“Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September 2006 - CERN - Geneva

Upload: rosamond-edwards

Post on 17-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

“Performance of BTVs during the CNGS commissioning”

E. Bravin AB/BI

NBI 2006

6th International workshop on Neutrino Beams and Instrumentation4-9 September 2006 - CERN - Geneva

Page 2: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 2

Beam TV Observation Systems (BTV) for CNGS

The devices are equipped with scintillating screens (Alumina) and/or OTR radiators (Titanium and Carbon)

There are two types of cameras: CCD (standard) and SYRA (radiation hard CMOS sensor)

2 BTVE in the SPS, one before and one after the extraction septa. (Alumina and Titanium + CCD)

3 BTV in LSS4 and TT40 (Alumina and Titanium + CCD)

6 BTVG in TT41 (Carbon and Titanium + CCD)

2 BTVG in the target area (Carbon and Titanium + SYRA)

Page 3: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 3

Images (OTR)

BTVG.411006BTVG.410406BTVG.410706 BTVG.411906 BTVG.412424

BTVG.412434BTVG.412445

BTVG.412108

Intensity ~ 1012 protons

BTVG.411006BTVG.410406BTVG.410706 BTVG.411906 BTVG.412424

BTVG.412434BTVG.412445

BTVG.412108

Intensity ~ 1013 protons

Page 4: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 4

Radiation

BTVI_TT40.4001051013 protonsSingle image

BTVI_TT40.4001051013 protons

Average of 20 images

Page 5: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 5

BTV

.410

406

BTV

.410

706

BTV

.411

006

BTV

.411

906

BTV

.412

424

BTV

.412

445

-1

-0.5

0

0.5

1

1.5

2

2.5

BTV

BPM

Po

siti

on

[m

m] Horizontal

BTV

.410

406

BTV

.410

706

BTV

.411

006

BTV

.411

906

BTV

.412

424

BTV

.412

445

-3-2.5

-2-1.5

-1-0.5

00.5

11.5

2

BTV

BPM

Po

siti

on

[m

m]

Vertical

TT41 BTVGBeam position

Page 6: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 6

TT41 BTVGBeam position

There is a considerable difference between the readings of the beam position monitors and the values calculated from the images.

It looks like the values from the BPMs are to be trusted

Investigations are ongoing in order to understand the discrepancy.

There must be a problem during the different stages of the survey and alignment procedure.

Page 7: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 7

BTV

.410

406

BTV

.410

706

BTV

.411

006

BTV

.411

906

BTV

.412

108

BTV

.412

424

BTV

.412

435

BTV

.412

445

0

0.2

0.4

0.6

0.8

1

1.2

1.4

s.y.opt

s.y.btv

Siz

e [m

m]

BTV.410

406

BTV.410

706

BTV.411

006

BTV.411

906

BTV.412

108

BTV.412

424

BTV.412

435

BTV.412

445

0

0.2

0.4

0.6

0.8

1

1.2

1.4

s.x.opt

s.x.btv

Siz

e [m

m]

Horizontal

Vertical

* = 5.5 mp/p= 1.5 10-4

* = 5.5 mp/p= 1.5 10-4

TT41 BTVGBeam Size

Page 8: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 8

TT41 BTVGBeam Size

In the horizontal plane the measured beam sizes agree rather well with the optics parameters calculated by MAD.

In the vertical plane this agreement is less good.

The last two cameras do not have sufficient resolution at the moment and the measured sizes are in fact just the bandpass of the instrument.

A problem in the alignment forced the adoption of a small magnification factor for the camera lenses of the last two devices. This will be corrected in the near future. In order to maximise the resolution the field of view will be reduced to ~25x25 mm2.

Page 9: “Performance of BTVs during the CNGS commissioning” E. Bravin AB/BI NBI 2006 6 th International workshop on Neutrino Beams and Instrumentation 4-9 September

E. Bravin AB/BI CERN - NBI 20065 September 2006 9

Conclusions

The BTV systems have been successfully used for the commissioning of CNGS

A few issues remain to be solved: Alignment errors Resolution limit for the last two devices

Differences between measured values and MAD optics to be understood

Radiation damage to the cameras (especially last two devices) to be monitored