TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN PAGE 1 C2 Part C2: Pricing Data Cover PART 2: PRICING DATA Document reference Title No of pages C2.1 Pricing instructions: Option B C2.2 Bill of Quantities

Upload: phamtuyen

Post on 28-Aug-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 1 C2 Part C2: Pricing Data Cover

PART 2: PRICING DATA

Document reference

Title No of pages

C2.1 Pricing instructions: Option B

C2.2 Bill of Quantities

Page 2: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 1 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

C2.1Pricing instructions: Option B

1. The conditions of contract

1.1. How the contract prices work and assesses it for progress payments

Clause 11 in NEC3 Engineering and Construction Contract, June 2005 (ECC) Option B states:

Identified and defined terms

11

11.2

(21) The Bill of Quantities is the bill of quantities as changed in accordance with this contract to accommodate implemented compensation events and for accepted quotations for acceleration.

(22) Defined Cost is the cost of the components in the Shorter Schedule of Cost

Components whether work is subcontracted or not excluding the cost of preparing quotations for compensation events

(28) The Price for Work Done to Date is the total of

The quantity of the work which the Contractor has completed for each item in the Bill of Quantities multiplied by the rate and

A proportion of each lump sum which is the proportion of the work covered by the item which the Contractor has completed.

Completed work is work without Defects which would either delay or be covered by immediately following work.

(31) The Prices are the lump sums and the amounts obtained by multiplying the rates by the quantities for the items in the Bill of Quantities.

This confirms that Option B is a re-measurement contract and the bill comprises only items measured

using quantities and rates or stated as lump sums. Value related items are not used. Time related items

are items measured using rates where the rate is a unit of time

1.2. Measurement and Payment

Clause 55.1 in Option B states, “Information in the Bill of Quantities is not Works Information or Site

Information”. This confirms that instructions to do work or how it is to be done are not included in the Bill,

but in the Works Information. Tis is further confirmed by Clause 20.1 which states, “The contractor

provides the Works in accordance with the Works Information”. Hence the Contractor does not provide

the Works in accordance with the Bill of Quantities. The Bill of Quantities is only a pricing document.

1.3. Guidance before Pricing and Measuring

a) Employers preparing tenders or contract documents, and tendering contractors are advised to consult

the sections dealing with the bill of quantities in the NEC3 Engineering and Construction Contract

(June 2014) Guidance Notes before preparing the bill of quantities or before entering rates and lump

sums into the bill.

Page 3: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 2 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

b) Historically, bill of quantities based contracts in South Africa have been influenced by the different

approaches of the civil engineering and building sectors of the industry through their respective

discipline based standard forms of contract and methods of measurement. This is particularly

apparent in the approach to the Preliminary and General Bill. On the other hand, because ECC3

caters for a number of disciplines in the same contract, including electrical works, a different

approach not currently found in local methods of measurement to the Preliminary and General Bill

items may have been used.

c) The NEC approach to the P&G bill assumes use will be made of method related charges for

Equipment applied to Providing the Works based on durations shown in the Accepted Programme,

fixed charges for the use of equipment that is required throughout the construction phase, time

related charges for people working in a supervisory capacity for the period required, and a lump sum

charges for other facilities or services not directly related to performing work items typically included

in other parts of the bill.

1.4. Symbols

The units of measurement described in the Bill of Quantities are metric units abbreviated as follows:

Abbreviation Description

m Meter

mm Millimetres

m2 Meters Squared

m3 Meters Cubed

Sum Lump Sum

ton Metric Ton (1000kg)

1.5. General Assumptions

d) Unless otherwise stated, items are measured net in accordance with the drawings, and no allowance

has been made in the quantities for waste.

e) The prices and rates stated for each item in the Bill of Quantities shall be treated as being fully

inclusive of all work, risks, liabilities, obligations, overheads, profit and everything necessary as

incureed or required by the Contractor in carrying out or providing that item.

f) Clause 63.13 in Option B provides that these rates and Prices may be used as a basis for

assessment of compensation events instead of defined cost.

Page 4: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 3 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

g) Where the contract requires detailed drawings, designs or other information to be provided, and no

rates or prices are included in the Bill specifically for such matters, then the Contractor is deemed to

have allowed for all costs associated with such requirements within the tendered rates and Prices in

the Bill of Quantities.

h) An item against which no Price is entered will be treated as covered by other Prices or Rates in the

Bill of Quantities. If a number of items are grouped together for pricing purposes, this will be treated

as a single lump sum.

i) The quantities contained in the Bill of Quantities may not be final and do not necessarily represent the

actual amount of work to be done. The quantities of work assessed and certified for payment by the

Project Manager at each assessment date will be used for determining payments due and not the

quantities given in the Bill of Quantities.

j) The short descriptions of the items of payment given in the Bill of Quantities are only for the purposes

of identifying the items. More detail regarding the extent of the work entailed under each item is

provided in the Works Information.

1.6. Amplification of or assumptions about measurement items

For the avoidance of doubt, the following is provided to assist in the interpretation of descriptions given in

the method of measurement. In the event of any ambiguity or inconsistency between the statements in

the method of measurement and this section, the interpretation given in this section shall be used.

C2.2 Preamble to Bill of Quantities

1. Notes to Tenderers

Page 5: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 4 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

For the purpose of this Bill of Quantities the following words shall have the meanings hereby assigned to

them:

Word Meaning

Item: This number is for reference only

Ref: This refers to the contractual clause applicable to the item of the bill

Description: The description describes in detail what the item is for

Unit: The unit of measure for each item of work as defined in the standard specifications or the

special provisions of this contract

Quantity: The number of units of work for each item

Rate: Payment per unit of work or material at which tenders offer to do the work or supply

material

Total: The product of quantity and Rate

2. Supplementary Preambles

a) The Contractor shall provide and afterwards remove all necessary temporary tarpaulins, barricades,

screens, fencing, temporary, waterproofing, dustproofing, etc. required to isolate any sections of the

existing works all to the satisfaction of the Principal Agent and remove when directed.

b) The Contractor shall cover up and protect from injury all work not removed and shall make good at

his own expense any damage that may occur.

c) Existing services must be maintained at all times to the existing buildings. If it is found necessary to

disconnect any service than suitable temporary or alternate services must be provided to the existing

buildings.

d) Special care shall be exercised during the progress of the work to ensure that any electrical cables,

water supply pipes and other services which may be encountered are not intefered with and notice

must be given to the Project Manager or Supervisor if any disconnection or alterations become

necessary.

e) Preparation of existing screeds/plaster shall imply the use of an approved screed or plaster repairing

compound.

f) All sizes and dimensions stated herein are approximate and deemed only sufficient to identify the

item of work concerned.

g) In taking down and removing existing work the utmost care must be taken to avoid any structural or

other damage to the remaining portions of the works and the Contractor shall provide all shoring,

Page 6: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 5 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

needling, strutting, etc to ensure the stability of all structures during the repair work. The Contractor

will be held solely responsible for the safety and structural stability of the works for the whole period

of the contract and must make good any damage at his own expense.

h) "Any water supply or other piping, etc that may be encountered and found necessary to disconnect or

cut are to be effectually stopped off and any new connections that may be necessary shall be made

with the proper fittings to the satisfaction of the Principal Agent.

i) The Contractor shall remove from the site all material, rubble, debris, rubbish, etc resulting from the

reapir works.

j) Building up of existing openings where given in number shall be deemed to include preparing existing

surfaces all round, brickwork properly toothed and bonded to existing and shot pinned to concrete,

wedging up and unless otherwise stated making good finishes on both

sides to match existing.

3. Old Materials to be Carted Away

Old materials from the repair works, except where described to be re-used or handed over, as well as all

rubbish, etc., must be regularly carted from the site and not be allowed to accumulate on or around the

site.

4. Handing Over Of Materials

Where certain materials or articles from the repair works or articles are described as to be handed over

by the Contractor to the Client Representative or Project Manager, such materials or articles shall be

transported to an area within the Port perimeter. The Contractor must obtain an official receipt listing the

materials or articles and dates of handing over. If the Contractor fails to submit the receipt when

requested, it shall be deemed that the materials or articles are still in his possession and he will be held

liable to the Client for the full replacement value thereof, which amount will be deducted from any monies

due to the Contractor.

5. View Site

Before submitting his tender the contractor shall visit the site and satisfy himself as to the nature and

extent of the work to be done and the value of the materials contained in the buildings or portions of the

buildings to be demolished. No claim for any variations of the contract sum in respect of the nature and

extent of the work or of inferior or damaged materials will be entertained by the Employer.

Page 7: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 6 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A

6. Cost management Obligations

It is specifically agreed that the contractor accepts the obligation of assisting the Project Manager in

implementing proper cost management on this project.

The contractor will be advised by the Project manager of all cost management procedures which will be

implemented to ensure that the final account does not exceed the budget.

7. VAT

Tenderers shall not add VAT to the individual items, VAT is to be included in the final summary.

Page 8: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 1 C2.2 Part C2: Pricing Data Activity Schedule

C2.2 Bill of Quantities The Tenderer details his Activity Schedule below or makes reference to his Activity Schedule and attaches it to this schedule. The details given below serve as guidelines only and the Tenderer may split or combine the activities to suit his particular methods.

PIPING UPGRADE

TENDER NUMBER: TBC

FINAL SUMMARY

DESCRIPTION AMOUNT

RAND

A: PRELIMINARY AND GENERAL B: DISMANTLING AND CLEARANCE FROM SITE OF EXISTING PIPING C: SUPPLY AND INSTALLATION OF SEA WATER CIRCULATION PIPING D: SUPPLY AND INSTALLATION OF FRESH WATER PIPING

TOTAL PRICE CARRIED TO FORM OF OFFER AND ACCEPTANCE (EXCLUDING VAT)

A: PRELIMINARY AND GENERAL

Page 9: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 2 C2.2 Part C2: Pricing Data Activity Schedule

ITEM REF DESCRIPTION UNIT QTY RATE AMOUNT

A1 Fixed Cost Items

A1.1 Contractual Requirements

A1.1.1 Provision of Performance Bond Sum 1

A1.1.2 Provision of Health and Safety File Sum 1

A1.1.3 All other Contractual and legal requirements Sum 1

A1.2 Facilities for Contractor

A1.2.1 Offices and storage sheds Sum 1

A1.2.2 Ablution and mess facilities Sum 1

A1.2.3 Tools and equipment Sum 1

A2 Time Related Items

A2.1 Plant and Equipment weeks 17

A2.2 Supervision weeks 17

Page 10: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 3 C2.2 Part C2: Pricing Data Activity Schedule

A2.3 Head Office Overheads weeks 17

A2.4 Other time related obligations weeks 17

TOTAL CARRIED FORWARD TO SECTION B SUMMARY:

B: DISMANTLING AND CLEARANCE FROM SITE OF EXISTING PIPING

ITEM REF DESCRIPTION UNIT QTY RATE AMOUNT

B1 Dismantling and Clearance from site of Existing Piping

B1.1

Compressed Air Piping (150mm DIA) m 400

B1.2

Fresh Water Piping (150mm DIA) m 900

B1.3 Circulating Sea Water piping (300mm DIA) m 900

B1.4 Fire fighting Sea Water Piping (300mm DIA) m 900

TOTAL CARRIED FORWARD TO SECTION C SUMMARY:

C: SUPPLY AND INSTALLATION OF SEA WATER CIRCULATION PIPING

Page 11: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 4 C2.2 Part C2: Pricing Data Activity Schedule

ITEM REF DESCRIPTION

Diam Length (mm) QTY

Supply Rate

Supply Cost

Erection Rate Erection Costs Total

C1

Supply Piping from Pump House

C1.1 Spool Piece, Flanged Both Sides 315NB 2000.00 1.00

C1.2 67.6° Short Bend, Flanged Both Sides 315NB -- 1.00

C1.3 Spool Piece, Flanged Both Sides 315NB 6000.00 1.00

C1.4 Spool Piece, Flanged Both Sides 315NB 1200.00 1.00

C1.5 67.6° Short Bend, Flanged Both Sides 315NB -- 1.00

C1.6 Spool Piece, Flanged Both Sides 315NB 300.00 1.00

C1.7 90° Short Bend, Flanged Both Sides 315NB -- 1.00

C1.8 90° Short Bend, Flanged Both Sides 315NB -- 1.00

C1.9 Spool Piece, Flanged Both Sides 315NB 6000.00 7.00

C1.10 Spool Piece, Flanged Both Sides 315NB 2500.00 1.00

C1.11 45° Long Radius, Flanged Both Sides 315NB -- 1.00

C1.12 Spool Piece, Flanged Both Sides 315NB 500.00 1.00

Page 12: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 5 C2.2 Part C2: Pricing Data Activity Schedule

C1.13 45° Long Radius, Flanged Both Sides 315NB -- 1.00

C1.14 Spool Piece, Flanged Both Sides 315NB 6000.00 5.00

C1.15 Spool Piece, Flanged Both Sides 315NB 4500.00 1.00

C1.16 Gate Valve 315NB -- 1.00

C1.17 Equal Tee 315NB -- 1.00

C2 Western Side Limb

C2.1 Concentric Reducer 315NB /250NB -- 1.00

C2.2 45° Short Radius Bend 250NB -- 1.00

C2.3 45° Short Radius Bend 250NB -- 1.00

C2.4 Gate VAlve 250NB -- 1.00

C2.5 45° Short Radius Bend 250NB -- 1.00

C2.6 45° Short Radius Bend 250NB -- 1.00

C2.7 Spool Piece, Flanged Both sides 250NB 6000.00 11.00

C2.8 Spool Piece, Flanged Both sides 250NB 4500.00 1.00

Page 13: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 6 C2.2 Part C2: Pricing Data Activity Schedule

C2.9 Unequal tee 250NB / 150NB -- 1.00

C2.10 Spool Piece, Flanged Both sides 250NB 6000.00 15.00

C2.11 Spool Piece, Flanged Both sides 250NB 1500.00 1.00

C2.12 Unequal Tee 250NB / 150NB -- 1.00

C2.13 Concentric Reducer 250NB /150NB -- 1.00

C2.14 Spool Piece, Flanged Both sides 150NB 6000.00 15.00

C2.15 Spool Piece, Flanged Both sides 150NB 1500.00 1.00

C2.16 Air /Vacuum Valve 25NB -- 1.00

C2.17 90° Short Radius Bend 150NB -- 1.00

C3 Western Side Risers

C3.1 90° Bend Short 150NB -- 3.00

C3.2 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C3.3 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C3.4 22.5° Bend Short 150NB -- 3.00

Page 14: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 7 C2.2 Part C2: Pricing Data Activity Schedule

C3.5 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C3.6 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C3.7 67.5° Bend Short 150NB -- 3.00

C3.8 Gate VAlve 150NB -- 3.00

C3.9 Flanged Coupling (Cam and Grove Type) -- -- 3.00

C4 Dock Underside Crossing

C4.1 90° Bend Short 315NB -- 1.00

C4.2 Spool Piece, Flanged Both sides 315NB 1500.00 1.00

C4.3 Gate VAlve 315NB -- 1.00

C4.4 Spool Piece, Flanged Both sides 315NB 2500.00 1.00

C4.5 90° Bend Short 315NB -- 1.00

C4.6 Spool Piece, Flanged Both sides 315NB 6000.00 2.00

C4.7 Spool Piece, Flanged Both sides 315NB 2000.00 1.00

C4.8 90° Bend Short 315NB -- 1.00

Page 15: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 8 C2.2 Part C2: Pricing Data Activity Schedule

C4.9 Spool Piece, Flanged Both sides 315NB 6000.00 33.00

C4.10 Spool Piece, Flanged Both sides, 150NB Drain Stub

315NB 6000.00 1.00

C4.11 Spool Piece, Flanged Both sides 315NB 2000.00 1.00

C4.12 Draining Gate Valve 150NB -- 1.00

C4.13 90° Bend Short 315NB -- 1.00

C4.14 Spool Piece, Flanged Both sides 315NB 6000.00 2.00

C4.15 Spool Piece, Flanged Both sides 315NB 2000.00 1.00

C4.16 90° Bend Short 315NB -- 1.00

C4.17 Spool Piece, Flanged Both sides 315NB 2500.00 1.00

C4.18 90° Bend Short 315NB -- 1.00

C4.19 90° Bend Short 315NB -- 2.00

C5 Eastern Side Limb

C5.1 Spool Piece, Flanged Both sides 250NB 6000.00 11.00

C5.2 Spool Piece, Flanged Both sides 250NB 4500.00 1.00

Page 16: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 9 C2.2 Part C2: Pricing Data Activity Schedule

C5.3 Unequal tee 250NB / 150NB -- 1.00

C5.4 Spool Piece, Flanged Both sides 250NB 6000.00 15.00

C5.5 Spool Piece, Flanged Both sides 250NB 1500.00 1.00

C5.6 Unequal Tee 250NB / 150NB -- 1.00

C5.7 12" to 6" Concentric Reducer 250NB /150NB -- 1.00

C5.8 Spool Piece, Flanged Both sides 150NB 6000.00 15.00

C5.9 Spool Piece, Flanged Both sides, with 25NB Socket

150NB 1500.00 1.00

C5.10 Air /Vacuum Valve 25NB -- 1.00

C5.11 90° Bend Short 150NB -- 1.00

C6 Eastern Side Risers

C6.1 90° Bend Short 150NB -- 3.00

C6.2 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C6.3 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C6.4 22.5° Bend Short 150NB -- 3.00

Page 17: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 10 C2.2 Part C2: Pricing Data Activity Schedule

C6.5 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C6.6 Spool Piece, Flanged Both sides 150NB 2500.00 3.00

C6.7 67.5° Bend Short 150NB -- 3.00

C6.8 Gate VAlve 150NB -- 3.00

C6.9 Flanged Hose Coupling (Cam and Grove Type)

-- -- 3.00

C7 Pipe Supports

C7.1 Fabricated Pipe Supports (min 70 x 70 x 6 L)

-- Support 100.00

TOTAL CARRIED FORWARD TO SECTION A SUMMARY:

D: SUPPLY AND INSTALLATION OF FRESH WATER PIPING

ITEM REF DESCRIPTION

Diam Length (mm) QTY

Supply Rate

Supply Cost

Erection Rate

Erection Costs Total

D1 Eastern Limb Manifold Piping

D1.1 Spool Piece, Flanged Both sides 150NB 6000.00 47

Page 18: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 11 C2.2 Part C2: Pricing Data Activity Schedule

D1.2 Spool Piece, Flanged Both sides 150NB 5000.00 2

D1.3 Spool Piece, Flanged Both sides 150NB 4500.00 2

D1.4 Spool Piece, Flanged Both sides 150NB 4000.00 2

D1.5 Spool Piece, Flanged Both sides 150NB 3500.00 2

D1.6 Spool Piece, Flanged Both sides 150NB 3000.00 2

D1.7 Blanked Flange 150NB -- 1

D1.8 78.75° Long Radius Bend, Flanged Both Sides 150NB -- 1

D1.9 90° Long Radius Bend, Flanged Both Sides 150NB -- 1

D1.10 45° Long Radius Bend, Flanged Both Sides 150NB -- 1

D1.11 Unequal Tee 150NB/80NB -- 5

D1.12 Gate VAlve 150NB -- 1

D1.13 Air /Vacuum Valve 25NB -- 1

D1.14 Fabricated Pipe Supports (min 50 x 50 x 5 L) -- -- 110

D2 Western Limb Manifold

D2.1 Spool Piece, Flanged Both sides 150NB 6000.00 47

Page 19: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 12 C2.2 Part C2: Pricing Data Activity Schedule

D2.2 Spool Piece, Flanged Both sides 150NB 5000.00 2

D2.3 Spool Piece, Flanged Both sides 150NB 4500.00 2

D2.4 Spool Piece, Flanged Both sides 150NB 4000.00 2

D2.5 Spool Piece, Flanged Both sides 150NB 3500.00 2

D2.6 Spool Piece, Flanged Both sides 150NB 3000.00 2

D2.7 Blanked Flange 150NB -- 1

D2.8 78.75° Long Radius Bend, Flanged Both Sides 150NB -- 1

D2.9 90° Long Radius Bend, Flanged Both Sides 150NB -- 1

D2.10 45° Long Radius Bend, Flanged Both Sides 150NB -- 1

D2.11 Unequal Tee 150NB/80NB -- 5

D2.12 Gate VAlve 150NB -- 1

D2.13 Air /Vacuum Valve 25NB -- 1

D2.14 Fabricated Pipe Supports (min 50 x 50 x 5 L) -- -- 110

D3 Risers x10 ( 5 in each limb)

Page 20: PART 2: PRICING DATA - Pricing... · DESCRIPTION OF THE WORKS DESIGN, ... Clause 11 in NEC3 Engineering and Construction Contract, ... More detail regarding the …

TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN

PAGE 13 C2.2 Part C2: Pricing Data Activity Schedule

D3.1 Spool Piece, 1 Side Flanged, 1 Side Butt Welded 80NB 1000.00 10

D3.2 Spool Piece, 1 Side Flanged, 1 Side Butt Welded 80NB 3100.00 10

D3.3 90° Long Radius Bend, Butt Welded 80NB -- 10

D3.4 22.5° Long Radius Bend, Butt Welded 80NB -- 10

D3.5 67.5° Long Radius Bend, Butt Welded 80NB -- 10

D3.6 Gate Valve 80NB -- 10

D3.7 Hose Coupling as per figure XX in C3 80NB -- 10

TOTAL CARRIED FORWARD TO SECTION A SUMMARY: