TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 1 C2 Part C2: Pricing Data Cover
PART 2: PRICING DATA
Document reference
Title No of pages
C2.1 Pricing instructions: Option B
C2.2 Bill of Quantities
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 1 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
C2.1Pricing instructions: Option B
1. The conditions of contract
1.1. How the contract prices work and assesses it for progress payments
Clause 11 in NEC3 Engineering and Construction Contract, June 2005 (ECC) Option B states:
Identified and defined terms
11
11.2
(21) The Bill of Quantities is the bill of quantities as changed in accordance with this contract to accommodate implemented compensation events and for accepted quotations for acceleration.
(22) Defined Cost is the cost of the components in the Shorter Schedule of Cost
Components whether work is subcontracted or not excluding the cost of preparing quotations for compensation events
(28) The Price for Work Done to Date is the total of
The quantity of the work which the Contractor has completed for each item in the Bill of Quantities multiplied by the rate and
A proportion of each lump sum which is the proportion of the work covered by the item which the Contractor has completed.
Completed work is work without Defects which would either delay or be covered by immediately following work.
(31) The Prices are the lump sums and the amounts obtained by multiplying the rates by the quantities for the items in the Bill of Quantities.
This confirms that Option B is a re-measurement contract and the bill comprises only items measured
using quantities and rates or stated as lump sums. Value related items are not used. Time related items
are items measured using rates where the rate is a unit of time
1.2. Measurement and Payment
Clause 55.1 in Option B states, “Information in the Bill of Quantities is not Works Information or Site
Information”. This confirms that instructions to do work or how it is to be done are not included in the Bill,
but in the Works Information. Tis is further confirmed by Clause 20.1 which states, “The contractor
provides the Works in accordance with the Works Information”. Hence the Contractor does not provide
the Works in accordance with the Bill of Quantities. The Bill of Quantities is only a pricing document.
1.3. Guidance before Pricing and Measuring
a) Employers preparing tenders or contract documents, and tendering contractors are advised to consult
the sections dealing with the bill of quantities in the NEC3 Engineering and Construction Contract
(June 2014) Guidance Notes before preparing the bill of quantities or before entering rates and lump
sums into the bill.
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 2 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
b) Historically, bill of quantities based contracts in South Africa have been influenced by the different
approaches of the civil engineering and building sectors of the industry through their respective
discipline based standard forms of contract and methods of measurement. This is particularly
apparent in the approach to the Preliminary and General Bill. On the other hand, because ECC3
caters for a number of disciplines in the same contract, including electrical works, a different
approach not currently found in local methods of measurement to the Preliminary and General Bill
items may have been used.
c) The NEC approach to the P&G bill assumes use will be made of method related charges for
Equipment applied to Providing the Works based on durations shown in the Accepted Programme,
fixed charges for the use of equipment that is required throughout the construction phase, time
related charges for people working in a supervisory capacity for the period required, and a lump sum
charges for other facilities or services not directly related to performing work items typically included
in other parts of the bill.
1.4. Symbols
The units of measurement described in the Bill of Quantities are metric units abbreviated as follows:
Abbreviation Description
m Meter
mm Millimetres
m2 Meters Squared
m3 Meters Cubed
Sum Lump Sum
ton Metric Ton (1000kg)
1.5. General Assumptions
d) Unless otherwise stated, items are measured net in accordance with the drawings, and no allowance
has been made in the quantities for waste.
e) The prices and rates stated for each item in the Bill of Quantities shall be treated as being fully
inclusive of all work, risks, liabilities, obligations, overheads, profit and everything necessary as
incureed or required by the Contractor in carrying out or providing that item.
f) Clause 63.13 in Option B provides that these rates and Prices may be used as a basis for
assessment of compensation events instead of defined cost.
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 3 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
g) Where the contract requires detailed drawings, designs or other information to be provided, and no
rates or prices are included in the Bill specifically for such matters, then the Contractor is deemed to
have allowed for all costs associated with such requirements within the tendered rates and Prices in
the Bill of Quantities.
h) An item against which no Price is entered will be treated as covered by other Prices or Rates in the
Bill of Quantities. If a number of items are grouped together for pricing purposes, this will be treated
as a single lump sum.
i) The quantities contained in the Bill of Quantities may not be final and do not necessarily represent the
actual amount of work to be done. The quantities of work assessed and certified for payment by the
Project Manager at each assessment date will be used for determining payments due and not the
quantities given in the Bill of Quantities.
j) The short descriptions of the items of payment given in the Bill of Quantities are only for the purposes
of identifying the items. More detail regarding the extent of the work entailed under each item is
provided in the Works Information.
1.6. Amplification of or assumptions about measurement items
For the avoidance of doubt, the following is provided to assist in the interpretation of descriptions given in
the method of measurement. In the event of any ambiguity or inconsistency between the statements in
the method of measurement and this section, the interpretation given in this section shall be used.
C2.2 Preamble to Bill of Quantities
1. Notes to Tenderers
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 4 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
For the purpose of this Bill of Quantities the following words shall have the meanings hereby assigned to
them:
Word Meaning
Item: This number is for reference only
Ref: This refers to the contractual clause applicable to the item of the bill
Description: The description describes in detail what the item is for
Unit: The unit of measure for each item of work as defined in the standard specifications or the
special provisions of this contract
Quantity: The number of units of work for each item
Rate: Payment per unit of work or material at which tenders offer to do the work or supply
material
Total: The product of quantity and Rate
2. Supplementary Preambles
a) The Contractor shall provide and afterwards remove all necessary temporary tarpaulins, barricades,
screens, fencing, temporary, waterproofing, dustproofing, etc. required to isolate any sections of the
existing works all to the satisfaction of the Principal Agent and remove when directed.
b) The Contractor shall cover up and protect from injury all work not removed and shall make good at
his own expense any damage that may occur.
c) Existing services must be maintained at all times to the existing buildings. If it is found necessary to
disconnect any service than suitable temporary or alternate services must be provided to the existing
buildings.
d) Special care shall be exercised during the progress of the work to ensure that any electrical cables,
water supply pipes and other services which may be encountered are not intefered with and notice
must be given to the Project Manager or Supervisor if any disconnection or alterations become
necessary.
e) Preparation of existing screeds/plaster shall imply the use of an approved screed or plaster repairing
compound.
f) All sizes and dimensions stated herein are approximate and deemed only sufficient to identify the
item of work concerned.
g) In taking down and removing existing work the utmost care must be taken to avoid any structural or
other damage to the remaining portions of the works and the Contractor shall provide all shoring,
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 5 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
needling, strutting, etc to ensure the stability of all structures during the repair work. The Contractor
will be held solely responsible for the safety and structural stability of the works for the whole period
of the contract and must make good any damage at his own expense.
h) "Any water supply or other piping, etc that may be encountered and found necessary to disconnect or
cut are to be effectually stopped off and any new connections that may be necessary shall be made
with the proper fittings to the satisfaction of the Principal Agent.
i) The Contractor shall remove from the site all material, rubble, debris, rubbish, etc resulting from the
reapir works.
j) Building up of existing openings where given in number shall be deemed to include preparing existing
surfaces all round, brickwork properly toothed and bonded to existing and shot pinned to concrete,
wedging up and unless otherwise stated making good finishes on both
sides to match existing.
3. Old Materials to be Carted Away
Old materials from the repair works, except where described to be re-used or handed over, as well as all
rubbish, etc., must be regularly carted from the site and not be allowed to accumulate on or around the
site.
4. Handing Over Of Materials
Where certain materials or articles from the repair works or articles are described as to be handed over
by the Contractor to the Client Representative or Project Manager, such materials or articles shall be
transported to an area within the Port perimeter. The Contractor must obtain an official receipt listing the
materials or articles and dates of handing over. If the Contractor fails to submit the receipt when
requested, it shall be deemed that the materials or articles are still in his possession and he will be held
liable to the Client for the full replacement value thereof, which amount will be deducted from any monies
due to the Contractor.
5. View Site
Before submitting his tender the contractor shall visit the site and satisfy himself as to the nature and
extent of the work to be done and the value of the materials contained in the buildings or portions of the
buildings to be demolished. No claim for any variations of the contract sum in respect of the nature and
extent of the work or of inferior or damaged materials will be entertained by the Employer.
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 6 Part C2: Pricing Data PRO-FAT-0215 Rev02 C2.1: Pricing instructions ECC Option A
6. Cost management Obligations
It is specifically agreed that the contractor accepts the obligation of assisting the Project Manager in
implementing proper cost management on this project.
The contractor will be advised by the Project manager of all cost management procedures which will be
implemented to ensure that the final account does not exceed the budget.
7. VAT
Tenderers shall not add VAT to the individual items, VAT is to be included in the final summary.
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 1 C2.2 Part C2: Pricing Data Activity Schedule
C2.2 Bill of Quantities The Tenderer details his Activity Schedule below or makes reference to his Activity Schedule and attaches it to this schedule. The details given below serve as guidelines only and the Tenderer may split or combine the activities to suit his particular methods.
PIPING UPGRADE
TENDER NUMBER: TBC
FINAL SUMMARY
DESCRIPTION AMOUNT
RAND
A: PRELIMINARY AND GENERAL B: DISMANTLING AND CLEARANCE FROM SITE OF EXISTING PIPING C: SUPPLY AND INSTALLATION OF SEA WATER CIRCULATION PIPING D: SUPPLY AND INSTALLATION OF FRESH WATER PIPING
TOTAL PRICE CARRIED TO FORM OF OFFER AND ACCEPTANCE (EXCLUDING VAT)
A: PRELIMINARY AND GENERAL
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 2 C2.2 Part C2: Pricing Data Activity Schedule
ITEM REF DESCRIPTION UNIT QTY RATE AMOUNT
A1 Fixed Cost Items
A1.1 Contractual Requirements
A1.1.1 Provision of Performance Bond Sum 1
A1.1.2 Provision of Health and Safety File Sum 1
A1.1.3 All other Contractual and legal requirements Sum 1
A1.2 Facilities for Contractor
A1.2.1 Offices and storage sheds Sum 1
A1.2.2 Ablution and mess facilities Sum 1
A1.2.3 Tools and equipment Sum 1
A2 Time Related Items
A2.1 Plant and Equipment weeks 17
A2.2 Supervision weeks 17
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 3 C2.2 Part C2: Pricing Data Activity Schedule
A2.3 Head Office Overheads weeks 17
A2.4 Other time related obligations weeks 17
TOTAL CARRIED FORWARD TO SECTION B SUMMARY:
B: DISMANTLING AND CLEARANCE FROM SITE OF EXISTING PIPING
ITEM REF DESCRIPTION UNIT QTY RATE AMOUNT
B1 Dismantling and Clearance from site of Existing Piping
B1.1
Compressed Air Piping (150mm DIA) m 400
B1.2
Fresh Water Piping (150mm DIA) m 900
B1.3 Circulating Sea Water piping (300mm DIA) m 900
B1.4 Fire fighting Sea Water Piping (300mm DIA) m 900
TOTAL CARRIED FORWARD TO SECTION C SUMMARY:
C: SUPPLY AND INSTALLATION OF SEA WATER CIRCULATION PIPING
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 4 C2.2 Part C2: Pricing Data Activity Schedule
ITEM REF DESCRIPTION
Diam Length (mm) QTY
Supply Rate
Supply Cost
Erection Rate Erection Costs Total
C1
Supply Piping from Pump House
C1.1 Spool Piece, Flanged Both Sides 315NB 2000.00 1.00
C1.2 67.6° Short Bend, Flanged Both Sides 315NB -- 1.00
C1.3 Spool Piece, Flanged Both Sides 315NB 6000.00 1.00
C1.4 Spool Piece, Flanged Both Sides 315NB 1200.00 1.00
C1.5 67.6° Short Bend, Flanged Both Sides 315NB -- 1.00
C1.6 Spool Piece, Flanged Both Sides 315NB 300.00 1.00
C1.7 90° Short Bend, Flanged Both Sides 315NB -- 1.00
C1.8 90° Short Bend, Flanged Both Sides 315NB -- 1.00
C1.9 Spool Piece, Flanged Both Sides 315NB 6000.00 7.00
C1.10 Spool Piece, Flanged Both Sides 315NB 2500.00 1.00
C1.11 45° Long Radius, Flanged Both Sides 315NB -- 1.00
C1.12 Spool Piece, Flanged Both Sides 315NB 500.00 1.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 5 C2.2 Part C2: Pricing Data Activity Schedule
C1.13 45° Long Radius, Flanged Both Sides 315NB -- 1.00
C1.14 Spool Piece, Flanged Both Sides 315NB 6000.00 5.00
C1.15 Spool Piece, Flanged Both Sides 315NB 4500.00 1.00
C1.16 Gate Valve 315NB -- 1.00
C1.17 Equal Tee 315NB -- 1.00
C2 Western Side Limb
C2.1 Concentric Reducer 315NB /250NB -- 1.00
C2.2 45° Short Radius Bend 250NB -- 1.00
C2.3 45° Short Radius Bend 250NB -- 1.00
C2.4 Gate VAlve 250NB -- 1.00
C2.5 45° Short Radius Bend 250NB -- 1.00
C2.6 45° Short Radius Bend 250NB -- 1.00
C2.7 Spool Piece, Flanged Both sides 250NB 6000.00 11.00
C2.8 Spool Piece, Flanged Both sides 250NB 4500.00 1.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 6 C2.2 Part C2: Pricing Data Activity Schedule
C2.9 Unequal tee 250NB / 150NB -- 1.00
C2.10 Spool Piece, Flanged Both sides 250NB 6000.00 15.00
C2.11 Spool Piece, Flanged Both sides 250NB 1500.00 1.00
C2.12 Unequal Tee 250NB / 150NB -- 1.00
C2.13 Concentric Reducer 250NB /150NB -- 1.00
C2.14 Spool Piece, Flanged Both sides 150NB 6000.00 15.00
C2.15 Spool Piece, Flanged Both sides 150NB 1500.00 1.00
C2.16 Air /Vacuum Valve 25NB -- 1.00
C2.17 90° Short Radius Bend 150NB -- 1.00
C3 Western Side Risers
C3.1 90° Bend Short 150NB -- 3.00
C3.2 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C3.3 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C3.4 22.5° Bend Short 150NB -- 3.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 7 C2.2 Part C2: Pricing Data Activity Schedule
C3.5 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C3.6 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C3.7 67.5° Bend Short 150NB -- 3.00
C3.8 Gate VAlve 150NB -- 3.00
C3.9 Flanged Coupling (Cam and Grove Type) -- -- 3.00
C4 Dock Underside Crossing
C4.1 90° Bend Short 315NB -- 1.00
C4.2 Spool Piece, Flanged Both sides 315NB 1500.00 1.00
C4.3 Gate VAlve 315NB -- 1.00
C4.4 Spool Piece, Flanged Both sides 315NB 2500.00 1.00
C4.5 90° Bend Short 315NB -- 1.00
C4.6 Spool Piece, Flanged Both sides 315NB 6000.00 2.00
C4.7 Spool Piece, Flanged Both sides 315NB 2000.00 1.00
C4.8 90° Bend Short 315NB -- 1.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 8 C2.2 Part C2: Pricing Data Activity Schedule
C4.9 Spool Piece, Flanged Both sides 315NB 6000.00 33.00
C4.10 Spool Piece, Flanged Both sides, 150NB Drain Stub
315NB 6000.00 1.00
C4.11 Spool Piece, Flanged Both sides 315NB 2000.00 1.00
C4.12 Draining Gate Valve 150NB -- 1.00
C4.13 90° Bend Short 315NB -- 1.00
C4.14 Spool Piece, Flanged Both sides 315NB 6000.00 2.00
C4.15 Spool Piece, Flanged Both sides 315NB 2000.00 1.00
C4.16 90° Bend Short 315NB -- 1.00
C4.17 Spool Piece, Flanged Both sides 315NB 2500.00 1.00
C4.18 90° Bend Short 315NB -- 1.00
C4.19 90° Bend Short 315NB -- 2.00
C5 Eastern Side Limb
C5.1 Spool Piece, Flanged Both sides 250NB 6000.00 11.00
C5.2 Spool Piece, Flanged Both sides 250NB 4500.00 1.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 9 C2.2 Part C2: Pricing Data Activity Schedule
C5.3 Unequal tee 250NB / 150NB -- 1.00
C5.4 Spool Piece, Flanged Both sides 250NB 6000.00 15.00
C5.5 Spool Piece, Flanged Both sides 250NB 1500.00 1.00
C5.6 Unequal Tee 250NB / 150NB -- 1.00
C5.7 12" to 6" Concentric Reducer 250NB /150NB -- 1.00
C5.8 Spool Piece, Flanged Both sides 150NB 6000.00 15.00
C5.9 Spool Piece, Flanged Both sides, with 25NB Socket
150NB 1500.00 1.00
C5.10 Air /Vacuum Valve 25NB -- 1.00
C5.11 90° Bend Short 150NB -- 1.00
C6 Eastern Side Risers
C6.1 90° Bend Short 150NB -- 3.00
C6.2 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C6.3 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C6.4 22.5° Bend Short 150NB -- 3.00
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 10 C2.2 Part C2: Pricing Data Activity Schedule
C6.5 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C6.6 Spool Piece, Flanged Both sides 150NB 2500.00 3.00
C6.7 67.5° Bend Short 150NB -- 3.00
C6.8 Gate VAlve 150NB -- 3.00
C6.9 Flanged Hose Coupling (Cam and Grove Type)
-- -- 3.00
C7 Pipe Supports
C7.1 Fabricated Pipe Supports (min 70 x 70 x 6 L)
-- Support 100.00
TOTAL CARRIED FORWARD TO SECTION A SUMMARY:
D: SUPPLY AND INSTALLATION OF FRESH WATER PIPING
ITEM REF DESCRIPTION
Diam Length (mm) QTY
Supply Rate
Supply Cost
Erection Rate
Erection Costs Total
D1 Eastern Limb Manifold Piping
D1.1 Spool Piece, Flanged Both sides 150NB 6000.00 47
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 11 C2.2 Part C2: Pricing Data Activity Schedule
D1.2 Spool Piece, Flanged Both sides 150NB 5000.00 2
D1.3 Spool Piece, Flanged Both sides 150NB 4500.00 2
D1.4 Spool Piece, Flanged Both sides 150NB 4000.00 2
D1.5 Spool Piece, Flanged Both sides 150NB 3500.00 2
D1.6 Spool Piece, Flanged Both sides 150NB 3000.00 2
D1.7 Blanked Flange 150NB -- 1
D1.8 78.75° Long Radius Bend, Flanged Both Sides 150NB -- 1
D1.9 90° Long Radius Bend, Flanged Both Sides 150NB -- 1
D1.10 45° Long Radius Bend, Flanged Both Sides 150NB -- 1
D1.11 Unequal Tee 150NB/80NB -- 5
D1.12 Gate VAlve 150NB -- 1
D1.13 Air /Vacuum Valve 25NB -- 1
D1.14 Fabricated Pipe Supports (min 50 x 50 x 5 L) -- -- 110
D2 Western Limb Manifold
D2.1 Spool Piece, Flanged Both sides 150NB 6000.00 47
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 12 C2.2 Part C2: Pricing Data Activity Schedule
D2.2 Spool Piece, Flanged Both sides 150NB 5000.00 2
D2.3 Spool Piece, Flanged Both sides 150NB 4500.00 2
D2.4 Spool Piece, Flanged Both sides 150NB 4000.00 2
D2.5 Spool Piece, Flanged Both sides 150NB 3500.00 2
D2.6 Spool Piece, Flanged Both sides 150NB 3000.00 2
D2.7 Blanked Flange 150NB -- 1
D2.8 78.75° Long Radius Bend, Flanged Both Sides 150NB -- 1
D2.9 90° Long Radius Bend, Flanged Both Sides 150NB -- 1
D2.10 45° Long Radius Bend, Flanged Both Sides 150NB -- 1
D2.11 Unequal Tee 150NB/80NB -- 5
D2.12 Gate VAlve 150NB -- 1
D2.13 Air /Vacuum Valve 25NB -- 1
D2.14 Fabricated Pipe Supports (min 50 x 50 x 5 L) -- -- 110
D3 Risers x10 ( 5 in each limb)
TRANSNET NATIONAL PORTS AUTHORITY TENDER NUMBER: TNPA 745/CIDB DESCRIPTION OF THE WORKS DESIGN, SUPPLY, FABRICATION AND INSTALLATION OF HDPE PIPING IN THE STURROCK DRY DOCK SERVICES TUNNEL IN THE PORT OF CAPE TOWN
PAGE 13 C2.2 Part C2: Pricing Data Activity Schedule
D3.1 Spool Piece, 1 Side Flanged, 1 Side Butt Welded 80NB 1000.00 10
D3.2 Spool Piece, 1 Side Flanged, 1 Side Butt Welded 80NB 3100.00 10
D3.3 90° Long Radius Bend, Butt Welded 80NB -- 10
D3.4 22.5° Long Radius Bend, Butt Welded 80NB -- 10
D3.5 67.5° Long Radius Bend, Butt Welded 80NB -- 10
D3.6 Gate Valve 80NB -- 10
D3.7 Hose Coupling as per figure XX in C3 80NB -- 10
TOTAL CARRIED FORWARD TO SECTION A SUMMARY: