pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/zone-ii final...

189
1 Punjab Cities Governance Improvement Project Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab REPORT Zone-II, Gujranwala February2016 NEC Consultants (Pvt.) Ltd.

Upload: trancong

Post on 19-Mar-2018

228 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1

Punjab Cities Governance Improvement Project

Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab

REPORT Zone-II, Gujranwala

February2016

NEC Consultants (Pvt.) Ltd.

Page 2: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

2

Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab

February 2016 NEC Consultants Pvt. Ltd Perfect SITE, 22 KM Ferozepur Road, Near GujjuMatta Metro Bus Station, Lahore +92-42-35273741-46, www.nec.com.pk [email protected] This study was assigned by The Urban Unit, Punjab

Page 3: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

3

DISCLAIMER No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying, recording or information storage and retrieval system, without prior written permission of the USPMSU. A publication of the Urban Sector Planning and Management Services Unit (Private) Limited, the opinion expressed in the document are solely those of the authors and publishing them does not in any way constitute an endorsement of the opinion by the USPMSU.

ACKNOWLEDGEMENTS This report has been prepared by The Urban Unit (Urban Sector Policy & Management Unit), P&D Department, Government of Punjab. The Urban Unit, under the Punjab Cities Governance Improvement Project (PCGIP)-DLI-4 is supporting WASAs for implementing Energy Audit Management Opportunities. Energy management opportunities have been extracted from the energy audits of WASA pumps. The Team Dr. NasirJaved Engr. AbidHussainy Engr. Ali Raza ShafqatUllah Muhammad Rizwan KashifShaukat Adnan Khan Editing & Layout By: Ms. MadihaQamar Printed in Pakistan Copyright: Urban Sector Planning and Management Services Unit (Private) Limited.

Page 4: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

4

CONTENTS Contents 4 List of Annexure 4 List of Figures 4 List of Tables 4 List of Acronyms and Abbreviations 5 Glossary 5 1.0 Introduction 7

1.1 Background 7 1.2 Methodology 7 1.3 Scope 8

2.0 Energy Audit Findings 9 2.1 Pumping system efficiency 9 2.2 Electricity consumption trend 11 2.3 Pumping system efficiency improvement potential 13 2.4 Interventions for the improvement of WASA stations 13

LIST OF ANNEXURE

I Energy Audit Reports 2 Selected Pictures

LIST OF FIGURES

I Pumping system efficiency category 11 2 Unit electricity consumption trend (tube wells) 12 3 Unit electricity consumption trend (disposal pumps) 12

LIST OF TABLES

1 Detail of WASAs pumps 8 2 Detail of Zone-II 9 3 Typical overall pumping system efficiency classification 10 4 Detail of motor loading and pumping system efficiency 10 5 Detail of water discharge and electricity consumption 11 6 System energy efficiency potential of pumps 13

7A Interventions & investment required in WASA stations-Zone-II 14 7B Interventions & investment required in WASA stations- Zone-II 16

Page 5: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

5

LIST OF ACRONYMS AND ABBREVIATIONS

Bhp Brake Horsepower Cusec Cubic Feet per Second Ehp Electrical Horsepower Gpm Gallon Per Minute Hp Horsepower kVA Kilo Volt Ampere kW Kilo Watt kWh Kilo Watt Hour LESCO Lahore Electric Supply Company m/s Meter Per Second m3/hr Cubic Meter Per Hour MCB Fuses or Miniature Circuit Breaker Mm Millimeter MS Mild Steel Psig Pound Per Square Inch (Gauge) RPM Revolution Per Minute TDH Total Dynamic Head VFD Variable Frequency Drive WASA Water and Sanitation Agency Whp Water Horsepower

GLOSSARY

Discharge Pressure

The pressure obtained at center line of pump discharge pipe using a calibrated gauge (psig). Discharge pressure is converted to feet and expressed as “Discharge Head”.

Brake Horsepower

The output horsepower of a motor to a pump; may also be used to refer to the required input horsepower to the pump itself.

Deep Well Turbine Pump

A turbine pump installed inside a well casing below the pumping water level in the well.

Discharge Head Head measured above center line of pump discharge pipe.

Drawdown The measured distance that a well’s water level changes from standing/static level to operating pumping level during observed test conditions.

Dynamic Head The sum of the pressure and the pumping head developed by a pump

Friction Head The head required to overcome the fluid friction in a pipe or water system

Friction Losses

Energy losses associated with moving water against rough surfaces. In water pumping applications, it is the water pressure lost as a result of contact between moving water and a pipeline or open channel.

GPM per Foot Drawdown

The ratio of capacity (GPM) to drawdown feet is useful in determining the well’s performance.

Head Alternate term for pressure. One pound per square inch (psi) = 2.31 feet of water head

Overall Plant The ratio of the water horsepower (the overall output of the plant)

Page 6: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

6

or Pumping System Efficiency

to input horsepower (the power input). The overall output can also be defined as the amount of horsepower required to deliver the measured capacity (water gallons per minute) and the measured total head.

Pumping Water Level

The well’s operating water level below center line of discharge pipe as observed during test condition

Static Water Level The well’s water level obtained when pumping plant is at rest.

Suction Head Head measured above center line of pump suction intake. Most often obtained with calibrated bourdon tube pressure gauge (suction pressure) and converted to feet by conversion factor 2.31 ft. water/psi

Suction Lift The distance between pump discharge head and water level.

Total Head

The sum of the water head above and below the center line of the pump discharge pipe. For well applications, the Total Head is the sum of the Discharge Head and the Pumping Water Level. Total head is used in determination of water horsepower and pump performance.

Water Horsepower

The output horsepower of a water pump. It is the combination of flow rate and pressure.

Page 7: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

7

1.0 Introduction 1.1 Background Energy Audit & Energy Efficiency Improvement gram Government of the Punjab, Pakistan with financial assistance from the World Bank, is implementing “Punjab Cities Governance Improvement Project (PCGIP)” for strengthening systems for improved planning, resource management, and accountability in five large cities of Punjab i.e. Lahore, Faisalabad, Multan, Gujranwala and Rawalpindi. The project utilizes a result-based approach and, consistent with this focus, the disbursement decisions to the city and its entities are based on achievement of pre-specified results, referred to as Disbursement linked Indicators (DLIs) which reflect priority elements in furthering the Government’s urban agenda, critical at the provincial level, within the existing legislative, regulative and policy framework of the Government. DLIs includes intermediate outcomes, incremental steps and results contributing to improved efficiency, effectiveness, accountability and service delivery during and beyond the project life by building capacities , system and processes . Disbursement Linked Indicator 4 (DLI -4) aims for improvements in own source revenue collection system that encourages the City Local Government (CDGs), Development Authorities (DAs) and Service providers (WASAs) to bring improved systems for revenue enhancement. This DLI is linked with the initiative of WASAs to carry out the Energy Audit for resources conservation and efficiency to improved service delivery, accountability and own source revenue. One of the proposed actions & initiatives to enhance revenue was to conduct energy audit of WASAs to reduce the power cost by various systematic analysis of the energy use and finding out the energy management opportunities. WASAs each year incur significant cost. It was Rs. 4,697 million in 2014 year for energy/Electricity bills, with an installed capacity of approximately 131 MW for 5,663 Million Gallons per Day (water management), which can be reduced through detailed energy audit and implementing its findings. In the context of existing scenario energy audit of WASAs is a technical and efficient way to obtain energy analysis and savings through improvements that optimize pumping systems of tube well stations and disposal stations to operate efficiently with significant cost saving. The Urban Planning and Management Services Unit, Pvt. Ltd. has assigned NEC Consultants Pvt. Ltd to conduct energy audits of WASAs in Punjab in five major cities of Lahore, Rawalpindi, Faisalabad, Multan and Gujranwala. This is the energy audit report of Zone-II of Gujranwala city. 1.2 Methodology The primary and secondary sources were used to collect data for different WASAs and pumps installed there. The Urban Unit provided information and contact detail of all the WASAs. An energy audit report template was developed to collect field data from each WASA subdivision. Prior to start the on field measurements of each subdivision, meetings were conducted with the respective WASA management and briefed them about the activity. The technical team then collected data by on field measurements of each pump and recorded in their energy audit report template. On the basis of this energy audit report template, The Urban Unit also developed Android based software to record data of each pump online. This data was also recorded on line in this Android based application.

Page 8: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

8

On the basis of field measurements, efficiency of the pumping system was calculated and energy efficiency opportunities were identified. 1.3 Scope The scope of the this assignment is to conduct energy audits of about 1,600 fresh water supply and wastewater disposal pumps installed at different WASA stations in five major cities of Lahore, Rawalpindi, Multan, Faisalabad and Gujranwala. The detail of these pumps is given in Table-1.

Table-1: Detail of WASAs Pumps

WASA Population

Served (Million)

Total Water Connections

Total Sewerage

Connections

Total Supply

Stations

Total Disposal Stations

Total No. of Pump

Sets WASA Lahore 5.48 587,595 583,532 491 99 776

WASA Gujranwala 0.54 29,375 97,236 66 23 112

WASA Faisalabad 1.55 110,452 217,002 87 43 222

WASA Multan 1.2 43,996 175,615 102 21 161

WASA Rawalpindi 1.17 92,468 38,437 362 - 362

Total 9.94 863,886 1,111,822 1,108 186 1,633 The efficiency of each pumping system was evaluated and energy efficiency improvement opportunities were identified for those pumping systems whose efficiencies were not at required level. The detail of reports prepared is as under:

- The energy audit report of each pump was prepared. - On the basis of each pump report, summary report of findings of each WASA

subdivision/zonewas prepared. - On the basis of each subdivision/zone summary report, one consolidated report of

each city for energy efficiency improvement opportunities of the WASAs was prepared.

Page 9: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

9

2.0 Energy Audit Findings There are 12 WASA water supply stations and 09 wastewater disposal pumps in Zone-II of Gujranwala city. The detail of these stations along with pumps installed capacity and actual discharge is given in Table-2:

Table-2: Detail of Zone-II

# WASA Station

No. of Water Supply Pumps

Installed

Installed Capacity (Cusec)

Actual Discharge (Cusec)

1 Bahtha Colony TW-36 01 4.0 4.52 2 DawoodWalaKhooKhiali TW-27 01 2.0 3.50 3 Jinnah Park KangniWala TW-34 01 2.0 1.47 4 Main Bazar Sarfraz Colony TW-31 01 2.0 1.87 5 Nowshera Road Tanki TW-39 01 4.0 4.41 6 Nowshera Road Disposal TW-35 01 2.0 2.32 7 Sheikhupura More TW-44 01 2.0 2.52 8 SheranwalaBagh New TW-48 01 2.0 2.54 9 SheranwalaBaghLady Park TW-47 01 2.0 2.33 10 Sialvi Town Jinnah Road TW-37 01 4.0 4.49 11 TankiKhiali Shah Pur TW-32 01 2.0 2.40 12 Tower Road Khiali New TW-30 01 2.0 2.35 Total 12 30.00 34.72 Wastewater Disposal Pumps

13 Abu Bakar Park Disposal 01 10.0 7.35 14 Kashmir Colony Disposal 01 5.0 4.90 15 Khiali Disposal P-01 01 15.0 8.57 16 Khiali Disposal P-02 01 12.0 8.57 17 Khiali Disposal P-05 01 10.0 7.84 18 Khiali Disposal P-06 01 10.0 6.37 19 Noshehra Road Disposal 01 10.0 7.15 20 Noshehra Road Sansi Disposal 01 20.0 19.11 21 Sarfraz Colony Disposal 01 10.0 7.59 Total 09 102.00 77.45

The installed capacity of WASA tube wells of Zone-II is 11.17 million m3 per annum whereas actual discharge is12.93 million m3 per annum, for average 10 hours per day operation and 365 days per year. This actual discharge is about 14% greater than the installed capacity. The installed capacity of WASA disposal pumps of Zone-II is 37.97 million m3 per annum whereas actual discharge is 28.83 million m3 per annum, for average 10 hours per day operation and 365 days per year. This actual discharge is about 24% lesser than the installed capacity. 2.1 Pumping System Efficiency Pumping plant performance can be classified as “Low”, “Fair”, “Good”, or “Excellent” by referring to the following table, which is based upon the results of thousands of pump tests conducted by Pacific Gas & Electric Company, USA. This classification is used to categorize WASA pumps.

Page 10: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

10

Table-3: Typical Overall Pumping System Efficiency Classification

Motor HP Low Fair Good Excellent 3-7.5 <44.0 44-49.9 50-54.9 >54.9

10 <46.0 46-52.9 53-57.9 >57.9 15 <47.1 48-53.9 54-59.9 >59.9

20-25 <48.0 50-56.9 57-60.9 >60.9 30-50 <52.1 52.1-58.9 59-61.9 >61.9 60-75 <56.0 56-60.9 61-65.9 >65.9 100 <57.3 57.3-62.9 63-66.9 >66.9 150 <58.1 58.1-63.4 63.5-68.9 >68.9 200 <59.1 59.1-63.8 63.9-69.4 >69.4 250 <59.1 59.1-63.8 63.9-69.4 >69.4 300 <60 60-64.0 64.1-69.9 >69.9

Source: Pacific Gas &Electric Company, USA The detail of pumping system efficiency and motor loading of each WASA station is given in Table-4. The calculations for the efficiency determination are given in the energy audit report of each pump in Annexure-1.

Table-4: Detail of Motor Loading and Pumping System Efficiency

WASA Station Motor Load

(%) Pumping System

Efficiency (%) Pumping System Efficiency Rating

Nowshera Road Tanki TW-39 94 72 EXCELLENT Sheikhupura More TW-44 90 80 EXCELLENT SheranwalaBagh New TW-48 89 76 EXCELLENT Bahtha Colony TW-36 81 65 GOOD DawoodWalaKhooKhiali TW-27 96 64 GOOD SheranwalaBagh Lady Park TW-47

86 64 GOOD

Sialvi Town Jinnah Road TW-37 84 67 GOOD TankiKhiali Shah Pur TW-32 90 58 FAIR Nowshera Road Disposal TW-35 102 59 FAIR Main Bazar Sarfraz Colony TW-31 99 41 LOW Jinnah Park KangniWala TW-34 56 50 LOW Tower Road Khiali New TW-30 91 54 LOW Disposal Pumps Kashmir Colony Disposal 92 64 EXCELLENT Khiali Disposal P-05 65 64 GOOD Khiali Disposal P-01 41 65 GOOD Abu Bakar Park Disposal 65 50 LOW Khiali Disposal P-02 71 37 LOW Khiali Disposal P-06 59 44 LOW Noshehra Road Disposal 68 34 LOW Noshehra Road Sansi Disposal 82 50 LOW Sarfraz Colony Disposal 65 46 LOW About 58% of the tube wells are under excellent and good category of pumping system efficiency whereas 42% are under fair and low category as illustrated in Fig-1.

Page 11: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

11

Figure-1: Pumping System Efficiency Category

About 33% of the operational disposal pumps are under excellent and good category whereas 67% are under low category of pumping system efficiency. 2.2 Electricity Consumption Trend The detail of annual water discharge and correspondingly electricity consumption and unit electricity consumption of each WASA station is given in Table-5.

Table-5: Detail of Water Discharge and Electricity Consumption

# WASA Station Annual Water

Discharge (m3)

Annual Electricity Consumption

(kWh)

Unit Electricity Consumption

(kWh/m3) 1 Bahtha Colony TW-36 1,514,385 251,824 0.17 2 DawoodWalaKhooKhiali TW-27 521,220 63,117 0.12 3 Jinnah Park KangniWala TW-34 547,500 77,061 0.14 4 Main Bazar Sarfraz Colony TW-31 976,010 227,758 0.23 5 Nowshera Road Tanki TW-39 1,642,500 324,145 0.20 6 Nowshera Road Disposal TW-35 605,535 118,160 0.20 7 Sheikhupura More TW-44 1,125,660 179,075 0.16 8 SheranwalaBagh New TW-48 1,138,800 176,139 0.15

9 SheranwalaBagh Lady Park TW-47 1,042,440 170,268 0.16

10 Sialvi Town Jinnah Road TW-37 1,504,530 258,925 0.17 11 TankiKhiali Shah Pur TW-32 894,250 149,229 0.17 12 Tower Road Khiali New TW-30 700,800 120,362 0.17 Total 12,213,630 2,116,063 0.17 Disposal Pumps

13 Abu Bakar Park Disposal 3,285,300 214,318 0.07 14 Kashmir Colony Disposal 1,460,000 80,232 0.05 15 Khiali Disposal P-01 3,193,750 150,819 0.05 16 Khiali Disposal P-02 3,193,750 263,549 0.08 17 Khiali Disposal P-05 2,920,000 176,616 0.06

Excellent25%

Good33%

Fair17%

Low25%

Page 12: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

12

18 Khiali Disposal P-06 2,372,500 162,048 0.07 19 Noshehra Road Disposal 5,062,550 353,071 0.07 20 Noshehra Road Sansi Disposal 12,811,500 723,272 0.06 21 Sarfraz Colony Disposal 3,390,120 214,318 0.06 Total 37,689,470 2,338,243 0.06 Total annual energy cost of Zone-II is about Rs. 58 million. The unit electricity consumption trend for each WASA station is illustrated in Fig-2.

Figure-2: Unit Electricity Consumption Trend (Tube Wells)

The unit electricity consumption trend for each disposal pump is illustrated in Fig-3.

Figure-3: Unit Electricity Consumption Trend (Disposal Pumps)

0

0.05

0.1

0.15

0.2

0.25

1 2 3 4 5 6 7 8 9 10 11 12

kWh/m3

0

0.01

0.02

0.03

0.04

0.05

0.06

0.07

0.08

0.09

1 2 3 4 5 6 7 8 9

kWh/m3

Page 13: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

13

2.3 Pumping System Efficiency Improvement Potential The 05 tube wells and 06 disposal pumps having system efficiency in the category of FAIR to LOW, as given in Table-4,have the potential of efficiency improvement into the GOOD category. Table-6 gives detail of this efficiency improvement potential.

Table-6: System Energy Efficiency Potential of Pumps

WASA Station

Existing Pumping Efficiency

(%)

Improved Pumping Efficiency

(%)

Annual

(kWh)

Saving

(Rs)

Imp.Adj

Rep

& Main

Intervention

Motor Repl.

Pump Repl.

Jinnah Park KangniWala TW-34

50 59 11,852 154,078 x x

Main Bazar Sarfraz Colony TW-31

41 61 73,886 960,520 x

Nowshera Road Disposal TW-35 59 61 3,709 48,215 x TankiKhiali Shah Pur TW-32 58 61 6,430 83,596 x Tower Road Khiali New TW-30

54 61 12,973 168,653 x

Abu Bakar Park Disposal 50 63 45,021 585,279 x Khiali Disposal P-02 37 63 107,580 1,398,540 x x Khiali Disposal P-06 44 63 49,360 641,675 x x Noshehra Road Disposal 34 63 164,406 2,137,275 x x Noshehra Road Sansi Disposal 50 64 158,560 2,061,274 x x Sarfraz Colony Disposal 46 63 56,888 739,548 x x Total 690,665 8,978,653

2.4 Interventions for the Improvement of WASA Stations Energy audit activity of Zone-II revealed that there are certain areas of electrical, mechanical and housekeeping which needs improvement. Table-7 presents detail of interventions and investment requirement in each WASA station for better, efficient and safe operation of WASA station. About Rs. 15.64 million are required to improve WASA stations of Zone-II of Gujranwala city.

Page 14: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

14

Table-7A: Interventions & Investment Required in WASA Stations- ZONE II

Intervention WASA Stations

Bahtha Colony TW-36

Dawood Wala Khoo

Khiali TW-27

Jinnah Park

Kangni Wala

TW-34

Main Bazar

Sarfraz Colony TW-31

Nowshera Road

Tanki TW-39

Nowshera

Road Disposal TW-

35

Sheikhupura More TW-44

Sheranwala Bagh

New TW-48

Sheranwala Bagh

Lady Park

TW-47

Sialvi Town Jinnah Road

TW-37

Tanki Khiali

Shah Pur TW-32

Tower Road Khiali New

TW-30

Abu Bakar Park

Disposal

Kashmir

Colony Dispos

al

Khiali Disposal

P-01

Electrical Install VFD × × × × × × × × × × × × × × × Install hour meter × × × × × × × × × × × × × × × Replace ampere meter × Replace volt meter × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × × × × × × × × × Install/connect capacitors at PFI plant

Install PFI control/relay × Install/replace motor terminal box /Improve open and loose motor connection

Improve panel condition Improve wiring condition Replace de-rated capacitors Relocate panel away from bore hole Replace electrical motor × × × Install fan in the panel × × × × × × × × × × × × × × × Replace PFI HRC fuses Replace PFI display meter × × × × × × × × × × × × × × × Correct date & time of electrical meter

Replace/correct electrical meter Replace change over Replace main circuit breaker

Page 15: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

15

Intervention WASA Stations

Bahtha Colony TW-36

Dawood Wala Khoo

Khiali TW-27

Jinnah Park

Kangni Wala

TW-34

Main Bazar

Sarfraz Colony TW-31

Nowshera Road

Tanki TW-39

Nowshera

Road Disposal TW-

35

Sheikhupura More TW-44

Sheranwala Bagh

New TW-48

Sheranwala Bagh

Lady Park

TW-47

Sialvi Town Jinnah Road

TW-37

Tanki Khiali

Shah Pur TW-32

Tower Road Khiali New

TW-30

Abu Bakar Park

Disposal

Kashmir

Colony Dispos

al

Khiali Disposal

P-01

Mechanical Replace damaged/install new flow meter × × × × × × × × × × × × × × × Replace damaged/install new digital pressure gauge × × × × × × × × × × × × × × × Control gland leakage Make operational/install new chlorinator × × × × × × × × × × × × Maintain ratchet plate Adjust impeller × × × Repair & maintenance of pump × Replace existing pumping system Maintain/install new non return valve

Housekeeping Improve general housekeeping × × × × × × × × × × × × × × × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline Maintain monthly record of fuel consumption × × × × × × × × × × × × × × ×

Station Wise Investment (M. Rs) 0.73 0.53 0.57 1.14 0.72 1.22 0.54 0.54 0.55 0.72 0.63 0.60 0.61 0.43 0.71

Annual Saving (M. Rs) 0.00 0.00 0.15 0.96 0.00 0.05 0.00 0.00 0.00 0.00 0.08 0.17 0.59 0.00 0.00 Payback (Year) 0.00 0.00 3.72 1.19 0.00 25.3 0.00 0.00 0.00 0.00 7.57 3.55 1.04 0.00 0.00

Page 16: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

16

Table-7B: Interventions & Investment Required in WASA Stations-ZONE II

Intervention WASA Stations

Khiali Disposal P-

02

Khiali Disposal

P-05

Khiali Disposal

P-06

Noshehra Road

Disposal

Noshehra Road Sansi

Disposal

Sarfraz Colony

Disposal

Electrical Install VFD × × × × × × Install hour meter × × × × × × Replace ampere meter Replace volt meter × × Replace over current relays × Replace over voltage relay × Install/maintain PFI plant × × × × × × Install/connect capacitors at PFI plant

Install PFI control/relay Install/replace motor terminal box

Improve panel condition Improve wiring condition Relocate panel away from bore hole

Replace electrical motor Install fan in the panel × × × × × × Replace PFI HRC fuses Replace PFI display meter × × × × × × Correct date & time of electrical meter

Replace/correct electrical meter

Replace change over Replace main circuit breaker

Page 17: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

17

Intervention WASA Stations

Khiali Disposal P-

02

Khiali Disposal

P-05

Khiali Disposal

P-06

Noshehra Road

Disposal

Noshehra Road Sansi

Disposal

Sarfraz Colony

Disposal

Mechanical Replace damaged/install new flow meter × × × × × ×

Replace damaged/install new digital pressure gauge × × × × × ×

Control gland leakage Maintain ratchet plate Adjust impeller × × × × × Repair & maintenance of pump × × × × ×

Replace existing pumping system

Maintain/install new non return valve

Housekeeping Improve general housekeeping × × × × × ×

Install shades on motor & pump

Fix panel properly Proper support of discharge pipeline

Maintain monthly record of fuel consumption × × × × × ×

Station Wise Investment (M. Rs) 0.92 0.61 0.90 0.89 1.19 0.89

Annual Saving (M. Rs) 1.40 0.00 0.64 2.14 2.06 0.74 Payback (Year) 0.65 0.00 1.39 0.42 0.58 1.20 Total Investment of Subdivision (M.Rs) = 15.64

Page 18: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

18

ANNEXURE-1

Energy Audit Reports

Page 19: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name Muhammad Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact EHSAN ULLAH

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 9 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

BAHTHA COLONY NOWSHEHRA SANSI (Tube well No.36)

0300-7478141

Page 20: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 21: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 14 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 4

Cusec m3/hr

vi) Head (H)180

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 100.98

BHP

ix) Speed (n)1400

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-07-10-8204

Page 22: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by

viii) Discharge Pressure 33 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 125 hp 93.75 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 174.2

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,485 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 280-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 4585

iii) Meter Time and Date

Correct FALSE Not Visible

Page 23: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues FAIR

Gland Leakage Minor

Non Return Valve OK

Chlorinator Not installed

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 (on which flowmeter is clamped)

v) Pipe Perimeter 1010 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 461 m3/hr

Velocity in Pipe 1.75 m/sec

Pressure

i) Pressure at Discharge Side of Pump 33 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 24: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 11 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 371.7 371 374

ii) Ampere 163.5 167.3 162.5

iii) Power Factor 0.75 0.74 0.73

iv) Appearant Power (kVA) 107.9 109.3 111.3

v) Running Power (kW) 75.85 77.5 75.4 76.3

vi) Reactive Power (kVAr) 69.5 70.4 73.3

vi) Motor Working on Loading Basis 81

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,502 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 87.9

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 76.23 ft

vi) Discharge Side Frictional Head 6.67 ft

vii) Dynamic Discharge Head (v+vi) 82.90 ft

Page 25: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 128.82 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 206.28

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 66.03 hp

xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 102.21 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 65.39 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.60 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 9 hrs

xxi) Daily Pump flow 4,149 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,514,385 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 251,824 kWh/yr

xxv) Annual Energy Expenditure on Pumping 3,273,716 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 64.6%. For 125 HP motor efficiency range 63.5-68.9% is considered to be GOOD efficiency range. This pumping system is efficient and needs no intervention.

Page 26: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 733,000 PKR

New 50 KVAr PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

No Water meter New water meter is recommeneded

No pressure gauge New Pressure gauge is recommeneded

Faulty Chlorinator New Chlorinator is recommeneded

Page 27: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name M ASLAM

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact ABDUL ISALAM

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2010

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 4 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

DAWOOD WALA KHOO KHIALI (Tube well No.27)

0340-3847546

Page 28: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 29: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand FLOW PAK Country PAK

ii) ModelB 12 FMC/4S

Serial

iii) Certification Mark

iv) Year of Manufacture2010

v) Flowrate (Q) 2

Cusec m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 60

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

11-0705

Page 30: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by

viii) Discharge Pressure 18 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85

v) Power Factor (Cos ɸ) 0.87

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,470 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 5107.9

iii) Meter Time and Date

Correct FALSE

Page 31: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues GOOD

Gland Leakage Nil

Non Return Valve OK

Chlorinator Not installed

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel No

Wiring GOOD

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 835 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 357 m3/hr

Velocity in Pipe 1.96 m/sec

Pressure

i) Pressure at Discharge Side of Pump 18 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 32: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 10 meter

ii) Pumping Water Level 13 meter

Electric Measurements

i) Voltage 418 424 412

ii) Ampere 73 61 69

iii) Power Factor 0.9 0.89 0.82

iv) Appearant Power (kVA) 53 45 49

v) Running Power (kW) 48 40 41 43.0

vi) Reactive Power (kVAr) 23 20 28

vi) Motor Working on Loading Basis 96

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,485 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 89.7

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 41.58 ft

vi) Discharge Side Frictional Head 8.35 ft

vii) Dynamic Discharge Head (v+vi) 49.93 ft

Page 33: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 92.57 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 159.74

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.74 hp

xiv) Brake Horsepower (bhp) (OEM Data) 60 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 57.64 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 61.24 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 63.75 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.12 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 4 hrs

xxi) Daily Pump flow 1,428 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 521,220 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 63,117 kWh/yr

xxv) Annual Energy Expenditure on Pumping 820,516 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 64%. For 60 HP motor efficiency 61-65.9% is considered to be GOOD.This pumping system is efficent. No need of any intervention regarding pumping system efficiency.

Page 34: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 528,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

No Flow meter New flow meter is recommended

New 25 Kvar PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

Page 35: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name Muhammad Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact NAEEM BUTT

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 1999

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

JINNAH PARK KANGNI WALA (Tube Well No.34)

NA

Page 36: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 37: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 14 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture1999

v) Flowrate (Q) 2

Cusec

vi) Head (H)150

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 42.65

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

15-6655

Page 38: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 8 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 13 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 50 hp 37.5 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 70

v) Power Factor (Cos ɸ) 0.87

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,470 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-S

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 478018

iii) Meter Time and Date

Correct FALSE

Page 39: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 50 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues Poor

Gland Leakage Average

Non Return Valve OK

Chlorinator NO

Flow Meter OK

Pressure Gauge Faulty

Bore Hole in Front of Panel YES

Wiring POOR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 8 (on which flowmeter is clamped)

v) Pipe Perimeter 670 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 150 m3/hr

Velocity in Pipe 1.28 m/sec

Pressure

i) Pressure at Discharge Side of Pump 15 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 40: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 11 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 395 397 398

ii) Ampere 36 30 35

iii) Power Factor 0.96 0.97 0.96

iv) Appearant Power (kVA) 22 21 22

v) Running Power (kW) 21 21 21 21.0

vi) Reactive Power (kVAr) 6 5 6

vi) Motor Working on Loading Basis 56

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,473 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 93.2

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 34.65 ft

vi) Discharge Side Frictional Head 3.70 ft

vii) Dynamic Discharge Head (v+vi) 38.35 ft

Page 41: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 84.27 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 67.12

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 14.05 hp

xiv) Brake Horsepower (bhp) (OEM Data) 42.65 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 28.15 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.95 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.93 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.14 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 1,500 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 547,500 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 77,061 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,001,793 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 59 %

xxvii) Water Flow after Efficiency Improvement 177 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.12 kWh/m3

xxix) Potential of Energy Reduction 15.38 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 11,852 kWh/yr

xxxi) Annual Financial Saving on Pumping 154,078 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 50%. For 50 HP motor efficiency <52.1% is considered to be LOW and 59-61.9% is GOOD efficiency range.This pumping system is inefficent. This pumping system requires impeller adjustment, repair and maintinance of pump to increase its

efficiency up to 59% which is GOOD efficiency. This intervention will save 154,078 Rs annually.

Page 42: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 573,000 PKR

Install VFDNo VFD

Faulty pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

No PFI Plant New 25 KVAr PFI Plant is recommended

Page 43: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name M IQBAL

i) Name of Pumping Station

ii) Name of Subdivision ZONE-2

iii) Operator Name & Contact M TARIQ

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2001

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 14 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

MAIN BAZAR SARFRAZ COLONY (Tube Well No.31)

0322-5611782

Page 44: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes (Non-operational) No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 45: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 14 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2001

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 45.9

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-8435

Page 46: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 29 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 21234

iii) Meter Time and Date

Correct FALSE

Page 47: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not Installed

Panel Condition/Issues GOOD

Gland Leakage Average

Non Return Valve OK

Chlorinator FAULTY

Flow Meter FAULTY

Pressure Gauge NO

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 840 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 191 m3/hr

Velocity in Pipe 1.05 m/sec

Pressure

i) Pressure at Discharge Side of Pump 29 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 48: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 11 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 405 405 405

ii) Ampere 83 87 85

iii) Power Factor 0.78 0.72 0.76

iv) Appearant Power (kVA) 58 59 56

v) Running Power (kW) 46 43 44 44.3

vi) Reactive Power (kVAr) 36 40 38

vi) Motor Working on Loading Basis 99

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,478 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 87.7

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 66.99 ft

vi) Discharge Side Frictional Head 2.41 ft

vii) Dynamic Discharge Head (v+vi) 69.40 ft

Page 49: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 115.32 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 85.46

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 24.49 hp

xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 59.43 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 53.36 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 41.21 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 14 hrs

xxi) Daily Pump flow 2,674 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 976,010 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 227,758 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,960,855 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 61 %

xxvii) Water Flow after Efficiency Improvement 283 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.16 kWh/m3

xxix) Potential of Energy Reduction 32.44 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 73,886 kWh/yr

xxxi) Annual Financial Saving on Pumping 960,520 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 41.2%. For 60 HP motor efficiency <56% is considered to be LOW and 61-65.9% is GOOD efficiency range.This pumping system is inefficent. This pumping system requires motor to be replaced to increase the efficiency up to 61% which is GOOD efficiency. This

intervention will save 960,520 Rs annually.

Page 50: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 1,143,000 PKR

No pressure gauge New Pressure gauge is recommeneded

Faulty Chlorinator New Chlorinator is recommeneded

Faulty Water meter New water meter is recommeneded

New 25 Kvar PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

Page 51: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name Muhammad Asalam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-2

iii) Operator Name & Contact M ABBAS

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 1999

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

NOSHERA ROAD TANKI (Tube Well No.39)

0321-6451764

Page 52: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 53: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 4

Cusec m3/hr

vi) Head (H)180

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 100.98

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-844

Page 54: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 12 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 50 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 125 hp 93.75 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 174.2

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,485 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 280-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 11050

iii) Meter Time and Date

Correct FALSE

Page 55: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues GOOD

Gland Leakage Minor

Non Return Valve OK

Chlorinator FAULTY

Flow Meter Not installed

Pressure Gauge OK

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 (on which flowmeter is clamped)

v) Pipe Perimeter 1000 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 450 m3/hr

Velocity in Pipe 1.71 m/sec

Pressure

i) Pressure at Discharge Side of Pump 50 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 56: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 12 meter

ii) Pumping Water Level 15 meter

Electric Measurements

i) Voltage 373 379 375

ii) Ampere 159 155 158

iii) Power Factor 0.85 0.81 0.83

iv) Appearant Power (kVA) 111 111 111

v) Running Power (kW) 89 87 89 88.3

vi) Reactive Power (kVAr) 52 57 55

vi) Motor Working on Loading Basis 94

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,488 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 92.9

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 115.5 ft

vi) Discharge Side Frictional Head 6.38 ft

vii) Dynamic Discharge Head (v+vi) 121.88 ft

Page 57: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 171.08 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 201.36

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 85.60 hp

xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 118.41 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 84.77 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 72.29 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 4,500 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,642,500 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 324,145 kWh/yr

xxv) Annual Energy Expenditure on Pumping 4,213,891 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 72.29%. For 125 HP motor efficiency >68.9 is considered to be Excellent efficiency .This pumping system requires no intervention.

Page 58: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 718,000 PKR

Install VFDNo VFD

No Water meter New water meter is recommeneded

Faulty Chlorinator New Chlorinator is recommeneded

No PFI Plant New 50 Kvar PFI Plant is recommended

Page 59: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name M Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact TASEER HUSSAIN

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 7 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

NOWSHERA ROAD DISPOSAL T/W (Tube Well No.35)

0313-7516886

Page 60: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 61: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)180

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 53.44

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-07-10-8205

Page 62: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 8 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 36 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 7018

iii) Meter Time and Date

Correct FALSE

Page 63: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues FAIR

Gland Leakage Minor

Non Return Valve OK

Chlorinator NO

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 8 (on which flowmeter is clamped)

v) Pipe Perimeter 670 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 237 m3/hr

Velocity in Pipe 2.03 m/sec

Pressure

i) Pressure at Discharge Side of Pump 36 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

200 (Combined for Tube Well & Disposal)

Page 64: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 11 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 396 403 400

ii) Ampere 87 82 86

iii) Power Factor 0.77 0.78 0.77

iv) Appearant Power (kVA) 60 57 59

v) Running Power (kW) 46 45 47 46.0

vi) Reactive Power (kVAr) 38 35 39

vi) Motor Working on Loading Basis 102

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,475 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 87.2

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 83.16 ft

vi) Discharge Side Frictional Head 9.18 ft

vii) Dynamic Discharge Head (v+vi) 92.34 ft

Page 65: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 138.26 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 106.05

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.43 hp

xiv) Brake Horsepower (bhp) (OEM Data) 53.44 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 61.66 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 68.18 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 59.09 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 7 hrs

xxi) Daily Pump flow 1,659 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 605,535 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 118,160 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,536,082 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 61 %

xxvii) Water Flow after Efficiency Improvement 245 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.19 kWh/m3

xxix) Potential of Energy Reduction 3.14 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 3,709 kWh/yr

xxxi) Annual Financial Saving on Pumping 48,215 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 59.01% but motor is running in overload condition (102%). For 60 HP motor efficiency range 56-60.9% is considered to be Fair and 61-65.9 % is GOOD.This pumping system is inefficent. This pumping system requires motor to be replaced to increase its efficiency up to 61% which is GOOD efficiency. This intervention will save 48,215 Rs annually.

Page 66: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 1,223,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

No Water meter New water meter is recommeneded

New 25 KVAr PFI Plant is recommendedNo PFI Plant

Replace motorMotor is in efficient

Install VFDNo VFD

Page 67: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name M ASLAM

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact M SHAMSHAD

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 12 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

SHEKHUPURA MORE (Tube Well No.44)

0321-5664525

Page 68: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 69: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 2

Cusec m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 45.9

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-8436

Page 70: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 40 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 23050

iii) Meter Time and Date

Correct FALSE

Page 71: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues GOOD

Gland Leakage Minor

Non Return Valve OK

Chlorinator NO

Flow Meter Faulty

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping FAIR

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 875 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 257 m3/hr

Velocity in Pipe 1.41 m/sec

Pressure

i) Pressure at Discharge Side of Pump 40 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 72: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 13 meter

ii) Pumping Water Level 17 meter

Electric Measurements

i) Voltage 388 386 388

ii) Ampere 76 81 77

iii) Power Factor 0.78 0.77 0.75

iv) Appearant Power (kVA) 51 54 52

v) Running Power (kW) 41 42 39 40.7

vi) Reactive Power (kVAr) 32 34 34

vi) Motor Working on Loading Basis 90

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,489 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 87.2

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 92.4 ft

vi) Discharge Side Frictional Head 4.42 ft

vii) Dynamic Discharge Head (v+vi) 96.82 ft

Page 73: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 152.58 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 86.25

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 43.60 hp

xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.51 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 94.99 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 79.98 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.16 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 12 hrs

xxi) Daily Pump flow 3,084 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,125,660 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 179,075 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,327,976 PKR/Yr

11 Summary of Findings

The Efficiency of this pumping system is Excellent. . This pumping system requires no intervention regarding pumping system efficiency.

Page 74: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 543,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

Faulty Flow meter New flow meter is recommended

New 25 Kvar PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

Page 75: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name Muhammad Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact KHAWAR NADEEM

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 12 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

SHERAWALA BAGH (WRESTLING) NEW (Tube Well No.48)

0300-7428684

Page 76: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 77: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 45.9

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-8438

Page 78: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 35 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 22499

iii) Meter Time and Date

Correct FALSE

Page 79: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues GOOD

Gland Leakage Average

Non Return Valve OK

Chlorinator Not installed

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring GOOD

Housekeeping FAIR

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 860 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 260 m3/hr

Velocity in Pipe 1.43 m/sec

Pressure

i) Pressure at Discharge Side of Pump 35 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 80: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 13 meter

ii) Pumping Water Level 17 meter

Electric Measurements

i) Voltage 381 382 384

ii) Ampere 77 73 81

iii) Power Factor 0.75 0.8 0.79

iv) Appearant Power (kVA) 51 48 54

v) Running Power (kW) 38 39 43 40.0

vi) Reactive Power (kVAr) 34 29 33

vi) Motor Working on Loading Basis 89

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,484 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 91.8

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 80.85 ft

vi) Discharge Side Frictional Head 4.52 ft

vii) Dynamic Discharge Head (v+vi) 85.37 ft

Page 81: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 141.13 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 87.25

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 40.80 hp

xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 53.62 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 88.89 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 76.09 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.15 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 12 hrs

xxi) Daily Pump flow 3,120 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,138,800 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 176,139 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,289,812 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 76.09%. For 60 HP motor efficiency > 65.9% is considered to be Excellent.This pumping system is efficent. This pumping system requires no intervention regarding pumping system efficiency.

Page 82: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 543,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

No Water meter New water meter is recommeneded

New 25 KVAr PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

Page 83: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name Muhammad Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact KHAWAR NADEEM

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 12 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

SHERAWALA BAGH LADY PARK (Tube Well No.47)

0300-7428684

Page 84: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 85: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 45.9

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-8439

Page 86: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 30 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 34285

iii) Meter Time and Date

Correct FALSE

Page 87: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues panel condition is good but volt meter is defective.

Gland Leakage Minor

Non Return Valve OK

Chlorinator NO

Flow Meter FAULTY

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring GOOD

Housekeeping FAIR

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 860 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 238 m3/hr

Velocity in Pipe 1.30 m/sec

Pressure

i) Pressure at Discharge Side of Pump 30 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 88: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 13 meter

ii) Pumping Water Level 16 meter

Electric Measurements

i) Voltage 379 381 379

ii) Ampere 77 69 76

iii) Power Factor 0.77 0.79 0.8

iv) Appearant Power (kVA) 51 46 45

v) Running Power (kW) 39 36 41 38.7

vi) Reactive Power (kVAr) 29 28 32

vi) Motor Working on Loading Basis 86

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,483 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 92.2

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 69.3 ft

vi) Discharge Side Frictional Head 3.77 ft

vii) Dynamic Discharge Head (v+vi) 73.07 ft

Page 89: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 125.55 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 106.50

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 33.22 hp

xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 51.83 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 72.39 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.10 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.16 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 12 hrs

xxi) Daily Pump flow 2,856 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,042,440 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 170,268 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,213,485 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 64%. For 60 HP motor efficiency range 61-65.9% is considered to be GOOD efficiency range.This pumping system is efficent. This pumping system requires no intervention.

Page 90: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 548,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

Faulty Water meter New water meter is recommeneded

New 25 Kvar PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

New V meter recommendedVolt meter faulty

Page 91: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer GULL/ HURR

WASA Staff Name M IQBAL

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact M ASHRAF

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 9 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

SIALVI TOWN JINNAH ROAD(Tube Well No.37)

0343-4979023

Page 92: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 93: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 14 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture2008

v) Flowrate (Q) 4

Cusec 270 m3/hr

vi) Head (H)180

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 100.98

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-07-10-8203

Page 94: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 34 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 125 hp 93.75 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 174.2

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,485 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 280-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading NOT VISIBLE

iii) Meter Time and Date

Correct FALSE

Page 95: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues FAIR. Ampere meter is faulty

Gland Leakage Minor

Non Return Valve OK

Chlorinator Not installed

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping GOOD

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 980 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 458 m3/hr

Velocity in Pipe 2.51 m/sec

Pressure

i) Pressure at Discharge Side of Pump 34 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 96: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 12 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 384 381 384.6

ii) Ampere 163 167 161.9

iii) Power Factor 0.72 0.7 0.74

iv) Appearant Power (kVA) 108.3 110.1 110.5

v) Running Power (kW) 78 77.1 80.1 78.4

vi) Reactive Power (kVAr) 75.1 78.6 74.3

vi) Motor Working on Loading Basis 84

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,487 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 92.9

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 6.56 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 78.54 ft

vi) Discharge Side Frictional Head 13.77 ft

vii) Dynamic Discharge Head (v+vi) 92.31 ft

Page 97: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 138.23 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 307.40

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 70.39 hp

xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 105.09 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 69.71 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 66.98 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 9 hrs

xxi) Daily Pump flow 4,122 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,504,530 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 258,925 kWh/yr

xxv) Annual Energy Expenditure on Pumping 3,366,024 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 67%. For 125 HP motor efficiencoy range 63.5-68.9 is considered to be Good so pumpming system is efficient and it requires no intervention.

Page 98: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 723,000 PKR

No pressure gauge New Pressure gauge is recommeneded

Faulty Chlorinator New Chlorinator is recommeneded

No Water meter New water meter is recommeneded

New 50 Kvar PFI Plant is recommendedNo PFI Plant

Install VFDNo VFD

Install a new ampere meterAmpere meter is defective

Page 99: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name Muhammad Aslam

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact SHOUKAT ALI

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2008

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

TANKI KHIALI SHAH PUR OHR (Tube Well No.32)

0344-4232894

Page 100: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 101: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 45.9

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-08-10-8434

Page 102: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 25 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 14197.48

iii) Meter Time and Date

Correct FALSE

Page 103: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues Fair. Ampere and volt meters are defective

Gland Leakage Minor

Non Return Valve OK

Chlorinator Not installed

Flow Meter Not installed

Pressure Gauge Not installed

Bore Hole in Front of Panel NO

Wiring FAIR

Housekeeping FAIR

OK

Foundation/Civil work OK

Ratchet plate ok

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 8 (on which flowmeter is clamped)

v) Pipe Perimeter 685 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 245 m3/hr

Velocity in Pipe 2.10 m/sec

Pressure

i) Pressure at Discharge Side of Pump 25 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 104: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 11 meter

ii) Pumping Water Level 15 meter

Electric Measurements

i) Voltage 394 389 390

ii) Ampere 74 85 80

iii) Power Factor 0.77 0.77 0.7

iv) Appearant Power (kVA) 51 57 54

v) Running Power (kW) 39 45 38 40.7

vi) Reactive Power (kVAr) 32 36 39

vi) Motor Working on Loading Basis 90

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,486 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 86.5

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 57.75 ft

vi) Discharge Side Frictional Head 9.86 ft

vii) Dynamic Discharge Head (v+vi) 67.61 ft

Page 105: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 116.81 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 82.22

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 31.82 hp

xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.51 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 69.32 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.37 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 2,450 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 894,250 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 149,229 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,939,980 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 61 %

xxvii) Water Flow after Efficiency Improvement 256 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.16 kWh/m3

xxix) Potential of Energy Reduction 4.31 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 6,430 kWh/yr

xxxi) Annual Financial Saving on Pumping 83,596 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 58.37%. For 60 HP motor efficiency range 56-60.9% is considered to be Fair and 61-65.9% is GOOD.This pumping system is inefficent. This pumping system requires impeller adjustment to increase its efficiency up to 61% which is GOOD efficiency.

This intervention will save83,596 Rs annually.

Page 106: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 633,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

No Flow meter New flow meter is recommended

New 25 Kvar PFI Plant is recommendedNo PFI Plant

It requires impeller adjsutmentPump is in efficient

No VFD Install VFD

Install new ampere and volt meters Ampere and volt meter faulty

Page 107: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer WASEEM /IZHAR

WASA Staff Name M ASLAM

i) Name of Pumping Station

ii) Name of Subdivision ZONE-II

iii) Operator Name & Contact M TARIQ

iv) Total Number of Pumps Installed 1

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation 2009

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty 1

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 1

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 8 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

TOWER ROAD KHIALI (NEW) (Tube Well No.30)

0321-6460720

Page 108: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

xiii) Availability of Chlorinator

Yes No

2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)

i) Type of Pump Deep Well

Submersible

Overhung

Between Bearing

ii) Mounting / Erection

Horizontal Vertical

Foundation

iii) Concrete Bolted Bolted

iv) Lubrication Type

Oil Water

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi 4

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Ground Water Aquafier Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Fresh Water Supply Network

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 109: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv)

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand K S B Country PAK

ii) ModelB 12 B/4

Serial

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 2

Cusec 270 m3/hr

vi) Head (H)165

ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 47.6

BHP

ix) Speed (n)1450

RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)

ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)

iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Foot Valve

Bends Control Valve

Strainer Elbows

iv) Storage Capacity of Suction Source (Aquafier)

v) Working Volume of Source

vi) Suction Lift (from Datum Line)

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure (Not Valid incase of Tubewells)

21-09-10-10045

Page 110: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe 10 inch

ii) Length of Discharge Pipe (Not known as directly connected to network underground)

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Control 1 Check

Bends Elbow 1

Strainer Wash out 0

iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))

v) Working Volume of Discharge Destination (Not known as directly connected to network underground))

vi) Discharge Elevation (from Datum Line) (In case of no gauge)

vii) Availbility of Pressure Gauge Yes No (Installed by Team)

viii) Discharge Pressure 27 psig

6 Motor Nameplate Data

i) Manufacturer SIEMENS

ii) Rated kW / hp 60 hp 45 kW

iii) Voltage Range (Volts) 380 Volts

iv) Current (Ampere) 85.4

v) Power Factor (Cos ɸ) 0.86

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 1,475 RPM

vii) Reference Frequency 50 C/S

viii) Insulation Class F

ix) Motor Frame Size 225-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading FAULTY

iii) Meter Time and Date

Correct FALSE

Page 111: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant Not installed

Panel Condition/Issues FAIR, no voltmeter

Gland Leakage NO

Non Return Valve OK

Chlorinator Not installed

Flow Meter OK

Pressure Gauge Not installed

Bore Hole in Front of Panel YES

Wiring GOOD

Housekeeping FAIR

OK

Foundation/Civil work OK

Ratchet plate OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 (on which flowmeter is clamped)

v) Pipe Perimeter 830 mm (on which flowmeter is clamped)

vi) Type of Clamping (V/N/Z) Z

viii) Flow Measurement 240 m3/hr

Velocity in Pipe 1.32 m/sec

Pressure

i) Pressure at Discharge Side of Pump 27 psig

ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)

Motor Terminal Box

Page 112: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

iii) Water Shutoff Head

Levels

i) Static Water Level 10 meter

ii) Pumping Water Level 14 meter

Electric Measurements

i) Voltage 391 390 388

ii) Ampere 75 80 81

iii) Power Factor 0.77 0.8 0.76

iv) Appearant Power (kVA) 51 54 54

v) Running Power (kW) 39 43 41 41.0

vi) Reactive Power (kVAr) 32 32 35

vi) Motor Working on Loading Basis 91

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 1,491 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 85.6

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

Calculations

10

i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft

ii) Static Suction Head (Only for WW Pump) ft

iii) Suction Side Frictional Head (Only for WW Pump) ft

iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft

v) Discharge Head (Pressure Gauge) 62.37 ft

vi) Discharge Side Frictional Head 3.80 ft

vii) Dynamic Discharge Head (v+vi) 66.17 ft

Page 113: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 112.09 ft

ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 80.54

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 29.91 hp

xiv) Brake Horsepower (bhp) (OEM Data) 47.6 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.96 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 62.84 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 54.43 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 8 hrs

xxi) Daily Pump flow 1,920 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 700,800 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 120,362 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,564,705 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 61 %

xxvii) Water Flow after Efficiency Improvement 269 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.15 kWh/m3

xxix) Potential of Energy Reduction 10.78 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 12,973 kWh/yr

xxxi) Annual Financial Saving on Pumping 168,653 PKR/Yr

11 Summary of Findings

Efficiency of the pumping system is 54%. For 60 HP motor efficiency <56% is considered to be LOW and 61-65.9% is GOOD.This pumping system is inefficent. This pumping system requires motor to be replaced to increase its efficiency up to 61% which is GOOD efficiency. This intervention will save 168,653 Rs annually.

Page 114: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

12 Estimated Investment for Improvement Plan 598,000 PKR

No pressure gauge New Pressure gauge is recommeneded

No Chlorinator New Chlorinator is recommeneded

Volt meter faulty New V meter is recommeneded

New 25 KVAr PFI Plant is recommendedNo PFI Plant

Replace motorMotor is in efficient

Page 115: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station ABU BAKAR PARK DISPOSAL

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Khaleeq-ur-rehman

iv) Total Number of Pumps Installed 4

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 4

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 4

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 12 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 116: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 03

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 117: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model KV PK 350/500 Serial 21-05-10-2841

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 10 Cusec 1,020 m3/hr

vi) Head (H) 40 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 64 BHP

ix) Speed (n) 725 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 20

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 118: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 12

ii) Length of Discharge Pipe (ft) 250

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 18 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer SEMIENS

ii) Rated kW / hp 100 hp 75 kW

iii) Voltage Range 400 Volts

iv) Current 140 Amperes

v) Power Factor (Cos ɸ) 0.84

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 735 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size 315-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 8602.69

iii) Meter Time and Date

Correct FALSE

Page 119: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200,200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues EXCELLENT

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring EXCELLENT

Housekeeping OK

Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 inches

v) Pipe Perimeter 1,020 mm

vi) Type of Clamping (V/N/Z)

viii) Flow Measurement 750 m3/hr 12.5 m3/min

Velocity in Pipe 2.86 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 82 meter

Electric Measurements Volt 389.3 394.3 392.7

Ampere 97.7 88.7 93.7

kW 48.67 Power Factor 0.74 0.79 0.76

vi) Motor Working on Loading Basis 65 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 746 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 85.5

Page 120: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 18 ft

vi) Frictional Head (Suction and Discahrge) 23.93 ft

Page 121: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 38.93 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 32.47 hp

xiv) Brake Horsepower (bhp) (OEM Data) 64.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65.24 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 50.73 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.77 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 12 hrs

xxi) Daily Pump flow 9,000 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 3,285,000 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 214,318 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,786,129 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 63 %

xxvii) Water Flow after Efficiency Improvement 949 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3

xxix) Potential of Energy Reduction 21.01 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 45,021 kWh/yr

xxxi) Annual Financial Saving on Pumping 585,279 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 49.77%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 585,279PKR.

Page 122: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 610,000 PKR

No water flow meter Water flowmeter is recommended

Install VFD No VFD

No pressure guage Digital pressure guage is recommended

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

Page 123: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station KASHMIR COLONY DISPOSAL

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Abid Ali 0300-0838425

iv) Total Number of Pumps Installed 2

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 2

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 2

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 8 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 124: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 01

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 125: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model SEWATEC K 250-40 IGIV Serial 9972156552/100/2

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 5 Cusec 510 m3/hr

vi) Head (H) 40 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 30 BHP

ix) Speed (n) 978 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 10

ii) Enter Length of Suction Pipe (ft) 10

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 126: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 10

ii) Length of Discharge Pipe (ft) 100

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 27 ft

Suction Side Elevation 5 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer KSB

ii) Rated kW / hp 40 hp 30 kW

iii) Voltage Range 400 Volts

iv) Current 59.3 Amperes

v) Power Factor (Cos ɸ) 0.84

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 980 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size 1-L-225-M-6

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading

iii) Meter Time and Date

Correct FALSE

Page 127: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 100 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues GOOD

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring EXCELLENT

Housekeeping OK

Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 10 inches

v) Pipe Perimeter 850 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 500 m3/hr 8.3333 m3/min

Velocity in Pipe 2.74 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 34 meter

Electric Measurements Volt 399.9 399.1 397.9

Ampere 48.6 47.6 49.5

kW 27.33 Power Factor 0.82 0.823 0.79

vi) Motor Working on Loading Basis 92 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 991 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 78.2

Page 128: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 5 ft

v) Static Discahrge Head 27 ft

vi) Frictional Head (Suction and Discahrge) 19.85 ft

Page 129: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 41.85 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 23.27 hp

xiv) Brake Horsepower (bhp) (OEM Data) 30.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 36.64 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 77.56 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 63.51 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 8 hrs

xxi) Daily Pump flow 4,000 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 1,460,000 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 80,232 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,043,010 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 63.51%. For pump attached with 40 HP motor, efficiency above 61% is considered to be excellent . This pumping system does not require any intervention.

Page 130: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 425,000 PKR

Install VFD No VFD

No pressure guage Digital pressure guage is recommended

No power factor improvement (PFI) plant is installed PFI of 20 KVAR is recommended

No water flow meter Water flowmeter is recommended

Page 131: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station KHIALI DISPOSAL P # 1

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Mohammad Iqbal

iv) Total Number of Pumps Installed 6

v) Total Number of Pumps in Operation 4

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 6

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 6

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 132: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 01

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 133: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model Serial

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 15 Cusec 1,530 m3/hr

vi) Head (H) ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP BHP

ix) Speed (n) RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 15

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 134: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 16

ii) Length of Discharge Pipe (ft) 100

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 31 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer EMIT

ii) Rated kW / hp 135 hp 101 kW

iii) Voltage Range 400 Volts

iv) Current 196 Amperes

v) Power Factor (Cos ɸ) 0.77

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 595 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class

ix) Motor Frame Size

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 10270.56

iii) Meter Time and Date

Correct FALSE

Page 135: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 600 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues VERY POOR

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring VERY POOR

Housekeeping OK

Motor Terminal OPEN AND LOSE MOTOR CONNECTIONS

Foundation/Civil work VIBRATE

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 16 inches

v) Pipe Perimeter 1,276 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 875 m3/hr 14.583 m3/min

Velocity in Pipe 1.87 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 35 meter

Electric Measurements Volt 397 393.6 395.2

Ampere 104.1 113.6 109.5

kW 41.1 Power Factor 0.59 0.54 0.56

vi) Motor Working on Loading Basis 41 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 595 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 86.5

Page 136: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 31 ft

vi) Frictional Head (Suction and Discahrge) 8.89 ft

Page 137: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 36.89 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 35.89 hp

xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 55.09 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 65.15 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 8,750 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 3,193,750 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 150,819 kWh/yr

xxv) Annual Energy Expenditure on Pumping 1,960,652 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 65.15%. For pump attached with 135 HP motor, efficiency above 63% is considered to be good . This pumping system does not requires any intervention.

Page 138: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 710,000 PKR

No water flow meter Water flowmeter is recommended

No VFD

Over current relays and over/under voltage relay is recommendedOver current relays and over/under voltage relay is not installed

No pressure guage Digital pressure guage is recommended

Install VFD

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

Page 139: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station KHIALI DISPOSAL P # 2

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Mohammad Iqbal

iv) Total Number of Pumps Installed 6

v) Total Number of Pumps in Operation 4

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 6

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 6

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 140: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 02

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 141: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model Serial

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 12 Cusec 1,224 m3/hr

vi) Head (H) ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP BHP

ix) Speed (n) RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 15

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 142: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 16

ii) Length of Discharge Pipe (ft) 100

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 31 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer EMIT

ii) Rated kW / hp 135 hp 101 kW

iii) Voltage Range 410 Volts

iv) Current 172 Amperes

v) Power Factor (Cos ɸ) 0.77

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 590 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class

ix) Motor Frame Size

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 10270.56

iii) Meter Time and Date

Correct FALSE

Page 143: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 600 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues VERY POOR

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring VERY POOR

Housekeeping OK

Motor Terminal OPEN AND LOSE MOTOR CONNECTIONS

Foundation/Civil work VIBRATE

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 16 inches

v) Pipe Perimeter 1,276 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 875 m3/hr 14.583 m3/min

Velocity in Pipe 1.87 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 35 meter

Electric Measurements Volt 389 389.6 391.7

Ampere 146.7 135.1 145.5

kW 71.82 Power Factor 0.76 0.7 0.76

vi) Motor Working on Loading Basis 71 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 590 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 88.7

Page 144: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 31 ft

vi) Frictional Head (Suction and Discahrge) 8.89 ft

Page 145: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 36.89 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 35.89 hp

xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 96.27 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 37.28 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.08 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 8,750 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 3,193,750 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 263,549 kWh/yr

xxv) Annual Energy Expenditure on Pumping 3,426,132 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 63 %

xxvii) Water Flow after Efficiency Improvement 1,479 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3

xxix) Potential of Energy Reduction 40.82 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 107,580 kWh/yr

xxxi) Annual Financial Saving on Pumping 1,398,540 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 37.28%. For pump attached with 135 HP motor, efficiency below 58% is considered to be low . This pumping system requires impeller adjustment ,repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 1,398,540PKR.

Page 146: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 915,000 PKR

Defective Volt meter

Over current relays and over/under voltage relay is recommendedOver current relays and over/under voltage relay is not installed

No pressure guage Digital pressure guage is recommended

Replace faulty Volt meter with correct one

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

No water flow meter Water flowmeter is recommended

No VFD Install VFD

Page 147: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station KHIALI DISPOSAL P # 5

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Mohammad Iqbal

iv) Total Number of Pumps Installed 6

v) Total Number of Pumps in Operation 4

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 6

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 6

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 148: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 05

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 149: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model KVPK K 300-500 D2 Serial 21-09-10-11265

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 10 Cusec 1,020 m3/hr

vi) Head (H) 50 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 78 BHP

ix) Speed (n) 960 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 35

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 150: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 12

ii) Length of Discharge Pipe (ft) 150

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 24 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer KSB

ii) Rated kW / hp 100 hp 75 kW

iii) Voltage Range 400 Volts

iv) Current 133 Amperes

v) Power Factor (Cos ɸ) 0.86

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 985 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size I-L-315-S-6

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 7353.21

iii) Meter Time and Date

Correct FALSE

Page 151: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues GOOD

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring GOOD

Housekeeping OK

Motor Terminal TIGHT AND PROPER MOTOR CONNECTIONS

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 inches

v) Pipe Perimeter 957 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 800 m3/hr 13.333 m3/min

Velocity in Pipe 3.05 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 56 meter

Electric Measurements Volt 391.9 389.8 392.7

Ampere 90.6 88 87.3

kW 48.13 Power Factor 0.81 0.79 0.81

vi) Motor Working on Loading Basis 65 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 989 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 88.9

Page 152: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 24 ft

vi) Frictional Head (Suction and Discahrge) 25.46 ft

Page 153: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 46.46 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 41.32 hp

xiv) Brake Horsepower (bhp) (OEM Data) 78.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 64.52 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 52.98 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.05 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 8,000 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 2,920,000 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 176,616 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,296,014 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 64.05%. For pump attached with 100 HP motor, efficiency above 63% is considered to be good . This pumping system does not require any intervention.

Page 154: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 610,000 PKR

Install VFD No VFD

No pressure guage Digital pressure guage is recommended

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

No water flow meter Water flowmeter is recommended

Page 155: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station KHIALI DISPOSAL P # 6

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Mohammad Iqbal

iv) Total Number of Pumps Installed 6

v) Total Number of Pumps in Operation 4

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 6

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 6

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 10 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 156: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 06

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 157: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model KV PK 350-500 D2 Serial 21-09-10-11264

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 10 Cusec 1,020 m3/hr

vi) Head (H) 50 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 78 BHP

ix) Speed (n) 960 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 35

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 158: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 12

ii) Length of Discharge Pipe (ft) 150

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 24 ft

Suction Side Elevation 5 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer KSB

ii) Rated kW / hp 100 hp 75 kW

iii) Voltage Range 400 Volts

iv) Current 133 Amperes

v) Power Factor (Cos ɸ) 0.86

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 985 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 7353.21

iii) Meter Time and Date

Correct FALSE

Page 159: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues GOOD

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring GOOD

Housekeeping OK

Motor Terminal TIGHT AND PROPER MOTOR CONNECTIONS

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 inches

v) Pipe Perimeter 957 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 650 m3/hr 10.833 m3/min

Velocity in Pipe 2.47 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 56 meter

Electric Measurements Volt 389 392 390.4

Ampere 85 82.8 84.6

kW 44.16 Power Factor 0.79 0.77 0.76

vi) Motor Working on Loading Basis 59 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 980 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 89.9

Page 160: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 5 ft

v) Static Discahrge Head 24 ft

vi) Frictional Head (Suction and Discahrge) 16.88 ft

Page 161: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 35.88 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 25.93 hp

xiv) Brake Horsepower (bhp) (OEM Data) 78.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 59.20 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 33.25 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 43.81 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 10 hrs

xxi) Daily Pump flow 6,500 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 2,372,500 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 162,048 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,106,627 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 63 %

xxvii) Water Flow after Efficiency Improvement 935 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3

xxix) Potential of Energy Reduction 30.46 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 49,360 kWh/yr

xxxi) Annual Financial Saving on Pumping 641,675 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 43.81%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 641,675PKR.

Page 162: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 895,000 PKR

No VFD

Replace faulty Volt meter by correct oneDefective Volt meter

No pressure guage Digital pressure guage is recommended

Install VFD

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

No water flow meter Water flowmeter is recommended

Pump is in efficent It requires impeller adjustment, repair and maintenance

Page 163: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station NOSHERA ROAD DISPOSAL

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Ghulam naseer 0345-6556461

iv) Total Number of Pumps Installed 3

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 3

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 3

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 19 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 164: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 03

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 165: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model KV PK 350/500 d-2 Serial 21-07-10-8012

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 10 Cusec 1,020 m3/hr

vi) Head (H) 48 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 70 BHP

ix) Speed (n) 725 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 30

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 166: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 12

ii) Length of Discharge Pipe (ft) 150

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 10 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer SEMIENS

ii) Rated kW / hp 100 hp 75 kW

iii) Voltage Range 400 Volts

iv) Current 140 Amperes

v) Power Factor (Cos ɸ) 0.84

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 735 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size 315-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading Damaged

iii) Meter Time and Date

Correct FALSE

Page 167: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200,200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues GOOD

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring GOOD

Housekeeping OK

Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 inches

v) Pipe Perimeter 957 mm

vi) Type of Clamping (V/N/Z)

viii) Flow Measurement 730 m3/hr 12.167 m3/min

Velocity in Pipe 2.78 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 55 meter

Electric Measurements Volt 390.3 384.4 388.2

Ampere 99.8 110.4 100.2

kW 50.64 Power Factor 0.76 0.74 0.69

vi) Motor Working on Loading Basis 68 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 741 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 84.8

Page 168: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 10 ft

vi) Frictional Head (Suction and Discahrge) 21.15 ft

Page 169: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 28.15 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 22.85 hp

xiv) Brake Horsepower (bhp) (OEM Data) 69.80 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 67.88 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.74 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 33.66 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 19 hrs

xxi) Daily Pump flow 13,870 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 5,062,550 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 353,071 kWh/yr

xxv) Annual Energy Expenditure on Pumping 4,589,929 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 63 %

xxvii) Water Flow after Efficiency Improvement 1,366 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.04 kWh/m3

xxix) Potential of Energy Reduction 46.56 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 164,406 kWh/yr

xxxi) Annual Financial Saving on Pumping 2,137,275 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 33.6%. For pump attached with 100 HP motor, efficiency below 57.3% is considered to be low. This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 2,137,275 PKR.

Page 170: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 890,000 PKR

No VFD

It requires impeller adjustment, repair and maintenancePump is in efficent

No pressure gauge Digital pressure gauge is recommended

Install VFD

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

No water flow meter Water flowmeter is recommended

Page 171: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station NOSHERA ROAD SANSI DISPOSAL

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact M.Asif Nadeem 0300-6401137

iv) Total Number of Pumps Installed 5

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 5

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 5

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 18 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 172: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source DAMAGED hrs/day

2 Pump Basic Information Pump # 01

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 173: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model SEWATEC K 400-500 GP Serial 9972926290/101

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 20 Cusec 2,040 m3/hr

vi) Head (H) 50 ft

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 108 BHP

ix) Speed (n) 988 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 20

ii) Enter Length of Suction Pipe (ft) 20

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 174: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 20

ii) Length of Discharge Pipe (ft) 450

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 16 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer KSB

ii) Rated kW / hp 180 hp 134 kW

iii) Voltage Range 400 Volts

iv) Current 231.8 Amperes

v) Power Factor (Cos ɸ) 0.87

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 990 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size I-L-315-L-6

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 1977.47

iii) Meter Time and Date

Correct FALSE

Page 175: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200,200,200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues EXCELLENT

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring EXCELLENT

Housekeeping OK

Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 20 inches

v) Pipe Perimeter 1,595 mm

vi) Type of Clamping (V/N/Z)

viii) Flow Measurement 1,950 m3/hr 32.5 m3/min

Velocity in Pipe 2.67 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 143 meter

Electric Measurements Volt 381.4 379.1

Ampere 196.6 205.7

kW 109.5 Power Factor 0.83 0.84

vi) Motor Working on Loading Basis 82 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 990 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 92.8

Page 176: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 16 ft

vi) Frictional Head (Suction and Discahrge) 20.83 ft

Page 177: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 33.83 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 73.35 hp

xiv) Brake Horsepower (bhp) (OEM Data) 108.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 146.78 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 67.91 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.97 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 18 hrs

xxi) Daily Pump flow 35,100 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 12,811,500 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 723,272 kWh/yr

xxv) Annual Energy Expenditure on Pumping 9,402,542 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 64 %

xxvii) Water Flow after Efficiency Improvement 2,498 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.04 kWh/m3

xxix) Potential of Energy Reduction 21.92 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 158,560 kWh/yr

xxxi) Annual Financial Saving on Pumping 2,061,274 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 50%. For pump attached with 180 HP motor, efficiency below 59% is considered to be low . This pumping system requires impeller adjustment and maintenance. After this its efficiency will be improved to 64% (GOOD Efficiency range), with annual savings of 2,061,274 PKR.

Page 178: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 1,190,000 PKR

It requires impeller adjustment, repair and maintenacePump is in efficient

No pressure guage Digital pressure guage is recommended

No power factor improvement (PFI) plant is installed PFI of 100 KVAR is recommended

No water flow meter Water flowmeter is recommended

Page 179: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

1 Pumping Station Information

1 Fresh Water Supply

2 Wastewater Disposal

3 Waste Water Treatment Plant

4 Water Treatment Plant

Name of Engineer

WASA Staff Name

i) Name of Pumping Station SARFRAZ COLONY DISPOSAL

ii) Name of Subdivision ZONE II

iii) Operator Name & Contact Khaleeq-ur-rehman

iv) Total Number of Pumps Installed 4

v) Total Number of Pumps in Operation 1

vi) Year of Starting Operation

vii) Types of Pumps

Standard Deep Well Water Turbine Pumps Qty

Submersible Deep Well Water Turbine Pumps Qty

Centrifugal Pump Qty 4

Submersible Disposal Pump Qty

vi) Operational Scheme of Pumps Qty

Independent 4

Series

Parallel

vii) Any Header / Tank / Reservoir

Yes No

viii) Any Record Keeping

Time Flow Pressure

Level Quality of Water Power Consumption

Maintenance Record Electricity Bill Fuel Consumption Data

viii) Daily Operational Time 12 hrs/day

ix) Annual Working Days 365 days

x) Source of Power

Energy Report of WASA Pumps

Page 180: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Primary GEPCO Secondary

xi) In Case of Secondary Power Source Fuel Data Details

xii) Operational Hours of Secondary Power Source hrs/day

2 Pump Basic Information Pump # 03

ii) Mounting / Erection

Horizontal Vertical Submersible

Foundation

iii) Concrete Bolted Bolted

iv)

v) Cooling Type

Water Cooled Air Cooled

vi) Number of Stages

Single Multi

vii) Pump and Motor Assembly

Direct Coupled Belt / Gear

viii) Source of Suction

Wet Well Overhead Tank Underground Tank

Pressurized Source

ix) Pump Discharge Destination

Overhead Tank Drain On Ground Reservoir

Pit

Pump Operational Scheme

On / OFF Proportional

x) Pump Flow Control

Throttle VFD Controlled

xi) Any Retrofits ?

Impeller Detail

Casing / Volute Detail

Line Shaft (DW) Detail

Column Sett. (DW) Detail

Page 181: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Motor Replacement Detail

Motor Rewinding Detail

xii) Self Priming

Yes No NA (not applicable)

xiii) Non Clogging (In case of wastewater)

Yes No

xiv) Flowmeter Available

Yes No

xv) Flowmeter Working

Working Properly Malfunctioning (Damaged)

3 Pump Nameplate Data

i) Make / Brand KSB Country PAK

ii) Model KVP 300-500 D2 Serial 21-11-10-12268

iii) Certification Mark

iv) Year of Manufacture

v) Flowrate (Q) 10 Cusec 1,020 m3/hr

vi) Head (H) 50

vii) Discharge Pressure (P) Psig

viii) Power / HP / BHP 75 BHP

ix) Speed (n) 960 RPM

x) Maximum Pressure (Pmax)

xi) Maxiumum Allowable Temperature

5 Piping System

Suction Side

Select Pipe Material of Construction MS Pipe

i) Enter Diameter of Suction Pipe (In) 12

ii) Enter Length of Suction Pipe (ft) 10

iii) Enter Fittings on Suction Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Flow control 1

Bends

Strainer 1

viii) Availbility of Pressure Gauge Yes No

ix) Suction Pressure

Page 182: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Discharge Side

Pipe Material of Construction MS Pipe

i) Diameter of Discharge Pipe (in) 12

ii) Length of Discharge Pipe (ft) 30

iii) Fittings on Discharge Pipe

Fitting Type 1 Qty Type 2 Qty Type 3 Qty

Valves Non return 1 1

Bends 1

Strainer

vi) Discharge Elevation (from Datum Line) 17 ft

Suction Side Elevation 3 ft

vii) Availbility of Pressure Gauge Yes No

viii) Discharge Pressure psig

6 Motor Nameplate Data

i) Manufacturer SEMIENS

ii) Rated kW / hp 100 hp 75 kW

iii) Voltage Range 400 Volts

iv) Current 140 Amperes

v) Power Factor (Cos ɸ) 0.84

Standard

Ambient Temp oC

Year of Manufacturing

Efficiency Class

IE3 Eff 1

IE2 Eff 2

IE1 Eff 3

Standard Efficiency

vi) Motor Speed 735 RPM

vii) Reference Frequency 50 Hz

viii) Insulation Class F

ix) Motor Frame Size 315-M

x)

7 Electrical System Observations

i) Electrical Meter Reference Number

ii) Meter Reading 8602.69

iii) Meter Time and Date

Correct FALSE

Page 183: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Lag by Lead by

iv) Transformer Rating (kVA) 200,200 Condition OK

Pump O & M Cost

v) Motor Starting Method

Direct Online Star (Wye) - Delta

Autotransformer Starter Soft Starter

Variable Frequency Drives

v) Electrical Protections Available

Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)

Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)

PFI Plant NOT INSTALLED

Panel Condition/Issues EXCELLENT

Gland Leakage NA

Non Return Valve NA

Flow Meter NA

Pressure Gauge NA

Wiring EXCELLENT

Housekeeping OK

Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX

Foundation/Civil work OK

Field Measurements

8 Flow Measurement

i) Flow Measurement Location

Discharge Pipe Suction Pipe

ii) Pipe Material of Construction MS Pipe

iii) Paint on Pipe Yes No

iv) Pipe Diameter 12 inches

v) Pipe Perimeter 1,020 mm

vi) Type of Clamping (V/N/Z) V

viii) Flow Measurement 774 m3/hr 12.9 m3/min

Velocity in Pipe 2.95 m/sec

Pressure

i) Pressure at Discharge Side of Pump psig

ii) Pressure at Suction Side of Pump

ii) Total Length (Suction+Discahrge Pipe) 12 meter

Electric Measurements Volt 389.3 394.3 392.7

Ampere 97.7 88.7 93.7

kW 48.67 Power Factor 0.74 0.79 0.76

vi) Motor Working on Loading Basis 65 %

Oversize Undersize Properly Sized

Speed

i) Speed of Motor 746 RPM

ii) Speed of Pump Impeller RPM

Noise Level

Noise Level (db(A)) Avg. Max: 85.5

Page 184: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Thermal Imaging

i) Motor Motor Pump Coupling

Pump Volute Casing Pump Bearings

Electric Panels

10 Calculations

ii) Static Suction Head (Only for WW Pump) 3 ft

v) Static Discahrge Head 17 ft

vi) Frictional Head (Suction and Discahrge) 21.08 ft

Page 185: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

viii) Total Dynamic Head of Pump (TDH) 35.08 ft

x) Specific Speed of Pump

Ns = RPM x GPM0.5 / H0.75

impeller rpm necessary to produce 1gpm/ft head 0

500-10,000, standard, 2,000-3,000 high efficiency

xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr

xii) Deviation of actual flow from the pump curve flow %

xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 30.19 hp

xiv) Brake Horsepower (bhp) (OEM Data) 75.00 hp

xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65.24 hp

xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 40.26 %

xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 46.28 %

xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3

xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh

xx) Daily Operational Time of Pump 12 hrs

xxi) Daily Pump flow 9,288 m3/day

xxii) Annual working days 365 days

xxiii) Annual Pump flow 3,390,120 m3/yr

xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 214,318 kWh/yr

xxv) Annual Energy Expenditure on Pumping 2,786,129 PKR/Yr

xxvi) Pumping System Efficiency after Improvement 63 %

xxvii) Water Flow after Efficiency Improvement 1,054 m3/hr

xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3

xxix) Potential of Energy Reduction 26.54 %

xxx) Reduced Annual Energy Consumption at Improved Efficiency 56,888 kWh/yr

xxxi) Annual Financial Saving on Pumping 739,548 PKR/Yr

11 Summary of Findings

Pumping system efficiency is 46.28%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 739,548PKR.

Page 186: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Issues & Recommendations

12 ISSUES RECOMMENDATIONS

i)

ii)

iii)

iv)

v)

vi)

vii)

viii)

ix)

x)

xi)

xii)

xiii)

xiv)

xv)

xvi)

xvii)

xviii)

Financial Analysis / Indicators

Estimated Investment for Improvement Plan 890,000 PKR

No VFD

It requires impeller adjustment repair and maintenancePump is in efficient

No pressure guage Digital pressure guage is recommended

Install VFD

No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended

No water flow meter Water flowmeter is recommended

Page 187: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

ANNEXURE-2

Selected Pictures

Page 188: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Housekeeping at TW 36 No fan cover at TW 27

Poor wiring at TW 34 No PFI at Safraz Colony

Sound measurement at Sheranwala View of discharge pipeline at TW 37

Page 189: pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/Zone-II Final Report.pdfpcgip.urbanunit.gov.pk

Faulty A meter at Abubakar Park Disposal Faulty A & V meter at Kashmir Colony Disposal

Poor wiring at Khiali Disposal Poor wiring at Khiali Disposal