pasadena water and power approve a project contingency amount of $2,500,000 for existing contracts...
TRANSCRIPT
Pasadena Water and Power
APPROVE A PROJECT CONTINGENCY AMOUNT OF $2,500,000 FOR EXISTING CONTRACTS RELATED TO THE LOCAL GENERATION REPOWERING PROJECT - PHASE II; INCREASE THE BUDGET BY $5,000,000;
AND APPROVE AN ADDITIONAL APPROPRIATION OF $10,000,000
City CouncilSeptember 29, 2014
Pasadena Water and Power
Recommendations For GT5 Repowering Project
1. Approve a project contingency of $2.5 million for six existing contracts. City Manager to authorize expenditures
2. Increase budget by $5 million from ~$132 to ~$137 million
> Increase FY2015 appropriation by $10 million … Increase $88 million (approval up to FY2015) to $98 million
§ $ 5 million by new appropriation; and§ $ 5 million by transferring amounts from the currently budgeted and appropriated capital
projects related to the local power plant
5
Financing•Interim - planned LOC•Long term – Electric Revenue Bonds
Pasadena Water and Power
Budget , Appropriation, Workplan, Funding and Financing
Project Budget: The estimated cost of the project …. Can not be spent without Appropriation approved by the City Council.
Appropriation: The funds that can be expended on the project.
Workplan: Projected annual cash flow (payments) against expenses
Fund: Pasadena Light and Power Fund maintained exclusively for the electric utility
operations and capital projects in accordance with the City of Pasadena Charter
Financing: Source of funds i.e. equity and/or Electric Revenue Bonds issued by the Light
and Power Fund
6
Pasadena Water and Power
Project Contingency of $2.5 million
7
Contractors Work Description Base Contract ContingencyTotal Contract (not to exceed)
Power Engineers Owner's engineer $3,000,000 $0 $3,000,000
Worley Parsons Air permitting $310,500 $20,000 $330,500
PCR Services Corp. CEQA study and EIR $211,997 $21,110 $233,107
GE Package Power Power Island Equipment $60,494,529 $1,376,000 $61,870,529
Process Unlimited International Project and construction I management
$3,004,000 $300,000 $3,304,000
ARB, Inc. Balance of Plant design I t and construction
$55,661,973 $0 $55,661,973
Total $122,682,999 $1,717,110 $124,400,109
1. Individual contract contingency amount will be used prior to using Project Contingency for that contract.
2. City Manager authorized to expend the Project Contingency.
3. Monthly report to MSC about the expenditure status of Project Contingency.
Pasadena Water and Power
Increase Budget by $ 5 million
8
$131,904,183
$127,697,205
$4,206,978
Natural gas pipeline/meter upgrades $2,200,000 Other misc. contracts, PO’s & Admin costs $1,506,978 Project Contingency for Existing Contracts $2,500,000 Budget contingency for unforeseen expenses $3,000,000
Proposed New Budget (Approved Budget + Additional Budget needed) $136,904,183
$9,206,978 Sub Total
Additional Budget Needed (Currently Committed Expenditures + Future Estimated Costs and Contingency – Currently Approved Budget) $5,000,000
Currently Approved Budget
Currently Committed Expenditures (contracts, staff costs and Art Funding)
Uncommitted remaining balance ($131,904,183 - $127,697,205)
Future Estimated Costs and Contingency
Pasadena Water and Power
Proposed Funding For GT-5 Project
9
Proposed Funding for the Repowering Project Current Projection Proposed Projection
Equity Fund $20,000,000 $20,000,000
Debt (Electric Revenue Bond Issuance)
a. 2013A Bonds $55,000,000 $55,000,000
b. Planned Letter of Credit and subsequent Electric Revenue Bond issuance $56,904,183 $61,904,183
Total $131,904,183 $136,904,183
Pasadena Water and Power
Increase FY2015 Appropriation by $ 10 million
10
AppropriationWorkplan (actual
up to FY2014)Appropriation
Workplan (actual up to FY2014)
Up to FY2013 $37,952,430 $4,160,697 $37,952,430 $4,160,697
FY2014 $35,900,000 $23,748,455 $35,900,000 $23,748,455
FY2015 $14,200,000 $55,008,226 $24,200,000 $70,038,024
FY2016 $36,208,667 $30,214,020
FY2017 $12,778,138 $8,742,987
Total $88,052,430 $131,904,183 $98,052,430 $136,904,183
Current Approvals/Estimates Proposed Approvals/Estimates
BUDGET
Pasadena Water and Power
Financing for $10 million Appropriation
1. $ 5 million by new appropriation; and2. $ 5 million by transferring amounts from the following local
power plant capital projects
11
AdditionsReduction
s
3194 Local Generation Repowering Project - Phase II $5,000,000
3180 Power Production Facility Improvements ($48,042) No material impact
3149 B-3 SCR Catalyst Replacement ($550,000)Recent testing showed satisfactory performance of the SCR catalyst which may not require replacement prior to B-3 retirement in FY2017
3186 GT-3 and GT-4 Renewals, Replacements, and Improvements ($625,807) No material impact
3182 GT-1 & GT-2 Renewals, Replacement, & Improvements ($3,776,151)Major upgrade will be deferred to FY 2016/17 depending on the decision to repair GT2.
Sub Total $5,000,000 ($5,000,000)
CIP# Description
FY 2015 Proposed Amendment Impact on the Project
Pasadena Water and Power
Future Administrative and Misc.. Costs
13
Misc. Contracts, Purchase Order and Admin Cost
Estimated Cost Remarks
Geotech $25,000 Legal Fees $100,000 CalARP Program Revision $25,000 PWP Labor and Material Cost $566,242 PSLF Model $10,000 Post Completion Noise Survey $50,000 Distribution /Transmission System Upgrades $500,000
Potentially required by Southern California Edison
Polisher Rental $50,000 Local Hire/Buy Local Misc. Exp. $5,375 Air Permitting Consultant $25,000 Acceptance Testing Consultant $25,000 Public Outreach $25,000 PCR Outstanding Claim $100,000 Sub Total $1,506,977
Breakdown for Miscellaneous Contracts, Purchase Order and Administrative Costs
Pasadena Water and Power
Currently Approved Contracts
14
Currently Approved Budget $131,904,183
Approved Major Contracts and Committed Expenditures
Contractors/expenses Base Contract Contingency Total Contract
Power Engineers $3,000,000 - $3,000,000
Worley Parsons $310,500 $20,000 $330,500
PCR Services Corp. $211,997 $21,110 $233,107
GE Package Power $60,494,529 $1,376,000 $61,870,529
Process Unlimited International $3,004,000 $300,000 $3,304,000
ARB, Inc. $55,661,973 - $55,661,973
Other Contracts, P.O’s and Art Funding (1% construction) $1,321,217 $1,321,217
PWP Labor and Material Cost $1,892,400 $1,892,400
Local Hire Consultant $83,479 $83,479
Sub Total $125,980,095 $1,717,110 $127,697,205
Uncommitted remaining balance ($131,904,183 - $127,697,205) = $4,206,978
Pasadena Water and Power
$5 million Transfer
15
Table 1: DETAIL OF PROPOSED FY 2015 CIP BUDGET AMENDMENTS
CIP# Description Appropriations Available for FY 2015
Planned expenditure through
FY 2015
Remaining appropriations
through FY 2015
FY 2015 Proposed Amendment Adjusted Appropriations
Through FY 2015 Impact on the Project
Additions Reductions
3194 Local Generation Repowering Project - Phase II $88,052,430 $88,052,430 $5,000,000 $93,052,430
3180 Power Production Facility Improvements $870,243 $120,000 $750,243 ($48,042) $822,201 No material impact
3149 B-3 SCR Catalyst Replacement $550,000 $550,000 ($550,000) $0Recent testing showed satisfactory performance of the SCR catalyst which may not require replacement prior to B-3 retirement in FY2017
3186 GT-3 and GT-4 Renewals, Replacements, and Improvements $715,807 $90,000 $625,807 ($625,807) $90,000 No material impact
3182 GT-1 & GT-2 Renewals, Replacement, & Improvements $3,926,151 $150,000 $3,776,151 ($3,776,151) $150,000 Major upgrade will be deferred to FY 2016/17
depending on the decision to repair GT2.
Sub Total $94,114,631 $5,000,000 ($5,000,000) $94,114,631
Zero net change
Zero Net Change in appropriations through FY 2015
Pasadena Water and Power
Increase FY2015 Appropriation by $ 10 million
16
AppropriationWorkplan (actual
upto FY2014)Appropriation
Workplan (actual upto FY2014)
Up to FY2013 $37,952,430 $4,160,697 $37,952,430 $4,160,697
FY2014 $35,900,000 $23,748,455 $35,900,000 $23,748,455
FY2015 $14,200,000 $55,008,226 $24,094,746 $70,038,024
FY2016 $36,208,667 $30,214,020
FY2017 $12,778,138 $8,742,987
Total $88,052,430 $131,904,183 $97,947,176 $136,904,183
Current Projection
Proposed Projection
$20,000,000 $20,000,000
$55,000,000 $55,000,000
$56,904,183 $61,904,183
$131,904,183 $136,904,183 Total
Proposed Funding for the Repowering Project
Current Estimates Proposed Estimates
Equity Fund
Debt (Electric Revenue Bond Issuance)
a. 2013A Bonds
b. Planned Letter of Credit and subsequent Electric Revenue Bond issuance
BUDGET
Pasadena Water and Power
Possible Scenario For schedule Interruption
17
Examples of needs for services that could jeopardize project schedule if there is no unused contingency in the approved budget
Dates City Council Approval Amount
Remaining Uncommitted Funds in
the approved $132 million budget
Need City Council approval for Budget
increase
Does project stop for lack of Budget approval
9/23/2014 Already approved, $132 million budget $4,206,978 No No
9/29/2014Project Contingency (pool of contingency for 6 existing
approved contracts)$2,500,000 $1,706,978 No No
10/29/2014, expected Gas meter/pipe upgrade contract $2,000,000 -$293,022 Yes, by 293,022 No
11/1/2015, hypothetical but possible
Geotech consultation (sudden need due to soil condition
encountered during excavation)$5,000 -$5,000 Yes, by $5,000
Yes, could be avoided by issuing a Purchase Order by staff provided there were
sufficient funds in the unused contingency
11/11/2015, hypothetical but possible
Outside attorney fee to prepare response to Court in CEQA
lawsuit$25,000 -$25,000 Yes, by $25,000
Yes, could be avoided by issuing a Purchase Order by staff provided there were
sufficient funds in the unused contingency
Proj
ect s
ched
ule
may
be
affec
ted,
BO
P an
d PI
E co
ntra
ctor
s may
dem
and
de
lay
char
ges