part i: general project information - sccrtc · 2015-05-05 · 2014 rtip funding request p page 2...

15
2014 RTIP Funding Request Page 2 Project Title: Sidewalk Infill PART I: General Project Information 1. Project Title: (Include general location and category of work within the title. For example “Porter St (Soquel-Main St) Road Rehab”. Please avoid using “Improvement” as part of the title and provide more descriptive title of what modifications are being done.) Sidewalk infill on Harkins Slough Road east of Ohlone Parkway and Main Street between Pennsylvania Drive and Pacifica Boulevard 2. Total Funding Requested: $144,000 Total Project Cost: $200,000 3. Implementing Agency: City of Watsonville 4. Sponsoring Public Agency that has Master Agreement with Caltrans: (if different from implementing agency) Same. 5. This is priority number 3 of 3 projects submitted. (If requesting funds for more than one project) 6. Project summary: (Briefly describe the project in 1 to 2 sentences) Install sidewalk where none currently exists along two highly travelled roadways. 7. Project Description/Scope: (Describe the scope of work for the project, including all capital improvements or program characteristics. Please describe the improvements associated with each mode of transportation as applicable. Attach additional information if needed.) Install pedestrian facilities at two locations as described below: 1. Six foot wide by 180 feet long sidewalk on the south side of Harkins Slough Road and east of Ohlone Parkway 2. Six foot wide by 450 feet long sidewalk on the north side of Main Street between Pennsylvania Drive and Pacific Boulevard. 8. Regional Transportation Plan (RTP) Project Number: (from draft 2014 RTP Project List , approved by the RTC August 15, 2013) None. a. Project costs are identified as Constrained” or Unconstrained” in the RTP list (8/2013) N/A 9. Project Cost by Mode: (List the approximate percentage of total project costs related to different transportation modes in the chart below. Project description (above) must include explanation of what will be done related to each applicable mode. For bicycle, pedestrian and transit components, indicate how much of the cost is associated with a new facility versus replacement of existing facility. For instance if a new sidewalk is added as part of a larger road where no sidewalk previously existed, that cost would be shown as “new”. If an existing sidewalk is taken out to widen the road, then a replacement sidewalk built, show cost under “replacement”.)

Upload: others

Post on 30-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 2

Project Title: Sidewalk Infill

PART I:

General Project Information

1. Project Title: (Include general location and category of work within the title. For example “Porter

St (Soquel-Main St) Road Rehab”. Please avoid using “Improvement” as part of the title and

provide more descriptive title of what modifications are being done.)

Sidewalk infill on Harkins Slough Road east of Ohlone Parkway and Main Street between

Pennsylvania Drive and Pacifica Boulevard

2. Total Funding Requested: $144,000

Total Project Cost: $200,000

3. Implementing Agency: City of Watsonville

4. Sponsoring Public Agency that has Master Agreement with Caltrans: (if different from

implementing agency) Same.

5. This is priority number 3 of 3 projects submitted. (If requesting funds for more than one

project)

6. Project summary: (Briefly describe the project in 1 to 2 sentences)

Install sidewalk where none currently exists along two highly travelled roadways.

7. Project Description/Scope: (Describe the scope of work for the project, including all capital

improvements or program characteristics. Please describe the improvements associated with each

mode of transportation as applicable. Attach additional information if needed.)

Install pedestrian facilities at two locations as described below:

1. Six foot wide by 180 feet long sidewalk on the south side of Harkins Slough Road and east of

Ohlone Parkway

2. Six foot wide by 450 feet long sidewalk on the north side of Main Street between Pennsylvania

Drive and Pacific Boulevard.

8. Regional Transportation Plan (RTP) Project Number: (from draft 2014 RTP Project List,

approved by the RTC August 15, 2013) None.

a. Project costs are identified as “Constrained” or “Unconstrained” in the RTP list

(8/2013) – N/A

9. Project Cost by Mode: (List the approximate percentage of total project costs related to different

transportation modes in the chart below. Project description (above) must include explanation of

what will be done related to each applicable mode. For bicycle, pedestrian and transit components,

indicate how much of the cost is associated with a new facility versus replacement of existing

facility. For instance if a new sidewalk is added as part of a larger road where no sidewalk

previously existed, that cost would be shown as “new”. If an existing sidewalk is taken out to widen

the road, then a replacement sidewalk built, show cost under “replacement”.)

Page 2: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 3

Project Title: Sidewalk Infill

*TSM=Transportation System Management (ex. ITS, signal synchronization); TDM=Transportation Demand

Management (ex. rideshare programs)

10. Project Location and Limits or Service Area: Parkway(attach an 8 1/2" x 11" map and/or photos if

available/ applicable; include street names)

Location one: Harkins Slough Road, east of Ohlone Parkway

Location two: Main Street between Pennsylvania Dr. & Pacifica Boulevard

a. Project Length: Harkins Slough Road = 180 feet Main Street = 450 feet

b. Circle the Complete Street Design Type: (See Table 2 of the Complete Streets Guidebook

online at http://sccrtc.org/projects/multi-modal/monterey-bay-area-complete-streets-guidebook/

for description)

% of Total

Cost

by Mode

New facility

cost (not

replacement) Replacement

Road Rehab %

Road –Auto Serving %

Bicycle % $ $

Pedestrian 100% $144,000 $0

Transit % $ $

TSM* % $ $

TDM* %

Planning %

TOTAL 100%

Harkins Slough Rd. Main Street

Page 3: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 4

Project Title: Sidewalk Infill

c. Provide information on existing and projected conditions/context for projects on roadways

(if applicable):

Existing With project (write

“N/C” if no change)

Functional classification of this road, as

defined by FHWA?*

Arterial-Both N/C

Right-of-way width 80’-Harkins Slough

120’-Main Street

N/C

Roadway pavement width 70’- Harkins Slough

80’- Main Street

N/C

# of automobile lanes NB/EB: 2 SB/WB: 2 NB/EB: 2 SB/WB: 2

2-Way Center Turn Lane (Yes/No) Yes N/C

Sidewalks (none, one side or both?) One Both

Sidewalk width 6’ N/C

Landscaping (Yes/No) Yes N/C

On-Street Parking (Yes/No) No N/C

Shoulder width N/A N/C

Bike lane width 5’ N/C

Intersections (Signalized/unsignalized) Signalized N/C

Pavement condition (poor, fair, good) Good/Harkins Slough

Rd.

N/C

Posted speed limit 25-Harkins Slough.

40 – Main St

N/C

Traffic Volumes 9,300-Harkins Slough

32,000 – Main St.

14,300-Harkins Slough

Rd. (2030)

52,000-Main St. (2030) (projected, what year)

Transit Route/Stops (Yes/No) Harkins Slough-No

Main St.-Yes

N/C

Truck Route (Yes/No) Yes N/C

Are accommodations for seniors, disabled,

and youth/students sufficient? (Yes/No)

No Yes

*Note: STP funds cannot be used on roads functionally classified as “local” or “rural minor

collectors” except for bridges not on federal-aid highways and as shown under STP Eligible

Activities

11. Project Schedule (Enter the proposed schedule or actual completion of various project milestones.

Complete either section A. Capital Projects or B. Non-Capital Projects, as appropriate):

A. Capital Projects:

Project Milestone Month/Year

Begin Environmental (PA&ED) Phase Jan.-2014

Circulate Draft Environmental

Document

Document Type (ex.

EIR) Cat Ex

End Environmental Phase (PA&ED Milestone) June-2014

Begin Design (PS&E) Phase July-2014

End Design Phase (complete PS&E) Dec.-2014

Page 4: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 5

Project Title: Sidewalk Infill

Begin Right of Way Phase Jan-2015

End Right of Way Phase (Right of Way Certification Milestone) Jan.-2015

Request Authorization to Proceed with Construction (completion of all prior tasks) July-2015

Award Contract Sep.-2015

End Construction Phase (Construction Contract Acceptance Milestone) Oct.-2015

End Closeout Phase (Closeout Report) June-2016

B. Non- Capital Projects:

Activity* (add additional lines if needed to reflect all tasks)

NONE

Start

Activities

(month/year)

End

Activities

(month/year)

*Please state the activity to be completed (ex. preliminary planning, project implementation,

project completion).

12. Contact Person/Project Manager Name: Murray A. Fontes

Telephone Number: 831-768-3117 E-mail: [email protected]

Page 5: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 6

Project Title: Sidewalk Infill

PART II

Project Benefits

Given the large backlog of transportation needs in the region and the extremely limited amount of

funding available, it is important to ensure that funds are used cost effectively to maximize benefits to

the transportation system. Additionally state and federal rules, as well as RTC policies, require

consideration of how projects will contribute towards implementation of the long-range transportation

plan, the achievement of one or more transportation goals, and implementation of state and federal

policies including the California Complete Streets Act of 2008, SB375, and MAP-21. Project benefits

will be taken into consideration when evaluating projects. Projects are not expected to address all of the

following. Please write N/A where something is not applicable to your project.

1. Generally, what are the benefits of this project? (ex. goal/purpose/benefit of project; problem to

be addressed; importance to the community)

Install sidewalk and complete sidewalk at two locations. One involves installation of a six foot wide

by 180 feet long sidewalk on the south side of Harkins Slough Road and east of Ohlone Parkway.

The new sidewalk will extend from the New School High School to the southeast corner of Harkins

Slough Road and Ohlone Parkway. The second involves installation of a six foot wide by 450 foot

long sidewalk on the north side of Main Street between Pennsylvania Drive and Pacifica Boulevard.

The new sidewalk will provide frontage improvements at the Town and Country Shopping Center

and create a continuous run of sidewalk on the north and east side of Main Street from Green Valley

Road to the Pajaro River

The project will benefit pedestrians in the City of Watsonville by installing sidewalks where none

currently exist. The new sidewalks will complete pedestrian facilities along two major

transportation corridors. These facilities will provide access for the disabled along corridors that

include transit bus facilities.

The Harkins Slough Road sidewalk will extend from the New School High School to the southeast

corner of Harkins Slough Road and Ohlone Parkway. It will complete a one mile long segment of

continuous sidewalk along the south side of the road that will extend from Green Valley Road to the

Watsonville Slough Bridge. This corridor provides access to Pajaro Valley High School and the

various businesses along Green Valley Road, Westgate Business Park, the City of Watsonville

Slough Trail network, the Overlook Shopping Center, the City of Watsonville Nature Center,

Ramsey Park and the Silver Leaf, Quiet Meadow, Bay Breeze and Sunset Cove Subdivisions.

The Main Street sidewalk will extend from Pennsylvania Drive to Pacifica Boulevard. It will

complete a 2.1 mile long segment of continuous sidewalk along the north and east sides of Main

Street that extends from Green Valley Road to the Pajaro River. This corridor includes several bus

stops and provides access to Pajaro Valley High School, Rolling Hills Middle School and the various

businesses along Green Valley Road, five shopping centers, the Watsonville Slough Trail network,

Ramsey Park, the downtown business area, the City Plaza, Civic Center, City Library and Post

Office.

2. How many travelers will be directly served by this project per day? 9,300 Harkins Slough Rd.,

32,000 Main Street

a. ADT volumes (if applicable) 9,300 Harkins Slough Rd., 32,000 Main Street.

Page 6: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 7

Project Title: Sidewalk Infill

b. Other (e.g. avg. number of people directly served/day; number of users of facility/day; TDM-

direct participants) Not available.

c. For projects with bike, ped, transit, or TDM elements – Number of people expected to shift from

automobile to alternative mode Not available (average per day)

d. Source(s) used to develop estimates shown above: None.

(e.g. http://www.ite.org/tripgeneration/otherresources.asp )

3. Who are the primary travelers served/targeted by project?

Commuters Recreational users Visitors

Youth K-12 Students College Students

Low income Seniors Disabled

Other__________________________

a. Briefly describe indirect beneficiaries of the project, if any:

4. What are the key destinations served by this project and distance (in approximate feet) from

project/facility?

Employment centers 100 feet Senior centers ______feet

Senior housing ______feet K-12 Schools 0 feet

Groceries/Services 100 feet Retail/Commercial center 100 feet

Transit centers ______feet Visitor destination 100 feet

Parks/recreational area 500 feet Civic/public facilities ______feet

Other__________________________

a. Are there other planned transportation and/or land use projects that could affect

circulation in the project area in the future? If yes, list projects.

No.

b. Are planned (future) land use projects anticipated to increase travel demand through

project area? (Mark yes or no for each mode)

Car: Yes No Transit: Yes No Truck/Goods: Yes No

Bike: Yes No Pedestrian: Yes No

5. What travel condition(s) are improved or impacted as a result of the proposed project design?

Check all that apply.

Safety: Improves transportation safety

There are currently perceived safety/speeding issues in the project area

Project will reduce fatal and/or injury collisions

There is a history of collisions in the project area

o Number of severe injury or fatal incidents in project area in past 10 years___

(Source? e.g. http://tims.berkeley.edu ___________________)

Improves safety for which modes: Pedestrian

Reduces potential for conflict between cyclists and/or pedestrians and vehicles

Page 7: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 8

Project Title: Sidewalk Infill

Safety improved for youth, vulnerable users (pedestrians/bicyclist), and transportation

disadvantaged (low income, seniors, disabled, minority status)

Provides access to emergency services

System Preservation: Preserves existing transportation infrastructure/facilities or services

o Pavement: Current PCI of road ________. Projected PCI with project________

o Why is this location/facility a priority for preservation, especially over other facilities?

(e.g. is project part of a pavement management plan) ____________________________

______________________________________________________________________

Reduces Vehicle Miles Traveled (VMT)

Reduces vehicle miles traveled per capita

Shifts automobile travel to alternative modes

Decreases the number of people traveling in single occupancy vehicles

Improves access to alternative modes (walk, bike, bus, carpool, etc)

Increases the percentage of people that could walk, bike, or take transit to key

destinations within 30-minutes or less

Increases ridesharing

Increases telework options

Expands Transportation Demand Management (TDM) Programs

Reduces the need for travel

Improves multimodal Level of Service

New multiuse path

Reduces automobile speeds, describe (e.g. traffic calming, speed limit, etc)

________________________________

Increases walking

There are currently lacking/insufficient pedestrian facilities

Improves connectivity, fills gap in sidewalk/pedestrian path network

Reduces distance to walk trip between neighborhood and key destination

Adds new sidewalks or paths on: one or both sides of the street

Widens sidewalk path of travel for current and projected pedestrian volumes

Adds missing curb ramps

Upgrades facility to meet ADA accessibility requirements, implement ADA

Implementation Plan

Reduces pedestrian crossing distance

Adds pedestrian signal heads

Adds pedestrian-actuated traffic signals or automatic pedestrian cycles

Adds audible countdown at intersection

Adds pedestrian-level lighting

Adds high visibility crosswalks

Adds illumination at crosswalks

Other crosswalk enhancements

Adds median safety islands

Minimizes driveways

Adds wayfinding signage

Adds shade trees (Street trees)

Adds planter or buffer strips

Page 8: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 9

Project Title: Sidewalk Infill

Adds benches or other types of seating

Increases bicycling

There are currently lacking/insufficient bicycle facilities

Improves connectivity, fills gap in bicycle network

Reduces distance to bike trip between neighborhood and key destination

New Class I bicycle path

New Class II bicycle path

Shared-Lane Marking (Sharrow)

New Bicycle boulevard

Widens bicycle lanes from ____ feet to _____feet wide

Widens outside lanes or improve shoulders

Adds bicycle actuation at signals (i.e., loop detectors and stencil or other means to make

signals responsive to bicycles)

Adds bicycle box at intersection

Adds color-treated bicycle lane

Adds floating bicycle lane

Adds signs, signals and pavement markings specifically related to bicycle operation on

roadways or shared-use facilities

Adds route/wayfinding signage

Adds long-term bicycle parking (e.g., for commuters and residents)

Adds short-term bicycle parking

Increases public transit usage

There are currently lacking/insufficient transit facilities

There are currently lacking/insufficient transit service

Improves connectivity of transit, fills gap in transit network

Improves transit service reliability, frequency and/or efficiency

ITS/signal priority

Priority bus lane

Bus bulbs/pull outs

Increases transit service, reduces headways

Increases access to transit

Adds sidewalks to bus stops

Adds bicycle racks on buses

Improves access for people with disabilities

Adds bus stop(s)

Improves bus stop/station (adds/upgrades seating, lighting, shade/shelter, trash can, route

information/maps, etc)

Provides real time bus arrival information

Adds Wi-Fi on bus

Reduces air pollution

Reduces greenhouse gas emissions (GHG)

Reduces fuel consumption

Improves travel time reliability of the transportation system. Which modes? _______________

Improves efficiency of the transportation system. Which modes? _______________

Page 9: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 10

Project Title: Sidewalk Infill

Implements Transportation System Management (TSM) programs/projects

Increases miles facility/service can carry passengers and/or freight/goods

Reduces total traffic congestion

Reduces peak period traffic congestion ___AM peak ____PM peak

Shifts peak travel to off-peak periods

Reduces freight traffic congestion

Reduces disparities in safety and access for people who are transportation disadvantaged due to

age, income, disability or limited English proficiency

Improves the convenience and quality of trips

Increases ecological function (such as: increases tree canopy; improves habitat;

improves water quality; reduces storm water runoff; enhances sensitive areas )

Other improvement(s). Please explain, if not addressed in prior questions:

6. Will project result in the elimination or reduction of an existing bike path or sidewalk? Will

the proposed project sever or remove all or part of an existing pedestrian or bicycle facility or

block or hinder pedestrian or bicycle movement? Yes No. If yes, please explain why this

condition is unavoidable and if bicycle and pedestrian accommodations are provided on an

adjacent/parallel street.

a. Was the facility being removed, modified, or replaced previously funded through the RTC?

Yes No N/A

7. Complete Streets Implementation/Design. Given the street design and existing and future

conditions, please complete the following (for projects on roadways). (See the Monterey Bay Area Complete

Street Guidebook for more information, definitions.)

a. Describe how this project is consistent with the guidebook:

The Monterey Bay Area Complete Streets Guidebook outlines various benefits that complete streets

can provide for a community. The proposed infill project will provide a number of these benefits,

including the following:

Transportation equity for will be provided for people experiencing poverty or language barriers,

people of color, older adults, youth, people with disabilities and other groups with limited or no

access to vehicles.

A safe, convenient and attractive travel choice will be available for pedestrians that use the Harkins

Slough Road and Main Street corridors.

Healthy Communities, Economy and Environment will be promoted with the addition of new

pedestrian facilities that encourage walking and improve the health of residents. More people

walking can mean less people driving and a reduction in GHG and criteria pollutant emissions that

contribute to respiratory disease.

Improved Access for People with Disabilities that could use the completed sidewalk network and

access the transit bus system.

Page 10: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 11

Project Title: Sidewalk Infill

Reinvestment in the Local Economy as pedestrians experience reductions in their vehicle costs,

increases in their discretionary incomes and use the increase to invest locally.

Economic Activity in the form of business activity and economic growth can be positively

impacted by the increased pedestrian use and the improved safety and health.

b. Is the project area a candidate for the following?

Road Diet (3 or more lanes, but ADT <20,000, bicycle collisions) Yes No

Traffic Calming: Yes No

Roundabout: Yes No

Transit/Bike/Ped Prioritization at Intersection: Yes No

Transit-Oriented Development/Transit Corridor (15 min. headways: Yes No

Neighborhood Shared Street: Yes No

Pedestrian Place: Yes No

c. Is the complete streets cross section/design for this type of street (as recommended in the Guidebook)

supportable for this project? Yes No

If not, explain why:

Lack of ROW width Insufficient Funding

Trees/environmental constraints Existing Structures

Other____________________________________________________________

d. Have alternative designs been considered? Yes No

e. What refinements of the cross section/design were needed?

Removed/partial zones (Guidebook Ch. 5) for:

Pedestrians Bicyclists Landscaping Vehicles Parking

Considered alternative routes/locations for:

Pedestrians Bicyclists Landscaping Vehicles Parking

f. Exemptions to Complete Streets (refer to Ch. 6 of the Guidebook)

Is the project exempt from accommodating certain users? Yes No

Is the cost excessively disproportionate to the need or probable use? Yes No

There is a documented absence of current and future need? Yes No

Other ___________________________________________________

8. Describe the public input plan for this project. Has public input been sought on this project? What is

the public engagement plan for implementing this project? Is it identified in an adopted plan or other

document? What has been/will be done to maximize participation for diverse members of the public in project

planning and implementation?

Improvement requested by residents through City Council member.

Page 11: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 12

Project Title: Sidewalk Infill

9. Stakeholder Outreach: Which stakeholder groups have already provided input, or will be

asked to provide input in future, on project scope and design?

Have specific changes been requested by stakeholders? Yes No

10. Describe project readiness/deliverability: Provide evidence of the project’s readiness/evidence that

project funding will result in timely completion of the project by discussing the schedule, right-of-way issues,

the involvement of other agencies and participants, and impacts on other jurisdictions, agencies, and

property owners. (For example: What is the status of right-of-way acquisition (if applicable)? Have the

owners been contacted? If so, are they willing to sell the property? What permits may be needed for this

project? Are there any adjacent jurisdictions, agencies, property owners, etc., who would be impacted by the

proposed project? If yes, please list and describe outreach efforts, dates, participants and any results/issues

that could impact the project’s schedule.)

Both project locations are adjacent to a single property owner, so coordination can be focused on just

two parties.

No right of way acquisition is necessary for the Harkins Slough Road location as the proposed

improvements are entirely within the existing road right of way. Some right of way acquisition will

be needed for the Main Street location as the proposed sidewalk is within an area that is privately

owned. While discussions with the property owner have taken place in the past, the effort will need

to be renewed to acquire the necessary right of way. Such discussions would begin in the next

several months.

The Main Street location is on State Highway 152 and a Caltrans encroachment permit will need to

be acquired prior to start of construction. The City shall apply for the permit after right of way

acquisition is complete.

Coordination with property owners at both locations will need to be initiated to ensure that the

proposed improvements address their concerns. The property owner adjacent to the Harkins Slough

Road location has landscaping installed within the road right of way. The City will communicate

with the owner to ensure that he/she is aware of the proposed improvements and can provide input as

to how the existing landscaping can be modified. The Main Street improvements are proposed

within an area of landscaping that is privately owned and maintained. The City shall discuss with

the owner how to modify the site to allow for sidewalk installation and minimize impact on the final

Group Provided

input

Will seek

input

Neighborhood Group X

Business Association

School

Property Owners X

Bicycle Committees

Pedestrian Committee

Group Provided

input

Will seek

input

Transit Agency

Adjacent jurisdictions X

Environmental Groups

Transportation

Disadvantaged

Senior Group

Page 12: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

2014 RTIP Funding Request

Page 13

Project Title: Sidewalk Infill

appearance of the landscaping.

Design and construction of the proposed pedestrian facilities will proceed quickly as the project

limits are defined by the existing curb, gutter and sidewalk. Installation of sidewalk is a standard

construction operation and can be done in a timely manner.

Page 13: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

Complete both sections A. "Cost/Funding Summary" and B. "Detailed Cost Estimate"

Enter the amount to be expended for each project phase in each fiscal year by funding source.

Totals should calculate automatically if electronic file is used.

Project Title:

Sources (Specify fund source type - ex.

RSTP,STIP, AB2766, Local, TDA, etc) Source Total

Committed or

Uncommitted? Env'l (PA/ED) Design (PS&E)

Right-of-Way

(ROW) Construction

New Funds Requested from RTC: $154,000 Uncommitted $0 $0 $10,000 $144,000

Source 2: $46,000 $10,000 $24,000 $0 $12,000

Source 3: $0 $0 $0 $0 $0

Source 4: $0 $0 $0 $0 $0

Source 5: $0 $0 $0 $0 $0

Source 6: $0 $0 $0 $0 $0

Source 7: $0 $0 $0 $0 $0

Total $200,000 $10,000 $24,000 $10,000 $156,000

Fiscal Year each component to begin 2014 2014 2015 2015

Env'l (PA/ED) Design (PS&E)

Right-of-Way

(ROW) Construction

Phase of Work

Round figures to the nearest thousand dollars

Sidewalk Infill Project

PART III

Project Budget & Funding Plan

A. Cost/Funding Summary

CAPITAL PROJECTS

P:\PROJECTS\grant applications\2013\oct 2013 rtc call for projects\project - infill\2014-Project-Application-Package-infill construction cost.xls

Page 14: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

Project Title: Sidewalk Infill Project

Item No.

1 Environmental Studies and Permits $12,000

2 Plans, Specifications, and Estimate $24,000

RIGHT OF WAY

3 Right of Way Acquisition $5,000

4 Right of Way Support $5,000

5

Utility Relocation (exclude if included in

construction) $0

TOTAL RIGHT OF WAY COMPONENT COST $10,000

Item Description Quantity Units Unit Cost Total

6 Construction Survey 1 LS 3,000.00 3,000.00

7 Water Pollution Control 1 LS 6,000.00 6,000.00

8 Storm Water Pollution Prevention Plan 1 LS 1,200.00 1,200.00

9 Mobilization 1 LS 12,000.00 12,000.00

10 Traffic Control System 1 LS 3,000.00 3,000.00

11 Remove Existing Markings 1 LS 2,400.00 2,400.00

12 Adjust Existing Utilities 1 LS 6,000.00 6,000.00

13 Excavation & Grading 250 CY 60.00 15,000.00

14 Conform - HMA Deep Lift 25 TN 120.00 3,000.00

15 Minor Concrete - Curb & Gutter 250 LF 30.00 7,500.00

16 Minor Concrete - Sidewalk 3,000 SF 18.00 54,000.00

17 Traffic Signs 6 EA 350.00 2,100.00

18 Traffic Striping, Markings and Markers 1 LS 2,400.00 2,400.00

19 Restore Landscaping 1 LS 12,000.00 12,000.00

20 Erosion Control 1 LS 2,400.00 2,400.00

21 Demobilization and As-Built Drawings 1 LS 12,000.00 12,000.00

22 Construction Management 1 LS 10,000.00 $10,000

TOTAL CONSTRUCTION ITEMS $154,000

200,000

PART III

Project Budget & Funding Plan

CAPITAL PROJECTS

B. "Detailed Cost Estimate"

CONSTRUCTION (update items to match actual items for project)

Engineer's Estimate

Total Cost

P:\PROJECTS\grant applications\2013\oct 2013 rtc call for projects\project - infill\2014-Project-Application-Package-infill construction cost.xls

Page 15: PART I: General Project Information - SCCRTC · 2015-05-05 · 2014 RTIP Funding Request P Page 2 roject Title: Sidewalk Infill PART I: General Project Information 1. Project Title:

City of Watsonville Grant ApplicationInfill Project

Project Locations