Kabul for their BHC or MCH clinics but it is not that simple.    The students of the nursing school are from various areas, mostly Kabul. 

AHDS is one of the biggest NGOs having 8 CHC, 4 BHC, 11 BHP and 8 MCH clinics in Kandahar  province.    They  have  their  own  training  programs  for male  and  female medical practitioners as shown in Table 2‐14and Table 2‐15. 

Table 2‐14  Training Centre Plan for Male Workers ACTIVITIES  DURATION LOCATION INPUT 

BHWs refresher course  1 week  RTC  BHWs Nurse refresher course  1 week  RTC  Nurse MLHWs refresher course  1 week  RTC  MLHWs Health educators refresher course  1 week  RTC  H.E Lab. Tech. Refresher course  1 week  RTC  Lab. tech. Detal Tech. Refresher course  1 week  RTC  Den. tech. PHC workshop  2 days  RTC  Doctors, MLHWs UTI workshop  2 days  RTC  Doctors, MLHWs Early warning system workshop  1 day  RTC  Doctors, MLHWs CDD workshop  2 days  RTC  Doctors, MLHWs HIS workshop  1 day  RTC  Doctors, MLHWs, RHB Nutrition / Malnutrition workshop  2 days  RTC  Doctors, MLHWs EPI plus workshop  2 days  RTC  Vaccinators Program Management workshop  2 days  RTC  Doctors, MHLWs Malaria workshop  2 days  RTC  Doctors, MHLWs Poisoning Seminar  2 days  RTC  Doctors, MHLWs Disaster Management & Firs aid workshop  2 days  RTC  Doctors, MHLWs Ari workshop  2 days  RTC  Doctors, MHLWs Source: AHDS 

Page 56: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-33 

Table 2‐15  Training Centre for Female Workers   DURATION LOCATION Disaster & Firs aid Management  2 days  City Clinic HIS workshop  2 days  City Clinic Poisoning Seminar  1 day  City Clinic Ari workshop  2 days  City Clinic Nutrition / Malnutrition workshop  2 days  City Clinic PHC workshop  2 days  City Clinic TBA Trainer Refresher Course  2 days  City Clinic EMOC Workshop  1 week  City Clinic Family Planning  2 days  City Clinic Nurse refresher course  2 days  City Clinic Health Educators refresher course  1 week  City Clinic Medical Problems during pregnancy 1 week  City Clinic CDD Workshop  2 days  City Clinic Early Warning System Workshop  2 days  City Clinic 

Source: AHDS 

There are 5 nursing schools in the country; one of them is in Mirwis hospital. There are 3  classes  for males  and  3  classes  for  females  as  shown  in  Table  2‐16.   Most  of  the teachers are doctors of  the hospital and hold  several posts at  that  time.    The  school year begins  in  June every year and  finishes after 9 months.    All school expenses are free for students.    Students who finish 9th grade, at the age of 14, can apply and take examinations.   Most female students study in Kabul or Pakistan before entering. 

Table 2‐16  Number of students in Kandahar Nursing School (Sep. 2002) Grade  1  2  3 Male  35  19  24 Female  18  24  37 

Source: Kandahar Nursing School 

In  2002,  there were  75 male  candidates  and  25  females,  of which  35 males  and  18 females  were  accepted.    At  the  end  of  each  year,  there  is  an  examination  for promotion to the next grade.    After 27 months study including practical training, they become  qualified  nurses.    The  facility  used  to  be  a  three‐storey  building  with  a dormitory, and at  that  time,  the ground and  first  floor were used  for disabled people with artificial limbs.    They do not have any practical plan for withdrawal. 

2.3.2. Selection of the Projects 

(1) Batch 1 Component 

Mirwis Regional Hospital was constructed more  than 28 years ago by Chinese Grant Aid.    Since 1980, Medical Equipment and Building Facilities have not been  replaced nor  have maintenance work  been  performed.    The  hospital  is managed  by  DOPH under  the  support  of  NGOs.    ICRC  provides  support  for  surgery,  MSF  provides support  for  infectious  diseases  treatment  and  PIMA  provides  support  for Gynaecology/Obstetrics.    Other  sections  face  the  lack  of  medical  services  and 

Page 57: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-34 

employee salaries due to non‐support from NGOs.    According to the survey result of PAMA (Department of Housing and Town Planning), 88 items of the building require renovation works.    During  the  survey  in  hospital,  the  Study  Team  also  found  that many places have to be repaired, but the total renovation of the hospital will need long term and serious consideration.    Based on the  limitation of the time, the Study Team decided  to  renovate  Kitchen  and  Laundry  of  Mirwis  Regional  Hospital.    The renovation aims at improvement of food service and hygiene condition of hospital. 

(2) Batch 2 Component 

Based on the discussions with DOPH, the Study Team decided to rate as high priority for the urgent project to supply commuter buses for transportation of female students and female teachers to Kandahar Nursing School. 

2.3.3. Design Policy and Concept 

(1) Renovation Works of Kitchen and Laundry of Mirwis Hospital (Batch 1) 

The  renovation  work  include  interior  and  exterior  repairs  and  electrical  and mechanical  repairs  for plumbing work.    Locally available materials were  selected as much as possible in repair works to enable minimal maintenance and operational cost.   The work also included supply and installation of kitchen and laundry equipment such as gas cooking system, stainless shelves, wash sink, cooking tables, furniture for dining hall,  office  furniture  and  automatic  laundry  machines.    Local  availability  of  spare parts was considered for selection. 

(2) Commuter Buses for Kandahar Nursing School (Batch 2) 

The  Study  Team  decided  on  three  commuter  buses  and  two  microbuses  for transporting 91 (the number of students as of 2002) students and teachers.    In addition, the following aspects were taken into consideration to provide sustainable use. 

Popular car in Kandahar for easy maintenance  Left‐hand‐drive car  Diesel engine car 

2.3.4. Contractual Arrangement 

(1) Renovation Works of Kitchen and Laundry of Mirwis Hospital (Batch 1) 

As a result of tender evaluation, the contract for building renovation work was signed on 30 December 2002, and  the  contract  for  supply and  installation of  the equipment was signed on 20 January 2003. 

Page 58: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-35 

(2) Commuter Buses for Kandahar Nursing School (Batch 2) 

As a result of  tender evaluation,  the contract for supply of vehicles was signed on 16 June 2003.    The vehicles were handed over to the Kandahar Nursing School/DOPH at the end of November 2003. 

2.3.5. Implementation of the Projects 

(1) Renovation Works of Kitchen and Laundry of Mirwis Hospital (Batch 1) 

The renovation work was completed at the end of May 2003,  including  installation of the equipment, and officially handed over to the Ministry of Public Health in Kandahar on 31 May 2003.    Trial cooking was held on  that day: 40 kg of rice was cooked with vegetables and meat  in  local style and  the occasion entertained a number of relevant people.    Additionally,  the Study Team decided  to  supply  tableware  such as  cooking knives, ladles, plates, glasses, and spoons. 

The list of equipment for kitchen and laundry is shown in Table 2‐17. 

Table 2‐17  List of Equipment for Kitchen & Laundry Items / Qty.  Items / Qty. Chest Freezer (556 litres) / 1  Bowls Sink with 3 Mixing Faucets 

(1800Wx750Dx850H) / 1 Reach‐in Refrigerator (681 litres) / 1  Portable Table (900Wx600Dx850H) / 2 Reach‐in Refrigerator (1175 litres) / 1  Table (1500Wx750Dx850H) / 1 Refrigerated Show Case (165 litter) / 1  Table (1500Wx900Dx850H) / 2 Gas Table (2700Wx900Dx850H) / 1  Work Table (1800Wx750Dx850H) / 1 Gas Table (2100Wx900Dx850H) / 1  Clean Table (1800Wx750Dx850H) / 1 Gas Kwali Kettle (150 litre) / 2  Bench with Cabinet Base (1800Wx750Dx850H) / 

1 Cutter Mixer / 1  Bench with Drain (1200Wx750Dx850H) / 2 Meat Chopper / 1  Rack Shelving (1518Wx613Dx1892H) / 2 Water Heater (40 litre) / 1  Rack Shelving (1821Wx613Dx1892H) / 1 Bain Marie / 1  Rack Shelving (1212Wx613Dx1578H) / 1 Work top Cabinet (1800Wx750Dx850H) / 1  Rack Shelving (1212Wx613Dx1892H) / 1   Wagon (1022Wx677Dx704H) / 3  Laundry Equipment / 1 Sink with Mixing Faucet / 1  Washing Machine (30kg) / 1   Washing Machine (10kg) / 1 Source: Study Team 

Page 59: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-36 

       

         Figure 2‐9  Installed Equipment in Mirwis Hospital 

(2) Commuter Buses for Kandahar Nursing School (Batch 2) 

The vehicles were handed over to the Kandahar Nursing School/ DOPH in the end of November 2003. 

Specifications for the buses are shown in Table 2‐18. 

Table 2‐18  Details of Commuter Bus and Microbus for Kandahar Nursing School Commuter  Quantity  3 Unit   Make & Model  Mitsubishi Motors, P15WHLNL   Type  4 x 2 Wheel Drive   Passenger  12 Seats   Others  Manual Transmission, Seatbelt, Air Conditioner Microbus  Quantity  2 Unit   Make  Mitsubishi Motors, BE637ELMSH   Type  4 x 2 Wheel Drive   Passenger  24 Seats   Others  Manual Transmission, Seatbelt, Air Conditioner Source: Study Team 

Page 60: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-37 

 Figure 2‐10  Commuter Buses 

2.3.6. Operation and Maintenance   

(1) Dining Hall and Kitchen Department, and Laundry Department of Mirwis Hospital (Batch 1) 

There  is no need to add kitchen staff and budget. Even  if the food demand  increases, they can manage by using the new kitchen equipment. On the other hand, the Ministry of Public Health and WFP supply the food products and raw material.    According to the new plan, constant supply of  food  items  including meats and milk, etc. and  raw material is to be managed by the Ministry of Public Health. 

Also,  there  is  no  need  to  increase  laundry  staff  or  budget.    Even  if work  volume increases they can manage using the new laundry machines. 

(2) Commuter Buses for Kandahar Nursing School (Batch 2) 

During the survey and discussion with DOPH, the Study Team found that DOPH did not have enough capacity for proper maintenance and repair for public vehicle due to lack of  spare parts  and  tools.    The  Study Team decided  to provide  spare parts  and tools along with Commuter Buses for sustainable use. 

2.4. Road Sector 

2.4.1. Overall View of the Road Sector 

(1) Existed Conditions of Road Development 

By virtue of  its geographic  location, Kandahar  city has prospered by  trade not only with  other  domestic  cities  such  as  Kabul  and  Herat  but  also  with  neighbouring countries such as Pakistan and Iran. 

There are  two national roads; one  is connecting Kabul, Kandahar and Herat, and  the other  is  connection Kandahar  to  Spin  Boldak  down  to  Pakistan.    The  road  lengths 

Page 61: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-38 

from Kandahar to Kabul and Kandahar to Spin Boldak are about 460 km and about 180 km, respectively.    The conditions of these roads are very poor except for the parts  in cities.    The road pavement  is mostly almost nonexistent or cracked severely at many parts.   Moreover,  almost  all  bridges  of  these  roads  collapsed.    Japan,  the U.S.,  and Saudi Arabia jointly committed to rehabilitate the road from Kabul to Kandahar down to  Herat.    Japan  and  the  U.S.  selected  consultants  to  study  and  design  this  road section  for  reconstruction.    The Asian Development Bank  (ADB) also committed  the rehabilitation of the road between Kandahar and Spin Boldak. 

In the central area of Kandahar city, a national highway runs from east to west, and this road  is very  crowded with vehicles  for various  rehabilitation activities and  for other economic activities.    Constant  traffic congestion  is observed at  the  intersection  in  the city centre especially during the rush hours in the morning and evening. 

Roads and streets, which form the city blocks, are allocated in a grid pattern in parallel to  and  at  right  angles with  the national  road.   Many  roads  in  the  city have narrow width, and especially the roads in the old city area have only about 6 m width. 

The Kandahar municipality has an old city master plan, which was prepared about 30 years ago, and the road network within the city has been constructed based on the plan.   With the increasing inflow of returned refugees and IDPs, the surrounding area of the city  is  occupied  with  their  settlement,  and  the  roads  in  this  area  are  used  in  a disorderly manner. 

(2)  Road Pavement 

There are roads of about 100 km length in total in Kandahar city, of which about 30 km are paved by asphalt, and the remaining 70 km have not been paved.    Because of less rainfalls and dry climate, unpaved  roads are heavily covered by  sandy dust.    Every car driving on such unpaved roads  lifts a cloud of dust  in  the air as  it passed along, which leads to almost zero visibility.    Also, dust causes various diseases, particularly respiratory diseases.    The municipality sprinkles water on streets by using a sprinkler truck every morning and evening, and also spreads crushed stones on roads to control dust  fling.    However,  it  appears  to  be  almost  totally  ineffective  because  of  the extremely dry climatic condition.   

There is a truck yard located in the old city area, where many heavy‐duty freight trucks with  full  loads go  in and out.    These  trucks are  in  fact prohibited  from entering  the city centre.    They enter and exit the truck yard, however, through the roads located in the  southern  part  of  the  city.    These  roads  are  largely  unpaved,  and  therefore,  the vehicles driving through the roads raise heavy clouds of dust.    The municipality has a plan  to make  these  roads  a  by‐pass  road  of  the  existing  national  road  that  passes through the central area of the city. 

Page 62: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-39 

Old City

Mirwize Hospital

Court

Gate To Kabul

To Pakistan To Herat

National Highway

National Highway

Paved Road

Unpaved Road

Under Paving Road

 Figure 2‐11  Road Network and Conditions of Road Paving in Kandahar City (2002) 

(2) Road Constructions and Maintenance 

Roads  in  Afghanistan  were  constructed,  operated  and maintained  for  a  long  time directly by governmental agencies.    In Kandahar, the Kandahar municipality and the Public Works Authority  (PWA which  is  under  the  control  of  the Ministry  of  Public Works  in  Kabul),  are  the  responsible  agencies  for  construction,  operation  and maintenance  of  roads.    In  principle,  the  municipality  is  responsible  for  the  roads within the city area, and PWA is responsible for the roads outside the city area.    These two agencies maintain staff, workers and construction machinery within the respective jurisdictions.    Due  to  insufficient budgets and staff, as well as  inadequate machinery in  terms  of  quantity,  performance  and  conditions,  their  operational  performance appears to be quite low. 

(3) Issues 

1) Dust from Unpaved Roads within the City 

The unpaved roads need to be paved as soon as possible, since they cause damage to the  health  of  the  city  inhabitants.    Paving  of  roads  in  Kandahar  city  is  urgently needed. 

2) Insufficient Construction Equipment of Public Sectors 

The municipality  and  the  PWA  want  to  pave  all  roads  in  and  around  the  city  to improve the poor road conditions.   However, they do not have adequate quality and quantity  of  equipment  for  road  construction  and  maintenance,  and  they  cannot improve  the  situation  due  to  shortage  of  annual  budget.    There  is  a  real  need  to provide  them with  reasonably  adequate  number  and  quality  of  equipment  for  road 

Page 63: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-40 

construction and maintenance as soon as possible.    At  the same time, workshops for proper maintenance of the equipment should be developed. 

3) No Future Plan on the City and Road Development 

The  existing  Master  Plan  was  prepared  almost  30  years  ago  and  the  situation  of Kandahar city has completely changed over the period particularly due to continuous drought  damages  and  long‐lasting  civil war.    A  new master  plan  of Kandahar  city associated with a  road master plan needs  to be  formulated  for  the  rehabilitation and development of the city. 

2.4.2. Selection of the Roads 

Based on discussions with the Kandahar Municipality, the Study Team decided to put high priority among the urgent projects to rehabilitate the following roads. 

(1) 6.0 km By‐Pass Road (Batch 1) 

This route consists of  five roads with about 6.0 km  length.    These  five roads exist  in the southern part of the city and run from east to west.    This route serves as a by‐pass of the existing national highway running through the city centre, and many trucks use this  route.    Except  for  some  short  sections, almost all  the parts of  this  route are not paved yet. 

(2) 2.3 km City Road (Batch 2) 

This  route  has  about  2.3  km  in  length  reaching  from  the  city  centre  to  the Mirwis Hospital.    This route is also unpaved.   Many people visit the hospital by vehicle and then wait in front of the hospital for their ride.    In addition, there are many donor and NGO  buildings  along  the  route.    Therefore, many  vehicles  are  driving  through  the route, which causes a serious problem of dust. 

(3) Kabul‐Kandahar Road (Batch 1) 

In addition, the Study Team decided to rehabilitate Kabul‐Kandahar Road from 5 km point to 20 km point in order to meet the growth of long‐haul traffic. 

2.4.3. Design Policy and Concept 

Design policy and concept can be summarised as follows: 

‐  Asphalt pavement and construction of concrete ditches provided within the existing road width     

‐  Alignment, width,  and  asphalt  thickness of  roads designed based on  local experience 

Page 64: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-41 

‐  Existing houses/buildings along the route principally not demolished   

‐ Future traffic volume and axle loads considered for the pavement design 

2.4.4. Implementation of the Projects 

(1) 6.0 km By‐Pass Road (Batch 1) 

The outlines of the routes selected are shown below. 

Table 2‐19  Outline of the Routes Road  Length (m)  Width (m)  Remarks A  2,400 14.0~16.0  Unpaved B  840 13.0  Unpaved C  1,170 16.0  Unpaved D  550 16.0  Unpaved E  1,000 26.0  Unpaved, median 

Total  5,950    Source: Study Team 

The  contract  for  road  construction work was  signed on 22  January 2003.    The work started in January 2003 and was completed in August 2003. 

(2) 2.3 km City Road (Batch 2) 

The  contract  for  road  construction  work  was  signed  on  24 May  2003.    The  work started on May 2003 and was completed in August 2003. 

  Figure 2‐12    6.0 km By‐Pass Road  Figure 2‐13    2.3 km City Road 

(3) Kabul‐Kandahar Road (Batch 1) 

The  contract  for  road  construction work was  signed on 4 February 2003.    The work started in December 2002 and was completed in March 2003. 

Page 65: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-42 

 Figure 2‐14  Kandahar – Kabul Road 

2.4.5. Operation and Maintenance 

At this moment, the rehabilitated roads have no damage and Kandahar Municipality is concentrating on paving new  roads.    However,  the municipality should monitor  the exact condition of all rehabilitated roads; it should receive a share of some budget for maintenance before the road conditions begin to deteriorate. 

2.5. Sanitation Sector 

2.5.1. Overall view of Sanitation Sector/ Garbage of Kandahar City 

(1) General 

Solid waste of Kandahar city can be classified as the scrap of sundry bricks and mud from  civil  construction  sites, agro‐wastes  including kitchen waste, plastics and night soil from houses.    Some people throw the solid waste into a garbage bin/bench; others throw it on roadside or gutter.    The garbage is not removed totally and some remains in the same places.    Data of garbage was not available, but a lot of soil and mud was found  in garbage  trucks  and  the poor  sanitation  in  the  city  affects  the health of  the urban population. 

General information from interviews and municipality profile: 

Solid waste generated per day:  350 ton/day    (630g/day/people)  Solid waste removed per day:  108 ton/day    (200g/day/people)  Number of vehicles of municipality:  15 trucks but only 9 trucks are functioning  Staff in the municipality for solid waste management:    210  Expenditure of municipality for solid waste (year of 2002):     

a.  Salary  (2,700,000afg×210×12 month)= Afg. 6,804,000,000 (US$136,080‐) b.  Fuel  (70km÷7km/liter×4 trip×300 day×Afg. 11,000/liter×9 truck)   = Afg. 1,188,000,000 (US$23,760‐) 

c.  Maintenance: N.A   

Page 66: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-43 

  Total : Afg. 7,992,000,000 (US$160,000‐/year)   Unresolved solid waste in city:    242 ton/day  Industrial waste:    N.A  Medical waste:    N.A  Garbage dumping places (bin/bench):  270 places  Dumping site:  Koto moreha, 15 km from city to the north.    Dumping site will be 

replaced because it is affecting ground water resources. 

(2) Existing Project for Solid Waste Management 

The project of health education and  community‐based waste  collecting  is ongoing at several areas in Kandahar city by collaboration of UN Habitat.    This programme is an essential  activity  for  health  as well  as  proper management  of  solid waste.    Due  to limited  funding,  however,  activity  is  still  small  scale.   More  funds  are  needed  to expand the activity of health education in the city and surrounding area.    Summary of the project is as follows: 

1) Background and Activities:   

It is impossible to collect garbage by truck in downtown area due to the narrow roads.   Given this situation, groups were formed for garbage collection from these city areas.   These groups  collect  the garbage  from houses and  transfer  it  to a  rubbish bin/bench located on main road.    Each house has to pay Afg. 30,000/month to the group  leader for  this  work.    At  present,  450  households  are  participating  in  the  activity.    One group consists of 40 to 50 houses. 

Simultaneously,  female  facilitators  are  going  house‐to‐house  in  pairs  to  pass  on  the basic health and hygiene message  to  the  families.    In addition, some members go  to girls schools, teaching about the benefit of having a clean environment and the need for a viable system of solid waste management with students. 

2) Project duration 

Project duration was one year from August 2002. 

3) Project member:   

Under  one  General  Supervisor,  several  supervisors  and  facilitators  carried  out  the project in communities as follows: 

Table 2‐20  Member for the Project for Solid Waste Management   District 1~4 (p) District 5 (p)  District 6 (p)  Total (p) Supervisor  1×4  2  8  8 Facilitator  4×4  8  8  32 Grand total  20  10  10  40 Source: Study Team 

Page 67: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-44 

2.5.2. Selection of the Project 

Statistics on exact waste and population is not available in Kandahar city.    According to  interviews  and  field  survey,  solid  waste  is  increasing  due  to  the  increasing population and this trend has continued since the collapse of Taliban regime.    There is no  proper management  of municipal  solid waste;  therefore,  construction waste  and night soil are left on roadsides and garbage bins. 

Kandahar city has 15 trucks with capacity of about 1 to 1.5 tons.    All of the trucks are very old and 6 trucks were not functional in October 2002.    UN‐Habitat donated four (4)  second‐hand  3‐ton  capacity  trucks.    At  that  time,  maximum  collection/ transportation capacity of these 13 trucks was estimated at about 100 tons a day. 

There  is  no  correct  and  reliable  data  on  solid waste  generation.    According  to  the calculation made from the HABITAT study, about 350 tons of solid waste is generated in Kandahar city, but only about 250 tons of waste is transported out of the city daily. 

There is no proper solid waste management in the city, so waste from construction sites and  night  soil  is  also  thrown  away  and  left  in  garbage  bin/box.    Solid  waste management  in Kandahar City  is  a major  issue  because  of  the  lack  of  not  only  the collection  system  itself,  but  also  planning  as  well  as  collection  and  transportation vehicles.    Therefore, solid waste  is affecting  the municipality environment as well as the health of the urban population. 

Because of this critical situation, even before making a solid waste management plan, additional vehicles are urgently needed.    Upon discussion with the Municipality, the Study Team decided  to  supply  cargo  trucks  for  solid waste collection use as Batch 2 component. 

2.5.3. Design Policy and Concept 

The Study Team considered that the minimum number of trucks would be supplied as urgent need by Batch 2 component.   

It might  be  possible  to  decrease  40%  of  the  solid waste  by  controlling  construction waste and night soil in the future.    Requirement of additional trucks is as follows: 

‐  40% waste reduction, so 350 tons×60%=210 tons (waste generated in one day) 

‐  210 tons of waste to be collected daily – present collection capacity of 100 tons = 110 tons (additional 110 tons required to be collected)   

‐  110  tons÷(3‐ton  capacity/truck×4  times  of  collection/day)  =  10  additional trucks (with capacity of 3 tons per truck) 

Page 68: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-45 

Due  to  lack  of  data  and  according  to  the  working  capacity  of  municipality,  it  is recommended that one third of the requirement, i.e., 3 trucks, be supplied as an urgent requirement.     

Specification of trucks is as follows: 

‐  Popular truck in Kandahar for easy maintenance 

‐  Flat Bed type 

‐  Left side steering 

‐  Diesel engine car 

2.5.4. Implementation of the Project 

The vehicles were handed over to the Kandahar Municipality at the end of November 2003. 

 Figure 2‐15  Garbage Truck 

2.5.5. Operation and Maintenance 

(1) Staffing 

One  (1) driver,  1 policeman  and  4 workers  for  a  total of  6 persons  are  required per truck. That means 18 additional workers for 3 trucks.    The municipality could manage these additional 18 workers from within its own manpower of about 210 at that time. 

(2) Cost 

•  Fuel  for  trucks  =  round  trip  30km/6km/liter×4  times/day×3  trucks×25 days/month×12 months×Afg. 20/liter = Afg.360,000/year (US$ 7,500) 

•  Others (spare parts, etc.) = Afg. 3,000×12 months×3trucks     = Afg. 108,000/year (US$ 2,250) 

Total expenditure for the operation of 3 trucks = Afg.468,000(US$9,750) 

Page 69: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2 

   

2-46 

(3) Operation and Maintenance 

The municipality  was  under  rehabilitation/restructuring  and  it  seemed  that  it  was difficult  to manage all of  the expenditures  for  the operation of  the additional  trucks.   So  temporarily, HABITAT  is  bearing  the  cost  of  operation  and maintenance  for  two years.    The municipality should prepare to shoulder this expense within two years. 

Page 70: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

   

3-1

CHAPTER 3 

Constraints and Measures to Implement the Urgent   

Rehabilitation Project 3.1.  Introduction 

Due  to  the  long‐lasting conflict and  the accompanying  socio‐economic problems,  the construction  industry  in Afghanistan has been completely devastated along with  the complete destruction of privately owned  construction machinery  and  equipment. To make matters worse, many experienced engineers and skilled workers were forced to flee  the  country. As a  result,  few  remaining  local  contractor  companies have enough capacity to maintain work quality in accordance with the technical specification.   

Since the collapse of the Taliban regime, a number of construction projects have started on various  facilities, not only  the public ones such as schools and hospitals, but also private offices and houses. Many  local contractors and merchants have been engaged in various construction activities mostly with foreign investors. Therefore, it is not rare for a  small construction company  to  receive more  than one contract  regardless of  its limited capacity. 

However,  according  to  the Draft National Development  Framework1  formulated  in April  2002,  one  of  the  principal  strategies  of  the Government  is  to  use  the  external assistance to build the physical infrastructure that lays the basis for a private‐sector‐led strategy of growth,  in  such manner  as  to  support  the building of human  and  social capital.  The  Government  considers  that  the  recent  rehabilitation  and  rebuilding activities  assisted  by  international  donor  agencies  and  NGOs  should  work  as  an effective leverage to revive the damaged economy of Afghanistan. 

Taking  this  Government’s  strategy  into  consideration,  URSP‐KDH  plans  to  employ Afghan  contractors  for  the urgent  rehabilitation projects,  although  there  are  risks  to complete  projects with  the  limited  capacity  of Afghan  contractors. As  a  result,  the construction projects could contribute to job creation in the project area. Tables 3.1 and 3.2  show  the  number  of  workers  employed  by  Batch  1  and  Batch  2  construction projects. 

                                                      1  The Draft was formulated for consultation with relevant agencies and organisations under the initiative of the

Board of the Afghan Assistance Coordination Authority (AACA).

Page 71: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-2

Table 3.1 The Number of Workers (Batch 1 Urgent Rehabilitation Projects) 

 

    

Table 3.2 The Number of Workers (Batch 2 Urgent Rehabilitation Projects) 

 

For  managing  the  local  contractors,  the  Study  Team  organised  the  Construction Management Service (CMS) Team, which consists of Japanese Site Representative and Chief  Supervisor,  and  seven  local  Field  Coordinators.  They  are  manage  quality assurance,  progress  control,  contractual  management,  and  other  construction supervisory  services  on  a  day‐to‐day  basis.  The  CMS  Team  prepared  a  Monthly Progress Report and  submitted  it  to  relevant Afghan and  Japanese agencies,  starting from November 2002 up to September 2004. The Monthly Progress Report covered the progress of work,  certification of payments, problems  encountered and  the  remedial actions undertaken, design changes approved or ordered, and other particular  issues which  occurred  during  the  reporting  month.  Also,  the  Monthly  Progress  Report touched  on  the  major  activities  to  be  undertaken  in  the  following  month.  The organisation of the CMS Team is shown in Figure 3.1. 

2003 2004

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

1,202 1,460 2,075 0 0 0 0 0 0 0 0 0 0 0

349 444 266 293 322 250 321 309 426 313 337 394 607 328

201 600 991 1,122 901 613 391 704 521 1,036 1,566 1,090 1,629 1,666

405 581 414 412 293 215 51 453 521 625 647 811 796 1,145

581 565 384 458 397 555 403 616 418 576 714 258 991 1,034

2,738 3,650 4,130 2,285 1,913 1,633 1,166 2,082 1,886 2,550 3,264 2,553 4,023 4,173

Mirwais Mena

TOTAL

Batch 2 UrgentRehabilitation Projects

Kaka Sayed Ahmad

City Road Batch 2

Aino

Sufi Saheb

2002 2003 2004

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

93 565 393 294 368 297 414 445 366 422 751 473 512 477 472 939 614 573 209

121 367 137 319 300 338 288 439 348 406 340 183 310 324 181 481 248 206 0

90 326 164 358 285 285 436 459 342 504 614 260 205 427 382 361 165 368 0

116 209 166 318 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 305 2,106 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 680 1,103 3,549 5,124 4,716 5,257 4,275 810 0 0 0 0 0 0 0 0 0 0420 2,147 2,268 6,944 6,077 5,636 6,395 5,618 1,866 1,332 1,705 916 1,027 1,228 1,035 1,781 1,027 1,147 209

Batch 1 UrgentRehabilitation Projects

Ahmad Shah Baba

Zahir Shahi

Malalai

Mirwais Hospital

KK Road

City Road Batch 0(1)(2)(2) TOTAL

Page 72: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-3

PCI Tokyo Head Quarter

Project Manager

Mr. S. KAWASAKI

Assistant Manager

Mr. H. KANAI

Chief Architect

Mr. T. SHIMOSEJICA/PCI Kandahar

PCI Kabul Office

Project Manager

Mr. S. KAWASAKI

ADMI. Team

JICA Kandahar Office

Government of Japan

Embassy of Japan

JICA Afghanistan Office

SC: Site Coordinator CC: Construction Coordinator

ARCHI. Team

Team Representative

Mr. T. MORIKAWA

Chief Supervisor

Mr. A. AIKAWA

C.C

Mr. Nazir

Coordinator

Mr. Khalid

Engineer (ME)

Mr. Hayat

Architect

Architect

Mr. Mohamad

SC

Mr. Ezzat

Chief Coordinator

Mr. K. YOSHIDA

Architect

Mr. Anwar

OM: Office Manager

OM

Mr. Usman

Secretary

Mr. Maqsood

Team Representative

Mr. K. OBARA

Guard

Guard

Guard

Guard

Guard

Guard

Office Boy

Mr. Asadullah

Receptionist

Mr. Yahya

Driver

Driver

Driver

Driver

Driver

Driver

Driver

Road Team

FE: Field Engineer RD: Road Coodinator

Team Representative

Mr. I. TANAKA

Chief Engineer

Mr. H Sherzai

Engineer

Mr. Toryalai

FE.

Mr. Majeed

Engineer

Mr. Zahir

RD.

Mr. Ali

Eng.

Mr. Naseem

Eng.

Mr. Mahmo

od

Soft Component

 

Figure 3.1 Organisation Chart of CMS Team   

The  CMS  Team  had  difficulty  in  managing  contractors  that  did  not  have enough experience  in  large‐scale  construction projects during  the war period, but as  it  is stated below,  the  transfer of construction  technology  to contractors and  priority  considerations  practiced  during  the  situation  particular  to  the project area carried the project to success. 

3.2.  Constraints 

(1)  Contractorʹs Financial Basis 

It  is generally  said  that  there  is an absolute  lack of  financial  capacity  for  reasonably sustaining  project  cash  flow.    No  contractor was  able  to  arrange  a  bank  guarantee, although  it was required  for advance payment  to  the  local contractor as performance security.    In addition, some contractors faced lack of funds for implementation of the Project. 

(2)  Lack of Banking System in Kandahar 

During  the  implementation  period,  in  spite  of  the  booming  economy  caused  by  a number  of  reconstruction  projects,  none  of  the  local  or  international  banks  opened branches in Kandahar. The construction payment should have been paid though bank remittance  from  the  viewpoint  of  security,  but  the CMS Team was  obliged  to make payment by cash. 

Page 73: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-4

(3)  Materials and Human Resource 

Price  of  construction material  was  not  stable  due  to  the  recent  booming  economy stimulated by the rush of construction projects including rehabilitation and rebuilding activities by international donor agencies and NGOs. In addition, there was shortage of labourers  as  well  as  experienced  technicians  in  the  project  area.  Especially  during harvest and summer season, the contractors faced the lack of not only skilled workers, but also  labourers. Many contractors  tried  to cover  this constraint by hiring Pakistani workers, but  these unsettled foreign workers  tended  to  leave  the construction site for their homeland especially when the security risks became high. Also, the contractor has been faced the problem of cost inflation of labour wages. 

(4)  Seasonality 

The critical path of  the construction work  is concreting works due  to  the hot climatic conditions in Kandahar during the months of June‐August. As can be seen in the table below, the average of the temperature in summer season reached more than 40 degrees. Therefore,  the  temperature  of  concrete was  carefully  checked  at  the  site  during  the summer  season.    In order  to minimise  risk,  and  to maintain  the quality of  concrete during  the  summer  season when  the  temperature  is high, water  is  sprinkled on  the portion of the concrete casting.  

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Year/Month

pers

on

0

5

10

15

20

25

30

35

40

45

50

Cel

sius

2,738 3,650 4,130 2,285 1,913 1,633 1,166 2,082 1,886 2,550 3,264 2,553 4,023 4,173 Avarage of Low Temparature  

Figure 3.2  Relation Between Temperature and Number of Labourers at the School Construction Site 

Page 74: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-5

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Jan-00

Year/Month

pers

on

0

5

10

15

20

25

30

35

Cel

sius

Number of Workers (Accumulative) Avarage of Low Temparature 

Figure 3.3  Relation Between Temperature and Number of Labourers at the Road Construction Site 

(5)  Security 

The security situation in Afghanistan is still unstable, especially in southern provinces including Kandahar. The Team was sometimes forced to suspend the works or to leave Kandahar when a security alert was given. 

3.3.  Measures Against the Constraints

(1)  Limited Ability of Local Contractors 

In order to maintain quality standards in accordance with the technical specifications, the CMS Team arranged on‐the‐job training for concrete mixing, sampling specimen of concrete cube, slump test, re‐bar arrangement, form works and so on.    Also, the CMS Team provided detailed drawings  and  shop drawings  for  the  construction works  to local contractors for easy reference. 

The CMS  Team  also  provided  concrete  compression  testing  equipment  to  the CMS office  for checking  the actual concrete strength of  the concrete  test pieces  from every site.    One‐week concrete strength and  the  four‐week concrete strength were checked by the test machine, and the proper measures were executed to solve any  insufficient grade of the casting concrete. 

Page 75: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-6

 

 

 

 

 

 

 

 

 

 

 

 

 

(2)  Contractorʹs financial basis 

Due  to  absolute  lack  of  financial  capacity  of  contractors,  advance  payment  was cancelled  and  10%  retention  was  applied  from  each  payment  instead  of  a  bank guarantee. Monthly payment was applied based on the mutual understanding despite the  original  agreement  between  the CMS  Team  and  the  contractors  for  the  smooth implementation of the work. 

(3)  Materials and Human Resource for Construction Works 

To avoid shortage of materials,  the CMS Team provided a special advanced payment arrangement to keep enough material stocks. The lack of skilled construction workers was addressed by hiring foreign workers for the works, which required advanced skills. But  in  exchange,  the  contractors  faced  cost  inflation  of  skilled  labour wages.  These constraints affected construction schedule. 

(4)  Concrete Casting in Summer Season 

The  temperature  of  concrete  casting  was  carefully  checked  at  the  site  during  the summer  season.  In order  to keep  the quality of  concrete during  the  summer  season 

Page 76: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

3-7

when  temperature  is high,  the quality of  the  concrete was  controlled directly by  the CMS Team by curing the concrete carefully. Of course, the temperature at each site was checked more frequently and more carefully than usual. 

3.4.  Conclusions and Recommendations 

There were various constraints on construction works in regard to establishing a fluid labor environment as described above. There were no simple measures  to  remove or loosen any of these constraints, but the following measures or approaches might have been the keys for successful outcome. 

Building the Capacity of Contractors 

As  described  above,  few  local  contractors  had  enough  capacity  to  maintain  work quality  in  accordance  with  the  technical  specification.  However,  some  contractors successfully developed  their  capacity  by practice during  the project.  For  example,  a contractor who undertook the construction of one of the Batch 1 schools learnt various management  skills  such  as  progress  management,  quality  management,  cash  flow management, and procurement management, so that the contractor developed enough capacity and accountability to receive another contract for a Batch 2 school. 

A Multi‐Criteria Approach to Contractor Selection 

As  described  above,  contractors  tend  to  receive  several  contracts  regardless  of  their limited  capacity.  Therefore,  special  care  should  be  taken  in  selecting  contractors.  In addition  to document  compliance,  technical  evaluation  and bid price, more detailed criteria  such  as  the  ability  for  cash  flow  management,  project  portfolio,  and organizational  background  should  be  applied  for  selection  in  order  to minimise  the risk caused by the lack of contractor ability. 

Page 77: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

   

4-1

CHAPTER 4 

SCHOOL MAINTENANCE IMPROVEMENT PROGRAMME (SOFT COMPONENT) 

4.1. Introduction 

School  Maintenance  Improvement  Programme  was  a  soft‐component  programme under URSP‐KDH.    The  purpose  of  the  programme was  effective  utilisation  of  the school  facilities  that  were  rehabilitated/constructed  under  the  Programme.    In addition  to  the  reconstruction of physical  facilities,  it was necessary  for efficient and sustainable utilisation of the constructed facilities to conduct a programme facilitating effective use of the facility.   

Lack  of  maintenance  skills,  tools  and  system,  however,  are  major  constraints  for effective  use  of  school  facilities  in  Kandahar  city.    There  is  no  efficient  support programme  to develop  the maintenance system of school  facilities.    Lack of hygiene knowledge such as on use of toilet, on the other hand, has caused diarrhoea and other infectious diseases  specifically  to  children  in  the  region.    The programme  strived  to improve the condition of school maintenance, including hygiene issues.   

4.2. Scope of the Programme 

For  the  purpose  of  improvement  of  the  above  condition,  main  objectives  of  the programme were the following: 

To  enable  teachers,  students  and  other  stakeholders  to  utilise  the rehabilitated/constructed school facilities effectively; 

To  establish  maintenance  system  for  the  effective  use  of  school  facilities  in Kandahar city; and 

To improve the hygiene conditions in the neighbouring communities. 

Beneficiaries of the programme were the Department of Education (DOE) and selected three  schools  (Ahmad  Shah  Baba  School,  Zahir  Shahi  School,  and Malalai  School).   The Study Team decided to implement the programme for three of the seven schools, because  teachers  of  the  remaining  four  schools  were  not  available. 1     Therefore, training courses were conducted at the three schools.    For the purpose of expanding to the remaining schools and establishing an effective school maintenance system for all schools  in Kandahar city and providing a hygienic school environment  in  the  future, DOE  was  involved  in  the  programme  implementation  as  a  key  player  of  school maintenance.     

                                                      1  The remaining four schools were still under construction when the programme commenced. 

Page 78: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

4-2

The main components of the programme were: 

Component 1:    Study  of  an  appropriate maintenance  system  for  school  facilities  in Kandahar city 

Component 2:    Training on operation and maintenance of the school facilities   

Component 3:    Hygiene education   

4.3. Implementation of the Programme 

The Study Team subcontracted the programme to a capable international NGO named International  Catholic Migration  Commission  (ICMC)  as  the  implementing  partner. The Study Team and the implementing partner carried out the programme at the three schools and used several methods in order to gather stakeholder opinions concerning improvement of hygiene conditions as well as effective use of the facilities.    Also, the implementing partner studied ways of how to sustain an effective maintenance system for school facilities in Kandahar city.   

The  Study  Team  and  ICMC  held  several  discussions  about  detail  contents  and methodology of the programme beginning July 2003.    On 11 August 2003, ICMC held a  stakeholders  workshop  on  school  maintenance  in  the  dining  room  in  Mirwais Hospital  (which  was  rehabilitated  by  URSP‐KDH),  inviting  a  broad  range  of stakeholders  such  as  governmental  officers,  principals,  teachers,  academics,  donors and NGOs.    The participants discussed  the  issues of past  and  existing maintenance systems  and  idea  of  appropriate  school maintenance  system.  The  programme  was completed by the end of November 2003, after the implementation of training courses.   

   Figure 4.1    Stakeholders Workshop 

The following is a summary of the results of the programme. 

Around  40  participants  discussed maintenance issues  Stakeholders  Workshop  at  Mirwais Hospital on 11 Aug 2003 

Page 79: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

4-3

Component 1: Study of an appropriate maintenance  system  for  school  facilities  in Kandahar city 

ICMC  conducted  a  large  number  of  interviews  and  group  discussions  with  the provincial education department  in Kandahar, school staff and students at  the  target schools and others  in Kandahar city and Kabul.  Interviews have also been held with the head  of  the maintenance department  at  the Ministry  of Education  in Kabul. All interviewees  cited  the  lack  of  resources  as  being  the  major  obstacle  to  proper maintenance of schools. The lack of resources cause the following effects: 

Overcrowding  Lack of discipline  Lack of community involvement in the schools    Low level of funding for maintenance  Lack of staff dedicated to maintenance  Lack of knowledge of staff generally 

The  implementing  partner  submitted  a  proposal  for  an  appropriate  school maintenance system in Kandahar to the DOE in November 2003 after a series of studies and discussions with the Study Team. The proposed maintenance plan emphasised the importance  of  community  involvement,  school  initiative  concerning  small‐scale maintenance activities, and maintenance training. The specific aspects of maintenance of physical infrastructure covered the following areas: 

The school surroundings  The buildings and walls  Carpentry items: desks, chairs, doors, windows, etc.  Electrical systems and related materials  Stores or warehouse  Water sources, hand pumps, tube well  Use of toilet  Fruit‐bearing plants and flowers at school 

Component 2: Training on operation and maintenance of the school facilities 

The  implementing partner conducted  the  training programme at  the  three schools  in September 2003 parallel with the maintenance study. There were 36 trainees including teachers and students who were expected to be responsible for maintenance activities. The  training  curriculum, which was developed  from  the process of  the maintenance study, covered the following areas: 

What is maintenance?  What needs to be maintained?  Who does the maintenance?  Using maintenance tools/materials 

Page 80: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

4-4

Budgeting  Avoiding potential pitfalls 

For  the purpose of practical  training,  in addition, maintenance kits  such as  spanners and hammers,  among  other  tools, were distributed  to  the participants  or  schools  as training materials.   

Component 3: Hygiene Education 

Hygiene education at the three schools was conducted in September 2003.    A total of 36 participants  including headmasters,  teachers, and  students  learned about hygiene issues using hygiene education materials made by Save the Children Alliance in Kabul and UNICEF.    The training curriculum covered the following areas: 

Who to target for hygiene education?  What is personnel hygiene?  Drug abuse  The importance of exercise for good health and hygiene  The importance of a clean environment for good hygiene  General health and hygiene message  Proper use of toilets 

In addition, ICMC distributed hygiene packs containing soap, toothbrush, tooth paste, nail clippers, and glycerine for dry skin to 7,500 students in the target schools.   

The detailed  result of  the programme  is  shown  in Part 3, Appendices on  the Urgent Rehabilitation Projects. 

4.4. Conclusions and Recommendations 

As of the end of URSP‐KDH, maintenance tools have been distributed not only to three schools in Batch 1 component but also to four schools in Batch 2 component. The Study Team evaluated  the Programme  in  January 2005. Principals and  teachers of  the  three schools practice maintenance and hygiene activities continually, and keep the facilities clean, although timing of the training programme was inappropriate due to the delay of construction works of target schools.   

The proposed maintenance plan, on  the other hand, has been mentioned by  the DOE staff  since  its  submission.  However,  the  plan  has  not  been  institutionalised  as  a maintenance  system  of  DOE  yet  because  of  the  frequent  replacement  of  directors during  the  implementation  period  and  lack  of  their  support.  For  the  purpose  of promoting  the  proposed  activities,  the  Study  Team  discussed  the  system  with  the Director and how to make effective use of it. The Director promised use of the proposal to  improve school maintenance  in Kandahar.  It  is necessary  for DOE  to  integrate  the plan into its maintenance system. 

Page 81: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

   

5-1

CHAPTER 5 

EVALUATION OF URGENT REHABILITATION PROJECTS 5.1.  Introduction 

A variety of rehabilitation and reconstruction needs in Afghanistan have emerged after the  23  years  of  prolonged war.  The  society  of Afghanistan  has  been  badly  affected politically,  economically,  and  socially  by  the war.  In  order  to  cope with  the  urgent needs,  URSP‐KDH  has  undertaken  the  rehabilitation  of  seven  schools,  Mirwais Hospital, and city roads in Kandahar city. It is important for a post‐conflict country to consider  the problems attributable  to  the conflict while responding  to various urgent rehabilitation and reconstruction needs.     

In  this  chapter,  the  Study  Team  evaluates  the Urgent  Rehabilitation  Projects  under URSP‐KDH  considering  the  peacebuilding  needs  and  the  governmental  policy  of Afghanistan. In addition, a comprehensive evaluation for all projects using quantitative and  qualitative methods was  conducted  during  the  final mission  of URSP‐KDH  in January  2005.  Considerations  on  future  aid  activities  in  the  post‐conflict  situation, moreover,  are  to  be  given  as  recommendations.  Such  considerations  have  been formulated chiefly as a result of the seminar in January 2005 as well as discussions with the government of Afghanistan, donor agencies and NGOs. 

5.2.  Rationale 

5.2.1.  Conflict Prevention   

Violent  conflict  is  a  serious obstacle  to  socio‐economic development  and    quality of life.  It  destroys  civilian  livelihoods,  infrastructures,  and  environment.  Thus,  for sustainable  development  and  durable  peace  it  is  important  to  reduce  the  causes  of conflict  in  parallel  to  providing  emergency  relief  and  rehabilitation  of  destroyed infrastructures resulting from conflict. Also, for prevention of recurrence of conflict it is important to formulate projects considering conflict prevention.   

Kandahar  is  a  homeland  of  the  Pashtun  although  there  are  small  numbers  of  other ethnic  groups  such  as  Persion,  and  various  tribal  groups  within  Pashtun.  In  fact, Kandahar city as the urban area of Southern Afghanistan is a multi‐ethnic society and yet  there  is  no  significant  ethnic  confrontation.  Thus,  urgent  rehabilitation  projects were selected not by considering ethnic balance, but by other factors such as promotion of  public  education  especially  for  girls.  Promotion  of  public  education  and empowerment  of  women  to  contribute  to  the  healthy  modernisation  and democratisation process of the post‐conflict Afghanistan.   

Page 82: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-2

Also, visible improvements such as the construction of school buildings, paving of city roads, and supply of vehicles made civilians  feel hopeful about positive change  from war to peace. 

5.2.2.  Government Policy 

For  the  purpose  of  establishing  a  strategic  road  map  toward  rehabilitation  and development in Afghanistan, the National Development Framework (NDF), the vision of Afghan government, was prepared  in April  2002 by  the AIA  in  cooperation with donors.    In  accordance  with  NDF,  the  National  Development  Budget  (NDB)  and National Priority Program were  established  in October  2002,  and  then were  revised responding  to  the  transformation  of  rehabilitation  and  development  needs  of Afghanistan  thereafter. Figure  5.1  lists  the  areas  covered  by  the Consultative Group (CG)  and Advisory Group  (AG), which  included  chief ministries,  donors,  and UN agencies, and support to prepare the NDB.    Since the establishment of NDB, basically all development activities in Afghanistan have been positioned in the NDB. 

 

Figure 5.1 National Development Framework and Donor Support 

Many of the urgent rehabilitation projects under URSP‐KDH were selected before the NDB  was  established.  However,  those  projects  were  able  to  be  positioned  as Sub‐programs in the NDB as shown in Table 5.1. 

Pillar 1: Social and Human Capital 1.1 Refugee & IDP Return 1.2 Education & Vocational Training 1.3 Health & Nutrition 1.4 Livelihoods & Social Protection 1.5 Cultural Heritage, Media & Sport 

Pillar 2: Physical Infrastructure/ Natural Resources 2.1 Transport 2.2 Energy, Mining & Telecommunications 2.3 Natural Resource Management 2.4 Urban Management 

Pillar  3:  Public  Administration  Reform  and  Economic Management 3.1 Trade & Investment 3.2 Public Administration Reform and Economic Management 3.3 Justice 3.4 National Police & Law Enforcement 3.5 Afghan National Army (ANA) 3.6 Mine Action 3.7 Disarmament, Demobilization, and Reintegration (DDR) 

A1 Gender A2 Environment A3 Humanitarian Affairs A4 Human Rights A5 Monitoring & Evaluation A6 Counter Narcotics 

Consultative Group (CG)  Advisory Group (AG) 

Page 83: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-3

Table 5.1 NDB and Urgent Rehabilitation Projects Priority Program in NDB  Sub‐program in NDB  Urgent Rehabilitation Projects 

Education Infrastructure  Rehabilitation/ Construction of the seven schools 

Education & Vocational Training 

Teacher Development  Teacher training on school maintenance Improved Equitable Distribution of Quality Health Services 

Rehabilitation of Mirwais Hospital   Commuter Buses for Kandahar Nursing School Health & Nutrition 

Decrease Incidence of Communicable Diseases 

Hygiene education 

Urban Planning & Management 

Pavement of city roads Urban Management 

Urban Infrastructure  Garbage trucks for Kandahar municipality Source: Study Team 

5.3.  Evaluation of Urgent Rehabilitation Projects 

URSP‐KDH quickly responded to the rehabilitation needs in Kandahar city along with the  government  policy  and  peacebuilding  needs.  The  projects were  designed  to  be relevant  in  terms  of meeting  such  needs. Also,  the  projects  contributed  to  not  only increasing  the  number  of  facilities,  but  also  recovering  the  functions  of  schools  and medical  institutions. Quick  and  visible  rehabilitation made  people  of Kandahar  feel positive about change to peace from war.   

Concerning school construction, on the other hand, local contractors and workers were able  to  increase  their capacity  through  the construction works which were  instructed and  supervised  by  Japanese  engineers.  In  addition,  the  projects  contributed  to employment generation of many construction workers (92,4861). 

Evaluation of the urgent rehabilitation projects is summarised in Table 5.2. 

                                                      1  See detail in “Final Report Part 3 Appendices” of the project. 

Page 84: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-4

Table 5.2 Evaluation Summary of the Urgent Rehabilitation Projects Evaluation Items 

Rehabilitation of seven schools and Soft Component 

Renovation of kitchen and laundry at Mirwais Hospital 

Commuter Buses 

Pavement of City Roads 

Garbage Trucks 

Relevance    Meet the NDB and huge needs of classrooms in Kandahar City 

  Meet the NDB and needs of Improved Equitable Distribution of Quality Health Services 

  Meet the NDB and needs of Improved Equitable Distribution of Quality Health Services 

  Meet the NDB and needs of urban infrastructure 

  Meet the NDB and needs of Urban Planning & Management 

Effectiveness    Constructed 98 classrooms accommodating pupils who were in temporary classrooms (tents)   More than 18,000 

students (including 4,500 girls) can study at the constructed classrooms   Teachers have positive 

ideas for maintenance of school facilities 

  Improvement of food services and hygiene condition in the hospital   Kitchen provides 

meals for 410 (300 inpatients and 110 duty staffs)   More than 180 linens 

and gowns a day are washed by provided washing machine 

    72 female students and 16 female teachers are using the provided 5 commuter buses.

  6.0‐km By‐pass road and 2.3 km road was paved   Creation of 

the smooth transportation   Reduction of 

clouds of sand dust caused by the vehicular traffic. 

  3 trucks collect garbage in Kandahar city running 75km/day/each

Efficiency    There were delays of construction or implementation due to unstable security conditions   Scale and design of 

school building seem to be over local capacity (capacity of local contractors was insufficient) 

  There were delays of construction or implementation due to unstable security condition 

  There were delays of distribution due to unstable security condition 

    There were delays of construction due to unstable security condition 

  There were delays of distribution due to unstable security condition 

Impact    Increase enrolment and attendance of pupils   Capacity building of 

local contractors through construction works   Generate employment 

  Renovated dining room is used as place for workshops which are conducted by donors and government agencies   Capacity building of 

local contractors through construction works   Generate employment

  ‐    Reduce dust   Capacity 

building of local contractors through construction works   Generate 

employment 

  ‐ 

Sustainability    Maintenance of school buildings seems to be insufficient   Some of facilities are 

broken especially in toilet 

  Insufficient use of renovated dining room       Some provided 

machines are broken sometimes 

  There is an out of operation bus due to lack of budget 

  Kandahar municipality continues to pave city roads by its own initiative 

  UN Habitat supports Municipality financially 

Quick Response 

  Yes    Yes    Yes    Yes    Yes 

Visibility    Yes    Yes    Yes    Yes    Yes Source: Study Team 

(1)  Education Sector 

Although  98  classrooms,  which  are  built  by  the  urgent  rehabilitation  projects,  are insufficient  to  eliminate  the  practicing  of  double/triple  shifts  with  overcrowded conditions in classrooms and/or holding classes outside classrooms, the situations have been  much  improved  creating  more  available  space  for  education  through  the 

Page 85: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-5

implementation of  the Programme.    Approximately  18,600  students have  attend  the rehabilitated schools as shown in Table 5.3. 

Table 5.3 Number of Students (as of January 2005) 

Name of School  Gender Grades          Total Grand total  Teachers Total

  1  2  3  4 5 6  7 8 9 10 11 12      

Ahmad Shah Baba  Male  500 400 400 400 310 370 300 300 290 100 90 40 3,500 89High School  Female 0 3,500 0 89

Zahir Shahi  Male  310 370 370 377 420 436 472 417 347 299 169 112 4,099 99High School  Female 205 156 290 190 841 4,940 27 126

Malalai  Male  600 350 250 1,200 22High School  Female 650 600 320 245 110 65 48 2,038 3,238 25 47

Sufi Suhab  Male  560 462 467 596 182 118 72 40 35 12 2,544 58School  Female 0 2,544 0 58

Mirwais Mena  Male  0 3School  Female 305 242 117 118 33 23 838 838 16 19

Kaka Sayed    Male  400 240 490 750 240 360 200 45 2,725 39Ahmad School  Female 0 2,725 9 48

Aino  Male  0 1Middle School  Female 300 150 180 100 50 20 800 800 19 20

Total  Male  2,370 1,822 1,9772,123 1,152 1,2841,044 802 672 411 259 152 14,068 311  Female 1,460 1,148 907 653 193 108 48 4,517 18,585 96 407

Source: Study Team

Concerning maintenance of  school  facilities,  some problems have  emerged  since  the completion of construction. Some school facilities such as door handles and desks have been broken.    Especially  toilet  flush  system  seems not  to work very well. There are two factors for  the problem. One  is shortage of water due  to frequent power failures. Another is behaviour of students. Some students, especially boys tend to use facilities roughly  and  break  them,  although  teachers  often  remind  them  to  use  facilities carefully.2  Bad behaviour of students seems to be a serious constraint for maintenance of  facilities.  For  the  improvement  of  maintenance,  it  is  necessary  to  strengthen monitoring activities not only by  teachers but also by students  themselves, especially older  students,  through  enhancing  ownership,  and  to  guide  parents  through teachers/parents regular meetings such as PTA, as well as students. Fortunately, some principals have declared  their willingness  to  tackle  the  issue during  the workshop  in January 2005.3 

On the other hand, the Study Team found a positive aspect concerning the utilisation of the  constructed  facilities.  Some  schools  have  used  classrooms  differently  from  the original  design.  They  allocated  classrooms  based  on  their  educational  needs 

                                                      2  Teachers argue that a cause of bad behaviour of students seems to be lack of right guidance by their parents. These parents often are uneducated due to the prolonged turmoil in Afghanistan. (Interview with teachers and principals in January 2005) 

3  See details in Chapter 2 

Page 86: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-6

considering the numbers of pupils and shifts, syllabus and curriculum. It seems to be a good practise. Table 5.4 shows the utilisation of the classrooms as of January 2005. 

Table 5.4    Utilisation of the Constructed Classrooms School Original Design Utilisation as of January 2005

20 Classrooms

18 Classrooms 1 Head Teacher/Teachers Room 1 Laboratory

1 Store Room 1 Store Room

Ahmad Shah Baba High School

Pupils: 2,304 Teachers: 54

Pupils: 3,500 Teachers: 89

10 Classrooms

8 Classrooms 2 Computer Rooms

1 Store Room 1 Store Room

Zahir Shahi High School

Pupils: 6,564 Teachers: 115

Pupils: 4,940 Teachers: 126

9 Classrooms

7 Classrooms 1 Head Teacher/Teachers Room 1 Art Room

1 Staff Room 1 Store Room

1 Kindergarten 1 Store Room

Malalai High School (Girls)

Pupils: 1,249 Teachers: 24

Pupils: 3,238 Teachers: 47

21 Classrooms 22 Classrooms 1 Head Teacher Room 1 Teachers Room 1 Store Room

1 Head Teacher/Teachers Room 1 Store Room

Sufi Suhab School

Pupils: - Teachers: -

Pupils: 2,544 Teachers: 58

15 Classrooms 16 Classrooms 1 Classroom on a septic tank

1 Head Teacher Room 1 Teachers Room 1 Store Room

1 Head Teacher/Teachers Room 1 Store Room

Mirwais Mena School (Girls)

Pupils: n.a Teachers: n.a

Pupils: 838 Teachers: 19

15 Classrooms 15 Classrooms 1 Head Teacher Room 1 Teachers Room 1 Store Room

1 Head Teacher Room 1 Teachers Room 1 Store Room

Kaka Sayed Ahmad School

Pupils: - Teachers: -

Pupils: 2,725 Teachers: 48

8 Classrooms 8 Classrooms 1 Store Room 1 Store Room

Aino Middle School (Girls)

Pupils: n.a Teachers: n.a

Pupils: 800 Teachers: 20 

Source: Study Team 

(2)  Health Sector 

Before the rehabilitation of those facilities, Mirwais Hospital served only Afghan bread, tea and some vegetable soup to the patients, and linens were washed by hand.    Now Mirwais  Hospital  additionally  serves  rice  and  sometimes  meat.    Also,  linens  are 

Page 87: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-7

washed by washing machines with hot water, making work conditions more sanitary.   Through  the  implementation of  the Project,  the  services and environment have been much improved. 

As  for commuter buses, due  to  the  traditional customs,  female students of Kandahar Nursing  School  found  it  difficult  to  go  to  school  even  if  they  lived  nearby.   Now school buses  can pick  them up  right  in  front of  their houses and  families who have daughters can allow them to go to the school. 

Concerning maintenance  system  of  facilities  and  equipment  in  kitchen  and  laundry, however, it seems to be insufficient. Mirwais hospital does not have regular monitoring system  for maintenance or any checklists, although  it has a maintenance  team which responds  to  problems.  For  better  maintenance  and  sustainable  use  of  provided equipment, it is necessary to establish “preventive maintenance system4” such as early warning through regular monitoring.    The hospital may also have to consider training of managers as well as staff for hospital management. 

(3)  Road Sector   

Road conditions in Kandahar city have been improved drastically due to the paving of roads.  In  addition,  vehicle  traffic  no  longer  leaves  a  cloud  of  sand  dust  behind. Residents along the roads highly appreciate JICA’s visible support. The 6.0 km by‐pass road was named “Ogata road5” upon its completion. Now, Kandahar Municipality has started  to  pave  other  roads  on  its  own  to  create  a  better  environment  and  smooth transportation.   

(4)  Sanitation Sector 

Kandahar Municipality  is making effort  to address  the problem of garbage collection with the support from UN‐Habitat, although it has limited resources such as the lack of collection  vehicles.    The  donated  trucks  are  running more  than  75  km  per  day  to collect  and dispose of garbage  in Kandahar  city.    It  is necessary  to  establish  a  solid waste management programme6  for the municipality.     

5.4.  Seminar on URSP‐KDH 

For  the purpose of better  future  collaboration among  the  stakeholders, a  seminar on URSP‐KDH was held in January 2005 at the end of the Programme. The seminar venue was  the dining  room  in Mirwais Hospital, which was  renovated by  the Programme. 

                                                      4  Preventive maintenance system can work better than responding problems after it becomes serious. It is same as “preventive medicine” in health sector. 

5  The name comes from Sadako Ogata, President of JICA (former UN High Commissioner for Refugees) 6  In the programme, institutional strengthening plan, budgeting plan, garbage collection system, and selection of dumping site, among other things, should be taken up. 

Page 88: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-8

More  than 20 participants  including  the Mayor of Kandahar city, Directors of DOPH and  Planning  Department,  a  representative  of  DOE,  principals  of  the  schools,  and representatives of UN agencies7,  JICA and  the Study Team attended  the seminar and discussed  about  effective  use  of  the  rehabilitated/constructed  facilities  by  the Programme following a presentation of outcomes of URSP‐KDH.   

 Figure 5.2    Seminar on URSP‐KDH (January 2005) 

During  the  seminar,  the  participants  exchanged  ideas  concerning  utilisation  of  the provided facilities to possible maximum extent. Some principals emphasised that their school  facilities  are  open  for  use  by  neighbouring  communities  for  the  purpose  of literacy  training,  although  it  seems  difficult  for  quite  a  number  of  people  in  the communities to attend under the current security condition. At the end of seminar, the Study Team  strongly  recommended  that  stakeholders who were  beneficiaries  of  the Programme should contribute to society and projects/programmes in the future. Most of  participants  appreciated  the  outcomes  of  URSP‐KDH  and  looked  forward  to cooperating with other projects/programmes of  JICA  in  the near  future.  In  addition, Afghan officials emphasised that other donors and UN agencies should learn from the Urgent Rehabilitation  Projects,  especially  regarding  the  high  quality  of  construction works. 

5.5.  Recommendations 

The  recommendations  of  the  Study  Team  for  better  project  implementation  in  the future are summarised by group below. 

                                                      7  UN agencies: UNAMA, UN‐Habitat, and WHO. 

Page 89: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-9

(1)  To the Stakeholders of URSP‐KDH Projects 

The  stakeholders  who  are  beneficiary  of  the  Programme  should  share  their experience and provide facilities to other projects/programmes in the future. They should contribute to their society. 

For  the  purpose  of  better maintenance  and  sustainable  use  of  the  constructed facilities  and  provided  equipment,  “Preventive maintenance  system”  should  be established. Regular monitoring is significantly important. 

For  the  purpose  of  enhancing  ownership  and  responsibility  of  rehabilitated facilities,  stakeholders  such  as  residents,  teachers,  and medical  staff  should  be involved in planning and design phases as well as post‐implementation phase. It is necessary  to hold regular stakeholder meetings before  implementation  to discuss the activities and maintenance issues after construction. 

(2)  To the Local government in Kandahar 

The government should take the  initiative for reconstruction and development of the region. It is necessary for the government to shake itself free from donor driven development and to enhance capacity instead. 

Government officers should participate in the process of planning, monitoring and evaluation to secure sustainability of the projects. 

For  the purpose of  securing budget  and  responsible organizations  for operation and maintenance of the facilities and equipment, the government should enhance its institutional capacity especially for monitoring, accounting and management by inviting foreign experts and participating in domestic/overseas training. 

(3)  To Donors 

Scale  and design  of  support projects  should  be decided  considering  capacity  of counterparts, national staff, and local contractors or NGOs. Sometimes challenges may bring unexpected impacts such as capacity building of local contractors. 

After  humanitarian  emergency  assistance  phase,  assistance  projects  concerning construction,  training,  and  institutional  building  should  be  secured  appropriate quality strictly.   

Collaboration should be made among different schemes of donor support such as dispatching experts, grant aid, and overseas training to succeed in the outcomes of URSP‐KDH. 

 

Page 90: Part 2 - JICA · Rehabilitation Programme is described in the Final Report Part 1, which was submitted in February 2003 by the Study Team.) (2) Implementation of Urgent Rehabilitation

URSP-KDH Final Report Part 2

   

5-10

For  the  purpose  of  quick  and  flexible  response,  donors  should  have  in‐house consulting engineers  (CEs)  in  the  country office  instead of bringing  in CEs  from abroad.   

Scope of the project should be modified with flexibility to respond to changeable situations. 

Security  is  the  most  important  issue  for  aid  workers,  and  so  donors  should increase their capacity for collecting information and reducing risks.