pbs office of the chief architect presents virtual design ... · • perspective of a pedestrian...

33
PBS Office of the Chief Architect Presents Virtual Design and Construction & Building Information Modeling Technology Presented By (in the order of appearance): Thomas Graves Project Systems Manager GSA PBS Office of the Chief Architect Charles Matta, FAIA Acting Director, Center for Federal Buildings and Modernization GSA PBS Office of the Chief Architect Calvin Kam Visiting Fellow, GSA PBS Office of the Chief Architect Ph.D. Candidate, Stanford University CIFE Martin Fischer, Ph.D. Director, Stanford University CIFE Associate Professor, CEE Department, Stanford University © Copyright 2005. All Rights Reserved.

Upload: others

Post on 11-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

PBS Office of the Chief Architect Presents

Virtual Design and Construction &Building Information Modeling Technology

Presented By (in the order of appearance):

Thomas GravesProject Systems Manager GSA PBS Office of the Chief Architect

Charles Matta, FAIA Acting Director, Center for Federal Buildings and Modernization GSA PBS Office of the Chief Architect

Calvin Kam Visiting Fellow, GSA PBS Office of the Chief Architect Ph.D. Candidate, Stanford University CIFE

Martin Fischer, Ph.D. Director, Stanford University CIFE Associate Professor, CEE Department, Stanford University

© Copyright 2005. All Rights Reserved.

Page 2: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

GSA’s Project Portfolio— 206 Active Major Projects, $12.1 Billion

Page 3: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

GSA’s Industry Partners— Over 500 Business Partners

Page 4: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

GSA’s Approach to BIM

Desired Outcome:

• Maintain and Advance Design Excellence

• Short Term—Projects On Time and Within Budget

• Long Term—Project Life-Cycle Knowledge Transfer

Initiatives:

• Expand National Leadership Role

• Business Process Change

• Leverage New Technology (BIM and IFC’s)

• Engage Other Owners

Page 5: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

GSA’s Approach to BIM

Industry Associations/Partners:

• IAI/NIBS, CIFE/Stanford, CURT, FFC

• AIA, AISC, AGC, CADD/GIS, FIATECH, OSCRE, etc.

Major Activities:

• Office of the Chief Architect’s Pilot Program

• Model Checking—Design Concepts Guidance

• Applied Science/CAVE

• Market Survey and Industry Exchange

Page 6: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

GSA Public Buildings Service and CURT— The Construction Users Roundtable

• 43 owner members, “The Owner’s Voice to the Construction Industry”

• Improving the way construction is planned, managed, accounted for, regulated and executed

• Changing and improving what owners permit, require and accept responsibility for

Page 7: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

CURT White Paper (August 2004) — Recommendations

• Owner-led collaborative project teams

• Integrated project structure

• Open, timely, and reliable information sharing

• Building Information Modeling (BIM)

Page 8: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Tom Graves

Process Change Enabled by New Technology

Level of Influence Curve—Paulson (1976)

Shifting Design Effort—CURT (2004)

Page 9: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

The OCA Pilot Program

• development of 3D-4D models, schedule optimization, cost analysis, animation, and presentations on selected projects

• neutral review and recommendation on technology proposals by AE’s, CM’s, technology consultants, and software vendors

• on-site presentations to regional associates and project teams

• management and coordination with technology consultants

• feedback to project teams pertaining to findings of conflict and coordination issues

Page 10: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

Defining the value proposition from the owner’s perspective

From the owner’s point of view, proper application of the technology improves:

• as-built documentation

• design visualization

• space report and program reconciliation

• design coordination

• communicate tenant/construction sequencing

• lighting study & energy simulation

• traffic/crowd egress simulation

• risk, facility management

Page 11: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

9 pilot projects to date on large-scale ongoing projects across the nation

Nine BIM pilots to date on different project types, across different project phases:

1. 26 Federal Plaza, New York, NY 2. Office Building, Houston, TX 3. U.S. Courthouse, El Paso, TX 4. 300 NLA Federal Bldg, Los Angeles, CA 5. Eisenhower Exec. Office Bldg, Washington, DC 6. GSA Regional Office Building, Washington, DC 7. GSA Central Office Building, Washington, DC 8. Border Station Prototype, U.S.-Canada Border 9. U.S. Courthouse, Portland, OR

Page 12: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

26 Federal Plaza, New York, NY

— Spatial study led to major savings with project planning and HVAC ductwork design & distribution

• an addition to a federal office tower in Manhattan, NY

• as-built 3D model based on laser scanning data at ¼” accuracy was compared against the design 3D model based on the the architectural, structural, and MEP design

• a major error of structural wall location was discovered; laser scan gave a true interstitial dimension that translated to a major saving

Laser Scanning Courtesy of Optira

Page 13: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Office Building, Houston, TX

— Design intent omissions uncovered and coordinated before construction bidding

• a new office building with innovative façade system

• building information modeling enabled early detection of design errors and omissions pertaining to the façade system

• the designer team was able to incorporate the findings, correct the drawings, and avoided costly change orders and RFI’s that would impact the project schedule

Page 14: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

U.S. Courthouse, El Paso, TX

— Automated 3D-based design review, conflicts detection, and resolution

• IFC data exchange with spatial information enables model checker to assess whether the design meets the GSA program

• informative quantitative data about building efficiency, fenestration ratio, volume ratio, rentable area, etc. according to GSA design guideline and the ANSI-BOMA standard can be obtained and automated with the BIM

Page 15: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

300 NLA Federal Bldg, Los Angeles, CA

— Model-based tenant phasing enables schedule reduction and improved cost predictability

• a fully occupied federal building will go through a 16-phase seismic upgrade and modernization

• data integration, 4D-modeling, and the Decision Dashboard enable the team to reduce overall schedule by 19% while uncovering major errors in cost assumptions

• 4D-modeling provides an effective means for communication with the tenant agencies

Page 16: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Eisenhower Executive Off Bldg, Wash D.C.

— A balance between security requirements and historical preservations

• a BIM and a Quicktime movie were constructed based on fabricator’s shop drawings, at 1/48” accuracy

• daylight and shadow were cast based on city’s longitude, latitude

• perspective of a pedestrian was simulated based on elevation and site dimensions

Page 17: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

GSA Regional Off Bldg, Wash D.C.

— Integration of spatial, organization, schedule, and cost information; simulate alternatives

• tenant phasing in a 2-phase modernization project

• information discrepancy was uncovered pertaining to existing tenant locations and sizes

• 4D models and the Decision Dashboard communicate the phasing plans and their cost/time implications across different alternatives

Page 18: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

GSA Central Off Bldg, Wash D.C.

— Energy analysis and computational fluid dynamic simulation of an existing office building

• BIM and IFC enabled direct model exchange with an energy consultant for a simulation of the thermal condition and energy usage of an existing facility

• thermal zones, construction materials, insulation types, and window properties are analyzed by a DOE-2 based program, which simulated energy consumption based on the occupancy activities across a typical work day.

-10

0

10

20

30

40

50

60

70

2 4 6 8 10 12 14 16 18 20 22 24

Space: 089 NC1st_

Courtesy of Olof Granlund Oy

Page 19: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Border Station Prototype, US-Canada Border

— BIM-based design in support of project planning and alternative analysis

• site orientation, vehicular flow, structural alternatives, material choices, and construction means and methods were studied during the early programming phase

• visual animation, orientation trade-off, and pre-fabrication studies were carried out with the building information model

Page 20: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

U.S. Courthouse, Portland, OR

— Improving the means of communications with the public, tenants, and bidding contractors

• a historical landmark undergoes a seismic upgrade with the installation of base isolators

• 4D modeling integrates design intent, structural engineers’ specifications, and a construction schedule into a single model

• the model and the animation fostered GSA’s communications with the public, tenants, and GC bidders

Page 21: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

Benefits of the Pilot Program

The pilots have assisted the project team to:

• uncover error in as-built documents [e.g., 26 Federal Plaza in Manhattan, NY]

• visualize [e.g., base isolation, historic window]

• compare and communicate alternate scenarios

• coordinate [e.g., innovative system]

• simulate [e.g., energy performance]

• analyze building program and automatically compute efficiency ratios using model checker

• optimize [e.g., project schedule in R9]

Page 22: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

“To BIM or Not to BIM”—from a PM’s perspective

1. What aspect(s) of 3D-based technology would make the most impact?

2. What are the cost and risks associated with your unique project setting (team, contract, clients, requirements, schedule, etc.)? Does the potential value worth the cost/risks?

Page 23: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Presentation by Charles Matta/Calvin Kam

Impacts and Outlook of the Pilot Program

Impacts:

• On sharing of experience with other federal agencies

• On the industry, culture, and processes

• On the attitude towards open standard

• On the importance of establishing an owner’s BIM and its requirements.

Outlook:

• OCA is further expanding its BIM-based pilot program

• adding BIM clauses in its facility and CADD standards

• engaging its regions, design consultants, contractors, and technology partners in the adoption of BIM-related technologies

Page 24: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Design-Construction Practice Goals

>= 50% of supply and sales

SomeGlobalization

Life-cycle cost 25% PoorSustainability

BetterGoodSafety

Very small varianceGreat++ productivity

Large VarianceGood?Productivity impact?

Function

Variance 1-5%Variance 5-30%Cost

1 y Design< .5 y ConstructVariance 1-5%

1-6 y Design~1.5 y ConstructVariance 5-100%

Schedule

Goal: 2015Practice: 2005

Page 25: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Amazing Accomplishments in Industry

• Product (building, scope) improvements– Usable square footage increased by 20% for same building footprint – Selection of mechanical systems based on comfort of facility users

and life cycle performance– CM/DM firm: Detailed design cost reduced by 75%, overall project

duration reduced by 55%, while increasing quality for a renovation project

– No field interference for complex steel structures

• Organization improvements– 4x stakeholder involvement in early project phases– Enabling real design/build

• Process improvements– 2x onsite labor productivity for heavy civil project with 100%

schedule reliability– Change orders reduced by 50%– Field-generated RFIs reduced by 60%– Structural steel optimized for field erection considering field welds

and bolts on every project

C t i t

Page 26: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Early User Input through Visualization

Page 27: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Test your mechanical system before you buy it

displacement cooling mixed cooling

Virtual building model enabled CFD simulation, which provided the decision basis to select the – initially -more expensive displacement cooling system because of its better life cycle performance.

Snapshots courtesy of Granlund, Helsinki, Finland

Page 28: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

PB: Subway Project

Source: http://www.mta.nyc.ny.us/capconstr/fstc/planned.htm

Large-scale implementation of 3D/4D modeling through CIFE Visiting Fellow Program

Page 29: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

4D Model of A, B, C Line Reconstruction Method

Page 30: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Design, manufacture, assemble: The building is at once both virtual and actual

Pictures courtesy of Strategic Project Solutions, San Francisco, CA

Page 31: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

Extreme Collaboration

Photograph courtesy of NASA/JPL/Caltech The CIFE iRoom

• Collaborative Engineering Project with– Collocated Organization– Advanced Technical Infrastructure– Formal Goal Metrics– Informal Process and Culture– Closed Knowledge Network

Page 32: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

How will you work in 2015?

Page 33: PBS Office of the Chief Architect Presents Virtual Design ... · • perspective of a pedestrian was simulated based on elevation and site dimensions. GSA Regional Off Bldg, ... dynamic

PBS Office of the Chief Architect Presents

Virtual Design and Construction &Building Information Modeling Technology

Presented By (in the order of appearance):

Thomas Graves [[email protected]]

Charles Matta, FAIA [[email protected]]

Calvin Kam [[email protected]]

Martin Fischer, Ph.D. [[email protected]]

© Copyright 2005. All Rights Reserved.