marsh insights: lng fsrus – a guide to risk and...
TRANSCRIPT
Marsh InsIghts:
lng FSRUS – A gUide to RiSk And inSURAnce
deceMBeR 2012
Marsh is a leading broker and risk adviser for FSRU projects.
the energy industry is evolving. As the costs of traditional energy sources increase, so too will the demand for alternative sources. Many nations are reluctant to use nuclear energy, so a significant proportion of surplus demand will need to be met through new sources of cheap, clean-burning natural gas. Some sources suggest that global gas demand will grow by 50% before 2030. if this proves to be the case the supply will have to be provided, at least in part, by imported liquefied natural gas (lng).
the increase in gas demand has
brought about the emergence of
Floating Storage Regasification
Units (FSRU). one reason for their
growing popularity is the significant
reduction in construction speed.
it takes approximately 40 months
to construct a conventional lng
revaporization terminal, whereas
a FSRU using an lng carrier can
be constructed in just 24 months.
FSRUs are also able to move
location, something that onshore
regasification facilities can not do,
enabling them to relocate from one
region to another as demand shifts,
while retaining the ability to trade as
an lng carrier.
the length of time required for the
construction of FSRUs has resulted
in a necessary shift away from
building onshore lng terminals, as
many countries forecast increasing
lng demand over the next two
years. FSRU’s are becoming the
terminal of choice in the 2-4 MtPA
(million tons per annum) lng
import range, making them a cost-
effective, flexible alternative to meet
increased regas demand. With
a capex of roughly US$100-300
million depending on location, there
is also a sizeable business advantage
when compared to an onshore lng
terminal, which typically has a capex
of about US$1 billion.
FSRU pRoject hoRizon
2 • Floating storage regasification units (FSRU) – A guide to risk and insurance
REGASIFICATION TRAINS TRANSFORMING LNGAT -160 CELSIUS TO GAS AT HIGH PRESSURE
STORAGE TANKSLOADING ARMS FOR RECEIVING LNG
EXPORT MANIFOLD
SEAWATER PUMPS FOR PUMPING SEAWATER TOREGAS TRAINS IN ORDER TOHEAT UP THE LNG
there are currently 11 FSRUs in operation and an additional 33 in various stages of construction. in Asia alone, we
may soon see as many as 20 new FSRU projects. the region’s regas demand is expected to grow by 7.5 billion cubic
feet per day over the next five years, while an FSRU has an average regas capacity of 350 million cubic feet per day.
there are four types of construction that fall under the FSRU category:
• Jetty based ship-to-ship transfer where vaporizers are installed onboard one ship, is perhaps the most
conventional.
• Buoy import systems involving subsea gas pipelines and lng vaporization ships.
• island jetty based ship-to-ship transfer systems.
• converted lng carriers with turret, subsea pipeline and vaporizer systems.
A varied selection of insurance and risk solutions exist to meet the requirements that such a combination of
regasification systems present.
Marsh • 3
inSURance pRogRaM deSignthe diagram below shows a typical project and operational insurance program design between a company terminal operator and an FSRU lessee.
tyPicAl PRoJect And oPeRAtionAl inSURAnce PRogRAM deSign
companies’ terminal operators’ insurances should focus on their assets under construction (e.g. jetty, gas pipework, loading arms and
tie ins to the gas grid) and protecting their terminaling revenue and their third party liabilities.
CONSTRUCTION OPERATIONAL FULLY OPERATIONAL
SUMMER 2014 SUMMER 2015
JETTY & PIPING (REGAS)
CAR & (DSU OPTION) & DTEP MAINTENANCE (24M)
PROJECT CARGO (& DSU OPTION)
PROJECT TPL
OPERATIONAL TPL INC MTOL
OPERATIONAL PD & BI & (LEASE FEE)
CONTINGENT BI - FSRU & FSU
HULL REFIT
HULL & P&I
LNG CARGO
TERRORISM / DSU TERRORISM OPERATIONAL (OPTION)
COMPANYINSURANCE
FSRU LEASE
KEYCAR: Construction All RisksDSU: Delay in Start-UP DTEP: Damage To Existing PropertyTPL: Third Party LiabilityMTOL: Marine Terminal Operator’s Liability PD: Property Damage BI: Business InterruptionP&I: Protection and Indemnity
FSRU leaseholders’ insurance will focus on the FSRU’s hull insurances, including Protection and indemnity (P&i), and any lng cargo
under their care and control. lng cargo, including that purchased from a lng producer, may need to be insured by the company,
although this will depend upon delivery terms (for example, whether Free on Board insurance or cost, insurance and Freight insurance).
4 • Floating storage regasification units (FSRU) – A guide to risk and insurance
conStRUction all RiSkS (caR) coveRage
iSSUe onShoRe cAR WelcAR oFFShoRe cAR
Premium cost lower cost optionUp to 2-3 times the price of
onshore cAR
Faulty Part coveragecoverage included to full value on piping and
onshore lng facilities
coverage sublimited for all jetty work
including trestles
Stand-by charge coverage Sublimited for offshore fabrication vessels
normal Action of the Sea coverageexcludes risk up to 1/20 year storm
conditionsincluded
dSU coverage Available dSU is limited and expensive
When tasked with insuring the construction of a jetty based gas import system, it should initially be established whether the jetty is linked to the
mainland or island based. For island based jetties, the WelcAR construction form will be required rather than the onshore cAR insurance form,
increasing the costs of project phase insurances. if the surrounding waters are known to be relatively benign and the jetty is linked to land, the
onshore cAR form would be recommended. Such choices raise many questions which Marsh, with extensive experience in this relatively new area,
is uniquely positioned to answer.
onShoRe cAR veRSUS oFFShoRe WelcAR FoRM FoR Jetty conStRUction
Marsh • 5
FSRUs employ tried and tested technology. however, risk management of FSRUs, both for construction and operation phases, presents a complex
web of insurance and contractual responsibilities. With so many different entities interacting, new risks and contingencies have arisen.
likely eventS inSURAnce PRotection contRActUAl RiSk MitigAtion
• Weather-related issues
– Windstorm with related tide/
swell forces.
– vessels moored to jetty systems.
– interruption of entire process for
repairs/replacement.
• Property damage insurances:
– Pre-operational:
- FSRU – marine risks conversion/
cAR policies.
- Jetty cAR/dSU policy.
– operational:
- Ships/FSRU – marine hull risks
policies.
- Bi and FSRU contingent Bi.
– liability insurances:
- Pre-operational.
- P&I risks – ships/FSRU.
- Jetty/pipelines.
• extent of force majeure clauses in FSRU
lease agreements.
• Responsibility for safe mooring.
• Risk of loss provisions arising out of FSRU
lease agreements.
• inter alia treatment of respective liability
risk from FSRU.
• Responsibilities defined for safe
operation and weather related shutdown
and emergency procedures.
• Ship Collision
– damaging FSRU or jetty, with
lng/gas escape and fire
potential.
– liquefied natural gas carriers
(lngcs) moored to jetties
similarly at risk.
– interruption of entire process for
repairs etc.
• Property damage insurances:
– Ships/FSRU – marine risks policies.
– Jetty/pipelines – “all risks”.
• Liability insurances:
– lng ships/FSRU.
– Jetty/pipelines.
– Marine terminal operator’s liability.
– charterers’ liability.
• Review insurance requirements of lng
shippers.
• examine mutual inter alia liability caps
between and third party lng shippers
and FSRU owners.
• ensure wide form Bi wording includes
vessel collision coverage.
• Review tug services contract for safe
berthing procedures.
FSRU process issue – Mechanical breakdown with fire.
– interruption for repairs etc.
• Property damage/hull insurances:
– FSRU - marine risks policies.
– LNG/gas – “all risks” cargo.
– Bi.
– terminal property damage.
– contingent Bi insurance for FSRU.
• negotiate for continuing costs in the
event of FSRU non-performance.
key
cAR: construction All Risks
P&i: Protection and indemnity
dSU: delay in Start-up
Bi: Business interruption
inSURance and contRact RiSk Mitigation
6 • Floating storage regasification units (FSRU) – A guide to risk and insurance
conclUSion
An FSRU project needs a sound risk management approach, whereby contract risk issues are
taken and assessed alongside the insurance strategy.
Risk and insurance issues will vary according to the:
• location and gas supply systems in place.
• type of FSRU jetty interface solution envisaged.
• Proposed FSRU lease agreement.
• gas off-take agreement and the back to back gas supply agreement in place.
• nature of port terminaling arrangements envisaged.
Risks should be assessed and mitigated using the support of risk engineers, contract managers
and marine safety specialists.
Sophisticated insurance solutions should be built for both project and operational phases to
protect the balance sheets of both parties to FSRU agreements.
the information contained herein is based on sources we believe reliable and should be understood to be general risk management and insurance information only. the information is not intended to be taken as advice with respect to any individual situation and cannot be relied upon as such.
in the United kingdom, Marsh ltd. is authorised and regulated by the Financial Services Authority for insurance mediation activities only.
© copyright 2012 Marsh ltd All rights reserved
viSit oUR WeBSite At: WWW.MARSh.coM
Beijing Unit 1506, north tower Beijing kerry centre 1 guang hua Road, chao Yang district Beijing, 100020, china
tel: +86 10 6533 4000
cape townBlock a, the Boulevard Searle Street, woodstock p.o. Box 253, cape town, 8000 South africa
tel: +27 21 833 4758
calgaRY 222 - 3rd avenue S.w. Suite 1100 calgary alberta t2p 0B4 canada
tel: +1 403 290 7900
dUBai16th Floor, al gurg tower 3 plot 125-117 Riggat al Buteen, Baniyas Road, deira p.o.Box 14937, dubai United arab emirates
tel: +971 4 223 7700
hoUSton1000 Main Street, Suite 3000 houston, texas 77002 United States
tel: +1 713 276 8000
londontower place london ec3R 5BU United kingdom
tel: +44 (0) 20 7357 1000
MadRid edificio puerta europa, paseo de la castellana, 216 Madrid, e-28046 Spain
tel: +34 914 569 400
MoScowSerebryanicheskaya embankment 29 Moscow, 109028 Russian Federation
tel: +7 495 787 7070
MUMBai1201-02, tower 2, one indiabulls centre jupiter Mills compound, 841 Senapati Bapat Marg elphinstone Road (w) Mumbai, 400013, india
tel: +91 226 651 2900
new YoRk1166 avenue of the americas new York, new York 10036-2708 United States
tel: +1 212 345 6000
oSlo vika atrium, Munkedamsveien 45 d oslo, n-0123 norway
tel: +47 22 01 10 00
peRthlevel 28, exchange plaza 2 the esplanade perth, wa 6000 australia
tel: +61 8 9289 3888
Rio de janeiRoav. Rio Branco, 125 - 19º andar cep 20.040-006 Rio de janeiro, Rj Brazil
tel: +55 21 2141 1650
San FRanciSco 345 california Street Suite 1300 San Francisco, ca 94104 United States
tel: +1 415 743 8000
SingapoRe8 Marina view #09-02 asia Square tower 1 Singapore 018960
tel: +65 6922 8048
contactPAUl nicholSonMarsh ltd, tower Place, london ec3R 5BU+44 (0)20 7357 [email protected]
BoB MoRRiSon Marsh ltd, tower Place, london ec3R 5BU +44 (0)20 7357 [email protected]