![Page 1: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/1.jpg)
1© 2006 Paul J. Solomon
Performance-BasedEarned Value®
Paul J. Solomon, PMPPerformance-Based Earned Value®
NDIA Systems Engineering ConferenceSan Diego, CAOctober 25, 2006
![Page 2: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/2.jpg)
2© 2006 Paul J. Solomon
Agenda
• DoD Policy and Guidance, Customer Expectations• Standards, Models, and Best Practices• Project Management with Performance-Based Earned
Value® (PBEVSM)• Better Acquisition Management
![Page 3: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/3.jpg)
3© 2006 Paul J. Solomon
Copyright Attribution
Copyright© 2006 by Paul Solomon.This material contains excerpts from the book,Performance-Based Earned Value.®The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based Earned Value® was written by Paul Solomon and Ralph Young and copyrighted by the IEEE, 2007.
![Page 4: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/4.jpg)
4© 2006 Paul J. Solomon
Project Management Shortfalls
• Inadequate early warning• Schedules, EV overstate true progress• Remaining work underestimated
![Page 5: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/5.jpg)
5© 2006 Paul J. Solomon
Does EVMS Really Integrate?
WBSWBSCOST SCHEDULE
Progress Plan
TECHNICALPERFORMANCE
100
1
Risk Profile
RISK
EVMS
![Page 6: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/6.jpg)
6© 2006 Paul J. Solomon
Value of Earned Value
EVM data will be reliable and accurate only if:
• The right base measures of technical performance are selected and
• Progress is objectively assessed.
![Page 7: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/7.jpg)
7© 2006 Paul J. Solomon
DoD Policy and Guidance,Customer Expectations
![Page 8: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/8.jpg)
8© 2006 Paul J. Solomon
Government Pays But Fails to Get Desired Outcomes
(a) Government Accountability Office
GAO Report
Title Findings and Recommendations
06-66 Defense Acquisitions: DOD Paid Billions in Award and Incentive Fees Regardless of Acquisition Outcomes
• Contractors not held accountable for achieving desired outcomes: o Cost goals o Schedule goals o Desired capabilities • Programs do not capture early on the requisite knowledge needed to effectively manage program risks
06-391 Defense Acquisitions: Assessments of Major Programs
DOD needs to change its requirements and budgeting processes to get desired outcomes from the acquisition process
![Page 9: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/9.jpg)
9© 2006 Paul J. Solomon
GAO Best Practices
GAO Report
Title Findings and Recommendations
04-722 06-215
Information Technology: DOD’s Acquisition Policies and Guidance DOD Systems Modernization
Best Practices and Controls: • Ensure that requirements are
traceable, verifiable, and controlled. • Trace requirements to system design
specifications and testing documents. • Continually measure an acquisition’s
performance, cost, and schedule against approved baselines.
![Page 10: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/10.jpg)
10© 2006 Paul J. Solomon
Policy for Systems Engineering in DOD Policy 2/20/04
Defense Acquisition Guidebook (DAG) 10/8/04
Systems Engineering Plan Preparation Guide (SEP) 2/10/06
WBS Handbook, Mil-HDBK-881A (WBS) 7/30/05
Integrated Master Plan (IMP) & Integrated Master Schedule Preparation & Use Guide (IMS) 10/21/05
DOD Policy & Guidance on SE
Risk Management Guide for DOD Acquisition (RISK) Aug. 06
![Page 11: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/11.jpg)
11© 2006 Paul J. Solomon
DOD Policy & Guides
Policy or Guide (1 of 3) Policy DAG SEP WBS IMSDevelop SEP P 4.2.3.2 1.0Technical reviews:
• Event-driven timing • Success criteria • Assess technical
maturity
P P
4.5.1 4.5.1
4.5.1
3.4.43.4.4 3.4.4
3.2.3.1 3.2.3.1 3.2.3.1
2.3, 3.3.2
Integrate SEP with: • IMP • IMS • Technical Performance
Measures (TPM) • EVM
4.5.1 4.5.1
4.5.1
3.4.53.4.5 3.4.43.4.5
1.2, 2.3 1.2, 2.3 1.2, 2.3 1.2, 2.3
![Page 12: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/12.jpg)
12© 2006 Paul J. Solomon
Guide (2 of 3) DAG SEP WBS IMS Integrate WBS with requirements specification, statements of work (SOW), IMP, IMS, and EVMS
2.2.3, 3.2.3.3
3.4.3
TPMs to compare actual vs. plan: • Technical development • Design maturity
4.5.5 3.4.4 3.3.2
TPMs to report degree to which system requirements are met:
• Performance • Cost • Schedule
4.5.5 3.4.4
Standards and models to apply SE 4.2.24.2.2.1
Institute requirements management and traceability 4.2.3.4
3.4.4
DOD Guides
![Page 13: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/13.jpg)
13© 2006 Paul J. Solomon
Standards, Models, and Best Practices
![Page 14: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/14.jpg)
14© 2006 Paul J. Solomon
DOD Technical Baselines
DAG Technical Review
DAG Baseline DAG IEEE 1220
System Functional Review
System Functional Baseline
4.3.3.4.3 Validated Requirements Baseline
Preliminary Design Review
System Allocated Baseline
4.3.3.4.4 Verified Physical Architecture
Critical Design Review
System Product Baseline
4.3.3.4.5 Verified Physical Architecture
Production Readiness Review
System Product Baseline
4.3.3.9.3 Verified Physical Architecture
![Page 15: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/15.jpg)
15© 2006 Paul J. Solomon
Requirements Progress
Assess progress …• Compare system
definitionAgainst requirements
a) Identify product metricsand expected values
Quality of productProgress towardssatisfying requirements
D) Compare results against requirements
6.8.1.5 d) Assess•Development maturity to date•Product’s ability to satisfy requirements6.8.6 Product metrics…at pre-established control pointsenable:• Overall system quality evaluation• Comparison to planned goals and targets
4.2.1 Planning process,Req. 10: Progress against requirements
6.8.1.5 Performance-basedprogress measurement6.8.6 Track product … metrics
EIA-632IEEE 1220
![Page 16: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/16.jpg)
16© 2006 Paul J. Solomon
Technical Performance Measures (TPM)
Planned value profile is time-phased achievement projected• Achievement to date• Technical milestone where TPM evaluation is reported
•Establish dates for– Checking Progress – Meeting full conformance to requirements
Predict future value of key technical parameters of the end system based on current assessments
TPMs are key to progressively assess technical progress
EIA-632: Glossary IEEE 1220: 6.8.1.5, Performance-based progress measurement
![Page 17: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/17.jpg)
17© 2006 Paul J. Solomon
TPM
• How well a system is achieving performance requirements
• Use actual or predicted values from:– Engineering measurements– Tests– Experiments– Prototypes
• Examples:– Payload– Response time– Range– Power– Weight
![Page 18: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/18.jpg)
18© 2006 Paul J. Solomon
TPM
100
150
Perc
ent R
equi
red
Valu
e
TPM Planned Value Profile
Tolerance Bands
Achievement to Date
Use TPMs as a base measure of EV
![Page 19: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/19.jpg)
19© 2006 Paul J. Solomon
Success Criteria of Technical Reviews
5.2.4.1 Subsystem reviewsa. Subsystem definition• Mature
– Meet SE milestone criteriaa. Component allocations and specifications
– Provide a sound subsystem conceptc. Subsystem risks assessed and mitigatedd. Trade-study data...substantiate that
subsystem requirements are achievable
IEEE 1220, Preliminary design stage
![Page 20: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/20.jpg)
20© 2006 Paul J. Solomon
Synthesis (Design)
• Design solution meets:– Allocated performance requirements– Functional performance requirements– Interface requirements– Workload limitations– Constraints– Use models and/or prototypes to determine
success
IEEE 1220, (6.6): Success Criteria
![Page 21: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/21.jpg)
21© 2006 Paul J. Solomon
Product Requirements
• CMMI, PMBOK Guide: Traceability and consistency
ProductRequire-ments
Baseline
Task 1Task 2Task 3
•Project Plans
•Activities•Work Products
Requirements Work
![Page 22: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/22.jpg)
22© 2006 Paul J. Solomon
Process and Product QA
• Product QA• CMMI:
• Objectively evaluate work products against clearly stated criteria
• Minimize subjectivity• EVMS:
• EV is measurement of quantity of work• “Quality and technical content of work
performed are controlled by other means!”
![Page 23: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/23.jpg)
23© 2006 Paul J. Solomon
Project Management with Performance-Based Earned Value® (PBEVSM)
![Page 24: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/24.jpg)
24© 2006 Paul J. Solomon
PBEV
• 4 Principles and 16 Guidelines• Specify most effective measures of project
performance• Requirements-driven plan• Consistent with standards and models • Tailorable and scalable, depending on risk• Lean
![Page 25: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/25.jpg)
25© 2006 Paul J. Solomon
PBEV Based on Standards and Models
• ANSI/EIA-632• IEEE 1220 • CMMI®• PMBOK® Guide• INCOSE SE Handbook• PSM. Practical Software and Systems Measurement: A
Foundation for Objective Project Management• Earned Value Management Systems (ANSI/EIA-748-A-
1998, reaffirmed August 28, 2002) (EVMS)
![Page 26: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/26.jpg)
26© 2006 Paul J. Solomon
Principles of PBEV
1. Integrate product requirements and quality into the project plan.
2. Specify performance towards meeting product requirements, including planned quality, as a base measure of earned value.
3. Integrate risk management with EVM.4. Tailor the application of PBEV according to the
risk.
![Page 27: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/27.jpg)
27© 2006 Paul J. Solomon
Supplemental PBEV Process FlowSupplemental PBEV Process Flow
Define the work (WBS)
Define the work (WBS)
Execute the planExecute the plan
Plan the work(Schedule & Budget)
Plan the work(Schedule & Budget)
Measure the workMeasure the work
Implementcorrective action
Implementcorrective action
Analyze variancesAnalyze variancesIncorporateinternal/external
changes
Incorporateinternal/external
changes
(P) Establish product requirements and
components(technical baseline)
(P) Establish product requirements and
components(technical baseline)
(P) Integrate productrequirements andquality with plan
(P) Integrate productrequirements andquality with plan
(P) Integrate riskmanagement with plan
(P) Integrate riskmanagement with plan
(P) Measure progresstowards meeting productrequirements and quality
(P) Measure progresstowards meeting productrequirements and quality
(P) = Supplemental PBEV Process
Guideline 1.1
Guidelines 1.2, 2.2
Guidelines 3.2, 3.2,4.1, 4.2
Guideline 2.7
![Page 28: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/28.jpg)
28© 2006 Paul J. Solomon
PBEV Techniques
• Measure quality– Work products (partial and complete)– Technical maturity of evolving product– Use analysis, models, simulations, prototypes
• Base EV on– Work products (drawings, code) and– Quality
![Page 29: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/29.jpg)
29© 2006 Paul J. Solomon
EX 1: Schedule Plan and Status
Status at April 30• Drawings completed: 41• Weight requirement not met• Diameter requirement met
Schedule Plan Jan. Feb. Mar. Apr. May Total Drawings 8 10 12 10 10 50
Requirements met: Weight 1 1 Diameter 1 1
![Page 30: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/30.jpg)
30© 2006 Paul J. Solomon
EX 1: Earned Value
Design (drawings)
Jan. Feb. Mar. Apr. May
Total
Planned drawings cur
8 10 12 10 10 50
Planned drawings cum
8 18 30 40 50
BCWS cur 320 400 480 400 400 2000BCWS cum 320 720 1200 1600 2000 2000 Actual drawings completed cur
9 10 10 12 8
Actual drawings completed cum
9 19 29 41 49
EV (drawings) cum
360 760 1160 1640 1960
Negative EV Reqs cum
-100
Net EV cum 360 760 1160 1640 -1860
SV = - 140
![Page 31: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/31.jpg)
31© 2006 Paul J. Solomon
EX 1: Variance Analysis
Variance analysis (drawings and requirements):• 1 drawing behind schedule - 40• Diameter requirement met - 0• Weight requirement not met: - 100 Schedule variance - 140
![Page 32: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/32.jpg)
32© 2006 Paul J. Solomon
Better Acquisition Management
![Page 33: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/33.jpg)
33© 2006 Paul J. Solomon
Acquisition Management
• Requirements, incentives, insight:– Solicitation/Request for Proposal (RFP)– Integrated Master Plan (IMP)– Integrated Baseline Review (IBR)– Integrated Master Schedule (IMS)– EVMS compliance assessments– Independent technical assessments– Monitor consistency and validity of reports– Independent EAC and risk assessments– Award fee criteria
Ensure Contractors Integrate SE with EVM
![Page 34: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/34.jpg)
34© 2006 Paul J. Solomon
Summary
• Integrate– Systems engineering with PBEV
• Product requirements• Manage the technical baseline• Technical performance measures• SE life cycle work products
– Technical>schedule>cost performance• Lean process
– Less work packages with right base measures• Agile
![Page 35: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/35.jpg)
35© 2006 Paul J. Solomon
Process Improvement
Developing an EVM Implementation Approach
Time
Dol
lars
Contract Budget Base
PM Baseline
DT / OT
REQUIREMENTSUNIT TEST
SYSTEM INTEGRATION TEST
MODIFIED CODE
REUSE CODE
SCHED
ULE
NEW C
ODE
QUALITY
FUNCTION POIN
TS
REWORKCSCI
CSUCSC
DESIGN
SLOC
COTS
MODULES
EVM CREDIT
SOFTWARE MEASUREMENTS
Using Software Metrics&
Measurements for Earned ValueToolkit
Dave Burgess Cost Department Head
Ted Rogers EVM Division Head
Chris Mushrush EVM Subject Matter Expert
Dave Kester EVM Subject Matter Expert
October 2004
Points of Contact Process: Earned Value Management AIR 4.2.3 Technical: Software Engineering AIR 4.1.4
SEI / CMMI NAVAIRSept. 2001Aug. 2005May 2006
![Page 36: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/36.jpg)
36© 2006 Paul J. Solomon
Process Improvement
But wait.There’s more!• Examples• Templates• Tips• Standards• FAR
![Page 37: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/37.jpg)
37© 2006 Paul J. Solomon
References• ®CMMI Is Registered by Carnegie Mellon University in the U.S. Patent
and Trademark Office.• ® Performance-Based Earned Value is registered by Paul Solomon in
the U.S. Patent and Trademark Office. PBEV is a Service Mark of Paul Solomon.
• ® PMBOK is registered by the Project Management Institute in the U.S. Patent and Trademark Office
• American National Standards Institute (ANSI)/Electronics Industries Alliance (EIA). ANSI/EIA 632, Processes for Engineering a System, EIA, Arlington, VA, 1998.
• CMMI, Capability Maturity Model Integration-Systems Engineering/Software Engineering/Integrated Product and Process Development, Version 1.1, 2002.
• INCOSE 2006. International Council on Systems Engineering (INCOSE). INCOSE Systems Engineering Handbook, version 3. June 2006. page 7.11
• Institute of Electrical and Electronics Engineers (IEEE). IEEE Std 1220TM-2005, IEEE Standard for Application and Management of the Systems Engineering Process. New York, 2005.
• Naval Air Systems Command (NAVAIR). “Using Software Metrics & Measurements for Earned Value Toolkit.” Department of the Navy (October 2004).
![Page 38: Performance-Based Earned Value...Performance-Based Earned Value.® The excerpts were reprinted courtesy of John Wiley & Sons, Inc. and the IEEE Computer Society Press. Performance-Based](https://reader030.vdocument.in/reader030/viewer/2022040601/5e8f482b933f8830320c8de3/html5/thumbnails/38.jpg)
38© 2006 Paul J. Solomon
References• PSM. Practical Software and Systems Measurement: A Foundation for
Objective Project Management, Version 4.0b, October 2000 (www.psmsc.com).• Solomon, Paul . “Practical Software Measurement, PBEV”, CrossTalk
(September 2001) www.stsc.hill.af.mil/crosstalk/2001/09/index.html.• Solomon, Paul. “Going From PBEV to the CMMI”, CrossTalk (September 2002)
www.stsc.hill.af.mil/crosstalk/2002/09/index.html.• Solomon, Paul , “Using CMMI to Improve Earned Value Management”
(CMU/SEI-2002-TN-016) (October 2002). www.sei.cmu.edu/publications/documents/02.reports/02tn016.html
• Solomon, Paul , “Integrating Systems Engineering with Earned Value Management”, Defense Acquisition, Technology and Logistics (AT&L) Magazine (May 2004). www.dau.mil/pubs/dam/05_06_2004/may-june04.pdf.
• USAF Space & Missile Systems Center, “Systems Engineering Primer and Handbook” (January 2004)
• Young, Ralph R. Effective Requirements Practices (Addison-Wesley, 2001).• Solomon, Paul. “Performance-Based Earned Value”, CrossTalk (August 2005)
www.stsc.hill.af.mil/crosstalk/2005/08/index.html.• Solomon, Paul. “Practical, Performance-Based Earned Value”, CrossTalk (May
2006)