pcgip.urbanunit.gov.pkpcgip.urbanunit.gov.pk/docs/energy/zone-ii final...
TRANSCRIPT
1
Punjab Cities Governance Improvement Project
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
REPORT Zone-II, Gujranwala
February2016
NEC Consultants (Pvt.) Ltd.
2
Energy Audit & Energy Efficiency Improvement Program for WASAs in Punjab
February 2016 NEC Consultants Pvt. Ltd Perfect SITE, 22 KM Ferozepur Road, Near GujjuMatta Metro Bus Station, Lahore +92-42-35273741-46, www.nec.com.pk [email protected] This study was assigned by The Urban Unit, Punjab
3
DISCLAIMER No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying, recording or information storage and retrieval system, without prior written permission of the USPMSU. A publication of the Urban Sector Planning and Management Services Unit (Private) Limited, the opinion expressed in the document are solely those of the authors and publishing them does not in any way constitute an endorsement of the opinion by the USPMSU.
ACKNOWLEDGEMENTS This report has been prepared by The Urban Unit (Urban Sector Policy & Management Unit), P&D Department, Government of Punjab. The Urban Unit, under the Punjab Cities Governance Improvement Project (PCGIP)-DLI-4 is supporting WASAs for implementing Energy Audit Management Opportunities. Energy management opportunities have been extracted from the energy audits of WASA pumps. The Team Dr. NasirJaved Engr. AbidHussainy Engr. Ali Raza ShafqatUllah Muhammad Rizwan KashifShaukat Adnan Khan Editing & Layout By: Ms. MadihaQamar Printed in Pakistan Copyright: Urban Sector Planning and Management Services Unit (Private) Limited.
4
CONTENTS Contents 4 List of Annexure 4 List of Figures 4 List of Tables 4 List of Acronyms and Abbreviations 5 Glossary 5 1.0 Introduction 7
1.1 Background 7 1.2 Methodology 7 1.3 Scope 8
2.0 Energy Audit Findings 9 2.1 Pumping system efficiency 9 2.2 Electricity consumption trend 11 2.3 Pumping system efficiency improvement potential 13 2.4 Interventions for the improvement of WASA stations 13
LIST OF ANNEXURE
I Energy Audit Reports 2 Selected Pictures
LIST OF FIGURES
I Pumping system efficiency category 11 2 Unit electricity consumption trend (tube wells) 12 3 Unit electricity consumption trend (disposal pumps) 12
LIST OF TABLES
1 Detail of WASAs pumps 8 2 Detail of Zone-II 9 3 Typical overall pumping system efficiency classification 10 4 Detail of motor loading and pumping system efficiency 10 5 Detail of water discharge and electricity consumption 11 6 System energy efficiency potential of pumps 13
7A Interventions & investment required in WASA stations-Zone-II 14 7B Interventions & investment required in WASA stations- Zone-II 16
5
LIST OF ACRONYMS AND ABBREVIATIONS
Bhp Brake Horsepower Cusec Cubic Feet per Second Ehp Electrical Horsepower Gpm Gallon Per Minute Hp Horsepower kVA Kilo Volt Ampere kW Kilo Watt kWh Kilo Watt Hour LESCO Lahore Electric Supply Company m/s Meter Per Second m3/hr Cubic Meter Per Hour MCB Fuses or Miniature Circuit Breaker Mm Millimeter MS Mild Steel Psig Pound Per Square Inch (Gauge) RPM Revolution Per Minute TDH Total Dynamic Head VFD Variable Frequency Drive WASA Water and Sanitation Agency Whp Water Horsepower
GLOSSARY
Discharge Pressure
The pressure obtained at center line of pump discharge pipe using a calibrated gauge (psig). Discharge pressure is converted to feet and expressed as “Discharge Head”.
Brake Horsepower
The output horsepower of a motor to a pump; may also be used to refer to the required input horsepower to the pump itself.
Deep Well Turbine Pump
A turbine pump installed inside a well casing below the pumping water level in the well.
Discharge Head Head measured above center line of pump discharge pipe.
Drawdown The measured distance that a well’s water level changes from standing/static level to operating pumping level during observed test conditions.
Dynamic Head The sum of the pressure and the pumping head developed by a pump
Friction Head The head required to overcome the fluid friction in a pipe or water system
Friction Losses
Energy losses associated with moving water against rough surfaces. In water pumping applications, it is the water pressure lost as a result of contact between moving water and a pipeline or open channel.
GPM per Foot Drawdown
The ratio of capacity (GPM) to drawdown feet is useful in determining the well’s performance.
Head Alternate term for pressure. One pound per square inch (psi) = 2.31 feet of water head
Overall Plant The ratio of the water horsepower (the overall output of the plant)
6
or Pumping System Efficiency
to input horsepower (the power input). The overall output can also be defined as the amount of horsepower required to deliver the measured capacity (water gallons per minute) and the measured total head.
Pumping Water Level
The well’s operating water level below center line of discharge pipe as observed during test condition
Static Water Level The well’s water level obtained when pumping plant is at rest.
Suction Head Head measured above center line of pump suction intake. Most often obtained with calibrated bourdon tube pressure gauge (suction pressure) and converted to feet by conversion factor 2.31 ft. water/psi
Suction Lift The distance between pump discharge head and water level.
Total Head
The sum of the water head above and below the center line of the pump discharge pipe. For well applications, the Total Head is the sum of the Discharge Head and the Pumping Water Level. Total head is used in determination of water horsepower and pump performance.
Water Horsepower
The output horsepower of a water pump. It is the combination of flow rate and pressure.
7
1.0 Introduction 1.1 Background Energy Audit & Energy Efficiency Improvement gram Government of the Punjab, Pakistan with financial assistance from the World Bank, is implementing “Punjab Cities Governance Improvement Project (PCGIP)” for strengthening systems for improved planning, resource management, and accountability in five large cities of Punjab i.e. Lahore, Faisalabad, Multan, Gujranwala and Rawalpindi. The project utilizes a result-based approach and, consistent with this focus, the disbursement decisions to the city and its entities are based on achievement of pre-specified results, referred to as Disbursement linked Indicators (DLIs) which reflect priority elements in furthering the Government’s urban agenda, critical at the provincial level, within the existing legislative, regulative and policy framework of the Government. DLIs includes intermediate outcomes, incremental steps and results contributing to improved efficiency, effectiveness, accountability and service delivery during and beyond the project life by building capacities , system and processes . Disbursement Linked Indicator 4 (DLI -4) aims for improvements in own source revenue collection system that encourages the City Local Government (CDGs), Development Authorities (DAs) and Service providers (WASAs) to bring improved systems for revenue enhancement. This DLI is linked with the initiative of WASAs to carry out the Energy Audit for resources conservation and efficiency to improved service delivery, accountability and own source revenue. One of the proposed actions & initiatives to enhance revenue was to conduct energy audit of WASAs to reduce the power cost by various systematic analysis of the energy use and finding out the energy management opportunities. WASAs each year incur significant cost. It was Rs. 4,697 million in 2014 year for energy/Electricity bills, with an installed capacity of approximately 131 MW for 5,663 Million Gallons per Day (water management), which can be reduced through detailed energy audit and implementing its findings. In the context of existing scenario energy audit of WASAs is a technical and efficient way to obtain energy analysis and savings through improvements that optimize pumping systems of tube well stations and disposal stations to operate efficiently with significant cost saving. The Urban Planning and Management Services Unit, Pvt. Ltd. has assigned NEC Consultants Pvt. Ltd to conduct energy audits of WASAs in Punjab in five major cities of Lahore, Rawalpindi, Faisalabad, Multan and Gujranwala. This is the energy audit report of Zone-II of Gujranwala city. 1.2 Methodology The primary and secondary sources were used to collect data for different WASAs and pumps installed there. The Urban Unit provided information and contact detail of all the WASAs. An energy audit report template was developed to collect field data from each WASA subdivision. Prior to start the on field measurements of each subdivision, meetings were conducted with the respective WASA management and briefed them about the activity. The technical team then collected data by on field measurements of each pump and recorded in their energy audit report template. On the basis of this energy audit report template, The Urban Unit also developed Android based software to record data of each pump online. This data was also recorded on line in this Android based application.
8
On the basis of field measurements, efficiency of the pumping system was calculated and energy efficiency opportunities were identified. 1.3 Scope The scope of the this assignment is to conduct energy audits of about 1,600 fresh water supply and wastewater disposal pumps installed at different WASA stations in five major cities of Lahore, Rawalpindi, Multan, Faisalabad and Gujranwala. The detail of these pumps is given in Table-1.
Table-1: Detail of WASAs Pumps
WASA Population
Served (Million)
Total Water Connections
Total Sewerage
Connections
Total Supply
Stations
Total Disposal Stations
Total No. of Pump
Sets WASA Lahore 5.48 587,595 583,532 491 99 776
WASA Gujranwala 0.54 29,375 97,236 66 23 112
WASA Faisalabad 1.55 110,452 217,002 87 43 222
WASA Multan 1.2 43,996 175,615 102 21 161
WASA Rawalpindi 1.17 92,468 38,437 362 - 362
Total 9.94 863,886 1,111,822 1,108 186 1,633 The efficiency of each pumping system was evaluated and energy efficiency improvement opportunities were identified for those pumping systems whose efficiencies were not at required level. The detail of reports prepared is as under:
- The energy audit report of each pump was prepared. - On the basis of each pump report, summary report of findings of each WASA
subdivision/zonewas prepared. - On the basis of each subdivision/zone summary report, one consolidated report of
each city for energy efficiency improvement opportunities of the WASAs was prepared.
9
2.0 Energy Audit Findings There are 12 WASA water supply stations and 09 wastewater disposal pumps in Zone-II of Gujranwala city. The detail of these stations along with pumps installed capacity and actual discharge is given in Table-2:
Table-2: Detail of Zone-II
# WASA Station
No. of Water Supply Pumps
Installed
Installed Capacity (Cusec)
Actual Discharge (Cusec)
1 Bahtha Colony TW-36 01 4.0 4.52 2 DawoodWalaKhooKhiali TW-27 01 2.0 3.50 3 Jinnah Park KangniWala TW-34 01 2.0 1.47 4 Main Bazar Sarfraz Colony TW-31 01 2.0 1.87 5 Nowshera Road Tanki TW-39 01 4.0 4.41 6 Nowshera Road Disposal TW-35 01 2.0 2.32 7 Sheikhupura More TW-44 01 2.0 2.52 8 SheranwalaBagh New TW-48 01 2.0 2.54 9 SheranwalaBaghLady Park TW-47 01 2.0 2.33 10 Sialvi Town Jinnah Road TW-37 01 4.0 4.49 11 TankiKhiali Shah Pur TW-32 01 2.0 2.40 12 Tower Road Khiali New TW-30 01 2.0 2.35 Total 12 30.00 34.72 Wastewater Disposal Pumps
13 Abu Bakar Park Disposal 01 10.0 7.35 14 Kashmir Colony Disposal 01 5.0 4.90 15 Khiali Disposal P-01 01 15.0 8.57 16 Khiali Disposal P-02 01 12.0 8.57 17 Khiali Disposal P-05 01 10.0 7.84 18 Khiali Disposal P-06 01 10.0 6.37 19 Noshehra Road Disposal 01 10.0 7.15 20 Noshehra Road Sansi Disposal 01 20.0 19.11 21 Sarfraz Colony Disposal 01 10.0 7.59 Total 09 102.00 77.45
The installed capacity of WASA tube wells of Zone-II is 11.17 million m3 per annum whereas actual discharge is12.93 million m3 per annum, for average 10 hours per day operation and 365 days per year. This actual discharge is about 14% greater than the installed capacity. The installed capacity of WASA disposal pumps of Zone-II is 37.97 million m3 per annum whereas actual discharge is 28.83 million m3 per annum, for average 10 hours per day operation and 365 days per year. This actual discharge is about 24% lesser than the installed capacity. 2.1 Pumping System Efficiency Pumping plant performance can be classified as “Low”, “Fair”, “Good”, or “Excellent” by referring to the following table, which is based upon the results of thousands of pump tests conducted by Pacific Gas & Electric Company, USA. This classification is used to categorize WASA pumps.
10
Table-3: Typical Overall Pumping System Efficiency Classification
Motor HP Low Fair Good Excellent 3-7.5 <44.0 44-49.9 50-54.9 >54.9
10 <46.0 46-52.9 53-57.9 >57.9 15 <47.1 48-53.9 54-59.9 >59.9
20-25 <48.0 50-56.9 57-60.9 >60.9 30-50 <52.1 52.1-58.9 59-61.9 >61.9 60-75 <56.0 56-60.9 61-65.9 >65.9 100 <57.3 57.3-62.9 63-66.9 >66.9 150 <58.1 58.1-63.4 63.5-68.9 >68.9 200 <59.1 59.1-63.8 63.9-69.4 >69.4 250 <59.1 59.1-63.8 63.9-69.4 >69.4 300 <60 60-64.0 64.1-69.9 >69.9
Source: Pacific Gas &Electric Company, USA The detail of pumping system efficiency and motor loading of each WASA station is given in Table-4. The calculations for the efficiency determination are given in the energy audit report of each pump in Annexure-1.
Table-4: Detail of Motor Loading and Pumping System Efficiency
WASA Station Motor Load
(%) Pumping System
Efficiency (%) Pumping System Efficiency Rating
Nowshera Road Tanki TW-39 94 72 EXCELLENT Sheikhupura More TW-44 90 80 EXCELLENT SheranwalaBagh New TW-48 89 76 EXCELLENT Bahtha Colony TW-36 81 65 GOOD DawoodWalaKhooKhiali TW-27 96 64 GOOD SheranwalaBagh Lady Park TW-47
86 64 GOOD
Sialvi Town Jinnah Road TW-37 84 67 GOOD TankiKhiali Shah Pur TW-32 90 58 FAIR Nowshera Road Disposal TW-35 102 59 FAIR Main Bazar Sarfraz Colony TW-31 99 41 LOW Jinnah Park KangniWala TW-34 56 50 LOW Tower Road Khiali New TW-30 91 54 LOW Disposal Pumps Kashmir Colony Disposal 92 64 EXCELLENT Khiali Disposal P-05 65 64 GOOD Khiali Disposal P-01 41 65 GOOD Abu Bakar Park Disposal 65 50 LOW Khiali Disposal P-02 71 37 LOW Khiali Disposal P-06 59 44 LOW Noshehra Road Disposal 68 34 LOW Noshehra Road Sansi Disposal 82 50 LOW Sarfraz Colony Disposal 65 46 LOW About 58% of the tube wells are under excellent and good category of pumping system efficiency whereas 42% are under fair and low category as illustrated in Fig-1.
11
Figure-1: Pumping System Efficiency Category
About 33% of the operational disposal pumps are under excellent and good category whereas 67% are under low category of pumping system efficiency. 2.2 Electricity Consumption Trend The detail of annual water discharge and correspondingly electricity consumption and unit electricity consumption of each WASA station is given in Table-5.
Table-5: Detail of Water Discharge and Electricity Consumption
# WASA Station Annual Water
Discharge (m3)
Annual Electricity Consumption
(kWh)
Unit Electricity Consumption
(kWh/m3) 1 Bahtha Colony TW-36 1,514,385 251,824 0.17 2 DawoodWalaKhooKhiali TW-27 521,220 63,117 0.12 3 Jinnah Park KangniWala TW-34 547,500 77,061 0.14 4 Main Bazar Sarfraz Colony TW-31 976,010 227,758 0.23 5 Nowshera Road Tanki TW-39 1,642,500 324,145 0.20 6 Nowshera Road Disposal TW-35 605,535 118,160 0.20 7 Sheikhupura More TW-44 1,125,660 179,075 0.16 8 SheranwalaBagh New TW-48 1,138,800 176,139 0.15
9 SheranwalaBagh Lady Park TW-47 1,042,440 170,268 0.16
10 Sialvi Town Jinnah Road TW-37 1,504,530 258,925 0.17 11 TankiKhiali Shah Pur TW-32 894,250 149,229 0.17 12 Tower Road Khiali New TW-30 700,800 120,362 0.17 Total 12,213,630 2,116,063 0.17 Disposal Pumps
13 Abu Bakar Park Disposal 3,285,300 214,318 0.07 14 Kashmir Colony Disposal 1,460,000 80,232 0.05 15 Khiali Disposal P-01 3,193,750 150,819 0.05 16 Khiali Disposal P-02 3,193,750 263,549 0.08 17 Khiali Disposal P-05 2,920,000 176,616 0.06
Excellent25%
Good33%
Fair17%
Low25%
12
18 Khiali Disposal P-06 2,372,500 162,048 0.07 19 Noshehra Road Disposal 5,062,550 353,071 0.07 20 Noshehra Road Sansi Disposal 12,811,500 723,272 0.06 21 Sarfraz Colony Disposal 3,390,120 214,318 0.06 Total 37,689,470 2,338,243 0.06 Total annual energy cost of Zone-II is about Rs. 58 million. The unit electricity consumption trend for each WASA station is illustrated in Fig-2.
Figure-2: Unit Electricity Consumption Trend (Tube Wells)
The unit electricity consumption trend for each disposal pump is illustrated in Fig-3.
Figure-3: Unit Electricity Consumption Trend (Disposal Pumps)
0
0.05
0.1
0.15
0.2
0.25
1 2 3 4 5 6 7 8 9 10 11 12
kWh/m3
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
1 2 3 4 5 6 7 8 9
kWh/m3
13
2.3 Pumping System Efficiency Improvement Potential The 05 tube wells and 06 disposal pumps having system efficiency in the category of FAIR to LOW, as given in Table-4,have the potential of efficiency improvement into the GOOD category. Table-6 gives detail of this efficiency improvement potential.
Table-6: System Energy Efficiency Potential of Pumps
WASA Station
Existing Pumping Efficiency
(%)
Improved Pumping Efficiency
(%)
Annual
(kWh)
Saving
(Rs)
Imp.Adj
Rep
& Main
Intervention
Motor Repl.
Pump Repl.
Jinnah Park KangniWala TW-34
50 59 11,852 154,078 x x
Main Bazar Sarfraz Colony TW-31
41 61 73,886 960,520 x
Nowshera Road Disposal TW-35 59 61 3,709 48,215 x TankiKhiali Shah Pur TW-32 58 61 6,430 83,596 x Tower Road Khiali New TW-30
54 61 12,973 168,653 x
Abu Bakar Park Disposal 50 63 45,021 585,279 x Khiali Disposal P-02 37 63 107,580 1,398,540 x x Khiali Disposal P-06 44 63 49,360 641,675 x x Noshehra Road Disposal 34 63 164,406 2,137,275 x x Noshehra Road Sansi Disposal 50 64 158,560 2,061,274 x x Sarfraz Colony Disposal 46 63 56,888 739,548 x x Total 690,665 8,978,653
2.4 Interventions for the Improvement of WASA Stations Energy audit activity of Zone-II revealed that there are certain areas of electrical, mechanical and housekeeping which needs improvement. Table-7 presents detail of interventions and investment requirement in each WASA station for better, efficient and safe operation of WASA station. About Rs. 15.64 million are required to improve WASA stations of Zone-II of Gujranwala city.
14
Table-7A: Interventions & Investment Required in WASA Stations- ZONE II
Intervention WASA Stations
Bahtha Colony TW-36
Dawood Wala Khoo
Khiali TW-27
Jinnah Park
Kangni Wala
TW-34
Main Bazar
Sarfraz Colony TW-31
Nowshera Road
Tanki TW-39
Nowshera
Road Disposal TW-
35
Sheikhupura More TW-44
Sheranwala Bagh
New TW-48
Sheranwala Bagh
Lady Park
TW-47
Sialvi Town Jinnah Road
TW-37
Tanki Khiali
Shah Pur TW-32
Tower Road Khiali New
TW-30
Abu Bakar Park
Disposal
Kashmir
Colony Dispos
al
Khiali Disposal
P-01
Electrical Install VFD × × × × × × × × × × × × × × × Install hour meter × × × × × × × × × × × × × × × Replace ampere meter × Replace volt meter × Replace over current relays Replace over voltage relay Install/maintain PFI plant × × × × × × × × × × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay × Install/replace motor terminal box /Improve open and loose motor connection
Improve panel condition Improve wiring condition Replace de-rated capacitors Relocate panel away from bore hole Replace electrical motor × × × Install fan in the panel × × × × × × × × × × × × × × × Replace PFI HRC fuses Replace PFI display meter × × × × × × × × × × × × × × × Correct date & time of electrical meter
Replace/correct electrical meter Replace change over Replace main circuit breaker
15
Intervention WASA Stations
Bahtha Colony TW-36
Dawood Wala Khoo
Khiali TW-27
Jinnah Park
Kangni Wala
TW-34
Main Bazar
Sarfraz Colony TW-31
Nowshera Road
Tanki TW-39
Nowshera
Road Disposal TW-
35
Sheikhupura More TW-44
Sheranwala Bagh
New TW-48
Sheranwala Bagh
Lady Park
TW-47
Sialvi Town Jinnah Road
TW-37
Tanki Khiali
Shah Pur TW-32
Tower Road Khiali New
TW-30
Abu Bakar Park
Disposal
Kashmir
Colony Dispos
al
Khiali Disposal
P-01
Mechanical Replace damaged/install new flow meter × × × × × × × × × × × × × × × Replace damaged/install new digital pressure gauge × × × × × × × × × × × × × × × Control gland leakage Make operational/install new chlorinator × × × × × × × × × × × × Maintain ratchet plate Adjust impeller × × × Repair & maintenance of pump × Replace existing pumping system Maintain/install new non return valve
Housekeeping Improve general housekeeping × × × × × × × × × × × × × × × Install shades on motor & pump Rain protection of motor & pump Fix panel properly Proper support of discharge pipeline Maintain monthly record of fuel consumption × × × × × × × × × × × × × × ×
Station Wise Investment (M. Rs) 0.73 0.53 0.57 1.14 0.72 1.22 0.54 0.54 0.55 0.72 0.63 0.60 0.61 0.43 0.71
Annual Saving (M. Rs) 0.00 0.00 0.15 0.96 0.00 0.05 0.00 0.00 0.00 0.00 0.08 0.17 0.59 0.00 0.00 Payback (Year) 0.00 0.00 3.72 1.19 0.00 25.3 0.00 0.00 0.00 0.00 7.57 3.55 1.04 0.00 0.00
16
Table-7B: Interventions & Investment Required in WASA Stations-ZONE II
Intervention WASA Stations
Khiali Disposal P-
02
Khiali Disposal
P-05
Khiali Disposal
P-06
Noshehra Road
Disposal
Noshehra Road Sansi
Disposal
Sarfraz Colony
Disposal
Electrical Install VFD × × × × × × Install hour meter × × × × × × Replace ampere meter Replace volt meter × × Replace over current relays × Replace over voltage relay × Install/maintain PFI plant × × × × × × Install/connect capacitors at PFI plant
Install PFI control/relay Install/replace motor terminal box
Improve panel condition Improve wiring condition Relocate panel away from bore hole
Replace electrical motor Install fan in the panel × × × × × × Replace PFI HRC fuses Replace PFI display meter × × × × × × Correct date & time of electrical meter
Replace/correct electrical meter
Replace change over Replace main circuit breaker
17
Intervention WASA Stations
Khiali Disposal P-
02
Khiali Disposal
P-05
Khiali Disposal
P-06
Noshehra Road
Disposal
Noshehra Road Sansi
Disposal
Sarfraz Colony
Disposal
Mechanical Replace damaged/install new flow meter × × × × × ×
Replace damaged/install new digital pressure gauge × × × × × ×
Control gland leakage Maintain ratchet plate Adjust impeller × × × × × Repair & maintenance of pump × × × × ×
Replace existing pumping system
Maintain/install new non return valve
Housekeeping Improve general housekeeping × × × × × ×
Install shades on motor & pump
Fix panel properly Proper support of discharge pipeline
Maintain monthly record of fuel consumption × × × × × ×
Station Wise Investment (M. Rs) 0.92 0.61 0.90 0.89 1.19 0.89
Annual Saving (M. Rs) 1.40 0.00 0.64 2.14 2.06 0.74 Payback (Year) 0.65 0.00 1.39 0.42 0.58 1.20 Total Investment of Subdivision (M.Rs) = 15.64
18
ANNEXURE-1
Energy Audit Reports
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name Muhammad Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact EHSAN ULLAH
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 9 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
BAHTHA COLONY NOWSHEHRA SANSI (Tube well No.36)
0300-7478141
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 14 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec m3/hr
vi) Head (H)180
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 100.98
BHP
ix) Speed (n)1400
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-07-10-8204
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by
viii) Discharge Pressure 33 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 125 hp 93.75 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 174.2
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 280-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 4585
iii) Meter Time and Date
Correct FALSE Not Visible
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues FAIR
Gland Leakage Minor
Non Return Valve OK
Chlorinator Not installed
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 (on which flowmeter is clamped)
v) Pipe Perimeter 1010 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 461 m3/hr
Velocity in Pipe 1.75 m/sec
Pressure
i) Pressure at Discharge Side of Pump 33 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 11 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 371.7 371 374
ii) Ampere 163.5 167.3 162.5
iii) Power Factor 0.75 0.74 0.73
iv) Appearant Power (kVA) 107.9 109.3 111.3
v) Running Power (kW) 75.85 77.5 75.4 76.3
vi) Reactive Power (kVAr) 69.5 70.4 73.3
vi) Motor Working on Loading Basis 81
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,502 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 76.23 ft
vi) Discharge Side Frictional Head 6.67 ft
vii) Dynamic Discharge Head (v+vi) 82.90 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 128.82 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 206.28
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 66.03 hp
xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 102.21 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 65.39 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.60 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 9 hrs
xxi) Daily Pump flow 4,149 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,514,385 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 251,824 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,273,716 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 64.6%. For 125 HP motor efficiency range 63.5-68.9% is considered to be GOOD efficiency range. This pumping system is efficient and needs no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 733,000 PKR
New 50 KVAr PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
No Water meter New water meter is recommeneded
No pressure gauge New Pressure gauge is recommeneded
Faulty Chlorinator New Chlorinator is recommeneded
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name M ASLAM
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact ABDUL ISALAM
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2010
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 4 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
DAWOOD WALA KHOO KHIALI (Tube well No.27)
0340-3847546
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand FLOW PAK Country PAK
ii) ModelB 12 FMC/4S
Serial
iii) Certification Mark
iv) Year of Manufacture2010
v) Flowrate (Q) 2
Cusec m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 60
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
11-0705
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by
viii) Discharge Pressure 18 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85
v) Power Factor (Cos ɸ) 0.87
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,470 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 5107.9
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues GOOD
Gland Leakage Nil
Non Return Valve OK
Chlorinator Not installed
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel No
Wiring GOOD
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 835 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 357 m3/hr
Velocity in Pipe 1.96 m/sec
Pressure
i) Pressure at Discharge Side of Pump 18 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 10 meter
ii) Pumping Water Level 13 meter
Electric Measurements
i) Voltage 418 424 412
ii) Ampere 73 61 69
iii) Power Factor 0.9 0.89 0.82
iv) Appearant Power (kVA) 53 45 49
v) Running Power (kW) 48 40 41 43.0
vi) Reactive Power (kVAr) 23 20 28
vi) Motor Working on Loading Basis 96
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,485 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.7
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 41.58 ft
vi) Discharge Side Frictional Head 8.35 ft
vii) Dynamic Discharge Head (v+vi) 49.93 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 92.57 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 159.74
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.74 hp
xiv) Brake Horsepower (bhp) (OEM Data) 60 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 57.64 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 61.24 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 63.75 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.12 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 4 hrs
xxi) Daily Pump flow 1,428 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 521,220 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 63,117 kWh/yr
xxv) Annual Energy Expenditure on Pumping 820,516 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 64%. For 60 HP motor efficiency 61-65.9% is considered to be GOOD.This pumping system is efficent. No need of any intervention regarding pumping system efficiency.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 528,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
No Flow meter New flow meter is recommended
New 25 Kvar PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name Muhammad Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact NAEEM BUTT
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 1999
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
JINNAH PARK KANGNI WALA (Tube Well No.34)
NA
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 14 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture1999
v) Flowrate (Q) 2
Cusec
vi) Head (H)150
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 42.65
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
15-6655
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 13 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 50 hp 37.5 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 70
v) Power Factor (Cos ɸ) 0.87
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,470 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-S
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 478018
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 50 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Poor
Gland Leakage Average
Non Return Valve OK
Chlorinator NO
Flow Meter OK
Pressure Gauge Faulty
Bore Hole in Front of Panel YES
Wiring POOR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 (on which flowmeter is clamped)
v) Pipe Perimeter 670 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 150 m3/hr
Velocity in Pipe 1.28 m/sec
Pressure
i) Pressure at Discharge Side of Pump 15 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 11 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 395 397 398
ii) Ampere 36 30 35
iii) Power Factor 0.96 0.97 0.96
iv) Appearant Power (kVA) 22 21 22
v) Running Power (kW) 21 21 21 21.0
vi) Reactive Power (kVAr) 6 5 6
vi) Motor Working on Loading Basis 56
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,473 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 93.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 34.65 ft
vi) Discharge Side Frictional Head 3.70 ft
vii) Dynamic Discharge Head (v+vi) 38.35 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 84.27 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 67.12
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 14.05 hp
xiv) Brake Horsepower (bhp) (OEM Data) 42.65 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 28.15 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.95 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.93 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.14 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 1,500 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 547,500 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 77,061 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,001,793 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 59 %
xxvii) Water Flow after Efficiency Improvement 177 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.12 kWh/m3
xxix) Potential of Energy Reduction 15.38 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 11,852 kWh/yr
xxxi) Annual Financial Saving on Pumping 154,078 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 50%. For 50 HP motor efficiency <52.1% is considered to be LOW and 59-61.9% is GOOD efficiency range.This pumping system is inefficent. This pumping system requires impeller adjustment, repair and maintinance of pump to increase its
efficiency up to 59% which is GOOD efficiency. This intervention will save 154,078 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 573,000 PKR
Install VFDNo VFD
Faulty pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
No PFI Plant New 25 KVAr PFI Plant is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name M IQBAL
i) Name of Pumping Station
ii) Name of Subdivision ZONE-2
iii) Operator Name & Contact M TARIQ
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2001
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 14 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
MAIN BAZAR SARFRAZ COLONY (Tube Well No.31)
0322-5611782
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes (Non-operational) No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 14 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2001
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 45.9
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-8435
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 29 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 21234
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not Installed
Panel Condition/Issues GOOD
Gland Leakage Average
Non Return Valve OK
Chlorinator FAULTY
Flow Meter FAULTY
Pressure Gauge NO
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 840 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 191 m3/hr
Velocity in Pipe 1.05 m/sec
Pressure
i) Pressure at Discharge Side of Pump 29 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 11 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 405 405 405
ii) Ampere 83 87 85
iii) Power Factor 0.78 0.72 0.76
iv) Appearant Power (kVA) 58 59 56
v) Running Power (kW) 46 43 44 44.3
vi) Reactive Power (kVAr) 36 40 38
vi) Motor Working on Loading Basis 99
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,478 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.7
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 66.99 ft
vi) Discharge Side Frictional Head 2.41 ft
vii) Dynamic Discharge Head (v+vi) 69.40 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 115.32 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 85.46
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 24.49 hp
xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 59.43 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 53.36 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 41.21 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.23 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 14 hrs
xxi) Daily Pump flow 2,674 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 976,010 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 227,758 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,960,855 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 283 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.16 kWh/m3
xxix) Potential of Energy Reduction 32.44 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 73,886 kWh/yr
xxxi) Annual Financial Saving on Pumping 960,520 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 41.2%. For 60 HP motor efficiency <56% is considered to be LOW and 61-65.9% is GOOD efficiency range.This pumping system is inefficent. This pumping system requires motor to be replaced to increase the efficiency up to 61% which is GOOD efficiency. This
intervention will save 960,520 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 1,143,000 PKR
No pressure gauge New Pressure gauge is recommeneded
Faulty Chlorinator New Chlorinator is recommeneded
Faulty Water meter New water meter is recommeneded
New 25 Kvar PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name Muhammad Asalam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-2
iii) Operator Name & Contact M ABBAS
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 1999
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
NOSHERA ROAD TANKI (Tube Well No.39)
0321-6451764
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec m3/hr
vi) Head (H)180
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 100.98
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-844
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 12 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 50 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 125 hp 93.75 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 174.2
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 280-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 11050
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues GOOD
Gland Leakage Minor
Non Return Valve OK
Chlorinator FAULTY
Flow Meter Not installed
Pressure Gauge OK
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 (on which flowmeter is clamped)
v) Pipe Perimeter 1000 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 450 m3/hr
Velocity in Pipe 1.71 m/sec
Pressure
i) Pressure at Discharge Side of Pump 50 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 12 meter
ii) Pumping Water Level 15 meter
Electric Measurements
i) Voltage 373 379 375
ii) Ampere 159 155 158
iii) Power Factor 0.85 0.81 0.83
iv) Appearant Power (kVA) 111 111 111
v) Running Power (kW) 89 87 89 88.3
vi) Reactive Power (kVAr) 52 57 55
vi) Motor Working on Loading Basis 94
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,488 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 115.5 ft
vi) Discharge Side Frictional Head 6.38 ft
vii) Dynamic Discharge Head (v+vi) 121.88 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 171.08 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 201.36
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 85.60 hp
xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 118.41 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 84.77 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 72.29 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 4,500 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,642,500 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 324,145 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,213,891 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 72.29%. For 125 HP motor efficiency >68.9 is considered to be Excellent efficiency .This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 718,000 PKR
Install VFDNo VFD
No Water meter New water meter is recommeneded
Faulty Chlorinator New Chlorinator is recommeneded
No PFI Plant New 50 Kvar PFI Plant is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name M Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact TASEER HUSSAIN
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 7 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
NOWSHERA ROAD DISPOSAL T/W (Tube Well No.35)
0313-7516886
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)180
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 53.44
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-07-10-8205
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 8 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 36 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 7018
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues FAIR
Gland Leakage Minor
Non Return Valve OK
Chlorinator NO
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 (on which flowmeter is clamped)
v) Pipe Perimeter 670 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 237 m3/hr
Velocity in Pipe 2.03 m/sec
Pressure
i) Pressure at Discharge Side of Pump 36 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
200 (Combined for Tube Well & Disposal)
iii) Water Shutoff Head
Levels
i) Static Water Level 11 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 396 403 400
ii) Ampere 87 82 86
iii) Power Factor 0.77 0.78 0.77
iv) Appearant Power (kVA) 60 57 59
v) Running Power (kW) 46 45 47 46.0
vi) Reactive Power (kVAr) 38 35 39
vi) Motor Working on Loading Basis 102
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,475 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 83.16 ft
vi) Discharge Side Frictional Head 9.18 ft
vii) Dynamic Discharge Head (v+vi) 92.34 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 138.26 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 106.05
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 36.43 hp
xiv) Brake Horsepower (bhp) (OEM Data) 53.44 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 61.66 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 68.18 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 59.09 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.20 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 7 hrs
xxi) Daily Pump flow 1,659 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 605,535 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 118,160 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,536,082 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 245 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.19 kWh/m3
xxix) Potential of Energy Reduction 3.14 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 3,709 kWh/yr
xxxi) Annual Financial Saving on Pumping 48,215 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 59.01% but motor is running in overload condition (102%). For 60 HP motor efficiency range 56-60.9% is considered to be Fair and 61-65.9 % is GOOD.This pumping system is inefficent. This pumping system requires motor to be replaced to increase its efficiency up to 61% which is GOOD efficiency. This intervention will save 48,215 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 1,223,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
No Water meter New water meter is recommeneded
New 25 KVAr PFI Plant is recommendedNo PFI Plant
Replace motorMotor is in efficient
Install VFDNo VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name M ASLAM
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact M SHAMSHAD
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
SHEKHUPURA MORE (Tube Well No.44)
0321-5664525
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 45.9
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-8436
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 40 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 23050
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues GOOD
Gland Leakage Minor
Non Return Valve OK
Chlorinator NO
Flow Meter Faulty
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping FAIR
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 875 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 257 m3/hr
Velocity in Pipe 1.41 m/sec
Pressure
i) Pressure at Discharge Side of Pump 40 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 13 meter
ii) Pumping Water Level 17 meter
Electric Measurements
i) Voltage 388 386 388
ii) Ampere 76 81 77
iii) Power Factor 0.78 0.77 0.75
iv) Appearant Power (kVA) 51 54 52
v) Running Power (kW) 41 42 39 40.7
vi) Reactive Power (kVAr) 32 34 34
vi) Motor Working on Loading Basis 90
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,489 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 87.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 92.4 ft
vi) Discharge Side Frictional Head 4.42 ft
vii) Dynamic Discharge Head (v+vi) 96.82 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 152.58 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 86.25
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 43.60 hp
xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.51 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 94.99 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 79.98 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.16 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 3,084 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,125,660 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 179,075 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,327,976 PKR/Yr
11 Summary of Findings
The Efficiency of this pumping system is Excellent. . This pumping system requires no intervention regarding pumping system efficiency.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 543,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
Faulty Flow meter New flow meter is recommended
New 25 Kvar PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name Muhammad Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact KHAWAR NADEEM
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
SHERAWALA BAGH (WRESTLING) NEW (Tube Well No.48)
0300-7428684
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 45.9
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-8438
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 35 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 22499
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues GOOD
Gland Leakage Average
Non Return Valve OK
Chlorinator Not installed
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring GOOD
Housekeeping FAIR
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 860 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 260 m3/hr
Velocity in Pipe 1.43 m/sec
Pressure
i) Pressure at Discharge Side of Pump 35 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 13 meter
ii) Pumping Water Level 17 meter
Electric Measurements
i) Voltage 381 382 384
ii) Ampere 77 73 81
iii) Power Factor 0.75 0.8 0.79
iv) Appearant Power (kVA) 51 48 54
v) Running Power (kW) 38 39 43 40.0
vi) Reactive Power (kVAr) 34 29 33
vi) Motor Working on Loading Basis 89
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,484 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 91.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 80.85 ft
vi) Discharge Side Frictional Head 4.52 ft
vii) Dynamic Discharge Head (v+vi) 85.37 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 141.13 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 87.25
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 40.80 hp
xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 53.62 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 88.89 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 76.09 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.15 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 3,120 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,138,800 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 176,139 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,289,812 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 76.09%. For 60 HP motor efficiency > 65.9% is considered to be Excellent.This pumping system is efficent. This pumping system requires no intervention regarding pumping system efficiency.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 543,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
No Water meter New water meter is recommeneded
New 25 KVAr PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name Muhammad Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact KHAWAR NADEEM
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
SHERAWALA BAGH LADY PARK (Tube Well No.47)
0300-7428684
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 45.9
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-8439
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 30 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 34285
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues panel condition is good but volt meter is defective.
Gland Leakage Minor
Non Return Valve OK
Chlorinator NO
Flow Meter FAULTY
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring GOOD
Housekeeping FAIR
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 860 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 238 m3/hr
Velocity in Pipe 1.30 m/sec
Pressure
i) Pressure at Discharge Side of Pump 30 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 13 meter
ii) Pumping Water Level 16 meter
Electric Measurements
i) Voltage 379 381 379
ii) Ampere 77 69 76
iii) Power Factor 0.77 0.79 0.8
iv) Appearant Power (kVA) 51 46 45
v) Running Power (kW) 39 36 41 38.7
vi) Reactive Power (kVAr) 29 28 32
vi) Motor Working on Loading Basis 86
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,483 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 9.84 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 69.3 ft
vi) Discharge Side Frictional Head 3.77 ft
vii) Dynamic Discharge Head (v+vi) 73.07 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 125.55 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 106.50
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 33.22 hp
xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 51.83 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 72.39 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.10 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.16 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 2,856 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,042,440 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 170,268 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,213,485 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 64%. For 60 HP motor efficiency range 61-65.9% is considered to be GOOD efficiency range.This pumping system is efficent. This pumping system requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 548,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
Faulty Water meter New water meter is recommeneded
New 25 Kvar PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
New V meter recommendedVolt meter faulty
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer GULL/ HURR
WASA Staff Name M IQBAL
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact M ASHRAF
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 9 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
SIALVI TOWN JINNAH ROAD(Tube Well No.37)
0343-4979023
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 14 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture2008
v) Flowrate (Q) 4
Cusec 270 m3/hr
vi) Head (H)180
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 100.98
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-07-10-8203
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 34 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 125 hp 93.75 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 174.2
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,485 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 280-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading NOT VISIBLE
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues FAIR. Ampere meter is faulty
Gland Leakage Minor
Non Return Valve OK
Chlorinator Not installed
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping GOOD
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 980 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 458 m3/hr
Velocity in Pipe 2.51 m/sec
Pressure
i) Pressure at Discharge Side of Pump 34 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 12 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 384 381 384.6
ii) Ampere 163 167 161.9
iii) Power Factor 0.72 0.7 0.74
iv) Appearant Power (kVA) 108.3 110.1 110.5
v) Running Power (kW) 78 77.1 80.1 78.4
vi) Reactive Power (kVAr) 75.1 78.6 74.3
vi) Motor Working on Loading Basis 84
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,487 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 6.56 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 78.54 ft
vi) Discharge Side Frictional Head 13.77 ft
vii) Dynamic Discharge Head (v+vi) 92.31 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 138.23 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 307.40
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 70.39 hp
xiv) Brake Horsepower (bhp) (OEM Data) 100.98 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 105.09 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 69.71 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 66.98 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 9 hrs
xxi) Daily Pump flow 4,122 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,504,530 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 258,925 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,366,024 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 67%. For 125 HP motor efficiencoy range 63.5-68.9 is considered to be Good so pumpming system is efficient and it requires no intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 723,000 PKR
No pressure gauge New Pressure gauge is recommeneded
Faulty Chlorinator New Chlorinator is recommeneded
No Water meter New water meter is recommeneded
New 50 Kvar PFI Plant is recommendedNo PFI Plant
Install VFDNo VFD
Install a new ampere meterAmpere meter is defective
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name Muhammad Aslam
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact SHOUKAT ALI
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2008
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
TANKI KHIALI SHAH PUR OHR (Tube Well No.32)
0344-4232894
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 45.9
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-08-10-8434
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 25 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 14197.48
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues Fair. Ampere and volt meters are defective
Gland Leakage Minor
Non Return Valve OK
Chlorinator Not installed
Flow Meter Not installed
Pressure Gauge Not installed
Bore Hole in Front of Panel NO
Wiring FAIR
Housekeeping FAIR
OK
Foundation/Civil work OK
Ratchet plate ok
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 8 (on which flowmeter is clamped)
v) Pipe Perimeter 685 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 245 m3/hr
Velocity in Pipe 2.10 m/sec
Pressure
i) Pressure at Discharge Side of Pump 25 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 11 meter
ii) Pumping Water Level 15 meter
Electric Measurements
i) Voltage 394 389 390
ii) Ampere 74 85 80
iii) Power Factor 0.77 0.77 0.7
iv) Appearant Power (kVA) 51 57 54
v) Running Power (kW) 39 45 38 40.7
vi) Reactive Power (kVAr) 32 36 39
vi) Motor Working on Loading Basis 90
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,486 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 86.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 57.75 ft
vi) Discharge Side Frictional Head 9.86 ft
vii) Dynamic Discharge Head (v+vi) 67.61 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 116.81 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 82.22
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 31.82 hp
xiv) Brake Horsepower (bhp) (OEM Data) 45.9 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.51 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 69.32 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 58.37 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 2,450 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 894,250 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 149,229 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,939,980 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 256 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.16 kWh/m3
xxix) Potential of Energy Reduction 4.31 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 6,430 kWh/yr
xxxi) Annual Financial Saving on Pumping 83,596 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 58.37%. For 60 HP motor efficiency range 56-60.9% is considered to be Fair and 61-65.9% is GOOD.This pumping system is inefficent. This pumping system requires impeller adjustment to increase its efficiency up to 61% which is GOOD efficiency.
This intervention will save83,596 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 633,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
No Flow meter New flow meter is recommended
New 25 Kvar PFI Plant is recommendedNo PFI Plant
It requires impeller adjsutmentPump is in efficient
No VFD Install VFD
Install new ampere and volt meters Ampere and volt meter faulty
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer WASEEM /IZHAR
WASA Staff Name M ASLAM
i) Name of Pumping Station
ii) Name of Subdivision ZONE-II
iii) Operator Name & Contact M TARIQ
iv) Total Number of Pumps Installed 1
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation 2009
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty 1
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 1
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 8 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
TOWER ROAD KHIALI (NEW) (Tube Well No.30)
0321-6460720
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
xiii) Availability of Chlorinator
Yes No
2 Pump Basic Information (Pump Ref # CITY_FWPS/WWDS_Pump #)
i) Type of Pump Deep Well
Submersible
Overhung
Between Bearing
ii) Mounting / Erection
Horizontal Vertical
Foundation
iii) Concrete Bolted Bolted
iv) Lubrication Type
Oil Water
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi 4
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Ground Water Aquafier Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Fresh Water Supply Network
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv)
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand K S B Country PAK
ii) ModelB 12 B/4
Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 2
Cusec 270 m3/hr
vi) Head (H)165
ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 47.6
BHP
ix) Speed (n)1450
RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) (Not Valid incase of Tubewells)
ii) Enter Length of Suction Pipe (ft) (Not Valid incase of Tubewells)
iii) Enter Fittings on Suction Pipe (Not Valid incase of Tubewells)
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Foot Valve
Bends Control Valve
Strainer Elbows
iv) Storage Capacity of Suction Source (Aquafier)
v) Working Volume of Source
vi) Suction Lift (from Datum Line)
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure (Not Valid incase of Tubewells)
21-09-10-10045
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe 10 inch
ii) Length of Discharge Pipe (Not known as directly connected to network underground)
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Control 1 Check
Bends Elbow 1
Strainer Wash out 0
iv) Storage Capacity of Discharge Destination (Not known as directly connected to network underground))
v) Working Volume of Discharge Destination (Not known as directly connected to network underground))
vi) Discharge Elevation (from Datum Line) (In case of no gauge)
vii) Availbility of Pressure Gauge Yes No (Installed by Team)
viii) Discharge Pressure 27 psig
6 Motor Nameplate Data
i) Manufacturer SIEMENS
ii) Rated kW / hp 60 hp 45 kW
iii) Voltage Range (Volts) 380 Volts
iv) Current (Ampere) 85.4
v) Power Factor (Cos ɸ) 0.86
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 1,475 RPM
vii) Reference Frequency 50 C/S
viii) Insulation Class F
ix) Motor Frame Size 225-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading FAULTY
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant Not installed
Panel Condition/Issues FAIR, no voltmeter
Gland Leakage NO
Non Return Valve OK
Chlorinator Not installed
Flow Meter OK
Pressure Gauge Not installed
Bore Hole in Front of Panel YES
Wiring GOOD
Housekeeping FAIR
OK
Foundation/Civil work OK
Ratchet plate OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 (on which flowmeter is clamped)
v) Pipe Perimeter 830 mm (on which flowmeter is clamped)
vi) Type of Clamping (V/N/Z) Z
viii) Flow Measurement 240 m3/hr
Velocity in Pipe 1.32 m/sec
Pressure
i) Pressure at Discharge Side of Pump 27 psig
ii) Pressure at Suction Side of Pump (Not Valid incase of Tubewells)
Motor Terminal Box
iii) Water Shutoff Head
Levels
i) Static Water Level 10 meter
ii) Pumping Water Level 14 meter
Electric Measurements
i) Voltage 391 390 388
ii) Ampere 75 80 81
iii) Power Factor 0.77 0.8 0.76
iv) Appearant Power (kVA) 51 54 54
v) Running Power (kW) 39 43 41 41.0
vi) Reactive Power (kVAr) 32 32 35
vi) Motor Working on Loading Basis 91
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 1,491 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 85.6
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
Calculations
10
i) Drawdown of Pump (Pumping water level - Static Water Level) 13.12 ft
ii) Static Suction Head (Only for WW Pump) ft
iii) Suction Side Frictional Head (Only for WW Pump) ft
iv) Dynamic Suction Head (ii+iii) (Only for WW Pump) ft
v) Discharge Head (Pressure Gauge) 62.37 ft
vi) Discharge Side Frictional Head 3.80 ft
vii) Dynamic Discharge Head (v+vi) 66.17 ft
viii) Total Dynamic Head of Pump (TDH) (vii + Pumping Water Level) 112.09 ft
ix) Specific Capacity of Pump (Water Turbine) gpm/ft of drawdown 80.54
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 29.91 hp
xiv) Brake Horsepower (bhp) (OEM Data) 47.6 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 54.96 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 62.84 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 54.43 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.17 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 8 hrs
xxi) Daily Pump flow 1,920 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 700,800 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 120,362 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,564,705 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 61 %
xxvii) Water Flow after Efficiency Improvement 269 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.15 kWh/m3
xxix) Potential of Energy Reduction 10.78 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 12,973 kWh/yr
xxxi) Annual Financial Saving on Pumping 168,653 PKR/Yr
11 Summary of Findings
Efficiency of the pumping system is 54%. For 60 HP motor efficiency <56% is considered to be LOW and 61-65.9% is GOOD.This pumping system is inefficent. This pumping system requires motor to be replaced to increase its efficiency up to 61% which is GOOD efficiency. This intervention will save 168,653 Rs annually.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
12 Estimated Investment for Improvement Plan 598,000 PKR
No pressure gauge New Pressure gauge is recommeneded
No Chlorinator New Chlorinator is recommeneded
Volt meter faulty New V meter is recommeneded
New 25 KVAr PFI Plant is recommendedNo PFI Plant
Replace motorMotor is in efficient
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station ABU BAKAR PARK DISPOSAL
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Khaleeq-ur-rehman
iv) Total Number of Pumps Installed 4
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 4
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 4
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 03
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model KV PK 350/500 Serial 21-05-10-2841
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H) 40 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 64 BHP
ix) Speed (n) 725 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 250
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 18 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer SEMIENS
ii) Rated kW / hp 100 hp 75 kW
iii) Voltage Range 400 Volts
iv) Current 140 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 735 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size 315-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 8602.69
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200,200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues EXCELLENT
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring EXCELLENT
Housekeeping OK
Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 1,020 mm
vi) Type of Clamping (V/N/Z)
viii) Flow Measurement 750 m3/hr 12.5 m3/min
Velocity in Pipe 2.86 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 82 meter
Electric Measurements Volt 389.3 394.3 392.7
Ampere 97.7 88.7 93.7
kW 48.67 Power Factor 0.74 0.79 0.76
vi) Motor Working on Loading Basis 65 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 746 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 85.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 18 ft
vi) Frictional Head (Suction and Discahrge) 23.93 ft
viii) Total Dynamic Head of Pump (TDH) 38.93 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 32.47 hp
xiv) Brake Horsepower (bhp) (OEM Data) 64.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65.24 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 50.73 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.77 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 9,000 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,285,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 214,318 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,786,129 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 949 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3
xxix) Potential of Energy Reduction 21.01 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 45,021 kWh/yr
xxxi) Annual Financial Saving on Pumping 585,279 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 49.77%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 585,279PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 610,000 PKR
No water flow meter Water flowmeter is recommended
Install VFD No VFD
No pressure guage Digital pressure guage is recommended
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station KASHMIR COLONY DISPOSAL
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Abid Ali 0300-0838425
iv) Total Number of Pumps Installed 2
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 2
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 2
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 8 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model SEWATEC K 250-40 IGIV Serial 9972156552/100/2
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 5 Cusec 510 m3/hr
vi) Head (H) 40 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 30 BHP
ix) Speed (n) 978 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 10
ii) Enter Length of Suction Pipe (ft) 10
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 10
ii) Length of Discharge Pipe (ft) 100
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 27 ft
Suction Side Elevation 5 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer KSB
ii) Rated kW / hp 40 hp 30 kW
iii) Voltage Range 400 Volts
iv) Current 59.3 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 980 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size 1-L-225-M-6
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 100 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues GOOD
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring EXCELLENT
Housekeeping OK
Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 10 inches
v) Pipe Perimeter 850 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 500 m3/hr 8.3333 m3/min
Velocity in Pipe 2.74 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 34 meter
Electric Measurements Volt 399.9 399.1 397.9
Ampere 48.6 47.6 49.5
kW 27.33 Power Factor 0.82 0.823 0.79
vi) Motor Working on Loading Basis 92 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 991 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 78.2
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 5 ft
v) Static Discahrge Head 27 ft
vi) Frictional Head (Suction and Discahrge) 19.85 ft
viii) Total Dynamic Head of Pump (TDH) 41.85 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 23.27 hp
xiv) Brake Horsepower (bhp) (OEM Data) 30.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 36.64 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 77.56 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 63.51 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 8 hrs
xxi) Daily Pump flow 4,000 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 1,460,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 80,232 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,043,010 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 63.51%. For pump attached with 40 HP motor, efficiency above 61% is considered to be excellent . This pumping system does not require any intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 425,000 PKR
Install VFD No VFD
No pressure guage Digital pressure guage is recommended
No power factor improvement (PFI) plant is installed PFI of 20 KVAR is recommended
No water flow meter Water flowmeter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station KHIALI DISPOSAL P # 1
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Mohammad Iqbal
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 4
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 6
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 15 Cusec 1,530 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 15
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 16
ii) Length of Discharge Pipe (ft) 100
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 31 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer EMIT
ii) Rated kW / hp 135 hp 101 kW
iii) Voltage Range 400 Volts
iv) Current 196 Amperes
v) Power Factor (Cos ɸ) 0.77
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 595 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 10270.56
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 600 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues VERY POOR
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring VERY POOR
Housekeeping OK
Motor Terminal OPEN AND LOSE MOTOR CONNECTIONS
Foundation/Civil work VIBRATE
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 16 inches
v) Pipe Perimeter 1,276 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 875 m3/hr 14.583 m3/min
Velocity in Pipe 1.87 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 35 meter
Electric Measurements Volt 397 393.6 395.2
Ampere 104.1 113.6 109.5
kW 41.1 Power Factor 0.59 0.54 0.56
vi) Motor Working on Loading Basis 41 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 595 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 86.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 31 ft
vi) Frictional Head (Suction and Discahrge) 8.89 ft
viii) Total Dynamic Head of Pump (TDH) 36.89 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 35.89 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 55.09 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 65.15 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.05 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 8,750 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,193,750 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 150,819 kWh/yr
xxv) Annual Energy Expenditure on Pumping 1,960,652 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 65.15%. For pump attached with 135 HP motor, efficiency above 63% is considered to be good . This pumping system does not requires any intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 710,000 PKR
No water flow meter Water flowmeter is recommended
No VFD
Over current relays and over/under voltage relay is recommendedOver current relays and over/under voltage relay is not installed
No pressure guage Digital pressure guage is recommended
Install VFD
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station KHIALI DISPOSAL P # 2
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Mohammad Iqbal
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 4
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 6
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 02
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model Serial
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 12 Cusec 1,224 m3/hr
vi) Head (H) ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP BHP
ix) Speed (n) RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 15
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 16
ii) Length of Discharge Pipe (ft) 100
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 31 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer EMIT
ii) Rated kW / hp 135 hp 101 kW
iii) Voltage Range 410 Volts
iv) Current 172 Amperes
v) Power Factor (Cos ɸ) 0.77
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 590 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 10270.56
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 600 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues VERY POOR
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring VERY POOR
Housekeeping OK
Motor Terminal OPEN AND LOSE MOTOR CONNECTIONS
Foundation/Civil work VIBRATE
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 16 inches
v) Pipe Perimeter 1,276 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 875 m3/hr 14.583 m3/min
Velocity in Pipe 1.87 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 35 meter
Electric Measurements Volt 389 389.6 391.7
Ampere 146.7 135.1 145.5
kW 71.82 Power Factor 0.76 0.7 0.76
vi) Motor Working on Loading Basis 71 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 590 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 88.7
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 31 ft
vi) Frictional Head (Suction and Discahrge) 8.89 ft
viii) Total Dynamic Head of Pump (TDH) 36.89 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 35.89 hp
xiv) Brake Horsepower (bhp) (OEM Data) 0.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 96.27 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 #DIV/0! %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 37.28 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.08 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 8,750 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,193,750 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 263,549 kWh/yr
xxv) Annual Energy Expenditure on Pumping 3,426,132 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 1,479 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3
xxix) Potential of Energy Reduction 40.82 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 107,580 kWh/yr
xxxi) Annual Financial Saving on Pumping 1,398,540 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 37.28%. For pump attached with 135 HP motor, efficiency below 58% is considered to be low . This pumping system requires impeller adjustment ,repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 1,398,540PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 915,000 PKR
Defective Volt meter
Over current relays and over/under voltage relay is recommendedOver current relays and over/under voltage relay is not installed
No pressure guage Digital pressure guage is recommended
Replace faulty Volt meter with correct one
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
No water flow meter Water flowmeter is recommended
No VFD Install VFD
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station KHIALI DISPOSAL P # 5
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Mohammad Iqbal
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 4
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 6
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 05
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model KVPK K 300-500 D2 Serial 21-09-10-11265
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H) 50 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 78 BHP
ix) Speed (n) 960 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 35
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 150
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 24 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer KSB
ii) Rated kW / hp 100 hp 75 kW
iii) Voltage Range 400 Volts
iv) Current 133 Amperes
v) Power Factor (Cos ɸ) 0.86
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 985 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size I-L-315-S-6
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 7353.21
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues GOOD
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring GOOD
Housekeeping OK
Motor Terminal TIGHT AND PROPER MOTOR CONNECTIONS
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 957 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 800 m3/hr 13.333 m3/min
Velocity in Pipe 3.05 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 56 meter
Electric Measurements Volt 391.9 389.8 392.7
Ampere 90.6 88 87.3
kW 48.13 Power Factor 0.81 0.79 0.81
vi) Motor Working on Loading Basis 65 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 989 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 88.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 24 ft
vi) Frictional Head (Suction and Discahrge) 25.46 ft
viii) Total Dynamic Head of Pump (TDH) 46.46 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 41.32 hp
xiv) Brake Horsepower (bhp) (OEM Data) 78.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 64.52 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 52.98 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 64.05 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 8,000 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,920,000 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 176,616 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,296,014 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 64.05%. For pump attached with 100 HP motor, efficiency above 63% is considered to be good . This pumping system does not require any intervention.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 610,000 PKR
Install VFD No VFD
No pressure guage Digital pressure guage is recommended
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
No water flow meter Water flowmeter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station KHIALI DISPOSAL P # 6
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Mohammad Iqbal
iv) Total Number of Pumps Installed 6
v) Total Number of Pumps in Operation 4
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 6
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 6
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 10 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 06
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model KV PK 350-500 D2 Serial 21-09-10-11264
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H) 50 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 78 BHP
ix) Speed (n) 960 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 35
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 150
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 24 ft
Suction Side Elevation 5 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer KSB
ii) Rated kW / hp 100 hp 75 kW
iii) Voltage Range 400 Volts
iv) Current 133 Amperes
v) Power Factor (Cos ɸ) 0.86
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 985 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 7353.21
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues GOOD
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring GOOD
Housekeeping OK
Motor Terminal TIGHT AND PROPER MOTOR CONNECTIONS
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 957 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 650 m3/hr 10.833 m3/min
Velocity in Pipe 2.47 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 56 meter
Electric Measurements Volt 389 392 390.4
Ampere 85 82.8 84.6
kW 44.16 Power Factor 0.79 0.77 0.76
vi) Motor Working on Loading Basis 59 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 980 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 89.9
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 5 ft
v) Static Discahrge Head 24 ft
vi) Frictional Head (Suction and Discahrge) 16.88 ft
viii) Total Dynamic Head of Pump (TDH) 35.88 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 25.93 hp
xiv) Brake Horsepower (bhp) (OEM Data) 78.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 59.20 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 33.25 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 43.81 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 10 hrs
xxi) Daily Pump flow 6,500 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 2,372,500 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 162,048 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,106,627 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 935 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3
xxix) Potential of Energy Reduction 30.46 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 49,360 kWh/yr
xxxi) Annual Financial Saving on Pumping 641,675 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 43.81%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 641,675PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 895,000 PKR
No VFD
Replace faulty Volt meter by correct oneDefective Volt meter
No pressure guage Digital pressure guage is recommended
Install VFD
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
No water flow meter Water flowmeter is recommended
Pump is in efficent It requires impeller adjustment, repair and maintenance
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station NOSHERA ROAD DISPOSAL
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Ghulam naseer 0345-6556461
iv) Total Number of Pumps Installed 3
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 3
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 3
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 19 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 03
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model KV PK 350/500 d-2 Serial 21-07-10-8012
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H) 48 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 70 BHP
ix) Speed (n) 725 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 30
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 150
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 10 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer SEMIENS
ii) Rated kW / hp 100 hp 75 kW
iii) Voltage Range 400 Volts
iv) Current 140 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 735 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size 315-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading Damaged
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200,200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues GOOD
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring GOOD
Housekeeping OK
Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 957 mm
vi) Type of Clamping (V/N/Z)
viii) Flow Measurement 730 m3/hr 12.167 m3/min
Velocity in Pipe 2.78 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 55 meter
Electric Measurements Volt 390.3 384.4 388.2
Ampere 99.8 110.4 100.2
kW 50.64 Power Factor 0.76 0.74 0.69
vi) Motor Working on Loading Basis 68 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 741 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 84.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 10 ft
vi) Frictional Head (Suction and Discahrge) 21.15 ft
viii) Total Dynamic Head of Pump (TDH) 28.15 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 22.85 hp
xiv) Brake Horsepower (bhp) (OEM Data) 69.80 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 67.88 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 32.74 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 33.66 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.07 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 19 hrs
xxi) Daily Pump flow 13,870 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 5,062,550 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 353,071 kWh/yr
xxv) Annual Energy Expenditure on Pumping 4,589,929 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 1,366 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.04 kWh/m3
xxix) Potential of Energy Reduction 46.56 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 164,406 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,137,275 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 33.6%. For pump attached with 100 HP motor, efficiency below 57.3% is considered to be low. This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 2,137,275 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 890,000 PKR
No VFD
It requires impeller adjustment, repair and maintenancePump is in efficent
No pressure gauge Digital pressure gauge is recommended
Install VFD
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
No water flow meter Water flowmeter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station NOSHERA ROAD SANSI DISPOSAL
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact M.Asif Nadeem 0300-6401137
iv) Total Number of Pumps Installed 5
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 5
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 5
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 18 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source DAMAGED hrs/day
2 Pump Basic Information Pump # 01
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model SEWATEC K 400-500 GP Serial 9972926290/101
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 20 Cusec 2,040 m3/hr
vi) Head (H) 50 ft
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 108 BHP
ix) Speed (n) 988 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 20
ii) Enter Length of Suction Pipe (ft) 20
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 20
ii) Length of Discharge Pipe (ft) 450
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 16 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer KSB
ii) Rated kW / hp 180 hp 134 kW
iii) Voltage Range 400 Volts
iv) Current 231.8 Amperes
v) Power Factor (Cos ɸ) 0.87
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 990 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size I-L-315-L-6
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 1977.47
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200,200,200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues EXCELLENT
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring EXCELLENT
Housekeeping OK
Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 20 inches
v) Pipe Perimeter 1,595 mm
vi) Type of Clamping (V/N/Z)
viii) Flow Measurement 1,950 m3/hr 32.5 m3/min
Velocity in Pipe 2.67 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 143 meter
Electric Measurements Volt 381.4 379.1
Ampere 196.6 205.7
kW 109.5 Power Factor 0.83 0.84
vi) Motor Working on Loading Basis 82 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 990 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 92.8
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 16 ft
vi) Frictional Head (Suction and Discahrge) 20.83 ft
viii) Total Dynamic Head of Pump (TDH) 33.83 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 73.35 hp
xiv) Brake Horsepower (bhp) (OEM Data) 108.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 146.78 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 67.91 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 49.97 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 18 hrs
xxi) Daily Pump flow 35,100 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 12,811,500 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 723,272 kWh/yr
xxv) Annual Energy Expenditure on Pumping 9,402,542 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 64 %
xxvii) Water Flow after Efficiency Improvement 2,498 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.04 kWh/m3
xxix) Potential of Energy Reduction 21.92 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 158,560 kWh/yr
xxxi) Annual Financial Saving on Pumping 2,061,274 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 50%. For pump attached with 180 HP motor, efficiency below 59% is considered to be low . This pumping system requires impeller adjustment and maintenance. After this its efficiency will be improved to 64% (GOOD Efficiency range), with annual savings of 2,061,274 PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 1,190,000 PKR
It requires impeller adjustment, repair and maintenacePump is in efficient
No pressure guage Digital pressure guage is recommended
No power factor improvement (PFI) plant is installed PFI of 100 KVAR is recommended
No water flow meter Water flowmeter is recommended
1 Pumping Station Information
1 Fresh Water Supply
2 Wastewater Disposal
3 Waste Water Treatment Plant
4 Water Treatment Plant
Name of Engineer
WASA Staff Name
i) Name of Pumping Station SARFRAZ COLONY DISPOSAL
ii) Name of Subdivision ZONE II
iii) Operator Name & Contact Khaleeq-ur-rehman
iv) Total Number of Pumps Installed 4
v) Total Number of Pumps in Operation 1
vi) Year of Starting Operation
vii) Types of Pumps
Standard Deep Well Water Turbine Pumps Qty
Submersible Deep Well Water Turbine Pumps Qty
Centrifugal Pump Qty 4
Submersible Disposal Pump Qty
vi) Operational Scheme of Pumps Qty
Independent 4
Series
Parallel
vii) Any Header / Tank / Reservoir
Yes No
viii) Any Record Keeping
Time Flow Pressure
Level Quality of Water Power Consumption
Maintenance Record Electricity Bill Fuel Consumption Data
viii) Daily Operational Time 12 hrs/day
ix) Annual Working Days 365 days
x) Source of Power
Energy Report of WASA Pumps
Primary GEPCO Secondary
xi) In Case of Secondary Power Source Fuel Data Details
xii) Operational Hours of Secondary Power Source hrs/day
2 Pump Basic Information Pump # 03
ii) Mounting / Erection
Horizontal Vertical Submersible
Foundation
iii) Concrete Bolted Bolted
iv)
v) Cooling Type
Water Cooled Air Cooled
vi) Number of Stages
Single Multi
vii) Pump and Motor Assembly
Direct Coupled Belt / Gear
viii) Source of Suction
Wet Well Overhead Tank Underground Tank
Pressurized Source
ix) Pump Discharge Destination
Overhead Tank Drain On Ground Reservoir
Pit
Pump Operational Scheme
On / OFF Proportional
x) Pump Flow Control
Throttle VFD Controlled
xi) Any Retrofits ?
Impeller Detail
Casing / Volute Detail
Line Shaft (DW) Detail
Column Sett. (DW) Detail
Motor Replacement Detail
Motor Rewinding Detail
xii) Self Priming
Yes No NA (not applicable)
xiii) Non Clogging (In case of wastewater)
Yes No
xiv) Flowmeter Available
Yes No
xv) Flowmeter Working
Working Properly Malfunctioning (Damaged)
3 Pump Nameplate Data
i) Make / Brand KSB Country PAK
ii) Model KVP 300-500 D2 Serial 21-11-10-12268
iii) Certification Mark
iv) Year of Manufacture
v) Flowrate (Q) 10 Cusec 1,020 m3/hr
vi) Head (H) 50
vii) Discharge Pressure (P) Psig
viii) Power / HP / BHP 75 BHP
ix) Speed (n) 960 RPM
x) Maximum Pressure (Pmax)
xi) Maxiumum Allowable Temperature
5 Piping System
Suction Side
Select Pipe Material of Construction MS Pipe
i) Enter Diameter of Suction Pipe (In) 12
ii) Enter Length of Suction Pipe (ft) 10
iii) Enter Fittings on Suction Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Flow control 1
Bends
Strainer 1
viii) Availbility of Pressure Gauge Yes No
ix) Suction Pressure
Discharge Side
Pipe Material of Construction MS Pipe
i) Diameter of Discharge Pipe (in) 12
ii) Length of Discharge Pipe (ft) 30
iii) Fittings on Discharge Pipe
Fitting Type 1 Qty Type 2 Qty Type 3 Qty
Valves Non return 1 1
Bends 1
Strainer
vi) Discharge Elevation (from Datum Line) 17 ft
Suction Side Elevation 3 ft
vii) Availbility of Pressure Gauge Yes No
viii) Discharge Pressure psig
6 Motor Nameplate Data
i) Manufacturer SEMIENS
ii) Rated kW / hp 100 hp 75 kW
iii) Voltage Range 400 Volts
iv) Current 140 Amperes
v) Power Factor (Cos ɸ) 0.84
Standard
Ambient Temp oC
Year of Manufacturing
Efficiency Class
IE3 Eff 1
IE2 Eff 2
IE1 Eff 3
Standard Efficiency
vi) Motor Speed 735 RPM
vii) Reference Frequency 50 Hz
viii) Insulation Class F
ix) Motor Frame Size 315-M
x)
7 Electrical System Observations
i) Electrical Meter Reference Number
ii) Meter Reading 8602.69
iii) Meter Time and Date
Correct FALSE
Lag by Lead by
iv) Transformer Rating (kVA) 200,200 Condition OK
Pump O & M Cost
v) Motor Starting Method
Direct Online Star (Wye) - Delta
Autotransformer Starter Soft Starter
Variable Frequency Drives
v) Electrical Protections Available
Earthing / Grounding Fuses or Miniature Circuit Breaker (MCB)
Earth Leakage Circuit Breaker (ELCB) and Residual Current Circuit Breaker (RCCB)
PFI Plant NOT INSTALLED
Panel Condition/Issues EXCELLENT
Gland Leakage NA
Non Return Valve NA
Flow Meter NA
Pressure Gauge NA
Wiring EXCELLENT
Housekeeping OK
Motor Terminal PROPERLY CONNECTED IN TERMINAL BOX
Foundation/Civil work OK
Field Measurements
8 Flow Measurement
i) Flow Measurement Location
Discharge Pipe Suction Pipe
ii) Pipe Material of Construction MS Pipe
iii) Paint on Pipe Yes No
iv) Pipe Diameter 12 inches
v) Pipe Perimeter 1,020 mm
vi) Type of Clamping (V/N/Z) V
viii) Flow Measurement 774 m3/hr 12.9 m3/min
Velocity in Pipe 2.95 m/sec
Pressure
i) Pressure at Discharge Side of Pump psig
ii) Pressure at Suction Side of Pump
ii) Total Length (Suction+Discahrge Pipe) 12 meter
Electric Measurements Volt 389.3 394.3 392.7
Ampere 97.7 88.7 93.7
kW 48.67 Power Factor 0.74 0.79 0.76
vi) Motor Working on Loading Basis 65 %
Oversize Undersize Properly Sized
Speed
i) Speed of Motor 746 RPM
ii) Speed of Pump Impeller RPM
Noise Level
Noise Level (db(A)) Avg. Max: 85.5
Thermal Imaging
i) Motor Motor Pump Coupling
Pump Volute Casing Pump Bearings
Electric Panels
10 Calculations
ii) Static Suction Head (Only for WW Pump) 3 ft
v) Static Discahrge Head 17 ft
vi) Frictional Head (Suction and Discahrge) 21.08 ft
viii) Total Dynamic Head of Pump (TDH) 35.08 ft
x) Specific Speed of Pump
Ns = RPM x GPM0.5 / H0.75
impeller rpm necessary to produce 1gpm/ft head 0
500-10,000, standard, 2,000-3,000 high efficiency
xi) Difference of Pump Curve flow and Measured Flow at the TDH m3/hr
xii) Deviation of actual flow from the pump curve flow %
xiii) Water Horsepower (whp) (TDH x Actual Measured Flow) 30.19 hp
xiv) Brake Horsepower (bhp) (OEM Data) 75.00 hp
xv) Electrical Horsepower(ehp) (Electrical Measurement at Motor input) 65.24 hp
xvi) Efficiency of Individual Pump (ηpump) (whp/bhp) x 100 40.26 %
xvii) Efficiency of Pumping System (ηsystem)Existing (whp/ehp) x 100 46.28 %
xviii) Existing Specific Pumping Energy (En(pumping01)) 0.06 kWh/m3
xix) Avg. Cost of Energy (Based on Grid and Backup) 13 PKR/kWh
xx) Daily Operational Time of Pump 12 hrs
xxi) Daily Pump flow 9,288 m3/day
xxii) Annual working days 365 days
xxiii) Annual Pump flow 3,390,120 m3/yr
xxiv) Annual Energy Consumption of Pump (En(pumping01) x Annual Pump Flow) 214,318 kWh/yr
xxv) Annual Energy Expenditure on Pumping 2,786,129 PKR/Yr
xxvi) Pumping System Efficiency after Improvement 63 %
xxvii) Water Flow after Efficiency Improvement 1,054 m3/hr
xxviii) Specific Energy Consumption at New Efficiency 0.05 kWh/m3
xxix) Potential of Energy Reduction 26.54 %
xxx) Reduced Annual Energy Consumption at Improved Efficiency 56,888 kWh/yr
xxxi) Annual Financial Saving on Pumping 739,548 PKR/Yr
11 Summary of Findings
Pumping system efficiency is 46.28%. For pump attached with 100 HP motor, efficiency below 57% is considered to be low . This pumping system requires impeller adjustment, repair and maintenance. After this adjustment its efficiency will be improved to 63% (GOOD Efficiency range), with annual savings of 739,548PKR.
Issues & Recommendations
12 ISSUES RECOMMENDATIONS
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
xviii)
Financial Analysis / Indicators
Estimated Investment for Improvement Plan 890,000 PKR
No VFD
It requires impeller adjustment repair and maintenancePump is in efficient
No pressure guage Digital pressure guage is recommended
Install VFD
No power factor improvement (PFI) plant is installed PFI of 50 KVAR is recommended
No water flow meter Water flowmeter is recommended
ANNEXURE-2
Selected Pictures
Housekeeping at TW 36 No fan cover at TW 27
Poor wiring at TW 34 No PFI at Safraz Colony
Sound measurement at Sheranwala View of discharge pipeline at TW 37
Faulty A meter at Abubakar Park Disposal Faulty A & V meter at Kashmir Colony Disposal
Poor wiring at Khiali Disposal Poor wiring at Khiali Disposal