paul drumm; 3rd december 2004; afc mm 1 why? goal: ultimate (cclrc defined) safety & design...

5
paul drumm; 3rd December 2004; AFC MM Why? Goal: Ultimate (CCLRC defined) Safety & Design Review How do we get there? • We need a Process What is needed? • Full Safety & Design assessment How do we ensure success? • Assessment within MICE but outside of the working groups • Propose D esign & S afety W orking G roup Based on group involved in AFCSWG¹ Expanded to cover all MICE – in a timely manner ¹ but with fewer letters – easier to repeat!

Post on 21-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

paul drumm; 3rd December 2004; AFC MM

1

Why?

• Goal: Ultimate (CCLRC defined)Safety & Design Review

– How do we get there?• We need a Process

– What is needed?• Full Safety & Design assessment

– How do we ensure success?• Assessment within MICE but outside of the working groups

• Propose Design & Safety Working Group– Based on group involved in AFCSWG¹– Expanded to cover all MICE – in a timely manner

¹ but with fewer letters – easier to repeat!

paul drumm; 3rd December 2004; AFC MM

2

AFCSWG – as was

• Original Concept for Absorber and Hydrogen System

• Process* heavy for most of MICE

• Ultimate goal stands

Outline designs

Preliminary Assessments

Proposal for final choice

Detailed design

Manufacture and installation

Permission to operate

RAL Defined Review

Failure ModesStress CalculationsInterlocks &Operational ProceduresContingency PlansPressure Vessel &ATEX regulations….

Hazard and Operability Assessment

Working Group

SequenceDocuments Required

MICE Hydrogen Safety Review Procedure

OK for detailed design

OK to Manufacture

Preliminary Hazard and Operability Assessments

ISIS Safety Officer

Reviews

Panel Review

+

+

*

paul drumm; 3rd December 2004; AFC MM

3

Morph to D&SWG…

• Role of existing working groups unchanged• Character and role of the “review panel” is

different:– Internal “audit” process

• unless D&SWG advises that an independent review is needed (matter of risk & competence within MICE)

– D&SWG guides documentation preparation through a series of audits

– D&SWG to assess the documentation• Not the same as a review (less overhead)

– Informs TB & EB on readiness for final review

paul drumm; 3rd December 2004; AFC MM

4

From Document... toPresentation byVideo?

Task LeaderTask Members

ProcessWing Design & Safety Group

Agree Procedure

Develop Concepts & DesignPrepare documentation

Review fit for purpose Documents ok

Pre-manufacture

Acceptance

Document Review

Review

FINALDocument

Audit

Detail Design & Safety…

Manufacture & Install

Operate

Rehearsal

RAL Review

RAL

Audit & Advise

Support

Audit & Advise

You are here!

Agree when ready

Agree when ready

Invitees?

Task LeaderTask Members

Task LeaderTask Members

Advice?

paul drumm; 3rd December 2004; AFC MM

5

Phase 1 Time Scales

• Beam Line needs to be in place end of 2006– Complete beam line review by end 2005– Radiation shielding is a more delicate matter– Target is a potential risk to ISIS operations– Beam Line is (probably low risk)

• ISIS/EID engineering staff• Following established & proven practices

• Spectrometer & Tracker– Low risk

• R&D activities– Medium - Potentially High – design to achieve Low Risk