pd -a-4.d - , ipdf.usaid.gov/pdf_docs/pdaad863c1.pdf · cimaragas no. 1 ; banjar, west java,...
TRANSCRIPT
PD - A-4D - I
REPUBLIC oF INonEsu
MINISTRy OF PUBLIC WORKS AND ELECTRIC POWER
DIRECTORATE GENERAL OF WATER RESOURCs BE VupUMNT
THE CITANDUY RIER BASIN
DEVELOPYEJNT FloTrCT
MONTHLY REPORT FOR THE PERI1O1
Ending 31 O tober 19147
SUBMITTED BY
ENGINEERING CONSULTANTS INC DENVER COLORADO iSA BANJAR INDONESIA
HOME OFFICE 1901 SOUTH NAVAJO STREET 0 DENVER COLORADO 80223 USA TELEPHONE 303938-3417 9 CABLE ECIDEN 0 DENVER COLORADO
0E29 0NINGCONSULTANTS
INC REPLY TO
PROYEK CITANDUY JL CIMARAGAS NO 1
BANJAR WEST JAVA INDONESIA
CABLE ECIBANJAR
October 31 1974
Directorate General of Water Resources Development Ministry of Public Works and Electric Power Jalan Pattimura 207Kebayoran Baru Jakarta Our file 1138131Republic of Indonesia
Mr1074 Subject Monthly ReportAttn Director of River and Cit anduy RiverSwampy Area Development
Basin Development
ProjectsDear Sir
We are herewith submitting our fifteenth monthly reportwhich covers the calender month of October 1974 This marks the thirdmonth of our second year of operation on the Citanduy Project We hopethat these reports have proved to be useful in judging the quality andthe quantity of works accomplished by the Consultants
We are particularly pleased to ackno77ledge receiptDirector Generals approval of theof the revised draft of the Segara AnakanFeasibility Report
Yours trulyEncl Thirty (30) copies Engineering Consultants Inc
of Progress Report No 13
CC I USAIDJakarta American Embassy
Jakarta Republic of Indonesia Attn Gi ord E Rogerr Aleer Engineering Section Resident Manager
Six (6) enclosures 2 Directorate of River and Swamps Banjar Office
Attn Ir Soebandi Wirosoemarto Project ManagerCitanduy Project Five (55 enclosures
3o PT Indah Karya BandungAttn Ir Sahat TP Siagian Counterpart Team Leader
Five (5) enclosures
4 ECIDenver Attn Mrs CM Langford Project Sponsor
Three k3) enclosures 5 ECIStaff Banjar
Four (4) enclosures
A PLANNING RESEARCH CORPORATION COMPANY
MONTHLY -PORT NO 15
Period Ending 311074
I GENERL
During the entire month of October the entire staff was engaged in the completion of the comprehensive study and preparation of the Master Plan and twelve (12) Appendicess These publications are scheduled for submittal in November 1974
The home office in Denverp Colorado has advised us that the revised and final version of the Segara Anakan Feasibility Study is complete and ready for printings Since the Director General has now approval the revised draft we will proceed with the final printing
A highlight of the month was the visit to the project area by the Director General of Water Resource Development and of hissome staff An oral presentation of current progress on the Citanduty Project Study was given by ECI Staff members
With the exception of our meteorological equipment and the ozalid printer all of our technical equipment has now been received Time and staff requirements permitting we will attempt to instruct our counterparts in the use of all equipment
I
II- PERS CNEL
A Present at last report
I Gifford E Rogers - Resident Manager
2 David E Bogan - Irr amp Draine Engineer 3 Robert E Struthers - Economist 4 Michael P Saunders - Planning Engineer
B Arrivals subsequent to last report - N o n e
G Departures subsequent to last report - N o n e
)Scheduled to depart this month - N a n e
E Scheduled to depart in November 1974 - N o n e
F Scheduled to arrive in November 1974 - N o n e
G Scheduled to arrive at a later date
l CM Langford - Project Sponsor
2
pim
- l
m
0000
r4-
03 o
-I ~
0
-T
0 C2o
0000 i)- T Ti --o oodo
($j 4 HeM
0 0 0 0
+3 4 3+ 3 a) 0) (0) ()
H (1)
c T
H 0
0ed 00
ri rj
-P-P 4 0) 0)
-P ot
0
0)
0
02
0 C f n r
V-r N N N
3
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
HOME OFFICE 1901 SOUTH NAVAJO STREET 0 DENVER COLORADO 80223 USA TELEPHONE 303938-3417 9 CABLE ECIDEN 0 DENVER COLORADO
0E29 0NINGCONSULTANTS
INC REPLY TO
PROYEK CITANDUY JL CIMARAGAS NO 1
BANJAR WEST JAVA INDONESIA
CABLE ECIBANJAR
October 31 1974
Directorate General of Water Resources Development Ministry of Public Works and Electric Power Jalan Pattimura 207Kebayoran Baru Jakarta Our file 1138131Republic of Indonesia
Mr1074 Subject Monthly ReportAttn Director of River and Cit anduy RiverSwampy Area Development
Basin Development
ProjectsDear Sir
We are herewith submitting our fifteenth monthly reportwhich covers the calender month of October 1974 This marks the thirdmonth of our second year of operation on the Citanduy Project We hopethat these reports have proved to be useful in judging the quality andthe quantity of works accomplished by the Consultants
We are particularly pleased to ackno77ledge receiptDirector Generals approval of theof the revised draft of the Segara AnakanFeasibility Report
Yours trulyEncl Thirty (30) copies Engineering Consultants Inc
of Progress Report No 13
CC I USAIDJakarta American Embassy
Jakarta Republic of Indonesia Attn Gi ord E Rogerr Aleer Engineering Section Resident Manager
Six (6) enclosures 2 Directorate of River and Swamps Banjar Office
Attn Ir Soebandi Wirosoemarto Project ManagerCitanduy Project Five (55 enclosures
3o PT Indah Karya BandungAttn Ir Sahat TP Siagian Counterpart Team Leader
Five (5) enclosures
4 ECIDenver Attn Mrs CM Langford Project Sponsor
Three k3) enclosures 5 ECIStaff Banjar
Four (4) enclosures
A PLANNING RESEARCH CORPORATION COMPANY
MONTHLY -PORT NO 15
Period Ending 311074
I GENERL
During the entire month of October the entire staff was engaged in the completion of the comprehensive study and preparation of the Master Plan and twelve (12) Appendicess These publications are scheduled for submittal in November 1974
The home office in Denverp Colorado has advised us that the revised and final version of the Segara Anakan Feasibility Study is complete and ready for printings Since the Director General has now approval the revised draft we will proceed with the final printing
A highlight of the month was the visit to the project area by the Director General of Water Resource Development and of hissome staff An oral presentation of current progress on the Citanduty Project Study was given by ECI Staff members
With the exception of our meteorological equipment and the ozalid printer all of our technical equipment has now been received Time and staff requirements permitting we will attempt to instruct our counterparts in the use of all equipment
I
II- PERS CNEL
A Present at last report
I Gifford E Rogers - Resident Manager
2 David E Bogan - Irr amp Draine Engineer 3 Robert E Struthers - Economist 4 Michael P Saunders - Planning Engineer
B Arrivals subsequent to last report - N o n e
G Departures subsequent to last report - N o n e
)Scheduled to depart this month - N a n e
E Scheduled to depart in November 1974 - N o n e
F Scheduled to arrive in November 1974 - N o n e
G Scheduled to arrive at a later date
l CM Langford - Project Sponsor
2
pim
- l
m
0000
r4-
03 o
-I ~
0
-T
0 C2o
0000 i)- T Ti --o oodo
($j 4 HeM
0 0 0 0
+3 4 3+ 3 a) 0) (0) ()
H (1)
c T
H 0
0ed 00
ri rj
-P-P 4 0) 0)
-P ot
0
0)
0
02
0 C f n r
V-r N N N
3
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
MONTHLY -PORT NO 15
Period Ending 311074
I GENERL
During the entire month of October the entire staff was engaged in the completion of the comprehensive study and preparation of the Master Plan and twelve (12) Appendicess These publications are scheduled for submittal in November 1974
The home office in Denverp Colorado has advised us that the revised and final version of the Segara Anakan Feasibility Study is complete and ready for printings Since the Director General has now approval the revised draft we will proceed with the final printing
A highlight of the month was the visit to the project area by the Director General of Water Resource Development and of hissome staff An oral presentation of current progress on the Citanduty Project Study was given by ECI Staff members
With the exception of our meteorological equipment and the ozalid printer all of our technical equipment has now been received Time and staff requirements permitting we will attempt to instruct our counterparts in the use of all equipment
I
II- PERS CNEL
A Present at last report
I Gifford E Rogers - Resident Manager
2 David E Bogan - Irr amp Draine Engineer 3 Robert E Struthers - Economist 4 Michael P Saunders - Planning Engineer
B Arrivals subsequent to last report - N o n e
G Departures subsequent to last report - N o n e
)Scheduled to depart this month - N a n e
E Scheduled to depart in November 1974 - N o n e
F Scheduled to arrive in November 1974 - N o n e
G Scheduled to arrive at a later date
l CM Langford - Project Sponsor
2
pim
- l
m
0000
r4-
03 o
-I ~
0
-T
0 C2o
0000 i)- T Ti --o oodo
($j 4 HeM
0 0 0 0
+3 4 3+ 3 a) 0) (0) ()
H (1)
c T
H 0
0ed 00
ri rj
-P-P 4 0) 0)
-P ot
0
0)
0
02
0 C f n r
V-r N N N
3
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
II- PERS CNEL
A Present at last report
I Gifford E Rogers - Resident Manager
2 David E Bogan - Irr amp Draine Engineer 3 Robert E Struthers - Economist 4 Michael P Saunders - Planning Engineer
B Arrivals subsequent to last report - N o n e
G Departures subsequent to last report - N o n e
)Scheduled to depart this month - N a n e
E Scheduled to depart in November 1974 - N o n e
F Scheduled to arrive in November 1974 - N o n e
G Scheduled to arrive at a later date
l CM Langford - Project Sponsor
2
pim
- l
m
0000
r4-
03 o
-I ~
0
-T
0 C2o
0000 i)- T Ti --o oodo
($j 4 HeM
0 0 0 0
+3 4 3+ 3 a) 0) (0) ()
H (1)
c T
H 0
0ed 00
ri rj
-P-P 4 0) 0)
-P ot
0
0)
0
02
0 C f n r
V-r N N N
3
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
pim
- l
m
0000
r4-
03 o
-I ~
0
-T
0 C2o
0000 i)- T Ti --o oodo
($j 4 HeM
0 0 0 0
+3 4 3+ 3 a) 0) (0) ()
H (1)
c T
H 0
0ed 00
ri rj
-P-P 4 0) 0)
-P ot
0
0)
0
02
0 C f n r
V-r N N N
3
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
IV MAOR PROBLEM AREAS
No major problems to reports
4
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
V PROGRESS
A Technical
The progress on the request to the Project for additional surveys and geological investigations are reported as follows
Matengeng Damsite
Drilling work is nearing completion
Segara Anakan
No work has been started on the geologic foundation exploration program to date
Citanduy River
All surveys requested have been received
Ciseel River
All surveys requested have been received
Sidareja Irrigation System
A request was made on 1 May 1974 for the drawings and design report for this area To datel only the drawing parts of the design report have been received It is understood that the design report has been received by the Project
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
Binangun No 2 Damsite
One copy of I2000 topo survey of the damsite area has
been received from the Froject
Banjar Damsite
One copy of the 12000 topo survey of the damsite area
has been received from the Projeot
B Administrative
The following tables show the standings of both the rupiah
and US $ accounts We have completed 8 3o of the contract time
and have utilized 81 of the approved manpowor During this
elapsed time we have expended some Rp 18252276 or about 75 of
our total rupiah budget Some U 465400 or 85 of the total
dollar budget has been expended
6
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
Budet Status - Rupiah Account
I t e m
Per Diem
Cables
Postage
Reproduction
Supplies amp Materials
Other Minor Items
Administrative Staff
T o t a 1
Budget
Authorized
12040000
11001000
1100000
2p00000
1100000
700000
6300000
24340000
AJ10UNT (Hp)
Spent Remaining
7253500 4786500
583237 516763
435358 664642
3285131 (1285131)
1372837 ( 272837)
701526 1526
4620687 11679313
18252276 6087724
status - u s Account
(Reimbursable Costs Only)
I t e m
Overseas Salary
Overseaa Differential
Overhead (Overseas)
Denver Office Salaries
Denver Office Overhead
Special Consultants
Per Diem
Transport (International)
Transportation Baggage Household Effects
Other Direct Costs
T o t a 1
Authorized
153680
39920
95-278
82050
57435
10000
2838
59400
20800
28500
54901
7
AIOUNT ( US $ )
Spent Remaining
135000 18680
35100 4820
88000 7278
70000 12050
49000 8435
5000 5000
2300 538
41000 18400
17000 3800
23000 5500
465400 84501
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
VIs PROGRAM
A Technical
We are expecting the final printed report to be supplied by
the Denver Office before the end of November The resident ECI
staff will concentrate first on the completion of the Master Plan
and appendices and second on the revision of the comprehensive
flood control scheme The comprehensive study and Master Plan will
be submitted in November The revised comprehensive flood control
scheme will be submitted in early December
B Financial
We have submitted our request for our sixth and last
Rupiah payment vhich is due in November
8
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
VII APPENDICES
Figure I - Manpower Strength (for end of period)
Figure 2 Actual vse Scheduled Progress
Table I - Manpower Schedule shy cumulative totals US
Table 2 - Manpower Schedule - cumulative totals
Indonesian (Counterpart)
Table 2A - Manpower Schedule - cumulative totals
Indonesian (Diroct Hire)
Table 3 - Arrivals and Departures US Nationals
Table 4 - Arrivals and Departures Indonesian
Table 5 - Schedule of Submissions
A-I
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
LEGEND
----- USNATIONALS
3rd COUNTRY NATIONALS
-- -- INDONESIAN COUNTERPART
INDONESIAN DIRECT HIRE
20
bull ~~~~~~ed eT E
US NATIONALS
idintTD
E
-w z z
0fA~4SHEDULE I N -D- OUNIERPAR
GA - 2
0 0 5 10 1S i
-TIME SCHEDULE-in month4
igu-r No1 1AN POWER STRENGTH (for nd of eriod)
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
100
90i
LEGEND
SSCHEDULED
ACTUAL
PROGRESS
PROGRESS
S
70
60 I
1
-
a 40Ioi j 30
20
H-I
Ii
I - 1
10
I 2 3 4 5 6 7 8 9 10 11 12 13
- REPORT NUMBER (sec table NoS)---shy
figure No2_ ACTUAL VS SCHEDULED PROGRESS (End of Report Period)
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
tableNo1 -MANPOWER SCHEDULE-cumulative totals in man months
U S RATIO NALS 1 9 7 3 1 9 7 4 I1975 TOTALSRESIDENT STAFF AUGSEPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC JAN ACTUAL
2 ROGERS -RES 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1 500 1800 R2SCHOENLrBER-C E 100 200 300 400 S00 600 700 800 900 1000 1100 1200 1300r1300 5 _ 1800
101 shy3 B 0 G A N -IRPIG 061 13--20161 261 361 461 A561 61 761 861 961 1061 1161 1261i1361 1461 shy
1400 4 - EDWARDS -AGRI 0 50 150 250 350 450 550 650 750 850 950 1050 1150 -- - 1150 1200 5 SCOTT -GEOL 053 153 253 353 453 553 653 710 710 750 850 950 1013 -- 1013 700 6 GARDNER -SOILS - 053 153 253 353 453 553 653 753 853 953 1053 1153 - -- -- 1153 12007 STRUTHERS -ECON - 053 153 253 353 453 553 53 753 853 953 1053 1153 1253 1353 1b008a SAUNDERS -PLAN - - - - I - -- 026 126 226 326 426 526 626 726 1100 9
SUB TOTALS 261 770 1470 2170 2870 3570 4270 49965753 6453 7193 7993 8793 9276 9676 106 00 HOME OFFamp TDY
1 LANGFOR D - SPON 013 0T3 013 013 013 029 058 058 05amp 058 058 116 116 - 2 002 W ILL - PLAN - 053 098 0898 038 058 Q98 098 09amp 0_9S 098 o 9 sa 098 6 00 3 AU-YE UNG - HYD 023 123 143 143 143 143 143 214 254 254 254 254 254 -- - 400
_ COL E -CE - -shy
- shy - - 030 130 185 shy - -
_5 BU R KE - ROCK - shy - - - 068 068 shy- - - - 068 200 6 CHURCHILL- ENVIR
- 079 179 189 189 189 189 189 - - 119 150 7 FLETCHER - LANDUSE - 061 161 Z61 361 400 400 400 400 - - - 0oo 400 8 SPECIALISTS AS ROD - - - - - - 900 9
SUB TOTALS 036 189 254 254 254 331 539 810 960 999 1Q29 1255 1310 1310 1310 2150 THIR-_OUNTRyNT I
I K U EH L -C E 019 1079 079 079 79 079 079 08 159 159 159 159 159 -- - - 159 2501 KTEESL00O-- 0190793 07 1-CE- 2 STEVENS LULX--- -013--shy 13 6 116 16 16 116 16 116 196 296 shy 1 296 400
SUB TOTALS 01 079 0921 192 155 I95 195 2 275 275 35 455 455 50 _ 34 [101108 3 64095 04 9 8 72 __ 03 10554 T10414]55 141 -00 S 181612616 ~~~3 O 1 66 727 64516 - -_ _ _ ___
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
table No2 MANPOWER SCHEDULE - cumulative totals in mcnmonths
I N DONE SIAN 19741 9 7 4 19751 TOTALS COUNTERPART AUG EPT OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT INOV DEC JAN IACTU AL
I IRSAHAT -TEAM LEADER 100 200 300 400 500 600 700 800 900 1000 l10o 1200 1300 1400 1S00 1800 2 RPARIJAN -C E - - ~ - - - 090 190 2-90 330 4_9 590 690 7903 IR RADHI - DRAIN 1600011 11 1 11 311 411 S11 611 711
890 1 1400
4 IRTOSSIN -AGRI - 050 15C 250 350 450 550 650 750 850 950 1050 1150 ~ 35 __1200
SIINSUGAN HY -GEOL 084 184 284 384 484 584 S84 621 2 821 21 - 9 16006 IRARWADI A00 140 24to 440 40 640A - 00 7 IRSISWoKo -FLOODCON - -200 10- - - - - 280
8 IR IMAM -ECON shy 050 150 2035450 550 -x A- 9 DRSSUBAGIO -SOILS _100 200 300 001 50 -
-- - 500 10 B N 00 2003 004o00 oo 600 200 8 11 OT E R S - G- 0 3 5 36 23 5 3 5 43 _ _ _ shy
y~12 OTHERS -178 478] 718 10681 129011490 1690J 0300796 ~f 17 8 1798 1798 1798 1799~ ______
SUBTOTALS 27B 778 1418 22S2 2974 3674 t 4515 S2B36023 6658 7395 sect75 917 5 10075 1077 Boc0
ASST COUNTERPARTj ____ - IRE BET - PL AN 100O 200 304o o600 -700 700 700_1 700 700 700 700 T00 700 __ __ 1400
2 P NAPITUPULU -TEAM 006 106 206 306 406 506 606 706 806 906 1006 1106 1206 3__630 -- - 1406 1800 3 T M NADAPDAP-HYDROL 006 106 206 a06 4L06 506 60 706 806 906 1006 11 6 1206 1306 1406 400
4SMRD SIL 3 322332 42 2 3923 1023 1123 _ - -J23 14 COq5 ADIWID0AJA - AGRI - 023 123 223 323 423 523 6234 723 823 823 1023 1123 1Z23 13236 DSWILDAN -ECON 0075 1600175 275 375 55-- 6075 175 775 77 77S - - - -77S 1200
7 DRSSITANGGANG - C E shy 020 o ~~700 o shy - - -~_ 20
10 OTHERS - - 060 160 160 160 1 60 1601 160 160 16o 10 160 160
SUB TO TAL S 112 119 83259 718 3 7 TOT I 90 ~ 6 493 5~P35693 61931693 7093 7C f70003
3 10 6 2614 _-_ - _T _676955 c t 97 7IL 12 1235 158162-68 j17568 18548 __ =_ _
_ __ _
rjT HERS - CUMULATIVE TOTALS OF Nv2UAL W4O HAVE LEFT THE PROJECTA NOT SHOWN DUE TO LIMITED TIME A$ISi CCLNLTANTS
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
table No2A_A MAN POWER SCHEDULE -cumulative totals in man months
IN DONESI AN
DIRECT H I R E
1 NUNGKI SW- SECR
_Z SRI Z OEMAR- CLERK
3- SU PIART - CJ ERK
-4 ETJIH SUHARI7 TYPIST
5 DJOELIANDI - INTER
- SULA TI INTER
7- A _- MESS
AUG-
062
Q62
029
013
-
-
-
1973
SEF OCT
162 262
162 262
129 229
113 213
094 194
Q 10 1
100 2
NOV
362
362
329
313
294
210
300
DEC
462
462
429
413
394
310
400
JAN
562
562
529
513
494
410
500
FEB
662
662
629
613
594
510
600
MAR APR
762 862
762 862
729 629
713 813
694 794
610 7J
70 80
MAY
312
962
929
913
8 4
80
900
1 974
JUNE JULY AUG-
1062 1i52 1-62
1062 1162 12F2
1029 1129 1229
1013 1113 1213
8134 _894 84
110_ 01 1110
10Ov 100 1200
SEPT
1362
1362
1329
1313
-
1210
1300
OCT NOV
1462
1462
1429
1413
1330
140 080
DEC
1975
JAN
TOTALS
ACTUALC
1600
180O
1300
1100
894 1100
1 00
D O--shy 1 0 0 O
12
SUBT OTAL S MISC--SUPPORT-
16 760 47070 70 3570 270 490 5670
6370 6970
7570 1 6 70 12 00 -
1 DRAFTSMEN
M1SCS P---
2 MESSENGER
3 DRIVERS
CUSTODI ANS
-
400
200
400
400
600
200
1500
200
800
400
600
400
ao00
600
3200
600
120 1400
00 O1000
3800
00
1600-1200
5000
1200
1800 2D00
1400 1600
500 62PO
140 69
2250 25j50
10o200 6Q00DCL)74
1- 100 2000
285
2200
O08200
220
315013450 3- 50 - -
2400 2QQ
2400 2600
3750 -_0
2 00
960
am2800
-
S U ElTTL 14-00 25-00 4200 5400 66 00 7800 9_o -02_001l1400 12650113-3-50 1525015 7891532-0 567 2
TT AL15___570 12 94_ 11370 132-7517017070 t4120 in26on26004 SNot specified in cofltracit _
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
TABLE NO 3 - ARRIVAL AND MPARTURES
A US TIONAS
POSITION ARRIVED 1 aJIMD
1 LAIEFORDI CM Project Sponsor 23-7-73 4- 8-73 LAAGFORD CM Project Sponsor 27-1-74 8- 2-74 LWNGFORDI CM Project Sponsor 7-7-74 23- 7-74
2 ROGERS GE Resident Manager 30-7-73 shy3 SCHOEXLEBER WJ Civil Engineer 1-8-73 6- 9-74 4 BOGtN DE Irrigo Engineer 12-8-73 -5 AJ-YEUN YIN Hydrologist 25-8-73 13-10-73
LJ-Yfql YIN Hydrologist 9-3-74 12-4-74 6 WILL ERIC Chief Planner 15-9-73 15-10-73 7 EDWIUDS RT Agriculturist 16-9-73 31- 8-74 8 STRUTHERS RE Ag Economics 15-9-73 -9 GARDNeR RA Soil Scientist 15-9-73 31- 8-74
10 OTT DP Geologist 15-9-73 17- 4-74 SCOTT DP Geologist 19-6-74 19- 9-74
11 PLETCHER HC Land Use amp Mngt 13-1-74 12- 5-74 12 CHURCHILL DICK Environmentalist 17-2-74 3- 4-74 13 SIJJNMERS MP Planner 17-3-74 -14 COL HaN Civil Engineer 22-6-74 17- 8-74 15 BURKE HW Rock Specialist 6-7-74 28- 7-74
B TID COUNTRY NATIONALS
IEHL MK Chief Engineer 26-8-73 18- 9-73 IEHL MK Chief Engineer 29-3-74 21- 4-74
2 STEVENS MA Flood Control 27-10-73 1-12-73 STEVENS M4 Flood Control 6-7-74 5- 9-74
A-7
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
TABLE NO 4 - ARRIVAS AND ]EPAR UBES
A iNDoN~siA _- COUNTERPART
N A ME POSITION RIE_)M TD Is Sahat TP Siagian Team Leader 25- 7-73 shy2 Yasin Umar K Civil Engineer 1- 8-73 7-12-733 Amirudin Plan Engineer 15- 8-73 1- 3-74
4 Tossin A Agricalturist 17- 9-73 shy5 Imam Hidayat Economist 19- 9-73 shy6 Yusron Lubis 1 ydrologist 25- 13-10-738-73 7 Achmad Djojoadinoto Irr amp Drain 12- 9-73 1- 3-748 Soebagiyo Soils 2-10-73 31-10-74 9 ling Sugandhy Geology 6-11-73 30- 9-74
10 Sriyono River Regime 1-11-73 1-12-7311 Parijan Civil Engineer 4- 2-74 shy12 Arwadi Nataniel Planner 18- 2-74 shy13 RacLhi Sinaro Irr amp Drain 25- 2-74 shy14 Sainpudjo Ulydrolor-j 11- 3-74 12- 4-7415- Krebet Suryondadari Planner 1- 8-73 shy16 Soekanto Geographer 20- 5-74 -
B -OApS
I T Maruly Nadapdap ]lydrology 29- 8-73 shy2 Wildan Aif i Economint 8-10-73 31- 5-74 3 E SumarcLi A oil amp Rec 24- 9-73 30- 9-744o Rahmat Adiwidjaja Agriculture 24- 9-73 31-10-745- P Napitupulu Team Leader 29- 8-73 31-10-74
6 Sitanjganf Civil Entrineer 1- 9-73 7- 9-74
C 1I MSug TREXT HI 1 Nungid SW Secretary 13- 8-73 shy2 Sri Z Oemar Clerk 13- 8-73 shy3 Supiarti Clerk 23- 8-73 shy4 Etjih Suhari Clerk 29- 8-73 shy5 Sylvia S Interpreter 3- 9-73 31- 5-74 6a Pauline Salianti Interpreter 28- 9-73 shy7 Dasiran Tapawira Messenger I- 9-73 -
Part time only - Project fu-ished counterparts
A-8
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9
WALE- NO 5 - C=JL FWMISSIgNS
FSORT CONTRACTDAE ATND RAR UJECT WUE SUMI MONTHS
1 2 3 I Mapping requirement 30- 9-73 30- 9-73 2 2 2 3 2 Basic data collection 30- 9-73 30- 9-73 2 2a 2 3 2 Addendum No I - 15-11-73 35 3 2 5 1 Ist Priority Project 30-11-73 30-11-73 4
Evaluamption 4 2 5 1 2nd Priority Project 30-12-73 30- 1-74 5Evaluation
4a Special Report - 15- 2 - 74 w shy4be Special Progress Report - 30- 4-74 5 2 5 1 Is t Feasibility Study 15- 8-74- 31- 8-74 125(Draft Form)
6 2 5 1 2n d Feasibility Study 30- 6-74 30- 6-74 11 (Draft)
7 2 5 1 1 Feasibility Studiy 15-11-74-- 155 (Final)
8 2 5- 1 2nd Feasibility Study 30- 9-74 14 (Final)
9 2 3 Comprehensive Study 15-11-742 145 (Draft )
10 2 4 Master Plan (Draft) 15-11-7 A 145 11 2 3 Comprehensive Study 31- 1-75 18
(Final) 12o 2 4 Master Plan (Final) 31- 1-75 18 13 2 6 4 Completion Report 31- 1-75 18
30 day extension recommended by Steering Committee in order to await soils analysis results
1 Special Report shy Technical and Socio-Economic Factors As They Affect Damite Selection
Special Progress Report to Steering Committee j Time extension approved by Steering Committee on 30-4-74
S 25-974
A-9