performance standard for protective coating (updated imo)

Download Performance Standard for Protective Coating (Updated IMO)

If you can't read please download the document

Upload: minhnn

Post on 29-Oct-2015

72 views

Category:

Documents


3 download

DESCRIPTION

training

TRANSCRIPT

  • application of paints and related products Surface roughness characteristics of blast-cleaned steel substrates. (4)

    Conductivity measured in accordance with ISO 8502-9: 1998. Preparation of steel substrate before application of paints and related products Test for the assessment of surface cleanliness. (5)

    Reference standard: ISO 8501-3: 2001 (grade P2). Preparation of steel substrate before application of paints and related products Visual assessment of surface cleanliness. (6)

    Reference standard: ISO 8502-3:1993. Preparation of steel substrate before application of paints and related products Test for the assessment of surface cleanliness.

    -3. The Society uses a sampling method to monitor that the coating inspector is using appropriate

    instruments, techniques and reporting methods in accordance with the inspection procedure reviewed by the Society in 3.

    4.4 Coating Inspectors Report (IMO PSPC 7., Part B 2.1.7) -1. The coating inspector is to record the results from the inspection in 4.3 and submit them to the

    Society. -2. The Society checks that the coating inspectors reports of surface preparation and coating

    application comply with the manufacturers Technical Data Sheet and Statement of Compliance or Type Approval Certificate.

    4.5 Corrective Actions for Non-Conformity (IMO PSPC 7., PR No.34 Chapter 4) -1. When deviations are found during the review in 4.3-3., the Society raises them with the coating

    inspector. -2. The coating inspector is responsible for identifying and implementing the corrective actions. -3. In the event that the corrective actions are not acceptable to the Society or in the event that

    corrective actions are not closed out, then the shipyard will be informed.

    4.6 Update of Coating Technical File (IMO PSPC 3.4, Part B 2.1.2) -1. The shipyard is to include the following documents regarding coating application in the

    Coating Technical File (CTF) specified in 5: (1) Shipyard work records of coating application (2) Coating log issued by the coating inspector checked in 4.4 (3) Shipyards verified inspection report

    5. Requirements After Coating

    5.1 Preparation of Coating Technical File (IMO PSPC 3.4, Part B 2.1.2, PR No.34 Chapter 5)

    -1. The shipyard is to document the specification of the coating system applied to the dedicated seawater ballast tanks and double-side skin spaces, the record of the shipyards and shipowners coating work, detailed criteria for coating selection, job specifications, inspection, maintenance and repair in the Coating Technical File (CTF) and submit it to the Society.

    -2. The Society reviews that the Coating Technical File contains at least the following items: (1) Copy of Statement of Compliance or Type Approval Certificate; (2) Copy of Technical Data Sheet, including:

    (a) Product name and identification mark and/or number;

    9

  • (b) Materials, components and composition of the coating system, colours; (c) Minimum and maximum dry film thickness; (d) Application methods, tools and/or machines; (e) Condition of surface to be coated (de-rusting grade, cleanness, profile, etc.); and (f) Environmental limitations (temperature and humidity);

    (3) Shipyard work records of coating application, including: (a) Applied actual space and area (in square metres) of each compartment; (b) Applied coating system; (c) Time of coating, thickness, number of layers, etc.; (d) Ambient condition during coating; and (e) Method of surface preparation;

    (4) Procedures for inspection and repair of coating system during ship construction; (5) Coating log issued by the coating inspector, stating that the coating was applied in

    accordance with the specifications to the satisfaction of the coating supplier representative and specifying deviations from the specifications;

    (6) Shipyards verified inspection report, including: (a) Completion date of inspection; (b) Result of inspection; (c) Remarks (if given); and (d) Coating inspectors signature; and

    (7) Procedures for in-service maintenance and repair of coating system.

    5.2 Corrective Actions for Non-Conformity (PR No.34 Chapter 5) -1. When deviations from the IMO PSPC are found during the review in 5.1, the Society reports

    them to the shipyard. -2. The shipyard is responsible for identifying the deviations and implementing the corrective

    actions.

    5.3 Maintenance of Coating Technical File Onboard Vessel (IMO PSPC 3.4, Part B2.1.6) -1. The Society checks that the Coating Technical File reviewed by the Society is maintained

    onboard the vessel after completion of the classification survey.

    6. Approval of Coating System (IMO PSPC Table1 1.3, Guidance for the Approval and Type Approval of Materials and Equipment for Marine Use 4.4, PR No.34 Chapter 1)

    -1. The Society issues a Certificate of Approval upon confirmation that the coating system complies with the IMO PSPC in accordance with the approval procedures specified in this chapter. -2. A coating manufacturer who intends to obtain approval from the Society for its coating system is to make an application in accordance with 6.2.

    6.1 General

    6.1.1 Application -1. The requirements of this chapter apply to tests and inspection for approval of coating system

    specified in 3.3-1.(2)(a). -2. Coating systems applicable for approval in accordance with this chapter are classified into

    three kinds as follows: (1) A coating system which does not combine epoxy based systems with shop primers (2) A coating system which combines epoxy based systems with shop primers

    10

  • (3) Alternative systems other than those above

    6.2 Application Procedures

    6.2.1 Application for Approval -1. Manufacturer who intends to obtain approval is to submit the application, in duplicate, stating

    the type and uses of the coating system accompanied by the reference materials and data, each in duplicate, as shown in 6.2.2 to the Society (one of its branches).

    6.2.2 Reference Materials and Data to be Attached to the Application for Approval -1. The following reference materials and data are to be attached to the application for approval.

    (1) Historical record of the company (the manufacturer) (2) Company background and brief description of the factory (3) The documents on Quality control system of the company (the manufacturer) (4) Kind of materials constituted coating system (names and trade names of the materials) (if

    6.1.1-2.(2), including kind of shop primer) (5) Table of chemical composition for coating (6) Record of service for field exposure (7) Marking (8) Test report (including Statement of Compliance and Type Approval Certificate, if any) (9) Specifications of the coating system (including the items specified in 5.1-2.(2), in

    principle) (10) Other documents which the Society considers necessary

    6.3 Confirmation of Manufacturing and Quality Control Procedure

    6.3.1 Survey -1. The confirmation is to be carried out to ensure whether the manufacturer has the capability to

    manufacture uniform quality of paints continuously for which approval has been applied by conducting survey on the manufacturing capability (factory installations, techniques, product quality control system, and in-house inspection facilities).

    6.3.2 Items of Confirmation Survey -1. In the factory investigation, the following items are to be investigated:

    (1) Whether or not the company inspection department and department responsible for the settlement of claims are well organized.

    (2) Whether or not the factory facilities and inspection facilities are well equipped. (3) Whether or not various specifications, work standards and quality control schemes are

    well organized and functioning.

    6.3.3 Omission of Confirmation Survey -1. The confirmation survey may be omitted if the coating is being manufactured in the same

    facilities and in almost the same way as coating from a previously approved coating system or if deemed unnecessary by the Society.

    6.4 Approval Test

    6.4.1 Approval Test -1. Approval test specified in 6.4.2 is to be carried out by The Research Institute of Marine

    Engineering (RIME), MARINTEK or a test laboratory which is recognized by the Society.

    11

  • -2. The Approval test may be omitted where deemed appropriate by the Society for epoxy based systems that are rated Good for 5 years of field exposure as specified in B4.2.4-2(1)(a), Guidance for the Survey and Construction of Steel Ships Part B.

    -3. In the case that a manufacturer wishes to have products which are manufactured in different locations under the same name, then infrared (IR) identification and specific gravity are to be used to demonstrate that they are the same coating, or individual approval tests will be required for the paint manufactured in each location.

    -4. The Society may require additional tests, however, if it considers them necessary.

    6.4.2 Test Procedure and Acceptance Criteria -1. The coating system is to be in accordance with the following requirements. Epoxy based

    systems tested prior to 1 July, 2008 need satisfy only the criteria for blistering and rust from the following requirements. Where deemed appropriate by the Society, these requirements may be omitted. (1) For protective coatings for dedicated seawater ballast tanks, annex 4 and annex 5 apply. (2) For protective coatings for double-side spaces of bulk carriers of 150 m in length and

    upwards other than dedicated seawater ballast tanks, annex 5 applies. (3) The application of 5 years field exposure is the following items;

    (a) Coating manufacturers records are to be examined to confirm coating system has 5 years field exposure.

    (b) A joint (coating manufacturer and the Society) survey of all ballast tanks of a selected vessel is to be carried out for the purpose of verifying compliance with the requirements of (a) and (e). The coating manufacturers representative is to be qualified as defined in 3.3-1.(3).

    (c) The selected vessel is to have ballast tanks in regular use, of which: At least one tank is approx 2000 m3 At least one tank is adjacent to a heated tank and At least one tank underdeck is exposed to the sun.

    (d) In the case that the selected vessel does not meet the requirements in (c) then the limitations are to be clearly stated on the type approval certificate. For example, the coating cannot be used in tanks adjacent to heated tanks or underdeck or tanks with volume greater than the size surveyed.

    (e) All ballast tanks are to be in GOOD condition, without touch up or repair in the prior 5 years.

    i) Good is defined as: Condition with spot rusting on less than 3% of the area under consideration without visible failure of the coating. Rusting at edges or welds, must be on less than 20% of edges or welds in the area under consideration.

    ii) Examples of how to report coating conditions with respect to areas under consideration should be as those given in B4.2.4-2, Guidance for the Survey and Construction of Steel Ships Part B.

    6.5 Notice of Approval

    6.5.1 Notification and Announcement of Approval -1. The Society examines the submitted documents specified in 6.2 to 6.4, and if found satisfactory,

    the coating system is approved and an approval certificate is issued to each brand. The date of issue of the approval certificate is to be coincided with the date of the approval test.

    -2. Once a year, the Society announces approved coating system in a form of a table.

    12

  • 6.5.2 Validity of Approval -1. Valid term of the Certificate of Approval specified in 6.5.1-1. will be 5 years from the date of

    approval. In case when the renewal of approval is carried out in accordance with the requirements in 6.5.3, valid term will be 5 years from the next day after the expiry date of the previous validity (hereinafter referred to as date of renewal)

    6.5.3 Renewal of Approval -1. In case of application for renewal of approval, the applicant is to submit a Certificate of

    Approval (original) and three copies of the data showing actual manufacturing records of the coating constituted coating system within the specific period together with an application from.

    -2. The Society conducts the factory inspection specified in 6.3. However, the Society may omit the factory inspection when actual manufacturing records are found to be satisfactory.

    -3. The factory inspection specified in -2 is to be completed within the valid term of Certificate of Approval in principle. However, for unavoidable circumstance, the factory inspection may be completed within a period of 3 months after the valid term upon the approval by the Society.

    -4. The Society examines the data showing actual manufacturing records specified in -1 and the result of factory inspection specified in -2, and if the Society considers them appropriate, approves the renewal of validity.

    6.5.4 Changes in Approval Content -1. In case of changes to an approved system, the applicant is to submit the Certificate of

    Approval (original) and three copies of the documents specified in 6.2.2 together with the application form.

    -2. The Society requests the factory inspection specified in 6.3 and approval test specified in 6.4 as necessary.

    -3. The Society examines the submitted data specified in -1 and reports of factory inspection and approval test specified in -2, and if the Society considers them appropriate, approves the changes in the approved content. In this case, as a rule, the validity of the Certificate of Approval specified in -1 is not changed.

    6.6 Verification Test

    6.6.1 Verification Test -1. The verification test is conducted when one of the following conditions occurs:

    (1) In case of doubt on the quality of products, judging from the service records of coating system

    (2) When the Society recognizes the necessity of the test because of the change of the constituent materials, etc.

    (3) When the Society considers necessary.

    6.7 Marking

    6.7.1 Marking -1. For formally approved paints, at least the following items are to be clearly marked on the paint

    container labels or other suitable places. (1) Brand name of paint (2) NK and approval number (3) Year and month of manufacture, and manufacturing number (4) Name of manufacturer

    13

  • 6.8 Revocation of Approval

    6.8.1 Revocation of Approval -1. In case any of the following (1) through (5) is relevant, the Society may revoke approval of the

    manufacturing process based on the requirements in this Chapter and give notice of the revocation to the manufacturer. The manufacturer which noticed the approval is withdrawn is to return Certificate of Approval and Particulars of Approval Conditions in question to the Society. (1) Failure in renewal of approval or verification test (2) When the manufacturer does not pay the approval fees. (3) When the coating system, whose manufacturing process has previously been granted

    approval, no longer conform to the given requirements due to amendments or implementation of conventions, law, rule and regulations.

    (4) When manufacturers have not been carried out the renewal of approval according to the requirements in 6.5.3.

    (5) When a request for revocation is made by the manufacturer.

    14

  • Annex 1 Coating Inspectors Qualifications (PR No.34 Chapter 2)

    1.1 Equivalent Qualification -1. The Society deems an equivalent qualification approved by the Society specified in

    3.3.-1.(3)(c) as a qualification that satisfies either (1) or (2). (1) Equivalent qualification is the successful completion, as determined by course tutor, of

    an approved course. (a) The course tutors are to be qualified with at least 2 years relevant experience and

    qualified to NACE Coating Inspector Level 2 or FROSIO Inspector Level III, or with an equivalent qualification.

    (b) Approved Course: A course that has a syllabus based on the issues associated with the PSPC including the following:- Health Environment and Safety Corrosion Materials and design International standards referenced in PSPC Curing mechanisms Role of the inspector Test instruments Inspection Procedures Coating specification Application Procedures Coating Failures Pre-job conference MSDS and product data sheet review Coating technical file Surface preparation Dehumidification Waterjetting Coating types and inspection criteria Specialized Application Equipment Use of inspection procedures for destructive testing and non destructive

    testing instruments. Inspection instruments and test methods Coating inspection techniques Cathodic protection Practical exercises, case studies.

    (c) Such a course is to have an acceptable measurement of performance, such as an examination with both theoretical and practical elements. The course and examination are to be approved by the Society.

    (2) Equivalent qualification arising from practical experience: An individual who: (a) has a minimum of 5-years practical work experience as a coating inspector of ballast

    tanks during new construction within the last 10 years, and (b) has successfully completed the examination given in 1.1-1.(1)(c).

    15

  • Annex 2 Example of Daily Log and Non-Conformity Report (IMO PSPC ANNEX 2)

    16

  • 17

  • Annex 3 Dry Film Thickness Measurements (IMO PSPC ANNEX 3)

    The following verification check points of DFT are to be taken: .1 one gauge reading per 5 m2 of flat surface areas; .2 one gauge reading at 2 to 3 m intervals and as close as possible to tank boundaries, but

    not further than 15 mm from edges of tank boundaries; .3 longitudinal and transverse stiffener members:

    One set of gauge readings as shown below, taken at 2 to 3 m run and not less than two sets between primary support members;

    Figure 3

    NOTE: Arrows of diagram indicate critical areas and should be understood to mean indication for both sides.

    .4 3 gauge readings for each set of primary support members and 2 gauge readings for each

    set of other members as indicated by the arrows in the diagram; .5 for primary support members (girders and transverses) one set of gauge readings for 2 to

    3 m run as shown in figure 3 above but not less than three sets; .6 around openings one gauge reading from each side of the opening; .7 five gauge readings per square metre (m2) but not less than three gauge readings taken at

    complex areas (i.e. large brackets of primary support members); and .8 additional spot checks to be taken to verify coating thickness for any area considered

    necessary by the coating inspector.

    18

  • Annex 4 Test on Simulated Ballast Tank Condition (IMO PSPC ANNEX 1 Appendix 1)

    1.1 Test condition Test on simulated ballast tank conditions is to satisfy each of the following conditions:

    (1) The test is to be carried out for 180 days. (2) There are to be 5 test panels. (3) Test panels are to be the following items. However, to facilitate innovation, alternative

    preparation, coating systems and dry film thicknesses may be used when clearly defined. (a) The size of each test panel is 200 mm x 400 mm x 3 mm. (b) Two of the panels (Panel 3 and 4 below) have a U-bar welded on. The U-bar is

    welded to the panel in a 120 mm distance from one of the short sides and 80 mm from each of the long sides.

    (c) The panels are to be treated according to this Standard, table 4.3-2, 1.1, 1.2 and 1.3,

    and coating system applied according to table 4.3-2., 1.4 and 1.5. (d) Shop primer to be weathered for at least 2 months and cleaned by low pressure

    washing or other mild method. Blast sweep or high pressure washing, or other primer removal methods not to be used.

    (e) Weathering method and extent are to take into consideration that the primer is to be the foundation for a 15 year target useful life system.

    (4) The reverse side of the test piece is to be painted appropriately, in order not to affect the test results.

    (5) As simulating the condition of actual ballast tank, the test cycle runs for two weeks with natural or artificial seawater and one week empty. The temperature of the seawater is to be kept at about 35C.

    (6) Test Panel 1: This panel is to be heated for 12 h at 50C and cooled for 12 h at 20C in order to simulate upper deck condition. The test panel is cyclically splashed with natural or artificial seawater in order to simulate a ships pitching and rolling motion. The interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    (7) Test Panel 2 has a fixed sacrificial zinc anode in order to evaluate the effect of cathodic protection. A circular 8 mm artificial holiday down to bare steel is introduced on the test panel 100 mm from the anode in order to evaluate the effect of the cathodic protection. The test panel is cyclically immersed with natural or artificial seawater.

    (8) Test Panel 3: to be cooled on the reverse side, in order to give a temperature gradient in order to simulate a cooled bulkhead in a ballast wing tank, and splashed with natural or artificial seawater in order to simulate a ships pitching and rolling motion. The gradient of temperature is approximately 20C, and the interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    (9) Test Panel 4 is to be cyclically splashed with natural or artificial seawater in order to

    19

  • simulate a ships pitching and rolling motion. The interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    (10) Test Panel 5 is to be exposed to dry heat for 180 days at 70C to simulate boundary plating between heated bunker tank and ballast tank in double bottom.

    Figure 4.1-1 Wave tank for testing of ballast tank coatings

    1.2 Test results -1. Prior to the testing, the following measured data of the coating system is to be reported:

    (1) Infrared (IR) identification of the base and hardener components of the coating; (2) Specific gravity* of the base and hardener components of the paint; and (3) Number of pinholes, low voltage detector at 90 V.

    (Remark) *: ISO 2811-1/4:1997. Paints and varnishes. Determination of density.

    -2. After the testing, the following measured data is to be reported: (1) Blisters and rust(1); (2) Dry film thickness (DFT) (use of a template)(2); (3) Adhesion value(3); (4) Flexibility(4) modified according to panel thickness (3 mm steel, 300 m coating, 150 mm

    cylindrical mandrel gives 2% elongation) for information only; (5) Cathodic protection weight loss/current demand/disbondment from artificial holiday; (6) Undercutting from scribe. The undercutting along both sides of the scribe is measured

    and the maximum undercutting determined on each panel. The average of the three maximum records is used for the acceptance. (Remark) (1)

    Reference standards: ISO 4628/2:2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of defects, and of intensity of

    20

  • uniform changes in appearance Part 2. ISO 4628/3: 2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of common types of defect Part 3: Designation of degree of rusting. (2)

    Nine equally distributed measuring points are used on panels size 150mm x 150 mm or 15 equally distributed measuring points on panels size 200mm x 400mm. (3)

    Reference standard: ISO 4624:2002. Pull-off test for adhesion. (4)

    Reference standards: ASTM D4145:1983. Standard Test Method for Coating Flexibility of Prepainted Sheet.

    1.3 Acceptance Criteria -1. The test results in 1.2 are to satisfy the following criteria in Table 1.3-1.:

    Table 1.3-1. Acceptance Criteria Item

    Acceptance criteria for epoxy based systems

    Acceptance criteria for alternative systems

    Blisters on panel

    No blisters

    No blisters

    Rust on panel

    Ri 0 (0%)

    Ri 0 (0%)

    Number of pinholes

    0 0

    Adhesive failure

    > 3.5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    > 5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    Cohesive failure

    > 3 MPa Cohesive failure in coating for 40% or more of the area.

    > 5 MPa Cohesive failure in coating for 40% or more of the area.

    Cathodic protection current demand calculated from weight loss

    < 5 mA/m2

    < 5 mA/m2

    Cathodic protection; disbondment from artificial holiday

    < 8 mm

    < 5 mm

    Undercutting from scribe < 8 mm

    < 5 mm

    U-bar Any defects, cracking or detachment at the angle or weld will lead to system being failed.

    Any defects, cracking or detachment at the angle or weld will lead to system being failed.

    -2. Epoxy based systems tested prior to 1 July, 2008 need satisfy only the criteria for blistering and rust in the table above.

    21

  • -3. Epoxy based systems tested when applied according to table 4.3-2 of this Standard are to satisfy the criteria for epoxy based systems as indicated in the table above. -4. Alternative systems not necessarily epoxy based and/or not necessarily applied according to table 4.3-2 of this Guidline are to satisfy the criteria for alternative systems as indicated in the table 1.3-1. above.

    1.4 Test report The test report is to include the following information:

    (1) Name of the manufacturer; (2) Date of tests; (3) Product name/identification of both paint and primer; (4) Batch number; (5) Data of surface preparation on steel panels, including the following:

    (a) Surface treatment; (b) Water soluble salts limit; (c) Dust; and (d) Abrasive inclusions;

    (6) Application data of coating system, including the following: (a) Shop primed; (b) Number of coats; (c) Recoat interval*; (d) Dry film thickness (DFT) prior to testing*; (e) Thinner*; (f) Humidity*; (g) Air temperature*; and (h) Steel temperature; (Remark) *

    Both of actual specimen data and manufacturers requirement/recommendation. (7) Test results according to 1.2; and (8) Judgment according to 1.3.

    22

  • Annex 5 Condensation Chamber Test (IMO PSPC ANNEX 1 Appendix 2)

    1.1 Test condition Condensation chamber test is to be conducted in accordance with applicable standards*.

    (1) The exposure time is 180 days. (2) There are to be 2 test panels. (3) Test panels are to be the following items. However, to facilitate innovation, alternative

    preparation, coating systems and dry film thicknesses may be used when clearly defined. (a) The size of each test panel is 150 mm x 150 mm x 3 mm. (b) The panels are to be treated according to the Performance Standard, table 4.3-2, 1.1,

    1.2 and 1.3 and coating system applied according to table 4.3-2., 1.4 and 1.5. (c) Shop primer to be weathered for at least 2 months and cleaned by low pressure

    washing or other mild method. Blast sweep or high pressure washing, or other primer removal methods not to be used.

    (d) Weathering method and extent are to take into consideration that the primer is to be the foundation for a 15 year target life system.

    (4) The reverse side of the test piece is to be painted appropriately, in order not to affect the test results. (Remark) *

    Reference standard: ISO 6270-1:1998 Paints and varnishes Determination of resistance to humidity Part 1: Continuous condensation.

    Figure 4.2-2. Condensation chamber

    1.2 Test results -1. Prior to the testing, the following measured data of the coating system is to be reported:

    (1) Infrared (IR) identification of the base and hardener components of the coating; (2) Specific gravity* of the base and hardener components of the paint; and

    23

  • (3) Number of pinholes, low voltage detector at 90 V. (Remark) *

    Reference standard: ISO 2811-1/4:1997. Paints and varnishes. Determination of density. -2. After the testing, the following measured data is to be reported:

    (1) Blisters and rust(1); (2) Dry film thickness (DFT) (use of a template)(2); (3) Adhesion value(3); (4) Flexibility(4) modified according to panel thickness (3 mm steel, 300 m coating, 150 mm

    cylindrical mandrel gives 2% elongation) for information only; (Remark) (1)

    Reference standards: ISO 4628/2:2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of defects, and of intensity of uniform changes in appearance Part 2. ISO 4628/3: 2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of common types of defect Part 3: Designation of degree of rusting. (2)

    Nine equally distributed measuring points are used on panels size 150mm x 150 mm or 15 equally distributed measuring points on panels size 200mm x 400mm. (3)

    Reference standard: ISO 4624:2002. Pull-off test for adhesion. (4)

    Reference standards: ASTM D4145:1983. Standard Test Method for Coating Flexibility of Prepainted Sheet.

    1.3 Acceptance criteria -1. The test results based on 1.2 are to satisfy the following criteria in table 1.3-1.:

    Table 1.3-1. Acceptance Criteria Item

    Acceptance criteria for epoxy based systems

    Acceptance criteria for alternative systems

    Blisters on panel

    No blisters

    No blisters

    Rust on panel

    Ri 0 (0%) Ri 0 (0%)

    Number of pinholes

    0 0

    Adhesive failure

    > 3.5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    > 5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    Cohesive failure

    > 3 MPa Cohesive failure in coating for 40% or more of the area.

    > 5 MPa Cohesive failure in coating for 40% or more of the area.

    -2. Epoxy based systems tested prior to 1 July, 2008 need satisfy only the criteria for blistering and

    rust in the table above. -3. Epoxy based systems tested when applied according to table 4.3-2 of this Guideline are to

    satisfy the criteria for epoxy based systems as indicated in the table above. -4. Alternative systems not necessarily epoxy based and/or not necessarily applied according to

    24

  • table 4.3-2 of this Guideline are to satisfy the criteria for alternative systems as indicated in the table 1.3-1. above.

    1.4 Test report The test report is to include the following information:

    (1) Name of the manufacturer; (2) Date of tests; (3) Product name/identification of both paint and primer; (4) Batch number; (5) Data of surface preparation on steel panels, including the following:

    (a) Surface treatment; (b) Water soluble salts limit; (c) Dust; and (d) Abrasive inclusions;

    (6) Application data of coating system, including the following: (a) Shop primed; (b) Number of coats; (c) Recoat interval*; (d) Dry film thickness (DFT) prior to testing*; (e) Thinner*; (f) Humidity*; (g) Air temperature*; and (h) Steel temperature; (Remark) *

    Both of actual specimen data and manufacturers requirement/recommendation. (7) Test results according to 1.2; and (8) Judgment according to 1.3.

    25

  • Appendix 1 IMO Resolution MSC.215 (82)

    26

  • PERFORMANCE STANDARD FOR PROTECTIVE COATINGS FOR DEDICATED SEAWATER BALLAST TANKS IN ALL TYPES OF SHIPS

    AND DOUBLE-SIDE SKIN SPACES OF BULK CARRIERS

    1 PURPOSE

    This Standard provides technical requirements for protective coatings in dedicated seawater ballast tanks of all type of ships of not less than 500 gross tonnage and double-side skin spaces arranged in bulk carriers of 150 m in length and upward1 for which the building contract is placed, the keels of which are laid or which are delivered on or after the dates referred to in SOLAS regulation II-1/3-2 as adopted by resolution MSC.216(82).

    2 DEFINITIONS

    For the purpose of this Standard, the following definitions apply: 2.1 Ballast tanks are those as defined in resolutions A.798(19) and A.744(18). 2.2 Dew point is the temperature at which air is saturated with moisture. 2.3 DFT is dry film thickness. 2.4 Dust is loose particle matter present on a surface prepared for painting, arising from blast-cleaning or other surface preparation processes, or resulting from the action of the environment. 2.5 Edge grinding is the treatment of edge before secondary surface preparation. 2.6 GOOD condition is the condition with minor spot rusting as defined in resolution A.744(18). 2.7 Hard coating is a coating that chemically converts during its curing process or a non-convertible air drying coating which may be used for maintenance purposes. Can be either inorganic or organic. 2.8 NDFT is the nominal dry film thickness. 90/10 practice means that 90% of all thickness measurements shall be greater than or equal to NDFT and none of the remaining 10% measurements shall be below 0.9 x NDFT. 2.9 Primer coat is the first coat of the coating system applied in the shipyard after shop primer application. 2.10 Shop-primer is the prefabrication primer coating applied to steel plates, often in automatic plants (and before the first coat of a coating system). 2.11 Stripe coating is painting of edges, welds, hard to reach areas, etc., to ensure good paint adhesion and proper paint thickness in critical areas. 2.12 Target useful life is the target value, in years, of the durability for which the coating system is designed. 2.13 Technical Data Sheet is paint manufacturers Product Data Sheet which contains detailed technical instruction and information relevant to the coating and its application.

    3 GENERAL PRINCIPLES

    3.1 The ability of the coating system to reach its target useful life depends on the type of coating system, steel preparation, application and coating inspection and maintenance. All these aspects contribute to the good performance of the coating system. 3.2 Inspection of surface preparation and coating processes shall be agreed upon between the shipowner, the shipyard and the coating manufacturer and presented to the Administration for

    27

  • review. The Administration may, if it so requires, participate in the agreement process. Clear evidence of these inspections shall be reported and be included in the Coating Technical File (CTF) (see paragraph 3.4). 3.3 When considering the Standard provided in section 4, the following is to be taken into account:

    .1 it is essential that specifications, procedures and the various different steps in the coating application process (including, but not limited to, surface preparation) are strictly applied by the shipbuilder in order to prevent premature decay and/or deterioration of the coating system;

    .2 the coating performance can be improved by adopting measures at the ship design stage such as reducing scallops, using rolled profiles, avoiding complex geometric configurations and ensuring that the structural configuration permits easy access for tools and to facilitate cleaning, drainage and drying of the space to be coated; and

    .3 the coating performance standard provided in this document is based on experience from manufacturers, shipyards and ship operators; it is not intended to exclude suitable alternative coating systems, providing a performance at least equivalent to that specified in this Standard is demonstrated. Acceptance criteria for alternative systems are provided in section 8.

    3.4 Coating Technical File 3.4.1 Specification of the coating system applied to the dedicated seawater ballast tanks and

    double-side skin spaces, record of the shipyards and shipowners coating work, detailed criteria for coating selection, job specifications, inspection, maintenance and repair2 shall be documented in the Coating Technical File (CTF), and the Coating Technical File shall be reviewed by the Administration.

    2 Guidelines to be developed by the Organization.

    3.4.2 New construction stage The Coating Technical File shall contain at least the following items relating to this Standard

    and shall be delivered by the shipyard at new ship construction stage: .1 copy of Statement of Compliance or Type Approval Certificate; .2 copy of Technical Data Sheet, including:

    - product name and identification mark and/or number; - materials, components and composition of the coating system, colours; - minimum and maximum dry film thickness; - application methods, tools and/or machines; - condition of surface to be coated (de-rusting grade, cleanness, profile, etc.);

    and - environmental limitations (temperature and humidity);

    .3 shipyard work records of coating application, including: - applied actual space and area (in square metres) of each compartment; - applied coating system; - time of coating, thickness, number of layers, etc.; - ambient condition during coating; and - method of surface preparation;

    .4 procedures for inspection and repair of coating system during ship construction;

    .5 coating log issued by the coating inspector stating that the coating was applied in accordance with the specifications to the satisfaction of the coating supplier representative and specifying deviations from the specifications (example of daily log and non-conformity report, see annex 2);

    28

  • .6 shipyards verified inspection report, including: - completion date of inspection; - result of inspection; - remarks (if given); and - inspector signature; and

    .7 procedures for in-service maintenance and repair of coating system2. 2

    Guidelines to be developed by the Organization. 3.4.3 In-service maintenance, repair and partial re-coating In-service maintenance, repair and

    partial re-coating activities shall be recorded in the Coating Technical File in accordance with the relevant section of the Guidelines for coating maintenance and repair2.

    2 Guidelines to be developed by the Organization.

    3.4.4 Re-coating If full re-coating is carried out, the items specified in paragraph 3.4.2 shall be recorded in the

    Coating Technical File. 3.4.5 The Coating Technical File shall be kept on board and maintained throughout the life of the

    ship.

    3.5 Health and safety The shipyard is responsible for implementation of national regulations to ensure the health and safety of individuals and to minimize the risk of fire and explosion.

    4 COATING STANDARD

    4.1 Performance standard This Standard is based on specifications and requirements which intend to provide a target useful coating life of 15 years, which is considered to be the time period, from initial application, over which the coating system is intended to remain in GOOD condition. The actual useful life will vary, depending on numerous variables including actual conditions encountered in service.

    4.2 Standard application Protective coatings for dedicated seawater ballast tanks of all ship types and double-side skin spaces arranged in bulk carriers of 150 m in length and upward shall at least comply with the requirements in this Standard.

    4.3 Special application 4.3.1 This Standard covers protective coating requirements for the ship steel structure. It is noted

    that other independent items are fitted within the tanks to which coatings are applied to provide protection against corrosion.

    4.3.2 It is recommended that this Standard is applied, to the extent possible, to those portions of permanent means of access provided for inspection not integral to the ship structure, such as rails, independent platforms, ladders, etc. Other equivalent methods of providing corrosion protection for the non-integral items may also be used, provided they do not impair the performance of the coatings of the surrounding structure. Access arrangements that are integral to the ship structure, such as increased stiffener depths for walkways, stringers, etc., are to fully comply with this Standard.

    4.3.3 It is also recommended that supports for piping, measuring devices, etc., be coated in accordance with the non-integral items indicated in paragraph 4.3.2.

    4.4 Basic coating requirements 4.4.1 The requirements for protective coating systems to be applied at ship construction for

    29

  • dedicated seawater ballast tanks of all ship types and double-side skin spaces arranged in bulk carriers of 150 m in length and upward meeting the performance standard specified in paragraph 4.1 are listed in table 1.

    4.4.2 Coating manufacturers shall provide a specification of the protective coating system to satisfy the requirements of table 1.

    4.4.3 The Administration shall verify the Technical Data Sheet and Statement of Compliance or Type Approval Certificate for the protective coating system.

    4.4.4 The shipyard shall apply the protective coating in accordance with the verified Technical Data Sheet and its own verified application procedures.

    Table 1 Basic coating system requirements for dedicated seawater ballast tanks of all type

    of ships and double-side skin spaces of bulk carriers of 150 m and upwards

    istic/ ment CharacterReference Standards

    Require

    1 g syst Design of coatin em .1 of the

    coating systemed by the

    ed maintenance. The following aspects, among other things should be considered:

    and deballasting operations;

    ection, the coating should be compatible with the cathodic protection system).

    ed

    t and technical assistance (if given) shall be recorded in the

    s or on ed spaces shall be able to

    withstand repeated heating and/or cooling without becoming

    Selection

    The selection of the coating system should be considerparties involved with respect to the service conditions and plann

    .1 location of space relative to heated surfaces; .2 frequency of ballasting .3 required surface conditions; .4 required surface cleanliness and dryness; .5 supplementary cathodic protections, if any (where coating is

    supplemented by cathodic prot

    Coating manufacturers shall have products with document

    satisfactory performance records and technical data sheets. Themanufacturers should also be capable of rendering adequate technical assistance. Performance records, technical data shee

    Coating Technical File. Coatings for application underneath sun-heated deck

    bulkheads forming boundaries of heat

    brittle. .2 Coating type

    ems.

    the test

    e in annex 1.

    mended.

    Epoxy based syst

    Other coating systems with performance according to procedur

    A multi-coat system with each coat of contrasting colour is recom

    30

  • The top coat shall be of a light colour in order to facilitatein-service inspection.

    .3 Coating pre-qualification test

    e of

    ex 1 or equivalent, which as a minimum meets the requirements for rusting and blistering; or which have

    less than GOOD may be accepted.

    x

    Epoxy based systems tested prior to the date of entry into forcthis Standard in a laboratory by a method corresponding to the test procedure in ann

    documented field exposure for 5 years with a final coating condition of not

    For all other systems, testing according to the procedure in anne

    1, or equivalent, is required. .4 Job specification

    seams only, may be reduced in scope where it is proven that the NDFT can be met by the coats applied in order to avoid

    ll be fully detailed in the CTF.

    re

    ants such as

    method according to the paint

    b specifications shall include the dry-to-recoat times and walk-on time given by the

    There shall be a minimum of two stripe coats and two spray coats, except that the second stripe coat, by way of welded

    unnecessary over thickness. Any reduction in scope of the second stripe coat sha

    Stripe coats shall be applied by brush or roller. Roller to be used for scallops, ratholes, etc., only.

    Each main coating layer shall be appropriately cured befo

    application of the next coat, in accordance with coating manufacturers recommendations. Surface contaminrust, grease, dust, salt, oil, etc. shall be removed prior to painting with proper manufacturers recommendation. Abrasive inclusions embedded in the coating shall be removed. Jo

    manufacturer. .5 NDFT (nominal

    total dry film thickness)3

    0 m with 90/10 rule for epoxy based coatings, other systems to coating manufacturers specifications.

    detailed

    e shall be taken to avoid increasing the thickness in an ess shall be regularly checked

    during application.

    es and quantities

    NDFT 32

    Maximum total dry film thickness according to manufacturers

    specifications. Car

    exaggerated way. Wet film thickn

    Thinner shall be limited to those typ

    recommended by the manufacturer. 2 PSP (Primary Surface Preparation) .1 Blasting and

    Profile. 4, 5

    humidity is above 85%; or of steel is less than 3C above the dew

    Sa 2; with profiles between 30-75 m Blasting shall not be carried out when: .1 the relative .2 the surface temperature

    31

  • point. Checking of the steel surface cleanliness and roughness profile

    nd before the application of the primer, in accordance with the shall be carried out at the end of the surface preparation a

    manufacturers recommendations. .2 Water soluble

    o NaCl

    dium chloride. salt limit

    equivalent t6

    50 mg/m2 of so

    .3 Shop primer based or equivalent. Zinc containing inhibitor free zinc silicate

    Compatibility with main coating system shall be confirmed by the coating manufacturer.

    3 r Secondary surface p eparation .1 Steel

    condition7

    The steel surface shall be prepared so that the coating selected can

    rinding weld beads and removing weld spatter and any other surface contaminant.

    , or

    achieve an even distribution at the required NDFT and have an adequate adhesion by removing sharp edges, g

    Edges to be treated to a rounded radius of minimum 2 mm

    subjected to three pass grinding or at least equivalent process before painting.

    .2 Surface treatment4

    d

    asting, high pressure water washing or equivalent method.

    xy coating system, it may be used in

    turer by the test in accordance with paragraph 1.7 of ithout wave movement.

    Sa 2 on damaged shop primer and welds.

    Sa 2 removing at least 70% of intact shop primer, which has not passed a prequalification certified by test procedures in 1.3.

    If the complete coating system comprising epoxy based main

    coating and shop primer has passed a pre-qualification certifieby test procedures in 1.3, intact shop primer may be retained provided the same epoxy coating system is used. The retained shop primer shall be cleaned by sweep bl

    If a zinc silicate shop primer has passed the pre-qualification test

    of 1.3 as part of an epocombination with other epoxy coatings certified under 1.3, provided that the compatibility has been confirmed by the manufacappendix 1 to annex 1 w

    .3ent

    4

    Butts St 3 or better or Sa 2 where practicable. Small damages up to 2% of total area: St 3. Contiguous damages over 25 m2 or over 2% of the total area of the tank, Sa 2 should be applied.

    p to be feathered.

    Surface treatm

    after erection

    Coating in overla .4 Profile

    irement In case of full or partial blasting 30-75 m, otherwise as

    requ recommended by the coating manufacturer.

    32

  • s5 .5 Dust8

    removed if visible on the surface to be Dust quantity rating 1 for dust size class 3, 4 or 5. Lower

    dust size classes to be coated without magnification.

    .6 soluble salts limit equivalent to NaCl after

    ng/ nding6

    Water

    blastigri

    50 mg/m2 of sodium chloride.

    .7 Oil contamination

    No oil contamination.

    4 Miscellaneous .1 entilation uring

    for a period after application is completed, as recommended by the coating manufacturer.

    V Adequate ventilation is necessary for the proper drying and cof coating. Ventilation should be maintained throughout the application process and

    .2

    conditions, in accordance with the manufacturers specifications.

    .2 the surface temperature is less than 3C above the dew point.

    Environmental conditions

    Coating shall be applied under controlled humidity and surface

    In addition, coating shall not be applied when: .1 the relative humidity is above 85%; or

    .3

    thickness shall be measured after each coat for quality

    thickness gauges (see annex 3).

    Testing of coating3

    Destructive testing should be avoided. Dry film

    control purpose and the total dry film thickness shall be confirmed after completion of final coat, using appropriate

    .4 all

    Repair

    Any defective areas, e.g. pin-holes, bubbles, voids, etc. should be marked up and appropriate repairs effected. All such repairs shbe re-checked and documented.

    3

    Type of gauge and calibration in accordance with SSPC-PA2: 2004. Paint Application

    Reference standard: ISO 8501-1: 1988/Suppl: 1994. Preparation of steel substrate

    of steel substrate before application of paints and related products Surface roughness characteristics of

    O 8502-9: 1998. Preparation of steel ore application of paints and related products Test for the assessment of

    Specification No.2. 4

    before application of paints and related products Visual assessment of surface cleanliness. 5

    Reference standard: ISO 8503-1/2: 1988. Preparation

    blast-cleaned steel substrates. 6

    Conductivity measured in accordance with ISsubstrate befsurface cleanliness. 7

    Reference standard: ISO 8501-3: 2001 (grade P2). Preparation of steel substrate before application of paints and related products Visual assessment of surface cleanliness. 8

    Reference standard: ISO 8502-3:1993. Preparation of steel substrate before application of paints and related products Test for the assessment of surface cleanliness.

    33

  • 5

    Resudocusatis independent of the coating manufacturer.

    6

    sure om Standard, the following shall be carried out by qualified ating inspectors certified to NACE Coating Inspector Level 2, FROSIO Inspector Level III

    t a eting inspec the

    coating process by spection items identified in section 6.2 to ensure comp n of surface preparation r work is extremely difficult to correct later in the co n ly examined for coating thickness. The inspector shall verify that appropriate collective measures have been carr o

    6.1.3 Results from the inspection shall be recorded by the inspector and shall be included in the efer to a ne

    6.2 Inspection item

    stage

    COATING SYSTEM APPROVAL

    lts from prequalification tests (table 1, paragraph 1.3) of the coating system shall be mented, and a Statement of Compliance or Type Approval Certificate shall be issued if found factory by a third party,

    COATING INSPECTION REQUIREMENTS

    6.1 General 6.1.1 To en

    coc pliance with this

    or equivalen6.1.2 Coa

    s v rified by the Administration. tors shall inspect surface preparation and coating application during

    carrying out, as a minimum, those inlia ce with this Standard. Emphasis shall be placed on initiation of each stage

    and coatings application as impropeati g progress. Representative structural members shall be non-destructive

    ied ut.

    CTF (r n x 2, Example of Daily Log and Non-conformity Report).

    s Construction Inspection items

    el, the relative humidity and the dew

    point shall be measured and recorded before the blasting process 1 The surface temperature of ste

    starts and at times of sudden changes in weather. 2 The surface of steel plates shall be tested for soluble salt and checked

    for oil, grease and other contamina

    tion. The cleanliness of the steel surface shall be monitored in the shop 3

    primer application process.

    Primary surface preparation

    4 The shop primer material shall be confirmed to meet the requirements of 2.3 of table 1.

    Thickness n e

    If compatibility with the main coating system has been declared, thethe thickness and curing of the zinc silicate shop primer to bconfirmed to conform to the specified values.

    g construction of the block and before secondary

    .

    1 After completinsurface preparation starts, a visual inspection for steel surfacetreatment including edge treatment shall be carried out

    Any oil, grease or other visible contamination to be removed.

    leaning and prior to coating, a visual

    tion of blasting and cleaning and prior to the application

    in at least one location per block.

    2 After blasting/grinding/cinspection of the prepared surface shall be carried out.

    On comple

    of the first coat of the system, the steel surface shall be tested for levels of remaining soluble salts

    Block assembly

    3 The surface temperature, the relative humidity and the dew point

    34

  • shall be monitored and recorded during the coating application and curing.

    4 Inspection to be performed of the steps in the coating application process mentioned in table 1.

    5 DFT measurements shall be taken to prove that the coating has been applied to the thickness as specified and outlined in annex 3.

    1 Visual inspection for steel surface condition, surface preparation and verification of conformance to other requirements in table 1, and the agreed specification to be performed.

    2 The surface temperature, the relative humidity and the dew point

    E tio

    rec n

    shall be measured and recorded before coating starts and regularly during the coating process.

    3 Inspection to be performed of the steps in the coating application tableprocess mentioned in 1.

    7 VERIFICATION REQUIREMENTS

    The following shall be carried out by the Administration prior to reviewing the Coating

    et and Statement of Compliance or Type Approval

    g identified in the Technical Data Sheet and Statement of Compliance or Type

    andards in

    nts.

    8 ALTERNATIVE SYSTEMS

    8.1 All systems that are not an epoxy based system applied according to table 1 of this Standard are defined as an alternative system. 8.2 This Standard is based on recognized and commonly used coating systems. It is not meant to exclude other, alternative, systems with proven equivalent performance, for example non epoxy based systems. 8.3 Acceptance of alternative systems will be subject to documented evidence that they ensure a corrosion prevention performance at least equivalent to that indicated in this Standard. 8.4 As a minimum, the documented evidence shall consist of satisfactory performance corresponding to that of a coating system which conforms to the Coating Standard described in section 4, a target useful life of 15 years in either actual field exposure for 5 years with final coating condition not less than GOOD or laboratory testing. Laboratory test shall be conducted in accordance with the test procedure given in annex 1 of this Standard.

    Technical File for the ship subject to this Standard: .1 check that the Technical Data She

    Certificate comply with this Standard; .2 check that the coating identification on representative containers is consistent with the

    coatinApproval Certificate;

    .3 check that the inspector is qualified in accordance with the qualification stparagraph 6.1.1;

    .4 check that the inspectors reports of surface preparation and the coatings application indicate compliance with the manufacturers Technical Data Sheet and Statement of Compliance or Type Approval Certificate; and

    .5 monitor implementation of the coating inspection requireme

    35

  • ANNEX 1 TEST PROCEDURES FOR COATING QUALIFICATION

    FOR DEDICATED SEAWATER BALLAST TANK OF ALL TYPES OF SHIPS AND DOUBLE-SIDE SKIN SPACES OF BULK CARRIERS COATING

    1 Scope

    These Procedures provide details of the test procedure referred to in paragraphs 5 and 8.3 of this Standard.

    2 Definitions

    Coating specification means the specification of coating systems which includes the type of coating system, steel preparation, surface preparation, surface cleanliness, environmental conditions, application procedure, acceptance criteria and inspection.

    3 Testing

    Coating specification shall be verified by the following tests. The test procedures shall comply with appendix 1 (Test on simulated ballast tank conditions) and appendix 2 (Condensation chamber tests) to this annex as follows:

    .1 For protective coatings for dedicated seawater ballast tanks, appendix 1 and appendix 2 shall apply.

    .2 For protective coatings for double-side spaces of bulk carriers of 150 m in length and upwards other than dedicated seawater ballast tanks, appendix 2 shall apply.

    36

  • APPENDIX 1 TEST ON SIMULATED BALLAST TANK CONDITIONS

    1 Test condition

    Test on simulated ballast tank conditions shall satisfy each of the following conditions:

    .1 The test shall be carried out for 180 days.

    .2 There are to be 5 test panels.

    .3 The size of each test panel is 200 mm x 400 mm x 3 mm. Two of the panels (Panel 3 and 4 below) have a U-bar welded on. The U-bar is welded to the panel in a 120 mm distance from one of the short sides and 80 mm from each of the long sides.

    The panels are to be treated according to this Standard, table 1.1, 1.2 and 1.3, and coating system applied according to table 1, paragraphs 1.4 and 1.5. Shop primer to be weathered for at least 2 months and cleaned by low pressure washing or other mild method. Blast sweep or high pressure washing, or other primer removal methods not to be used. Weathering method and extent shall take into consideration that the primer is to be the foundation for a 15 year target useful life system. To facilitate innovation, alternative preparation, coating systems and dry film thicknesses may be used when clearly defined.

    .4 The reverse side of the test piece shall be painted appropriately, in order not to affect the test results.

    .5 As simulating the condition of actual ballast tank, the test cycle runs for two weeks with natural or artificial seawater and one week empty. The temperature of the seawater is to be kept at about 35C.

    .6 Test Panel 1: This panel is to be heated for 12 h at 50C and cooled for 12 h at 20C in order to simulate upper deck condition. The test panel is cyclically splashed with natural or artificial seawater in order to simulate a ships pitching and rolling motion. The interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    .7 Test Panel 2 has a fixed sacrificial zinc anode in order to evaluate the effect of cathodic protection. A circular 8 mm artificial holiday down to bare steel is introduced on the test panel 100 mm from the anode in order to evaluate the effect of the cathodic protection. The test panel is cyclically immersed with natural or artificial seawater.

    .8 Test Panel 3: to be cooled on the reverse side, in order to give a temperature gradient in order to simulate a cooled bulkhead in a ballast wing tank, and splashed with natural or artificial seawater in order to simulate a ships pitching and rolling motion. The gradient of temperature is approximately 20C, and the interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    .9 Test Panel 4 is to be cyclically splashed with natural or artificial seawater in order to simulate a ships pitching and rolling motion. The interval of splashing is 3 s or faster. The panel has a scribe line down to bare steel across width.

    37

  • .10 Test Panel 5 is to be exposed to dry heat for 180 days at 70C to simulate boundary plating between heated bunker tank and ballast tank in double bottom.

    Figure 1 Wave tank for testing of ballast tank coatings

    2 Test results

    2.1 Prior to the testing, the following measured data of the coating system shall be reported: .1 infrared (IR) identification of the base and hardener components of the coating; .2 specific gravity9 of the base and hardener components of the paint; and .3 number of pinholes, low voltage detector at 90 V.

    2.2 After the testing, the following measured data shall be reported: .1 blisters and rust10; .2 dry film thickness (DFT) (use of a template)11; .3 adhesion value12; .4 flexibility13 modified according to panel thickness (3 mm steel, 300 m coating, 150 mm

    cylindrical mandrel gives 2% elongation) for information only; .5 cathodic protection weight loss/current demand/disbondment from artificial holiday; .6 undercutting from scribe. The undercutting along both sides of the scribe is measured and

    the maximum undercutting determined on each panel. The average of the three maximum records is used for the acceptance. 9

    Reference standard: ISO 2811-1/4:1997. Paints and varnishes. Determination of density. 10

    Reference standards: ISO 4628/2:2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of defects, and of intensity of uniform changes in appearance Part 2. ISO 4628/3: 2003. Paints and varnishes Evaluation of degradation of coatings Designation of quantity and size of common types of defect Part 3: Designation of degree of rusting.

    38

  • 11 Nine equally distributed measuring points are used on panels size 150mm x 150 mm or

    15 equally distributed measuring points on panels size 200mm x 400mm. 12

    Reference standard: ISO 4624:2002. Pull-off test for adhesion. 13

    Reference standards: ASTM D4145:1983. Standard Test Method for Coating Flexibility of Prepainted Sheet.

    3 Acceptance criteria

    3.1 The test results based on section 2 shall satisfy the following criteria: Item

    Acceptance criteria for epoxy based systems applied according to Table 1 of this Standard

    Acceptance criteria for alternative systems

    Blisters on panel

    No blisters

    No blisters

    Rust on panel

    Ri 0 (0%)

    Ri 0 (0%)

    Number of pinholes

    0 0

    Adhesive failure

    > 3.5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    > 5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    Cohesive failure

    > 3 MPa Cohesive failure in coating for 40% or more of the area.

    > 5 MPa Cohesive failure in coating for 40% or more of the area.

    Cathodic protection current demand calculated from weight loss

    < 5 mA/m2

    < 5 mA/m2

    Cathodic protection; disbondment from artificial holiday

    < 8 mm

    < 5 mm

    Undercutting from scribe < 8 mm

    < 5 mm

    U-bar Any defects, cracking or detachment at the angle or weld will lead to system being failed.

    Any defects, cracking or detachment at the angle or weld will lead to system being failed.

    3.2 Epoxy based systems tested prior to the date of entry into force of this Standard shall satisfy only the criteria for blistering and rust in the table above. 3.3 Epoxy based systems tested when applied according to table 1 of this Standard shall satisfy the criteria for epoxy based systems as indicated in the table above. 3.4 Alternative systems not necessarily epoxy based and/or not necessarily applied according to table 1 of this Standard shall satisfy the criteria for alternative systems as indicated in the table

    39

  • above.

    4 Test report

    The test report shall include the following information: .1 name of the manufacturer; .2 date of tests; .3 product name/identification of both paint and primer; .4 batch number; .5 data of surface preparation on steel panels, including the following:

    - surface treatment; - water soluble salts limit; - dust; and - abrasive inclusions;

    .6 application data of coating system, including the following: - shop primed; - number of coats; - recoat interval14; - dry film thickness (DFT) prior to testing14; - thinner14; - humidity14; - air temperature14; and - steel temperature;

    .7 test results according to section 2; and

    .8 judgment according to section 3. 14

    Both of actual specimen data and manufacturers requirement/recommendation.

    40

  • APPENDIX 2 CONDENSATION CHAMBER TEST

    1 Test condition

    Condensation chamber test shall be conducted in accordance with applicable standards15. .1 The exposure time is 180 days. .2 There are to be 2 test panels. .3 The size of each test panel is 150 mm x 150 mm x 3 mm. The panels are to be treated

    according to the Performance Standard, table 1, paragraphs 1, 2 and 3 and coating system applied according to table 1, paragraphs 1.4 and 1.5. Shop primer to be weathered for at least 2 months and cleaned by low pressure washing or other mild method. Blast sweep or high pressure washing, or other primer removal methods not to be used. Weathering method and extent shall take into consideration that the primer is to be the foundation for a 15 year target life system. To facilitate innovation, alternative preparation, coating systems and dry film thicknesses may be used when clearly defined.

    .4 The reverse side of the test piece shall be painted appropriately, in order not to affect the test results. 15

    Reference standard: ISO 6270-1:1998 Paints and varnishes Determination of resistance to humidity Part 1: Continuous condensation.

    Figure 2 Condensation chamber

    2 Test results

    According to section 2 (except for paragraphs 2.2.5 and 2.2.6) of appendix 1.

    41

  • 3 Acceptance criteria

    3.1 The test results based on section 2 shall satisfy the following criteria: Item

    Acceptance criteria for epoxy based systems applied according to table 1 of this standard

    Acceptance criteria for alternative systems

    Blisters on panel

    No blisters

    No blisters

    Rust on panel

    Ri 0 (0%) Ri 0 (0%)

    Number of pinholes

    0 0

    Adhesive failure

    > 3.5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    > 5 MPa Adhesive failure between substrate and coating or between coats for 60% or more of the areas.

    Cohesive failure

    > 3 MPa Cohesive failure in coating for 40% or more of the area.

    > 5 MPa Cohesive failure in coating for 40% or more of the area.

    3.2 Epoxy based systems tested prior to the date of entry into force of this Standard shall satisfy only the criteria for blistering and rust in the table above. 3.3 Epoxy based systems tested when applied according to table 1 of this Standard shall satisfy the criteria for epoxy based systems as indicated in the table above. 3.4 Alternative systems not necessarily epoxy based and/or not necessarily applied according to table 1 of this Standard shall satisfy the criteria for alternative systems as indicated in the table above.

    4 Test report

    According to section 4 of appendix 1.

    42

  • ANNEX 2 EXAMPLE OF DAILY LOG AND NON-CONFORMITY REPORT

    43

  • 44

  • ANNEX 3

    DRY FILM THICKNESS MEASUREMENTS

    The following verification check points of DFT are to be taken: .1 one gauge reading per 5 m2 of flat surface areas; .2 one gauge reading at 2 to 3 m intervals and as close as possible to tank boundaries, but

    not further than 15 mm from edges of tank boundaries; .3 longitudinal and transverse stiffener members:

    One set of gauge readings as shown below, taken at 2 to 3 m run and not less than two sets between primary support members;

    Figure 3

    NOTE: Arrows of diagram indicate critical areas and should be understood to mean indication for both sides.

    .4 3 gauge readings for each set of primary support members and 2 gauge readings for each

    set of other members as indicated by the arrows in the diagram; .5 for primary support members (girders and transverses) one set of gauge readings for 2 to

    3 m run as shown in figure 3 above but not less than three sets; .6 around openings one gauge reading from each side of the opening; .7 five gauge readings per square metre (m2) but not less than three gauge readings taken at

    complex areas (i.e. large brackets of primary support members); and .8 additional spot checks to be taken to verify coating thickness for any area considered

    necessary by the coating inspector.

    45

  • Appendix 2 IACS Procedural Requirement No.34

    46

  • IACS Procedural Requirement on Application of the IMO Performance Standard for Protective Coatings (PSPC), Resolution MSC.215(82),

    under IACS Common Structural Rules for Bulk Carriers and Oil Tankers

    This IACS Procedural Requirement is to be read in conjunction with the IMO Performance Standard for Protective Coatings (PSPC), Resolution MSC.215(82). Application of the referenced international standards footnoted therein is mandatory under this Procedural Requirement. 1. IACS Procedure for Coating System Approval

    Type Approval Certificate showing compliance with the PSPC section 5 shall be issued if the results of either method A+D, or B+D, or C+D are found satisfactory by the Society.

    Method A: Laboratory Test 1.1 Coating pre-qualification test shall be carried out by the test laboratory which is recognized by the Society and meets the requirements set out in IACS UR Z17 paragraphs 4, 5, 6 and 7 (except for 4.6 & 5.3) as below. 1.2 Results from satisfactory pre-qualification tests (PSPC table 1, paragraph 1.3 of the PSPC) of the coating system shall be documented and submitted to the Society.

    Method B: 5 years field exposure 1.3 Coating manufacturers records are to be examined to confirm coating system has 5 years field exposure. 1.4 A joint (coating manufacturer/Society) survey of all ballast tanks of a selected vessel is to be carried out for the purpose of verification of compliance with the requirements of sections 1.3 and 1.7. The coating manufacturers representative is to be qualified as defined in 2.2. 1.5 The selected vessel is to have ballast tanks in regular use, of which:

    At least one tank approx 2000 m3 At least one tank shall be adjacent to heated tank and At least one tank underdeck exposed to sun.

    1.6 In the case that the selected vessel does not meet the requirements in 1.5 then the limitations shall be clearly stated on the type approval certificate. For example, the coating cannot be used in tanks adjacent to heated tanks or underdeck or tanks with volume greater than the size surveyed. 1.7 All ballast tanks are to be in GOOD condition, without touch up or repair in the prior 5 years. 1.7.1 Good is defined as: Condition with spot rusting on less than 3% of the area under

    consideration without visible failure of the coating. Rusting at edges or welds, must be on less than 20% of edges or welds in the area under consideration.

    1.7.2 Examples of how to report coating conditions with respect to areas under consideration should be as those given in IACS Recommendation 87* Appendix 1.

    * IACS Recommendation 87 is not mandatory.

    Note: This Procedural Requirement is to be applied by IACS Societies to ships subject to the IACS CSR for Bulk Carriers and for Oil Tankers which are contracted for construction on or after 8 December 2006 and until the date of application referred to in para.1 of SOLAS Chapter II-1, Part A-1, Reg.3-2, as adopted by resolution MSC.216(82).

    47

  • Method C: Existing Marintek B1* Approvals. 1.8 Epoxy Coatings Systems with existing satisfactory Marintek test reports minimum level B1 issued before Dec 8th 2006 can be accepted. 1.9 Such coatings are to be applied in accordance with Table 1 of the PSPC rather than the application conditions used during the approval test which may differ from the PSPC, unless these are more stringent than table 1 of the PSPC.

    Method D: Coating Manufacturer 1.10 The coating manufacturer shall meet the requirements set out in IACS UR Z17 paragraphs 4, 5, 6 and 7, (except for 4.6), which is to be verified by the Society. 1.11 In the case that a manufacturer wishes to have products which are manufactured in different locations under the same name, then infrared (IR) identification and specific gravity shall be used to demonstrate that they are the same coating, or individual approval tests will be required for the paint manufactured in each location. 2. IACS Procedure for Assessment of Coating Inspectors Qualifications

    2.1 Coating inspectors required to carry out inspections in accordance with the IMO PSPC section 6 are to be qualified to NACE Coating Inspector Level 2 , FROSIO Inspector Level III, or an equivalent qualification. Equivalent qualifications are described in 2.3 below. 2.2 However only coating inspectors with at least 2 years relevant coating inspector experience and qualified to NACE Coating Inspector Level 2 or FROSIO Inspector Level III, or with an equivalent qualification, can write and/or authorise procedures, or decide upon corrective actions to overcome non-compliances.

    2.3 Equivalent Qualification: 2.3.1 Equivalent qualification is the successful completion, as determined by course tutor, of an

    approved course. 2.3.1.1 The course tutors shall be qualified with at least 2 years relevant experience and qualified

    to NACE Coating Inspector Level 2 or FROSIO Inspector Level III, or with an equivalent qualification.

    2.3.1.2 Approved Course: A course that has a syllabus based on the issues associated with the PSPC including the following:- Health Environment and Safety Corrosion Materials and design International standards referenced in PSPC Curing mechanisms Role of inspector Test instruments Inspection Procedures Coating specification Application Procedures Coating Failures Pre-job conference MSDS and product data sheet review Coating technical file Surface preparation

    48

  • Dehumidification Waterjetting Coating types and inspection criteria Specialized Application Equipment Use of inspection procedures for destructive testing and non destructive testing instruments. Inspection instruments and test methods Coating inspection techniques Cathodic protection Practical exercises, case studies.

    Examples of approved courses may be internal courses run by the coating manufacturers or shipyards etc. 2.3.1.3 Such a course shall have an acceptable measurement of performance, such as an examination with both theoretical and practical elements. The course and examination shall be approved by the Society. 2.3.2 Equivalent qualification arising from practical experience: An individual who:

    has a minimum of 5-years practical work experience as a coating inspector of ballast tanks during new construction within the last 10 years, and has successfully completed the examination given in 2.3.1.3.

    3. IACS Procedure for Inspection Agreement (the PSPC 3.2)

    3.1 The procedure for inspection of surface preparation and coating processes shall be agreed upon, between the shipowner, the shipyard and coating manufacturer. It should be presented by the shipyard to the Society for review and as a minimum shall comply with the PSPC. It is to be included in the Coating Technical File. 3.2 Any deviations in the procedure relative to the PSPC noted during the review shall be raised with the shipyard, which is responsible for identifying and implementing the corrective actions. 3.3 A class certificate is not to be issued until all required corrective actions have been closed out to the satisfaction of the Society. 4. IACS Procedure for Verification of Application of the PSPC

    4.1 The verification requirements of section 7 of the PSPC are to be carried out by the Society. 4.1.1 Monitoring implementation of the coating inspection requirements, as called for in section

    7.5 of the PSPC means checking, on a sampling basis, that the inspectors are using the correct equipment, techniques and reporting methods as described in the inspection procedures reviewed by the Society.

    4.2 Any deviations found under 4.1.1 are to be raised initially with the coating inspector, who is responsible for identifying and implementing the corrective actions.

    4.3 In the event that corrective actions are not acceptable to the Society or in the event that corrective actions are not closed out then the shipyard shall be informed.

    4.4 A class certificate is not to be issued until all required corrective actions have been closed out to the satisfaction of the Society.

    49

  • 5. IACS Procedure for Coating Technical File Review

    5.1 The shipyard is responsible for compiling the Coating Technical File (CTF) either in paper or electronic format, or a combination of the two. 5.2 The CTF is to contain all the information required by the PSPC section 3.4. 5.3 The CTF shall be reviewed for content in accordance with the PSPC section 3.4.2. 5.4 Any deviations found under 5.3 are to be raised with the shipyard, which is responsible for identifying and implementing the corrective actions. 5.5 A class certificate is not to be issued until all required corrective actions have been closed out to the satisfaction of the Society.

    50

  • Appendix 3 IACS IMO PSPC Q&As and Common Interpretations

    6 Feb 2007

    51

  • IMO PSPC - Q&As and Common Interpretations IMO

    PSPC Topic Approved Clarification Items Q&As and Common

    Interpretations 1

    General fee 2006/12/21

    Classification fee including detail scope of verification and inspection.

    Verification and inspection in accordance with the IACS PR34

    2

    2.5 edges 2007/1/31

    PSPC 2.5 reads: Edge grinding is the treatment of edge before secondary surface preparation.

    Edges mean all sharp edges (non-radiused or with a radius less than 2 mm). Which includes both thermally and mechanically edges. All sharp edges (non - radiused or radius less than 2mm) are subject to edge grinding. All edges with the exception of the natural rounded edges of sections (or profiled steel bars) are subject to two stripe coats.

    3

    2.11 Sharp edges 2006/12/21

    Do edges mean sharp edges or flame cut edges? Are automated welds included or not for stripe coats?

    Edges means all edges except the natural rounded edges of sections (or profiled steel bars). Automated welds need stripe coat.

    4

    3.2 inspection requirements 2007/1/31

    PSPC 3.2 reads: Inspection of surface preparation and coating processes shall be agreed upon between the ship owner, the shipyard and the coating manufacturer and presented to the Administration for review.

    PSPC inspection requirements are the minimum to be applied, there is no provision for that to be reduced. There is no provision for a reduction within CSR.

    5

    3.4.1 Record 2007/2/21

    What is Record of the shipyards and shipowners coating work? For shipbuilding, is it the same as 3.4.2-3/6?

    Yes

    6

    4.4.2 coating specifications 2006/12/21

    What should be included in the specification? If the specification

    Manufacturers need to provide a specification detailing all the requirements of table 1

    52

  • means the coating specification which is defined in ANNEX1, is it possible to use PSPC as a coating specification because PSPC is covered the required inclusions?

    of the PSPC.

    7

    4.4.2 coating specifications 2007/1/31

    PSPC 4.4.2 reads: Coating manufacturers shall provide a specification of the protective coating system to satisfy the requirements of table 1.

    The specification may be the technical data sheet if all the information required is provided on it. This question should be addressed to paint manufacturers. The specification should contain application procedure, acceptance criteria and inspection etc. as specified in paragraph 2 of annex 1 of the PSPC.

    8

    4.4.3/ table 1-1.3

    paint and manufacturer

    list 2006/12/21

    Type approved paint and manufacturer list including verified technical data sheet.

    Coating manufacturers should provide details of the type approved coatings in accordance with PSPC. This is no different from other manufacturers providing details of their products and relevant certification.

    9

    table 1-1. type approval certificate 2006/12/21

    Is further consideration necessary to the coating systems which have a type approval certificate?

    Yes as required by sect 3.2 agreement between all parties. Coating systems must meet all relevant requirements of the PSPC

    10 table 1-1.2 light color 2006/12/21 Definition of light color?

    light colour as agreed by all parties in PSPC sect 3.2

    11

    table 1-1.2 light color 2007/1/31

    Table 1-1.1.2, 4th bullet reads: The top coat shall be of a light colour in order to facilitate in-service inspection.

    A light colour means a colour that reflects light to an extent that a simple flash light (hand torch) will make inspection easy fast. Normally light grey, off-white, swimming pool

    53

  • blue/green etc. easily distinguishable from rust.

    12

    table 1-1.3 type epoxy 2006/12/21

    1) Is winter type epoxy required separate prequalification test including shop primer compatibility test according to Annex 1? 2) Intact shop primer should be removed or not, in case 5 years field exposure are validate as a type approval test? 3) Is separate compatibility test for shop primer required? If yes, please provide detail test procedure.

    1) Yes winter and summer type coating are considered different unless IR identification and specific gravity demonstrates that they are the same. 2) shop primer should be removed if it cannot be demonstrated to be compatible with the coating to be used. 3) No because it should be included as coating system which is confirmed by the coating manufacturer.

    13

    table 1-1.4 NDFT 2006/12/21

    Who and how to prove that the NDFT can be met in way of welded seam in order to skip second stripe coat.

    measure flat plate adjacent to the weld, approved by the inspector ref table

    14

    table 1-1.4 stripe coats 2006/12/21

    Does Stripe coats shall be applied by brush or roller. Roller to be used for scallops, ratholes, etc. only. interpret that Stripe coats shall be applied by brush or roller. However, stripe coat for scallops, ratholes, etc. to be applied by roller?

    As discussed at MSC 82 by the IMO informal Group of Experts the understanding is that stripe coat to be applied by brush. However in way of rat holes, scallops etc a roller may be used.

    15

    table 1-1.4 stripe coats 2007/1/31

    Table 1-1.4, 1st bullet reads: There shall be a minimum of two stripe coats and two spray coats, except that the second stripe coat, by way of welded seams only, may be reduced in scope where it is proven that the NDFT can be met by the coats applied in order to avoid unnecessary over

    It was confirmed at MSC 82 that stripe coats are to be applied by brush, this includes all welds. However where edges are rounded to a radius greater or equal to 2 mm, stripe coats may be applied by brush or roller. Two stripe coats are to be applied to all edges and all irregular welding beads. One

    54

  • thickness. Any reduction in scope of the second stripe coat shall be fully detailed in the CTF.

    stripe coat may be applied in way of smooth automatic weld beads subject to confirmation that the NDFT has been achieved by thickness measurement of the coating after the second spray coat. Measurement of this NDFT is to be immediately adjacent to the weld bead.

    16

    table 1-1.4 stripe coats 2007/1/31

    Table 1-1.4, 2nd bullet reads: Stripe coats shall be applied by brush or roller. Roller to be used for scallops, ratholes, etc., only.

    Etc. means or similar.

    17

    table 1-1.5 wet film thickness 2007/1/31

    Table 1-1.5, 3rd bullet reads: Wet film thickness shall be regularly checked during application.

    Wet film thickness shall be regularly checked during application for quality control by the Builder. PSPC does not state who should check WFT, it is accepted for this to be the builder. DFT is to be done as part of the inspection section 6.

    18

    table 1-2.1 steel surface cleanliness 2007/2/21

    The last para. reads: Checking of the steel surface cleanliness and roughness profile shall be carried out at the end of the surface preparation and before the application of the primer, in accordance with the manufacturers recommendations. Section 6.2 Inspection item-Primary surface preparation, the statements is very clear about the time for checking steel temperature, relative humidity and dew

    As agreed in Sect 3.2 of PSPC and noted in the shipyard procedure. If it is an automated system it may be monitored instead of measuring every plate as long as it is noted in the shipyard procedure and meets the requirements of Table1-2.

    55

  • point: before the blasting process starts and at time of sudden changes in weather. How about the testing of salt content and checking of oil, greese and other contamination? Shall we check all of the plate or random check can be accepted?

    19

    table 1-2.2 measurement of salt 2006/12/21

    1) How many measurements of salt shall be required during primary surface stage? 2) How to measure the salt during automated process? 3) How to convert only sodium chloride from the conductivity measure in accordance with ISO 8502-9?

    1) As agreed in Sect 3.2 PSPC 2) measure salt and remove before going into shot blasting or have shipyard procedures to check occasional readings after shot blasting 3) The whole conductivity value is calculated to NaCl in accordance with the manufacturers test instrument manual.

    20

    table 1-3 blcok and after erection 2007/2/21

    it is separate into two group: Block & after Erection. How to define the painting work for joints and damages of Grand Assembly or Pre-Erection? (The blocks had been coated before combine)

    Can be categorized as after erection.

    21

    table 1-3.1 one pass 2006/12/21

    One pass edge cut machining or one pass grinding followed by disc papering on remaining edges are considered equivalent to three pass grinding or not.

    Only if a radius of 2mm is achieved.

    22

    table 1-3.1 rounded radius 2007/1/31

    Edges to be treated to a rounded radius of minimum 2mm, or subjected to three pass grinding or at least

    The PSPC requires all edges to be rounded to a radius of 2 mm minimum or that havent been subject to three pass

    56

  • equivalent process before painting.

    grinding. An example of an equivalent process is a dedicated edge grinding machine which will provide the profile equal to radius 2 mm or three pass grinding by a single pass.

    23

    table 1-3.2 shop primer 2006/12/21

    1) Does The retained shop primer shall be cleaned by sweep blasting, high pressure water washing or equivalent method. interpret that The contamination on retained shop primer shall be cleaned by sweep blas