pdd_guangdong shenzhen

Upload: kumarnadarajah

Post on 06-Apr-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 PDD_Guangdong Shenzhen

    1/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)

    Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring plan

  • 8/2/2019 PDD_Guangdong Shenzhen

    2/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 2

    SECTION A. General description of project activity

    A.1. Title of the project activity:

    >>

    Title: Guangdong Shenzhen Laohukeng Landfill Gas Utilization Project

    Version: 2.2

    Date: 14/03/2011

    A.2. Description of the project activity:

    >>

    Guangdong Shenzhen Laohukeng Landfill Gas Utilization Project (hereinafter referred to as

    the proposed project) is to collect and utilize the landfill gas (LFG) generated from

    Laohukeng landfill site in Shenzhen City, Guangdong Province, P. R. China. Shenzhen

    Laohukeng landfill started to receive municipal waste in December 2002, and it had anaverage reception of 1,033,059 tonnes

    1of waste per year during 2003 to 2009. The landfill

    will reach its maximum designed capacity by 2012.

    The proposed project involves the installation of a gas collection system, flaring equipment

    and electricity generation system at Laohukeng landfill site. A certain amount of methane in

    the LFG will be combusted in the generators to produce electricity for local grid. The

    excessive LFG and all the LFG collected during the period when electricity is not produced

    will be flared. The generator technology employed is from GE, a world leading company in

    manufacturing gas engines and generators. The proposed project will assist in transferring

    advanced LFG utilization technology to China. Three GE gas engines (unit capacity of 1.063

    MW) will be installed with a total capacity of 3.189 MW at the beginning and gradually

    reduced to two generators and finally one generator due to diminishing LFG2. The annualoperational hour is 6750 hours and the annual electricity output is 19,373 MWh at the first

    crediting period. The electricity generated by the proposed project will be sold to China

    Southern Power Grid to replace certain capacity of coal-fired power plants. The annual

    emission reduction is estimated to be 196,846 tonnes of CO2e for the first crediting period.

    The purpose of the proposed project is to utilize landfill gas to generate power and

    deliver it to China Southern Power Grid. For the proposed project,

    (a) Prior to the start of implementation of the project activity, the LFG is released toatmosphere directly and there is no power generation unit at the site of the proposed

    project, and the electricity was supplied by the China Southern Power Grid which isdominated by fossil fuel-fired power plants.

    (b) The project scenario is the implementation of the proposed project, the installationand operation of 3 sets of LFG generators with a total capacity of 3.189MW which

    will supply an average annual generation of 19,373MWh at the first crediting period

    to China Southern Power Grid and replace the same amount of electricity generated

    by fossil fuel-fired power plants connected to China Southern Power Grid. The LFG

    which is not used in generators will be flared.

    1Source: Statistics data from Urban Administration Bureau of Baoan District, which is the

    management organization of Laohukeng landfill.

    2

    According to the ex-ante estimation, totally three generators will be reduced to two sets in the 11th

    operational year, and then reduced to one set in the 17 th operational year. The actual generator

    reduction year will be based on the actual LFG generation conditions.

  • 8/2/2019 PDD_Guangdong Shenzhen

    3/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 3

    (c) The baseline scenario of the proposed project is the atmospheric release of LFG andthe electricity supply of equal amount as the proposed project from the China

    Southern Power Grid. The baseline scenario of the proposed project is the same asthe scenario prior to the start of the implementation of the project activity.

    The Project will have several positive social and environmental impacts as indicated in the

    following:

    1. GHG emission reduction

    The proposed project will utilize methane for electricity generation. The electricity generated

    by the proposed project will be sold to the China Southern Power Grid to replace the capacity

    of fossil fuel power plants.

    2. Contribution to environment protectionThe main social and environmental contribution of the proposed project will be a positive

    effect on the health of people in local community. By managing this landfill properly the air

    pollution in the local surroundings will decrease and odour nuisance and health risks of local

    people will be reduced.

    3. Clean energy demonstration

    Advanced foreign technology will be employed, which will enhance technology transfer

    activity. The proposed project will provide an example that can be used by others that may

    want to develop advanced and more efficient clean electricity generation using landfill gas

    throughout China.

    4. Job opportunity creation

    The newly installed capacity by the proposed project will directly benefit the local region by

    creating new jobs and will increase the local resident income and improve their life quality.

    In conclusion, the proposed project is consistent with Chinas national energy policy and

    sustainable development strategy.

    A.3. Project participants:

    >>

    Name of Party involved

    (host) indicates a host

    Party)

    Private and/or public

    entity(ies) project

    participants (as applicable)

    Kindly indicate if the Party

    involved wishes to be

    considered as projectparticipant (Yes/No)

    Peoples Republic of

    China (host)

    Shenzhen Dongjiang Lisai

    Recycled Power Co., Ltd.No

    The NetherlandsE.ON Climate & Renewables

    GmbHNo

    (*) In accordance with the CDM modalities and procedures, at the time of making the

    CDM-PDD public at the stage of validation, a Party involved may or may not have

    provided its approval. At the time of requesting registration, the approval by the Party (ies)

    involved is required.

    A.4. Technical description of the project activity:

  • 8/2/2019 PDD_Guangdong Shenzhen

    4/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 4

    A.4.1. Location of the project activity:

    A.4.1.1. Host Party(ies):

    >>

    Peoples Republic of China

    A.4.1.2. Region/State/Province etc.:

    >>

    Guangdong Province

    A.4.1.3. City/Town/Community etc:

    >>

    Baoan District, Songgang Township, Shenzhen City

    A.4.1.4. Detail of physical location, including information

    allowing the unique identification of this project activity (maximum one page):

    >>

    The proposed project activity is located at Tangxiayong Laohukeng Landfill site, Songgang

    Town, Baoan District, Shenzhen City, Guangdong Province, P. R. China. The geographical

    coordinates of the center point of the landfill are east longitude 11350'28.28'' (113.8412) and

    north latitude 2249'53.05'' (22.8314). The geographical coordinates of the factory building

    are east longitude 11350'27.95'' (113.8411) and north latitude 2249'52.80'' (22.8313).

    Geographical location of the project is showed in Figure 1 and Figure 2.

  • 8/2/2019 PDD_Guangdong Shenzhen

    5/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 5

    Figure 1: The proposed project on the map of P. R. China

    Figure 2: the proposed project on the map of Guangdong province

    A.4.2. Category(ies) of project activity:

    >>

    Category: Renewable electricity in grid-connected applications

    Sectoral Scope: 13 Waste Handling and Disposal

    A.4.3. Technology to be employed by the project activity:

    >>

    The proposed project is to utilize landfill gas for electricity generation in Shenzhen City,

    Guangdong Province, P. R. China. The proposed project is a grid-connected renewableenergy project.

  • 8/2/2019 PDD_Guangdong Shenzhen

    6/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 6

    Prior to the start of implementation of the project activity, the LFG is released to atmosphere

    directly and there is no power generation unit at the site of the proposed project, and theelectricity was supplied by the China Southern Power Grid. The baseline scenario of the

    proposed project is the same as the scenario prior to the start of the implementation of the

    project activity.

    By replacing the electricity generated from fossil fuel-fired power plants dominated China

    Southern Power Grid and the flare of unused landfill gas, the proposed project activity will

    achieve considerable greenhouse gas (GHG) emission reductions by reducing CO2 and CH4emissions.

    The proposed project consists of LFG recovery and utilization system, including LFG

    collection, pre-treatment, electricity generation, flaring, monitoring and data recording.

    Gas collection system

    The proposed project will apply modern LFG collection system which will consist of newly

    installed branch pipes, head pipes, and extraction wells for effective collection of the LFG.

    The expected LFG capture efficiency is in the range of 40%~50% (40% when the landfill is

    still accepting waste and 50% when the landfill is covered)3.

    Gas pre-treatment system

    Prior to flaring or combustion in generators, captured LFG must be pre-treated to remove its

    impurities and moisture. For the LFG to the generator, the pretreatment includes primary filter,

    blower and secondary filter. The primary filter can remove both the solid impurities and water

    from LFG, and the particle size after treated by primary filter is less than 50m. The LFGafter treated by the secondary filter can meet the requirement of generators and the particle

    size in it is less than 5m. For the LFG to the flare, it will go through a primary filter with

    blower before it goes into the flare.

    Electricity generation system

    The proposed project will install 3 generators with capacities of 1,063kW each, which amount

    to a total installed capacity of 3.189MW. The selected generators are GE Jenbacher gas

    engines. The main technical specifications of the generators are provided in the following

    table:

    Table A-1, generator specifications4

    Parameter Unit DataModel - JGS320 GS-L.L

    Quantity set 3

    Rated power kW 1,063

    Rated voltage kV 0.4

    Rated air input Nm3/h 605

    Lifetime Hour 120,0005

    3Source: Page 22, FSR.

    4Source: generator purchase contract

    5 According to the statement from power generator manufacture, the equipment lifetime is 60,000

    hours based on standard maintenance schedule. According to the manufacturers maintenance manual,

  • 8/2/2019 PDD_Guangdong Shenzhen

    7/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 7

    Load Factor % 776

    Generator efficiency % 97.2

    Furthermore, a 10kV substation will be constructed on the project site, connecting the

    proposed project to Songbei substation via a 10kV line, and then the power produced by the

    proposed project can be transmitted to the Guangdong Power Grid, which is an integral part

    of the China Southern Power Grid.

    The proposed project will use GE Jenbacher gas engines coming from the Europe, thus it

    involves international technology transfer to the host party.

    Flaring system

    An enclosed LFG flaring system is directly connected to the LFG collection system. It is used

    to combust the surplus collected LFG. The flaring system consists of tower and flareequipment. The main specifications of the flare are as follows:

    Table A-2, flare specifications7

    Parameter Unit Data

    Flow rate Nm3/hr 300-3000

    Combustion temperature 600-1200

    Burn rate >99%

    A.4.4. Estimated amount of emission reductions over the chosen creditingperiod:

    >>

    A crediting period of 7 years (01/04/2011- 31/03/2018, renewable twice) is selected for the

    project activity. An estimation of expected emission reductions over the crediting period is

    provided in the table below.

    the operational hours can be repeated with the overhaul after the 60,000 hours. Hence, the lifetime of

    the generator is 120,000 hours.

    6 Source: page 24, FSR. According to the FSR, the annual total power generation is 21,526MWh for 3

    generators (3.189MW), 14,351MWh for 2 generators (2.126MW) and 7,175MWh for 1 generator

    (1.063MW). The full load operational hour is 6750 hours. Hence, the plant load factor is 77%

    (6750/8760=77%). Considering that the capacity of internal loads are about 450kW (page 44, FSR), it

    is estimated that auxiliary consumption and transmission loss will account for 10% of the total power

    generation. Hence, the net electricity supplied to the grid by the project is 19,373MWh, 12,915MWh

    and 6,458MWh respectively. As the sums of the internal loads (450kW) are more than 10% of the

    installed capacity (3.189MW), the 10% auxiliary consumption is conservative.

    7Source: flare purchase contract

  • 8/2/2019 PDD_Guangdong Shenzhen

    8/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 8

    A.4.5. Public funding of the project activity:

    >>

    There is no public funding for this project.

    8According to FSR, methane generation from the landfill in each year is different, thus the emission

    reduction is different in each year. Considering the start date of crediting period is 01/04/2011, soseparate calculations of emission reduction were applied for the first and last year of the crediting

    period.

    YearsAnnual estimation of emission reductions

    in tonnes of CO2e8

    01/04/2011- 31/12/2011 147,38201/01/2012-31/12/2012 211,316

    01/01/2013-31/12/2013 279,416

    01/01/2014-31/12/2014 225,134

    01/01/2015-31/12/2015 186,640

    01/01/2016-31/12/2016 158,869

    01/01/2017-31/12/2017 138,416

    01/01/2018-31/3/2018 30,746

    Total estimated

    reductions (tonnes of

    CO2e)

    1,377,923

    Total number of the first crediting years 7Annual average over the crediting period

    of estimated reductions (tonnes of CO2e)196,846

  • 8/2/2019 PDD_Guangdong Shenzhen

    9/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 9

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology

    applied to the project activity:

    >>

    The approved methodology applied in the proposed project activity is ACM0001 (Version 11,

    EB47) Consolidated baseline and monitoring methodology for landfill gas project

    activities. For more information regarding the methodology please refer to

    http://cdm.unfccc.int/methodologies/PAmethodologies/approved.html

    The methodology also refers to the latest version of the following tools:

    Tool for the demonstration and assessment of additionality (Version 05.2, EB39)

    Tool to determine methane emissions avoided from disposal of waste at a solid waste disposal

    site (Version 05, EB55)Tool to determine project emissions from flaring gases containing methane (Version 01, EB28)

    Tool to calculate the emission factor for an electricity system (Version 02, EB50)

    Tool to calculate project or leakage CO2 emission from fossil fuel combustion (Version 02,

    EB41)

    Combined tool to identify the baseline scenario and demonstrate additionality (Version 02.2,

    EB28)

    Tool to calculate baseline, project and/or leakage emissions from electricity consumption

    (Version 01, EB39)

    B.2. Justification of the choice of the methodology and why it is applicable to the

    project activity:

    >>

    The approved consolidated methodology: ACM0001 (Version 11) is applicable to landfill gas

    capture project activities, where the baseline scenario is the partial or total atmospheric release

    of the gas and the project activities include situations such as:

    (a) The captured gas is flared; and/or(b) The captured gas is used to produce energy (e.g. electricity/thermal energy).(c) The captured gas is used to supply consumers through natural gas distribution

    network. If emissions reductions are claimed for displacing natural gas, project

    activities may use approved methodology AM0053.

    The baseline scenario of the proposed project is the atmospheric release of LFG and the

    electricity supply of equal amount as the proposed project from the China Southern PowerGrid. The baseline scenario of the proposed project is the same as the scenario prior to the

    start of the implementation of the project activity.

    As previously described, the proposed project is to collect LFG and utilize partial LFG for

    power generation. The excessive LFG will be flared. The proposed project meets situation (a)

    and (b) above and since the project does not involve natural gas it is not related to c) neither.

    Therefore, ACM0001 is applicable.

    B.3. Description of the sources and gases included in the project boundary:

    >>

    According to the methodology ACM0001, the project boundary is the site of the project

    activity where the gas is captured and destroyed/used.

  • 8/2/2019 PDD_Guangdong Shenzhen

    10/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 10

    If the electricity for project activity is sourced from grid or electricity generated by the LFG

    captured would have been generated by power generation sources connected to the grid, the

    project boundary shall include all the power generation sources connected to the grid to whichthe project activity is connected.

    In this case, the electricity for the proposed project is sourced from China Southern Power

    Grid and electricity generated by the LFG captured would have been generated by power

    generation sources connected to China Southern Power Grid. So the project boundary

    includes the whole LFG related system (e.g. LFG collection, LFG flaring, LFG power

    generation system, auxiliary equipment, etc.) and all grid-connected power plants connected

    to China Southern Power Grid.

    According to the Tool to calculate the emission factor for an electricity system (version 02),

    the delineation of grid boundaries as provided by the DNA of China9

    is used. China Southern

    Power Grid is the project electricity system. The transmission among China Southern PowerGrid and other grids (Central China Power Grid) is taken into account.

    Source Gas Included? Justification / Explanation

    CH4 Yes The major source of emissions in the

    baseline.

    N2O No N2O emissions are small compared to

    CH4 emissions from landfills. Exclusion

    of this gas is conservative.

    Emissions

    from

    decomposition

    of waste at the

    landfill site

    CO2 No CO2 emissions from the decomposition

    of organic waste are not accounted

    CO2 Yes Electricity may be consumed from thegrid or generated onsite/offsite in the

    baseline scenario

    CH4 No Excluded for simplification. This is

    conservative.

    Emissionsfrom

    electricity

    consumption

    N2O No Excluded for simplification. This is

    conservative.

    CO2 No The thermal energy generation is not

    included in the project activity.

    CH4 No The thermal energy generation is not

    included in the project activity.

    Baseline

    Emissions

    from thermal

    energy

    generation

    N2O No The thermal energy generation is not

    included in the project activity.CO2 No The fossil fuel consumption is not

    included in the project activity. But it

    will be monitored if any.

    CH4 No Excluded for simplification. This

    emission source is assumed to be very

    small.

    On-site fossil

    fuel

    combustion

    due to the

    project

    activity other

    than for

    electricity

    generation

    N2O No Excluded for simplification. This

    emission source is assumed to be very

    small.ProjectActivity

    Emissions CO2 Yes May be an important emission source.

    9http://qhs.ndrc.gov.cn/qjfzjz/t20090703_289357.htm

  • 8/2/2019 PDD_Guangdong Shenzhen

    11/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 11

    CH4 No Excluded for simplification. This

    emission source is assumed to be very

    small.

    from on-site

    electricity use

    N2O No Excluded for simplification. This

    emission source is assumed to be very

    small.

    The following figure shows the boundary of the baseline scenario and project activity.

    B.4. Description of how the baseline scenario is identified and description of the

    identified baseline scenario:

    >>

    According to ACM0001, the procedures for the selection of the most plausible baseline

    scenario are analyzed as follows:

    Step 1: Identification of alternative scenarios

    Alternatives for the disposal/treatment of the waste in the absence of the project activity, i.e.

    the scenario relevant for estimating baseline methane emissions, to be analysed should include,

    inter alia:

    LFG1: The project activity (i.e. capture of landfill gas and its flaring and/or its use)

    undertaken without being registered as a CDM project activity;

    LFG2: Atmospheric release of the landfill gas or partial capture of landfill gas and destruction

    to comply with regulations or contractual requirements, or to address safety and odour

    concerns.

    If LFG is used for generation of electric or heat energy for export to a grid and/or to a nearby

    industry or used on-site, realistic and credible alternatives should also be separately

    determined for:

    Power generation in the absence of the project activity

    Heat generation in the absence of the project activity.

  • 8/2/2019 PDD_Guangdong Shenzhen

    12/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 12

    For power generation, the realistic and credible alternative(s) may include, inter alia:

    P1: Power generated from landfill gas undertaken without being registered as CDMproject activity;

    P2: Existing or construction of a new on-site or off-site fossil fuel fired cogeneration

    plant;

    P3: Existing or construction of a new on-site or off-site renewable based cogeneration

    plant;

    P4: Existing or construction of a new on-site or off-site fossil fuel fired captive power

    plant;

    P5: Existing or construction of a new on-site or off-site renewable based captive power

    plant;

    P6: Existing and/or new grid-connected power plants.

    For heat generation,The proposed project doesnt involve thermal energy generation component. Therefore, all

    the alternatives of heat generation are not considered.

    Step 2: Identify the fuel for the baseline choice of energy source taking into account the

    national and/or sectoral policies as applicable.

    There is no existing fossil fuel power plant or plan to construct a new on-site or off-site fossil

    fuel fired cogeneration plant or captive power plant. The comparable installed capacity of the

    fossil fuel-fired plants with equivalent annual power supply as the project will be lower than

    3.189 MW, while coal-fired plants with a capacity of 135 MW or less are prohibited from

    development in large grid such as provincial girds

    10

    according to current regulations in China.So, alternative P2 and P4 are excluded.

    There is no existing renewable based power plant or plan to construct a new on-site or off-site

    renewable based cogeneration plant or captive power plant. Construction a new on-site or off-

    site renewable based cogeneration plant or captive power plant needs additional investment

    and technical efforts. Furthermore there is no hydro, wind11

    or other renewable resource

    available in the location of the proposed project for power generation. So, alternative P3 and

    P5 are excluded too.

    P3 and P5 are in compliance with all applicable legal and regulatory requirements in China.

    As described above, plausible alternative scenarios for the proposed project are LFG1, LFG2for LFG utilization and P1, P6 for power generation.

    For LFG1, it is in compliance with all mandatory applicable legal and regulatory requirements

    in China.

    10Notice on Strictly Prohibiting the Installation of Fuel-fired Generation with the Capacity of 135MW

    or below issued by the General Office of the State Council, decree no. 2002-6

    11

    According to page 6 and 7, the FSR of the proposed project, there is no river at the project site, theannual average wind speed is 2.6m/s, its not likely to develop hydro power or wind power project at

    the project site.

  • 8/2/2019 PDD_Guangdong Shenzhen

    13/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 13

    For LFG2, Laohukeng landfill was built in 2002, when Technical code for municipal solid

    waste sanitary landfill (CJJ17-1988, issued on 23 Dec 1998) and Standard for pollution

    control on the landfill site for domestic waste (GB16889-1997, issued on 2 Jul 1997) wereavailable.

    Both regulations specify safety limits for methane concentration in the air and buildings

    around landfill sites and document the procedures of venting LFG to remove the gas from the

    site and disperse it safely into the atmosphere. They also suggest that LFG should be flared or

    where possibly utilized.

    However, due to the significant financial and technical difficulties widely recognized in the

    sector, the activities of methane recovery and flaring/utilization have not been widely

    practiced in China. Although Chinese government encouraged the collection of LFG from

    waste dumps in the past few years, but the fact was still that most of the landfills just vent the

    gas to atmosphere without any exhaust and flaring system, even more than 90% of thousandlandfills in China just simply dump the waste without sanitation filling

    12. It is still a blank

    paper for landfill management to establish landfill gas recovery and utilization systems, as

    quoted from China National Action Plan for Recovery and Utilization of landfill Gas which

    is sponsored by China State Environment Protection Administration (SEPA), together with

    UNDP and GEF.

    Most recently, in Feb 2007, the Ministry of Construction issued a circular on the outcome of

    nationwide inspection on hazard-free treatment of domestic waste landfill sites, concluding

    that the inspection of 372 landfill sites located across 31 provinces, autonomous regions and

    municipalities in China revealed that 92.76% of the landfills have no landfill gas recovery and

    utilization facilities. Among the 372 landfill sites, a total of 237 were constructed after year200013

    . Other landfills, which installed LFG recovery system, were supported by CDM or

    other international supporting scheme.

    On the basis of above evidence, it is justifiable to conclude that atmospheric release of the

    landfill gas is still widespread in China.

    Therefore, LFG2 is a plausible alternative and could be considered as a baseline scenario.

    For P1, it is in compliance with all applicable legal and regulatory requirements in China.

    For P6, it is in compliance with all applicable legal and regulatory requirements in China.

    Outcome of step 2:

    According to the analysis above, the possible combinations of baseline are as follows:

    Table B-2: analysis of the possible baseline options and scenarios combinations

    Power generation P1: Power generated from

    landfill gas undertaken

    without being registered as

    P6: Electricity provided by

    China Southern Power Grid

    12

    http://www.gzuda.gov.cn/news/view.asp?id=XW200302111552083224&fdID=CL2003021115192455

    50&tbCo

    13http://www.huanke.com.cn/08/article.asp?articleid=416

  • 8/2/2019 PDD_Guangdong Shenzhen

    14/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 14

    LFG utilization CDM project activity

    LFG1: The project activity

    undertaken without beingregistered as a CDM project

    activity

    Combination Option 1:

    The proposed projectundertaken without being

    registered as a CDM project

    activity

    Not applicable.

    If the LFG is utilized togenerate electricity and

    replace the electricity from

    the power grid, then this part

    of electricity generation in

    the grid is not necessary

    LFG2: Atmospheric release

    of the landfill gas

    Not applicable.

    If the LFG is directly

    released to atmosphere, then

    no electricity could be

    generated.

    Combination Option 2:

    Atmospheric release of LFG

    and use the electricity from

    grid

    According to the analysis in the table above, the realistic and credible combination baseline

    options can be combination Option 1 and 2:

    Combination Option 1:

    The proposed project is undertaken without being registered as a CDM project activity (LFG1

    + P1).

    Combination Option 2:

    To release LFG from landfill to atmospheric and use the electricity from grid, which is

    business as usual (LFG2 + P6).

    Step 3: Step 2 of the latest approved version of Tool for demonstration and assessment ofAdditionality shall be used to assess which of these alternatives should be excluded from

    further consideration

    Based on the financial analysis illustrated in the following Section B.5., without CER revenue

    taken into account, the after-tax IRR of total investment of the proposed project is lower than

    the benchmark IRR 8%, please see step 2 in B.5. for detailed information. Therefore, if not

    undertaken as a CDM project, the proposed project is not financially attractive. Hence,

    Combination Option 1 is excluded from further consideration.

    Outcome of Step 3:

    Only Combination Option 2 is remained as alternative.

    Step 4: Where more than one credible and plausible alternative remains, project

    participants shall, as a conservative assumption, use the alternative baseline scenario that

    results in the lowest baseline emissions as the most likely baseline scenario.

    This step is not selected due to Combination Option 2 is the only alternative left.

    It can be concluded that the baseline scenario of the project activity is Combination Option 2

    consisting of LFG2 and P6.

    BaselineScenario

    Landfill gas Electricity Heat

    Description of situation

    1 LFG2 P6 N/A The atmospheric release of

    landfill gas or landfill gas

  • 8/2/2019 PDD_Guangdong Shenzhen

    15/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 15

    is partially captured and

    subsequently flared. The

    electricity is obtained fromexisting and/or new grid-

    connected power plants.

    Hence, Combination Option 2 (LFG2 + P6), which is the same as the scenario 1 in the

    methodology ACM0001 is considered as the baseline scenario of the proposed project.

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced

    below those that would have occurred in the absence of the registered CDM project

    activity (assessment and demonstration of additionality):

    >>

    The additionality of the proposed project is demonstrated and assessed by the approved Tool

    for the Demonstration and Assessment of Additionality (Version 05.2). Following steps

    include:

    The following table is the timeline of the proposed project showing that the benefits of CDM

    had been taken into account when making the decision to implement the proposed project.

    Table B-6 Timeline of the proposed project

    Date Key Events Comment

    02/2008 Feasibility Study Report (FSR) developed In the FSR, the

    implementation of CDM

    and CDM revenue had

    been taken intoconsideration to overcome

    the finance

    unattractiveness of the

    project.

    08/10/2008 CDM consultancy contract signed

    05/12/2008 The prior consideration of CDM was

    submitted to NDRC

    08/12/200814

    The notification of prior consideration of

    CDM was approved by NDRC

    17/08/2009 EIA was approved by Shenzhen

    Environment Protection Bureau

    23/09/2009 The project was approved by Shenzhen

    Development and Reform Commission

    08/03/2010 Emission Reduction Purchase Agreement

    signed

    10/03/2010 Pre-treatment and flare system contract

    signed

    Project starting date

    18/03/2010 Power generator purchase contract signed

    22/03/2010 Construction contract signed

    24/03/2010 Loan contract signed

    21/05/2010 Chinese LoA obtained

    14 The date is quoted from project participant, although it is not indicated in the NDRC's approval

    document.

  • 8/2/2019 PDD_Guangdong Shenzhen

    16/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 16

    06/05/2010 Construction started

    03/06/2010 Contract on validation signed

    08/07/2010 The prior consideration of CDM form wassent to UNFCCC secretariat

    03/08/2010 Dutch LoA obtained

    Step 1. Identification of alternatives to the project activity consistent with current laws and

    regulations

    Sub-step 1a. Define alternatives to the project activities:

    Alternatives for the disposal/treatment of the waste in the absence of the project activity,

    i.e. the scenario relevant for estimating baseline methane emissions, to be analysed should

    include, inter alia:

    LFG1: The project activity (i.e. capture of landfill gas and its flaring and/or its use)

    undertaken without being registered as a CDM project activity;

    LFG2: Atmospheric release of the landfill gas or partial capture of landfill gas and

    destruction to comply with regulations or contractual requirements, or to address safety

    and odour concerns.

    If LFG is used for generation of electric or heat energy for export to a grid and/or to a

    nearby industry or used on-site, realistic and credible alternatives should also be separately

    determined for:

    Power generation in the absence of the project activity

    Heat generation in the absence of the project activity.

    For power generation, the realistic and credible alternative(s) may include, inter alia:

    P1: Power generated from landfill gas undertaken without being registered as CDM

    project activity;

    P2: Existing or construction of a new on-site or off-site fossil fuel fired cogeneration

    plant;

    P3: Existing or construction of a new on-site or off-site renewable based cogeneration

    plant;

    P4: Existing or construction of a new on-site or off-site fossil fuel fired captive power

    plant;

    P5: Existing or construction of a new on-site or off-site renewable based captive powerplant;

    P6: Existing and/or new grid-connected power plants.

    For heat generation,

    The proposed project doesnt involve thermal energy generation component. Therefore, all

    the alternatives of heat generation are not considered.

    Sub-step 1b. Enforcement of applicable laws and regulations:

    As analyzed in Section B.4. Sub-step 2, the realistic and credible options can be alternative

    Combination Option 1 and 2:

    Combination Option 1:

    The proposed project undertaken without being registered as a CDM project activity.

  • 8/2/2019 PDD_Guangdong Shenzhen

    17/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 17

    Combination Option 2:

    To release LFG from landfill to atmosphere, and use the electricity from grid, which isbusiness as usual.

    Step 2. Investment analysis

    The purpose of this step is to determine whether the proposed project activity is economically

    or financially less attractive than other alternatives without an additional funding that may be

    derived from the CDM project activities. The investment analysis was conducted in the

    following steps:

    Sub-step 2a. Determine appropriate analysis method

    The three analysis methods suggested by Tools for the demonstration and assessment of

    additionality are simple cost analysis (option I), investment comparison analysis (option II)

    and benchmark analysis (option III). Since the proposed project will earn revenues fromnot only the CDM but also the electricity output the simple cost analysis method is not

    applicable. Investment comparative analysis method is only applicable to the case that

    alternative baseline scenario is similar to the proposed project, so that comparative

    analysis can be conducted. The alternative baseline scenario of the proposed project is the

    China Southern Power Grid rather than a new investment project. Therefore option II is

    not an applicable method either. The proposed project will use benchmark analysis method

    based on Project IRR.

    Sub-step 2b. Apply benchmark analysis (Option III)

    According to Clause 1.11, page 2 of theInterim Rules on Economic Assessment of Electric

    Engineering Retrofit Projects, the financial benchmark IRR of Chinese power industries,including waste-to-energy project is 8% of the total investment, which has been used

    widely for Feasibility Studies of the power project investments.

    Sub-step 2c. Calculation and comparison of financial indicators

    Based on the above-mentioned benchmark, the calculation and comparative analysis of

    financial indicators for the proposed project are carried out in sub-step 2c.

    (1) Basic parameters for calculation of financial indicators

    Based on the Feasibility Study Report of the proposed project, basic parameters for

    calculation of financial indicators are as follows:

    Key parameters for the calculation of financial indicatorsBasic parameters Value Data source

    Installed capacity (MW) 3.18915

    FSR

    Net power supply (MWh) 19,37316

    FSR

    15The installed capacity is 3.189 MW (3*1063kW) at beginning. It will be reduced to 2.126 MW

    (2*1063kW) in the 11th operational year and to 1.063 MW (1*1063kW) in the 17 th operational year

    due to the decrease of LFG generation.

    16 According to the page 24 FSR, the annual total power generation is 21,526MWh for 3 generators

    (3.189MW), 14,351MWh for 2 generators (2.126MW) and 7,175MWh for 1 generator (1.063MW).

    Considering that the capacity of internal loads are about 450kW (page 44, FSR), it is estimated thatauxiliary consumption and transmission loss will account for 10% of the total power generation. The

    net electricity generation is 19,373 MWh at beginning. It will reduce to 12,915 MWh in the 11th

  • 8/2/2019 PDD_Guangdong Shenzhen

    18/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 18

    Tariff(Yuan/kWh) 0.689 (incl. VAT) in

    the initial 15 years;

    0.439 (incl. VAT)after the initial 15

    years.

    FSR17

    Total static investment

    (million Yuan)54.4852

    FSR

    Loan ratio 70% FSR

    Loan interest rate 5.94%Government

    document18

    Depreciation year 13 FSR

    Depreciation rate 7.31%19

    FSR

    Residual value rate 5%20

    FSR

    Project lifetime(year)21 (1 year forconstruction and 20

    years for operation)

    FSR

    Average annual O&M

    (million Yuan)21

    6.02

    FSR

    Tax FSR

    VAT (%) 17% FSR22

    City tax 7% FSR23

    Education tax 3% FSR24

    Income tax (%) 25% FSR25

    operational year and reduce to 6,458 MWh in the 17th

    operational year due to the decrease of power

    generator units. As the sums of the internal loads (450kW) are more than 10% of the installed capacity

    (3.189MW), the 10% auxiliary consumption is conservative.

    17 Based on Tentative Management Measures for Price and Sharing of Expense for Electricity

    Generation from Renewable Energy. The nearby projects include (1) Shenzhen Xiaping Landfill Gas

    Collection and Utilization Project (Ref. 0887), the tariff of which is 0.63Yuan/kWh; (2) Meizhou

    Landfill Gas Recovery and Utilization as Energy (Ref. 0176), the tariff of which is 0.55Yuan/kWh.

    18http://www.pbc.gov.cn/publish/zhengcehuobisi/631/1269/12693/12693_.html, the interest rate

    changed from 7.83% (FSR) to 5.94% when the project started.

    19

    http://www.chinatax.gov.cn/n8136506/n8136593/n8137537/n8138532/8233864.html, which saysthe depreciation year for equipments is no less than 10 years. Industrial enterprises have the right to set

    a number in this range.

    20 Industrial Enterprise Financial Regulation issued by Ministry of Finance, in which the residual rate is

    between 3%-5% (Page 5). Industrial enterprises have the right to set a number in this range.21

    Annual O&M includes Water fee, maintenance, salary and welfare, landfill gas utilization fee, repairfee and miscellaneous cost.

    22 The data is from FSR, which is the same as the value in the active regulation - Provisional

    Regulations on Value Added Tax (Ref. State Council Order 538)

    23http://www.gov.cn/banshi/2005-08/19/content_24817.htm

    24http://www.gov.cn/jrzg/2005-09/24/content_69824.htm

    25 The data is from FSR, which is the same as the value in the active regulation - Income Tax Law (Ref.

    President of P.R China Order [2007] No. 63)

  • 8/2/2019 PDD_Guangdong Shenzhen

    19/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 19

    CER

    Expected CERs Price

    (Euro/tCO2e)

    8.7 Estimated

    Exchange Rate (Yuan/Euro) 9.32 Estimated

    (2) Comparison of IRR for the proposed project and the financial benchmark

    In accordance with the benchmark analysis (Option III), the proposed project will not be

    considered as financially attractive if its financial indicators (such as IRR) are lower than

    the benchmark rate.

    As shown in Table 1, without the CDM revenue, the IRR of total investment is lower than

    the benchmark rate 8%. Thus the proposed project does not look financially attractive to

    the investors. However, with the CDM revenue, IRR of the Project is significantly

    improved and exceeds the benchmark rate. Therefore, the proposed project with the CDMrevenue can be considered as financially viable to the investors.

    Table 1 Financial indicators of the Shenzhen Laohukeng Landfill Gas project

    Project IRR (benchmark = 8%)

    Without CDM revenue -4.14%

    With CDM revenue 27.98%

    Sub-step 2d. Sensitivity analysis (only applicable to options II and III):

    In accordance with the Tool for demonstration and assessment of additionality (Version

    05.2), the objective of sensitivity analysis is to examine whether the conclusion regarding the

    financial attractiveness is robust to reasonable variations in the critical assumption. Theinvestment analysis provides a valid argument in favor of additionality only if consistently

    supports (for a realistic range of assumptions) the conclusion that the project activity is

    unlikely to be the most financially attractive or is unlikely to be least financially attractive.

    According to Guidance on the Assessment of Investment Analysis (Version 03.1), only

    variables, including the initial investment cost, that constitute more than 20% of either total

    project costs or total project revenues should be subjected to reasonable variation. Therefore,

    four parameters of the total static investment, annualO&M cost, net power supply and

    tariffwere identified as the main variable factors for the proposed project.

    The critical factors that influence the Project IRR are mainly as follows:

    1) Total static investment;

    2) Annual O&M cost;

    3) Net power supply;

    4) Tariff

    Table 2 Fluctuation rates of parameters when the project IRR reaches to 8%

    Total static investment O&M cost Tariff Net power supply

    -43.1% -38.3% 34.8% 34.8%

  • 8/2/2019 PDD_Guangdong Shenzhen

    20/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 20

    For all four parameters, it is unlikely to increase or decrease to the point the project IRR reach

    the benchmark. The detail analysis is as follows:

    Total static investment

    The total static investment needs to decrease by 43.1% when the project IRR meets the

    benchmark of 8%. However, the contracted investment by July 2010 has summed up to

    70.60%26

    of total static investment. Therefore, the total static investment is not likely to

    decrease by 43.1% to exceed benchmark.

    O&M cost

    The O&M cost needs to decrease by 38.3% when the project IRR meets the benchmark of 8%.

    According to the FSR of the proposed project, the O&M cost is the sum of the repair cost,

    maintenance cost, material charge, salary and welfare, LFG utilization fee and miscellaneouscost, each of the above cost is calculated by some fixed parameters such as the installed

    capacity, the normal standard for utilization of equipments etc. Furthermore, according to the

    China Statistic Yearbook 2009 (http://www.stats.gov.cn/tjsj/ndsj/2009/indexch.htm), the

    Producer Price Index for Manufactured Goods from the year 2004 to 2008 was 106.1, 104.9,

    103.0, 103.1 and 106.9 respectively, which indicated that the operation and maintenance cost

    is always increasing. So annual O&M cost is unlikely to decrease by more than 38.3%.

    Tariff

    The tariff needs to increase by 34.8% when the project IRR meets the benchmark of 8%.According to the Tentative Management Measures for Price and Sharing of Expense for

    Electricity Generation from Renewable Energy issued by the NDRC on 05/01/2006, the

    electricity tariff for landfill gas utilization power plant is fixed to be the provincial

    desulphurization coal-fired power plant benchmark tariff in 2005 plus the subsidy tariff,

    which is 0.25RMB/kWh during the initial 15 years. And the subsidy tariff will be cancelled

    after 15 years.

    The desulphurization coal-fired power plant benchmark tariff in Guangdong province in 2005

    was 0.439RMB/kWh (source: http://china.em51.com/news/shownews.asp?id=1848). So, the

    tariff of the proposed project is 0.689 RMB/kWh (0.439+0.25=0.689) during the initial 15

    years and 0.439RMB/kWh after the initial 15 years. In addition, the tariff of similar LFG

    projects shown in Table 3 ranges in 0.42-0.63 RMB/kWh27

    . Therefore, the tariff of theproposed project is unlikely to reach that high level.

    Net power supply

    26The contracted investment has summed up to be 38.47 million RMB by the day of onsite interview,

    July 19, 2010. The contracts have been provided to DOE for validation.

    27http://cdm.unfccc.int/Projects/DB/DNV-CUK1135170125.82/view(Ref. 0176);

    http://cdm.unfccc.int/Projects/DB/SGS-UKL1169636952.02/view(Ref. 0887);http://cdm.unfccc.int/Projects/DB/JCI1175576815.21/view(Ref.1075);

    http://www.netinform.net/KE/files/pdf/Huizhou_Landfill_Gas_CDM_PDD_ACM0001.pdf

  • 8/2/2019 PDD_Guangdong Shenzhen

    21/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 21

    The net power supply needs to increase by 34.8% when the project IRR meets the benchmark

    of 8%, which puts the annual operating hour as high as 9099 hours. Considering that there are

    totally 8760 hours in one year, this increase is impossible to happen. Hence, the net powersupply is impossible to increase by 34.8% to make the project IRR reach the 8% benchmark.

    The auxiliary consumption and power loss was estimated to be 10% of the total power

    generation. As the sums of the internal loads (450kW)28

    were more than 10% of the installed

    capacity (3.189MW), the 10% auxiliary consumption is conservative. Moreover, even

    assuming that the auxiliary consumption and power loss was 0, the project IRR is 1.59%, still

    much lower than the 8% benchmark.

    In conclusion of the sensitive analysis, as the financial indicators vary within reasonable range,

    the proposed project remains financially unattractive without CDM support and the proposed

    project is additional. Hence, the Scenario 1) is not a realistic alternative.

    Step 3: Barrier analysis

    Not applicable (Only Step 2 is selected).

    Step 4. Common practice analysis

    Sub-step 4a. Analyze other activities similar to the proposed project activity:

    In China, the investment climate (e.g. with regards to taxes, loan policy and electricity tariffs)

    is only similar and comparable in the same province. Therefore, the common practice region

    and comparable framework is provincial and the proposed project is compared to other

    projects in Guangdong Province.

    In April 2002, China implemented the policy "Separate power plants from network and

    compete in price to enter network29

    The objective of this power sector reform is to establish a

    more commercialized power market in China. Power project investment has to be under a

    more commercialized condition and considers project investment return more seriously. Since

    market condition for power generation project development changes much since April 2002,

    this common practice analysis starts from April 2002.

    For the proposed project, LFG is collected and used to produce electricity energy, the similar

    activities including those LFG collection and destruction (for power generation, thermal

    energy production or simply flared) projects.

    According to Summary of Urban Garbage Disposal Industry Development in 2007, Tentative

    Study on Future Market of Power Generation by Landfill Gas (LFG)30 and other related

    sources, the similar projects are list in the following table:

    Table 3 similar LFG utilization projects in Guangdong province

    No. Project title Remark

    1 Guangzhou Datianshan Landfill Gas Utilization Project31

    Sino-foreign

    28Source: page 44, FSR of the proposed project.

    29China implemented the policy "Separate power plants from network and compete in price to enter

    network"

    30Huang Xi, Nonferrous Metals Engineering & Research, 2009 (12): 80-83

  • 8/2/2019 PDD_Guangdong Shenzhen

    22/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 22

    cooperative project &

    Built and operated in

    1999.2 Meizhou Landfill Gas Recovery and Utilization as Energy CDM

    (Ref. 0176)

    3 Shenzhen Xiaping Landfill Gas Collection and Utilization

    Project

    CDM

    (Ref. 0887)

    4 Guangzhou Xingfeng Landfill Gas Recovery and Electricity

    Generation CDM Project

    CDM

    (Ref. 1075)

    5 Huizhou Landfill Gas Recovery and Utilization Project32 CDM

    (Under validation)

    Sub-step 4b. Discuss any similar options that are occurring:

    Based on the table above, there are totally five similar projects, four of which are CDM

    project activities with 3 registered (No. 2 - 4) and one under validation (No. 5). These projects

    are not to be included in this analysis.

    The Guangzhou Datianshan Landfill Gas Utilization Project (No. 1) was the first LFG

    utilization project in China and was a sino-foreign cooperative project operated by foreign

    company in 199933. It was a public funding assistance project and project built and operated

    before April 2002, enjoying advantage in access to financing and faced different investment

    climate.

    In a word, landfill gas utilization project is not common practise in Guangdong province.

    In conclusion, the proposed project is additional and the project owner considered applying

    for CDM project to overcome the difficulties before the construction of the proposed project.

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    >>

    According to ACM0001, the emission reduction of the proposed project is calculated as

    follows:

    Baseline emissions

    yBLtheryLFGyBLelecyLFGCHyBLyprojecty CEFETCEFELGWPMDMDBE ,,,,,,4,, ** (1)

    Where:

    BEy = Baseline emissions in yeary (tCO2e)

    MDproject,y = The amount of methane that would have been destroyed/combusted

    during the year, in tonnes of methane (tCH4) in project scenario

    31 http://solidwaste.chinaep-tech.com/landfill-gas-power/33196.htm

    32

    http://cdm.unfccc.int/Projects/Validation/DB/FPXFSQIQTJDSN5X0QLJX13RZ55K8RW/view.html

    33 Reference: Comprehensive Utilization of Landfill Gas by Huang Xiaowen and Wu Sanda,

    Environmental Sanitation Engineering, 2006 (8):9 - 11

  • 8/2/2019 PDD_Guangdong Shenzhen

    23/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 23

    MDBL,y = The amount of methane that would have been destroyed/combusted

    during the year in the absence of the project due to regulatory

    and/or contractual requirement, in tonnes of methane (tCH4)GWPCH4 = Global Warming Potential value for methane for the first

    commitment period is 21 tCO2e/tCH4

    ELLFG,y = Net quantity of electricity produced using LFG, which in the

    absence of the project activity would have been produced by power

    plants connected to the grid or by an on-site/off-site fossil fuel

    based captive power generation, during year y, in megawatt hours

    (MWh)

    CEFelec,BL,y = CO2 emissions intensity of the baseline source of electricity

    displaced, in tCO2e/MWh. This is estimated as per equation (9)

    below

    ETLFG,y = The quantity of thermal energy produced utilizing the landfill gas,

    which in the absence of the project activity would have beenproduced from onsite/offsite fossil fuel fired boiler, during the year

    y in TJ

    CEFther,BL,y = CO2 emissions intensity of the fuel used by boiler to generate

    thermal energy which is displaced by LFG based thermal energy

    generation, in tCO2e/TJ. This is estimated as per equation (10)

    below

    Step 1: Calculation of MDBL,y

    In cases where regulatory or contractual requirements do not specifyMDBL,y or no historic

    data exists for LFG captured and destroyed an Adjustment Factor (AF) shall be used andjustified, taking into account the project context:

    AFMDMD yprojectyBL *,, (2)

    LFG utilization to energy is not common practice in South China until very recently.

    According to ERMs survey, currently less than 5% landfill sites in China have LFG

    collection and flaring schemes and even less have gas utilization facilities34

    .

    Based on the description above, the LFG recovery and utilization is not common in South

    China. They are mainly released to atmosphere without any treatment.

    Hence, the value of AF is set as 0% according to ACM0001 that no quantity of methane

    would be destroyed without the project activity and will be monitored during the whole

    crediting period. Consequently, MDBL,y is zero according to equation (2).

    Step 2: Calculation of MDproject,y

    The methane destroyed by the project activity (MDproject,y) during a year is determined by

    monitoring the quantity of methane actually flared and gas used to generate electricity and/or

    produce thermal energy and/or supply to end users via natural gas distribution pipeline, if

    applicable, and the total quantity of methane captured.

    34

    Reference: CDM Umbrella Guidelines for MSW in China(http://www.frankhaugwitz.info/doks/cdm/2004_05_19_China_CDM_MSW_Guidelines_Final_Draft_

    WB.pdf ).

  • 8/2/2019 PDD_Guangdong Shenzhen

    24/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 24

    The sum of the quantities fed to the flare(s), to the power plants(s), to the boiler(s) and to the

    natural gas distribution network (estimated using equation (3)) must be compared annuallywith the total quantity of methane generated. The lowest value of the two must be adopted as

    MDproject,y.

    The following procedure applies when the total quantity of methane generated is the highest.

    The working hours of the energy plants(s) and the boiler(s) should be monitored and no

    emission reduction could be claimed for methane destruction in the energy plant or the boiler

    during non-operational hours.

    yPLythermalyyelectricityflaredyproject MDMDMDMDMD ,,,,, (3)

    Where:

    MDflared,y = Quantity of methane destroyed by flaring (tCH4)MDelectricity,y = Quantity of methane destroyed by generation of electricity (tCH4)

    MDthermal,y = Quantity of methane destroyed for the generation of thermal energy

    (tCH4)

    MDPL,y = Quantity of methane sent to the pipeline for feeding to the natural gas

    distribution network (tCH4)

    According to the proposed project activity, in the case that the power generation units are

    under maintenance and/or landfill gas captured exceed the demand for power generation, the

    remaining part of the landfill gas will be fed into a flare to be destructed. Therefore, the

    annual amount of methane destruction by flaring can be estimated by the following formula:

    4,4,4,, /** CHyflareCHyCHyflareyflared GWPPEDwLFGMD (4)Where:

    LFGflare,y = Quantity of landfill gas fed to the flare(s) during the year measured in

    cubic meters (m3)

    wCH4,y = Average methane fraction of the landfill gas as measured during the year

    and expressed as a fraction (in m3

    CH4/m3

    LFG)

    DCH4 = Methane density expressed in tonnes of methane per cubic meter of

    methane (tCH4/m3CH4)

    PEflare,y = Project emissions from flaring of the residual gas stream in year y

    (tCO2e) determined following the procedure described in the Tool to

    determine project emissions from flaring gases containing Methane. If

    methane is flared through more than one flare, the PEflare,yshall bedetermined for the flare using the tool

    According to the description in Tool to determine project emissions from flaring gases

    containing Methane, the project emission from flaring gases is calculated as follows:

    1000)1( 4,

    ,

    8760

    1

    ,CH

    hflare

    hRGh

    yflare

    GWPTMPE

    (5)

    Where:

    PEflare,y = Project emissions from flaring of the residual gas stream in yeary

    (tCO2e)

    TMRG,h = Mass flow rate of methane in the residual gas in the hourh (kg/h)flare,h = Flare efficiency in hourh

  • 8/2/2019 PDD_Guangdong Shenzhen

    25/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 25

    GWPCH4 = Global Warming Potential of methane valid for the commitment period

    According to tool to determine project emissions from flaring gases containing methane, incase of enclosed flares and use of the default value for the flare efficiency, the flare efficiency

    in the hour h (flare,h) is 90%, if the temperature in the exhaust gas of the flare (Tflare) is

    above 500 for more than 40 minutes during the hour h and the manufacturers

    specifications on proper operation of the flare are met continuously during the hour h.

    According to the technical specifications provided by the manufacture of the flare equipment,

    the combustion temperature of the flare ranges from 600 to 1200, which is above 500

    . Hence, the default value of 90% is selected. The quantity of methane flow rate in the

    residual gas flowing into the flare is calculated as following:

    nCHhRGCHhRGhRG fvFVTM ,4,,4,, (6)

    Where:

    TMRG,h = Mass flow rate of methane in the residual gas in the h (kg/h)

    FVRG,h = Volumetric flow rate of the residual gas in dry basis at normal conditions in

    hourh (m3/h)

    fvCH4,RG,h = Volumetric fraction of methane in the residual gas on dry basis in hourh

    CH4,n = Density of methane at normal conditions (0.716 kg/m3)

    The volumetric fraction of the methane in the residual gas is equal to the volumetric fraction

    of the methane measured in gas analyzer G.

    For the ex-ante estimation of proposed project, the values ofFVRG,handfvCH4,RG,h are constant

    yearly ignoring the hourly change.

    The annual amount methane destruction in power plant can be estimated by the following

    formula:

    4,4,, CHyCHyyelectricityyelectricit DwLFGMD (7)

    Where:

    MDelectricity,y = Quantity of methane destroyed by generation of electricity

    wCH4,y = Volumetric fraction of methane in LFG

    LFGelectricity,y = Quantity of landfill gas fed into electricity generator

    DCH4 = Density of methane at normal conditions

    According to FSR, the methane fraction of the same kind of landfill gas in China ranges in

    40%-60%, with mostly greater than 50%. Therefore, the wCH4,y of the proposed project is set

    to be 50% . According to Tool to determine methane emissions avoided from disposal of

    waste at a solid waste disposal site, DCH4 is 0.0007168 tCH4/m3CH4 at 0 and 1013 bar.

    The proposed project doesnt involve heat generation component and feeding to the natural

    gas distribution network component, therefore MDthermal,y and MDPL,y is set as 0.

    Ex-ante estimation of the amount of methane that would have been destroyed/combusted

    during the year, in tonnes of methane (MDproject,y)

    The ex-ante estimation of the amount of methane that would have been destroyed/combusted

    during the year, in tonnes of methane (MDproject,y) will be done with the latest version of the

  • 8/2/2019 PDD_Guangdong Shenzhen

    26/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 26

    approved Tool to determine methane emissions avoided from disposal of waste at a solid

    waste disposal site, considering the following additional equation:

    4,,4, / CHySWDSCHyproject GWPBEMD (8)

    Where:

    BECH4,SWDS,y = Methane generation from the landfill in the absence of the project

    activity at year y (tCO2e), calculated as per the Tool to determine

    methane emissions avoided from disposal of waste at a solid waste

    disposal site. The tool estimates methane generation adjusted for, using

    adjustment factor (f) any landfill gas in the baseline that would have been

    captured and destroyed to comply with relevant regulations or

    contractual requirements, or to address safety and odor concerns. As this

    is already accounted for in equation 2, f in the tool shall be assigned avalue 0

    Furthermore the following guidance should be taken into account:

    In the tool x will refer to the year since the landfill started receiving wastes [x

    runs from the first year of landfill operation (x=1) to the year for which

    emissions are calculated (x=y)];

    Sampling to determine the different waste types is not necessary, the waste

    composition can be obtained from previous studies.

    The efficiency of the degassing system which will be installed in the project activity should

    be taken into account while estimating the ex-ante estimation.

    The landfill gas collection system will not collect 100% of the gas from the landfill site.According to the FSR, 40% of the landfill gas will be collected when the landfill is open and

    50% when it is closed. Therefore, as a conservative measure we will use this collection

    efficiency for the emission reduction estimations.

    The amount of methane that would in the absence of the project activity be generated from

    disposal of waste at the solid waste disposal site (BECH4,SWDS,y) is calculated with a multi-phase

    model. The calculation is based on a first order decay (FOD) model recommended by the

    Revised 2006 IPCC Guideline for National Greenhouse Gas Inventory. The model

    differentiates between the different types of wastej with respectively different decay rates kj

    and different fractions of degradable organic carbon (DOCj). The model calculates the

    methane generation based on the actual waste streams Wj,x disposed in each yearx, starting

    with the first year after the start of the project activity until the end of the yeary, for which

    baseline emissions are calculated (years x with x = 1 to x = y).

    According to the Tool to determine methane emissions avoided from disposal of waste at a

    solid waste disposal site, the amount of methane produced in the yeary (BECH4,SWDS,y) is

    calculated as follows:

    y

    x j

    kxyk

    jxjfCHySWDSCH

    jj eeDOCWMCFDOCFOXGWPfBE1

    )(

    ,4,,4 )1(12

    16)1()1(

    (9)

    Where:BECH4,SWDS,y = Methane emissions avoided during the yeary from preventing waste

  • 8/2/2019 PDD_Guangdong Shenzhen

    27/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 27

    disposal at the solid waste disposal site (SWDS) during the period from

    the start of the project activity to the end of the year y (tCO2e)

    = Model correction factor to account for model uncertainties (0.9)f = Fraction of methane captured at the SWDS and flared, combusted or

    used in another manner

    GWPCH4 = Global Warming Potential (GWP) of methane, valid for the relevant

    commitment period

    OX = Oxidation factor (reflecting the amount of methane from SWDS that is

    oxidised in the soil or other material covering the waste)

    F = Fraction of methane in the SWDS gas (volume fraction) (0.5)

    DOCf = Fraction of degradable organic carbon (DOC) that can decompose

    MCF = Methane correction factor

    Wj,x = Amount of organic waste typej prevented from disposal in the SWDS in

    the yearx (tons)

    DOCj = Fraction of degradable organic carbon (by weight) in the waste typej

    kj = Decay rate for the waste typej

    j = Waste type category (index)

    x = Year during the crediting period: x runs from the first year of the firstcrediting period (x = 1) to the year y for which avoided emissions arecalculated (x = y)

    y = Year for which methane emissions are calculated

    Step 3: Determination of CEFelec,BL,yIn case the baseline is electricity generated by plants connected to the grid the emission factor

    should be calculated according to Tool to calculate the emission factor for an electricity

    system.

    Therefore,

    yCMgridyBLelec EFCEF ,,,, (10)

    This methodological tool Tool to calculate the emission factor for an electricity

    system(version 02) determines the CO2 emission factor for the displacement of electricity

    generated by power plants in an electricity system, by calculating the operating margin

    (OM) and build margin (BM) as well as the combined margin (CM). The operating

    margin refers to a cohort of power plants that reflect the existing power plants whose

    electricity generation would be affected by the proposed CDM project activity. The buildmargin refers to a cohort of power units that reflect the type of power units whose

    construction would be affected by the proposed CDM project activity.

    The Tool to calculate the emission factor for an electricity system provides procedures to

    determine the following parameters:

    Parameter SI Unit Description

    EFgrid,CM,y tCO2/MWh Combined margin CO2 emission factor for the project electricity

    system in year y

    EFgrid,BM,y tCO2/MWh Build margin CO2 emission factor for the project electricity system in

    year yEFgrid,OM,y tCO2/MWh Operating margin CO2 emission factor for the project electricity

  • 8/2/2019 PDD_Guangdong Shenzhen

    28/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 28

    system in year y

    The following seven steps are applied to calculate the emission factor for an electricity system:STEP 1: Identify the relevant electricity system.

    STEP 2: Choose whether to include off-grid power plants in the project electricity system

    (optional)

    STEP 3: Select a method to determine the operating margin (OM).

    STEP 4: Calculate the operating margin emission factor according to the selected method.

    STEP 5: Identify the group of power units to be included in the build margin (BM).

    STEP 6: Calculate the build margin emission factor.

    STEP 7: Calculate the combined margin (CM) emissions factor.

    Step 1: Identify the relevant electricity system

    The DNA of the host country has published a delineation of the project electricity system and

    connected electricity systems, this delineation is used. Following the DNA delineation, the

    project electricity system is the China Southern Power Grid (SCPG), which consists of

    Guangdong Province, Guangxi Autonomous Region, Yunnan Province and Guizhou Province

    Power Grids.

    For the purpose of determining the operating margin emission factor, use one of the following

    options to determine the CO2 emission factor(s) for net electricity imports (EFgrid,import,y) from

    a connected electricity system within the same host country(ies):

    (a) 0 tCO2/MWh, or

    (b) The weighted average operating margin (OM) emission rate of the exportinggrid, determined as described in step 4 (d) below; or

    (c) The simple operating margin emission rate of the exporting grid, determinedas described in step 4 (a), if the conditions for this method, as described in

    step 3 below, apply to the exporting grid; or

    (d) The simple adjusted operating margin emission rate of the exporting grid,determined as described in step 4 (b) below.

    The option (c) is selected to calculate the CO2 emission factor for net electricity imports

    (EFgrid,import,y) from other power grid.

    Step 2. Choose whether to include off-grid power plants in the project electricity system

    (optional)

    According to the Approval of electricity connection to China Southern Power Grid, all the

    power generated by the project activity will be supplied to the power grid company. Thus, the

    proposed project does not include off-grid power plants in the project electricity system

    referred in apply to Tool to calculate the emission factor for an electricity system.

    Step 3. Select a method to determine the operating margin (OM)

    The calculation of the operating margin emission factor (EFgrid,OM,y) is based on the

    following methods:

    (a) Simple OM, or

  • 8/2/2019 PDD_Guangdong Shenzhen

    29/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 29

    (b) Simple adjusted OM, or

    (c) Dispatch Data Analysis OM, or

    (d) Average OM.

    Any of the four methods can be used, however, the simple OM method (option a) can only be

    used if low-cost/must-run resources constitute less than 50% of total grid generation in: 1)

    average of the five most recent years, or 2) based on long-term averages for hydroelectricity

    production.

    SCPG only possesses 26.726% of its total electricity generation that comes from renewable

    energy sources in 2007, 26.292% in 2006, 30.938% in 2005, 29.912% in 2004, 41.752% in

    2003, 32.938% in 2002 and 33.705% in 200135

    .Hence, the low operating cost/must run

    sources is much less than 50% of the total grid generation, which accords with the definedcondition of Option (a), but not Option (d). Consequently, Option (a) is selected to calculate

    the operating margin emission factor of the proposed project.

    For the simple OM, the simple adjusted OM and the average OM, the emissions factor can be

    calculated using either of the two following data vintages:

    Ex ante option: If the ex ante option is chosen, the emission factor is determinedonce at the validation stage, thus no monitoring and recalculation of the

    emissions factor during the crediting period is required. For grid power plants,

    use a 3-year generation-weighted average, based on the most recent data

    available at the time of submission of the CDM-PDD to the DOE for validation.

    For off-grid power plants, use a single calendar year within the 5 most recentcalendar years prior to the time of submission of the CDM-PDD for validation

    Ex post option: If the ex post option is chosen, the emission factor is determinedfor the year in which the project activity displaces grid electricity, requiring the

    emissions factor to be updated annually during monitoring. If the data required to

    calculate the emission factor for year y is usually only available later than six

    months after the end of year y, alternatively the emission factor of the previous

    year (y-1) may be used. If the data is usually only available 18 months after the

    end of yeary, the emission factor of the year proceeding the previous year (y-2)

    may be used. The same data vintage (y, y-1 or y-2) should be used throughout all

    crediting periods.

    The data vintage chosen should be documented in the CDM-PDD and not be changed during

    the crediting periods.

    The ex-ante option is selected for the proposed project and the three most recent years

    available at the time of submission of the CDM-PDD to the DOE for validation are 2005-

    2007.EFgrid,OM,y is fixed during the first crediting period.

    Step 4. Calculate the operating margin emission factor according to the selected method

    The Simple OM emission factor is calculated as the generation-weighted average CO2

    emissions per unit net electricity generation (tCO2/MWh) of all generating power plants

    35China Electric Power Yearbook, 2002-2008

  • 8/2/2019 PDD_Guangdong Shenzhen

    30/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 30

    serving the system, not including low-cost / must-run power plants / units. The simple OM

    may be calculated:

    Option A: Based on the net electricity generation and a CO2 emission factor of eachpower unit, or

    Option B: Based on the total net electricity generation of all power plants servingthe system and the fuel types and total fuel consumption of the project electricity

    system.

    For the proposed project activity, the required data for the exercise of Option A is not

    available and those of Option B can be obtained from official sources, and off-grid power

    plants are not included in the calculation, therefore, Option B is chosen to calculate the

    operating margin emission factor:

    For Option B, the Simple OM emission factor is calculated based on the net electricity

    supplied to the grid by all power plants serving the system, not including low-cost / must-run

    power plants / units, and based on the fuel type(s) and total fuel consumption of the project

    electricity system.

    Option B Calculation based on total fuel consumption and electricity generation of the

    system

    Under this option, the simple OM emission factor is calculated based on the net electricity

    supplied to the grid by all power plants serving the system, not including low-cost / must-run

    power plants / units, and based on the fuel type(s) and total fuel consumption of the projectelectricity system, as follows:

    y

    yiCOyi

    i

    yi

    yOMsimplegridEG

    EFNCVFC

    EF,,,,

    ,,

    2

    (11)

    Where:

    EFgrid,OMsimple,y = Simple operating margin CO2 emission factor in yeary (tCO2/MWh)

    FCi,y = Amount of fossil fuel type i consumed in the project electricity system

    in yeary (mass or volume unit)

    NCVi,y = Net calorific value (energy content) of fossil fuel type i in yeary (GJ /mass or volume unit)

    EFCO2,i,y = CO2 emission factor of fossil fuel type i in yeary (tCO2 /GJ)

    EGy = Net electricity generated and delivered to the grid by all power sources

    serving the system, not including low-cost / must-run power plants /

    units, in yeary (MWh)

    i = All fossil fuel types combusted in power sources in the project

    electricity system in yeary

    y = The relevant year as per the data vintage chosen in Step 3

    Step 5. Identify the group of power units to be included in the build margin

    The sample group of power units m used to calculate the build margin consists of either:

    (a) The set of five power units that have been built most recently, or

  • 8/2/2019 PDD_Guangdong Shenzhen

    31/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 31

    (b) The set of power capacity additions in the electricity system that comprise 20%

    of the system generation (in MWh) and that have been built most recently.

    Project participants should use the set of power units that comprises the larger annual

    generation.

    However, it is very difficult to obtain the data of the five power plants built most recently

    because these data are considered as confidential information by the company itself and the

    Grid in China. Therefore, a deviation36

    approved by the EB is applied here in the calculation

    that is to calculate the new capacity additions and the proportion of each technology of power

    generation. Then the weighing of capacity additions of different technologies will be worked

    out. Finally the emission factor will be calculated by employing the efficiency factor

    representing the best technology commercially available.

    In terms of vintage of data, project participants can choose between one of the following two

    options:

    Option 1. For the first crediting period, calculate the build margin emission factor ex-ante

    based on the most recent information available on units already built for sample group m at

    the time of CDM-PDD submission to the DOE for validation. For the second crediting period,

    the build margin emission factor should be updated based on the most recent information

    available on units already built at the time of submission of the request for renewal of the

    crediting period to the DOE. For the third crediting period, the build margin emission factor

    calculated for the second crediting period should be used. This option does not require

    monitoring the emission factor during the crediting period.

    Option 2. For the first crediting period, the build margin emission factor shall be updated

    annually, ex-post, including those units built up to the year of registration of the project

    activity or, if information up to the year of registration is not yet available, including those

    units built up to the latest year for which information is available. For the second crediting

    period, the build margin emissions factor shall be calculated ex-ante, as described in option 1

    above. For the third crediting period, the build margin emission factor calculated for the

    second crediting period should be used.

    For the proposed project, Option 1 is chosen to calculate build margin emission factor.

    Step 6. Calculate the build margin emission factorThe build margin emission factor is the generation-weighted average emission factor

    (tCO2/MWh) of all power units m during the most recent yeary for which power generation

    data is available, calculated as follows:

    m

    ym

    m

    ymELym

    yBMgridEG

    EFEG

    EF,

    ,,,

    ,, (12)

    Where:

    36Source: http://cdm.unfccc.int/Projects/Deviations/index.html?p=3

  • 8/2/2019 PDD_Guangdong Shenzhen

    32/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 32

    EFgrid,BM,y = Build margin CO2 emission factor in yeary (tCO2/MWh)

    EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m in yeary

    (MWh)EFEL,m,y = CO2 emission factor of power unit m in yeary (tCO2/MWh)

    m = Power units included in the build margin

    y = Most recent historical year for which power generation data is available

    No matter which options for calculating BM factor mentioned in Step 5 was adopted for the

    proposed project; the same issue on data availability must be addressed. Currently, it is very

    difficult to get the capacity margin data of power plants in China, since these data as well as

    net quantity of electricity generated and delivered to the grid and fuel consumption data in

    power unit m are regarded as commercial secrets or only for internal usage. The following

    deviation was adopted to calculate the Build Margin emission factor.

    Sub-step 1: With the energy balance sheet in China Energy Statistical Yearbook for the

    most recent year, calculating the respective percentages of CO2 emissions from coal fired

    power generation, oil fired power generation, and gas fired power generation against total

    CO2 emissions from fossil fuel fired power generation:

    ji

    yiCOyiyji

    jCOALi

    yiCOyiyji

    yCoalEFNCVF

    EFNCVF

    ,

    ,,,,,

    ,

    ,,,,,

    ,

    2

    2

    (13)

    ji

    yiCOyiyji

    jOILi

    yiCOyiyji

    yOilEFNCVF

    EFNCVF

    ,

    ,,,,,

    ,

    ,,,,,

    ,

    2

    2

    (14)

    ji

    yiCOyiyji

    jGASi

    yiCOyiyji

    yGasEFNCVF

    EFNCVF

    ,

    ,,,,,

    ,

    ,,,,,

    ,

    2

    2

    (15)

    Where:

    Fi,j,y = The amount of fuel i (in a mass or volume unit)consumed in provincej in year y;

    NCVi,y = Net calorific value (energy content) of fossil fuel type i (GJ/mass or volume unit) in

    year y;EFCO2,i = CO2 emission factor of fossil fuel typeIin year y (tCO2/GJ)

    COAL, OIL and GAS are aggregation of various kinds of coal, oil and gas as fossil fuels.

    Sub-step 2: Calculation of emission factor of relevant thermal power

    yAdvGasGasyAdvOilOilyAdvCoalCoalyThermal EFEFEFEF ,,,,,,, (16)

    Where:

    EFCoal,Adv,y, EFOil,Adv,y and EFGas,Adv,y refer to the emission factors representing best

    technologies commercially available for coal, oil and gas fired power plants, respectively.(See Annex 3 for detailed calculation).

  • 8/2/2019 PDD_Guangdong Shenzhen

    33/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 33

    i,

    , , 6,

    3.6

    10

    y

    Coal Adv ybest coal

    NCV OXIDEF

    GENE

    (17)

    i,

    , , 6, /

    3.6

    10

    y

    Oil Adv ybest oil gas

    NCV OXIDEF

    GENE

    (18)

    i,

    , , 6, /

    3.6

    10

    y

    Gas Adv ybest oil gas

    NCV OXIDEF

    GENE

    (19)

    Where:

    ,best coalGENE and , /best oil gasGENE refer to the optimum commercial, coal, oil and gas fired

    power supply efficiency.

    OXID refers to Carbon Oxidation Factor of fossil fuel type i consumed by the power plantsin the China Southern Power Grid.

    Use the share of different type of capacity in total capacity addition as weight, the weighted

    average of emission factors of different type capacity is calculated as the Build Margin

    emission factorEFgrid,BM,y of China Southern Power Grid(see Annex 3 for detailed calculation):

    Sub-step 3: Calculation of BM of the Grid

    yThermal

    yTotal

    yThermal

    yBMgrid EFCAP

    CAPEF ,

    ,

    ,

    ,, (20)

    Where:

    CAPTotal,y = The total newly added electricity generation capacity (MW)

    CAPThermal,y = The newly added electricity generation capacity of thermal power (MW)

    Step 7. Calculate the combined margin emission factor

    The combined margin emission factor is calculated as follows:

    BMyBMgridOMyOMgridyCMgrid wEFwEFEF ,,,,,, (21)

    Where:

    EFgrid,BM,y = Build margin CO2 emission factor for the project electricity system in yeary

    (tCO2/MWh)

    EFgrid,OM,y = Operating margin CO2 emission factor for the project electricity system in yeary(tCO2/MWh)

    wOM = Weighting of operating margin emissions factor (%)

    wBM = Weighting of build margin emissions factor (%)

    For the proposed project, the default values of wOM and wBM are:

    wOM = wBM = 0.5 for the first crediting period.

    The default weights are adopted for the proposed project, the baseline emission factor is:

    BMyBMgridOMyOMgridyCMgrid wEFwEFEF ,,,,,,

    = 0.9987 0.5 + 0.5772 0.5 = 0.78795tCO2/MWh

    Step d: Calculation of ETLFG,yBecause the proposed project doesnt involve heat component, ETLFG,y is assumed to be zero.

  • 8/2/2019 PDD_Guangdong Shenzhen

    34/81

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

    CDM Executive Boardpage 34

    Project Emissions

    Considering when electricity generators will be under regular maintenance and sometimesshut down, the electricity will be purchased form the SCPG during this period of time.

    Therefore, there will be project emissions and calculated following the latest version of Tool

    to calculate project emissions from electricity consumption.

    yjFCyECy PEPEPE ,,, (22)

    Where:

    PEEC,y = Emissions from consumption of electricity in the project case. The project emissions

    from electricity consumption (PEEC,y) will be calculated following the latest version

    of Tool to calculate baseline, project and/or leakage emissions from electricity

    consumption. If in the baseline a part of LFG was captured then the electricityquantity used in calculation is electricity used in project activity net of that

    consumed in the baseline.

    PEFC,j,y = Emissions from consumption of heat in the project case. The project emissions from

    fossil fuel combustion (PEFC,j,y ) will be calculated following the latest version of

    Tool to calculate project or leakage CO2 emissions from fossil fuel combustion.

    For this purpose, the processes j in the tool corresponds to all fossil fuel combustion

    in the landfill, as well as any other on-site fuel combustion for the purposes of the

    project activity. If in the baseline part of a LFG was captured then the heat quantity

    used in calculation is fossil fuel used in project activity net of that consumed in the

    baseline.

    In the project design stage, the electricity consumption of electricity in the proposed project(PEEC,j,y) is very small and can be neglected, so it is set