PeopleSoft Upgrades Best Practices. Tom Reznicek and Patrick Savage. Save the Date. APRIL 7-11, 2014 Sands Expo and Convention Center Las Vegas, Nevada. QuestDirect.org/COLLABORATE. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PeopleSoft Upgrades  Best Practices

QuestDirect.org

PeopleSoft Upgrades Best Practices

Tom Reznicek and Patrick Savage

Page 2: PeopleSoft Upgrades  Best Practices

QuestDirect.org

APRIL 7-11, 2014Sands Expo and Convention CenterLas Vegas, Nevada

Save the Date

QuestDirect.org/COLLABORATE

COLLABORATE 14- Quest Forum is THE source for PeopleSoft roadmaps & news. It matters where you register! All PeopleSoft education and events run through Quest

Page 3: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Agenda• Introduction of Speakers and Emtec• Project Success• Project Shortcomings and Solutions

Page 4: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Project Successes

Page 5: PeopleSoft Upgrades  Best Practices

QuestDirect.org

On Time Within Budget• Kept a detailed project plan so people knew

what was expected of them and when• Had regularly scheduled meetings to review

plan, risks, and resolve issues• Kept upper management involved in project

Page 6: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Final Move to Production on Time• Developed detailed task list for go-live weekend• Leveraged PeopleSoft Change Assistant• Had specific call-in times for progress reporting• Used production like hardware on the final test

move to production to get accurate timing for the real move to production

Page 7: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Latest User Data Security Migration• Developed method to migrate permission lists

and roles separate from user data• Created diagrams and client deliverable to

explain security migration plan

Page 8: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Trained Two Client Resources• Resources had PeopleSoft Upgrade experience

but did not execute test scripts• Allowed upgrade weekend tasks to be split

between 3 people• Documented manual steps• Documented common issues and resolutions

Page 9: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Reduced Data Conversion Time (72 hours to 42 minutes)

• Identified slow processes by running Application Engine tracing and data conversion steps report

• Tech leads tuned slow processes

Page 10: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Move to Production Completed On-Time• Used job properties in Change Assistant to record

time, file name, and issues• Let Change Assistant accept errors (i.e. duplicate

keys) and clean after scripts run• Created go-live spreadsheet with pre and post steps• Bypassed some backups saving hours

Page 11: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Knowledgeable Team• Technically strong and larger than previous

upgrade teams• Two Emtec resources to go to with concerns• Knowledgeable Emtec PeopleSoft Upgrade

Specialist• Cyber Source configured without additional Cyber

Source specific consultants

Page 12: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Prepared Microsoft SQL Server• Turned off database logging before scripts started• Monitored database file size• Added memory to database server• Set maximum memory usage on database to

allow for other processes on server

Page 13: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Updated/Validated User Guides• Guides consolidated multiple documents into one

document per business area• Created process flow diagrams for requisition and

PO entry• New testing documents for requisition and voucher

approval, GL reports, and other processes• Created technical check printer setup document

Page 14: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Minor Post Go-Live Issues• Extensive testing:

– Leveraged existing test scripts by updating menu navigation and business process changes for version 9.1

– Last round of testing done on production hardware– End users involved in system and user acceptance

testing

Page 15: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Went Live On-Time & Within Budget• Managed issues with Excel worksheet, included

owner and resolution • Assigned close action, which identified resolutions

required for production and how to apply to production

Page 16: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Functional Ch. 2 & 6 Steps Completed Quickly

• Functional users completed Ch. 2 tasks to reduce the number of transactions processed

• Wrote SQL statements to perform validation checks before conversion

• Identified Ch. 2 & 6 steps that had to be performed for A in test moves to production

Page 17: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Project Shortcomings and Solutions

Page 18: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Test Scripts Not as Usable as Thought

• Review test plans and scripts upfront in project• Review any work already done

Page 19: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Canadian Payroll Customization Removed and Later Re-Added

• Verify removal of customizations with the business

Page 20: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Differing Data Conversion Hours

• Ensure final test move has as much in common with eventual go-live as possible

• Should have ensured three data conversion processes were able to run error-free prior to go-live to accurately gauge run time

Page 21: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Applied Large Maintenance Pack Taking Longer in Production

• Keep more careful track of how much time it takes to apply large Maintenance Pack post-upgrade so more accurate estimate could be made

Page 22: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Initial Upgrade Pass Overlaid Delivered V9.1 Objects with V8.9

• Confirm initial upgrade pass is correct• Confirm filter that removed non-customizations is run• Confirm compare report is configured properly

Page 23: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Go-Live Move to Production Fell Behind in Day 2

• Escalate issues faster when processes run behind schedule

• Document how performance issues will be investigated and have required tools ready

• Do not apply new patches after last move to production• All hand-offs should be done by phone call and e-mail

Page 24: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Identified PM Areas for Improvement

• Keep checklist from RFP to make sure everything taken care of

• Some deadlines missed by project phase• Assign 1-2 people to check with everyone

regarding environment restarts and refreshes

Page 25: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Longer Testing Than Estimated• Test check printing earlier for MICR and signature fonts• Test nVision reports earlier in process• Have Hyperion environment refreshed and ready for

PeopleSoft testing• Test credit card transactions through to Cyborg • After initial install, test system while consultants on-site• Test on same operating system (64 bit) as production

Page 26: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Open Billing and Payable Transactions in Database from 2001

• Identify open transactions early in upgrade process and clean up transactions before go-live

• Run Ch. 2 tasks to identify open transactions to clean up

Page 27: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Environments Required and Migration Path Not Communicated

• Define environments and naming at the start• Define migration path and how environments will

be validated and kept up to date• Do not build test environment too early in upgrade• Define how performance issues will be debugged

and have proper tools installed on database

Page 28: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Wrong Initial Move to Production

• Confirm the “Initial Alter Audit” is complete before starting to use an environment

Page 29: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Application Engine Jobs Run Manually Instead of Running Change Assistant

• Install PeopleSoft Change Assistant on Windows Admin Server

• Workstation version does not allow for automatic processing of application engine jobs

Page 30: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Security Migrated Twice and Custom Objects Built Twice

• Apply the security after migration of custom code• Build database objects after migration of custom

code

Page 31: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Knowledge Transfer Not Completed between 1st Team and Current Emtec Team

• Document what was completed by first team and what will need to be completed by second team

Page 32: PeopleSoft Upgrades  Best Practices

QuestDirect.org

Thank you for listening.