peco (distribution transformer)

29
DISTRIBUTION TRANSFORMER PRESENTATION

Upload: farhan-saadat

Post on 25-Nov-2015

126 views

Category:

Documents


10 download

DESCRIPTION

Peco

TRANSCRIPT

  • DISTRIBUTION TRANSFORMER

    PRESENTATION

  • BRIEF NOTE.

    Electrical transmission and distribution revolutionized with the invention of transformer. All Power

    generating units have to transmit and distribute power to the end user with the help of

    transformer. Distribution transformer is the main equipment for all utility companies, under

    WAPDA. AJK and KESC.

    Distribution Transformer demand will increase in Pakistan, Afghanistan and Iraq after war of

    terrorism. Major manufacturers in Pakistan will yield benefits, if they prepare themselves now

    for future business.

    PECO is only company in Pakistan who can yield Maximum benefit through its Transformer and

    Tower packages.

    Now is the time for PECO to establish and over come problems by 2010.

    PECO investment Pay Back is with in 5 years for this business due to the following

    advantages.

    Familiar with Wapda/Kesc utility companies due to tower business

    Technical manpower available

    Machinery and Equipment available due to similar work

    Material similarity will increase price advantage in quatitative purchase.

    Testing equipment/instrument similarity for Motor andTransformer

    Civil work will be minimum due to existing premises availability

  • CONSULTANCY SERVICES FOR PROJECT EXECUTION P.E.C.O. TRANSFORMER MANUFACTURING

    UNIT.

    Objectives: To initiate and provide all necessary technical expertise for

    establishment of electrical equipment manufacturing

    capabilities within the existing setup.

    The work shall be undertaken in phases:

    Phase1: Manufacturing of distribution transformers for the utility

    companies having requirement of upto 630 KVA for WAPDA, upto 1500 KVA for K.E.S.C.

    and for private sector having requirement upto 4000//KVA Transformers.

    Phase2: Manufacturing of pad mounted transformers for WAPDA,

    and Private housing societies, Kiosk (package ) substation

    and transformers for foreign markets (export)

    Phase3: Induction of other equipment in production line like :

    11KV and LV instrument transformers

    Medium Voltage switchgear

    Low Voltage switchgear

    Medium Voltage Bus ways

    EHV instrument transformers

    Industrial battery chargers

    MV and EHV line hardware

    Phase4: Joint venture with international Known manufacturer for design supports.

    Capabilities of Consultants are competent and capable of handling the project from

    the consultants: conception until completion. They have in house expertise, graduate

    engineers having over 30 years of working experience with renowned

    manufacturer of similar equipment.

    Services shall be provided from Consultants offices and full time engagement of the one expert at works

  • Technical: Provide design, manufacturing drawings and drawings for wapda approval for 25,

    50, 100, and 200 KVA transformer. (It is anticipated that by the time these rating

    come in regular production, in house capability will be developed for the designing

    of transformers. Consultants services shall however be available in case design/drawing of more rating are required,), Compilation of all formalities for pre-

    qualification with WAPDA. KESC and other public sector organization. Arrange

    and monitor type testing of transformer in Rawat HV lab and obtain prototype

    approval from wapda.

    Material Supply

    Chain Management : Make effective material supply chain system to ensure delivery in time, of quality

    and quantity to ensure timely completion of orders and quick rolling of available

    funds. Identify vendors for locally made components and locally available

    materials. Keep track of quality requirement with vendors . Monitor Procurement of

    imported material in quantities matching the production fore cast

    Marketing: Organize and train personnel for aggressive marketing both in public and private

    sector and for export.

  • 1. Basic Construction of Distribution Transformer, Almost

    same from all manufacturers.

    2. PECO has advantage due to similar manufacturing units

    i.e. Motor & Tower, which will share materials and

    quantitative price benefit will be the Key for success.

  • Market Analysis

    PECO manufacturing unit for Distribution Transformer will be capable of production as per WAPDA, K.E.S.C and Export orders. Also PECO design office will be capable of designing transformers to customers specifications. In fact the production capabilities of PECO will be superior in many respects from others. But the future expansion and justification for higher share will depend on performance of Justin-Time (JIT) supply. ISO 9000 Quality Management Certification is also to be the top priority after Commissioning and production start-up.

    Engineering design section and test laboratory will be the key for success in this product. Apart from WAPDA and KESC, the private sector industry, Builders and mega projects are the real source of profitable business.

    Future expansion in the following products will increase the profitability and market share.

    1. Special transformers.A) Dry type transformer

    B) Traction Transformer

    2. Furnace Transformers

    3. Energy efficient Transformers

    4. 11 KV current and Potential Transformers

    5. EHV (Extra High Voltage) Current Transformers

    6. Load Breaker Switches

  • 1. Analysis of Distribution of Transformer, Present Share and future Potential:

    These are established shares of local manufacturers in WAPDA /KESC business

    and private sector.

    Sr. Company Present Share Future Potential

    No.

    1. SIEMENS 28% Siemens have capacity to take 40% share in WAPDA

    2. PEL 28% PEL have enhanced their manufacturing capabilities by adding latest machinery and facilities at new site on Feroz Pur Road Lahore.

    3. Transfo Power 14% They have got maximum share, which they can produce

    4. ELEMETEC 10% They have potential to go up to 15%

    5 Transfab 2.5% They will remain same in near future

    6. Hammad 4% They will remain same in near future

    7. Syed Bhais 2.5% They will demand more share next year after proto type approvals up to 10%

    8. Pan Power 2.5% They will remain with in 2 3%9. A .B. Ampere 2.5% They will remain with in 2 3%10. ACE Indigo 2.5% They will remain with in 2 3%11. Climax 2.0% They are in problem and fading out

    12 MML 1.5% They can take up to 5%

    13 Johnson & Phillips 1.0% They are out of WAPDA business and no chance to be in near future

    - Siemens & PEL are enjoying this business share.

    - Transfo power is at its maximum share

    - Elmetec is at its peak .

    - Short fall is seen in delivery from smaller participant due to financial/manufacturing

    limitations

    Siemens

    28%

    PEL

    28%

    Transfopower

    14%

    ELEMETEC

    10%

    Other

    10%

    Available for new

    Comers

    10%

    Slice 7

    0%

  • Local Manufacturer's Production in Last Three Year as Per PEMA Assessments

    Sr. Company Present Share Production in Nos.

    No. 2005 2006 2007

    1. Siemens 28% 43,800 26,000 23,200

    2. PEL 28% 33,000 19,500 17,400

    3. Transfo Power 14% 16,500 9,750 8,700

    4. Elmetec 10% 7,000 3,900 3,480

    5. Transfab 2.50% 3,500 1,950 1,740

    6. Hammad 4.00% 2,400 1,300 1,160

    7. Syed Bhais 2.50% - - 380

    8. A. B. Ampere 2.50% - - 300

    9. ACE Indigo 2.50% - - 450

    10. Climax 2.00% 1,400 1,000 500

    11. MML 1.50% 1,200 800 400

    12. Johnson &

    Phillips

    1.50% 1,200 600 300

  • siemens 43800

    PEL 33000

    Transfo power 16500

    Elmeter 7000

    Others 2400

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    45000

    Production No.s

    (2005)

    siemens PEL Transfo

    power

    Elmeter Others

    Companies

    Local Manufacturer's Production in Last Three Year as Per PEMA

    Assessments

  • Domestic Customers:

    WAPDA / Utility Companies under WAPDA:

    Their standard ratings are 10,15,25,50,100,200,400 and 630 KVA and for pad mounted transformers 100,200 and 300 KVA

    . Karachi Electric Supply Company (KESC):

    Their standard ratings are 250, 500, 1000, 1500 KVA. KESC also purchases transformers of WAPDA ratings.

    AJK Electricity Department:

    AJK purchases transformers of WAPDA ratings up to 200 KVA

    Gilgit and Northern Areas (Works Department)

    They purchase transformers according to WAPDA ratings. They have also requirements of small step up transformers.

    Private Housing Societies:

    These Societies purchase Pole Mounted and Pad Mounted Transformers as per WAPDA ratings.

    Private Industrial Customers:

    They purchase transformers non WAPDA ratings, generally 300, 500, 750, 1000, 1250, 1500, 2000, 2500 and 4000 KVA. Steel furnaces have demand of Furnace transformers as well

    .

    Some other Government and semi government departments and autonomous bodies have occasional requirements like Atomic Energy Commission, WASA, PTCL, Railways etc

    .

    Export Potential:

    SIEMENS and PEL have been and are exporting Distribution Transformers to Middle East.

    There is still Export Potentials for Countries like Afghanistan, Bangladesh, Kuwait, Iraq , East Africa

  • Projection WAPDA Orders

    Year 2008-09 25 KVA Rs, 120,000 total quantity

    50KVA Rs, 170,000 40,000 Nos.

    100KVA Rs, 261,000

    200KVA RS, 403,000

    Yearwise Wapda orders

    Year

    Transformer Rating

    25 KVA 50KVA 100KVA 200KVA Total QTY

    PURCHASE PRICE IN

    Rs.

    QUANTITY IN Nos.

    2005-06 54,000 74,000 117,600 176,500 70,000

    2006-07 93,000 131,000 209,500 322,000 35,000

    2007-08 86,000 121,000 194,000 299,000 40,000

  • MACHINERY REQUIRMENT FOR PECO PLANT

    PECO has advantage of being in fabrication of Transmission Towers and motor manufacturing therefore have most of the machinery. How

    ever we are enlisting minimum requirement and suggested requirement for prequalification in WAPDA and efficient manufacturing at PECO

    Sr.

    No.

    Machinery Min. Reqd. WAPDA

    Approval

    Suggestion For

    Producing 300/ 350

    Transformer Month

    Machinery Available with PECO

    1. Machine Shop

    Central Lath Machine 3, 5, 8, 10, 12 5 10 Available

    Milling Machine 1 3 do

    Chuck Head Lathe 1 2 do

    Tool Grinder 1 3 do

    Shaper Machine 1 3 do

    Table Drill Machine 2 3 do

    2. Tank Shop

    Iron worker 40T 1 1 Available

    Tube cutting machine 1 2 do

    Tube bending machine 2 3 do

    Notching machine 1 1

    do (Heavy duty).

    Radial drilling machine 1 2 do

    Shearing machine 3 1 1 do

    Shearing machine 10 1 1 do

    Tank rolling machine 1 2 do

    Hydraulic tank body sizing machine 1 2 do

  • Sr. No. Machinery Min. Reqd. WAPDA

    Approval

    Suggestion For Producing

    300/ 350 Transformer Month

    Machinery

    Available with

    PECO

    Body sizing jigs 1 Set for each Rating

    Tank Frame Bending Machine 1 2Available

    Welding Plants 8 12 do

    Power Press 15 40 Tons With Dies 6 10 do

    Vertical Drilling Machine 3 5 do

    Portable Drilling Machine 2 4 do

    Tool Grinder 2 2 do

    1. Shot Blasting and Paint Shop:

    Shot Blasting Machine 1 Available

    Compressor 2 do

    2. Core Shop:

    Multiple Cutter Core Slitting Machine 1 2

    Single Cutter Core Slitting Machine 1 2

    Power Press With Dies. 6 12 Available

    Cutter For Slitting Machine 12 sets, 24 sets,

    Blade Grinder 1 2 Available

    3. Insulation Shop:

    Manual Paper Cutter 1 2 Available

    Press Pahn Paper Cutter 1 2 do

  • Sr.

    No.

    Machinery Min. Reqd. WAPDA Approval Suggestion For

    Producing

    300/ 350

    Transformer

    Month

    Machinery Available

    with PECO

    Press Pahn Paper Winder 1 2

    Power Press For Oil Ducts 1 2 Available

    Ring Cutter 1 2

    Manual Press For L-Rings 1 2 Available

    1. Winding Shop

    L.T Winding Machine Large 1 2

    L.T Winding Machine Medium 2 4

    H.T Winding Machine 6 10

    Varnish Treatment Of Coils 1 3 Available

    Oven For Coil Drying Medium) 1 2 do

    Butt Welding Machine 1 2

    2. Carpentry Shop

    Band Saw 1 2 Available

    Wood Planner 1 2 do

    Table band saw machine 1 2 do

    Tool Grinder 1 2 do

    3. Assembly Shop

    Core Stacking Jigs 2 Sets For Each Rating

  • Sr.

    No.

    Machinery Min. Reqd.

    WAPDA

    Approval

    Suggestion For Producing

    300/ 350 Transformer Month

    Machinery Available

    with PECO

    Induced Voltage MG-Set 1

    Regulating Transformer 1

    Silicon Steel Losses Meter 1

    Regulating Transformer 1

    Silicon Steel Losses Meter 1

    Paint Thickness Meter 1

    Tank Pressure Tester (Leakages) 1

    Dielectric Test Sets 1

    Flash Point Tester 1

    Viscosity Meter 1

    Acidicity Test Equipment 1 Set

    Pour Point Testing Equip. 1

    Weighing Scale 1

    1. Store

    Steel Racks To Properly Store Materials And

    Tools

    2. Other Facilities

    Over Head Cranes (5 Tons) 1 3

    Transformer Tanks Testing System Small. 1 2

    Transformer Tanks Testing System Large 1 1

    HPT Trolley 6 10

    Fork Lifter 1 2 Available

  • Sr. No. Machinery Min. Reqd. WAPDA

    Approval

    Suggestion For

    Producing 300/ 350

    Transformer Month

    Machinery Available with

    PECO

    Transformer Oil Storage Tank 2 3

    Oil Filtration Plant For Used Oil

    Stand By Generator 200 KVA

    Centralized Compressor Large

    Weighing Scale 1000 kg

    Computer, Printer Photo Copier, (For

    Store And Testing Lab).

    Rubber Hammers

    3. Factory Tools

    Scissors 9, 12 Available

    Rubber Hammers

    Wooden Hammers

    Nose pliers. Available

    Wire cutter do

    Hammer 100g 1kg Available

    Ring spanner sets

    Screw wrenches. Available

    Screw Drivers. do

    Key spanners do

    Vanier calipers do

    Micro meter do

  • Sr.

    N o.

    Machinery Min. Reqd. WAPDA Approval Suggestion For Producing

    300/ 350 Transformer

    Month

    Machinery Available

    with PECO

    Drill machine with drills do

    Steel measuring tapes do

    Insides calipers do

    Steel rulers do

    Smooth files do

    Half round files do

    Angle scales do

    Portable disc grinders do

    Hole punch do

    Pipe wrench do

    Cable knife do

    Vice do

    Copper strip cutter

    C Clamp

    Center punch Available

    Hand tape sets with handle

    Chisel for wood work

    Chisel for steel work Available

    Hack saw with blades do

    Paint brushes

    Spray guns Available

    Wood saw do

    Tip cutter

  • MATERIAL RATES

    Copper : Rs. 800 / kg

    Silicon Steel : Rs. 420 / kg

    Oil : Rs. 143 / kg

    Mild Steel : Rs. 90 / kg

    Which gives material cost as under:

    KVA copper S.S M.S Oil Total

    25 32,000 33,600 9,000 10,585 85,185

    50 464,00 48,720 13,050 15,515 123,685

    100 71,200 74,760 20,070 23,780 189,810

    200 109,600 115,080 30870 36,395 291,945

    400 231,200 243,180 65,160 77,140 616,680

    630 336,800 354,060 94,860 112,085 897,805

    Generally Material Cost is 70% of the selling price of a transformer. Based on this selling prices should be:

    25KVA : Rs. 121,692

    50 KVA : Rs. 176,692

    100 KVA : Rs. 271,157

    200 KVA : Rs. 417,064

    400 KVA : Rs. 880,971

    630 KVA : Rs, 1,282,578

    Note :

    These Selling Prices should yield minimum 10% Profit.

  • Tanks Core Clamp Core Steel L.V. Coil H.V .Coill

    Fabrication Fabrication Sitting & Cutting Winding Winding

    Short Core Building Varnishing

    Blasting & Clamping

    De-Rusting Assy. of L.V.

    Coil on Core

    Assy. of H.V.

    Coil on Core

    Preliminary Ratio & Inside testing

    Painting

    Complete Internal Assy.

    Inspection

    Tanking & Oil Filling

    Bushing Connection

    Testing

    Final Painting & Finishing

    Customer Inspection

    Delivery

    Manufacturing Flow Diagram

  • Capital Investment:

    1. Cost of development of manufacturing facilities:

    Civil work: Buildings and Structures (new or modification), floors, trucking

    pathways, foundations for machines.

    Mechanical works: Overhead cranes, steel structures or shed as required.

    Electrical Works: Electrification, lighting, connections to machines.

    Utilities: Electrical power, 400-500 Amps load of fully equipped and operational

    Facilities, gas, water.

    2. Cost of machinery, available in house, shifting, cleaning, making good for work if lying idle.

    3. Cost of new machinery, plants, equipments, tools, instruments, jigs, fixtures. Their installation and commissioning

    .

    4. Initial Consultancy fee

    5. All incidental or contingency expenses to be made for assets and facilities of permanent nature

    The Major Portion of anticipated capital cost will be required and utilized during the first six month as concentration during the last six months of twelve months period shall be on production of prototypes and prequalification with WAPDA.

  • SUMMARY OF TOTAL ESTIMATE FOR PECO MANUFACTURING UNIT

    Machinery Local Rs, 1,75,00,000/= (Most of them are available in PECO.)

    Machinery and testing Rs, 2,50,00,000,/= These are testing equipment

    Equipment (Import) and basic Wapda Requirement for

    prequalification.

    Local Installation Utilities etc. Rs. 17,00,000/=

    Labor, civil work, oven & tanks. Rs. 50,00,000

    Capital Coat Investment TOTAL Rs. 4,92,00,000

  • Running Expenses:

    These expenses are to be worked out in 3 steps. Running expenses during the first 12 months (1st year), during the next 12 months ( 2nd year)

    and for 5 next years. 7 years period should be kept for the total return of capital investment as well.

    First year is for establishing the facilities, staff and workers training and familiarization with the place and importance of

    work.

    Second year will be for consolidation and preparation to takeoff.

    Third year on ward, the company should stand by the leading manufacturers of transformer

    Running expenses during the 1st two years need to be carefully calculated, preferably for every month and then added for

    the year. From 3rd year onward, these will be pretty smooth except for the material cost

    .

    Running expenses during the 1st 12 months shall include:

    1. Salaries for assigned staff / workers, temporary or permanent.

    2. utilities: water, electricity, gas.

    3. Transportation, communication.

    4. Cost of materials for prototypes 25-200 KVA.

    5. Testing fee, retesting if required. WAPDA related fees and cost.

    6. Consumable Material.

    7. Contingency expenses like entertainment, public relations costs (rather WAPDA relations), pre-qualification visits expenses.

    8. Material for educational orders (which will be recovered from the sales)

    Income during this time will be from execution of educational orders.

    Running expenses during 12-24 months period

    It is anticipated that factory will be in regular production. If expenses are maintained to achieve break even In these 12 months, it will be a big

    achievement as orders will be less and cost to get the orders will be more. Workers and staff strength shall still be growing during this period.

    Material requirement shall be based on quantity anticipated for break even, with funds rolling of minimum thrice in the year.

    Financial charges as expenses are needed to be added accordingly.

    Cost to be shared with the other productive units of the company needs to be carefully taken care of in the feasibility as it will have impact on

    profitability.

  • Profitability

    Total weight of transformers are:

    25KVA 285 kg

    50 KVA 415kg

    100 KVA 638kg

    200 KVA 980kg

    400 KVA 20698kg

    630 KVA 31010kg

    Generally the material used has the following percentage:

    Copper, brass : 14% of the total weight

    Silicon Steel : 28%

    Oil : 23%

    Mild Steel etc: : 35%

    Hence material used shall be:

    KVA copper Silicon Steel Mild Steel Oil

    Kg Kg Kg Kg (Lit)

    25 40 80 100 65 (73)

    50 58 116 145 96 (107)

    100 89 178 223 ` 147 (164)

    200 137 274 343 225 (251)

    400 289 579 724 476 (532)

    630 421 843 1054 692 (773)

  • Profitability based on above:

    For regular production of 100 Transformer of 100KVA (or equivalent ) per month during the first year of regular operation, after approval of prototype, means ;

    Material to be consumed during the year : 100 x 189.810 x 12 = 227,772,000. based on above selling prices, selling income should be 100 x 271,157 x 12 = 325,388,400 and 5% gross profit during the first year of operation will be : Rs. 1,62,69,442

  • Five year production plan and running costs

    Below mentioned ratting and quantities have been considered for calculation of material cost.

    YEAR 25 KVA 50 KVA 100KVA 200 KVA

    First year 15 15 15 15

    2nd year 150 150 150 150

    3rd year 300 300 300 300

    4th year 450 450 450 450

    5th year 500 500 500 500

  • Production of Transformers can also be expressed in terms of KVA.

    YEAR Production KVA / year Production KVA / month

    First year 5625 469

    2nd year 56250 4688

    3rd year 112500 9375

    4th year 168750 14063

    5th year 187500 15625

  • Summary:Five Year Projections

    Category Key detail year 1 year 2 year 3 year 4 year 5

    Over head

    Staff and workers

    salaries, utilities,

    all non

    production

    expenses.

    5.45 18.6 25.4 25.5 25.5

    Consultancy fee & expanses

    Design / drawing

    s of 25,50,100 &

    200 KVA,

    prototype

    approvals.

    Complete

    technical,

    organization,

    procedural

    support.

    4.5 3.6 2.4 1.2 1.2

    MaterialsFor production

    including

    consumables

    10 117 257.4 424.71 519

    Total Cost of production & selling 19.95 139.2 285.2 451.4 545.2

    Sale value of production 14.8 150 330 544.5 665.5

    Net Profit & Loss 5.15 10.8 44.8 93.1 119.8

    Pay back with in 5 years .

  • Note:

    1. The following sales values have been taken:

    25KVA: Rs. 121,692

    50 KVA: Rs. 176,692

    100 KVA: Rs. 271,157

    200 KVA: Rs. 417,064

    2. sales values are increased 10% each year.

    3. Overheads shall remain more or less constant during the last three years

    4. Increased production will result in increased profitability.

    5. Accurate estimates of material requirements, timely order in bulk quantities shall result in reduction in material

    costs hence increase in profitability.