peace river site c hydro project archaeological site reconciliation
TRANSCRIPT
PEACE RIVER SITE C HYDRO PROJECT Archaeological Site Reconciliation Peace River Fort St. John to Hudson’s Hope B.C.
Peace River Site C Hydro Project Archaeological Site Reconciliation
Peace River Fort St. John to Hudson’s Hope, B.C.
Prepared by Dave Hutchcroft
July 2009
I. R. Wilson Consultants Ltd.
13-6782 Veyaness Road, Victoria, British Columbia V8M 2C2
Tel: (250) 652-4652 Fax: (250) 652-2377 E-mail: [email protected]
Prepared for
B.C. Hydro
6911 Southpoint Drive
Transmission Engineering, 5th Floor
Burnaby, B.C.
V3N 4X8
i
Credits
Editors
Shane D. Bond Ian R. Wilson
Project Manager
Shane D. Bond
Author Dave Hutchcroft
Digital Imaging
Tracy Cardinal
Report Production Derece Powell
ii
Management Summary
The locations and dimensions of 337 previously recorded archaeological sites within B.C.
Hydro’s proposed Peace River Site C pondage area were examined, primarily by
comparing the original site inventory forms and locational information on the Remote
Access to Archaeological Data (RAAD) application maintained by the Archaeology
Branch to orthophotographs and LiDAR images for the same area. Sites were found to
consist of five main types: 227 lithic scatters, 72 isolated finds (also lithics), 27 historic
sites, four palaeontological sites and two cultural depression sites. The records for five
additional sites were also examined, from which it was determined that three of these
were not archaeological in nature. Most of the examined sites were recorded during the
1970s during a multi-year site inventory project for the original Site C dam proposal.
Recommendations were made to the Archaeology Branch to move 219 of the sites on
RAAD from as little as 10 or 20 m to as much as approximately 800 m. Recommended
relocations were made with varying degrees of confidence due to extreme variation in the
quality of the original site form information. The locations of the remaining 118 sites
were left unchanged on RAAD with a similar range in confidence levels. Appendices are
attached to this report which list a complete site inventory for the study area, describe the
rationale for moving or leaving unchanged site polygons on a site-by-site basis, provide
comments regarding any difficulties in site form interpretation and note the relocation
confidence level rating for each site.
As approximately two-thirds of the examined sites in conflict with future development
activities were not subjected to subsurface testing at the time of their original
documentation, it is further recommended that additional fieldwork be completed at these
sites in order to accurately determine site nature, extent and significance.
An additional appendix summarizes comments from the Archaeology Branch regarding
the recommended site relocations. Only recommendations for seven of the 219 sites are
not accepted at this time, although future ground-truthing of these seven sites may result
in later Branch agreement with these recommendations.
iii
Table of Contents
CREDITS .........................................................................................................................................................i
MANAGEMENT SUMMARY...................................................................................................................... ii
TABLE OF CONTENTS .............................................................................................................................. iii
1. INTRODUCTION................................................................................................................................1
2. METHODOLOGY ..............................................................................................................................2
3. THE SITES...........................................................................................................................................4
4. RESULTS .............................................................................................................................................6
5. PROBLEMS.......................................................................................................................................10
6. RECOMMENDATION.....................................................................................................................12
LIST OF FIGURES
Figure 1: Example of LiDAR Use for Replotting Site Boundaries .......................................................... 8
Figure 2: Example of Orthophotograph Use for Replotting Site Orientation ........................................... 9
APPENDICES: A. TABLE 1: ARCHAEOLOGICAL SITE INVENTORY TABLE
B. TABLE 2: ARCHAEOLOGICAL SITE RECONCILIATION TABLE
C. EXAMPLE OF DEFICIENT SITE FORM
D. ARCHAEOLOGY BRANCH COMMENTS RE SITE RELOCATION
RECOMMENDATIONS
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 1
1. INTRODUCTION
At the request of B.C. Hydro, I.R. Wilson Consultants Ltd. (I.R. Wilson) reviewed the
locations of previously recorded archaeological sites situated along the Peace River and
its major tributaries in the vicinity of the potential Site C hydroelectric project. Most of
these sites were recorded during the studies completed for the Site C dam in the mid- to
late-1970s.
The primary goal of the present study was to reconcile site locations and polygons in the
study area presented on the Provincial Government’s online Remote Access to
Archaeological Data application (hereafter referred to as RAAD) with site locations and
other information described on British Columbia Archaeological Site Inventory forms.
As much of the information presented on RAAD is derived from the often sparse data
provided on early site inventory forms from the 1970s, inconsistencies and inaccuracies
are often present. In many cases, sites had been plotted on RAAD based solely on the
basis of the latitude and longitude coordinates on the original site forms due to the very
cursory nature of the rest of the information.
The Archaeology Branch of the Ministry of Tourism, Culture and the Arts maintains and
regularly updates both the RAAD application and the archaeological site inventory
database based on site reconciliation work such as this.
Site verifications were undertaken within an identified study area, roughly a conservative
boundary within which engineering investigations might occur or within which impact
lines may be established.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 2
2. METHODOLOGY
I.R. Wilson downloaded the RAAD information for this project from the Archaeology
Branch, thereby obtaining a list of all sites in the general project area. Hard copies of the
original inventory forms for these sites were then obtained from the same office for
comparative purposes on a site-by-site basis.
When comparing the two information sources, extensive use was also made of the
orthophotographs and LiDAR application provided by B.C. Hydro. The former was often
able to depict landmarks referenced on the site forms such as roads, paths or trails, fields,
forested areas, houses, watercourses, etc. They were also useful in measuring distances
described on site forms due to their ability to adjust for topographic relief and other
distortions present in normal air photographs. Use of LiDAR was also extremely valuable
due to its ability to depict terrain characteristics such as terraces, slopes, gullies, roads or
trails in forested areas, etc., not otherwise discernible on orthophotographs. Google Earth
was also used where possible to identify landmarks described on site forms, such as street
or creek names, which could not be otherwise confirmed.
Where possible and if necessary, site locations were moved and site polygons altered on
RAAD to more accurately reflect information provided on the site inventory forms.
A five point rating scheme (Low [L], Low-Moderate [LM], Moderate [M], Moderate-
High [MH], and High [H]) was employed to reflect the reviewers’ confidence in the site
location, whether unchanged or relocated. Factors contributing to this scheme included:
clarity and detail of the written site descriptions and access instructions on the
original site forms
quality of the forms’ sketch maps, where included
accuracy of the given site coordinates (GPS, noted on only two forms, provided
the highest degree of accuracy)
level of consistency between the site locations shown on the sketch maps and as
described in the site access instructions,
ability to discern landscape features, roads, structures, streams, etc. described on
the site forms on the associated orthophotographs and LiDAR application, and
reviewer intuition and knowledge regarding those physical landscape factors
supporting archaeological site presence.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 3
Regardless of the rating level, in all cases where sites were relocated, confidence level
was higher in the new placements than in the original locations.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 4
3. THE SITES
The archaeological review determined that 337 archaeological sites are recorded within
the general identified study area. Although most of these sites were recorded during the
initial Site C archaeological inventory undertaken in the 1970s and early 1980s, 25 were
found to have been documented since then in response to other proposed developments,
primarily associated with the oil and gas industry.
Five main site types were represented among these 337 reviewed sites and include lithic
scatters (227), isolated finds (72), historic sites (27), paleontological sites consisting of
bison remains (4), and cultural depression sites (2). Five additional recorded sites fell into
a miscellaneous category. Three of these five miscellaneous sites are not considered to be
archaeological.
Lithic scatters, the largest category, are defined as surface and/or subsurface dispersals of
lithic (i.e. stone) tools and/or chipped stone flakes left over from the manufacture of those
tools. One hundred and eighty-five (185) of these sites were confined to the surface, 28 to
subsurface, and 14 to both surface and subsurface. One of the lithic scatter sites, HaRl 2,
was reported to also contain at least four historic First Nations graves when recorded in
1973.
Isolated finds, the second largest site type, were represented by surface (54 sites) or
subsurface (18 sites) occurrences of a single artifact. All of the isolated finds reviewed
during this study consisted of lithic artifacts.
Cultural depression sites are those consisting of one or more surface-excavated pits that
may represent food cache pits, roasting pits or habitation features. Two such sites were
reviewed during this study, one consisting of five depressions and the other of two
depressions, all circular in shape. One was associated with a small lithic scatter and the
other with an isolated lithic artifact.
The 27 historic sites consisted of historic forts HbRe 1, HbRe 32 and HbRf 31
(respectively, Old Fort, Fort St. John II and Rocky Mountain Fort), nine log cabins, ten
sites containing historic buildings, one root cellar, one historic graveyard and three
miscellaneous occurrences of historic remains.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 5
Three hundred and seven (307) sites, including four historic sites (the three fort sites and
the historic graveyard) are automatically protected by the Heritage Conservation Act
(HCA) and may not be disturbed except under authority of a permit issued by the
Archaeology Branch. The remaining 23 historic sites, all dating to the 20th century, the
four paleontological sites and the three non-archaeological sites are not automatically
protected by the Act.
A summary of site types and other relevant information, including site protection status
and the projected need for additional archaeological fieldwork where development
conflicts are present, is depicted in Appendix A, Table 1.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 6
4. RESULTS
Two hundred and nineteen sites or 65% of the recorded 337 sites were moved on RAAD
in accordance with the above procedures. Of these, only 19 (8.6%) were moved with a
high degree of confidence. However, 44 sites (20.1%) were relocated with a moderate-
high confidence level, and 72 (32.9%) with a moderate confidence level. Thirty-nine sites
(17.8%) were moved with a low-moderate degree of confidence and 45 sites (20.6%)
with a low degree. In all cases, however, the reviewers were highly confident that the
new locations were more accurate than originally plotted. Relocations ranged in distance
from as little as 10 or 20 m to as much as approximately 800 m.
Of these 219 sites, 201 were classified as lithic scatters or isolated lithic finds, 13 were
historic sites, and three were paleontological sites. Two sites had been assigned a Legacy
status by the Archaeology Branch since they were determined to be non-heritage sites
subsequent to their initial documentation.
The locations of 118 sites (or 35%) were left unchanged on RAAD. Of these, there was a
high degree of confidence in only 17 (14.4%) of the original site locations. There was a
moderate-high level of confidence that another 17 sites (14.4%) were accurately mapped
a moderate degree and that a further 20 sites (16.9%) were originally accurately located.
Seven sites (5.9%) were left unchanged in location with low-moderate confidence level,
although all were felt to be in the general vicinity of the correct location. Finally, only a
low confidence level could be assigned to the original locations of 57 sites (48.3 %), with
no confidence assigned to three of these. This is due to the poor quality of the associated
site forms which would not allow these sites to be replotted with any degree of accuracy.
Of these 118 sites, 101 were classified as lithic scatters or isolated lithic finds, 14 were
historic sites, one was a historic site with a lithic scatter, one was a paleontological site,
and one was a site assigned Legacy status by the Archaeology Branch.
A summary table describing the rationale for moving site polygons (or not), is depicted
on a site-by-site basis in Appendix B, Table 2. Also included in this table are comments
regarding difficulties, where present, in site form interpretation as well as the confidence
level rating in the revised or unadjusted location for each site.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 7
Figures 1 and 2 illustrate examples of sites relocated through the respective uses of
LiDAR and orthophotographs. In the first example, LiDAR was used to move HbRg 11
from its incorrect RAAD location down a terrace slope to the top of the terrace as
described on the site form (site length was also increased to match the sketch map). In the
second example, an orthophotograph was employed to slightly rotate the area of HbRf
13, as incorrectly shown on RAAD to extend downslope, to enable its correct orientation
and placement entirely on top of the slope and crossing into the adjacent field as depicted
on the sketch map.
HbRg-11
HbRg-13
HbRg-11
±
1:6,000
IRW 09-2162
Site C Overview
Original Archaeological Site Boundary
Revised Archaeological Site Boundary
Figure 1
Example of LiDAR Use for Replotting Site Orientation
I.R. Wilson Consultants Ltd.
Peace River Site C Site Reconciliation Project
Page 8
Scale
0 150Meters
HbRf-13
HbRf-13
±
1:1,000
IRW 09-2162
Site C Overview
Original Archaeological Site Boundary
Revised Archaeological Site Boundary
Figure 2
Example of Orthophoto Use for Replotting Site Orientation
I.R. Wilson Consultants Ltd.
Peace River Site C Site Reconciliation Project
Page 9
Scale
0 25Meters
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 10
5. PROBLEMS
Several difficulties with the site record were apparent during this study that, depending
on their level of accumulation, compromised the ability of the reviewers to effectively
plot accurate site locations. These include:
Lack of detailed site access information including distances to sites from
recognizable permanent landmarks. Too many forms were prepared giving
distances from wooden telephone poles, transmission line poles, wooden fence
posts, land survey markers, etc., most of which are not discernable on LiDAR or
orthophotographs, nor would be expected to exist some 35 years after the sites
were initially recorded;
Poor quality of site maps which, in eight cases, were completely absent. Many site
maps did not include distance scales, north arrows and legends, all of which are
required information. The best site location maps were those prepared from air
photos, or which otherwise included recognizable landmarks such as prominent
roads, creeks, bridges, bluffs, etc.;
Distance measurements given confusedly on the same form in feet and metres,
and/or miles and kilometers;
Lack of current LiDAR or orthophotograph coverage for some areas at the fringes
of the project area; and
Lack of sufficient subsurface testing at most archaeological sites to confidently
support site boundaries as described on their associated forms or to enable proper
assessments of site significance. For instance, of the 299 surface and/or
subsurface lithic scatters or isolated lithic find sites reviewed, approximately 230
had not been subjected to any subsurface testing in order to properly ascertain
their boundaries. Furthermore, of those 70 or so sites which had been tested, 26
had only been subjected to one shovel test or one 1 x 1 m excavation unit where
the potential for additional cultural deposits was extremely high. Only 15 lithic
sites appear to have had a sufficient level of testing completed to enable a high
confidence in their depicted site boundaries. An additional four sites may have
been sufficiently tested.
An example of a site form exhibiting some of the qualities noted above which inhibited
the site relocation process is included as Appendix C. Deficiencies include: no detailed
access information, including distances and directions; incorrect latitude/longitude
coordinates which place the site on the south side of the Peace River rather than the
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 11
correct north side; no reference to whether or not site material was collected, and; poor
sketch map which does not include a distance scale nor places the site in a wider
geographical context.
Peace River Site C Site Reconciliation Project
I. R. Wilson Consultants Ltd. Page 12
6. RECOMMENDATION
The primary recommendation resulting from this study relates mostly to the lack of
previous testing to confirm site boundaries and context. Owing to the absence or lack of
sufficient testing at most of the sites described in this report, as well as other above
described problems with site forms, the revised polygons as presented on RAAD should
not be taken as depicting site boundaries with any degree of accuracy. In almost all cases
where sites are in conflict with potential ground-altering development activities,
additional fieldwork is recommended to properly document those sites. This
recommendation applies to approximately two-thirds of the reviewed sites, as outlined in
Appendix A.
Fieldwork may include field verification of site locations where in doubt, testing to
accurately determine site nature, extent and significance, and/or mitigative excavation.
Any such undertaken activities must be conducted under the authority of one or more
Heritage Conservation Act permits issued by the Archaeology Branch.
This recommendation applies solely to physical archaeological evidence of past human
activity, and in no way attempts to encompass any traditional land use or heritage
concerns of the various First Nations people with traditional territories in the study area.
Appendix A
Appendix A: Table 1
I.R. Wilson Consultants Ltd. Appendix A - 1
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
GlRk 1 LS Surface 2 flakes Y Y N Y N-340 m from TL 1977-009 1979-032
GlRk 3 IF Subsurface 1 flake in tree
root N Y Y 6 STs N ? on T/L RoW 1979-032
HaRe 18
LS Surface 2 flakes, 1
chipped knife ? Y N Y N – 600 m from T/L 1987-033
20 LS Subsurface 4 flakes Y-FSJNPM Y Y 28 STs (3 +) Y N - outside AZ 2000-166
HaRg 2 LS Subsurface 5 flakes Y-FSJNPM Y Y 15 STs N construction 2001-100
3 IF Subsurface Retouched
Flake Y-FSJNPM Y Y 28 STs (1+) N ? on T/L RoW 2006-068
4 LS Subsurface 1 point, 13
flakes Y-FSJNPM Y Y 134 STs (7+) N construction 2007-072
11 LS Subsurface 11 flakes Y-FSYNPM Y Y 156 STs (11 +) N N – off T/L but in TEM 2008-090
HaRh 1 LS Surface 3 flakes, 1
chipped knife N Y N Y
N – outside AZ but in TEM
1977-009 1979-032
HaRi 1 LS Surface Core, side-
notched point N Y N Y
N – outside AZ but in TEM
1977-009
HaRj 1 LS Surface Flakes N Y N Y Hwy relocation 74-29, 76-13, 78-14
2 LS Surface
Flakes (includes
retouched), cores, bifaces
Y/N Y N Y N – outside AZ 74-29/76-13/ 77-
09/78-14
3 IF Surface Flake Y Y N Y N- ~100 m outside
bdy 1976-013
4 LS Surface Flakes N/Y Y N Y slumpage 1974-029 5 IF Surface Flake N Y N Y slumpage 1974-029? 6 LS Surface Flakes (2) N Y N Y slumpage 1976-013 7 LS Surface Flakes (2) Y Y N Y slumpage 1976-013? 8 LS Surface Cores (2) N Y N Y Slumpage? 1976-013 9 LS Surface 1 core, 2 flakes N Y N Y slumpage 1976-013
10 LS Surface Cores (2) ? Y N Y slumpage 1976-013? 11 IF Surface Flake N Y N Y N – outside AZ 1976-013
HaRj 12 LS Surface Scraper/3
flakes N Y N Y N – 215 m outside AZ 1976-013
13 LS Surface Point, RF, flake N Y N Y slumpage 1976-013? 14 LS S/SS 7 surf flakes Y Y Y 1-1x2 EU Y slumpage ? 15 IF Subsurface Core Y Y N Y slumpage 77-9/78-14 16 LS Surface Flakes N Y N Y slumpage 1978-014 17 LS Surface Scraper/flake Y Y N Y ? - inside bdy 1978-014 18 LS Surface Flakes Y Y N Y Slumpage 77-9/78-14 19 LS Subsurface Flakes/tools Y Y Y 1-1x1 EU Y Flooding 77-9/78-14 21 LS S/SS Flakes N Y Y 1 ST Y Slumpage 1978-014
HaRj 22 IF Subsurface Flake Y Y Y 1 ST Y Slumpage? 1978-014
I.R. Wilson Consultants Ltd. Appendix A- 2
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
H23 Log Cabin N/A Ca. 1920 N/A N N N Slumpage? 1978-014 24 IF Subsurface flake Y Y Y 1 ST Y Slumpage? 1978-014
HaRk 1 General Activity
S/SS Excavated 1979 Y Y Y 8-1x1 Units Y Flooding? 1978-14 1979-12
2 LS Surface Scraper, flakes Y Y N Y Flooding. Poor map &
desc. 76-13?
4 IF Surface Flake Y Y N Y ? - inside bdy ? 5 LS Surface Y Y N Y Slumpage? 1974-029 6 LS Surface ? Y N Y Flooding 1974-029 7 LS Surface ? Y N Y Flooding? 1974-029 8 LS Surface ? Y N Y Flooding 1974-029
H9 Log Cabin N/A 1900s, 4 C.D.s N/A N N N Flooding 1974-029 H10 Log Cabin N/A 1900s N/A N N N Flooding 74-29/79-12
11 LS Surface Incl. SN Point Y Y N Y N-65 m outside 1974-029 12 LS Surface Y/N Y N Y Flooding 1974-029 13 LS Surface With cabin Y Y N Y Flooding 1974-029 14 LS Surface 5 circ. Rings N Y N Y Flooding 1974-029? 15 LS Surface Y/N Y N Y Flooding 1974-029 16 LS Surface Y Y N Y Flooding 1974-029 17 LS Surface N Y N Y Flooding 74-29/76-13/78-14 18 LS Surface 1 Knife/1 point Y (owner) Y N Y Flooding 74-29/76-13/79-12 19 LS Surface 2 flakes N Y N Y Flooding 76-13/79-12 20 LS Subsurface 4 flakes Y Y Y 1-1x1 EU Y Outside? 77-9/78-14
HaRk
21 LS Surface 57 items Y/N Y N Y Mostly outside 77-9/78-14
22 LS Surface 4 flakes N Y Y? Y Slumpage 77-9/79-12 23 LS Subsurface Y Y N 1-1x1 EU Y Flooding 77-9/78-14 24 IF Surface Biface Y Y N Y Flooding 77-9/78-14 25 LS Surface 26 flakes Y Y N Y Flooding 77-9/78-14 26 LS Surface I flake/1 core N Y N Y Flooding 77-9/78-14 27 LS Surface Pt/3flakes N Y N Y Slumpage? 77-9/78-14
H29 Hist.Bldgs N/A 1920s, 3 bldgs N/A N N N Flooding 77-9/78-14 H30 Log Cabin N/A 20th century? N/A N N N Flooding 77-9/78-14 H31 Log Cabin N/A Ca. 1945 N/A N N N Flooding 77-9/78-14 H32 Log Cabin N/A 20th century? N/A N N N Flooding 77-9/78-14 H33 Log Cabin N/A 1920s-legacied N/A N N N Flooding 77-9/78-14
HaRk H34
Log Cabin N/A 1900 –1915 N/A N N N Flooding 77-9/78-14
35 LS Subsurface 11 flakes-? ret. Y Y Y 5-1x1 EUs Y Flooding 77-9/78-14 36 IF Surface Flake Y Y N Y Flood. Bad map 77-9/78-14 37 LS Surface 1core/1 flake N Y N Y Flooding 1978-014 38 LS Surface biface/18 flakes Y Y N Y Flooding 1978-014 40 LS Surface 2 flakes/2 tools Y Y N Y Slumpage 1978-014
I.R. Wilson Consultants Ltd. Appendix A- 3
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
41 LS Surface Large site Y Y N Y Slumpage 1978-014
42 LS Surface 20+ tools/
flakes Y Y N Y Slumpage? 1978-014
HaRl 1 Burial? S/SS Historic
gravehouses N Y N Y N – outside AZ.
1954 survey, 1978-014
2 LS/burial S/SS Scraper/flakes
& 4 historic graves?
Y- artifacts (RBCM)
Y N Y N – outside AZ 1973-028 1978-014
3 LS Surface 2 mounds Y (RBCM) Y N Y Flooding 73-28/78-14
4 LS Surface Incl. historic
bldgs Y (RBCM) Y N Y Flooding 73-28/78-14
5 TU Legacied-anecdotal
Ceremonial boulder
N/A N N N Flooding 73-28/78-14
6 LS Surface 4 flakes ? Y N Y Flooding 73-28/78-14
7 Non-site Legacied Pile of
sandstone blocks
N/A N N N Flooding 74-29/78-14
9 LS Surface Scraper/5
flakes Y Y N Y N – outside AZ 1974-029
10 LS Surface 2 flakes Y Y N Y Flooding ?
12 LS Surface Flakes etc. Y/N Y N Y Y? – if moved may be
in hwy realignment 1974-029
13 LS Surface 2 flakes Y Y N Y N-outside bdy 1974-029
14 LS Surface 5 flakes, 1 point Y-Flakes,N-
pt Y N Y Flooding 1974-029
15 LS Surface 2 flakes/3 cores N Y N Y Flooding. No site map 1976-013 16 IF Surface Chitoth N Y N Y N – outside AZ 1976-013 17 IF Surface Chitoth N Y N Y N – outside AZ 1976-013
18 LS Surface Flakes, cores, 2
ret flakes Y-flakes Y N Y Flooding 76-13/79-12
19 IF Surface Flake N Y N Y Flooding 1976-013 20 IF Surface Flake N Y N Y Flooding 1978-014 21 IF Surface Flake N Y N Y Flooding 1978-014
H22 Historic Subsurface Hearth/burnt bone/sq. nail
Y (nail) N N N Flooding 1978-014
23 LS Surface
A: flakes, cores,
scraper, spall tools; B: adze
N-A; Y-B Y N Y Flooding 77-9/79-12
HaRl 24 IF Surface Flake N Y N Y Flooding 1978-014
HbRe H1
Historic fort/burial
S/SS “Old Fort”-
bldgs & hist. native graves
N Y N Y N– downstream of
dam 1954 survey 1974-
029
H2 Hist.Bldg. N/A 1910 police
building N N N N
N– downstream of dam
1974-029
I.R. Wilson Consultants Ltd. Appendix A- 4
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
4 IF Surface 1 flake ? Y N Y N-downstream 1974-029 5 IF Surface Scraper ? Y N Y N-downstream 1974-029 6 IF Surface Chopper ? Y N Y N-downstream 1974-029
12 LS Surface 2 flakes ? Y N Y N-downstream 1974-029
H32 Historic fort S/SS Fort St John II Y Y Y-1987 6-50 x 50 cm
EUs Y
Just inside SL, till invest. area
1987-013
54 LS Subsurface 1742
flakes/tools Y-FSJNPM Y Y
15 STs, 6-1x1 m EU, 1-2x.5 m EU
N Site removed under
SAP 2002-110, 2002-
116 HbRe
55 LS Subsurface 177flakes/tools Y-FSJNPM Y Y
16 STs (2 +), 1 EU
Y? Till invest. area 2002-110
HbRf 1 LS Surface? 1957 site form Y-Nat Mus HCA N Y Inside SL. Poor form,
site unlocatable None
8 Feature S/SS Burnt sand-stone slabs
N/A Y N Y? Flooding 76-13/77-09/ 78-14/
9 IF Surface Flake Y Y N Y Slumpage 1974-029
10 LS Surface Non-specific ? Y N Y Poor form, site
unlocatable 1974-029
11 LS Surface 2 flakes ? Y N y Poor form, site
unlocatable 1974-029
12 IF Surface Flake Y Y N Y Poor form, site
unlocatable 1974-029
13 LS Surface Flakes/ 1 pp N/Y Y N Y slumpage 74-29/77-09/ 1978-
014
14 LS Surface 2 cores/6 flakes ? Y N Y Till invest.
Poor form, site unlocatable
1974-029
15 LS Surface 2 flakes Y Y N Y Till invest.
Poor form, site unlocatable
1974-029
16 LS Surface 11 flakes-road
cut ? Y N Y
Till invest. Poor form, site
unlocatable 1974-029
17 LS surface 2 flakes ? Y N Y Till invest.
Poor form, site unlocatable
1974-029
18 IF Surface Flake ? Y N Y Slumpage? No map
on form 1974-029
19 LS Surface 2 flakes 100 m
apart ? Y N Y
Slumpage, till investigation
1974-029
20 LS Surface 3 flakes Y Y N Y Till invest. 1974-029 21 IF Surface Flake Y Y N Y? Flooding? 1974-029 22 IF Surface Flake Y Y N Y? Till invest. 1974-029
H23 Hist.Bldgs N/A Farmhses,
1900s N/A N N N Till invest. 1977-009
I.R. Wilson Consultants Ltd. Appendix A- 5
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
HbRf 24 LS Surface 15 flakes/tools N Y N Y Till invest. 1977-009 25 LS Surface 59 flakes/tools N Y Y 1975-unknown Y Till invest. 74-29/78-14n 26 IF Surface Flake Y Y N Y Till invest. 74-29/78-14 27 LS Surface 5 flakes ? Y N Y Slumpage? 1976-013? 28 LS Surface 2 flakes N Y N Y Slumpage? 1974-029
29 Non-
heritage S/SS
4 depressions (oval) tested
1981, assessed as non-cultural
N/A N Y-1981 2 trenches N Flooding 1974-029 MO
1981-18
30 LS Surface 21 flakes N Y Y-1981 STs- unknown
number Y?
Dam constr. D Alexander (81)
couldn’t find
1974-029 MO 1981-18
H31 Historic fort S/SS Rocky Mtn Fort Y Y Y-1975 Both-unknown
number Y Flooding
74-29/76-13/ 86-14/ 87-13
32 LS Surface Core, flake ? Y N Y
Dam constr. Site already destroyed?
May be outside application line
1974-029
33 IF Surface Flake Y Y N Y N – outside AZ 74-29/78-14 H34 Log cabin N/A HBC? N/A N N N N-outside bdy 74-29/79-32
35 LS Surface 3 flakes ? Y N Y Till invest. 74-29/76-13/ 1978-
014
36 IF Surface Flake ? Y N Y Till invest. 74-29/76-13/ 1978-
014
H37 Log bldgs N/A 20th century N/A N N N flooding 74-29/76-13/ 1978-
014
40 LS S/SS
11 flakes-1974 50 flakes-1981 Much debitage, core, scraper-
2008
N-74,Y-81, y-2008
(FSJNPM) Y Y-1981
1981: 10-1x1 EUs; 2008: 199 ATs, 1-1x10 m
trench
N Dam constr. 74-29/81-18/ 2008-
340
41 LS Surface 2 flakes N Y Y 1 ST? N Dam/flooding 76-13/78-14/ 77-
9/79-32
42 Buried deposit
Subsurface Ash/shell N Y N Y Flooding 76-13/77-09/ 1978-
014
HbRf 43 LS Surface 20 flakes Y Y Y-1979 20 neg tests Y Slumpage 77-9/78-14/ 1979-
032 HbRf 44 IF Surface Core N Y N Y Till invest. 77-9/78-14
45 IF Surface Flake N Y N Y Slumpage? 77-9/78-14 46 LS Surface 3 flakes Y Y N Y Slumpage 77-9/78-14 47 LS Surface 3 flakes Y Y N Y Slumpage 77-9/78-14 48 IF Surface Core Y Y N Y Till invest. 1978-014 50 LS Surface 10 flakes/tools Y Y N Y Till invest. 74-29/78-14 51 LS Surface 5 flakes, 2 tools N Y N Y Till invest. 1978-014 54 LS Surface 5 flakes N Y N Y Till invest. 78-14/79-12
I.R. Wilson Consultants Ltd. Appendix A- 6
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
55 IF Surface Core N Y N Y Till invest. 1978-014 56 IF Surface Flake N Y N Y Till invest. 1978-014? 57 IF Surface Core N Y N Y Till invest 1978-014 58 IF Surface Core N Y N Y Till invest. 1978-014 59 LS Surface 8 flakes N Y N Y Dam constr/ flooding 1978-014 60 LS Surface 7 flakes N Y N Y Flooding 1978-014
61 LS S/SS Several flakes
& tools Y-only 2 blue chert Flakes
Y Y 1978:1? 1x1 m EU; 1981: 21 1x1 m EUs
N? Dam constr./ flooding 78-14/81-18
62 LS S/SS Large site, 800 flakes & tools
Y Y Y ~100 1x1 (?) m
units Y? Dam constr./ flooding
1981-MO-18:pp 51-89
63 LS S/SS ~150 flakes in concentration
Y Y Y 34 STs (1+), 13-1x1 m EUs (2 +)
N? Dam constr. 1981-MO-18:pp 91-
96
64 IF Surface Flake Y Y Y 34 STs (neg) N Dam constr. 1981-MO-18:pp 97-
99
65 LS Surface 42 flakes/cores Y Y Y 4 EUs (neg) Y Dam constr. 81-MO-18: pp 100-
105
66 LS S/SS 20 flakes Y Y Y 32 STs, 1-80 x
80 cm unit Y? Dam constr.
81-MO-18: pp 106-109
67 LS Surface Point base,
flake Y Y Y
5-1x1 m EUs (neg)
N? Dam constr. 81-MO-18: pp 110,
111
68 Paleo SS-gravel pit Bison elements Y N N N Dam constr. 81-MO-18: pp 112-
115 69 Paleo SS-gravel pit Bison vertebra Y N N N Dam constr. 1981-MO-18 79 LS Surface 4 flakes Y-FSJNPM Y Y 201 neg STs N Till invest. 2002-116
80 LS Surface 15 flakes Y-FSJNPM Y Y 40 neg STs N? Till invest. 2002-116
81 LS Surface
1 point, 1 core, 1 retouched flake, flakes, scraper, bone
Y-FSJNPM Y N Y Till invest. 2003-054
HbRf 82 LS Subsurface 3 flakes Y-FSJNPM Y Y 29 STs (1 +) N Dam constr. 2004-094 HbRg 4 LS? Surface Flakes/bone ? Y N Y Flooding? 74-29: p 89
5 LS Surface Flakes N Y N Y Flooding? 74-29: p 89 6 LS Surface Flakes N Y N Y Flooding? 74-29: p 90 7 LS Surface Flakes Y/N Y N Y Flooding? 74-29: p 90
8 LS Surface Flakes Y Y N Y N-outside AZ 74-29/76-13/ 77-
09/78-14
9 LS Surface 3 flakes Y Y N Y N-outside AZ 74-29/76-13/ 77-
09/78-14
10 LS surface 4 flakes Y Y N Y N-outside AZ 74-29/76-13/ 77-
09/78-14 11 LS Surface Flakes N Y N Y Flooding 74-29: p 90
I.R. Wilson Consultants Ltd. Appendix A- 7
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
12 LS Surface Several flakes Y/N Y N Y N-outside AZ 74-29/76-13/ 77-
09/78-14 13 LS Surface Flakes Y Y N Y Slumpage?
14 LS Surface Flakes Y Y N Y Slumpage? 74-29/77-09/ 1978-
014
15 LS Surface Large site:non-specific lithics
?-1954 Y-1974
Y N Y Flooding? 74-29:p 87
16 LS Surface 2 flakes Y Y N Y Flooding
17 LS Surface 6 cores,12
flakes N Y N Y Flooding?
76-13/77-09/ 1978-014
18 LS Surface 10 flakes, 1
core N Y N Y Flooding?
76-13/77-09/ 1978-014
19 LS Surface 6 flakes N Y N Y Flooding?
20 LS Surface 20 flakes, 1
core N Y N Y Hwy relocation
21 LS Surface 20 flakes N Y N Y Hwy relocation 22 IF Subsurface Flake N Y Y 1 ST Y Flooding 23 IF Subsurface Core Y Y Y 1-1 x 1 m unit Y Flooding 77-9/78-14 24 LS Surface Flakes, 1 pp N Y N Y Hwy relocation 77-9/78-14 25 IF Surface Flake N Y N Y Hwy relocation 77-9/78-14
HbRg
26 IF Surface Flake N Y N Y N-outside AZ 1977-009 1978-014
H27 Hist.Bldgs N/A 2 1920s barns N/A N N N Hwy relocation 77-9/78-14 H28 Hist.Bldgs N/A 3 1920s bldgs N/A N N N Hwy relocation 77-9/78-14 29 LS Surface 5 flakes N Y N Y Slumpage 77-9/78-14 30 LS Subsurface 1 core, flakes Y Y Y 1-1 x 1 m unit Y Hwy relocation 77-9/78-14
31 IF Surface Projectile point Y Y N Y N-47 m outside
boundary 1978-014
32 LS Surface 2 flakes N Y N Y Hwy relocation 1978-014 33 LS Surface 44 flakes N Y N Y Hwy relocation 1978-014
HbRg 35
IF Subsurface 1 flake Y Y Y 1 ST Y Hwy relocation 1978-014
36 LS Subsurface 28
flakes/shatter Y-FSJNPM Y Y 11 STS (6+) Y Till invest. 2003-054
37 IF Subsurface Flake Y-FSJNPM Y Y 11 STs (1 +) Y Till invest. 2003-054 38 LS Surface Flakes Y-FSJNPM Y N Y Slumpage 2005-283
HbRh 1 LS Surface Several flakes & tools-’54 +
‘74 Y Y N Y Flooding 74-29/79-12
2 LS surface Flakes/scrapers
Rept’d burial Y Y N Y Flooding 74-29/79-12
6 LS Surface Core/flakes Y/N Y N Y Flooding 78-14/79-12 7 LS Surface Flakes Y Y N Y Hwy relocation 1974-029
I.R. Wilson Consultants Ltd. Appendix A- 8
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
8 LS Surface points
referenced Y Y Y-1976
6-1x1 m EUs, 4-50 x 100 cm
? Hwy relocation 74-29/76-13
10 LS Surface 7 flakes, 1 core Y Y N Y Hwy relocation 74-29/76-13/ 1979-
012 11 LS Surface 11 flakes Y Y N Y Hwy relocation 76-13/79-12
12 LS Surface Flakes,bifaces, hammerstone
Y Y N Y Hwy relocation 74-29/76-13
13 LS Surface Flakes (incl. retouched &
utilized) Y Y N Y N-outside AZ 1976-013
16 LS Surface 18 Flakes,
biface, core Y Y N Y Hwy relocation 74-29/79-12
17 LS S/SS Several flakes
& tools Y/N Y Y
STs – unknown #
Y Flooding ? 78/79 prelim
report
18 LS S/SS Sev.
flakes/tools Y/N Y Y 1? ST Y Flooding 1979-012
19 LS Surface 13 flakes ? Y N Y Flooding 1974-029
HbRh 20
LS Surface SN point, 2
flakes, 2 tools Y Y N Y Flooding 1974-029
21 LS Surface 31 flakes, 2
points Y Y N Y Flooding 1974-029
22 LS Surface Flakes & ? Y Y N Y Hwy relocation 1974-029 23 LS Surface Flakes/biface Y Y N Y N-outside AZ 74-29/79-12
24 LS Surface Flakes/tools ? Y N Y Hwy relocation 74-29/76-13/ 77-
09/78-14 26 Paleo SS-gravel pit Lg vertebra Y-F&W N N N Hwy relocation 1976-013
27 LS Surface 8 Flakes, 5
cores, scraper ? Y N Y Flooding 1976-013
28 LS Surface Flake/scraper N Y N Y Flooding 1976-013 29 LS Surface 2 flakes Y(owner) Y N Y Flooding 1976-013
30 Paleo? Surface Bison bone,
creek deposit Y(owner) N N N Hwy relocation
76-13/77-9/ 1978-014
HbRh 31
IF Surface Core N Y N Y N-outside AZ 76-13/77-09
32 LS Surface Core & scraper N Y N Y Flooding 1976-013
33 LS S/SS 417
Flakes/tools ‘76(owner)
Y-1977 Y Y
’76: 20 units: 9 -1x1; 11-2x2
Y? Hwy relocation 76-13/77-9/ 1979-
012 34 LS Surface 1 core, 1 flake N Y N Y Flooding 1976-013
35 Historic Surface
3 depressions, glass frags,
bottles, iron – historic ford
N N N N Flooding 1976-013
I.R. Wilson Consultants Ltd. Appendix A- 9
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
36 LS S/SS
40 Flakes (1 retouched), 1 microblade, 3
cores
N Y Y-1976 ? – no report Y? Flooding 1976-013
37 LS Surface 1 core, 2 flakes N Y N Y Flooding 1976-013 38 LS Surface 2 flakes N Y N Y Flooding 1976-013 40 LS Surface Flakes, scraper N Y N Y Hwy relocation 1976-013 41 LS Surface 2 flakes ? Y N Y Hwy relocation 1976-013 42 LS Surface Flakes, chitoth ? Y N Y Hwy relocation 1976-013 44 LS Surface Flakes, 3 cores N Y N Y Flooding 1976-013
H45 Historic N/A Root cellar N/A N N N Flooding 46 IF Subsurface Core Y Y Y 1 ST Y Flooding 76-13/78-14 47 IF Surface Flake N Y N Y Hwy relocation 76-13/78-14
48 LS Surface 3 flakes ? Y N Y Hwy relocation 76-13/78-14 49 LS Surface p. pt., flake Y(pt)/N Y N Y Hwy relocation 76-13/78-14 50 IF Surface Core N Y N Y Hwy relocation 76-13/78-14 51 LS Surface 3 flakes N Y N Y Hwy relocation 76-13/78-14 52 IF Subsurface Flake Y Y Y 1 ST Y Flooding 76-13/78-14
53 LS Surface Flakes in trail
cut N Y N Y Flooding 76-13/78-14
54 LS Subsurface 2 flakes Y Y Y 1 1x1 m EU Y Hwy relocation 77-9/78-14 55 LS Surface? 2 Flakes (1 ret.) Y Y Y? 1 ST? Y Hwy relocation 77-9/78-14
56 LS Subsurface 500+ Flakes,
cores, ret Flakes
Y Y Y 1 1x1 m EU? Y N- 85 m outside
boundary 77-9/78-14
57 IF Subsurface Flake Y Y Y 1 1x1 m EU Y Hwy relocation 77-9/78-14 58 IF Surface Chithos Y(owner) Y N Y Flooding 77-9/78-14
H59 Hist.Bldgs N/A 2 log cabins, 2 barns-20th cent
N/A N N N Hwy relocation 77-9/78-14
H60 Hist.Bldgs N/A 20th cent N/A N N N Flooding 77-9/78-14
H61 Hist.Bldgs N/A Log structure,
ca. 1944 N/A N N N Hwy relocation 77-9/78-14
62 LS Subsurface 9 Flakes, 7
cores Y Y Y 2 STs Y N-60 m outside 1978-014
HbRh 63
LS Subsurface 30 flakes Y Y Y 3 STs Y Hwy relocation 1978-014
64 LS Subsurface 2 Flakes, 7
cores ? Y Y 1 ST Y Hwy relocation 1978-014
65 LS Surface 6-12 flakes N Y N Y Flooding 1978-014
66 LS Subsurface 39 Flakes, 3 bone frags
? Y Y 1 ST? Y Flooding 77-9/78-14
67 IF Surface Flake N Y N Y Hwy relocation 1978-014 68 LS Subsurface 2 flakes Y Y Y 1 ST Y Hwy relocation 1978-014
I.R. Wilson Consultants Ltd. Appendix A- 10
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
69 LS Surface Scraper, core,
3 bifaces, Flakes
N Y N Y Hwy relocation 1978-014
70 LS Surface Core, quartzite N Y N Y N-72 m outside
boundary 1978-014
71 LS S/SS Flake, scraper Y Y Y 1 ST Y N-32 m outside 1978-014 72 IF Surface Hammerstone Y Y N Y N-outside AZ 1978-014 73 IF Surface Flake N Y N Y N-outside AZ 1978-014
74 LS Surface Core, pebble (retouched) p
N Y N Y N-outside AZ 1978-014
75 LS surface 5 Flakes, core Y Y N Y N-outside AZ 1978-014
76 LS Surface 10-12 flakes N Y N Y Hwy relocation 78-14/79-12 77 IF Surface Surface N Y N Y Hwy relocation 78-14/79-12
78 LS Surface 10-15 Flakes, 2 cores, scraper
N Y N Y Hwy relocation 78-14/79-12
79 LS Surface Several cores &
flakes N Y N Y N-109 m outside bdy 76-13/79-12
80 LS Surface Flakes & burnt
bone Few Flakes-
FSJNPM Y N
Y-needs relocat’n in
field Hwy relocation? 1992-059
81 LS Surface Flakes I Flake-
FSJNPM Y N
Y-needs field
verifying Hwy relocation? 1992-059
82 LS Surface Flakes (incl 1 obsidian), 2 split cores
Y-FSJNPM Y N Y-needs
field verifying
Hwy relocation? 1992-059
83 LS Surface Flakes I Flake-
FSJNPM Y N
Y-needs field
verifying Hwy relocation? 1992-059
84 LS Surface Flakes (incl 1
obsidian) Few Flakes-
FSJNPM Y N
Y-needs field
verifying Hwy relocation? 1992-059
85 IF Subsurface Flake Y-FSJNPM Y Y 58 STs (1 +) N but poss
SAP Hwy relocation? 2000-151
87 LS Subsurface 3 flakes Y Y Y 50 STs (1 +) N N – 45 m E of realigned hwy
2003-002 2003-098
HbRh 100
IF Subsurface Flake Y Y Y 15 STs (1 +) N Hwy relocation 2008-298
101 LS Subsurface 9 flakes Y Y Y 31 STs (4 +) N Hwy realignment 2008-298 102 LS Subsurface 25 flakes Y Y Y 27 tests N Slumpage 2008-365
HbRi 1 LS Surface Flakes, 1,piece
esquillee Y/N Y N Y
N -33 m outside AZ boundary
1974-029
I.R. Wilson Consultants Ltd. Appendix A- 11
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
2 LS Surface Scraper, flakes Y/N Y N Y N-87 m outside
boundary 74-29/79-12
3 LS Surface Flakes, bones N Y N Y N-33 m outside
boundary 1974-029
HbRi 4 LS Surface Flakes Y Y N Y N-65 m outside
boundary 1974-029
5 LS Surface 2 flakes N Y N Y Hwy relocation 74-29/77-9/ 1978-
014
6 LS Surface
Lge site in plowed field:
cores, bifaces PP, scrapers,
flakes
Y ’74-SFU; 2008
(FSJNPM) Y N Y Hwy relocation 74-29/08 NP
7 LS/CD Surface 4 flakes, 5 circ depressions
? Y N Y Hwy relocation 1974-029
8 IF/CD Surface 1 flake, 2 circ depressions
? Y N Y Hwy relocation 74-29/79-12
9 LS Surface 12 flakes ? Y N Y Flooding 74-29/79-12
10 LS Surface 15 cores, 28
flakes, hammerstone
? Y N Y Flooding 1976-013?
11 IF Surface Flake N Y N Y Flooding 76-13/79-12
12 LS Surface 10 cores, 11
flakes (1 ret.), chopper
N Y N Y Flooding 1976-013?
13 LS Surface 5 flakes N Y N Y Hwy relocation 1976-013 14 LS Surface 2 flakes N Y N Y Hwy relocation 1976-013
15 IF Surface Retouched
Flake Y(owner) Y N Y Hwy relocation 1976-013
23 LS Surface 2 flakes Y Y N Y N-outside AZ 77-09/78-14 24 IF Surface Flake N Y N Y Flooding 77-9/79-12 25 IF Surface Flake N Y N Y Flooding 77-9/79-12
26 LS Subsurface 15 flakes Y Y Y 1-1x1 m unit Y N-340 m outside AZ
bdy 77-9/78-14
27 LS Subsurface 16 flakes Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14
28 LS Subsurface 19 Flakes (1
ret.) Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14
29 IF Subsurface Flake Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14 31 IF Subsurface adze-like tool Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14
HbRi 32 IF Subsurface Flake Y Y Y 1-1x1 m unit Y N-outside AZ 77-9/78-14
33 LS Surface Lithics, may
join w/ HbRi 9 & 34
Y Y N Y Hwy relocation 77-9/78-14
I.R. Wilson Consultants Ltd. Appendix A- 12
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
34 LS Surface Non-specific
lithics, may join w/ HbRi 9 & 33
Y Y N Y Hwy relocation 1978-014
(35) LS Surface 3 cores, 2
Flakes N Y N
(36) LS Surface Core, chipped
cobble Y Y N
(37) LS Surface 3 Flakes, core Y Y N (38) IF Surface Scraper N Y N (39) LS Surface 2 flakes N Y N 40 IF Surface Flake N Y N
Y
Hwy relocation. These 6 sites have all been merged into one site – HbRi 40 – and a new polygon drawn
1978-014
41 LS S/SS 35-40 flakes, 10 cores, ret.
flake,biface tip Y/N Y Y 2 STs ? Y Flooding 1978-014
42 LS Surface 20-25 Flakes,
core N Y N Y Flooding 1978-014
43 LS Surface 9 Flakes (1
ret.), scraper N Y N Y Flooding 1978-014
44 LS Surface 1 core, 2 flakes N Y N Y Flooding 1978-014 46 IF Surface Flake N Y N Y Flooding 1979-012 47 LS Surface 5 flakes N Y N Y Flooding 1979-012
HbRj 1 LS Surface Flakes. Bifaces also reported
Y Y N Y Hwy relocation 74-29/76-13/ 77-
9/78-14
2 IF Surface Flake Y Y N Y N-87 m outside AZ
boundary 1974-029
3 LS Surface 2 flakes ? Y N Y N-235 m outside bdy
4 LS Surface Flake, biface Y Y N Y N-65 m outside AZ
boundary 1974-029
5 IF Surface Flake ? Y N Y N-outside AZ
6 LS Surface Pt, 2 scrapers, flakes, glass,
ceramics Y/N Y N Y Flooding
7 LS Surface Flake/FCR N Y N Y Hwy relocation 1979-012 8 IF Surface Core ? Y N Y Hwy relocation 1976-013 9 IF Surface Flake N Y N Y Flooding 1976-013
H10 Historic Surface Logs, sq-head nails, cables
N N N N Flooding 1976-013
HbRj 11 IF Surface Chopper N Y N Y Hwy relocation 1978-014
20 LS Surface 9 flakes, 1 core N Y N Y Hwy relocation. Site
straddles AZ boundary
77-9/78-14
21 IF Subsurface Flake Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14
I.R. Wilson Consultants Ltd. Appendix A- 13
Site Type
Surface or Subsurface
Site Comments
Collected?
Protected (HCA)?
Tested? # STs / EUs Fieldwk Needed?
Conflict/ Comments
Permit #s
22 LS Subsurface 9 flakes Y Y Y 1-1x1 m unit Y N – outside TEM 1977-009 2005-163 23 LS Surface 5 flakes Y Y N Y Hwy relocation 77-9/78-14
24 LS Surface 9 Flakes (1 util.), core
N Y N Y Hwy relocation 77-9/78-14
25 LS Subsurface 2 flakes Y Y Y 1-1x1 m unit Y Hwy relocation 77-9/78-14
26 LS Surface 300
Flakes/tools in 17 x 28 m area
N Y Y 1 neg 1x1 m unit Y Hwy relocation 77-9/78-14
H27 Hist.Bldgs N/A Log cabin, 2
barns, ca 1944 N/A N N N Hwy relocation 77-9/78-14
28 LS Surface Flake, ret.
Flake ? Y N Y Hwy relocation 1976-013
I.R. Wilson Consultants Ltd. Appendix A- 14
Glossary:
HCA = Heritage Conservation Act
Site Type: LS = lithic scatter IF = isolated find
CD = cultural depression TU= traditional use site
Legacy = site determined by Archaeology Branch as non-cultural, not locatable, unprotected by HCA and/or of insufficient interest or significance to warrant documentation
Repositories:
FSJNPM = Fort St John/North Peace Museum, Fort St. John Nat. Mus. = Museum of Civilization (formerly National Museum), Hull
RBCM = Royal British Columbia Museum, Victoria Owner = landowner at time of site documentation
Note: Collections all to SFU Dep’t of Archaeology unless otherwise noted.
Appendix B
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
GlRk 1Modeling purposes only
yLeft as is, in correct general location along eastern upper terrace of canyon
no l-m yes
~340 m away from transmission line
GlRk 3Transmission
yMoved slightly north to fall on transmission line cut, unable to determine exact location due to lack of detailed info
yes l yes
HaRe 18 Modeling purposes only
yLeft as is, site form too vague and distance inaccurate, appears to be outside transmission line and construction areas
no l yes~600 m from transmission line
HaRe 20 Modeling purposes only
y Not enough data to plot, no l yesmay not need to include in model
HaRg 2 Slide Area y Moved slightly south in accordance with sketch map yes h yes
HaRg 3Transmission
yLeft as is, cannot reconcile, likely impact negligible, artifact collected
no l yes
HaRg 4Slide Area
yConsistent with GPS coordinates, did not move, could not confirm with written access description
no m yes
HaRg 11 Modeling y Plots at given UTM coordinates taken from GPS in field, left no h yes
HaRh 1Modeling purposes only
yleave as is, cannot distinguish between road and railbed, site is on road
no m yes
HaRi 1Modeling purposes only
yLeft as is, site located on SE side of road at approximate distance from Big Lake given on site form
no l-m yes
HaRj 1Impact Line Work/Highway Relocation
y yMoved based on terrace edge, poor site description and map
yes l yes
HaRj 10Impact Line Work/Highway Relocation
y y Moved based on original site map and written description yes m-h yes
HaRj 11Modeling purposes only
y Left as is, isolated find in hay field no m yes
HaRj 12Modeling purposes only
yMoved to approximate location as given on original site sketch map
yes l-m yes~215 m from permit app line
HaRj 13Impact Line Work/Highway Relocation
y y Confirmed based on original site description no h yes
HaRj 14Impact Line Work/Highway Relocation
y yMoved and expanded site area from 1 x 1 m to 30 x 8 m based on verbal description of measurements and location
yes m yes
HaRj 15Impact Line Work/Highway Relocation
y y Moved based on original site map and verbal description yes m yes
HaRj 16Impact Line Work/Highway Relocation
y y Moved based on original site map and verbal description yes m yes
HaRj 17Impact Line Work/Highway Relocation
y yMoved southwest to edge of gravel pit in accordance with distance and bearing measurements on site form sketch map
yes m-h yes
HaRj 18Impact Line Work/Highway Relocation
y y Moved based on original site map and verbal description yes m yes
HaRj 19Impact Line Work/Highway Relocation
y yMoved slightly back onto terrace edge, ~600 artifacts in one EU, site likely extends further
yes m yes
HaRj 2Modeling purposes only
yMay be 600 m too far to the NE but too little information to move
no l yes
HaRj 21Impact Line Work/Highway Relocation
y yMoved to terrace edge - site form says 50 x 10 m, but left as 1 x 1 m as no site boundary on original map
yes l yes
HaRj 22Full Supply Level
yMoved both HaRj 22 and 24 to lower terrace and spaced ~89 m apart as per site form description
yes l yes
HaRj 23Impact Line Work/Highway Relocation
y y Moved based on association with HaRj 21 and site sketch yes l-m yes
HaRj 24Full Supply Level
yMoved both HaRj 22 and 24 to lower terrace and spaced ~89m apart as per site form description
yes l yes
HaRj 3 Modeling purposes only
yMoved south to "animal path" along edge of terrace in accordance with written description and extremely vague site sketch
yes l yes~100 m outside boundary
HaRj 4Impact Line Work/Highway Relocation
y yMoved based on location of gravel pit on ortho photo and tractor cut on lidar
yes l-m yes
I.R. Wilson Consultants Ltd. Appendix B - 1
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HaRj 5Impact Line Work/Highway Relocation
y y Moved based on sketch map and lidar scarp edge yes m yes
HaRj 6Full Supply Level
ymoved based on sketch map and description, 5 m from terrace edge as seen on lidar
yes m yes
HaRj 7Full Supply Level
y moved based on sketch map and description yes m yes
HaRj 8Impact Line Work/Highway Relocation
y y moved based on written description and site map yes m yes
HaRj 9Impact Line Work/Highway Relocation
y yMoved slightly towards terrace edge, site desciption says 50 m long, RAAD shows 75 m, left polygon same shape
yes m-h yes
HaRk 1
Inundation/Impact Line Work/Highway Relocation
y y y Left as is - already reconcilled by Archaeology Branch no h yes
HaRk 10
Inundation/Impact Line Work/Highway Relocation
y y yLeft as is - site description seems to plot in approximately same location
no h yes
HaRk 11Modeling purposes only
y Moved onto field as per written instructions and sketch map yes h yes65 m outside boundary
HaRk 12
Inundation/Impact Line Work/Highway Relocation
y y y Left as is based on site map and description no h yes
HaRk 13
Inundation/Impact Line Work/Highway Relocation
y y yLeft as is, should be easy to locate in field as part of site is cabin
no h yes cabin on site
HaRk 14Impact Line Work/Highway Relocation
y yRe-drew site boundary to more accurately reflect site sketch map
no h yes
HaRk 15Impact Line Work/Highway Relocation
y yLeft as is, site dimensions may be inaccurate, site form says 20x40m but testing not done to confirm this
no h yes
HaRk 16
Inundation/Impact Line Work/Highway Relocation
y y y Left as is, site dimensions appear correct no m-h yes
HaRk 17Impact Line Work/Highway Relocation
y ySite length doubled and moved to follow old Hwy 29 RoW to be more consistent with site sketch
yes m-h yes
HaRk 18Impact Line Work/Highway Relocation
y y Moved site SW to match written description and sketch map yes m-h yes
HaRk 19Impact Line Work/Highway Relocation
y y Left as is based on site description and sketch map no m yes
HaRk 2
Inundation/Impact Line Work/Highway Relocation
y y y Impossible to reconcile, bad map, poor directions… no low to nil yes
HaRk 20Impact Line Work/Highway Relocation
y yLeft as is, moved to west based on pole location shown on HaRk 21 sketch map
no l yes
HaRk 21Impact Line Work/Highway Relocation
y yRe-drew according to written site dimensions along transmission line
no m-h yes
HaRk 22Impact Line Work/Highway Relocation
y yLeft as is based on sketch map, but distance from road junction to site is incorrect on site form (given in miles but should be km)
no m-h yes
HaRk 23
Inundation/Impact Line Work/Highway Relocation
y y yMoved approximately 200m based on directional measurements given on sketch map
yes m yes
HaRk 24Impact Line Work/Highway Relocation
y yMoved to west and south based on site description and sketch measurements, moved to inside innundation zone, reduced site area to reflect site description as isolated find
yes l-m yes
I.R. Wilson Consultants Ltd. Appendix B - 2
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HaRk 25Impact Line Work/Highway Relocation
y yMoved south and west based on measurements on sketch map
yes l-m yes
HaRk 26Impact Line Work/Highway Relocation
y yMoved south and east to lie on road according to site sketch map and written description
yes m yes
HaRk 27Impact Line Work/Highway Relocation
y yMoved to east side of last pole in accordance with site form access information, enlarged site area to 10 x 10m
yes m-h yes
HaRk 29Impact Line Work/Highway Relocation
y yLocation unchanged; however site area given as 1/2 acre not a point as shown
no m-h yes
HaRk 30Impact Line Work/Highway Relocation
y yWritten site access instructions confusing, moved slightly west to match measurements from Zelinka's cabin (HaRk 31)
yes m yes
HaRk 31Impact Line Work/Highway Relocation
y yChanged polygon from point to include all three structures as seen on ortho photo
no m-h yes
HaRk 32
Inundation/Impact Line Work/Highway Relocation
y y yReduced site size, moved slightly to NW into centre of field to match site description
no h yes
HaRk 33
Inundation/Impact Line Work/Highway Relocation
y y ySite has been legacied by Arch Branch - did not adjust location
no low to nil yes
HaRk 34
Inundation/Impact Line Work/Highway Relocation
y y yMoved closer to Farrell Creek in accordance with site description and site sketch map
yes m-h yes
HaRk 35Impact Line Work/Highway Relocation
y yPoor written directions, moved based on relationship to HaRk-30
yes m yes
HaRk 36Impact Line Work/Highway Relocation
y yLeft as is, site is in approximate location but not enough detail on site form to be confident in location
no l yes
HaRk 37Impact Line Work/Highway Relocation
y yMoved west and south to terrace edge as per sketch map and site description
yes l-m yes
HaRk 38Impact Line Work/Highway Relocation
y yMoved south and west to edge of forested area and across Peace River from stream to match site description; written site dimensions not consistent with map or RAAD polygon
yes l-m yes
HaRk 4Impact Line Work/Highway Relocation
y yLeft as is, could not determine from sketch or written info exact location
no l yes
HaRk 40Impact Line Work/Highway Relocation
y yReduced site dimensions to match written description and to move site entirely onto terrace
yesh for location
but m for length
yes
HaRk 41Impact Line Work/Highway Relocation
y yMoved slightly west and reduced size due to disbelief that site is as large as stated - missing decimal?
yes l yes
HaRk 42Impact Line Work/Highway Relocation
y yMoved slightly west and reduced size due to disbelief that site is as large as stated - missing decimal?
yes l yes
HaRk 5Impact Line Work/Highway Relocation
y yLeft as is as no site map - form for nearby site HaRk 4 also unsuccessfully examined for possible HaRk 5 location.
no m yes
HaRk 6
Inundation/Impact Line Work/Highway Relocation
y y yMoved to top of terrace from creek bed. Immediately north of highway and east of dry creek bed, site dimensions not accurate, no map provided
yes m yes
HaRk 7Impact Line Work/Highway Relocation
y y Left as is - no map provided no m-h yes
HaRk 8
Inundation/Impact Line Work/Highway Relocation
y y y Moved to top of terrace from creek bed. No map provided yes m-h yes
HaRk 9Full Supply Level
ySite description too vague to plot but is in general area of current polygon locations
no l yes
I.R. Wilson Consultants Ltd. Appendix B - 3
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HaRl 1 Modeling purposes only
yLeft as is, location of cemetery too vague from site form but should be locatable on ground once in Hudson's Hope. HaRl 1 and HaRl 2 may be same site.
no l yes native graveyard
HaRl 10
Inundation/Impact Line Work/Highway Relocation
y y y Left as is - very poor site form and sketch map no low to nil yes
HaRl 12 Modeling purposes only
yAccess description on site form does not match site location shown on RAAD but may be 850 m to the NE in possible conflict with highway realignment
no l yes
HaRl 13Modeling purposes only
y Moved to power line cut and Lynx Creek yes m-h yes
HaRl 14Impact Line Work/Highway Relocation
y yMoved to end of previous access road as shown on LIDAR; site dimensions given as 30x30 m, not a point
yes m-h yes
HaRl 15 Impact Line y y Cannot verify, not shown on sketch map, directions poor no l yes
HaRl 16Modeling purposes only
yMoved slightly to the north and west along terrace edge to approximate location shown on site sketch map
yes m yes
HaRl 17Modeling purposes only
yMoved slightly to the west to top of terrace edge to match site form sketch map
yes m yes
HaRl 18
Inundation/Impact Line Work/Highway Relocation
y y yMoved and rotated polygon to fit landform and match written description on site form
yes m yes
HaRl 19Impact Line Work/Highway Relocation
y y Moved to road based on sketch map and landform yes m yes
HaRl 2Modeling purposes only
yMay be same site as HaRl 1, left as is, see comment for HaRl 1
no l yes yesPioneer Cemetery
HaRl 20Full Supply Level
yMoved to east side of road based on distance recorded on site form and sketch map
yes h yes
HaRl 21Full Supply Level
yMoved to east side of road based on distance recorded on site form and sketch map
yes h yes
HaRl 22Full Supply Level
yMoved to east side of road based on distance recorded on site form and sketch map and lidar
yes h yes
HaRl 23Full Supply Level
y
Site noted to be close to old ferry terminal; site dimensions not accurate on RAAD but could be as much as 150m long; moved to approximate location of white rock as noted in HaRl 24
yes l-m yes
HaRl 24Full Supply Level
y Moved based on site description and sketch maps yes m yes
HaRl 3Impact Line Work/Highway Relocation
y y Left as is at end of Bodekar Road, no site sketch no m-h yes
HaRl 4Full Supply Level
yMoved to edge of Peace River - site references ferry and historic building
yes m-h yesincludes historic buildings onsite
HaRl 5 Full Supply Level
ySite location based on unconfirmed anecdotal information - has been legacied by Archaeology Branch
no l yesreported ceremonial boulder
HaRl 6Impact Line Work/Highway Relocation
y yMoved to SW corner of Dudley & Rutledge to be more consistent with Lat/Long coordinates on site form
yes l yes
HaRl 7 Full Supply Level
yMoved to island in accordance with site form description; however site legacied by Archaeology Branch as non-site.
yes l-m yessandstone blocks
HaRl 9 Modeling purposes only
yLeft as is, written site form directions lead to current location, but sketch map shows roads that don't seem to exist
no l yes
HbRe 1 Modeling purposes only
yLeft as is, appears to be in correct location as described on 1954 form, but 1974 update states that site could not be re-located.
no l yes"Old Fort" - fur trade fort
HbRe 12Modeling purposes only
yMoved slightly east to place in road cut as per site sketch map
yes l-m yes
HbRe 2Modeling purposes only
yMoved closer to Peace River as per written site form instructions
yes l-m yesPolice Building - 1910
HbRe 4Modeling purposes only
yMoved to west, along bluff edge near apparent gas well as shown on ortho photo and as indicated on site form
yes m yes
HbRe 5Modeling purposes only
yMoved west to top of 2nd bluff from west edge of field as indicated on site form
yes m yes
I.R. Wilson Consultants Ltd. Appendix B - 4
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRe 6Modeling purposes only
y Moved onto bluff as indicated on site form yes l-m yes
HbRe 32Till Investigation
yLeft as is based on written site description and map, however coordinates given are inaccurate
no m yes Old Fort St John II
HbRe 54 Till Investigation
yLeft as is based on written site description and coordinates but site location appears to have been incorrectly switched with nearby site HbRe 55
no m-h yes
HbRe 55 Till Investigation
yLeft as is based on written site description and coordinates but site location appears to have been incorrectly switched with nearby site HbRe 54
no m-h yes
HbRf 1Till Investigation
y No data available to verify site location no l yes
HbRf 10Impact Line Work/Highway Relocation/Till Investigation
y y yNot locatable, coordinates incorrect, sketch map extremely poor
no l yes
HbRf 11Impact Line Work/Highway Relocation/Till Investigation
y y yNot locatable, coordinates incorrect, sketch map extremely poor
no l yes
HbRf 12Impact Line Work/Highway Relocation/Till Investigation
y y yNot locatable, coordinates incorrect, sketch map extremely poor
no l yes
HbRf 13Impact Line Work/Highway Relocation/Till Investigation
y y yMoved slightly west and rotated polygon to align with landform and fences on ortho photo. Good site form sketch map, based on air photo
yes h yes
HbRf 14Till Investigation
yNot locatable, coordinates incorrect, sketch map and directions extremely poor
no l yes
HbRf 15Till Investigation
yNot locatable, coordinates incorrect, sketch map and directions extremely poor
no l yes
HbRf 16Till Investigation
yNot locatable, coordinates incorrect, sketch map and directions extremely poor
no l yes
HbRf 17Till Investigation
yNot locatable, coordinates incorrect, sketch map and directions extremely poor
no l yes
HbRf 18
Impact Line Work/Highway Relocation/Till Investigation/Slide Area
y y y yNot locatable, coordinates incorrect, sketch map and directions extremely poor
no l yes
HbRf 19Impact Line Work/Highway Relocation/Till Investigation
y y yMoved slightly to the north and east and rotated polygon to lie along edge of field as per written description and site sketch map
yes m yes
HbRf 20Till Investigation
yMoved south into plowed field as per written site description and sketch map
yes l yes
HbRf 21Impact Line Work/Highway Relocation
y yMoved south and east to more closely resemble sketch map and approximate distance from road
yes m yes
HbRf 22Till Investigation
y Left as is based on written description and sketch map no l-m yes
HbRf 23Impact Line Work/Highway Relocation/Till Investigation
y y yLeft as is, unable to accurately choose the described 2 historic buildings from cluster of structures; should be obvious in field
no m yes
HbRf 24Till Investigation
yReshaped and moved slightly north to lie along edge of old stream/dune, general location okay
yes m yes
HbRf 25Impact Line Work/Highway Relocation/Till Investigation
y y yMoved north in accordance with distance measurements and sketch map
yes h yes
HbRf 26Till Investigation
yMoved north in accordance with site sketch map and location of HbRf 25
yes l-m yes
I.R. Wilson Consultants Ltd. Appendix B - 5
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRf 27Impact Line Work/Highway Relocation/Slide Area
y y y Moved to north along bluff in accordance with sketch map yes m yes
HbRf 28Impact Line Work/Highway Relocation/Slide Area
y y yMoved north into plowed field as per written description and sketch map
yes l-m yes
HbRf 29Full Supply Level/Dam Location
y yMoved to south side of Moberly River; unsure which terrace site belongs on as well as its orientation and distance to Peace River
yes l yes 4 natural depressions, tested 1981
HbRf 30Impact Line Work/Highway Relocation/Dam Location
y y y
Left as is, Alexander in 1981 states that despite extensive testing site could not be relocated and is likely destroyed due to gravel extraction, site dimension not plotted accurately, location appears correct according to written access description
no l yes
HbRf 31Full Supply Level/Slide Area
y yAppears to be in correct location, moved slightly west to top of terrace
yes l-m yesRocky Mountain Fort
HbRf 32Dam Location
yLeft as is, gravel pits surrounding current location, need to re-examine, may be destroyed
no l yes on edge of area of permit area
HbRf 33 Modeling purposes only
yLeft as is, believed to be in general area based on access description, Lat/Long coordinates place site south of highway
no l yes
HbRf 34Modeling purposes only
y Left as is, site form too poor to replot no l yes
HbRf 35Till Investigation
y Left as is, site form too poor to replot no l yes
HbRf 36Till Investigation
y Left as is, site form too poor to replot no l yes
HbRf 37Full Supply Level/Slide Area
y yMoved to east to lie along landform and apparent bulldozer cut in accordance with site form.
yes l yes
HbRf 40Impact Line Work/Highway Relocation/Dam Location
y y yRe-drew site boundary in accordance with site form sketch maps and descriptions; 2008 update states 1974 site dimensions and configuration appear to be accurate
yes h yes
HbRf 41
Full Supply Level/Dam Location/Slide Area
y y yMoved to edge of highest terrace based on detailed sketch map and landform on LIDAR
yes m yes
HbRf 42Full Supply Level/Slide Area
y yMoved to edge of Peace River in apparent caterpillar cut in accordance with site form description
yes l yesash/shell deposit only
HbRf 43Slide Area
yMoved to terrace edge along "tractor cut" to more closely resemble sketch map
yes l yes
HbRf 44Till Investigation
yMoved to edge of field based on written site description, bearings and distances and sketch map
yes m-h yes
HbRf 45Slide Area
yMoved south and west to lie along seismic line at approximate distance from intersection as per site form
yes l yes
HbRf 46Slide Area
yLeft as is; poor written directions and sketch map which are inconsistent, cannot move accurately
no l yes
HbRf 47Slide Area
yLeft as is; poor written directions and sketch map which are inconsistent, cannot move accurately
no l yes
HbRf 48 Till Investigation
yLeft as is, appears in appoximate location based on sketch map, distances stated as originating from cabin but specific cabin is undeterminable
no m yes
HbRf 50 Till Investigation
yLeft as is, unclear as to rationale for site dimensions shown on site form, location approximates coordinates given on form
no l yes
HbRf 51Impact Line Work/Highway Relocation/Till Investigation
y y yMoved north based on sketch map but could not confirm by distance along road given on site form
yes l yes
HbRf 54Till Investigation
yMoved SW and rotated polygon to align with site form written description and sketch map
yes m yes
I.R. Wilson Consultants Ltd. Appendix B - 6
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRf 55Impact Line Work/Highway Relocation/Till Investigation
y y yLeft as is, could not reference, many discrepencies between written directions and sketch map
no l yes
HbRf 56Impact Line Work/Highway Relocation/Till Investigation
y y yLeft as is, could not reference, many discrepencies between written directions and sketch map
no l yes
HbRf 57Impact Line Work/Highway Relocation/Till Investigation
y y yLeft as is, could not reference, many discrepencies between written directions and sketch map
no l yes
HbRf 58Impact Line Work/Highway Relocation/Till Investigation
y y yMoved site to opposite side of landform in accordance with site sketch map
yes h yes
HbRf 59
Full Supply Level/Dam Location/Slide Area
y y y
Moved to intermediate terrace from lower terrace in accordance with site form description, sketch map looks like site at the edge of the terrace, Alexander reports site destroyed 1981
yes l yes
HbRf 60
Full Supply Level/Dam Location/Slide Area
y y yMoved to top of terrace along dirt road in accordance with sketch map and written instructions
yes l yes
HbRf 61
Full Supply Level/Dam Location/Slide Area
y y yMoved to intersection of road cuts in accordance with site form sketch map
yes l yes
HbRf 62
Full Supply Level/Dam Location/Slide Area
y y yMoved slightly NW to edge of Moberly River in accordance with site form and sketch map
yes h yes
HbRf 63Dam Location
yMoved to centre of clearing as shown on site form sketch map, increased site dimensions to ~5 x 5m
yes h yes
HbRf 64Dam Location
yRe-sized and moved to the west in accordance with distance and bearing measurements from edge of field as indicated on site form
yes h yes
HbRf 65Dam Location/Slide Area
y yLeft as is, site location matches description on site form, dimensions not correct in RAAD and possibly on site form
no h yes
HbRf 66Dam Location
yRe-drew site boundary as per site form sketch map associated and to conform with landforms shown on LIDAR
yes h yes
HbRf 67Dam Location/Slide Area
y yLeft as is, isolated find has been collected, site could not be relocated by Alexander in 1981 - stated as likely destroyed
no m yes
HbRf 68Dam Location
yBison remains spread over large area were collected, unprotected site, did not adjust site boundary but location is accurate according to site form
no h yes
HbRf 69Dam Location
yMoved into gravel pit in accordance with site form, site stated as likely destroyed
yes l yes
HbRf 79Till Investigation
y
Left as is, mapped according to site UTM coordinates which seem accurate and are along referenced road; however Borden numbers may be mixed up between HbRf 80 and HbRf 79
no m yes
HbRf 8
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly to lower terrace as shown on LIDAR to conform with site sketch map
yes m yesburned sandstone slabs
HbRf 80Till Investigation
y
Left as is, mapped according to site UTM coordinates, which seem accurate and are along referenced road; however Borden numbers may be mixed up between HbRf 80 and HbRf 79
no m yes
HbRf 81Till Investigation
yLeft as is, appears to be in correct location by written description and site coordinates
no h yes
HbRf 82Dam Location/Slide Area
y yMoved slightly north to top of ridge as per site form directions, could not locate siesmic line on ortho photo or LIDAR
yes l yes
I.R. Wilson Consultants Ltd. Appendix B - 7
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRf 9Impact Line Work/Highway Relocation/Slide Area
y y yMoved slightly west to top of bluff as per site access description on form
yes m yes
HbRg 10Modeling purposes only
yMoved west to edge of bluff overlooking gully in accordance with site form sketch map
yes m yes
HbRg 11
Inundation/Impact Line Work/Highway Relocation
y y y
Moved site north to top of terrace and extended site boundary to ravine edge of Tea Creek in accordance with site form sketch map. However site dimensions are now not consistent with site form written description.
yes m-h yes
HbRg 12Modeling purposes only
yLeft as is, appears to be in correct location based on site form sketch map
no m yes
HbRg 13Impact Line Work/Highway Relocation
y yLeft as is, site description and map are sketchy but likley that site is below major slope on slope break above the field
no m yes
HbRg 14Impact Line Work/Highway Relocation
y yMoved to edge of terrace, site form and sketch map poor and could not accurately locate
yes l yes
HbRg 15 Impact Line Work/Highway Relocation
y y
Re-drew so site was large polygon, not point as initially shown on RAAD, as it is a large site; site form indicate 100 x 2000 yards along intermediate terrace of the Peace River on same landform as HbRg 4 and 28, not confident of dimensions
yes m yespossible village site
HbRg 16Full Supply Level/Slide Area
y yLeft site as is, plotted based on Lat/Long coordinates recorded on site form, sketch map provides no additional information
no l yes
HbRg 17Impact Line Work/Highway Relocation
y y Moved slightly west to match location on site sketch map yes m yes
HbRg 18Impact Line Work/Highway Relocation
y yMoved south to road cut, extended boundary to be 60 x 10m along road as per site form description, exact location of site along road is not known
yes m yes
HbRg 19Impact Line Work/Highway Relocation
y yMoved south to top of break and edge of Wilder Creek ravine based on sketch map and written description
yes m-h yes
HbRg 20Impact Line Work/Highway Relocation
y yLeft as is, cannot accurately determine location but is currently located on the correct landform as per site description
no l-m yes
HbRg 21Impact Line Work/Highway Relocation
y y Left as is based on site form sketch map no m-h yes
HbRg 22 Full Supply Level
yMoved to top of terrace and immediately south of apparent coulee to be consistent with site form description
yes m yes
HbRg 23Full Supply Level/Slide Area
y yLeft as is based primarily on bearing to Wilder Creek, no distance given
no l yes
HbRg 24Impact Line Work/Highway Relocation
y yMoved to edge of terrace in accordance with site sketch map; site dimensions listed as 5 x 16 m but left as point as we could not determine site orientation
yes m-h yes
HbRg 25Impact Line Work/Highway Relocation
y yMoved to edge of landform as indicated on site form and sketch map
yes m-h yes
HbRg 26Modeling purposes only
yLeft as is, appears to be in correct location based on site form sketch map
no m-h yes
HbRg 27Impact Line Work/Highway Relocation
y y Left as is, based on site sketch map no h yes
HbRg 28Impact Line Work/Highway Relocation
y yLeft as is, site consists of two areas (3 buildings) 100m apart. As currently shown site boundary only includes most easterly area.
no m-h yes
HbRg 29Slide Area
y Moved onto seismic line as per site form and sketch map yes m-h yes
HbRg 30Impact Line Work/Highway Relocation
y yLeft as is, could not verify based on bearings and distances given on site form, seems to be on correct landform, no sketch map available
no l yes
HbRg 31 Modeling purposes only
y Left as is based on site sketch map no m yesoutside boundary (47 m)
I.R. Wilson Consultants Ltd. Appendix B - 8
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRg 32Impact Line Work/Highway Relocation
y yMoved to west onto terrace edge according to site sketch map, site is erroding out of bluff
yes l-m yes
HbRg 33Impact Line Work/Highway Relocation
y yMoved to north and west to edge of bluff in accordance with site form
yes l-m yes
HbRg 35Impact Line Work/Highway Relocation
y yMoved to east along edge of bluff in accordance with site form, distance and bearing on site form incorrect?
yes l-m yes
HbRg 36Till Investigation
yLeft as is, site location matches description on site form and sketch map
no h yes
HbRg 37Till Investigation
yNo LIDAR or ortho photo but just inside boundary; could not confirm location
no l yes
HbRg 38Slide Area
yLeft as is, site form indicates location as on trail at top of bank
no h yes
HbRg 4Impact Line Work/Highway Relocation
y yMoved to first terrace on point of bluff close to ravine as per sparse information on site form
yes l-m yes
HbRg 5Impact Line Work/Highway Relocation
y yMoved site boundary slightly north to straddle road and sit on terrace edge, dimensions are vague
yes h yes
HbRg 6Impact Line Work/Highway Relocation
y yMoved boundary slightly upslope to include portion of the top of the terrace; however, unsure of dimensions but fairly confident site is in correct location
yes m-h yes
HbRg 7Impact Line Work/Highway Relocation
y yMoved to top of mound in plowed field as per site form and site sketch map
yes m yes
HbRg 8Modeling purposes only
yMoved to west along road in accordance with site form description
yes l yes
HbRg 9Modeling purposes only
yMoved west to opposite side of road and slightly south in accordance with site form sketch map
yes l yes
HbRh 1
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly north to straddle rim of "Bentley's Island" as noted on site map and site description, site dimensions appear not to be accurately recorded
yes m-h yesstraddles boundary
HbRh 10Impact Line Work/Highway Relocation
y yMoved north and east to road and on terrace edge, re-drew to match site dimesions
yes l yes
HbRh 100Modeling purposes only
y Left as is based on coordinates given on site form no m yespossible island in flood area
HbRh 101Modeling purposes only
y Left as is based on coordinates given on site form no m yespossible island in flood area
HbRh 102Slide Area
yLeft as is written access description too vague to accurately plot but is on correct landform
no l-m yes
HbRh 11Impact Line Work/Highway Relocation
y yMoved east and north to approximate location as shown on site sketch, described as on old field road which does not appear on LIDAR
yes l yes
HbRh 12Impact Line Work/Highway Relocation
y y
Site dimension improbable, huge site in plowed field; site form access description too vague to plot site accurately but is near Watson's Sunny Hills Ranch, needs to be verified in field
no l yes
HbRh13Modeling purposes only
y
Moved west and south based on site form sketch map and written description, site dimensions given as 200 x 200 m but there is no way to confirm size, RAAD depicts it as a point
yes l-m yes
HbRh 16Impact Line Work/Highway Relocation
y y Moved slightly north and west just off terrace edge yes m-h yes
HbRh 17
Inundation/Impact Line Work/Highway Relocation
y y yMoved entirely onto field, but given site dimensions of 600 x 450 m appear to be significantly overestimated; however general location appears correct
yes m-h yesstraddles boundary
HbRh 18
Inundation/Impact Line Work/Highway Relocation
y y yMoved to west and north slightly to be on slope as per site form, altered site dimensions to match site form
yes m yes
HbRh 19
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to east to incorporate gully and north to off Hwy 29, increased length to enclose western artifact find; however poor site form and map
yes m yes
I.R. Wilson Consultants Ltd. Appendix B - 9
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRh 2
Inundation/Impact Line Work/Highway Relocation
y y yMoved to top of terrace, site drawn as significantly larger than dimensions given
yes m-h yes
HbRh 20
Inundation/Impact Line Work/Highway Relocation/Slide Area
y y y yMoved north to top of terrace out of trees and into plowed field - may be part of HbRh 21
yes m yes
HbRh 21
Inundation/Impact Line Work/Highway Relocation/Slide Area
y y y y
Moved site north to lie north of bluff, concentration of artifacts noted to be mainly on tops of knolls. Site dimension seem to be grossly exaggerated and may be composed of many smaller sites -needs testing to confirm
yes l yes
HbRh 22Impact Line Work/Highway Relocation
y yLeft as is, general feeling is that NE end of site is likely close to proper location but SW corner extends too far. Site dimensions not consistent with site description
no l-m yes
HbRh 23Modeling purposes only
yLeft as is, written access description confusing, no sketch map
no l yes
HbRh 24Impact Line Work/Highway Relocation
y y Moved site to edge of terraces based on sketch map yes m-h yes
HbRh 26Impact Line Work/Highway Relocation
y yMoved slightly west so site is close to stream complex and falls within gravel pit area as per site form
yes m yes
HbRh 27
Inundation/Impact Line Work/Highway Relocation
y y yMoved east to hummock noted on site form and south of field road
yes m yes
HbRh 28Full Supply Level
yMoved northeast to road to be consistent with stated distance of 75 east of forest
yes m yes
HbRh 29
Inundation/Impact Line Work/Highway Relocation
y y yMoved south and west to point 10 m from road and closer to Peace River accordance with site form
yes l-m yes
HbRh 30Impact Line Work/Highway Relocation
y y Moved to creek bed from edge as per site form description yes l yes
HbRh 31 Modeling purposes only
yLeft as is, location seems to be correct based on site form,;site dimensions inaccurate - isolated find, redrew as 2.5m radius circle
no m yes
HbRh 32
Inundation/Impact Line Work/Highway Relocation
y y yLeft as is, location is approximate (2 items found), but nothing to justify moving, current location appears good
no l-m yes
HbRh 33Impact Line Work/Highway Relocation
y y
Re-drew site boundary to reflect 1979 map which was prepared following 1977 excavation, excluding hwy and gravel pit; site dimension given as 552 m but probably meant 55.2m?
no m-h yes
HbRh 34
Inundation/Impact Line Work/Highway Relocation
y y yMoved site north and west to lie on top of terrace and in prairie, shortened site to place site entirely on prairie as per site form
yes m yes
HbRh 35Inundation
yMoved east and north to lie along terrace edge, reshaped polygon to be 20 x 30m as per site form
yes l-m yes
HbRh 36
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to west along road to end of 'cattle trail', 4 find spots - 39 flakes, 3 cores, 1 microblade. Tested 1976, refers to "attached report" but not evident
yes m-h yes
HbRh 37
Inundation/Impact Line Work/Highway Relocation
y y y Moved slightly NE to end of landform south of Hwy 29 yes m yes
HbRh 38
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly to the SW and increased in size to place within unforested area as per site form sketch map
yes m-h yes
HbRh 40Impact Line Work/Highway Relocation
y yMoved to west on top of terrace edge and reduced n-s dimension as per site form
yes m-h yes
I.R. Wilson Consultants Ltd. Appendix B - 10
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRh 41Impact Line Work/Highway Relocation
y yLeft as is, appears to be in correct location by written description and sketch map, may not be impacted
no m-h yes
HbRh 42Impact Line Work/Highway Relocation
y yRe-drew to south and west to match site sketch and moved to impact zone; however, given site dimensions are inconsistent with map
no m-h yes
HbRh 44
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly NW onto edge of terrace, site dimesions left as given but may be longer, may not be impacted
yes m yes
HbRh 45Inundation
yMoved to upper terrace and further N along Peace River in accordance with site form sketch map; however specific location on terrace is ambiguous
yes l-m yes
HbRh 46
Inundation/Impact Line Work/Highway Relocation
y y yMoved site east and down to bottom of slope in accordance with site form description
yes l-m yes
HbRh 47Impact Line Work/Highway Relocation
y yMoved site slightly west of original location using site form transmission pole reference (found on ortho) and distance and bearing info as per site form
yes m-h yes
HbRh 48 Impact Line Work/Highway Relocation
y y
Moved site slightly south and east of original location using site form transmission pole reference (found on ortho) and distance and bearing info as per site form; site form indicates location on top of 4m high hill but could not confirm hill location on LIDAR
yes m yes
HbRh 49Impact Line Work/Highway Relocation
y yMoved to edge of terraces in accordance with site map, written description inconsistent with map
yes l yes
HbRh 50Impact Line Work/Highway Relocation
y y
Moved south and west in accordance with site sketch and written description using site form transmission pole reference (found on ortho) and distance and bearing info as per site form
yes m-h yes
HbRh 51Impact Line Work/Highway Relocation
y yMoved site south to terrace edge; located transmission line pole referenced on site form but bearings from pole appear to be 180 degrees off.
yes l yes
HbRh 52
Inundation/Impact Line Work/Highway Relocation
y y yMoved west to foot of terrace to be more consistent with site form however location along terrace is too vague and written access instructions too complex to follow confidently.
yes l yes
HbRh 53
Inundation/Impact Line Work/Highway Relocation
y y yMoved site SSW to top of small rise of land between road junction
yes m yes
HbRh 54Impact Line Work/Highway Relocation
y yMoved north to comply with written description of site location, bearings and distance from fence line
yes m yes
HbRh 55Impact Line Work/Highway Relocation
y y
Moved to opposite side of road in accordance with site sketch map, placed in depression along terrace edge but written access description is too vague to confirm exact location
yes l-m yes
HbRh 56
Inundation/Impact Line Work/Highway Relocation
y y yMoved 750m SW to approximate location as per site sketch as coordinates given are inaccurate. May be much larger site 1 unit = 500+ flakes and tool
yes l-m yes
HbRh 57 Modeling purposes only
y Moved to approximate location based on site sketch yes l yesoutside boundary (85 m)
HbRh 58
Inundation/Impact Line Work/Highway Relocation
y y yMoved to approximate location based on site sketch and bearing and distance information
yes m yes
HbRh 59 Impact Line Work/Highway Relocation
y y
Moved site boundary significantly. Noted inconsitency in that sketch maps references two possible sets of buildings as HbRh 59, but written description notes that only one, the furthest north set of buildings, is HbRh 59. The other is HbRh 60
yes m yes
HbRh 6
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly northwest and rotated polygon so site would follow terrace edge and extend into wooded area as per site form description
yes m-h yes
I.R. Wilson Consultants Ltd. Appendix B - 11
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRh 60
Inundation/Impact Line Work/Highway Relocation
y y yMoved HbRh 60 to original RAAD location of HbRh 59 as 59 is located further north as per site sketch map
yes h yes
HbRh 61Impact Line Work/Highway Relocation
y y Moved north slightly in accordance with site sketch map yes m yes
HbRh 62Modeling purposes only
y
Moved north to approximate location as shown on sketch map, however road construction in area (shown on ortho photo) since 1978 when site recorded makes determination of exact location problematic
yes l-m yesoutside boundary (60 m)
HbRh 63Impact Line Work/Highway Relocation
y y
Moved north to top of terrace, reshaped to conform with site dimension, however road construction in area (shown on ortho photo) since 1978 when site recorded makes determination of exact location problematic
yes m yes
HbRh 64Impact Line Work/Highway Relocation
y y
Moved north and east to approximate location as per site sketch, however road construction in area (shown on ortho photo) since 1978 when site recorded makes determination of exact location problematic
yes l-m yes
HbRh 65
Inundation/Impact Line Work/Highway Relocation
y y y
Moved north based on ortho photo showing possible sand dune and caterpillar cut as referenced in site form, map inconclusive, coordinates inaccurate, used site access description to relocate
yes l yes
HbRh 66
Inundation/Impact Line Work/Highway Relocation
y y yMoved north and east between two ponds in boggy area as per site description, identification of specific ponds is unclear
yes l-m yes
HbRh 67Impact Line Work/Highway Relocation
y yMoved from lower to intermediate terrace as per written description, placed in approximate location as per poor sketch map
yes l yes
HbRh 68Impact Line Work/Highway Relocation
y yMoved north and east to old field road as per site sketch map
yes l yes
HbRh 69Impact Line Work/Highway Relocation
y yMoved site to east and north to lie in field as shown, altered shape dimensions as derived from sketch map (no site dimensions given on site form)
yes m yes
HbRh 7Modeling purposes only
yLeft as is, location approximate, site dimensions as given on site form
no m yespossible island in flood zone
HbRh 70 Modeling purposes only
yMoved north as per site sketch map and revised HbRh 69 boundary
yes l yesoutside boundary (72 m)
HbRh 71 Modeling purposes only
yMoved north and east as per site sketch maps and revised HbRh 69 boundary
yes l yesoutside boundary (32 m)
HbRh 72 Modeling purposes only
yMoved to next easterly field in accordance with sketch map and Lat/Long coordinates, re-drew site to 2.5m radius circle to reflect site category as isolated find
yes l-m yes
HbRh 73Modeling purposes only
yMoved to east in accordance with sketch map and Lat/Long coordinates
yes l-m yes
HbRh 74Modeling purposes only
yMoved to east in accordance with sketch map and Lat/Long coordinates
yes l-m yes
HbRh 75 Modeling purposes only
yMoved to east in accordance with sketch map and re-drew to more closely resemble written site dimensions and sketch map
yes l-m yes
HbRh 76Impact Line Work/Highway Relocation
y yMoved west to point on SW end of terrace as per site sketch
yes m yes
HbRh 77Impact Line Work/Highway Relocation
y yMoved to SW point on small point of land midway along landform based on sketch map
yes m yes
HbRh 78Impact Line Work/Highway Relocation
y yLeft as is; shown on RAAD in slump scar at edge of plateau which is not really determinable based on sketch map and site access info.
no l yes
HbRh 79Highway Realignment
y Left as is, appears to be in correct location from sketch map no h yes
HbRh 8Impact Line Work/Highway Relocation
y yMoved southwest to match site form sketch map. Note east end of site may have been impacted by gravel pit since original 1974 site form
yes m-h yes
HbRh 80 Highway Realignment
yLeft as is, cannot obtain approximate location from site description or site sketch, coordinates do not place site close to RAAD polygon
no l yes
I.R. Wilson Consultants Ltd. Appendix B - 12
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRh 81-85Highway Realignment
y
Left as is; coordinates on site form don't match RAAD locations, sketch maps too large-scale to accurately pick feature landform; site locations need to be confirmed in field before highway realignment occurs
no l yes
HbRh 87 Impact Line Work/Highway Relocation
y y
Moved east of highway realignment closer to transmission line pole located on ortho and mentioned on site form. Reduced site dimension to small radius circle as per site form update 1998 (1 positive shovel test)
yes m-h yes
to east of highway realignment not in TEM
HbRi 1 Modeling purposes only
yMoved to SW and rotated polygon to follow edge of field and site sketch map
yes l-m yesoutside boundary (33 m)
HbRi 10Inundation/Impact Line Work/Highway Relocation
y y y
Reduced site area on RAAD so as not to extend into forest and removed eastern portion in accordance with site form sketch map, location of site now matches written and site form sketch although dimensions inconsistent with written description of 250 x 200 m
yes h yes
HbRi 11
Inundation/Impact Line Work/Highway Relocation
y y y Moved slightly SW in accordance with site form map yes m yes
HbRi 12
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly NNW to edge of field, re-drew according to site sketch
yes m-h yes
HbRi 13Impact Line Work/Highway Relocation
y yMoved north and slightly west to straddle hwy and viewpoint access road as per site form map
yes h yes
HbRi 14Impact Line Work/Highway Relocation
y yMoved slightly north based on site sketch map, written access description poor
yes m yes
HbRi 15Impact Line Work/Highway Relocation
y y Moved slightly east to match site form sketch map yes m yes
HbRi 2Modeling purposes only
y Moved SW based on site map, written description vague yes l-m yes
moved to outside boundary (87 m)
HbRi 23 Modeling purposes only
yMoved north and west to hillock with tractor cut shown on LIDAR as per written site form instructions and sketch map
yes l-m yes
HbRi 24
Inundation/Impact Line Work/Highway Relocation
y y yMoved slightly east to old and new roads junction to follow site sketch map
yes m yes
HbRi 25
Inundation/Impact Line Work/Highway Relocation
y y yMoved north and west to place site on top of terrace at approximate distance from road junction in accordance with site form and sketch map
yes m yes
HbRi 26Modeling purposes only
y
Moved to west in accordance with detailed written distance and bearing measurements and placed on hummocky landform, reduced size of polygon to 5m diameter circle although further testing may prove site to be larger
yes m yesoutside boundary (340 m)
HbRi 27Impact Line Work/Highway Relocation
y y
Moved to west in accordance with detail written distance and bearing measurements, reduced size of polygon to 5m diameter circle although further testing may prove site to be larger
yes m yes
HbRi 28Impact Line Work/Highway Relocation
y y
Moved to NW in accordance with detailed written distance and bearing measurements, reduced size of polygon to 5m diameter circle although further testing may prove site to be larger
yes m yes
HbRi 29Impact Line Work/Highway Relocation
y y
Moved to east based on written description and bearing/distances from transmission pole as indicated on site form. No site map but detailed site access info provided on form
yes m yes
HbRi 3Modeling purposes only
y Moved SW based on site map and written description yes m yes
moved to outside boundary (33 m)
I.R. Wilson Consultants Ltd. Appendix B - 13
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRi 31Impact Line Work/Highway Relocation
y y
Moved to SW in accordance with detailed written distance and bearing measurements, reduced size of polygon to 5m diameter circle although further testing may prove site to be larger
yes m yes
HbRi 32 Modeling purposes only
yMoved to SW in accordance with written site access description and bearing/distance from pole 37/4 (found on ortho photo)
yes m yes
HbRi 33Impact Line Work/Highway Relocation
y y
Moved and re-drew to match site form sketch map. Directions to site on sketch map given as km but likely are miles; seems to encompass HbRi 9's relocated position so they may be the same site
yes m-h yes
HbRi 34
Inundation/Impact Line Work/Highway Relocation
y y yMoved north into field and re-drew according to site sketch map and written description. Likely joins with HbRi 33 and HbRi 9
yes m-h yes
HbRi 35Impact Line Work/Highway Relocation
y yHbRi 35 to 39 combined with HbRi 40 by Archaeology Branch. See note for HbRi 40.
yes m-h yes
HbRi 36Impact Line Work/Highway Relocation
y yHbRi 35 to 39 combined with HbRi 40 by Archaeology Branch. See note for HbRi 40.
yes m-h yes
HbRi 37Impact Line Work/Highway Relocation
y yHbRi 35 to 39 combined with HbRi 40 by Archaeology Branch. See note for HbRi 40.
yes m-h yes
HbRi 38Impact Line Work/Highway Relocation
y yHbRi 35 to 39 combined with HbRi 40 by Archaeology Branch. See note for HbRi 40.
yes m-h yes
HbRi 39Impact Line Work/Highway Relocation
y yHbRi 35 to 39 combined with HbRi 40 by Archaeology Branch. See note for HbRi 40.
yes m-h yes
HbRi 4 Modeling purposes only
yLeft as is, poor site description and sketch map make it impossible to obtain exact location, given as near unspecified gravel pit
no l yesoutside boundary (65 m)
HbRi 40Impact Line Work/Highway Relocation
y y
Plotted outside edge of new polygon HbRi-40 based on original site forms for Hbi 35 to 40 . Moved original site and expanded to north to capture all six relocated sites and place entirely in field
yes m-h yes
HbRi 41
Inundation/Impact Line Work/Highway Relocation
y y yReconfigured to land form and truncated east end of polygon to match written description and sketch map
yes h yes
HbRi 42
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to top of intermediate terrace in field according to distance and bearing info on site sketch map
yes m-h yes
HbRi 43
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to top of intermediate terrace in field according to distance and bearing info on site sketch map
yes m-h yes
HbRi 44
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to top of intermediate terrace in field according to distance and bearing info on site sketch map
yes m-h yes
HbRi 46
Inundation/Impact Line Work/Highway Relocation
y y yMoved site to road cut following distance and bearing info given on site form
yes m yes
HbRi 47
Inundation/Impact Line Work/Highway Relocation
y y yMoved 40 m south on road following distance and bearing info given on site form
yes m yes
HbRi 5Impact Line Work/Highway Relocation
y y Left as is, appears to match written site form update by BPH no m-h yes
HbRi 6Impact Line Work/Highway Relocation
y yLeft as is, 2008 revisit resulted in collection of artifacts from NW corner of site along Breakin Hill road, eastern extent of site not confirmed on either visit
no h yes
HbRi 7Impact Line Work/Highway Relocation
y yLeft as is, no site sketch map, depressions are stated as down hillside, poor access description
no l yes
I.R. Wilson Consultants Ltd. Appendix B - 14
Appendix B: Table 2
Arch Site Conflict Dam Area Slide AreaInundation
ZoneHighway
RelocationImpact Line
WorkTill
InvestigationOnly for
ModelingTransmission
LineComments on Site relocation and/or Verification Moved
Site Location
Confidence Level
Historic Paleontological Legacy Lithic Comment
HbRi 8Impact Line Work/Highway Relocation
y yLeft as is, poor site sketch and written description making accuratesite re-location impossible
no l yes
HbRi 9
Inundation/Impact Line Work/Highway Relocation
y y yMoved north into field from bottom of terrace based on site form description, directions and distances which seem consistent with site map
yes m yes
HbRj 1Impact Line Work/Highway Relocation
y y
Moved point to edge of ravine ~225m from original location although information to vague to plot actual site; site form indicates site is on both sides of ravine based on antecdotal info from landowner
yes l yes
HbRj 10Full Supply Level
yMoved slightly north and east to location beside gravel bar as per written description on site form
yes m yes
HbRj 11Impact Line Work/Highway Relocation
y yLeft as is, site in approximate location as per site sketch map
no m yes
HbRj 2Modeling purposes only
yMoved to approximate location based on site sketch map although information to vague to plot accurately,
yes l yesjust outside boundary
HbRj 20Impact Line Work/Highway Relocation
y yMoved based on vague description and location of swamp on ortho, although access info poorly described on site form
yes l yesstraddles boundary
HbRj 21Impact Line Work/Highway Relocation
y yLeft as is based on vague description and sketch map; assumed location of pole 31-3 as seen on ortho but access info is poorly described on site form
no l yes
HbRj 22Impact Line Work/Highway Relocation
y yMoved to just outside boundary based on original site form and sketch map and assumed location of pole 31-3 as seen on ortho photo
yes l yes
just outside boundary (17 m)' not covered by TEM
HbRj 23Impact Line Work/Highway Relocation
y yMoved to approximate location north of transmission line poles as given on original site form and sketch map
yes m yes
HbRj 24Impact Line Work/Highway Relocation
y y
Moved to location as described on original site form sketch map, assuming location of pole 31-3; written description puts site north of transmission line but access info and map place site on the transmission line
yes l yes
HbRj 25Impact Line Work/Highway Relocation
y yMoved to location as described on original site form sketch map, assuming location of pole 31-3 as seen on ortho photo
yes l yes
HbRj 26Impact Line Work/Highway Relocation
y yMoved site slightly west to match sketch map, which was drawn from airphoto
yes l-m yes
HbRj 27Impact Line Work/Highway Relocation
y yLeft as is as unclear from sketch map as to specific building referenced, although would be easy to locate in field
no m yes
HbRj 28Impact Line Work/Highway Relocation
y yMoved to intermediate terrace on edge of ravine in accordance with site sketch map
yes m yes
HbRj 3 Modeling purposes only
yMoved outside boundary as evident on form and ortho photo, although information very vague, and written description and sketch map almost impossible to follow.
yes l yesmoved to ~235 m outside boundary
HbRj 4Impact Line Work/Highway Relocation
y yLeft as is, site in clearing as indicated in written and sketch map info on site form
no m-h yes
HbRj 5Modeling purposes only
yMoved based on location of hillock as described on site form and sketch map
yes l-m yes
HbRj 6 Impact Line Work/Highway Relocation
y y
Moved polygon to both sides of Whistler Creek as indicated on form, additional polygon added on east side to reflect this, site may continue into ravine and forested area to south and could be affected by flooding up the ravine
yes l-m yes
HbRj 7Impact Line Work/Highway Relocation
y yMoved slightly north, site impossible to locate via access info, good site map confirms site location
yes m-h yes
HbRj 8Impact Line Work/Highway Relocation
y yMoved onto terrace, but unable to determine which ridge from written description or site map
yes l yes
HbRj 9Impact Line Work/Highway Relocation
y yLeft as is, site is located on breaks above river but cannot accurately determine specific location from poor written description and site map
no l yes
I.R. Wilson Consultants Ltd. Appendix B - 15
Appendix C
Appendix D
Further to IR Wilson’s recommendation to the Archaeology Branch that the locational
and/or areal polygons for 219 sites be changed on its RAAD application, Doris Lundy of
the Branch’s Archaeological Site Inventory Section responded that, with the following
seven exceptions, the recommendation was accepted. The seven exceptions are:
HaRk 6: due to ambiguities in the site form’s access description, Ms Lundy has
left the site in its original plotted location on the west side of Dry Creek, not the
east side of the creek as recommended by IR Wilson. IRW’s confidence level in
the recommended move was “moderate” but ground-truthing and GPS
confirmation may elevate this.
HbRj 3: the site, an extremely small lithic scatter found in a field on the Ardill
Ranch, has been left in its original location by the Archaeology Branch instead of
moved to the next field to the east as recommended (with “low” confidence) by
IR Wilson. The Branch feels that the relocation rationale (shape of the field on the
site form sketch map as compared to the same orthophoto) is insufficient to
support the recommended change. Needs ground-truthing.
HbRj 20, 21, 22, 24 and 25: all five sites are located on the same landform on the
east side of the Halfway River north of Hwy 29. The site forms provide detailed
written access information in the form of bearings and distances, which were
primarily used by IRW (using orthophotos and LiDAR) to re-plot the sites.
However, as all of the sites were revisited in 2003 and/or 2005, at which time
GPS readings were taken, the Archaeology Branch has elected to stay with the
original GPS’d locations rather than the revised IRW locations (all of which were
plotted with “low” confidence). As the locations for these sites appear to have
been changed as much as three times already, further ground-truthing is
recommended.